I PEKERJAAN PENDAHULUAN
1 Survey Pengukuran - 300,000.00 300,000.00
2 Pembersihan Lokasi 88.00 m2 15,250.00 1,342,000.00
3 Papan Nama Proyek 1.00 Bh 250,000.00 250,000.00
1,892,000.00
II PEKERJAAN COR BETON
1 Urugan pasir 42.24 m³ 123,750.00 5,227,125.75
2 Pas. Mal kayu 120.00 m¹ 65,575.00 7,869,000.00
3 Beton Ready Mix K.225 91.56 m³ 1,193,387.55 109,266,564.08
4 Labur aspal 1,8 kg/m2 + tabur pasir 763.00 m² 18,392.86 14,033,748.68
136,396,438.51
III PEKERJAAN LAIN-LAIN
1 ADM + Lap photo - 1,000,000.00 1,000,000.00
2 Biaya asbuilt drawing - 250,000.00 250,000.00
3 Pembersihan akhir 52.00 m2 6,375.00 331,500.00
1,581,500.00
REKAPITULASI
I PEKERJAAN PENDAHULUAN Rp. 1,892,000.00 ###
II PEKERJAAN COR BETON Rp. 136,396,438.51
III PEKERJAAN LAIN-LAIN Rp. 1,581,500.00
JUMLAH Rp. 139,869,938.51 ###
PPN 10 % Rp. 13,986,993.85
JUMLAH SETELAH PPN 10 % Rp. 153,856,932.36
DIBULATKAN RP. 153,856,000.00
TERBILANG : SERATUS EMPAT PULUH SEMBILAN JUTA DELAPAN RATUS TUJUH
PULUH RIBU RUPIAH
SOFIAN HASAN
Direktur
FR
RENCANA ANGGARAN BIAYA (RAB)
I PEKERJAAN PENDAHULUAN
1 Survey Pengukuran - 407,000.00 407,000.00
2 Pembersihan Lokasi 88.00 m 2
- -
3 Papan Nama Proyek 1.00 Bh 250,000.00 250,000.00
657,000.00
II PEKERJAAN COR BETON
1 Urugan pasir 42.24 m³ 211,500.00 8,933,633.10
2 Pas. Mal kayu 120.00 m¹ - -
3 Beton Ready Mix K.225 91.56 m³ 15,583.33 1,426,809.69
4 Labur aspal 1,8 kg/m2 + tabur pasir 763.00 m² - -
10,360,442.79
III PEKERJAAN LAIN-LAIN
1 ADM + Lap photo - 1,000,000.00 1,000,000.00
2 Biaya asbuilt drawing - 250,000.00 250,000.00
3 Pembersihan akhir 52.00 m2 - -
1,250,000.00
REKAPITULASI
I PEKERJAAN PENDAHULUAN Rp. 657,000.00 ###
II PEKERJAAN COR BETON Rp. 10,360,442.79
III PEKERJAAN LAIN-LAIN Rp. 1,250,000.00
JUMLAH Rp. 12,267,442.79 ###
PPN 10 % Rp. 1,226,744.28
JUMLAH SETELAH PPN 10 % Rp. 13,494,187.07
DIBULATKAN RP. 13,494,000.00
TERBILANG : SERATUS EMPAT PULUH SEMBILAN JUTA DELAPAN RATUS TUJUH
PULUH RIBU RUPIAH
SOFIAN HASAN
Direktur
R
RENCANA ANGGARAN BIAYA (RAB)
I PEKERJAAN PENDAHULUAN
1 Survey Pengukuran - 407,000.00 407,000.00
2 Pembersihan Lokasi 88.00 m 2
15,250.00 1,342,000.00
3 Papan Nama Proyek 1.00 Bh 250,000.00 250,000.00
- 1,999,000.00
II PEKERJAAN COR BETON - 0
1 Urugan pasir 42.24 m³ 123,750.00 5,227,125.75
2 Pas. Mal kayu 120.00 m¹ 65,575.00 7,869,000.00
3 Beton Ready Mix K.225 91.56 m³ 1,193,387.55 109,266,564.08
4 Labur aspal 1,8 kg/m2 + tabur pasir 763.00 m² 18,392.86 14,033,748.68
- 136,396,438.51
III PEKERJAAN LAIN-LAIN -
1 ADM + Lap photo - 1,000,000.00 1,000,000.00
2 Biaya asbuilt drawing - 250,000.00 250,000.00
3 Pembersihan akhir 52.00 m2 6,375.00 331,500.00
1,581,500.00
REKAPITULASI
I PEKERJAAN PENDAHULUAN Rp. 1,999,000.00 ###
II PEKERJAAN COR BETON Rp. 136,396,438.51
III PEKERJAAN LAIN-LAIN Rp. 1,581,500.00
JUMLAH Rp. 139,976,938.51 ###
PPN 10 % Rp. 13,997,693.85
JUMLAH SETELAH PPN 10 % Rp. 153,974,632.36
DIBULATKAN RP. 153,974,000.00
TERBILANG : SERATUS EMPAT PULUH SEMBILAN JUTA DELAPAN RATUS TUJUH
PULUH RIBU RUPIAH
SOFIAN HASAN
Direktur
RENCANA ANGGARAN BIAYA (RAB)
I PEKERJAAN PENDAHULUAN
1 Survey Pengukuran - 407,000.00 407,000.00
2 Pembersihan Lokasi 88.00 m2 77,500.00 6,820,000.00
3 Papan Nama Proyek 1.00 Bh 250,000.00 250,000.00
- 7,477,000.00
II PEKERJAAN COR BETON - 0
1 Urugan pasir 42.24 m³ - -
2 Pas. Mal kayu 120.00 m¹ 24,750.00 2,970,000.00
3 Beton Ready Mix K.225 91.56 m³ - -
4 Labur aspal 1,8 kg/m2 + tabur pasir 763.00 m² - -
- 2,970,000.00
III PEKERJAAN LAIN-LAIN -
1 ADM + Lap photo - 1,000,000.00 1,000,000.00
2 Biaya asbuilt drawing - 250,000.00 250,000.00
3 Pembersihan akhir 52.00 m2 43,137.50 2,243,150.00
3,493,150.00
REKAPITULASI
I PEKERJAAN PENDAHULUAN Rp. 7,477,000.00 ###
II PEKERJAAN COR BETON Rp. 2,970,000.00
III PEKERJAAN LAIN-LAIN Rp. 3,493,150.00
JUMLAH Rp. 13,940,150.00 ###
PPN 10 % Rp. 1,394,015.00
JUMLAH SETELAH PPN 10 % Rp. 15,334,165.00
DIBULATKAN RP. 15,334,000.00
TERBILANG : SERATUS EMPAT PULUH SEMBILAN JUTA DELAPAN RATUS TUJUH
PULUH RIBU RUPIAH
SOFIAN HASAN
Direktur
DAFTAR ANALISA PEKERJAAN KOTA PALEMBANG
TAHUN ANGGARAN 2014 SEMESTER I
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1.1 1 M' Pagar Sementara dari Kayu Tinggi 2 Meter
a. Bahan
1.250 Btg Kayu Gelam dia. 6-8 8,800.00 11,000.00 11,000.00
2.500 Kg Semen Portland 1,700.00 4,250.00 4,250.00
0.005 M3 Pasir Beton 118,750.00 593.75 593.75
0.009 M3 Koral Beton 518,850.62 4,669.66 4,669.66
0.072 M3 Kayu 5/7 kelas IV 1,650,000.00 118,800.00 118,800.00
0.060 Kg Paku Biasa 2"-5" 28,500.00 1,710.00 1,710.00
0.400 Lt Teer/Residu 49,500.00 19,800.00 19,800.00
160,823.41 160,823.41
b. Tenaga
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.020 Oh Mandor 150,000.00 3,000.00 3,000.00
62,000.00 62,000.00
b. Tenaga
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.020 Oh Mandor 150,000.00 3,000.00 3,000.00
62,000.00 62,000.00
1.3 1 M' Pagar Sementara dari Kawat Duri Tinggi 1,8 Meter
a. Bahan
1.000 Btg Kayu Gelam dia. 6-8 8,800.00 8,800.00 8,800.00
2.000 Kg Semen Portland 1,700.00 3,400.00 3,400.00
25.000 Kg Kawat Duri 16,500.00 412,500.00 412,500.00
0.005 M3 Pasir Beton 118,750.00 593.75 593.75
0.009 M3 Koral Beton 518,850.62 4,669.66 4,669.66
0.060 Kg Paku Biasa 2"-5" 28,500.00 1,710.00 1,710.00
431,673.41 431,673.41
b. Tenaga
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.300 Oh Pekerja 77,500.00 23,250.00 23,250.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.020 Oh Mandor 150,000.00 3,000.00 3,000.00
54,250.00 54,250.00
b. Tenaga
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.005 Oh Mandor 150,000.00 750.00 750.00
22,500.00 22,500.00
b. Tenaga
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
1.000 Oh Tukang Batu 125,000.00 125,000.00 125,000.00
2.000 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.300 Oh Kepala Tukang 150,000.00 45,000.00 45,000.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
582,500.00 582,500.00
b. Tenaga
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
0.200 Oh Kepala Tukang 150,000.00 30,000.00 30,000.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
365,000.00 365,000.00
b. Tenaga
1.500 Oh Tukang Kayu 125,000.00 187,500.00 187,500.00
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
0.150 Oh Kepala Tukang 150,000.00 22,500.00 22,500.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
295,000.00 295,000.00
a. Bahan
1.250 Btg Kayu Gelam dia. 6-8 8,800.00 11,000.00 11,000.00
0.186 M3 Kayu 1,650,000 306,900.00 306,900.00
0.300 Kg Paku Biasa 28,500.00 8,550.00 8,550.00
18.000 Kg Semen Portland 1,700.00 30,600.00 30,600.00
0.030 M3 Pasir Beton 118,750.00 3,562.50 3,562.50
0.050 M3 Koral Beton 518,850.62 25,942.53 25,942.53
1 M2 Seng Gelombang BJLS 8,167.50 8,167.50 8,167.50
1.350 Lbr Plywood 4 mm 82,500.00 111,375.00 111,375.00
506,097.53 506,097.53
b. Tenaga
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
0.200 Oh Kepala Tukang 150,000.00 30,000.00 30,000.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
365,000.00 365,000.00
a. Bahan
0.036 M3 Kayu Kls. IV 1,650,000 59,400.00 59,400.00
0.080 Kg Paku Biasa 28,500.00 2,280.00 2,280.00
1.000 Btg Kaso 5/7 89,700.00 89,700.00 89,700.00
151,380.00 151,380.00
b. Tenaga
0.300 Oh Tukang Kayu 125,000.00 37,500.00 37,500.00
0.0015 Oh Mandor 150,000.00 225.00 225.00
37,725.00 37,725.00
a. Bahan
1.000 Btg Bambu & 6 - 8 /600 cm 55,000.00 55,000.00 55,000.00
0.250 Kg Tali Ijuk 12,540.00 3,135.00 3,135.00
58,135.00 58,135.00
b. Tenaga
0.017 Oh Tukang Kayu 125,000.00 2,125.00 2,125.00
0.002 Oh Kepala Tukang 150,000.00 300.00 300.00
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.013 Oh Mandor 150,000.00 1,950.00 1,950.00
23,750.00 23,750.00
a. Bahan
0.150 M3 Batu Belah 15/20/Batu Kali 385,000.00 57,750.00 57,750.00
0.090 M3 Batu Pecah 5/7 385,000.00 34,650.00 34,650.00
0.010 M3 Pasir Pasang 118,750.00 1,187.50 1,187.50
93,587.50 93,587.50
b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
85,000.00 85,000.00
b. Tenaga
0.042 Oh Pekerja 77,500.00 3,255.00 3,255.00
0.004 Oh Kepala Tukang 150,000.00 600.00 600.00
0.042 Oh Tukang 125,000.00 5,250.00 5,250.00
0.002 Oh Mandor 150,000.00 300.00 300.00
9,405.00 9,405.00
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.019 Oh Mandor 150,000.00 2,850.00 2,850.00
27,650.00 27,650.00
b. Tenaga
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.019 Oh Mandor 150,000.00 2,850.00 2,850.00
27,650.00 27,650.00
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
1.000 Oh Mandor 150,000.00 150,000.00 150,000.00
174,800.00 174,800.00
II PEKERJAAN TANAH
a. Tenaga
0.735 Oh Pekerja 77,500.00 56,962.50 56,962.50
- - Tukang Gali - - -
- - Kepala Tukang - - -
0.073 Oh Mandor 150,000.00 10,950.00 10,950.00
67,912.50 67,912.50
a. Tenaga
0.823 Oh Pekerja 77,500.00 63,782.50 63,782.50
- - Tukang Gali - - -
- - Kepala Tukang - - -
0.083 Oh Mandor 150,000.00 12,450.00 12,450.00
76,232.50 76,232.50
a. Tenaga
0.050 Oh Pekerja 77,500.00 3,875.00 3,875.00
- - Tukang Gali - - -
- - Kepala Tukang - - -
0.005 Oh Mandor 150,000.00 750.00 750.00
4,625.00 4,625.00
a. Tenaga
0.516 Oh Pekerja 77,500.00 39,990.00 39,990.00
- - Tukang Gali - - -
- - Kepala Tukang - - -
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
47,490.00 47,490.00
b. Tenaga
0.300 Oh Pekerja 77,500.00 23,250.00 23,250.00
- - Tukang Gali - - -
- - Kepala Tukang - - -
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
24,750.00 24,750.00
a. Bahan
1.200 M3 Koral 518,850.62 622,620.74 622,620.74
622,620.74 622,620.74
b. Tenaga
1.000 M3 Upah dan Pemadatan 6,600.00 6,600.00 6,600.00
6,600.00 6,600.00
a. Bahan
1.2000 M3 Tanah Urug 60,500.00 72,600.00 72,600.00
72,600.00 72,600.00
b. Tenaga
0.3000 Pekerja 77,500.00 23,250.00 23,250.00
0.0330 Mandor 150,000.00 4,950.00 4,950.00
28,200.00 28,200.00
b. Tenaga
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00
b. Tenaga
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00
Jumlah 928,106.25 211,500.00 1,139,606.25
a. Bahan
1.100 M3 Batu Belah 15/20 cm / batu kali 385,000.00 423,500.00 423,500.00
392.000 Kg Semen Portland 1,700.00 666,400.00 666,400.00
0.314 M3 Pasir Pasang 118,750.00 37,287.50 37,287.50
1,127,187.50 1,127,187.50
b. Tenaga
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00
b. Tenaga
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00
b. Tenaga
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00
b. Tenaga
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00
b. Tenaga
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00
a. Bahan
0.450 M3 Batu Belah 15/20 cm / batu kali 385,000.00 173,250.00 173,250.00
280.000 Kg Semen Portland 1,700.00 476,000.00 476,000.00
0.450 M3 Pasir Beton 118,750.00 53,437.50 53,437.50
0.670 M3 Koral Beton 518,850.62 347,629.92 347,629.92
1,050,317.42 1,050,317.42
b. Tenaga
2.380 Oh Pekerja 77,500.00 184,450.00 184,450.00
0.300 Oh Tukang Batu 125,000.00 37,500.00 37,500.00
0.030 Oh Kepala Tukang 150,000.00 4,500.00 4,500.00
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
238,450.00 238,450.00
a. Bahan
0.019 M3 Pasir Urug 82,500.00 1,567.50 1,567.50
0.094 M3 Pasir Beton 118,750.00 11,162.50 11,162.50
0.150 M3 Koral Beton 518,850.62 77,827.59 77,827.59
60.500 Kg Semen Portland 1,700.00 102,850.00 102,850.00
45.000 Kg Besi Beton 12,075.00 543,375.00 543,375.00
0.900 Kg Kawat Beton 19,800.00 17,820.00 17,820.00
0.032 M3 Kayu Kaso 5/7 1,650,000.00 52,800.00 52,800.00
0.120 Kg Paku 28,500.00 3,420.00 3,420.00
0.090 Ltr Minyak Bekisting 13,200.00 1,188.00 1,188.00
0.240 Kg Plamir Tembok 8,800.00 2,112.00 2,112.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
814,122.59 814,122.59
b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
0.670 Oh Tukang Batu 125,000.00 83,750.00 83,750.00
0.067 Oh Kepala Tukang 150,000.00 10,050.00 10,050.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
178,800.00 178,800.00
3.11 1 M' Pembuatan Tiang Pancang (35 x 35) cm, Beton Bertulang
a. Bahan
0.016 M3 Pasir Urug Darat 82,500.00 1,320.00 1,320.00
0.080 M3 Pasir Beton 118,750.00 9,500.00 9,500.00
0.125 M3 Koral Beton 518,850.62 64,856.33 64,856.33
49.000 Kg Semen Portland 1,700.00 83,300.00 83,300.00
34.500 Kg Besi Beton 12,075.00 416,587.50 416,587.50
0.700 Kg Kawat Beton 19,800.00 13,860.00 13,860.00
0.027 M3 Kayu Kaso 5/7 1,650,000.00 44,550.00 44,550.00
0.120 Kg Paku 28,500.00 3,420.00 3,420.00
0.090 Ltr Minyak Bekisting 13,200.00 1,188.00 1,188.00
0.200 Kg Plamir Tembok 8,800.00 1,760.00 1,760.00
640,341.83 640,341.83
b. Tenaga
0.800 Oh Pekerja 77,500.00 62,000.00 62,000.00
0.500 Oh Tukang Batu 125,000.00 62,500.00 62,500.00
0.050 Oh Kepala Tukang 150,000.00 7,500.00 7,500.00
0.040 Oh Mandor 150,000.00 6,000.00 6,000.00
138,000.00 138,000.00
b. Tenaga
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00
a. Bahan
782 Bh Batu Bata Lobang 850.00 664,700.00 664,700.00
3.296 Zak Semen Portland 72,800.00 239,948.80 239,948.80
0.333 M3 Pasir Pasang 118,750.00 39,543.75 39,543.75
944,192.55 944,192.55
b. Tenaga
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00
IV PEKERJAAN DINDING
4.1 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 1 Ps
a. Bahan
140 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 192,500.00 192,500.00
64.030 Kg Semen Portland 1,700.00 108,851.00 108,851.00
0.059 M3 Pasir Pasang 118,750.00 7,006.25 7,006.25
308,357.25 308,357.25
b. Tenaga
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
82,875.00 82,875.00
b. Tenaga
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
82,875.00 82,875.00
b. Tenaga
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
82,875.00 82,875.00
a. Bahan
117 Bh Bata Lobang 9 x 9 x 19 cm 850.00 99,450.00 99,450.00
26.550 Kg Semen Portland 1,700.00 45,135.00 45,135.00
0.093 M3 Pasir Pasang 118,750.00 11,043.75 11,043.75
155,628.75 155,628.75
b. Tenaga
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
82,875.00 82,875.00
b. Tenaga
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
82,875.00 82,875.00
a. Bahan
140 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 192,500.00 192,500.00
22.200 Kg Semen Portland 1,700.00 37,740.00 37,740.00
0.102 M3 Pasir Pasang 118,750.00 12,112.50 12,112.50
242,352.50 242,352.50
b. Tenaga
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
82,875.00 82,875.00
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
41,050.00 41,050.00
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
41,050.00 41,050.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
41,050.00 41,050.00
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
41,050.00 41,050.00
a. Bahan
70 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 96,250.00 96,250.00
9.680 Kg Semen Portland 1,700.00 16,456.00 16,456.00
0.0450 M3 Pasir Pasang 118,750.00 5,343.75 5,343.75
118,049.75 118,049.75
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
41,050.00 41,050.00
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
41,050.00 41,050.00
a. Bahan
70 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 96,250.00 96,250.00
6.500 Kg Semen Portland 1,700.00 11,050.00 11,050.00
0.050 M3 Pasir Pasang 118,750.00 5,937.50 5,937.50
113,237.50 113,237.50
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
41,050.00 41,050.00
a. Bahan
36 Bh Roster / Terawang 4,675.00 168,300.00 168,300.00
12.800 Kg Semen Portland 1,700.00 21,760.00 21,760.00
0.035 M3 Pasir Pasang 118,750.00 4,156.25 4,156.25
194,216.25 194,216.25
b. Tenaga
0.300 Oh Pekerja 77,500.00 23,250.00 23,250.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0150 Oh Mandor 150,000.00 2,250.00 2,250.00
39,500.00 39,500.00
b. Tenaga
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.450 Oh Pekerja 77,500.00 34,875.00 34,875.00
55,875.00 55,875.00
V PEKERJAAN PLESTERAN
5.1 1 M2 Plesteran 1 Pc : 1 Ps, Tebal 15 mm
a. Bahan
12.920 Kg Semen Portland 1,700.00 21,964.00 21,964.00
0.013 M3 Pasir Pasang 118,750.00 1,543.75 1,543.75
23,507.75 23,507.75
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00
a. Bahan
5.200 Kg Semen Portland 1,700.00 8,840.00 8,840.00
0.020 M3 Pasir Pasang 118,750.00 2,375.00 2,375.00
11,215.00 11,215.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00
a. Bahan
4.320 Kg Semen Portland 1,700.00 7,344.00 7,344.00
0.022 M3 Pasir Pasang 118,750.00 2,612.50 2,612.50
9,956.50 9,956.50
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00
a. Bahan
3.680 Kg Semen Portland 1,700.00 6,256.00 6,256.00
0.023 M3 Pasir Pasang 118,750.00 2,731.25 2,731.25
8,987.25 8,987.25
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00
a. Bahan
0.009 M3 Semen Merah 41,800.00 376.20 376.20
0.009 M3 Pasir Pasang 118,750.00 1,068.75 1,068.75
1,444.95 1,444.95
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00
a. Bahan
0.007 M3 Semen Merah 41,800.00 292.60 292.60
0.015 M3 Pasir Pasang 118,750.00 1,781.25 1,781.25
2,073.85 2,073.85
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00
a. Bahan
14.280 Kg Semen Portland 1,700.00 24,276.00 24,276.00
0.023 M3 Pasir Pasang 118,750.00 2,731.25 2,731.25
27,007.25 27,007.25
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
49,250.00 49,250.00
a. Bahan
10.800 Kg Semen Portland 1,700.00 18,360.00 18,360.00
0.026 M3 Pasir Pasang 118,750.00 3,087.50 3,087.50
21,447.50 21,447.50
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
49,250.00 49,250.00
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
49,250.00 49,250.00
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
49,250.00 49,250.00
a. Bahan
0.009 M3 Semen Merah 41,800.00 376.20 376.20
0.018 M3 Pasir Pasang 118,750.00 2,137.50 2,137.50
2,513.70 2,513.70
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
49,250.00 49,250.00
a. Bahan
9.300 Kg Semen Portland 1,700.00 15,810.00 15,810.00
0.018 M3 Pasir Pasang 118,750.00 2,137.50 2,137.50
17,947.50 17,947.50
b. Tenaga
0.260 Oh Pekerja 77,500.00 20,150.00 20,150.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.013 Oh Mandor 150,000.00 1,950.00 1,950.00
50,100.00 50,100.00
a. Bahan
7.070 Kg Semen Portland 1,700.00 12,019.00 12,019.00
0.021 M3 Pasir Pasang 118,750.00 2,493.75 2,493.75
14,512.75 14,512.75
b. Tenaga
0.260 Oh Pekerja 77,500.00 20,150.00 20,150.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.013 Oh Mandor 150,000.00 1,950.00 1,950.00
50,100.00 50,100.00
a. Bahan
4.320 Kg Semen Portland 1,700.00 7,344.00 7,344.00
0.016 M3 Pasir Pasang 118,750.00 1,900.00 1,900.00
9,244.00 9,244.00
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
35,625.00 35,625.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
VI PEKERJAAN KAYU
6.1 1 M3 Pasang Kusen Pintu dan Jendela K.kls. I (Kayu Jati, Unglen)
a. Bahan
1.100 M3 Kayu Jati, Balok ( Kayu kelas I) 9,075,000.00 9,982,500.00 9,982,500.00
9,982,500.00 9,982,500.00
b. Tenaga
6.000 Oh Pekerja 77,500.00 465,000.00 465,000.00
20.000 Oh Tukang Kayu 125,000.00 2,500,000.00 2,500,000.00
2.000 Oh Kepala Tukang 150,000.00 300,000.00 300,000.00
0.300 Oh Mandor 150,000.00 45,000.00 45,000.00
3,310,000.00 3,310,000.00
b. Tenaga
6.000 Oh Pekerja 77,500.00 465,000.00 465,000.00
18.000 Oh Tukang Kayu 125,000.00 2,250,000.00 2,250,000.00
2.000 Oh Kepala Tukang 150,000.00 300,000.00 300,000.00
0.300 Oh Mandor 150,000.00 45,000.00 45,000.00
3,060,000.00 3,060,000.00
a. Bahan
1.200 M3 Kayu Kls. III 3,630,000.00 4,356,000.00 4,356,000.00
4,356,000.00 4,356,000.00
b. Tenaga
6.000 Oh Pekerja 77,500.00 465,000.00 465,000.00
18.000 Oh Tukang Kayu 125,000.00 2,250,000.00 2,250,000.00
2.000 Oh Kepala Tukang 150,000.00 300,000.00 300,000.00
0.300 Oh Mandor 150,000.00 45,000.00 45,000.00
3,060,000.00 3,060,000.00
a. Bahan
0.036 M3 Kayu Kls. III 3,630,000.00 130,680.00 130,680.00
0.050 Kg Paku Biasa 2" - 5" 28,500.00 1,425.00 1,425.00
132,105.00 132,105.00
b. Tenaga
0.350 Oh Pekerja 77,500.00 27,125.00 27,125.00
1.050 Oh Tukang Kayu 125,000.00 131,250.00 131,250.00
0.105 Oh Kepala Tukang 150,000.00 15,750.00 15,750.00
0.018 Oh Mandor 150,000.00 2,700.00 2,700.00
176,825.00 176,825.00
b. Tenaga
0.350 Oh Pekerja 77,500.00 27,125.00 27,125.00
1.050 Oh Tukang Kayu 125,000.00 131,250.00 131,250.00
0.105 Oh Kepala Tukang 150,000.00 15,750.00 15,750.00
0.018 Oh Mandor 150,000.00 2,700.00 2,700.00
176,825.00 176,825.00
b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
2.500 Oh Tukang Kayu 125,000.00 312,500.00 312,500.00
0.250 Oh Kepala Tukang 150,000.00 37,500.00 37,500.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
435,000.00 435,000.00
b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
2.500 Oh Tukang Kayu 125,000.00 312,500.00 312,500.00
0.250 Oh Kepala Tukang 150,000.00 37,500.00 37,500.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
435,000.00 435,000.00
b. Tenaga
0.800 Oh Pekerja 77,500.00 62,000.00 62,000.00
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
0.200 Oh Kepala Tukang 150,000.00 30,000.00 30,000.00
0.040 Oh Mandor 150,000.00 6,000.00 6,000.00
348,000.00 348,000.00
b. Tenaga
0.800 Oh Pekerja 77,500.00 62,000.00 62,000.00
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
0.200 Oh Kepala Tukang 150,000.00 30,000.00 30,000.00
0.040 Oh Mandor 150,000.00 6,000.00 6,000.00
348,000.00 348,000.00
b. Tenaga
0.800 Oh Pekerja 77,500.00 62,000.00 62,000.00
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
0.200 Oh Kepala Tukang 150,000.00 30,000.00 30,000.00
0.040 Oh Mandor 150,000.00 6,000.00 6,000.00
348,000.00 348,000.00
b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
3.000 Oh Tukang Kayu 125,000.00 375,000.00 375,000.00
0.300 Oh Kepala Tukang 150,000.00 45,000.00 45,000.00
0.300 Oh Mandor 150,000.00 45,000.00 45,000.00
542,500.00 542,500.00
b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
3.000 Oh Tukang Kayu 125,000.00 375,000.00 375,000.00
0.300 Oh Kepala Tukang 150,000.00 45,000.00 45,000.00
0.500 Oh Mandor 150,000.00 75,000.00 75,000.00
572,500.00 572,500.00
b. Tenaga
0.600 Oh Pekerja 77,500.00 46,500.00 46,500.00
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
0.200 Oh Kepala Tukang 150,000.00 30,000.00 30,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
331,000.00 331,000.00
Jumlah 219,435.00 331,000.00 550,435.00
a. Bahan
0.0196 M3 Kayu Kelas II 6,600,000.00 129,360.00 129,360.00
1.000 Lbr Plywood Sungkai 3 mm 121,000.00 121,000.00 121,000.00
0.300 Ltr Lem Kayu 22,000.00 6,600.00 6,600.00
0.030 Kg Paku Biasa /2" - 1"
1
32,500.00 975.00 975.00
257,935.00 257,935.00
b. Tenaga
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
0.200 Oh Kepala Tukang 150,000.00 30,000.00 30,000.00
0.600 Oh Pekerja 77,500.00 46,500.00 46,500.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
331,000.00 331,000.00
a. Bahan
1.100 M3 Kayu Kelas II, Balok 6,600,000.00 7,260,000.00 7,260,000.00
15 Kg Besi Strip 11,000.00 165,000.00 165,000.00
0.800 Kg Paku Biasa 2" - 5" 28,500.00 22,800.00 22,800.00
7,447,800.00 7,447,800.00
b. Tenaga
4.000 Oh Pekerja 77,500.00 310,000.00 310,000.00
12.000 Oh Tukang Kayu 125,000.00 1,500,000.00 1,500,000.00
1.200 Oh Kepala Tukang 150,000.00 180,000.00 180,000.00
0.200 Oh Mandor 150,000.00 30,000.00 30,000.00
2,020,000.00 2,020,000.00
a. Bahan
0.012 M3 Kayu Kelas III, Untuk genteng kodok/biasa 3,630,000.00 43,560.00 43,560.00
0.014 M3 Kayu Kelas III, untuk genteng beton/keramik 3,630,000.00 50,820.00 50,820.00
0.150 Kg Paku Biasa 2" - 5" 28,500.00 4,275.00 4,275.00
kayu kls. III, untuk genteng kodok/biasa 47,835.00 47,835.00
kayu kls. III, untuk genteng beton 55,095.00 55,095.00
b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.005 Oh Mandor 150,000.00 750.00 750.00
22,500.00 22,500.00
kayu kls. III, untuk genteng kodok/biasa 47,835.00 22,500.00 70,335.00
kayu kls. III, untuk genteng beton 55,095.00 22,500.00 77,595.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.250 Oh Tukang Kayu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
57,875.00 57,875.00
a. Bahan
0.012 M3 Kayu Kls. II 6,600,000.00 79,200.00 79,200.00
0.100 Kg Paku Biasa 2" - 5" 28,500.00 2,850.00 2,850.00
82,050.00 82,050.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.250 Oh Tukang Kayu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
57,875.00 57,875.00
a. Bahan
0.023 M3 Kayu Jati, Balok 9,075,000.00 208,725.00 208,725.00
0.150 Kg Paku Biasa 2" - 5" 28,500.00 4,275.00 4,275.00
213,000.00 213,000.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.300 Oh Tukang Kayu 125,000.00 37,500.00 37,500.00
0.030 Oh Kepala Tukang 150,000.00 4,500.00 4,500.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
59,000.00 59,000.00
a. Bahan
0.023 M3 Kayu Kls. II 6,600,000.00 151,800.00 151,800.00
0.150 Kg Paku Biasa 2" - 5" 28,500.00 4,275.00 4,275.00
156,075.00 156,075.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.300 Oh Tukang Kayu 125,000.00 37,500.00 37,500.00
0.030 Oh Kepala Tukang 150,000.00 4,500.00 4,500.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
59,000.00 59,000.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.300 Oh Tukang Kayu 125,000.00 37,500.00 37,500.00
0.030 Oh Kepala Tukang 150,000.00 4,500.00 4,500.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
59,000.00 59,000.00
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.350 Oh Tukang Kayu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
70,250.00 70,250.00
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.350 Oh Tukang Kayu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
70,250.00 70,250.00
b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.0050 Oh Mandor 150,000.00 750.00 750.00
37,250.00 37,250.00
b. Tenaga
0.110 Oh Pekerja 77,500.00 8,525.00 8,525.00
0.220 Oh Tukang Kayu 125,000.00 27,500.00 27,500.00
0.022 Oh Kepala Tukang 150,000.00 3,300.00 3,300.00
0.005 Oh Mandor 150,000.00 750.00 750.00
40,075.00 40,075.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.250 Oh Tukang Kayu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
57,875.00 57,875.00
b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
29,250.00 29,250.00
6.38 1 M' Pasang Lisplang Ukuran 2 x (2 x 20) cm, Kayu Kls. III
a. Bahan
0.0088 M3 Kayu Kls. III 3,630,000.00 31,944.00 31,944.00
0.060 Kg Paku Biasa 2" - 5" 28,500.00 1,710.00 1,710.00
33,654.00 33,654.00
b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
29,250.00 29,250.00
a. Bahan
0.0195 M3 Kayu Kls. II, Balok 6,600,000.00 128,700.00 128,700.00
0.007 M3 Kayu Kls.II, Papan 6,600,000.00 46,200.00 46,200.00
0.100 Kg Paku Biasa 2" - 5" 28,500.00 2,850.00 2,850.00
177,750.00 177,750.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.450 Oh Tukang Kayu 125,000.00 56,250.00 56,250.00
0.045 Oh Kepala Tukang 150,000.00 6,750.00 6,750.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
85,875.00 85,875.00
a. Bahan
0.0195 M3 Kayu Kls. III, Balok 3,630,000.00 70,785.00 70,785.00
0.007 M3 Kayu Kls. III, Papan 3,630,000.00 25,410.00 25,410.00
0.100 Kg Paku Biasa 2" - 5" 28,500.00 2,850.00 2,850.00
99,045.00 99,045.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.450 Oh Tukang Kayu 125,000.00 56,250.00 56,250.00
0.045 Oh Kepala Tukang 150,000.00 6,750.00 6,750.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
85,875.00 85,875.00
a. Bahan
0.0195 M3 Kayu Kls. II, Balok 6,600,000.00 128,700.00 128,700.00
0.007 M3 Kayu Kls. II, Papan 6,600,000.00 46,200.00 46,200.00
0.100 Kg Paku Biasa 2" - 5" 28,500.00 2,850.00 2,850.00
177,750.00 177,750.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.450 Oh Tukang Kayu 125,000.00 56,250.00 56,250.00
0.045 Oh Kepala Tukang 150,000.00 6,750.00 6,750.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
85,875.00 85,875.00
6.42 1 M Pasang Dinding Pemisah Plywood Rangkap, Rangka Kayu Kelas III
2
a. Bahan
0.0195 M3 Kayu Kelas III, Balok 3,630,000.00 70,785.00 70,785.00
0.007 M3 Kayu Kelas III, Papan 3,630,000.00 25,410.00 25,410.00
0.100 Kg Paku Biasa 2" - 5" 28,500.00 2,850.00 2,850.00
0.560 Ltr Lem Kayu 22,000.00 12,320.00 12,320.00
1.000 Lbr Plywood 4' x 8' x 4 mm 82,500.00 82,500.00 82,500.00
193,865.00 193,865.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.600 Oh Tukang Kayu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
101,000.00 101,000.00
6.47 1 M2 Pasang lapis plywood Sungkay tanpa rangka, politur dan lis profil
a. Bahan
0.36 Kpg Plywood Sungkay 3 mm 121,000.00 43,560.00 43,560.00
0.050 Kg Paku 1/2" - 1 " 32,500.00 1,625.00 1,625.00
45,185.00 45,185.00
b. Tenaga
0.075 Oh Tukang Kayu 125,000.00 9,375.00 9,375.00
0.0075 Oh Kepala Tukang 150,000.00 1,125.00 1,125.00
0.025 Oh Pekerja 77,500.00 1,937.50 1,937.50
0.0013 Oh Mandor 150,000.00 195.00 195.00
12,632.50 12,632.50
45,185.00 12,632.50 57,817.50
6.48 1 M2 Pasang lapis plywood Sungkay + list kayu, tanpa rangka dan politur
a. Bahan
0.36 Kpg Plywood Sungkay 3 mm 121,000.00 43,560.00 43,560.00
0.250 LS List kayu 2,750.00 687.50 687.50
0.150 Kg Paku 1/2" - 2 " 32,500.00 4,875.00 4,875.00
2.000 Lbr Amplas 3,850.00 7,700.00 7,700.00
56,822.50 56,822.50
b. Tenaga
0.096 Oh Tukang Kayu 125,000.00 12,000.00 12,000.00
0.010 Oh Kepala Tukang 150,000.00 1,425.00 1,425.00
0.046 Oh Pekerja 77,500.00 3,565.00 3,565.00
0.0023 Oh Mandor 150,000.00 345.00 345.00
17,335.00 17,335.00
Bahan
0.36 Kpg Plywood Jati 3 mm 121,000.00 43,560.00 43,560.00
0.36 Kpg Plywood 20 mm 278,000.00 100,080.00 100,080.00
0.600 Kg Lem Vinyl 9,350.00 5,610.00 5,610.00
0.150 Ltr Politur dasar 53,900.00 8,085.00 8,085.00
0.372 Ltr Politur jadi 58,300.00 21,687.60 21,687.60
2.000 Lbr Amplas 3,850.00 7,700.00 7,700.00
0.220 Kg Paku 28,500.00 6,270.00 6,270.00
192,992.60 192,992.60
Tenaga
0.025 Oh Pekerja 77,500.00 1,937.50 1,937.50
0.135 Oh Tukang Kayu 125,000.00 16,875.00 16,875.00
0.024 Oh Kepala Tukang 150,000.00 3,525.00 3,525.00
0.0038 Oh Mandor 150,000.00 570.00 570.00
22,907.50 22,907.50
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
192,992.60 22,907.50 215,900.10
b. Tenaga
0.450 Oh Tukang Kayu 125,000.00 56,250.00 56,250.00
0.0450 Oh Kepala Tukang 150,000.00 6,750.00 6,750.00
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
85,875.00 85,875.00
b. Tenaga
1.650 Oh Pekerja 77,500.00 127,875.00 127,875.00
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
174,875.00 174,875.00
b. Tenaga
1.650 Oh Pekerja 77,500.00 127,875.00 127,875.00
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
174,875.00 174,875.00
7.5 1 M Membuat
3
Beton Tak Bertulang, 1 Pc : 2 Ps : 3 Kr
a. Bahan
232.000 Kg Semen Portland 1,700.00 394,400.00 394,400.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
860,853.48 860,853.48
b. Tenaga
1.650 Oh Pekerja 77,500.00 127,875.00 127,875.00
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
174,875.00 174,875.00
b. Tenaga
1.650 Oh Pekerja 77,500.00 127,875.00 127,875.00
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
174,875.00 174,875.00
b. Tenaga
1.650 Oh Pekerja 77,500.00 127,875.00 127,875.00
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
174,875.00 174,875.00
b. Tenaga
1.650 Oh Pekerja 77,500.00 127,875.00 127,875.00
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
174,875.00 174,875.00
b. Tenaga
2.000 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
1.000 Oh Mandor 150,000.00 150,000.00 150,000.00
354,000.00 354,000.00
b. Tenaga
2.000 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
1.000 Oh Mandor 150,000.00 150,000.00 150,000.00
354,000.00 354,000.00
b. Tenaga
2.000 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
1.000 Oh Mandor 150,000.00 150,000.00 150,000.00
354,000.00 354,000.00
7.16 1 M Membuat
3
Beton Tak Bertulang, 1 Pc : 1 Ps : 1 Split
a. Bahan
615.000 Kg Semen Portland 1,700.00 1,045,500.00 1,045,500.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.520 M3 Koral Beton Pecah Split 518,850.62 269,802.32 269,802.32
1,377,052.32 1,377,052.32
b. Tenaga
2.000 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
1.000 Oh Mandor 150,000.00 150,000.00 150,000.00
354,000.00 354,000.00
7.17 1 M Membuat
3
Beton Kedap Air dengan Strorox - 100
a. Bahan
400.000 Kg Semen Portland 1,700.00 680,000.00 680,000.00
0.480 M3 Pasir Beton 118,750.00 57,000.00 57,000.00
0.800 M3 Koral Beton 2/3 363,000.00 290,400.00 290,400.00
1.200 Kg Strorox - 100 - - -
1,027,400.00 1,027,400.00
b. Tenaga
2.000 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
1.000 Oh Mandor 150,000.00 150,000.00 150,000.00
354,000.00 354,000.00
Jumlah
b. Tenaga
0.007 Oh Pekerja 77,500.00 542.50 542.50
0.007 Oh Tukang Besi 125,000.00 875.00 875.00
0.0007 Oh Kepala Tukang 150,000.00 105.00 105.00
0.0003 Oh Mandor 150,000.00 45.00 45.00
1,567.50 1,567.50
b. Tenaga
0.005 Oh Pekerja 77,500.00 387.50 387.50
0.005 Oh Tukang Besi 125,000.00 625.00 625.00
0.0005 Oh Kepala Tukang 150,000.00 75.00 75.00
0.0003 Oh Mandor 150,000.00 45.00 45.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
1,132.50 1,132.50
Jumlah
b. Tenaga
0.300 Oh Pekerja 77,500.00 23,250.00 23,250.00
0.260 Oh Tukang Kayu 125,000.00 32,500.00 32,500.00
0.026 Oh Kepala Tukang 150,000.00 3,900.00 3,900.00
0.005 Oh Mandor 150,000.00 750.00 750.00
60,400.00 60,400.00
b. Tenaga
0.300 Oh Pekerja 77,500.00 23,250.00 23,250.00
0.260 Oh Tukang Kayu 125,000.00 32,500.00 32,500.00
0.026 Oh Kepala Tukang 150,000.00 3,900.00 3,900.00
0.005 Oh Mandor 150,000.00 750.00 750.00
60,400.00 60,400.00
a. Bahan
0.040 M3 Kayu Kls. IV 1,650,000.00 66,000.00 66,000.00
0.400 Kg Paku Biasa 2"- 5" 28,500.00 11,400.00 11,400.00
0.018 M3 Balok Kayu Kls. IV 1,650,000.00 29,700.00 29,700.00
2.000 Btg Kayu Gelam dia. 6-8 cm 8,800.00 17,600.00 17,600.00
124,700.00 124,700.00
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.330 Oh Tukang Kayu 125,000.00 41,250.00 41,250.00
0.033 Oh Kepala Tukang 150,000.00 4,950.00 4,950.00
0.006 Oh Mandor 150,000.00 900.00 900.00
71,900.00 71,900.00
a. Bahan
0.020 M3 Kayu Kls. IV 1,650,000.00 33,000.00 33,000.00
0.500 Btg Hek 9,900.00 4,950.00 4,950.00
2.000 Btg Kayu Gelam dia. 6-8 cm 8,800.00 17,600.00 17,600.00
0.200 Kg Paku Biasa 2"- 5" 28,500.00 5,700.00 5,700.00
61,250.00 61,250.00
b. Tenaga
0.160 Oh Pekerja 77,500.00 12,400.00 12,400.00
0.165 Oh Tukang Kayu 125,000.00 20,625.00 20,625.00
0.017 Oh Kepala Tukang 150,000.00 2,475.00 2,475.00
0.003 Oh Mandor 150,000.00 450.00 450.00
35,950.00 35,950.00
7.26 1 M Pasang Bekisting Untuk Lantai, plat dak (untuk bangunan gedung)
2
a. Bahan
0.040 M3 Kayu Kls. IV 1,650,000.00 66,000.00 66,000.00
0.400 Kg Paku Biasa 2"- 5" 28,500.00 11,400.00 11,400.00
0.015 M3 Balok Kayu Kls.IV 1,650,000.00 24,750.00 24,750.00
6.000 Btg Kayu Gelam dia. 6-8 cm 8,800.00 52,800.00 52,800.00
154,950.00 154,950.00
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.330 Oh Tukang Batu 125,000.00 41,250.00 41,250.00
0.033 Oh Kepala Tukang 150,000.00 4,950.00 4,950.00
0.006 Oh Mandor 150,000.00 900.00 900.00
71,900.00 71,900.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.330 Oh Tukang Kayu 125,000.00 41,250.00 41,250.00
0.033 Oh Kepala Tukang 150,000.00 4,950.00 4,950.00
0.006 Oh Mandor 150,000.00 900.00 900.00
71,900.00 71,900.00
a. Bahan
1.0 M3 Beton Ready Mix K 250 1,045,000.00 1,065,900.00 1,065,900.00
1,065,900.00 1,065,900.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
1 Ls Pengangkutan dan mobilisasi mobil Pick up 15,583.33 15,583.33 15,583.33
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
199,170.88 199,170.88
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
183,587.55 183,587.55
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
1 Ls Pengangkutan dan mobilisasi mobil Pick up 15,583.33 15,583.33 15,583.33
199,170.88 199,170.88
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
183,587.55 183,587.55
a. Bahan
1.0 M3 Beton Ready Mix K 300 1,155,000.00 1,178,100.00 1,178,100.00
1,178,100.00 1,178,100.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
1 Ls Pengangkutan dan mobilisasi mobil Pick up 15,583.33 15,583.33 15,583.33
199,170.88 199,170.88
a. Bahan
1.0 M3 Beton Ready Mix K 300 1,155,000.00 1,178,100.00 1,178,100.00
1,178,100.00 1,178,100.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
183,587.55 183,587.55
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
183,587.55 183,587.55
7.42 1 M' Pasang Kayu Mal Bekisting untuk Beton Ready Mix jalan
a. Bahan
0.5 Kpg Papan Kayu Kls. IV 18,150.00 9,075.00 9,075.00
0.200 Kg Paku Biasa 2"- 5" 28,500.00 5,700.00 5,700.00
0.009 M3 Balok Kayu Kls. IV 1,650,000.00 14,850.00 14,850.00
29,625.00 29,625.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
b. Tenaga
0.160 Oh Pekerja 77,500.00 12,400.00 12,400.00
0.165 Oh Tukang Kayu 125,000.00 20,625.00 20,625.00
0.0165 Oh Kepala Tukang 150,000.00 2,475.00 2,475.00
0.003 Oh Mandor 150,000.00 450.00 450.00
35,950.00 35,950.00
a. Bahan
0.0264 M3 Kayu Kls. IV 1,650,000.00 43,560.00 43,560.00
0.600 Kg Paku Biasa 2"- 5" 28,500.00 17,100.00 17,100.00
0.500 Btg Kayu Gelam dia. 6-8 cm 8,800.00 4,400.00 4,400.00
65,060.00 65,060.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.050 Oh Tukang Kayu 125,000.00 6,250.00 6,250.00
0.005 Oh Kepala Tukang 150,000.00 750.00 750.00
0.007 Oh Mandor 150,000.00 1,050.00 1,050.00
19,675.00 19,675.00
b. Tenaga
3.900 Oh Pekerja 77,500.00 302,250.00 302,250.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
1.040 Oh Tukang Kayu 125,000.00 130,000.00 130,000.00
1.050 Oh Tukang Besi 125,000.00 131,250.00 131,250.00
0.245 Oh Kepala Tukang 150,000.00 36,750.00 36,750.00
0.165 Oh Mandor 150,000.00 24,750.00 24,750.00
668,750.00 668,750.00
b. Tenaga
7.300 Oh Pekerja 77,500.00 565,750.00 565,750.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
3.300 Oh Tukang Kayu 125,000.00 412,500.00 412,500.00
2.100 Oh Tukang Besi 125,000.00 262,500.00 262,500.00
0.570 Oh Kepala Tukang 150,000.00 85,500.00 85,500.00
0.250 Oh Mandor 150,000.00 37,500.00 37,500.00
1,407,500.00 1,407,500.00
b. Tenaga
7.300 Oh Pekerja 77,500.00 565,750.00 565,750.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
3.300 Oh Tukang Kayu 125,000.00 412,500.00 412,500.00
2.100 Oh Tukang Besi 125,000.00 262,500.00 262,500.00
0.570 Oh Kepala Tukang 150,000.00 85,500.00 85,500.00
0.250 Oh Mandor 150,000.00 37,500.00 37,500.00
1,407,500.00 1,407,500.00
b. Tenaga
7.300 Oh Pekerja 77,500.00 565,750.00 565,750.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
3.300 Oh Tukang Kayu 125,000.00 412,500.00 412,500.00
2.100 Oh Tukang Besi 125,000.00 262,500.00 262,500.00
0.570 Oh Kepala Tukang 150,000.00 85,500.00 85,500.00
0.250 Oh Mandor 150,000.00 37,500.00 37,500.00
1,407,500.00 1,407,500.00
Jumlah 3,354,953.48 1,407,500.00 4,762,453.48
b. Tenaga
5.960 Oh Pekerja 77,500.00 461,900.00 461,900.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
2.800 Oh Tukang Kayu 125,000.00 350,000.00 350,000.00
1.400 Oh Tukang Besi 125,000.00 175,000.00 175,000.00
0.455 Oh Kepala Tukang 150,000.00 68,250.00 68,250.00
0.208 Oh Mandor 150,000.00 31,200.00 31,200.00
1,130,100.00 1,130,100.00
a. Bahan
0.320 M3 Kayu Kls. IV 1,650,000.00 528,000.00 528,000.00
3.200 Kg Paku Biasa 2"- 5" 28,500.00 91,200.00 91,200.00
150 Kg Besi Beton Polos 12,075.00 1,811,250.00 1,811,250.00
2.250 Kg Kawat Beton 19,800.00 44,550.00 44,550.00
232 Kg Semen Portland 1,700.00 394,400.00 394,400.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
0.120 M3 Kayu Balok Kls. IV 1,650,000.00 198,000.00 198,000.00
32 Btg Kayu Gelam dia. 6-8 cm 8,800.00 281,600.00 281,600.00
3,815,453.48 3,815,453.48
b. Tenaga
5.800 Oh Pekerja 77,500.00 449,500.00 449,500.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
2.800 Oh Tukang Kayu 125,000.00 350,000.00 350,000.00
1.050 Oh Tukang Besi 125,000.00 131,250.00 131,250.00
0.420 Oh Kepala Tukang 150,000.00 63,000.00 63,000.00
0.185 Oh Mandor 150,000.00 27,750.00 27,750.00
1,065,250.00 1,065,250.00
7.53 1 M Membuat
3
Balok Beton Bertulang ( 100 Kg Besi + Bekisting )
a. Bahan
0.320 M3 Kayu Kls. IV 1,650,000.00 528,000.00 528,000.00
3.200 Kg Paku Biasa 2"- 5" 28,500.00 91,200.00 91,200.00
110 Kg Besi Beton Polos 12,075.00 1,328,250.00 1,328,250.00
2.250 Kg Kawat Beton 19,800.00 44,550.00 44,550.00
232 Kg Semen Portland 1,700.00 394,400.00 394,400.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
0.120 M3 Kayu Balok Kls. IV 1,650,000.00 198,000.00 198,000.00
32 Btg Kayu Gelam dia. 6-8 cm 8,800.00 281,600.00 281,600.00
3,332,453.48 3,332,453.48
b. Tenaga
5.800 Oh Pekerja 77,500.00 449,500.00 449,500.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
2.800 Oh Tukang Kayu 125,000.00 350,000.00 350,000.00
1.050 Oh Tukang Besi 125,000.00 131,250.00 131,250.00
0.420 Oh Kepala Tukang 150,000.00 63,000.00 63,000.00
0.185 Oh Mandor 150,000.00 27,750.00 27,750.00
1,065,250.00 1,065,250.00
b. Tenaga
5.600 Oh Pekerja 77,500.00 434,000.00 434,000.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
2.640 Oh Tukang Kayu 125,000.00 330,000.00 330,000.00
1.050 Oh Tukang Besi 125,000.00 131,250.00 131,250.00
0.400 Oh Kepala Tukang 150,000.00 60,000.00 60,000.00
0.193 Oh Mandor 150,000.00 28,950.00 28,950.00
1,027,950.00 1,027,950.00
b. Tenaga
5.600 Oh Pekerja 91,300.00 511,280.00 511,280.00
0.350 Oh Tukang Batu 47,300.00 16,555.00 16,555.00
2.640 Oh Tukang Kayu 47,300.00 124,872.00 124,872.00
1.050 Oh Tukang Besi 47,300.00 49,665.00 49,665.00
0.400 Oh Kepala Tukang 7,150.00 2,860.00 2,860.00
0.193 Oh Mandor 66,000.00 12,738.00 12,738.00
717,970.00 717,970.00
a. Bahan
0.250 M3 Kayu Kls. IV 1,650,000.00 412,500.00 412,500.00
3.000 Kg Paku Biasa 2"- 5" 28,500.00 85,500.00 85,500.00
200.000 Kg Besi Beton Polos 12,075.00 2,415,000.00 2,415,000.00
3.000 Kg Kawat Beton 19,800.00 59,400.00 59,400.00
232.000 Kg Semen Portland 1,700.00 394,400.00 394,400.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
0.105 M3 Kayu Balok Kls. IV 1,650,000.00 173,250.00 173,250.00
14.000 Btg Kayu Gelam dia. 6-8 cm 8,800.00 123,200.00 123,200.00
4,129,703.48 4,129,703.48
b. Tenaga
5.600 Oh Pekerja 77,500.00 434,000.00 434,000.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
2.300 Oh Tukang Kayu 125,000.00 287,500.00 287,500.00
1.400 Oh Tukang Besi 125,000.00 175,000.00 175,000.00
0.405 Oh Kepala Tukang 150,000.00 60,750.00 60,750.00
0.202 Oh Mandor 150,000.00 30,300.00 30,300.00
1,031,300.00 1,031,300.00
7.57 1 M' Membuat Kolom Penguat Beton Bertulang ( 11 x 11 ) cm + bekisting (kolom praktis)
a. Bahan
0.002 M3 Kayu Kls. IV 1,650,000.00 3,300.00 3,300.00
0.010 Kg Paku Biasa 2"- 5" 28,500.00 285.00 285.00
3.000 Kg Besi Beton Polos 12,075.00 36,225.00 36,225.00
0.450 Kg Kawat Beton 19,800.00 8,910.00 8,910.00
4.000 Kg Semen Portland 1,700.00 6,800.00 6,800.00
0.006 M3 Pasir Beton 118,750.00 712.50 712.50
0.009 M3 Koral Beton 518,850.62 4,669.66 4,669.66
60,902.16 60,902.16
b. Tenaga
0.060 Oh Pekerja 77,500.00 4,650.00 4,650.00
0.020 Oh Tukang Batu 125,000.00 2,500.00 2,500.00
0.020 Oh Tukang Kayu 125,000.00 2,500.00 2,500.00
0.020 Oh Tukang Besi 125,000.00 2,500.00 2,500.00
0.006 Oh Kepala Tukang 150,000.00 900.00 900.00
0.003 Oh Mandor 150,000.00 450.00 450.00
13,500.00 13,500.00
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.330 Oh Tukang Batu 125,000.00 41,250.00 41,250.00
0.033 Oh Kepala Tukang 150,000.00 4,950.00 4,950.00
0.006 Oh Mandor 150,000.00 900.00 900.00
71,900.00 71,900.00
7.60 1 M3 Beton Ready Mix K-175 untuk Kolom, Balok, Plat Lantai, tangga dengan Concrete Pump (belalai)
a. Bahan
1.020 M3 Beton Ready Mix K-175 935,000.00 953,700.00 953,700.00
953,700.00 953,700.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
0.16667 M3 Concrete Pump 409,815.23 68,303.91 68,303.91
251,891.46 251,891.46
7.61 1 M Beton Ready Mix K-175 untuk Kolom, Balok, Plat Lantai, tangga tanpa Concrete Pump (belalai)
3
a. Bahan
1.020 M3 Beton Ready Mix K-175 935,000.00 953,700.00 953,700.00
953,700.00 953,700.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
183,587.55 183,587.55
7.62 1 M3 Beton Ready Mix K-225 untuk Kolom, Balok, Plat Lantai, tangga dengan Concrete Pump (belalai)
a. Bahan
1.020 M3 Beton Ready Mix K-225 990,000.00 1,009,800.00 1,009,800.00
1,009,800.00 1,009,800.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
0.16667 M3 Concrete Pump 409,815.23 68,303.91 68,303.91
251,891.46 251,891.46
7.63 1 M Beton Ready Mix K-225 untuk Kolom, Balok, Plat Lantai, tangga tanpa Concrete Pump (belalai)
3
a. Bahan
1.020 M3 Beton Ready Mix K-225 990,000.00 1,009,800.00 1,009,800.00
1,009,800.00 1,009,800.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
183,587.55 183,587.55
7.64 1 M3 Beton Ready Mix K-275 untuk Kolom, Balok, Plat Lantai, tangga dengan Concrete Pump (belalai)
a. Bahan
1.020 M3 Beton Ready Mix K-275 1,100,000.00 1,122,000.00 1,122,000.00
1,122,000.00 1,122,000.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
0.16667 M3 Concrete Pump 409,815.23 68,303.91 68,303.91
251,891.46 251,891.46
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.075 Oh Tukang Kayu 125,000.00 9,375.00 9,375.00
0.008 Oh Kepala Tukang 150,000.00 1,200.00 1,200.00
0.008 Oh Mandor 150,000.00 1,200.00 1,200.00
23,400.00 23,400.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.075 Oh Tukang Kayu 125,000.00 9,375.00 9,375.00
0.008 Oh Kepala Tukang 150,000.00 1,200.00 1,200.00
0.008 Oh Mandor 150,000.00 1,200.00 1,200.00
23,400.00 23,400.00
b. Tenaga
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.002 Oh Mandor 150,000.00 300.00 300.00
59,300.00 59,300.00
8.7 1 M' Pasang Bubung Genteng Keramik KIA Natural atau sejenis
a. Bahan
3.000 Bh Genteng Bubung Keramik KIA Natural atau sejenis 22,000.00 66,000.00 66,000.00
8.000 Kg Semen Portland 1,700.00 13,600.00 13,600.00
0.032 M3 Pasir Pasang 118,750.00 3,800.00 3,800.00
83,400.00 83,400.00
b. Tenaga
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.002 Oh Mandor 150,000.00 300.00 300.00
59,300.00 59,300.00
8.8 1 M' Pasang Bubung Genteng Keramik KIA Warna atau sejenis
a. Bahan
3.000 Bh Genteng Bubung Keramik KIA Warna atau sejenis 27,500.00 82,500.00 82,500.00
8.000 Kg Semen Portland 1,700.00 13,600.00 13,600.00
0.032 M3 Pasir Pasang 118,750.00 3,800.00 3,800.00
99,900.00 99,900.00
b. Tenaga
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.002 Oh Mandor 150,000.00 300.00 300.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
59,300.00 59,300.00
b. Tenaga
0.140 Oh Pekerja 77,500.00 10,850.00 10,850.00
0.067 Oh Tukang Kayu 125,000.00 8,375.00 8,375.00
0.007 Oh Kepala Tukang 150,000.00 1,050.00 1,050.00
0.007 Oh Mandor 150,000.00 1,050.00 1,050.00
21,325.00 21,325.00
b. Tenaga
0.140 Oh Pekerja 77,500.00 10,850.00 10,850.00
0.067 Oh Tukang Kayu 125,000.00 8,375.00 8,375.00
0.007 Oh Kepala Tukang 150,000.00 1,050.00 1,050.00
0.007 Oh Mandor 150,000.00 1,050.00 1,050.00
21,325.00 21,325.00
b. Tenaga
0.140 Oh Pekerja 77,500.00 10,850.00 10,850.00
0.067 Oh Tukang Kayu 125,000.00 8,375.00 8,375.00
0.007 Oh Kepala Tukang 150,000.00 1,050.00 1,050.00
0.007 Oh Mandor 150,000.00 1,050.00 1,050.00
21,325.00 21,325.00
b. Tenaga
0.140 Oh Pekerja 77,500.00 10,850.00 10,850.00
0.067 Oh Tukang Kayu 125,000.00 8,375.00 8,375.00
0.007 Oh Kepala Tukang 150,000.00 1,050.00 1,050.00
0.007 Oh Mandor 150,000.00 1,050.00 1,050.00
21,325.00 21,325.00
b. Tenaga
0.140 Oh Pekerja 77,500.00 10,850.00 10,850.00
0.067 Oh Tukang Kayu 125,000.00 8,375.00 8,375.00
0.007 Oh Kepala Tukang 150,000.00 1,050.00 1,050.00
0.007 Oh Mandor 150,000.00 1,050.00 1,050.00
21,325.00 21,325.00
b. Tenaga
0.084 Oh Pekerja 77,500.00 6,510.00 6,510.00
0.125 Oh Tukang Kayu 125,000.00 15,625.00 15,625.00
0.013 Oh Kepala Tukang 150,000.00 1,950.00 1,950.00
0.004 Oh Mandor 150,000.00 600.00 600.00
24,685.00 24,685.00
b. Tenaga
0.084 Oh Pekerja 77,500.00 6,510.00 6,510.00
0.125 Oh Tukang Kayu 125,000.00 15,625.00 15,625.00
0.013 Oh Kepala Tukang 150,000.00 1,950.00 1,950.00
0.004 Oh Mandor 150,000.00 600.00 600.00
24,685.00 24,685.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
31,000.00 31,000.00
a. Bahan
1.020 M2 Genteng Metal 40,700.00 41,514.00 41,514.00
0.200 Kg Paku Biasa 2" - 5" 28,500.00 5,700.00 5,700.00
47,214.00 47,214.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.001 Oh Mandor 150,000.00 150.00 150.00
29,650.00 29,650.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.001 Oh Mandor 150,000.00 150.00 150.00
29,650.00 29,650.00
b. Tenaga
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.020 Oh Mandor 150,000.00 3,000.00 3,000.00
62,000.00 62,000.00
b. Tenaga
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.020 Oh Mandor 150,000.00 3,000.00 3,000.00
62,000.00 62,000.00
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.150 Oh Tukang Kayu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.013 Oh Mandor 150,000.00 1,950.00 1,950.00
42,325.00 42,325.00
a. Bahan
1.020 M2 Seng Gelombang BJLS 8,167.50 8,330.85 8,330.85
0.020 Kg Paku Biasa /2" - 1"
1
32,500.00 650.00 650.00
8,980.85 8,980.85
b. Tenaga
0.120 Oh Pekerja 77,500.00 9,300.00 9,300.00
0.060 Oh Tukang Kayu 125,000.00 7,500.00 7,500.00
0.006 Oh Kepala Tukang 150,000.00 900.00 900.00
0.006 Oh Mandor 150,000.00 900.00 900.00
18,600.00 18,600.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.070 Oh Tukang Kayu 125,000.00 8,750.00 8,750.00
0.008 Oh Kepala Tukang 150,000.00 1,200.00 1,200.00
0.006 Oh Mandor 150,000.00 900.00 900.00
22,475.00 22,475.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.750 Oh Tukang Kayu 125,000.00 93,750.00 93,750.00
0.008 Oh Kepala Tukang 150,000.00 1,200.00 1,200.00
0.006 Oh Mandor 150,000.00 900.00 900.00
107,475.00 107,475.00
b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
1.000 Oh Tukang Kayu 125,000.00 125,000.00 125,000.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
135,750.00 135,750.00
IX PEKERJAAN LANGIT-LANGIT
9.1 1 M2 Langit-langit Asbes/Eternit ( 1,00 x 1,00 ) m, Tebal 2,7 mm
a. Bahan
1.100 Lbr Asbes/Eternit Tebal 2,7 mm 25,300.00 27,830.00 27,830.00
0.010 Kg Paku 32,500.00 325.00 325.00
28,155.00 28,155.00
b. Tenaga
0.030 Oh Pekerja 77,500.00 2,325.00 2,325.00
0.070 Oh Tukang Kayu 125,000.00 8,750.00 8,750.00
0.007 Oh Kepala Tukang 150,000.00 1,050.00 1,050.00
0.0015 Oh Mandor 150,000.00 225.00 225.00
12,350.00 12,350.00
a. Bahan
1.100 Lbr Asbes / Eternit Tebal 3,5 mm 29,700.00 32,670.00 32,670.00
0.010 Kg Paku 32,500.00 325.00 325.00
32,995.00 32,995.00
b. Tenaga
0.030 Oh Pekerja 77,500.00 2,325.00 2,325.00
0.070 Oh Tukang Kayu 125,000.00 8,750.00 8,750.00
0.007 Oh Kepala Tukang 150,000.00 1,050.00 1,050.00
0.0015 Oh Mandor 150,000.00 225.00 225.00
12,350.00 12,350.00
a. Bahan
0.360 Kpg Kalsiboard Tebal 3,5 mm 72,800.00 26,208.00 26,208.00
0.010 Kg Paku 32,500.00 325.00 325.00
26,533.00 26,533.00
b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0035 Oh Mandor 150,000.00 525.00 525.00
19,950.00 19,950.00
b. Tenaga
19,950.00 19,950.00
9.5 1
a.M Langit-langit
Bahan
2
0.012 Kg
0.060 Asbes/Eternit,
M3 Paku
Kayu Rangka Kayu Kls. II
Kls. II, Balok
Biasa 6,600,000.00
28,500.00 79,200.00
1,710.00 79,200.00
1,710.00
1.100 M2 Asbes / Eternit tebal 2,7 mm 25,300.00 27,830.00 27,830.00
1.100 M2 Asbes / Eternit tebal 3,5 mm 29,700.00 32,670.00 32,670.00
Tebal 2,7 mm 108,740.00 108,740.00
Tebal 3,5 mm 113,580.00 113,580.00
b. Tenaga
0.180 Oh Pekerja 77,500.00 13,950.00 13,950.00
0.320 Oh Tukang Kayu 125,000.00 40,000.00 40,000.00
0.032 Oh Kepala Tukang 150,000.00 4,800.00 4,800.00
0.009 Oh Mandor 150,000.00 1,350.00 1,350.00
60,100.00 60,100.00
1 M2 Eternit tebal 2,7 mm, rangka kayu kls. II 108,740.00 60,100.00 168,840.00
1 M2 Eternit tebal 3,5 mm, rangka kayu kls. II 113,580.00 60,100.00 173,680.00
b. Tenaga
0.180 Oh Pekerja 77,500.00 13,950.00 13,950.00
0.320 Oh Tukang Kayu 125,000.00 40,000.00 40,000.00
0.032 Oh Kepala Tukang 150,000.00 4,800.00 4,800.00
0.009 Oh Mandor 150,000.00 1,350.00 1,350.00
60,100.00 60,100.00
1 M2 Eternit tebal 2,7 mm, rangka kayu kls. III 73,100.00 60,100.00 133,200.00
1 M2 Eternit tebal 3,5 mm, rangka kayu kls. III 77,940.00 60,100.00 138,040.00
1 M2 Kalsiboard tebal 3,5 mm, rangka kayu kls. II 107,118.00 78,950.00 186,068.00
1 M2 Kalsiboard tebal 4,5 mm, rangka kayu kls. II 109,170.00 78,950.00 188,120.00
1 M2 Kalsiboard tebal 3,5 mm, rangka kayu kls. III 71,478.00 78,950.00 150,428.00
1 M2 Kalsiboard tebal 4,5 mm, rangka kayu kls. III 73,530.00 78,950.00 152,480.00
b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0035 Oh Mandor 150,000.00 525.00 525.00
19,950.00 19,950.00
b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0035 Oh Mandor 150,000.00 525.00 525.00
19,950.00 19,950.00
b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0035 Oh Mandor 150,000.00 525.00 525.00
19,950.00 19,950.00
b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0035 Oh Mandor 150,000.00 525.00 525.00
19,950.00 19,950.00
b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0035 Oh Mandor 150,000.00 525.00 525.00
19,950.00 19,950.00
b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0035 Oh Mandor 150,000.00 525.00 525.00
19,950.00 19,950.00
b. Tenaga
0.270 Oh Pekerja 77,500.00 20,925.00 20,925.00
0.400 Oh Tukang Kayu 125,000.00 50,000.00 50,000.00
0.040 Oh Kepala Tukang 150,000.00 6,000.00 6,000.00
0.0135 Oh Mandor 150,000.00 2,025.00 2,025.00
78,950.00 78,950.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
1 M2 Plywood tebal 3 mm, rangka kayu kls. III 64,242.00 78,950.00 143,192.00
1 M2 Plywood tebal 4 mm, rangka kayu kls. III 74,970.00 78,950.00 153,920.00
1 M2 Plywood tebal 6 mm, rangka kayu kls. III 82,278.00 78,950.00 161,228.00
1 M2 Plywood tebal 9 mm, rangka kayu kls. III 98,730.00 78,950.00 177,680.00
1 M2 Plywood tebal 12 mm, rangka kayu kls. III 113,526.00 78,950.00 192,476.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.600 Oh Tukang Kayu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
101,000.00 101,000.00
b. Tenaga
0.260 Oh Pekerja 77,500.00 20,150.00 20,150.00
0.400 Oh Tukang Kayu 125,000.00 50,000.00 50,000.00
0.040 Oh Kepala Tukang 150,000.00 6,000.00 6,000.00
0.0130 Oh Mandor 150,000.00 1,950.00 1,950.00
78,100.00 78,100.00
1 M2 Gypsum Board 9 mm, rangka kayu kls. III 86,328.98 78,100.00 164,428.98
1 M2 Gypsum Board 9 mm, rangka kayu kls. II 121,968.98 78,100.00 200,068.98
1 M2 Gypsum Board 9 mm, rangka besi hollow 2/4 galvanis 111,518.98 78,100.00 189,618.98
X PEKERJAAN SANITASI
b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
1.500 Oh Tukang Batu 125,000.00 187,500.00 187,500.00
1.500 Oh Kepala Tukang 150,000.00 225,000.00 225,000.00
0.160 Oh Mandor 150,000.00 24,000.00 24,000.00
514,000.00 514,000.00
b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
1.500 Oh Tukang Batu 125,000.00 187,500.00 187,500.00
0.300 Oh Kepala Tukang 150,000.00 45,000.00 45,000.00
0.110 Oh Mandor 150,000.00 16,500.00 16,500.00
326,500.00 326,500.00
b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
1.000 Oh Tukang Batu 125,000.00 125,000.00 125,000.00
0.100 Oh Kepala Tukang 150,000.00 15,000.00 15,000.00
0.100 Oh Mandor 150,000.00 15,000.00 15,000.00
232,500.00 232,500.00
b. Tenaga
1.200 Oh Pekerja 77,500.00 93,000.00 93,000.00
1.450 Oh Tukang Batu 125,000.00 181,250.00 181,250.00
0.150 Oh Kepala Tukang 150,000.00 22,500.00 22,500.00
0.100 Oh Mandor 150,000.00 15,000.00 15,000.00
311,750.00 311,750.00
b. Tenaga
2.100 Oh Pekerja 77,500.00 162,750.00 162,750.00
0.750 Oh Tukang Batu 125,000.00 93,750.00 93,750.00
0.070 Oh Kepala Tukang 150,000.00 10,500.00 10,500.00
0.110 Oh Mandor 150,000.00 16,500.00 16,500.00
283,500.00 283,500.00
b. Tenaga
1.800 Oh Pekerja 77,500.00 139,500.00 139,500.00
2.700 Oh Tukang Batu 125,000.00 337,500.00 337,500.00
0.540 Oh Kepala Tukang 150,000.00 81,000.00 81,000.00
0.110 Oh Mandor 150,000.00 16,500.00 16,500.00
574,500.00 574,500.00
10.8 Memasang 1 Buah Bak Mandi Porselin Batu Bata Volume 0,30 m3
a. Bahan
0.400 M3 Batu Bata 638,500.00 255,400.00 255,400.00
120 Kg Semen Portland 1,700.00 204,000.00 204,000.00
0.300 M3 Pasir Pasang 118,750.00 35,625.00 35,625.00
360 Bh Porselen ( 11 x 11 ) cm 770.00 277,200.00 277,200.00
6 Kg Semen Nat 17,500.00 105,000.00 105,000.00
877,225.00 877,225.00
b. Tenaga
6 Oh Pekerja 77,500.00 465,000.00 465,000.00
3 Oh Tukang Batu 125,000.00 375,000.00 375,000.00
0.300 Oh Kepala Tukang 150,000.00 45,000.00 45,000.00
0.300 Oh Mandor 150,000.00 45,000.00 45,000.00
930,000.00 930,000.00
b. Tenaga
3.500 Oh Pekerja 77,500.00 271,250.00 271,250.00
4.500 Oh Tukang Batu 125,000.00 562,500.00 562,500.00
0.900 Oh Kepala Tukang 150,000.00 135,000.00 135,000.00
0.900 Oh Mandor 150,000.00 135,000.00 135,000.00
1,103,750.00 1,103,750.00
b. Tenaga
3.000 Oh Pekerja 77,500.00 232,500.00 232,500.00
4.500 Oh Tukang Batu 125,000.00 562,500.00 562,500.00
0.900 Oh Kepala Tukang 150,000.00 135,000.00 135,000.00
0.900 Oh Mandor 150,000.00 135,000.00 135,000.00
1,065,000.00 1,065,000.00
10.11 Memasang 1 M' Pipa Penyalur Air Limbah Jenis Pipa Tanah, dia. 15 cm
a. Bahan
1.600 M' Pipa Tanah (Paralon) dia. 15 cm 136,125.00 217,800.00 217,800.00
0.680 Kg Semen Portland 1,700.00 1,156.00 1,156.00
0.013 M3 Pasir Pasang 118,750.00 1,543.75 1,543.75
0.011 M3 Pasir Urug 82,500.00 907.50 907.50
221,407.25 221,407.25
b. Tenaga
0.060 Oh Pekerja 77,500.00 4,650.00 4,650.00
0.030 Oh Tukang Batu 125,000.00 3,750.00 3,750.00
0.003 Oh Kepala Tukang 150,000.00 450.00 450.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
9,225.00 9,225.00
Jumlah 221,407.25 9,225.00 230,632.25
10.12 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata Ukuran (30 x 30)
cm, Tinggi 35 cm
a. Bahan
0.145 M3 Batu Bata 638,500.00 92,582.50 92,582.50
44.000 Kg Semen Portland 1,700.00 74,800.00 74,800.00
0.070 M3 Pasir Pasang 118,750.00 8,312.50 8,312.50
0.070 M3 Batu Kerikil 440,000.00 30,800.00 30,800.00
1.600 Kg Besi Beton 12,075.00 19,320.00 19,320.00
0.060 M3 Pasir Beton 118,750.00 7,125.00 7,125.00
232,940.00 232,940.00
b. Tenaga
3.200 Oh Pekerja 77,500.00 248,000.00 248,000.00
1.015 Oh Tukang Batu 125,000.00 126,875.00 126,875.00
0.0015 Oh Kepala Tukang 150,000.00 225.00 225.00
0.016 Oh Mandor 150,000.00 2,400.00 2,400.00
377,500.00 377,500.00
10.13 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata Ukuran (45 x 45)
cm, Tinggi 50 cm
a. Bahan
0.250 M3 Batu Bata 638,500.00 159,625.00 159,625.00
77.000 Kg Semen Portland 1,700.00 130,900.00 130,900.00
0.130 M3 Pasir Pasang 118,750.00 15,437.50 15,437.50
0.020 M3 Batu Kerikil 440,000.00 8,800.00 8,800.00
2.600 Kg Besi Beton 12,075.00 31,395.00 31,395.00
0.090 M3 Pasir Beton 118,750.00 10,687.50 10,687.50
356,845.00 356,845.00
b. Tenaga
1.420 Oh Pekerja 77,500.00 110,050.00 110,050.00
0.473 Oh Tukang Batu 125,000.00 59,125.00 59,125.00
0.047 Oh Kepala Tukang 150,000.00 7,050.00 7,050.00
0.071 Oh Mandor 150,000.00 10,650.00 10,650.00
186,875.00 186,875.00
10.14 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata Ukuran (60 x 60)
cm, Tinggi 65 cm
a. Bahan
0.371 M3 Batu Bata 638,500.00 236,883.50 236,883.50
114.000 Kg Semen Portland 1,700.00 193,800.00 193,800.00
0.184 M3 Pasir Pasang 118,750.00 21,850.00 21,850.00
0.033 M3 Batu Kerikil 440,000.00 14,520.00 14,520.00
4.850 Kg Besi Beton 12,075.00 58,563.75 58,563.75
0.120 M3 Pasir Beton 118,750.00 14,250.00 14,250.00
539,867.25 539,867.25
b. Tenaga
2.160 Oh Pekerja 77,500.00 167,400.00 167,400.00
0.720 Oh Tukang Batu 125,000.00 90,000.00 90,000.00
0.100 Oh Tukang Gali 125,000.00 12,500.00 12,500.00
0.072 Oh Kepala Tukang 150,000.00 10,800.00 10,800.00
0.108 Oh Mandor 150,000.00 16,200.00 16,200.00
296,900.00 296,900.00
a. Bahan
1.200 M' Pipa Galvanis 20,350.00 24,420.00 24,420.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 7,122.50 7,122.50
31,542.50 31,542.50
b. Tenaga
0.054 Oh Pekerja 77,500.00 4,185.00 4,185.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.027 Oh Mandor 150,000.00 4,050.00 4,050.00
20,835.00 20,835.00
a. Bahan
1.200 M' Pipa Galvanis 25,740.00 30,888.00 30,888.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 9,009.00 9,009.00
39,897.00 39,897.00
b. Tenaga
0.054 Oh Pekerja 77,500.00 4,185.00 4,185.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.027 Oh Mandor 150,000.00 4,050.00 4,050.00
20,835.00 20,835.00
b. Tenaga
0.054 Oh Pekerja 77,500.00 4,185.00 4,185.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.027 Oh Mandor 150,000.00 4,050.00 4,050.00
20,835.00 20,835.00
a. Bahan
1.200 M' Pipa Galvanis 45,870.00 55,044.00 55,044.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 16,054.50 16,054.50
71,098.50 71,098.50
b. Tenaga
0.108 Oh Pekerja 77,500.00 8,370.00 8,370.00
0.180 Oh Tukang Batu 125,000.00 22,500.00 22,500.00
0.018 Oh Kepala Tukang 150,000.00 2,700.00 2,700.00
0.0054 Oh Mandor 150,000.00 810.00 810.00
34,380.00 34,380.00
b. Tenaga
0.108 Oh Pekerja 77,500.00 8,370.00 8,370.00
0.180 Oh Tukang Batu 125,000.00 22,500.00 22,500.00
0.018 Oh Kepala Tukang 150,000.00 2,700.00 2,700.00
0.0054 Oh Mandor 150,000.00 810.00 810.00
34,380.00 34,380.00
a. Bahan
1.200 M' Pipa PVC 6,850.00 8,220.00 8,220.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 2,397.50 2,397.50
10,617.50 10,617.50
b. Tenaga
0.036 Oh Pekerja 77,500.00 2,790.00 2,790.00
0.060 Oh Tukang Batu 125,000.00 7,500.00 7,500.00
0.006 Oh Kepala Tukang 150,000.00 900.00 900.00
0.0018 Oh Mandor 150,000.00 270.00 270.00
11,460.00 11,460.00
a. Bahan
1.200 M' Pipa PVC 7,900.00 9,480.00 9,480.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 2,765.00 2,765.00
12,245.00 12,245.00
b. Tenaga
0.036 Oh Pekerja 77,500.00 2,790.00 2,790.00
0.060 Oh Tukang Batu 125,000.00 7,500.00 7,500.00
0.006 Oh Kepala Tukang 150,000.00 900.00 900.00
0.0018 Oh Mandor 150,000.00 270.00 270.00
11,460.00 11,460.00
a. Bahan
1.200 M' Pipa PVC 16,900.00 20,280.00 20,280.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 5,915.00 5,915.00
26,195.00 26,195.00
b. Tenaga
0.036 Oh Pekerja 77,500.00 2,790.00 2,790.00
0.060 Oh Tukang Batu 125,000.00 7,500.00 7,500.00
0.006 Oh Kepala Tukang 150,000.00 900.00 900.00
0.0018 Oh Mandor 150,000.00 270.00 270.00
11,460.00 11,460.00
b. Tenaga
0.054 Oh Pekerja 77,500.00 4,185.00 4,185.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.0027 Oh Mandor 150,000.00 405.00 405.00
17,190.00 17,190.00
b. Tenaga
0.081 Oh Pekerja 77,500.00 6,277.50 6,277.50
0.135 Oh Tukang Batu 125,000.00 16,875.00 16,875.00
0.0135 Oh Kepala Tukang 150,000.00 2,025.00 2,025.00
0.0041 Oh Mandor 150,000.00 615.00 615.00
25,792.50 25,792.50
a. Bahan
1.000 Bh Kran Air 23,800.00 23,800.00 23,800.00
0.025 Bh Seal Tape 5,500.00 137.50 137.50
23,937.50 23,937.50
b. Tenaga
0.010 Oh Pekerja 77,500.00 775.00 775.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.005 Oh Mandor 150,000.00 750.00 750.00
15,525.00 15,525.00
Resapan
0.750 M3 Koral Beton 518,850.62 389,137.97 389,137.97
1 M3 Pasir Pasang 118,750.00 118,750.00 118,750.00
4 M' Pipa dia. 4" 59,500.00 238,000.00 238,000.00
2 Bh Buis Beton dia. 50 cm 75,000.00 150,000.00 150,000.00
10 Kg Ijuk 9,900.00 99,000.00 99,000.00
5,997,807.05 5,997,807.05
b. Tenaga
0.006 Oh Tukang Besi 125,000.00 750.00 750.00
0.060 Oh Pekerja 77,500.00 4,650.00 4,650.00
0.006 Oh Kepala Tukang 150,000.00 900.00 900.00
0.0003 Oh Mandor 150,000.00 45.00 45.00
6,345.00 6,345.00
b. Tenaga
0.650 Oh Tukang Besi Konstruksi 125,000.00 81,250.00 81,250.00
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.065 Oh Kepala Tukang 150,000.00 9,750.00 9,750.00
0.032 Oh Mandor 150,000.00 4,800.00 4,800.00
146,175.00 146,175.00
b. Tenaga
1.050 Oh Tukang Besi Konstruksi 125,000.00 131,250.00 131,250.00
1.050 Oh Pekerja 77,500.00 81,375.00 81,375.00
0.105 Oh Kepala Tukang 150,000.00 15,750.00 15,750.00
0.00525 Oh Mandor 150,000.00 787.50 787.50
229,162.50 229,162.50
a. Bahan
1.000 M2 Pintu Lipat 418,000.00 418,000.00 418,000.00
418,000.00 418,000.00
b. Tenaga
1.050 Oh Tukang Besi Konstruksi 125,000.00 131,250.00 131,250.00
1.050 Oh Pekerja 77,500.00 81,375.00 81,375.00
0.105 Oh Kepala Tukang 150,000.00 15,750.00 15,750.00
0.0052 Oh Mandor 150,000.00 780.00 780.00
229,155.00 229,155.00
b. Tenaga
0.800 Oh Tukang Besi Konstruksi 125,000.00 100,000.00 100,000.00
0.080 Oh Pekerja 77,500.00 6,200.00 6,200.00
0.080 Oh Kepala Tukang 150,000.00 12,000.00 12,000.00
0.004 Oh Mandor 150,000.00 600.00 600.00
118,800.00 118,800.00
a. Bahan
1.000 Btg Besi Holo 30/30 154,000.00 154,000.00 154,000.00
154,000.00 154,000.00
b. Tenaga
0.800 Oh Tukang Besi Konstruksi 125,000.00 100,000.00 100,000.00
0.080 Oh Pekerja 77,500.00 6,200.00 6,200.00
0.080 Oh Kepala Tukang 150,000.00 12,000.00 12,000.00
0.004 Oh Mandor 150,000.00 600.00 600.00
118,800.00 118,800.00
a. Bahan
1.000 M2 Roll Door 643,500.00 643,500.00 643,500.00
643,500.00 643,500.00
b. Tenaga
1.500 Oh Tukang Besi Konstruksi 125,000.00 187,500.00 187,500.00
1.050 Oh Pekerja 77,500.00 81,375.00 81,375.00
0.105 Oh Kepala Tukang 150,000.00 15,750.00 15,750.00
0.0052 Oh Mandor 150,000.00 780.00 780.00
285,405.00 285,405.00
b. Tenaga
1.050 Oh Tukang Besi Konstruksi 125,000.00 131,250.00 131,250.00
1.050 Oh Pekerja 77,500.00 81,375.00 81,375.00
0.105 Oh Kepala Tukang 150,000.00 15,750.00 15,750.00
0.0052 Oh Mandor 150,000.00 780.00 780.00
229,155.00 229,155.00
b. Tenaga
0.350 Oh Tukang Kayu 125,000.00 43,750.00 43,750.00
0.350 Oh Pekerja 77,500.00 27,125.00 27,125.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.00175 Oh Mandor 150,000.00 262.50 262.50
76,387.50 76,387.50
b. Tenaga
0.350 Oh Tukang Kayu 125,000.00 43,750.00 43,750.00
0.350 Oh Pekerja 77,500.00 27,125.00 27,125.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.00175 Oh Mandor 150,000.00 262.50 262.50
76,387.50 76,387.50
b. Tenaga
1.200 Oh Tukang Las 125,000.00 150,000.00 150,000.00
1.200 Oh Pekerja 77,500.00 93,000.00 93,000.00
0.012 Oh Kepala Tukang 150,000.00 1,800.00 1,800.00
0.00060 Oh Mandor 150,000.00 90.00 90.00
244,890.00 244,890.00
a. Bahan
1.100 M2 Kawat Harmonika 42,900.00 47,190.00 47,190.00
0.020 Kg Paku Biasa /2" - 1"
1
32,500.00 650.00 650.00
0.0018 M3 Kayu Kls.III, Papan 3,630,000.00 6,534.00 6,534.00
54,374.00 54,374.00
b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0005 Oh Mandor 150,000.00 75.00 75.00
21,825.00 21,825.00
a. Bahan
1.100 M2 Kawat Nyamuk 19,800.00 21,780.00 21,780.00
0.020 Kg Paku Biasa /2" - 1"
1
32,500.00 650.00 650.00
0.0018 M3 Kayu Kls.III, Papan 3,630,000.00 6,534.00 6,534.00
28,964.00 28,964.00
b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0005 Oh Mandor 150,000.00 75.00 75.00
21,825.00 21,825.00
b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0005 Oh Mandor 150,000.00 75.00 75.00
21,825.00 21,825.00
a. Bahan
1.100 M2 Kawat Burung 22,000.00 24,200.00 24,200.00
0.020 Kg Paku Biasa /2" - 1"
1
32,500.00 650.00 650.00
0.0018 M3 Kayu Kls.III, Papan 3,630,000.00 6,534.00 6,534.00
31,384.00 31,384.00
b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0005 Oh Mandor 150,000.00 75.00 75.00
21,825.00 21,825.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.400 Oh Tukang Kayu 125,000.00 50,000.00 50,000.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.00125 Oh Mandor 150,000.00 187.50 187.50
65,562.50 65,562.50
b. Tenaga
0.040 Oh Pekerja 77,500.00 3,100.00 3,100.00
0.400 Oh Tukang Kayu 125,000.00 50,000.00 50,000.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.00125 Oh Mandor 150,000.00 187.50 187.50
57,037.50 57,037.50
a. Bahan
0.300 Lbr Seng Plat 3' x 6' bjls 116,600.00 34,980.00 34,980.00
0.100 Kg Paku Biasa /2" - 1"
1
32,500.00 3,250.00 3,250.00
0.019 M3 Kayu Kls.III, Papan 3,630,000.00 68,970.00 68,970.00
0.500 Kg Besi Strip 11,000.00 5,500.00 5,500.00
112,700.00 112,700.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.250 Oh Tukang Kayu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.00125 Oh Mandor 150,000.00 187.50 187.50
46,812.50 46,812.50
b. Tenaga
0.060 Oh Pekerja 77,500.00 4,650.00 4,650.00
0.600 Oh Tukang Kayu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.003 Oh Mandor 150,000.00 450.00 450.00
89,100.00 89,100.00
b. Tenaga
0.005 Oh Pekerja 77,500.00 387.50 387.50
0.500 Oh Tukang Kayu 125,000.00 62,500.00 62,500.00
0.005 Oh Kepala Tukang 150,000.00 750.00 750.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
64,012.50 64,012.50
b. Tenaga
0.015 Oh Pekerja 77,500.00 1,162.50 1,162.50
0.150 Oh Tukang Kayu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.00075 Oh Mandor 150,000.00 112.50 112.50
22,275.00 22,275.00
b. Tenaga
0.050 Oh Pekerja 77,500.00 3,875.00 3,875.00
0.500 Oh Tukang Kayu 125,000.00 62,500.00 62,500.00
0.050 Oh Kepala Tukang 150,000.00 7,500.00 7,500.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
74,250.00 74,250.00
b. Tenaga
0.015 Oh Pekerja 77,500.00 1,162.50 1,162.50
0.150 Oh Tukang Kayu/kaca 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.00075 Oh Mandor 150,000.00 112.50 112.50
22,275.00 22,275.00
a. Bahan
1.100 M2 Kaca Polos 220,000.00 242,000.00 242,000.00
242,000.00 242,000.00
b. Tenaga
0.0165 Oh Pekerja 77,500.00 1,278.75 1,278.75
0.165 Oh Tukang Kayu/kaca 125,000.00 20,625.00 20,625.00
0.0165 Oh Kepala Tukang 150,000.00 2,475.00 2,475.00
0.0008 Oh Mandor 150,000.00 120.00 120.00
24,498.75 24,498.75
b. Tenaga
0.025 Oh Pekerja 77,500.00 1,937.50 1,937.50
0.250 Oh Tukang Kayu/kaca 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.00125 Oh Mandor 150,000.00 187.50 187.50
37,125.00 37,125.00
a. Bahan
1.100 M2 Kaca Cermin Tebal 3 mm 136,400.00 150,040.00 150,040.00
150,040.00 150,040.00
b. Tenaga
0.015 Oh Pekerja 77,500.00 1,162.50 1,162.50
0.150 Oh Tukang Kayu/kaca 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.00075 Oh Mandor 150,000.00 112.50 112.50
22,275.00 22,275.00
a. Bahan
1.100 M2 Kaca Cermin Tebal 5 mm 212,300.00 233,530.00 233,530.00
233,530.00 233,530.00
b. Tenaga
0.015 Oh Pekerja 77,500.00 1,162.50 1,162.50
0.150 Oh Tukang Kayu/kaca 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.00075 Oh Mandor 150,000.00 112.50 112.50
22,275.00 22,275.00
b. Tenaga
0.015 Oh Pekerja 77,500.00 1,162.50 1,162.50
0.150 Oh Tukang Kayu/kaca 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.00075 Oh Mandor 150,000.00 112.50 112.50
22,275.00 22,275.00
b. Tenaga
0.015 Oh Pekerja 77,500.00 1,162.50 1,162.50
0.150 Oh Tukang Kayu/kaca 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.00075 Oh Mandor 150,000.00 112.50 112.50
22,275.00 22,275.00
a. Bahan
11.870 Bh Ubin Granito 30 x 30 cm 22,550.00 267,668.50 267,668.50
10.000 Kg Semen Portland 1,700.00 17,000.00 17,000.00
0.0215 M3 Pasir Pasang 118,750.00 2,553.13 2,553.13
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
313,471.63 313,471.63
b. Tenaga
0.260 Oh Pekerja 77,500.00 20,150.00 20,150.00
0.125 Oh Tukang Batu 125,000.00 15,625.00 15,625.00
0.0125 Oh Kepala Tukang 150,000.00 1,875.00 1,875.00
0.013 Oh Mandor 150,000.00 1,950.00 1,950.00
39,600.00 39,600.00
a. Bahan
3.000 Bh Ubin Teralux Marmer 60 x 60 cm 94,400.00 283,200.00 283,200.00
8.190 Kg Semen Portland 1,700.00 13,923.00 13,923.00
0.045 M3 Pasir Pasang 118,750.00 5,343.75 5,343.75
1.000 Kg Semen Warna 17,500.00 17,500.00 17,500.00
319,966.75 319,966.75
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.120 Oh Tukang Batu 125,000.00 15,000.00 15,000.00
0.0120 Oh Kepala Tukang 150,000.00 1,800.00 1,800.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
38,050.00 38,050.00
a. Bahan
6.250 Bh Ubin Teralux Marmer 40 x 40 cm 52,800.00 330,000.00 330,000.00
8.800 Kg Semen Portland 1,700.00 14,960.00 14,960.00
0.0215 M3 Pasir Pasang 118,750.00 2,553.13 2,553.13
1.300 Kg Semen Warna 17,500.00 22,750.00 22,750.00
370,263.13 370,263.13
b. Tenaga
0.672 Oh Pekerja 77,500.00 52,080.00 52,080.00
0.224 Oh Tukang Batu 125,000.00 28,000.00 28,000.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.022 Oh Kepala Tukang 150,000.00 3,300.00 3,300.00
0.034 Oh Mandor 150,000.00 5,100.00 5,100.00
88,480.00 88,480.00
b. Tenaga
0.700 Oh Pekerja 77,500.00 54,250.00 54,250.00
0.340 Oh Tukang Batu 125,000.00 42,500.00 42,500.00
0.034 Oh Kepala Tukang 150,000.00 5,100.00 5,100.00
0.035 Oh Mandor 150,000.00 5,250.00 5,250.00
107,100.00 107,100.00
b. Tenaga
0.080 Oh Pekerja 77,500.00 6,200.00 6,200.00
0.040 Oh Tukang Batu 125,000.00 5,000.00 5,000.00
0.004 Oh Kepala Tukang 150,000.00 600.00 600.00
0.004 Oh Mandor 150,000.00 600.00 600.00
12,400.00 12,400.00
b. Tenaga
0.800 Oh Pekerja 77,500.00 62,000.00 62,000.00
0.040 Oh Tukang Batu 125,000.00 5,000.00 5,000.00
0.004 Oh Kepala Tukang 150,000.00 600.00 600.00
0.004 Oh Mandor 150,000.00 600.00 600.00
68,200.00 68,200.00
b. Tenaga
0.060 Oh Pekerja 77,500.00 4,650.00 4,650.00
0.030 Oh Tukang Batu 125,000.00 3,750.00 3,750.00
0.003 Oh Kepala Tukang 150,000.00 450.00 450.00
0.003 Oh Mandor 150,000.00 450.00 450.00
9,300.00 9,300.00
a. Bahan
3.330 Bh Plint Ubin Granito 10 x 30 cm 7,516.67 25,030.50 25,030.50
1.650 Kg Semen Portland 1,700.00 2,805.00 2,805.00
0.0032 M3 Pasir Pasang 118,750.00 380.00 380.00
0.100 Kg Semen Warna 17,500.00 1,750.00 1,750.00
29,965.50 29,965.50
b. Tenaga
0.900 Oh Pekerja 77,500.00 69,750.00 69,750.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.0045 Oh Mandor 150,000.00 675.00 675.00
83,025.00 83,025.00
b. Tenaga
0.900 Oh Pekerja 77,500.00 69,750.00 69,750.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.0045 Oh Mandor 150,000.00 675.00 675.00
83,025.00 83,025.00
b. Tenaga
0.900 Oh Pekerja 77,500.00 69,750.00 69,750.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.0045 Oh Mandor 150,000.00 675.00 675.00
83,025.00 83,025.00
b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00
a. Bahan
50 Bh Ubin Keramik Artistik 10 x 10 cm 6,100.00 305,000.00 305,000.00
11.380 Kg Semen Portland 1,700.00 19,346.00 19,346.00
0.042 M3 Pasir Pasang 118,750.00 4,987.50 4,987.50
2.000 Kg Semen Warna 17,500.00 35,000.00 35,000.00
364,333.50 364,333.50
b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00
a. Bahan
100 Bh Ubin Keramik Artistik 5 x 20 cm 6,100.00 610,000.00 610,000.00
11.380 Kg Semen Portland 1,700.00 19,346.00 19,346.00
0.042 M3 Pasir Pasang 118,750.00 4,987.50 4,987.50
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
660,583.50 660,583.50
b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00
a. Bahan
5 Bh Plint Keramik Artistik 10 x 20 cm 6,100.00 30,500.00 30,500.00
1.650 Kg Semen Portland 1,700.00 2,805.00 2,805.00
0.0032 M3 Pasir Pasang 118,750.00 380.00 380.00
0.100 Kg Semen Warna 17,500.00 1,750.00 1,750.00
35,435.00 35,435.00
b. Tenaga
0.090 Oh Pekerja 77,500.00 6,975.00 6,975.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.0045 Oh Mandor 150,000.00 675.00 675.00
20,250.00 20,250.00
a. Bahan
5 Bh Plint Keramik Artistik 10 x 10 cm 6,100.00 30,500.00 30,500.00
1.650 Kg Semen Portland 1,700.00 2,805.00 2,805.00
0.0032 M3 Pasir Pasang 118,750.00 380.00 380.00
0.120 Kg Semen Warna 17,500.00 2,100.00 2,100.00
35,785.00 35,785.00
b. Tenaga
0.090 Oh Pekerja 77,500.00 6,975.00 6,975.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.0045 Oh Mandor 150,000.00 675.00 675.00
20,250.00 20,250.00
b. Tenaga
0.090 Oh Pekerja 77,500.00 6,975.00 6,975.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.0045 Oh Mandor 150,000.00 675.00 675.00
20,250.00 20,250.00
b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00
b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00
b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00
a. Bahan
11.11 Bh Ubin Keramik Warna 30 x 30 cm 5,981.82 66,458.00 66,458.00
11.380 Kg Semen Portland 1,700.00 19,346.00 19,346.00
0.042 M3 Pasir Pasang 118,750.00 4,987.50 4,987.50
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
117,041.50 117,041.50
b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00
a. Bahan
11.11 Bh Ubin Keramik Putih 30 x 30 cm 5,590.91 62,115.00 62,115.00
11.380 Kg Semen Portland 1,700.00 19,346.00 19,346.00
0.042 M3 Pasir Pasang 118,750.00 4,987.50 4,987.50
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
112,698.50 112,698.50
b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00
b. Tenaga
0.090 Oh Pekerja 77,500.00 6,975.00 6,975.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.0045 Oh Mandor 150,000.00 675.00 675.00
20,250.00 20,250.00
a. Bahan
1.050 M2 Carpet 6 mm 82,500.00 86,625.00 86,625.00
0.350 Kg Lem Vinyl 9,350.00 3,272.50 3,272.50
89,897.50 89,897.50
b. Tenaga
0.170 Oh Pekerja 77,500.00 13,175.00 13,175.00
0.170 Oh Tukang Batu 125,000.00 21,250.00 21,250.00
0.017 Oh Kepala Tukang 150,000.00 2,550.00 2,550.00
0.0085 Oh Mandor 150,000.00 1,275.00 1,275.00
38,250.00 38,250.00
Jumlah 89,897.50 38,250.00 128,147.50
b. Tenaga
0.170 Oh Pekerja 77,500.00 13,175.00 13,175.00
0.170 Oh Tukang Batu 125,000.00 21,250.00 21,250.00
0.017 Oh Kepala Tukang 150,000.00 2,550.00 2,550.00
0.0085 Oh Mandor 150,000.00 1,275.00 1,275.00
38,250.00 38,250.00
Jumlah 317,432.50 38,250.00 355,682.50
b. Tenaga
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.0325 Oh Mandor 150,000.00 4,875.00 4,875.00
104,250.00 104,250.00
b. Tenaga
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.500 Oh Tukang Batu 125,000.00 62,500.00 62,500.00
0.050 Oh Kepala Tukang 150,000.00 7,500.00 7,500.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
122,550.00 122,550.00
Jumlah 99,222.50 122,550.00 221,772.50
b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.500 Oh Tukang Batu 125,000.00 62,500.00 62,500.00
0.050 Oh Kepala Tukang 150,000.00 7,500.00 7,500.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
122,550.00 122,550.00
b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00
a. Bahan
1.050 M2 Batu Candi hitam 247,500.00 259,875.00 259,875.00
0.100 Kg Anti Lumut/Vernis batu 71,500.00 7,150.00 7,150.00
11.750 Kg Semen Abu-abu 1,700.00 19,975.00 19,975.00
0.035 M3 Pasir Pasang 118,750.00 4,156.25 4,156.25
291,156.25 291,156.25
b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00
a. Bahan
1.020 M2 Batu alam/Palimanan 184,800.00 188,496.00 188,496.00
0.100 Kg Anti Lumut/Vernis batu 71,500.00 7,150.00 7,150.00
12.440 Kg Semen Abu-abu 1,700.00 21,148.00 21,148.00
0.025 M3 Pasir Pasang 118,750.00 2,968.75 2,968.75
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
246,012.75 246,012.75
b. Tenaga
0.720 Oh Pekerja 77,500.00 55,800.00 55,800.00
0.650 Oh Tukang Batu 125,000.00 81,250.00 81,250.00
0.065 Oh Kepala Tukang 150,000.00 9,750.00 9,750.00
0.035 Oh Mandor 150,000.00 5,250.00 5,250.00
152,050.00 152,050.00
b. Tenaga
0.120 Oh Pekerja 77,500.00 9,300.00 9,300.00
0.120 Oh Tukang Batu 125,000.00 15,000.00 15,000.00
0.012 Oh Kepala Tukang 150,000.00 1,800.00 1,800.00
0.006 Oh Mandor 150,000.00 900.00 900.00
27,000.00 27,000.00
b. Tenaga
0.3500 Oh Pekerja 77,500.00 27,125.00 27,125.00
0.0175 Oh Mandor 150,000.00 2,625.00 2,625.00
29,750.00 29,750.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
Oh Tukang Cat 125,000.00 0.00 0.00
Oh Kepala Tukang 150,000.00 0.00 0.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
12,000.00 12,000.00
a. Bahan
0.050 Kg Sabun 12,320.00 616.00 616.00
616.00 616.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
Oh Tukang Cat 125,000.00 0.00 0.00
Oh Kepala Tukang 150,000.00 0.00 0.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
12,000.00 12,000.00
14.3 1 m Mengerok karat cat lama permukaan baja dengan cara manual
2
a. Bahan
0.050 Kg Sabun 12,320.00 616.00 616.00
616.00 616.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
Oh Tukang Cat 125,000.00 0.00 0.00
Oh Kepala Tukang 150,000.00 0.00 0.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
12,000.00 12,000.00
a. Bahan
0.050 Kg Sabun 12,320.00 616.00 616.00
616.00 616.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
Oh Tukang Cat 125,000.00 0.00 0.00
Oh Kepala Tukang 150,000.00 0.00 0.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
12,000.00 12,000.00
a. Bahan
0.080 Kg Dempul Jadi 22,000.00 1,760.00 1,760.00
0.020 Kg Minyak Cat 6,600.00 132.00 132.00
0.010 Kg Batu Apung 2,000.00 20.00 20.00
1,912.00 1,912.00
b. Tenaga
0.040 Oh Pekerja 77,500.00 3,100.00 3,100.00
0.040 Oh Tukang Cat 125,000.00 5,000.00 5,000.00
0.004 Oh Kepala Tukang 150,000.00 600.00 600.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
9,075.00 9,075.00
b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.105 Oh Tukang Cat 125,000.00 13,125.00 13,125.00
0.004 Oh Kepala Tukang 150,000.00 600.00 600.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
19,525.00 19,525.00
a. Bahan
0.350 Ltr Residu atau Ter 49,500.00 17,325.00 17,325.00
17,325.00 17,325.00
b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
Oh Tukang Cat 125,000.00 0.00 0.00
Oh Kepala Tukang 150,000.00 0.00 0.00
0.006 Oh Mandor 150,000.00 900.00 900.00
8,650.00 8,650.00
a. Bahan
0.150 Ltr Vernis 27,500.00 4,125.00 4,125.00
0.050 Kg Dempul 22,000.00 1,100.00 1,100.00
0.100 Lbr Ampelas 3,850.00 385.00 385.00
0.010 Bh Kuas 13,750.00 137.50 137.50
5,747.50 5,747.50
b. Tenaga
0.160 Oh Pekerja 77,500.00 12,400.00 12,400.00
0.160 Oh Tukang Cat 125,000.00 20,000.00 20,000.00
0.016 Oh Kepala Tukang 150,000.00 2,400.00 2,400.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
35,175.00 35,175.00
Penutup )
a. Bahan
0.120 Kg Cat Dasar 48,500.00 5,820.00 5,820.00
0.180 Kg Cat Penutup 2 Kali, mutu C 13,750.00 2,475.00 2,475.00
0.180 Kg Cat Penutup 2 Kali, mutu B 28,600.00 5,148.00 5,148.00
0.180 Kg Cat Penutup 2 Kali, Mutu B, anti lumut/jamur 30,250.00 5,445.00 5,445.00
Cat Mutu C 8,295.00 8,295.00
Cat Mutu B 11,265.00 11,265.00
Cat Mutu B, anti lumut/jamur 10,770.00 10,770.00
b. Tenaga
0.028 Oh Pekerja 77,500.00 2,170.00 2,170.00
0.042 Oh Tukang Cat 125,000.00 5,250.00 5,250.00
0.0042 Oh Kepala Tukang 150,000.00 630.00 630.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
8,425.00 8,425.00
a. Bahan
0.100 Kg Meni Besi 46,200.00 4,620.00 4,620.00
0.010 Bh Kuas 13,750.00 137.50 137.50
4,757.50 4,757.50
b. Tenaga
0.020 Oh Pekerja 77,500.00 1,550.00 1,550.00
0.200 Oh Tukang Cat 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
31,050.00 31,050.00
a. Bahan
0.100 Kg Meni Besi 46,200.00 4,620.00 4,620.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.010 Bh Kuas 13,750.00 137.50 137.50
0.002 M3 Perancah Kayu/Gelam dia. 8 319,000.00 638.00 638.00
5,395.50 5,395.50
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.225 Oh Tukang Cat 125,000.00 28,125.00 28,125.00
0.0225 Oh Kepala Tukang 150,000.00 3,375.00 3,375.00
0.0075 Oh Mandor 150,000.00 1,125.00 1,125.00
52,000.00 52,000.00
a. Bahan
7.560 Kg Cat Kilat 44,000.00 332,640.00 332,640.00
5.320 Ltr Thinner 13,200.00 70,224.00 70,224.00
5 Kg Ross Polac 30,800.00 154,000.00 154,000.00
4 Kg Isamu 52,800.00 211,200.00 211,200.00
4 Kg Epoxi 55,000.00 220,000.00 220,000.00
4 Lbr Amplas Niken 7,150.00 28,600.00 28,600.00
1 Ls Alat Bantu / Compressor 5,500.00 5,500.00 5,500.00
1,022,164.00 1,022,164.00
b. Tenaga
8.000 Oh Tukang Cat 125,000.00 1,000,000.00 1,000,000.00
0.800 Oh Kepala Tukang 150,000.00 120,000.00 120,000.00
4.000 Oh Pekerja 77,500.00 310,000.00 310,000.00
0.200 Oh Mandor 150,000.00 30,000.00 30,000.00
1,460,000.00 1,460,000.00
a. Bahan
0.466 Kg Cat Tembok mutu B, anti lumut/jamur 30,250.00 14,096.50 14,096.50
0.100 Kg Epoxi 55,000.00 5,500.00 5,500.00
0.233 Kg Mill 36,300.00 8,457.90 8,457.90
1.000 Ls Alat Bantu / Compressor 550.00 550.00 550.00
28,604.40 28,604.40
b. Tenaga
0.524 Oh Tukang Cat 125,000.00 65,440.00 65,440.00
0.080 Oh Kepala Tukang 150,000.00 12,000.00 12,000.00
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.020 Oh Mandor 150,000.00 3,000.00 3,000.00
111,440.00 111,440.00
Jumlah 28,604.40 111,440.00 140,044.40
a. Bahan
1.500 Kg Wood Filler ( dempul) 35,200.00 52,800.00 52,800.00
1.500 Kg Wood Stain ( pewarna) 66,000.00 99,000.00 99,000.00
1.500 Kg Sanding Sealer ( Cat dasar ) 41,800.00 62,700.00 62,700.00
2.400 Kg Melamic Clear 66,000.00 158,400.00 158,400.00
2 Ltr Thinner 43,500.00 87,000.00 87,000.00
6 Lbr Amplas Niken 7,150.00 42,900.00 42,900.00
1 Ls Alat Bantu / Compressor 5,500.00 5,500.00 5,500.00
508,300.00 508,300.00
b. Tenaga
12 Oh Tukang Cat 125,000.00 1,500,000.00 1,500,000.00
1.200 Oh Kepala Tukang 150,000.00 180,000.00 180,000.00
2.000 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.100 Oh Mandor 150,000.00 15,000.00 15,000.00
1,850,000.00 1,850,000.00
b. Upah
1.000 ls Tukang Instalasi listrik 93,500.00 93,500.00 93,500.00
93,500.00 93,500.00
b. Upah
1.000 ls Tukang Instalasi listrik 93,500.00 93,500.00 93,500.00
93,500.00 93,500.00
b. Upah
1.000 ls Tukang Instalasi listrik 93,500.00 93,500.00 93,500.00
93,500.00 93,500.00
b. Upah
1.000 ls Tukang Instalasi listrik 93,500.00 93,500.00 93,500.00
93,500.00 93,500.00
SOFIAN HASAN
Direktur
DAFTAR HARGA SATUAN UPAH, BAHAN BANGUNAN DAN PERALATAN
TAHUN 2014 SEMESTER I
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
A UPAH
1 Kepala Tukang Oh 150,000.00
###
2 Tukang Oh 125,000.00
###
3 Mandor Oh 150,000.00
###
4 Pekerja Tidak Terlatih Oh 77,500.00
###
4 Pekerja Terlatih Oh 90,000.00
###
5 Masinis Oh 90,000.00
###
5 Operator Oh 165,000.00
###
6 Sopir Oh 110,000.00
###
7 Pembantu Masinis / Operator Oh 82,500.00
###
8 Supervisor Oh 82,500.00
###
9 Pemasak Aspal Oh 49,500.00
###
8 Penjaga Oh 44,000.00
###
9 Pembantu sopir Oh 82,500.00
###
10 Mekanik Oh 148,500.00
###
11 Surveyor Oh 82,500.00
###
B BAHAN/MATERIAL
1 Agregat halus m3 518,850.62
###
2 Agregat Kasar m3 518,850.62
###
3 Agregat kelas A m3 459,250.00
###
4 Agregat kelas B m3 399,300.00
###
5 Agregat kelas C m3 477,400.00
###
6 Aluminium Foil m2 20,350.00
###
7 Alcubond m2 715,000.00
###
8 Amplas Biasa Lbr 3,850.00
###
9 Amplas Niken Lbr 7,150.00
###
10 Atap Aluminium Zink Coated (seng) tebal 0,25 mm Lbr 47,300.00
###
11 Atap Aluminium Zink Coated (seng) tebal 0,3 mm Lbr 66,000.00
###
12 Atap Aluminium Zink Coated (seng) tebal 0,4 mm Lbr 91,300.00
###
13 Atap Aluminium Zincalume, tebal 0,25 mm Lbr 68,200.00
###
14 Atap Aluminium Zincalume, tebal 0,3 mm Lbr 68,750.00
###
15 Atap Aluminium Zincalume, tebal 0,4 mm Lbr 83,600.00
###
16 Atap Aluminium Gelombang tebal 0,5 mm Lbr 110,000.00
###
17 Atap Fiber warna"Polycarbonat" tbl. 4-5 mm m2 88,000.00
###
18 Atap Genteng Beton Lokal buah 4,620.00
###
19 Atap Genteng Beton buah 6,270.00
###
20 Atap Genteng Beton Cisangkan buah 8,250.00
###
21 Atap Genteng Buleleng buah 2,530.00
###
22 Atap Genteng Keramik biasa berglazur buah 8,800.00
###
23 Atap Genteng Keramik Berglazur Natural buah 13,200.00
###
24 Atap Genteng Keramik sejenis Berglazur warna buah 18,700.00
###
25 Atap Genteng Metal Biasa (88 cm X 77 cm) m2 40,700.00
###
26 Atap Genteng Metal Warna (120 cm X 76 cm) m2 44,000.00
###
27 Atap Genteng Metal Zincalume 2x4 (38,5 cm X 80cm) m2 176,000.00
###
28 Atap Genteng Metal Zincalume berpasir (77cmX100cm) m2 93,500.00
###
29 Atap Genteng Metal Zincalume berpasir biasa m2 66,000.00
###
30 Atap Genteng Kodok buah 1,100.00
###
31 Atap Onduline m2 74,800.00
###
32 Asbes polos 100 x 100 tbl = 4 mm Lbr 26,400.00
###
33 Asbes Gelombang Kecil, lebar 80 cm m2 27,500.00
###
34 Asbes Gelombang Kecil, lebar 105 cm m2 35,200.00
###
35 Asbes Gelombang Besar, lebar 105 cm m2 38,500.00
###
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
36 Asbes Gelombang motif genteng m2 36,850.00
###
37 Aspal Curah kg 13,200.00
###
38 Aspal Drum kg 13,200.00
###
39 Aquaproof kg 346,000.00
###
40 Bak Cuci Stainless Steel buah 212,300.00
###
41 Bak Cuci Teraso buah 357,500.00
###
42 Bak Fibreglass buah 198,000.00
###
43 Bak Teraso buah 198,000.00
###
44 Bambu dia. 6-8 cm/6m Btg 55,000.00
###
45 Batako buah 2,860.00
###
46 Batu Andesit hitam kecoklatan m2 209,000.00
###
47 Batu alam kecoklatan (Sangarong) m2 203,500.00
###
48 Batu Bata lobang m3 638,500.00
###
1 Aspal Bitumen kg 10,353.40
49 Batu Bata Kecil buah 1,375.00
###
2 Batu Bata Lobang buah 850.00
###
3 Batu Candi hitam m2 247,500.00
###
4 Batu Kali m3 385,000.00
###
5 Batu Kali tempel m2 102,300.00
###
6 Batu Karang Pilang m2 653,400.00
###
7 Batu Kerikil m3 440,000.00
###
3 Batu Koral beton m3 518,850.62
###
4 Batu Koral Jagung m3 363,000.00
###
5 Batu Krokos m3 431,200.00
###
6 Batu Palimanan kuning/hijau m2 184,800.00
###
7 Batu Palimanan kuning/hijau + bevel m2 184,800.00
###
8 Batu Pecah 0.5 - 1 (screen) m3 495,000.00
###
9 Batu Abu 0.00 - 0.5 (filler) m3 500,500.00
###
10 Batu Pecah 1.3 - 1.9 (spilt) m3 518,850.62
###
63 Batu Pecah 1 cm - 2 cm m3 357,500.00
###
11 Batu Pecah 2/3 m3 518,850.62
###
12 Batu Pecah 3/5 m3 508,750.00
###
13 Batu Pecah 5/7 m3 385,000.00
###
14 Batu Marmer m2 330,000.00
###
15 Batu Roster / Terawang biasa buah 4,675.00
###
16 Besi dia. 5 mm Batang 24,200.00
###
17 Besi dia. 6 mm KS Batang 27,500.00
###
18 Besi dia. 8 mm KS TI Batang 56,100.00
###
19 Besi dia. 10 mm KS TI Batang 88,000.00
###
20 Besi dia. 12 mm KS TI Batang 121,000.00
###
21 Besi dia. 14 mm KS TI Batang 203,500.00
###
22 Besi dia. 16 mm KS TI Batang 195,000.00
###
23 Besi dia. 19 mm KS TI Batang 302,500.00
###
4 Besi Beton Polos kg 12,075.00
###
5 Besi Baja Profil WF, I dan H kg 11,542.65
###
6 Besi Baja Konstruksi ( CNP, INP,dan besi L) kg 16,500.00
###
7 Besi Beam Clamp dan Plat Siku m2 24,750.00
###
8 Besi Hollow baja 20 X 40, tb. 2mm Batang 154,000.00
###
9 Besi Hollow baja 40 X 40, tb. 2mm Batang 176,000.00
###
10 Besi Hollow baja 30 X 60, tb. 2mm Batang 209,000.00
###
11 Besi Hollow Plafond 2 X 4 Batang 27,500.00
###
12 Besi Strip kg 11,000.00
###
13 Besi Strip 2 X 3 M' 5,500.00
###
14 Beton Ready Mix K - 125 m3 880,000.00
###
15 Beton Ready Mix K - 175 m3 935,000.00
###
2 Beton Ready Mix K - 225 m3 990,000.00
###
3 Beton Ready Mix K - 250 m3 1,045,000.00
###
4 Beton Ready Mix K - 275 m3 1,100,000.00
###
5 Beton Ready Mix K - 300 m3 1,155,000.00
###
6 Beton Ready Mix K - 350 m3 1,100,000.00
###
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
7 Beton Ready Mix K - 400 m4 1,265,000.00
###
8 Bubungan Asbes Gelombang Besar m' 26,400.00
###
9 Bubungan Asbes Gelombang Kecil m' 25,850.00
###
10 Bubungan/Nok Genteng Beton Buah 6,600.00
###
11 Bubungan Genteng Buleleng Buah 5,720.00
###
12 Bubungan/ Nok genteng Keramik biasa berglazur Buah 11,000.00
###
13 Bubungan/Nok genteng Keramik sejenis berglazur Buah 22,000.00
###
14 Bubungan gtg Keramik sejenis warna berglazur Buah 27,500.00
###
15 Bubungan/Nok Genteng Metal/aluminium M' 33,000.00
###
16 Bubungan Genteng Kodok Buah 4,400.00
###
17 Cat Dasar kg 48,500.00
###
18 Cat Antara kg 27,500.00
###
19 Cat Kayu dan Besi Anti Rayap kg 49,500.00
###
20 Cat Khusus Glossy dan Quick Drying kg 33,000.00
###
3 Cat Minyak warna (biasa) mutu C kg 44,000.00
###
4 Cat Minyak mutu B kg 68,700.00
###
5 Cat Minyak Semprot kg 46,200.00
###
6 Cat Meni Besi kg 40,700.00
###
7 Cat Meni Besi /kayu/ Flincote kg 46,200.00
###
8 Cat Penutup kg 90,200.00
###
9 Cat Tembok mutu C (Vinotex,Q-Luc, dan sejenis) kg 13,750.00
###
10 Cat Tembok mutu B (Catylax,vinilex, dan sejenis) kg 28,600.00
###
11 Cat Tembok mutu B, Anti Lumut dan Jamur kg 30,250.00
###
12 Cat Tembok mutu A (Mowilex,Kemtone,Dulux,dll) kg 104,500.00
###
13 Closed Duduk Setara (sejenis standar KIA) unit 605,000.00
###
14 Closed Duduk Standar (sejenis Ex.TOTOC721FV1) unit 2,892,000.00
###
15 Closed Duduk Halmar unit 3,520,000.00
###
16 Closed Duduk mutu C unit 2,062,500.00
###
17 Closed Duduk mutu A unit 4,840,000.00
###
18 Closed Duduk mutu B unit 2,992,000.00
###
19 Closed Duduk standar unit 2,530,000.00
###
20 Closet Duduk / Monoblok bh 594,000.00
###
21 Closet Jongkok Porselen / biasa buah 176,000.00
###
6 Minyak solar untuk industri / Minyak aspal liter 6,050.00
22 Closet Jongkok Teraso buah 35,200.00
###
23 Closed Jongkok Standart / sejenis (mutu B) unit 198,000.00
###
24 Closed Jongkok sejenis ( mutu A) Unit 297,000.00
###
25 Shower Spray TX 403 SV 3 buah 357,500.00
###
26 Coneblock biasa tebal 6 cm buah 1,980.00
###
27 Coneblock warna tebal 6 cm buah 2,640.00
###
28 Coneblock biasa tebal 8 cm buah 2,695.00
###
29 Coneblock warna tebal 8 cm buah 3,300.00
###
30 Cornice (bubuk Semen putih utk gypsum) kg 7,700.00
###
31 Dempul Jadi kg 22,000.00
###
32 Dempul Ross Polac kg 30,800.00
###
33 Dempul Isamu kg 52,800.00
###
34 Dolken Kayu dia. 8 - 10/400 cm m3 319,000.00
###
35 Door Closer buah 264,000.00
###
36 Door Holder buah 33,000.00
###
37 Door Stoper buah 33,000.00
###
38 Door Stop buah 24,200.00
###
39 Ember hitam buah 7,150.00
###
40 Engsel Biasa buah 19,800.00
###
41 Engsel Kuningan 4" buah 33,000.00
###
42 Engsel Pintu buah 19,800.00
###
43 Epoxi kg 55,000.00
###
44 Eternit 100 x 100 tebal 2,7 mm Lbr 25,300.00
###
45 Eternit 100 x 100 tebal 3,5 mm Lbr 29,700.00
###
46 Filler m3 1,375.00
###
47 Fitting plafond listrik buah 9,900.00
###
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
48 Glass Block buah 26,400.00
###
49 Grendel/Slot Tanam 4" buah 82,500.00
###
50 Grendel biasa buah 17,600.00
###
51 Gypsum Board ( 120 x 240 x 9 ) mm lbr 82,900.00
###
52 Hordeng Horizontal Blind (aluminium) m2 101,200.00
###
53 Hordeng Vertikal Blind m3 104,500.00
###
54 Ijuk Kg 9,900.00
###
55 Jendela Aluminium + Kaca Reyband 5 mm m2 902,000.00
###
56 Jendela Besi m2 330,000.00
###
57 Jendela Bingkai Nako 100 cm X 70 cm Unit 99,000.00
###
58 Jendela Bingkai Nako m2 148,500.00
###
59 Kabel NYA 1,5 mm m' 4,290.00
###
60 Kabel NYA 2,5 mm m' 5,720.00
###
61 Kabel NYA 4.0 mm m' 6,600.00
###
62 Kabel NYM 2 X 1,5 mm m' 11,000.00
###
63 Kabel NYM 2 X 2,5 mm m' 14,300.00
###
64 Kabel NYM 2 X 4,0 mm m' 19,800.00
###
65 Kaca Cermin 3 mm m2 136,400.00
###
66 Kaca Cermin 5 mm m2 212,300.00
###
67 Kaca Patri m2 1,760,000.00
###
68 Kaca Bening 3 mm m2 71,500.00
###
69 Kaca Bening 4 mm m2 82,500.00
###
70 Kaca Bening 5 mm m2 121,000.00
###
71 Kaca Bening 8 mm m2 220,000.00
###
72 Kaca Bening 10 mm m2 260,700.00
###
73 Kaca Buram 12 mm m2 429,000.00
###
74 Kaca Rayband 5 mm m2 110,000.00
###
75 Kaca Buram/Es 5 mm m2 118,800.00
###
76 Bingkai Kaca Nako Set 15,400.00
###
77 Kaca Naco 6 daun Set 59,400.00
###
78 Kaca Naco 8 daun Set 68,200.00
###
79 Kaca Naco Rayben 5 mm, 6 daun Set 59,400.00
###
80 Kaca Naco Rayben 5 mm, 8 daun Set 67,100.00
###
81 Kait angin Jendela Buah 16,500.00
###
82 Kalsiboard 3,5 mm (120 cm X 240 cm) Kpg 72,800.00
###
83 Kalsiboard 4,5 mm (120 cm X 240 cm) Kpg 78,500.00
###
84 Kapur kg 6,600.00
###
85 Karpet tebal 6 mm m2 82,500.00
###
7 Kawat Beton kg 19,800.00
###
8 Kawat Burung m2 22,000.00
###
9 Kawat Duri m' 16,500.00
###
10 Kawat Harmonika m2 42,900.00
###
11 Kawat Jaring pagar lbr 30,800.00
###
12 Kawat Kassa m2 16,500.00
###
13 Kawat Las Dos 110,000.00
###
14 Kawat Nyamuk m2 19,800.00
###
15 Kawat Seng Polos kg 20,900.00
###
16 Kayu Gelam dia. 6-8 btg 8,800.00
###
17 Kayu Gelam dia. 10-12 btg 9,900.00
###
18 Kayu Hek btg 9,900.00
###
19 Kayu Lis 1/3 m' 11,550.00
###
20 Kayu Lis 1/4 m' 12,650.00
###
21 Kayu Lis Profil kecil m' 2,750.00
###
22 Kayu Lis Profil sedang m' 3,850.00
###
23 Kayu Lis Profil besar m' 8,250.00
###
24 Kayu Mosaik 30 x 30 cm Buah 6,875.00
###
25 Kayu Kaso 5/7 kelas III (Meranti dan sejenis) Btg 89,700.00
###
26 Kayu Kelas I (Unglen, Jati) m3 9,075,000.00
###
27 Kayu Kelas II (Petanang dan sejenis) m3 6,600,000.00
###
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
28 Kayu Kelas III (Meranti dan sejenis) m3 3,630,000.00
###
29 Kayu Papan 3/20 Kls. III m3 3,630,000.00
###
4 Kayu Kelas IV (Racuk dan sejenis) m3 1,650,000.00
###
5 Kayu Papan kelas IV keping 18,150.00
###
6 Kayu Racuk m3 1,980,000.00
###
7 Kayu Reng btg 37,500.00
###
8 Keramik lantai/dinding 20 x 20/25 cm putih polos Kotak 63,800.00
###
Keramik lantai/dinding 20 x 20/25 cm putih polos buah 2,552.00
###
9 Keramik lantai 20 x 20 cm warna, mutu C Kotak 57,200.00
###
Keramik lantai 20 x 20 cm warna, mutu C buah 2,288.00
###
10 Keramik lantai 20 x 20 cm warna, mutu B Kotak 68,200.00
###
Keramik lantai 20 x 20 cm warna, mutu B buah 2,728.00
###
11 Keramik dinding 20 x 25 cm warna Kotak 65,000.00
###
Keramik dinding 20 x 25 cm warna buah 3,250.00
###
12 Keramik lantai 20 x 25 cm warna, mutu B Kotak 67,300.00
###
Keramik lantai 20 x 25 cm warna, mutu B buah 3,365.00
###
13 Keramik lantai 30 x 30 cm warna Kotak 65,800.00
###
Keramik lantai 30 x 30 cm warna buah 5,981.82
###
14 Keramik lantai 30 x 30 cm putih polos Kotak 61,500.00
###
Keramik lantai 30 x 30 cm putih polos buah 5,590.91
###
15 Keramik lantai 40 x 40 cm warna mutu C Kotak 57,200.00
###
Keramik lantai 40 x 40 cm warna mutu C buah 9,152.00
###
16 Keramik lantai 40 x 40 cm warna mutu B Kotak 85,600.00
###
Keramik lantai 40 x 40 cm warna mutu B buah 14,266.67
###
17 Keramik lantai motif kayu (kasar) mutu A Kotak 118,700.00
###
18 Klem Talang Paralon Buah 19,783.33
###
19 Klem kabel listrik biasa Buah 154.00
###
20 Klem kabel listrik Buah 3,300.00
###
21 Korosin Ltr 2,200.00
###
22 Kran Air buah 23,800.00
###
23 Kuas 3"-4" buah 13,750.00
###
24 Kunci Gembok buah 9,350.00
###
25 Kunci Lemari buah 8,800.00
###
26 Kunci Pintu Kamar Tidur (Hotel) buah 440,000.00
###
27 Kunci Pintu KM/WC (lux) buah 385,000.00
###
28 Kunci Selot buah 14,300.00
###
29 Kunci Tanam biasa mutu C buah 50,000.00
###
30 Kunci Tanam 2 slaag biasa buah 96,800.00
###
31 Kunci Tanam 2 slaag mutu B buah 168,500.00
###
32 Kunci Tanam Kamar Mandi buah 38,600.00
###
33 L.bow listrik buah 2,750.00
###
34 Lampu Down Light buah 46,750.00
###
35 Lampu Hologen 50 watt buah 13,750.00
###
36 Lampu Hologen 150 watt buah 27,500.00
###
37 Lampu Hologen Box buah 110,000.00
###
38 Lampu TL 10 Watt buah 7,700.00
###
39 Lampu TL 20 Watt buah 11,000.00
###
40 Lampu TL 40 Watt (bambu) buah 115,500.00
###
41 Lampu Pijar 25 Watt Putih buah 5,500.00
###
42 Lampu Pijar 40 Watt Putih buah 6,050.00
###
43 Lantai Granit 30/30 Buah 22,550.00
###
44 Lantai Granit 40/40 Buah 48,400.00
###
45 Lantai Granit 60/60 Buah 128,700.00
###
46 Lantai Kayu Panil Gracewood m2 387,750.00
###
47 Las dop listrik Buah 550.00
###
48 Lem Kayu ltr 22,000.00
###
49 Lem Vinyl Kg 9,350.00
###
50 List Gypsum Besar m' 32,800.00
###
51 List Gypsum Kecil m' 17,500.00
###
52 Mangkok Saklar listrik Buah 1,980.00
###
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
53 MCB Buah 48,400.00
###
54 MCB Box isi 4 grup Buah 27,500.00
###
55 MCB Box isi 8 grup Buah 60,500.00
###
56 Melamic Clear kg 66,000.00
###
57 Melamic Gloss/dop (Finishing) kg 66,000.00
###
58 Mill kg 36,300.00
###
59 Minyak Bekisting liter 13,200.00
###
60 Minyak Cat liter 6,600.00
###
61 Minyak solar untuk industri / Minyak aspal liter 0.00
62 Minyak Gardan liter 0.00
63 Minyak Hidrolik liter 0.00
64 Minyak Selinder liter 0.00
65 Mozaik kayu lantai Uk. 30 x 30 cm buah 8,250.00
###
66 Pagar BRC, uk. 240 cm X 120 cm, dia. 5,5 mm Unit 379,500.00
###
67 Pagar BRC, uk. 240 cm X 90 cm, dia. 6 mm Unit 412,500.00
###
6 Paku Biasa bermacam ukuran 2" - 5" kg 28,500.00
###
4 Paku Biasa 1/2" - 1" kg 32,500.00
###
4 Paku Sumbat buah 660.00
###
4 Paku Beton buah 770.00
###
4 Paku Gypsum kg 35,000.00
###
4 Paku Seng,Asbes kg 24,200.00
###
4 Paku Asbes buah 660.00
###
4 Paku Sekrup 3,5" Kg 63,500.00
###
4 Paku Sekrup 3,5" buah 685.00
###
4 Parquet Jati m2 423,500.00
###
7 Pasir Beton / Pasang m3 118,750.00
###
8 Pasir Urug m3 82,500.00
###
9 Pewarna nat Bks 11,000.00
###
10 Pintu Alluminium m2 704,000.00
###
11 Pintu Besi Baja m2 2,145,000.00
###
12 Pintu Lipat m2 418,000.00
###
13 Pintu PVC lengkap + pemasangan Unit 231,000.00
###
14 Pipa besi medium 2 mm & 1/2", pjg 6 m M' 20,350.00
###
15 Pipa besi medium 2 mm & 3/4", pjg 6 m M' 25,740.00
###
16 Pipa besi medium 2 mm & 1", pjg 6 m M' 32,092.50
###
17 Pipa besi medium 2 mm & 1,5", pjg 6 m M' 45,870.00
###
18 Pipa besi medium 2 mm & 2", pjg 6 m M' 57,750.00
###
19 Pipa besi medium 2 mm & 2,5", pjg 6 m M' 75,350.00
###
20 Pipa besi medium 2 mm & 3", pjg 6 m M' 119,350.00
###
21 Pipa besi medium 2 mm & 4", pjg 6 m M' 155,540.00
###
22 Pipa paralon listrik 5/8" Btg 6,600.00
###
23 Pipa PVC & 1/2" mutu A (Wavin dan sejenis) M' 6,850.00
###
24 Pipa PVC biasa & 1/2" mutu B M' 5,250.00
###
25 Pipa PVC & 3/4" mutu A (Wavin dan sejenis) M' 7,900.00
###
26 Pipa PVC & 3/4" mutu B M' 6,650.00
###
27 Pipa PVC & 1" mutu A (Wavin dan sejenis) M' 9,800.00
###
28 Pipa PVC & 1" mutu B M' 7,200.00
###
29 Pipa PVC & 1.5" mutu A (Wavin dan sejenis) M' 16,900.00
###
30 Pipa PVC & 1.5" mutu B M' 9,950.00
###
31 Pipa PVC & 2" mutu A ( Wavin dan sejenis) M' 20,150.00
###
32 Pipa PVC & 2" mutu B M' 14,050.00
###
33 Pipa PVC & 3" mutu A (Wavin dan sejenis) M' 38,700.00
###
34 Pipa PVC & 3" mutu B M' 26,500.00
###
35 Pipa PVC & 4" mutu A ( Wavin dan sejenis) M' 59,500.00
###
36 Pipa PVC & 4" mutu B M' 38,000.00
###
37 Pipa PVC & 6" (15 cm) mutu A (Wavin dan sejenis) M' 136,125.00
###
38 Pipa Stainless 2", tebal 1 mm M' 82,500.00
###
39 Pipa Stainless 2", tebal 0.8 mm M' 73,920.00
###
40 Pipa Stainless 2,5", tebal 1 mm M' 104,720.00
###
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
41 Pipa Stainless 2,5", tebal 1.2 mm M' 92,400.00
###
42 Plamir Tembok kg 8,800.00
###
43 Plamir Kayu kg 23,300.00
###
44 Plat stainless, tebal 1 mm, uk. 244 cm X 122 cm Lbr 1,870,000.00
###
45 Plint keramik 10 x 30 cm warna buah 4,400.00
###
46 Plint keramik 10 x 40 cm warna buah 14,520.00
###
47 Plint Ubin PC Abu-abu 15 x 20 cm buah 880.00
###
48 Plint Ubin PC Abu-abu 10 x 30 cm buah 935.00
###
49 Plint Ubin PC Abu-abu 10 x 40 cm buah 962.50
###
50 Plywood warna/Jabarwood Lbr 121,000.00
###
51 Plywood Jati 3 mm Lbr 121,000.00
###
52 Plywood Sungkay 3 mm/ megatick Lbr 121,000.00
###
53 Plywood 3 mm Lbr 52,700.00
###
14 Plywood 4 mm Lbr 82,500.00
###
15 Plywood 6 mm Lbr 102,800.00
###
16 Plywood 9 mm Lbr 148,500.00
###
17 Plywood 12 mm Lbr 189,600.00
###
18 Plywood 20 mm Lbr 278,000.00
###
19 Politur dasar ltr 53,900.00
###
20 Politur Jadi ltr 58,300.00
###
21 Porselin Putih Uk. 10 x 10 cm buah 770.00
###
22 Porselin Warna Uk. 10 x 10 cm buah 1,100.00
###
23 Rangka Atap baja ringan untuk atap genteng, genteng m2 313,500.00
###
keramik, beton, dll + pemasangan 0.00
24 Rangka Atap baja ringan untuk atap seng metal, atap m2 237,820.00
###
asbes, aluminium, sirap, dll + pemasangan 0.00
25 Rangka Atap baja ringan bentuk joglo/bertumpuk/ m2 309,870.00
###
khusus + pemasangan 0.00
26 Rangka Atap baja ringan "Pryda" untuk atap Pelana, m2 281,050.00
###
Metal dan keramik + pemasangan 0.00
27 Rangka Atap baja ringan "Pryda" untuk atap Perisai, m2 309,870.00
###
Metal dan keramik + pemasangan 0.00
28 Rangka Atap baja ringan "Pryda" untuk atap Joglo, m2 360,360.00
###
Metal dan keramik + pemasangan 0.00
29 Rel Pintu Dorong Unit 264,000.00
###
30 Rolling Door Standar, t=4 mm, (minimal pas. 7 M2) m2 643,500.00
###
31 Rolling Door Standar, t=5 mm, (minimal pas. 7 M2) m2 693,000.00
###
32 Sanding Sealer Impra (Cat dasar) Kg 41,800.00
###
33 Seal Tape buah 5,500.00
###
34 Semen ( 50 kg ) Zak 72,800.00
###
15 Semen Portland ( PC ) kg 1,700.00
###
16 Semen Putih (40 kg) Zak 98,300.00
###
17 Semen Putih Kg 2,850.00
###
18 Semen Merah m3 41,800.00
###
19 Semen Nat kg 17,500.00
###
20 Seng Gelombang, lebar 70 cm m2 8,167.50
###
21 Seng Plat 120 cm X 240 cm lbr 116,600.00
###
22 Seng Plat 33 cm M' 14,520.00
###
23 Seng Plat 38 cm M' 20,350.00
###
24 Seng Plat 45 cm M' 22,000.00
###
25 Seng Plat 55 cm M' 28,600.00
###
26 Seng Plat 88 cm M' 36,300.00
###
27 Seng Plat 92 cm M' 38,500.00
###
28 Sabun Kg 12,320.00
###
29 Soda Api Kg 33,000.00
###
30 Soft Board ( 120 x 240 ) mm lbr 74,250.00
###
31 Saklar Tunggal biasa Buah 6,600.00
###
32 Saklar Ganda biasa Buah 14,850.00
###
33 Saklar Tunggal National Buah 23,800.00
###
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
34 Saklar Ganda National Buah 38,500.00
###
35 Scafolding tg 1,77 m X 1,77 m Unit 880,000.00
###
36 Roda Scafolding 4 buah Unit 467,500.00
###
37 Smartruss Aluminium Magnesium 0.00
- Lysaght Smartruss C 75.100 M' 24,750.00
###
- Lysaght Smartruss C 75.75 M' 20,680.00
###
- Reng U T S 40 M' 17,930.00
###
- Screw / Dynabolt Buah 2,090.00
###
- Valery Gutter Talang Jurai M' 137,940.00
###
- Strap Bracing M' 13,750.00
###
38 Stop Kontak biasa Buah 18,700.00
###
39 Stop kontak AC Buah 82,500.00
###
40 Sunscreen Aluminium M2 412,500.00
###
41 T.Duss listrik Buah 1,320.00
###
42 Talang Paralon, pjg 4 m btg 52,800.00
###
43 Tali Ijuk Kg 12,540.00
###
44 Ijuk m3 26,400.00
###
45 Tanah Liat/Urug m3 55,000.00
###
46 Tanah Puru m3 60,500.00
###
47 Tanah Sirtu m3 88,000.00
###
48 Taekwood 3 mm m2 43,800.00
###
49 Taekwood 4 mm biasa m2 51,500.00
###
50 Ter / Residu liter 49,500.00
###
51 Textil Tape roll 7,535.00
###
52 Thinner biasa Liter 13,200.00
###
53 Thinner Cat Glossy (Cobra dan sejenis) Liter 43,500.00
###
54 Urinoir buah 154,000.00
###
55 Urinoir mutu A unit 181,500.00
###
56 Vernis ltr 27,500.00
###
57 Vernis Batu Kg 71,500.00
###
58 Wallpaper m2 308,000.00
###
59 Wastafel biasa buah 335,000.00
###
60 Wastafel Halmar unit 468,000.00
###
61 Wastafel mutu A unit 635,000.00
###
62 Wood Filler Impra (dempul) Klg 35,200.00
###
63 Wood Stain Impra (cat pewarna) Klg 66,000.00
###
C PERALATAN
1 Alat Bantu jam 82,485.98
1 Asphalt Finisher jam 929,341.99
###
2 Asphalt Mixing Plant jam 8,248,597.50
###
3 Asphalt Sprayer jam 85,785.41
###
4 Compresor jam 219,962.60
###
5 Concrete Mixer jam 230,960.73
###
6 Concrete Pump jam 409,815.23
###
7 Concrete Vibrator jam 223,134.59
###
2 Dump Truck 3,5 Ton jam 343,141.66
###
3 Dump Truck 10 Ton jam 384,934.55
###
3 Excavator jam 659,887.80
###
4 Filter jam 43,992.52
###
5 Genset jam 274,953.25
###
6 Grader jam 1,099,813.00
###
7 Loader jam 1,099,813.00
###
8 Pneumatic Tired Roller jam 247,457.93
###
9 Tandem Roller jam 1,099,813.00
###
10 Flatbed Truck 3,5 ton jam 247,457.93
###
11 Water Tank Truck jam 274,953.25
###
12 Generator jam 575,692.09
###
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
13 Alat Bantu jam 82,485.98
###
14 Roller 3 roda jam 1,099,813.00
###
3 Sprayer, Selfprof jam 153,973.82
###
4 Buldozer jam 734,020.31
###
5 Scaffolding 177cm X 177 cm, Tg. 177 cm Set/Bulan 52,241.12
###
6 Stone Crusher (Pemecah batu) jam 948,444.82
###
7 Pengaduk beton jam 109,981.30
###
8 Stemper jam 26,395.51
###
E 9 Roller, Vibrator Pneu jam 1,099,813.00
###
10 Water Pump jam 274,953.25
###
SOFIAN HASAN
Direktur
JADWAL PELAKSANAAN
I PEKERJAAN PENDAHULUAN
1 Survey Pengukuran 0.29 0.29
2 Pembersihan Lokasi 0.96 0.32 0.64
3 Pek. Cor Beton Ready Mix K. 225 78.06 8.67 13.01 14.19 15.61 14.19 9.40 2.97
4 Labur Aspal 1.8 kg/m2 + tabur pasir 10.03 3.34 4.01 2.67
PROGRES MINGGUAN 100.00 0.79 2.22 4.39 11.46 13.01 14.19 15.61 14.19 9.58 6.94 4.63 2.97
KOMULATIF PROGRES MINGGUAN 0.00 0.79 3.01 7.41 18.86 31.87 46.07 61.68 75.87 85.46 92.39 97.03 100.00
4.5454545455
#N/A #N/A #N/A #N/A
SOFIAN HASAN
Direktur
1.20
1.00
0.80
0.60
0.40
0.20
-
0.29 0.29
DAFTAR HARGA SATUAN UPAH DAN BAHAN
SURVEY PER JULI 2013
HARGA
NO URAIAN SATUAN
PASAR (Rp)
A UPAH
1 Kepala Tukang Oh 110,000.00
2 Tukang Oh 90,000.00
3 Mandor Oh 90,000.00
4 Pekerja Tidak Terlatih Oh 65,000.00
5 Pekerja Terlatih Oh 75,000.00
B BAHAN/MATERIAL
1 Agregat Halus m3 422,500.00
2 Agregat Kasar m3 400,000.00
3 Agregat Kelas A m3 380,000.00
4 Agregat Kelas B m3 367,500.00
5 Agregat Kelas C m3 337,500.00
6 Aluminium Foil m2 17,000.00
7 Alcubond m2 622,500.00
8 Amplas Biasa Lbr 3,000.00
9 Amplas Niken Lbr 6,000.00
10 Atap Aluminium Zink Coated (seng) tebal 0,25 mm Lbr 45,000.00
11 Atap Aluminium Zink Coated (seng) tebal 0,3 mm Lbr 57,000.00
12 Atap Aluminium Zink Coated (seng) tebal 0,4 mm Lbr 80,000.00
13 Atap Aluminium Zincalume, tebal 0,25 mm Lbr 59,000.00
14 Atap Aluminium Zincalume, tebal 0,3 mm Lbr 61,000.00
15 Atap Aluminium Zincalume, tebal 0,4 mm Lbr 74,000.00
16 Atap Aluminium Gelombang tebal 0,5 mm Lbr 98,000.00
17 Atap Fiber warna"Polycarbonat" tbl. 4-5 mm m2 77,500.00
18 Atap Genteng Beton Lokal buah 4,000.00
19 Atap Genteng Beton buah 5,450.00
20 Atap Genteng Beton Cisangkan buah 7,000.00
21 Atap Genteng Buleleng buah 2,150.00
22 Atap Genteng Keramik biasa berglazur buah 7,700.00
23 Atap Genteng Keramik Berglazur Natural buah 9,700.00
24 Atap Genteng Keramik sejenis Berglazur warna buah 14,500.00
25 Atap Genteng Metal Biasa (88 cm X 77 cm) m2 34,000.00
26 Atap Genteng Metal Warna (120 cm X 76 cm) m2 35,000.00
27 Atap Genteng Metal Zincalume 2x4 (38,5 cm X 80cm) m2 152,000.00
28 Atap Genteng Metal Zincalume berpasir (77cmX100cm) m2 82,000.00
29 Atap Genteng Metal Zincalume berpasir biasa m2 56,000.00
30 Atap Genteng Kodok buah 900.00
31 Atap Onduline m2 64,000.00
32 Asbes polos 100 x 100 tbl = 4 mm Lbr 22,800.00
33 Asbes Gelombang Kecil, lebar 80 cm m2 22,000.00
34 Asbes Gelombang Kecil, lebar 105 cm m2 25,000.00
35 Asbes Gelombang Besar, lebar 105 cm m2 29,000.00
36 Asbes Gelombang motif genteng m2 27,000.00
37 Aquaproof kg 52,500.00
38 Bak Cuci Stainless Steel buah 245,000.00
39 Bak Cuci Teraso buah 185,000.00
40 Bak Fibreglass buah 220,000.00
41 Bak Teraso buah 180,000.00
42 Bambu dia. 6-8 cm/6m Btg 50,000.00
43 Batako buah 2,250.00
44 Batu Andesit hitam kecoklatan m2 170,000.00
45 Batu alam kecoklatan (Sangarong) m2 170,000.00
46 Batu Bata lobang m3 470,000.00
47 Batu Bata Kecil buah 875.00
48 Batu Bata Lobang buah 650.00
49 Batu Candi hitam m2 215,000.00
50 Batu Kali m3 375,000.00
HARGA
NO URAIAN SATUAN
PASAR (Rp)
51 Batu Kali tempel m2 85,000.00
52 Batu Karang Pilang m2 576,000.00
53 Batu Kerikil m3 400,000.00
54 Batu Koral beton m3 390,000.00
55 Batu Koral Jagung m3 330,000.00
56 Batu Krokos m3 392,000.00
57 Batu Palimanan kuning/hijau m2 168,000.00
58 Batu Palimanan kuning/hijau + bevel m2 168,000.00
59 Batu Pecah 0.5 - 1 (screen) m3 408,800.00
60 Batu Abu 0.00 - 0.5 (filler) m3 385,000.00
61 Batu Pecah 1.3 - 1.9 (spilt) m3 420,000.00
62 Batu Pecah 2/3 m3 425,000.00
63 Batu Pecah 3/5 m3 470,000.00
64 Batu Pecah 5/7 m3 425,000.00
65 Batu Marmer m2 288,960.00
66 Batu Roster / Terawang biasa buah 4,100.00
67 Besi dia. 5 mm Batang 20,500.00
68 Besi dia. 6 mm KS Batang 23,000.00
69 Besi dia. 8 mm KS TI Batang 49,000.00
70 Besi dia. 10 mm KS TI Batang 78,000.00
71 Besi dia. 12 mm KS TI Batang 110,000.00
72 Besi dia. 14 mm KS TI Batang 175,000.00
73 Besi dia. 16 mm KS TI Batang 192,000.00
74 Besi dia. 19 mm KS TI Batang 260,000.00
75 Besi Beton Polos kg 14,000.00
76 Besi Baja Profil WF, I dan H kg 14,500.00
77 Besi Baja Konstruksi ( CNP, INP,dan besi L) kg 13,500.00
78 Besi Beam Clamp dan Plat Siku m2 22,500.00
79 Besi Hollow baja 20 X 40, tb. 2mm Batang 120,000.00
80 Besi Hollow baja 40 X 40, tb. 2mm Batang 140,000.00
81 Besi Hollow baja 30 X 60, tb. 2mm Batang 170,000.00
82 Besi Hollow Plafond 2 X 4 Batang 23,500.00
83 Besi Strip kg 9,000.00
84 Besi Strip 2 X 3 M' 4,000.00
85 Beton Ready Mix K - 125 m3 800,000.00
86 Beton Ready Mix K - 175 m3 850,000.00
87 Beton Ready Mix K - 225 m3 900,000.00
88 Beton Ready Mix K - 250 m3 950,000.00
89 Beton Ready Mix K - 275 m3 1,000,000.00
90 Beton Ready Mix K - 300 m3 1,050,000.00
91 Beton Ready Mix K - 350 m3 1,100,000.00
92 Beton Ready Mix K - 400 m3 1,150,000.00
93 Bubungan Asbes Gelombang Besar m' 22,750.00
94 Bubungan Asbes Gelombang Kecil m' 21,000.00
95 Bubungan/Nok Genteng Beton Buah 6,000.00
96 Bubungan Genteng Buleleng Buah 5,200.00
97 Bubungan/ Nok genteng Keramik biasa berglazur Buah 8,500.00
98 Bubungan/Nok genteng Keramik sejenis berglazur Buah 18,500.00
99 Bubungan gtg Keramik sejenis warna berglazur Buah 25,000.00
100 Bubungan/Nok Genteng Metal/aluminium M' 30,000.00
101 Bubungan Genteng Kodok Buah 4,000.00
102 Cat Dasar kg 30,000.00
103 Cat Antara kg 23,000.00
104 Cat Kayu dan Besi Anti Rayap kg 25,000.00
105 Cat Khusus Glossy dan Quick Drying kg 26,500.00
106 Cat Minyak warna (biasa) mutu C kg 38,000.00
107 Cat Minyak mutu B kg 46,000.00
108 Cat Minyak Semprot kg 40,000.00
109 Cat Meni Besi kg 21,000.00
110 Cat Meni Besi /kayu/ Flincote kg 21,000.00
111 Cat Penutup kg 82,000.00
112 Cat Tembok mutu C (Vinotex,Q-Luc, dan sejenis) kg 12,000.00
HARGA
NO URAIAN SATUAN
PASAR (Rp)
113 Cat Tembok mutu B (Catylax,vinilex, dan sejenis) kg 21,000.00
114 Cat Tembok mutu B, Anti Lumut dan Jamur kg 23,000.00
115 Cat Tembok mutu A (Mowilex,Kemtone,Dulux,dll) kg 90,000.00
116 Closed Duduk Setara (sejenis standar KIA) unit 530,000.00
117 Closed Duduk Standar (sejenis Ex.TOTOC721FV1) unit 2,100,000.00
118 Closed Duduk Halmar unit 3,062,000.00
119 Closed Duduk mutu C unit 1,780,000.00
120 Closed Duduk mutu A unit 4,270,000.00
121 Closed Duduk mutu B unit 2,593,000.00
122 Closed Duduk standar unit 2,151,000.00
123 Closet Duduk / Monoblok bh 500,000.00
124 Closet Jongkok Porselen / biasa buah 145,000.00
125 Closet Jongkok Teraso buah 25,000.00
126 Closed Jongkok Standart / sejenis (mutu B) unit 165,000.00
127 Closed Jongkok sejenis ( mutu A) Unit 200,000.00
128 Shower Spray TX 403 SV 3 buah 325,000.00
129 Coneblock biasa tebal 6 cm buah 1,450.00
130 Coneblock warna tebal 6 cm buah 1,650.00
131 Coneblock biasa tebal 8 cm buah 1,900.00
132 Coneblock warna tebal 8 cm buah 2,200.00
133 Cornice (bubuk Semen putih utk gypsum) kg 6,000.00
134 Dempul Jadi kg 18,000.00
135 Dempul Ross Polac kg 25,000.00
136 Dempul Isamu kg 46,000.00
137 Dolken Kayu dia. 8 - 10/400 cm m3 275,000.00
138 Door Closer buah 240,000.00
139 Door Holder buah 30,000.00
140 Door Stoper buah 300,000.00
141 Door Stop buah 22,000.00
142 Ember hitam buah 6,500.00
143 Engsel Biasa buah 16,000.00
144 Engsel Kuningan 4" buah 27,000.00
145 Engsel Pintu buah 16,000.00
146 Epoxi kg 48,000.00
147 Eternit 100 x 100 tebal 2,7 mm Lbr 21,000.00
148 Eternit 100 x 100 tebal 3,5 mm Lbr 24,000.00
149 Filler m3 185,000.00
150 Fitting plafond listrik buah 8,500.00
151 Glass Block buah 22,500.00
152 Grendel/Slot Tanam 4" buah 72,500.00
153 Grendel biasa buah 14,500.00
154 Gypsum Board ( 120 x 240 x 9 ) mm lbr 60,000.00
155 Hordeng Horizontal Blind (aluminium) m2 92,000.00
156 Hordeng Vertikal Blind m3 95,000.00
157 Ijuk Kg 8,500.00
158 Jendela Aluminium + Kaca Reyband 5 mm m2 750,000.00
159 Jendela Besi m2 300,000.00
160 Jendela Bingkai Nako 100 cm X 70 cm Unit 87,700.00
161 Jendela Bingkai Nako m2 105,000.00
162 Kabel NYA 1,5 mm m' 3,800.00
163 Kabel NYA 2,5 mm m' 4,300.00
164 Kabel NYA 4.0 mm m' 5,300.00
165 Kabel NYM 2 X 1,5 mm m' 6,000.00
166 Kabel NYM 2 X 2,5 mm m' 8,500.00
167 Kabel NYM 2 X 4,0 mm m' 15,000.00
168 Kaca Cermin 3 mm m2 120,000.00
169 Kaca Cermin 5 mm m2 185,000.00
170 Kaca Patri m2 1,350,000.00
171 Kaca Bening 3 mm m2 62,000.00
172 Kaca Bening 4 mm m2 72,000.00
173 Kaca Bening 5 mm m2 100,000.00
174 Kaca Bening 8 mm m2 185,000.00
HARGA
NO URAIAN SATUAN
PASAR (Rp)
175 Kaca Bening 10 mm m2 225,000.00
176 Kaca Buram 12 mm m2 377,500.00
177 Kaca Rayband 5 mm m2 90,000.00
178 Kaca Buram/Es 5 mm m2 100,000.00
179 Bingkai Kaca Nako Set 14,000.00
180 Kaca Naco 6 daun Set 54,000.00
181 Kaca Naco 8 daun Set 62,000.00
182 Kaca Naco Rayben 5 mm, 6 daun Set 47,000.00
183 Kaca Naco Rayben 5 mm, 8 daun Set 60,000.00
184 Kait angin Jendela Buah 15,000.00
185 Kalsiboard 3,5 mm (120 cm X 240 cm) Kpg 55,000.00
186 Kalsiboard 4,5 mm (120 cm X 240 cm) Kpg 58,000.00
187 Kapur kg 6,000.00
188 Karpet tebal 6 mm m2 74,500.00
189 Kawat Beton kg 26,000.00
190 Kawat Burung m2 20,000.00
191 Kawat Duri m' 15,000.00
192 Kawat Harmonika m2 39,000.00
193 Kawat Jaring pagar lbr 28,000.00
194 Kawat Kassa m2 15,000.00
195 Kawat Las Dos 100,000.00
196 Kawat Nyamuk m2 18,000.00
197 Kawat Seng Polos kg 19,000.00
198 Kayu Gelam dia. 6-8 btg 8,000.00
199 Kayu Gelam dia. 10-12 btg 9,000.00
200 Kayu Hek btg 9,000.00
201 Kayu Lis 1/3 m' 10,500.00
202 Kayu Lis 1/4 m' 11,500.00
203 Kayu Lis Profil kecil m' 2,500.00
204 Kayu Lis Profil sedang m' 3,500.00
205 Kayu Lis Profil besar m' 7,500.00
206 Kayu Mosaik 30 x 30 cm Buah 6,250.00
207 Kayu Kaso 5/7 kelas III (Meranti dan sejenis) Btg 55,000.00
208 Kayu Kelas I (Unglen, Jati) m3 8,250,000.00
209 Kayu Kelas II (Petanang dan sejenis) m3 6,000,000.00
210 Kayu Kelas III (Meranti dan sejenis) m3 3,300,000.00
211 Kayu Papan 3/20 Kls. III m3 3,300,000.00
212 Kayu Kelas IV (Racuk dan sejenis) m3 1,500,000.00
213 Kayu Papan kelas IV keping 16,500.00
214 Kayu Racuk m3 1,650,000.00
215 Kayu Reng btg 30,000.00
216 Keramik lantai/dinding 20 x 20/25 cm putih polos Kotak 58,000.00
Keramik lantai/dinding 20 x 20/25 cm putih polos buah 2,320.00
217 Keramik lantai 20 x 20 cm warna, mutu C Kotak 52,000.00
Keramik lantai 20 x 20 cm warna, mutu C buah 2,080.00
218 Keramik lantai 20 x 20 cm warna, mutu B Kotak 62,000.00
Keramik lantai 20 x 20 cm warna, mutu B buah 2,480.00
219 Keramik dinding 20 x 25 cm warna Kotak 68,000.00
Keramik dinding 20 x 25 cm warna buah 3,400.00
220 Keramik lantai 20 x 25 cm warna, mutu B Kotak 46,600.00
Keramik lantai 20 x 25 cm warna, mutu B buah 2,330.00
221 Keramik lantai 30 x 30 cm warna Kotak 48,000.00
Keramik lantai 30 x 30 cm warna buah 4,320.43
222 Keramik lantai 30 x 30 cm putih polos Kotak 48,000.00
Keramik lantai 30 x 30 cm putih polos buah 4,320.43
223 Keramik lantai 40 x 40 cm warna mutu C Kotak 52,000.00
Keramik lantai 40 x 40 cm warna mutu C buah 8,320.00
224 Keramik lantai 40 x 40 cm warna mutu B Kotak 65,000.00
Keramik lantai 40 x 40 cm warna mutu B buah 10,400.00
225 Keramik lantai motif kayu (kasar) mutu A Kotak 50,000.00
226 Klem Talang Paralon Buah 2,750.00
227 Klem kabel listrik biasa Buah 140.00
HARGA
NO URAIAN SATUAN
PASAR (Rp)
228 Klem kabel listrik Buah 3,000.00
229 Korosin Ltr 2,000.00
230 Kran Air buah 10,000.00
231 Kuas 3"-4" buah 12,500.00
232 Kunci Gembok buah 8,500.00
233 Kunci Lemari buah 8,000.00
234 Kunci Pintu Kamar Tidur (Hotel) buah 400,000.00
235 Kunci Pintu KM/WC (lux) buah 350,000.00
236 Kunci Selot buah 13,000.00
237 Kunci Tanam biasa mutu C buah 25,000.00
238 Kunci Tanam 2 slaag biasa buah 65,000.00
239 Kunci Tanam 2 slaag mutu B buah 90,000.00
240 Kunci Tanam Kamar Mandi buah 27,000.00
241 L.bow listrik buah 2,500.00
242 Lampu Down Light buah 42,500.00
243 Lampu Hologen 50 watt buah 12,500.00
244 Lampu Hologen 150 watt buah 25,000.00
245 Lampu Hologen Box buah 100,000.00
246 Lampu TL 10 Watt buah 7,000.00
247 Lampu TL 20 Watt buah 10,000.00
248 Lampu TL 40 Watt (bambu) buah 105,000.00
249 Lampu Pijar 25 Watt Putih buah 5,000.00
250 Lampu Pijar 40 Watt Putih buah 5,500.00
251 Lantai Granit 30/30 Buah 20,500.00
252 Lantai Granit 40/40 Buah 44,000.00
253 Lantai Granit 60/60 Buah 117,000.00
254 Lantai Kayu Panil Gracewood m2 352,500.00
255 Las dop listrik Buah 500.00
256 Lem Kayu ltr 20,000.00
257 Lem Vinyl Kg 8,500.00
258 List Gypsum Besar m' 22,000.00
259 List Gypsum Kecil m' 12,000.00
260 Mangkok Saklar listrik Buah 1,800.00
261 MCB Buah 44,000.00
262 MCB Box isi 4 grup Buah 25,000.00
263 MCB Box isi 8 grup Buah 55,000.00
264 Melamic Clear kg 60,000.00
265 Melamic Gloss/dop (Finishing) kg 60,000.00
266 Mill kg 33,000.00
267 Minyak Bekisting liter 12,000.00
268 Minyak Cat liter 6,000.00
269 Minyak solar untuk industri / Minyak aspal liter
270 Minyak Gardan liter
271 Minyak Hidrolik liter
272 Minyak Selinder liter
273 Mozaik kayu lantai Uk. 30 x 30 cm buah 7,500.00
274 Pagar BRC, uk. 240 cm X 120 cm, dia. 5,5 mm Unit 345,000.00
275 Pagar BRC, uk. 240 cm X 90 cm, dia. 6 mm Unit 375,000.00
276 Paku Biasa bermacam ukuran 2" - 5" kg 15,000.00
277 Paku Biasa 1/2" - 1" kg 18,000.00
278 Paku Sumbat buah 600.00
279 Paku Beton buah 700.00
280 Paku Gypsum kg 25,000.00
281 Paku Seng,Asbes kg 22,000.00
282 Paku Asbes buah 600.00
283 Paku Sekrup 3,5" Kg 45,000.00
284 Paku Sekrup 3,5" buah 450.00
285 Parquet Jati m2 385,000.00
286 Pasir Beton / Pasang m3 95,000.00
287 Pasir Urug m3 100,000.00
288 Pewarna nat Bks 10,000.00
289 Pintu Alluminium m2 640,000.00
HARGA
NO URAIAN SATUAN
PASAR (Rp)
290 Pintu Besi Baja m2 1,950,000.00
291 Pintu Lipat m2 380,000.00
292 Pintu PVC lengkap Unit 210,000.00
293 Pipa besi medium 2 mm & 1/2", pjg 6 m M' 18,500.00
294 Pipa besi medium 2 mm & 3/4", pjg 6 m M' 23,400.00
295 Pipa besi medium 2 mm & 1", pjg 6 m M' 29,175.00
296 Pipa besi medium 2 mm & 1,5", pjg 6 m M' 41,700.00
297 Pipa besi medium 2 mm & 2", pjg 6 m M' 52,500.00
298 Pipa besi medium 2 mm & 2,5", pjg 6 m M' 68,500.00
299 Pipa besi medium 2 mm & 3", pjg 6 m M' 108,500.00
300 Pipa besi medium 2 mm & 4", pjg 6 m M' 141,400.00
301 Pipa paralon listrik 5/8" Btg 6,000.00
302 Pipa PVC & 1/2" mutu A (Wavin dan sejenis) M' 4,000.00
303 Pipa PVC biasa & 1/2" mutu B M' 3,750.00
304 Pipa PVC & 3/4" mutu A (Wavin dan sejenis) M' 5,500.00
305 Pipa PVC & 3/4" mutu B M' 4,600.00
306 Pipa PVC & 1" mutu A (Wavin dan sejenis) M' 7,500.00
307 Pipa PVC & 1" mutu B M' 4,750.00
308 Pipa PVC & 1.5" mutu A (Wavin dan sejenis) M' 13,000.00
309 Pipa PVC & 1.5" mutu B M' 8,000.00
310 Pipa PVC & 2" mutu A ( Wavin dan sejenis) M' 16,375.00
311 Pipa PVC & 2" mutu B M' 10,500.00
312 Pipa PVC & 3" mutu A (Wavin dan sejenis) M' 32,125.00
313 Pipa PVC & 3" mutu B M' 17,500.00
314 Pipa PVC & 4" mutu A ( Wavin dan sejenis) M' 52,000.00
315 Pipa PVC & 4" mutu B M' 30,000.00
316 Pipa PVC & 6" (15 cm) mutu A (Wavin dan sejenis) M' 123,750.00
317 Pipa Stainless 2", tebal 1 mm M' 75,000.00
318 Pipa Stainless 2", tebal 0.8 mm M' 67,200.00
319 Pipa Stainless 2,5", tebal 1 mm M' 95,200.00
320 Pipa Stainless 2,5", tebal 1.2 mm M' 84,000.00
321 Plamir Tembok kg 8,000.00
322 Plamir Kayu kg 17,000.00
323 Plat stainless, tebal 1 mm, uk. 244 cm X 122 cm Lbr 1,700,000.00
324 Plint keramik 10 x 30 cm warna buah 4,000.00
325 Plint keramik 10 x 40 cm warna buah 13,200.00
326 Plint Ubin PC Abu-abu 15 x 20 cm buah 800.00
327 Plint Ubin PC Abu-abu 10 x 30 cm buah 850.00
328 Plint Ubin PC Abu-abu 10 x 40 cm buah 875.00
329 Plywood warna/Jabarwood Lbr 110,000.00
330 Plywood Jati 3 mm Lbr 110,000.00
331 Plywood Sungkay 3 mm/ megatick Lbr 110,000.00
332 Plywood 3 mm Lbr 42,000.00
333 Plywood 4 mm Lbr 68,000.00
334 Plywood 6 mm Lbr 88,000.00
335 Plywood 9 mm Lbr 125,000.00
336 Plywood 12 mm Lbr 160,000.00
337 Plywood 20 mm Lbr 210,000.00
338 Politur dasar ltr 49,000.00
339 Politur Jadi ltr 53,000.00
340 Porselin Putih Uk. 10 x 10 cm buah 700.00
341 Porselin Warna Uk. 10 x 10 cm buah 1,000.00
342 Rangka Atap baja ringan untuk atap genteng, genteng m2 285,000.00
keramik, beton, dll + pemasangan
343 Rangka Atap baja ringan untuk atap seng metal, atap m2 216,200.00
asbes, aluminium, sirap, dll + pemasangan
344 Rangka Atap baja ringan bentuk joglo/bertumpuk/ m2 281,700.00
khusus + pemasangan
345 Rangka Atap baja ringan "Pryda" untuk atap Pelana, m2 255,500.00
Metal dan keramik + pemasangan
346 Rangka Atap baja ringan "Pryda" untuk atap Perisai, m2 281,700.00
Metal dan keramik + pemasangan
HARGA
NO URAIAN SATUAN
PASAR (Rp)
347 Rangka Atap baja ringan "Pryda" untuk atap Joglo, m2 327,600.00
Metal dan keramik + pemasangan
348 Rel Pintu Dorong Unit 240,000.00
349 Rolling Door Standar, t=4 mm, (minimal pas. 7 M2) m2 585,000.00
350 Rolling Door Standar, t=5 mm, (minimal pas. 7 M2) m2 630,000.00
351 Sanding Sealer Impra (Cat dasar) Kg 38,000.00
352 Seal Tape buah 3,500.00
353 Semen ( 50 kg ) Zak 68,000.00
354 Semen Portland ( PC ) kg 1,750.00
355 Semen Putih (40 kg) Zak 85,000.00
356 Semen Putih Kg 2,000.00
357 Semen Merah m3 38,000.00
358 Semen Nat Bks 12,000.00
359 Seng Gelombang, lebar 70 cm m2 7,425.00
360 Seng Plat 120 cm X 240 cm lbr 96,250.00
361 Seng Plat 33 cm M' 13,200.00
362 Seng Plat 38 cm M' 17,600.00
363 Seng Plat 45 cm M' 18,000.00
364 Seng Plat 55 cm M' 20,440.00
365 Seng Plat 88 cm M' 31,360.00
366 Seng Plat 92 cm M' 31,360.00
367 Sabun Kg 11,200.00
368 Soda Api Kg 30,000.00
369 Soft Board ( 120 x 240 ) mm lbr 67,500.00
370 Saklar Tunggal biasa Buah 6,000.00
371 Saklar Ganda biasa Buah 8,250.00
372 Saklar Tunggal National Buah 15,500.00
373 Saklar Ganda National Buah 23,500.00
374 Scafolding tg 1,77 m X 1,77 m Unit 700,000.00
375 Roda Scafolding 4 buah Unit 425,000.00
376 Smartruss/baja ringan sejenis Aluminium Magnesium
- Lysaght Smartruss/sejenis C 75.100 M' 22,500.00
- Lysaght Smartruss/sejenis C 75.75 M' 18,800.00
- Reng U T S 40 M' 16,300.00
- Screw / Dynabolt Buah 1,900.00
- Valery Gutter Talang Jurai M' 125,400.00
- Strap Bracing M' 12,500.00
377 Stop Kontak biasa Buah 17,000.00
378 Stop kontak AC Buah 65,000.00
379 Sunscreen Aluminium M2 375,000.00
380 T.Duss listrik Buah 1,000.00
381 Talang Paralon, pjg 4 m btg 47,000.00
382 Tali Ijuk Kg 11,400.00
383 Ijuk m3 24,000.00
384 Tanah Liat/Urug m3 57,000.00
385 Tanah Puru m3 62,500.00
386 Tanah Sirtu m3 80,000.00
387 Taekwood 3 mm m2 33,000.00
388 Taekwood 4 mm biasa m2 36,000.00
389 Ter / Residu liter 4,100.00
390 Textil Tape roll 6,850.00
391 Thinner biasa Liter 12,000.00
392 Thinner Cat Glossy (Cobra dan sejenis) Liter 25,000.00
393 Urinoir buah 120,000.00
394 Urinoir mutu A unit 1,500,000.00
395 Vernis ltr 24,000.00
396 Vernis Batu Kg 65,000.00
397 Wallpaper m2 75,000.00
398 Wastafel biasa buah 265,000.00
399 Wastafel Halmar unit 280,000.00
400 Wastafel mutu A unit 450,000.00
401 Wood Filler Impra (dempul) Klg 32,000.00
HARGA
NO URAIAN SATUAN
PASAR (Rp)
402 Wood Stain Impra (cat pewarna) Klg 60,000.00
C PERALATAN
1 Compresor jam
2 Concrete Mixer jam
3 Concrete Pump jam
4 Concrete Vibrator jam
5 Dump Truck jam
6 Excavator jam
7 Filter jam
8 Genset jam
9 Grader jam
10 Loader jam
11 Pneumatic Tired Roller jam
12 Tandem Roller jam
13 Flatbed Truck 3,5 ton jam
14 Water Tank Truck jam
15 Generator jam
16 Alat Bantu jam
17 Roller 3 roda jam
18 Sprayer, Selfprof jam
19 Buldozer jam
20 Scaffolding 177cm X 177 cm, Tg. 177 cm Set/Bulan
21 Stone Crusher (Pemecah batu) jam
22 Pengaduk beton jam
23 Stemper jam
24 Roller, Vibrator Pneu jam
25 Water Pump jam
D SERVICE
1 AC Window/Split/Multi Ls
2 Dispenser Ls
3 Kulkas/Freezer Ls
4 Kompor Gas 2T Ls
5 Kompor Gas 4T Ls
6 Mesin Cuci Ls
7 Pompa Air Ls
8 Instalasi listrik Ls
Tim Survey,
2. Isrok, ST ………………………………
b. Upah
1.00 Ls Tukang engsel tanam 125,000.00 125,000.00
125,000.00 125,000.00
b. Upah
1.00 Ls Tukang Pasang Closed Duduk 125,000.00 125,000.00 125,000.00
125,000.00 125,000.00
b. Upah
1.00 Ls Tukang Pasang 65,000.00 65,000.00
65,000.00 65,000.00
b. Upah
1.00 Ls Tukang Kaca film 55,000.00 55,000.00
55,000.00 55,000.00
b. Upah
1.00 Oh Tukang saringan air 5,000.00 5,000.00
5,000.00 5,000.00
- 83 -
Daftar Analisa Pekerjaan Taksir Tahun 2013 Semester II
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
b. Upah
1.00 Ls Pekerja + tukang 65,000.00 65,000.00
b. Upah
1.00 Ls Pekerja 750.00 750.00
b. Upah
1.00 Ls Pekerja pintu 55,000.00 75,000.00 75,000.00
75,000.00 75,000.00
b. Upah
1.00 Ls Tukang 431,200.00 431,200.00
431,200.00 431,200.00
b. Upah
1.00 Oh Pekerja 7,000.00 7,000.00
7,000.00 7,000.00
b. Upah
0.15 Oh Pekerja 55,000.00 8,250.00 8,250.00
0.03 Oh Kepala tukang 99,000.00 2,970.00 2,970.00
0.0252 Oh Mandor 99,000.00 2,650.00 2,650.00
13,870.00 13,870.00
- 84 -
Daftar Analisa Pekerjaan Taksir Tahun 2013 Semester II
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
1,833,250.00 1,833,250.00
b. Upah
3.00 Oh Pekerja 77,500.00 232,500.00 232,500.00
1.00 Oh Kepala tukang 150,000.00 150,000.00 150,000.00
0.9048 Oh Mandor 150,000.00 135,720.00 135,720.00
518,220.00 518,220.00
b. Upah
3.00 Oh Pekerja 77,500.00 232,500.00 232,500.00
3.00 Oh Kepala tukang 150,000.00 450,000.00 450,000.00
0.7619 Oh Mandor 150,000.00 80,000.00 80,000.00
762,500.00 762,500.00
b. Upah
0.80 Oh Pekerja 77,500.00 62,000.00 62,000.00
2.00 Oh Tukang 82,500.00 165,000.00 165,000.00
0.20 Oh Kepala tukang 150,000.00 30,000.00 30,000.00
0.040 Oh Mandor 150,000.00 6,000.00 6,000.00
263,000.00 263,000.00
b. Upah
0.80 Oh Pekerja 77,500.00 62,000.00 62,000.00
2.00 Oh Tukang 82,500.00 165,000.00 165,000.00
0.20 Oh Kepala tukang 150,000.00 30,000.00 30,000.00
0.040 Oh Mandor 150,000.00 6,000.00 6,000.00
263,000.00 263,000.00
- 85 -
Daftar Analisa Pekerjaan Taksir Tahun 2013 Semester II
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
1.00 bh Pintu kayu (medang) panel 900,000.00 900,000.00 900,000.00
- 86 -
Daftar Analisa Pekerjaan Taksir Tahun 2013 Semester II
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
1.00 M2 Alkabon + Rangka + Pasangan 550,000.00 550,000.00 550,000.00
b. Tenaga
0.3500 Oh Pekerja 55,000.00 19,250.00 19,250.00
0.0175 Oh Mandor 99,000.00 1,732.50 1,732.50
20,982.50 20,982.50
Mengetahui/ Menyetujui :
Kepala Dinas Pekerjaan Umum
Cipta Karya dan Perumahan Kota Palembang
- 87 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II
Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
I PEKERJAAN PERSIAPAN
1.2 1 M' Pagar Sementara dari Seng Gelombang Tinggi 2 Meter Rp 231,139.41
1.3 1 M' Pagar Sementara dari Kawat Duri Tinggi 1,8 Meter Rp 485,923.41
1.15 1 M' Pasang Pagar Kawat Jaring Galvanis Tinggi 1 Meter Rp 22,772.20
II PEKERJAAN TANAH
- 88 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II
Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
3.10 1 M' Pembuatan Tiang Pancang (40 x 40) cm, Beton Bertulang Rp 992,922.59
3.11 1 M' Pembuatan Tiang Pancang (35 x 35) cm, Beton Bertulang Rp 778,341.83
IV PEKERJAAN DINDING
- 89 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II
Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
V PEKERJAAN PLESTERAN
- 90 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II
Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
5.17 1 M2 Plesteran 1 Pc : 6 Ps, Tebal 20 mm Rp 63,420.50
VI PEKERJAAN KAYU
6.1 1 M3 Pasang Kusen Pintu dan Jendela K.kls. I (Kayu Jati, Unglen) Rp 13,292,500.00
6.3 1 M3 Pasang Kusen Pintu dan Jendela Kayu Kelas III Rp 7,416,000.00
6.10 1 M2 Pasang Pintu dan Jendela Kaca Kayu Kls. III Rp 475,050.00
6.19 1 M2 Pasang Kaso + Reng Genteng Kayu Kls. III Genteng kodok Rp 70,335.00
Genteng beton Rp 77,595.00
6.20 1 M2 Pasang Kaso + Reng Genteng Kayu Kls. II Genteng kodok Rp 105,975.00
- 91 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II
Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
Genteng beton Rp 119,175.00
6.21 1 M2 Pasang Kaso + Reng Atap Sirap,seng/asbes Kayu Kls. II Atap sirap Rp 141,600.00
Atap seng/asbes Rp 98,700.00
6.22 1 M2 Pasang Kaso + Reng Atap Sirap,seng/asbes Kayu Kls. III Atap sirap Rp 92,595.00
Atap seng/asbes Rp 69,000.00
6.25 1 M2 Pasang Rangka Langit-langit (1,00 x 1,00) m, Kayu Kls. III Rp 104,285.00
6.26 1 M2 Pasang Rangka Langit-langit (30 x 60) cm, Kayu Jati Rp 272,000.00
6.27 1 M2 Pasang Rangka Langit-langit (30 x 60) cm, Kayu Kls. II Rp 215,075.00
6.28 1 M2 Pasang Rangka Langit-langit (30 x 60) m, Kayu Kls. III Rp 146,765.00
6.29 1 M2 Pasang Rangka Langit-langit (30 x 30) cm, Kayu Jati Rp 320,975.00
6.30 1 M2 Pasang Rangka Langit-langit (30 x 30) cm, Kayu Kls. II Rp 254,150.00
6.31 1 M2 Pasang Rangka Langit-langit (30 x 30) m, Kayu Kls. III Rp 173,960.00
6.32 1 M' Pasang Lisplang Ukuran (3 x 20) cm, Kayu Jati Rp 104,015.00
6.33 1 M' Pasang Lisplang Ukuran (3 x 20) cm, Kayu Kls. II Rp 86,195.00
6.34 1 M' Pasang Lisplang Ukuran (3 x 30) cm, Kayu Jati Rp 141,325.00
6.35 1 M' Pasang Lisplang Ukuran (3 x 30) cm, Kayu Kls. II Rp 114,100.00
6.36 1 M' Pasang Lisplang Ukuran 2 x (3 x 20) cm, Kayu Kls.II Rp 155,285.00
6.37 1 M' Pasang Lisplang Ukuran 2 x (2 x 20) cm, Kayu Kls. II Rp 87,720.00
6.38 1 M' Pasang Lisplang Ukuran 2 x (2 x 20) cm, Kayu Kls. III Rp 62,904.00
6.40 1 M2 Pasang Rangka Dinding Pemisah + Papan Kayu Kls. III Rp 184,920.00
6.41 1 M2 Pasang Dinding Pemisah Teakwood Rangkap, Rangka Kayu kls. II Rp 263,625.00
6.42 1 M2 Pasang Dinding Pemisah Plywood Rangkap, Rangka Kayu Kelas III Rp 294,865.00
6.45 1 M' Pasang List Plafond Kayu Profil Kayu Profil Kecil Rp 7,590.00
Kayu Profil Sedang Rp 8,745.00
Kayu Profil Besar Rp 13,365.00
6.47 1 M2 Pasang lapis plywood Sungkay tanpa rangka, politur dan lis profil Rp 57,817.50
- 92 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II
Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
6.48 1 M2 Pasang lapis plywood Sungkay + list kayu, tanpa rangka dan politur Rp 74,157.50
6.50 1 M2 Dinding Sekat Teakwood 4 mm, Rangkap + Rangka Kayu kls. II Rp 322,050.00
6.51 1 M2 Dinding pemisah Plywood Sungkai rangkap + rangka kayu kls. II Rp 380,585.00
7.26 1 M2 Pasang Bekisting Untuk Lantai, plat dak (untuk bangunan gedung) Rp 226,850.00
- 93 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II
Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
7.42 1 M' Pasang Kayu Mal Bekisting untuk Beton Ready Mix jalan Rp 65,575.00
7.55 1 M3 Membuat 1/2 Dinding Beton Bertulang ( 100 Kg Besi + Bekisting) Rp 3,100,273.48
7.57 1 M' Membuat Kolom Penguat Beton Bertulang ( 11 x 11 ) cm + bekisting (kolom praktis) Rp 74,402.16
7.59 1 M2 Pasang Bekisting Untuk Lantai, plat dak dengan plywood 4 mm Rp 255,725.00
- 94 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II
Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
7.60 1 M3 Beton Ready Mix K-175 untuk Kolom, Balok, Plat Lantai, tangga dengan Concrete Pump (belalai Rp 1,205,591.46
7.61 1 M3 Beton Ready Mix K-175 untuk Kolom, Balok, Plat Lantai, tangga tanpa Concrete Pump (belalai) Rp 1,137,287.55
7.62 1 M3 Beton Ready Mix K-225 untuk Kolom, Balok, Plat Lantai, tangga dengan Concrete Pump (belalai Rp 1,261,691.46
7.63 1 M3 Beton Ready Mix K-225 untuk Kolom, Balok, Plat Lantai, tangga tanpa Concrete Pump (belalai) Rp 1,193,387.55
7.64 1 M3 Beton Ready Mix K-275 untuk Kolom, Balok, Plat Lantai, tangga dengan Concrete Pump (belalai Rp 1,373,891.46
8.7 1 M' Pasang Bubung Genteng Keramik KIA Natural atau sejenis Rp 142,700.00
8.8 1 M' Pasang Bubung Genteng Keramik KIA Warna atau sejenis Rp 159,200.00
8.10 1 M2 Pasang Atap Asbes Gelombang kecil lbr 0,8 tbl 4 mm Rp 54,479.00
8.11 1 M2 Pasang Atap Asbes Gelombang kecil lbr 1,05 tbl 4 mm Rp 62,949.00
8.13 1 M2 Pasang Atap Asbes Gelombang besar lbr 1,05 tbl 4 mm Rp 66,579.00
- 95 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II
Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
8.26 1 M2 Pasang Atap Seng Gelombang Rp 27,580.85
IX PEKERJAAN LANGIT-LANGIT
9.6 1 M2 Langit-langit Asbes/Eternit, Rangka Kayu Kls. III Tebal 2,7 mm Rp 133,200.00
Tebal 3,5 mm Rp 138,040.00
9.8 1 M2 Langit-langit Kalsiboard, Rangka Kayu Kls. III Tebal 3,5 mm Rp 150,428.00
Tebal 4,5 mm Rp 152,480.00
- 96 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II
Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
X PEKERJAAN SANITASI
10.8 Memasang 1 Buah Bak Mandi Porselin Batu Bata Volume 0,30 m3 Rp 1,807,225.00
10.11 Memasang 1 M' Pipa Penyalur Air Limbah Jenis Pipa Tanah, dia. 15 cm Rp 230,632.25
10.12 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata Ukuran (30 x 30) cm, Tinggi 35 cm Rp 610,440.00
10.13 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata Ukuran (45 x 45) cm, Tinggi 50 cm Rp 543,720.00
10.14 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata Ukuran (60 x 60) cm, Tinggi 65 cm Rp 836,767.25
- 97 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II
Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
11.20 1 m' Pasang Talang 1/2 Lingkaran Dia. 10 cm, Seng BJLS Rp 159,512.50
- 98 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II
Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
12.1 1 Buah Pasang Kunci Tanam mutu B Rp 257,600.00
12.21 1 Set Pekerjaan Pasang Jendela Kaca Nako Biasa Nako 6 daun Rp 97,075.00
Nako 8 daun Rp 105,875.00
12.22 1 Set Pekerjaan Pasang Jendela Kaca Nako Rayben
Nako 6 daun, rayben Rp 97,075.00
Nako 8 daun, rayben Rp 104,775.00
- 99 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II
Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
13.8 1 m' Pasang Plint Ubin Granito Ukuran 10 x 40 cm Rp 45,511.25
13.33 1 m2 Pasang Dinding Batu Tempel Hitam/Kali + anti lumut (vernis) Rp 240,246.25
13.34 1 m2 Pasang Dinding Batu Candi Hitam + anti lumut (vernis) Rp 392,706.25
- 100 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II
Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
13.37 1 m2 Pasang Dinding batu Alam/Andesit + anti lumut(vernis) Rp 422,746.75
14.3 1 m2 Mengerok karat cat lama permukaan baja dengan cara manual Rp 12,616.00
14.7 1 m2 Pengecatan Bidang Kayu Baru ( 1 Lapis Plamir, 1 lapis Cat Rp 51,157.00
Dasar, 2 Lapis Cat Penutup )
14.8 1 m2 Pengecatan Bidang Kayu Baru ( 1 Lapis Plamir, 1 lapis Cat Rp 70,975.00
Dasar, 3 Lapis Cat Penutup )
14.10 1 m2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter Rp 25,975.00
14.12 1 m2 Pengecatan Tembok Baru ( 1 Lapis Plamir, 1 lapis Cat Cat mutu C Rp 20,050.00
Dasar, 2 Lapis Cat Penutup ) Cat mutu B Rp 23,911.00
Cat Mutu B Anti lumut/jamur Rp 24,340.00
Cat Mutu A Anti lumut/jamur Rp 43,645.00
14.13 1 m2 Pengecatan Tembok Lama ( 1 lapis Cat Dasar, 2 Lapis cat Cat mutu C Rp 16,720.00
Penutup ) Cat mutu B Rp 19,690.00
Cat Mutu B Anti lumut/jamur Rp 19,195.00
14.15 1 m2 Pengecatan Permukaan Baja dengan Meni Besi dan perancah Rp 57,395.50
14.16 10 m2 Cat Semprot minyak Chames Stones ( 1/2 Ducco ) = Untuk 1 M2 Rp 248,216.40
- 101 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II
Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
15.1 1 Titik Pemasangan Saklar Lampu = Untuk 1 Titik Rp 263,296.00
PEKERJAAN TAKSIR
- 102 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II
Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
Pintu folding gate tebal 1,2mm Rp 940,000.00
- 103 -