RENCANA ANGGARAN BIAYA (RAB)

PROYEK : PT. BANK MANDIRI (Persero) Tahun 2014


PEKERJAAN : REHAB TOILET PRIA DAN TOILET WANITA LANTAI II
LOKASI : KANTOR BANK MANDIRI CABANG CINDE JL. JEND. SUDIRMAN
NO. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
1 2 4 5 6

I PEKERJAAN PENDAHULUAN
1 Survey Pengukuran - 300,000.00 300,000.00
2 Pembersihan Lokasi 88.00 m2 15,250.00 1,342,000.00
3 Papan Nama Proyek 1.00 Bh 250,000.00 250,000.00
1,892,000.00
II PEKERJAAN COR BETON
1 Urugan pasir 42.24 m³ 123,750.00 5,227,125.75
2 Pas. Mal kayu 120.00 m¹ 65,575.00 7,869,000.00
3 Beton Ready Mix K.225 91.56 m³ 1,193,387.55 109,266,564.08
4 Labur aspal 1,8 kg/m2 + tabur pasir 763.00 m² 18,392.86 14,033,748.68
136,396,438.51
III PEKERJAAN LAIN-LAIN
1 ADM + Lap photo - 1,000,000.00 1,000,000.00
2 Biaya asbuilt drawing - 250,000.00 250,000.00
3 Pembersihan akhir 52.00 m2 6,375.00 331,500.00
1,581,500.00

REKAPITULASI
I PEKERJAAN PENDAHULUAN Rp. 1,892,000.00 ###
II PEKERJAAN COR BETON Rp. 136,396,438.51
III PEKERJAAN LAIN-LAIN Rp. 1,581,500.00
JUMLAH Rp. 139,869,938.51 ###
PPN 10 % Rp. 13,986,993.85
JUMLAH SETELAH PPN 10 % Rp. 153,856,932.36
DIBULATKAN RP. 153,856,000.00
TERBILANG : SERATUS EMPAT PULUH SEMBILAN JUTA DELAPAN RATUS TUJUH
PULUH RIBU RUPIAH

Palembang, 26 Februari 2014


CV. HABIBI PUTRA PRATAMA

SOFIAN HASAN
Direktur

FR
RENCANA ANGGARAN BIAYA (RAB)

PROYEK : PT. BANK MANDIRI (Persero) Tahun 2014


PEKERJAAN : REHAB TOILET PRIA DAN TOILET WANITA LANTAI II
LOKASI : KANTOR BANK MANDIRI CABANG CINDE JL. JEND. SUDIRMAN
NO. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
1 2 4 5 6

I PEKERJAAN PENDAHULUAN
1 Survey Pengukuran - 407,000.00 407,000.00
2 Pembersihan Lokasi 88.00 m 2
- -
3 Papan Nama Proyek 1.00 Bh 250,000.00 250,000.00
657,000.00
II PEKERJAAN COR BETON
1 Urugan pasir 42.24 m³ 211,500.00 8,933,633.10
2 Pas. Mal kayu 120.00 m¹ - -
3 Beton Ready Mix K.225 91.56 m³ 15,583.33 1,426,809.69
4 Labur aspal 1,8 kg/m2 + tabur pasir 763.00 m² - -
10,360,442.79
III PEKERJAAN LAIN-LAIN
1 ADM + Lap photo - 1,000,000.00 1,000,000.00
2 Biaya asbuilt drawing - 250,000.00 250,000.00
3 Pembersihan akhir 52.00 m2 - -
1,250,000.00

REKAPITULASI
I PEKERJAAN PENDAHULUAN Rp. 657,000.00 ###
II PEKERJAAN COR BETON Rp. 10,360,442.79
III PEKERJAAN LAIN-LAIN Rp. 1,250,000.00
JUMLAH Rp. 12,267,442.79 ###
PPN 10 % Rp. 1,226,744.28
JUMLAH SETELAH PPN 10 % Rp. 13,494,187.07
DIBULATKAN RP. 13,494,000.00
TERBILANG : SERATUS EMPAT PULUH SEMBILAN JUTA DELAPAN RATUS TUJUH
PULUH RIBU RUPIAH

Palembang, 26 Februari 2014


CV. HABIBI PUTRA PRATAMA

SOFIAN HASAN
Direktur

R
RENCANA ANGGARAN BIAYA (RAB)

PROYEK : PT. BANK MANDIRI (Persero) Tahun 2014


PEKERJAAN : REHAB TOILET PRIA DAN TOILET WANITA LANTAI II
LOKASI : KANTOR BANK MANDIRI CABANG CINDE JL. JEND. SUDIRMAN

NO. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA


1 2 4 5 6

I PEKERJAAN PENDAHULUAN
1 Survey Pengukuran - 407,000.00 407,000.00
2 Pembersihan Lokasi 88.00 m 2
15,250.00 1,342,000.00
3 Papan Nama Proyek 1.00 Bh 250,000.00 250,000.00
- 1,999,000.00
II PEKERJAAN COR BETON - 0
1 Urugan pasir 42.24 m³ 123,750.00 5,227,125.75
2 Pas. Mal kayu 120.00 m¹ 65,575.00 7,869,000.00
3 Beton Ready Mix K.225 91.56 m³ 1,193,387.55 109,266,564.08
4 Labur aspal 1,8 kg/m2 + tabur pasir 763.00 m² 18,392.86 14,033,748.68
- 136,396,438.51
III PEKERJAAN LAIN-LAIN -
1 ADM + Lap photo - 1,000,000.00 1,000,000.00
2 Biaya asbuilt drawing - 250,000.00 250,000.00
3 Pembersihan akhir 52.00 m2 6,375.00 331,500.00
1,581,500.00

REKAPITULASI
I PEKERJAAN PENDAHULUAN Rp. 1,999,000.00 ###
II PEKERJAAN COR BETON Rp. 136,396,438.51
III PEKERJAAN LAIN-LAIN Rp. 1,581,500.00
JUMLAH Rp. 139,976,938.51 ###
PPN 10 % Rp. 13,997,693.85
JUMLAH SETELAH PPN 10 % Rp. 153,974,632.36
DIBULATKAN RP. 153,974,000.00
TERBILANG : SERATUS EMPAT PULUH SEMBILAN JUTA DELAPAN RATUS TUJUH
PULUH RIBU RUPIAH

Palembang, 26 Februari 2014


CV. HABIBI PUTRA PRATAMA

SOFIAN HASAN
Direktur
RENCANA ANGGARAN BIAYA (RAB)

PROYEK : PT. BANK MANDIRI (Persero) Tahun 2014


PEKERJAAN : REHAB TOILET PRIA DAN TOILET WANITA LANTAI II
LOKASI : KANTOR BANK MANDIRI CABANG CINDE JL. JEND. SUDIRMAN
NO. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
1 2 4 5 6

I PEKERJAAN PENDAHULUAN
1 Survey Pengukuran - 407,000.00 407,000.00
2 Pembersihan Lokasi 88.00 m2 77,500.00 6,820,000.00
3 Papan Nama Proyek 1.00 Bh 250,000.00 250,000.00
- 7,477,000.00
II PEKERJAAN COR BETON - 0
1 Urugan pasir 42.24 m³ - -
2 Pas. Mal kayu 120.00 m¹ 24,750.00 2,970,000.00
3 Beton Ready Mix K.225 91.56 m³ - -
4 Labur aspal 1,8 kg/m2 + tabur pasir 763.00 m² - -
- 2,970,000.00
III PEKERJAAN LAIN-LAIN -
1 ADM + Lap photo - 1,000,000.00 1,000,000.00
2 Biaya asbuilt drawing - 250,000.00 250,000.00
3 Pembersihan akhir 52.00 m2 43,137.50 2,243,150.00
3,493,150.00

REKAPITULASI
I PEKERJAAN PENDAHULUAN Rp. 7,477,000.00 ###
II PEKERJAAN COR BETON Rp. 2,970,000.00
III PEKERJAAN LAIN-LAIN Rp. 3,493,150.00
JUMLAH Rp. 13,940,150.00 ###
PPN 10 % Rp. 1,394,015.00
JUMLAH SETELAH PPN 10 % Rp. 15,334,165.00
DIBULATKAN RP. 15,334,000.00
TERBILANG : SERATUS EMPAT PULUH SEMBILAN JUTA DELAPAN RATUS TUJUH
PULUH RIBU RUPIAH

Palembang, 26 Februari 2014


CV. HABIBI PUTRA PRATAMA

SOFIAN HASAN
Direktur
DAFTAR ANALISA PEKERJAAN KOTA PALEMBANG
TAHUN ANGGARAN 2014 SEMESTER I

SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

I PEKERJAAN PERSIAPAN
1.1 1 M' Pagar Sementara dari Kayu Tinggi 2 Meter
a. Bahan
1.250 Btg Kayu Gelam dia. 6-8 8,800.00 11,000.00 11,000.00
2.500 Kg Semen Portland 1,700.00 4,250.00 4,250.00
0.005 M3 Pasir Beton 118,750.00 593.75 593.75
0.009 M3 Koral Beton 518,850.62 4,669.66 4,669.66
0.072 M3 Kayu 5/7 kelas IV 1,650,000.00 118,800.00 118,800.00
0.060 Kg Paku Biasa 2"-5" 28,500.00 1,710.00 1,710.00
0.400 Lt Teer/Residu 49,500.00 19,800.00 19,800.00
160,823.41 160,823.41

b. Tenaga
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.020 Oh Mandor 150,000.00 3,000.00 3,000.00
62,000.00 62,000.00

Jumlah 160,823.41 62,000.00 222,823.41

1.2 1 M' Pagar Sementara dari Seng Gelombang Tinggi 2 Meter


a. Bahan
1.250 Btg Kayu Gelam dia. 6-8 8,800.00 11,000.00 11,000.00
2.500 Kg Semen Portland 1,700.00 4,250.00 4,250.00
1.200 Lbr Seng Gelombang 3"-5" 8,167.50 9,801.00 9,801.00
0.005 M3 Pasir Beton 118,750.00 593.75 593.75
0.009 M3 Koral Beton 518,850.62 4,669.66 4,669.66
0.072 M3 Kayu 5/7 kelas IV 1,650,000.00 118,800.00 118,800.00
0.060 Kg Paku Biasa 2"-5" 28,500.00 1,710.00 1,710.00
0.450 Kg Meni Besi 40,700.00 18,315.00 18,315.00
169,139.41 169,139.41

b. Tenaga
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.020 Oh Mandor 150,000.00 3,000.00 3,000.00
62,000.00 62,000.00

Jumlah 169,139.41 62,000.00 231,139.41

1.3 1 M' Pagar Sementara dari Kawat Duri Tinggi 1,8 Meter
a. Bahan
1.000 Btg Kayu Gelam dia. 6-8 8,800.00 8,800.00 8,800.00
2.000 Kg Semen Portland 1,700.00 3,400.00 3,400.00
25.000 Kg Kawat Duri 16,500.00 412,500.00 412,500.00
0.005 M3 Pasir Beton 118,750.00 593.75 593.75
0.009 M3 Koral Beton 518,850.62 4,669.66 4,669.66
0.060 Kg Paku Biasa 2"-5" 28,500.00 1,710.00 1,710.00
431,673.41 431,673.41

b. Tenaga
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.300 Oh Pekerja 77,500.00 23,250.00 23,250.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.020 Oh Mandor 150,000.00 3,000.00 3,000.00
54,250.00 54,250.00

Jumlah 431,673.41 54,250.00 485,923.41

1.4 1 M' Pengukuran dan Pemasangan Bouwplank


a. Bahan
0.012 M3 Kayu 5/7 kelas IV 1,650,000.00 19,800.00 19,800.00
0.020 Kg Paku Biasa 2" - 5" 28,500.00 570.00 570.00
0.007 M3 Kayu Papan 3/20 3,630,000.00 25,410.00 25,410.00
45,780.00 45,780.00

b. Tenaga
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.005 Oh Mandor 150,000.00 750.00 750.00
22,500.00 22,500.00

Jumlah 45,780.00 22,500.00 68,280.00

1.5 1 M2 Pembuatan Kantor Sementara, Dengan Lantai Plesteran


a. Bahan
1.250 Btg Kayu Gelam dia. 6-8 8,800.00 11,000.00 11,000.00
0.180 M3 Kayu 1,650,000.00 297,000.00 297,000.00
0.850 Kg Paku Biasa 28,500.00 24,225.00 24,225.00
1.100 Kg Besi Strip 11,000.00 12,100.00 12,100.00
35.000 Kg Semen Portland 1,700.00 59,500.00 59,500.00
0.150 M3 Pasir Pasang 118,750.00 17,812.50 17,812.50
0.100 M3 Pasir Beton 118,750.00 11,875.00 11,875.00
0.150 M3 Koral Beton 518,850.62 77,827.59 77,827.59
30 Bh Bata Merah 1,375.00 41,250.00 41,250.00
0.250 Lbr Seng Plat 116,600.00 29,150.00 29,150.00
2.000 Bh Jendela Nako 99,000.00 198,000.00 198,000.00
0.080 M2 Kaca Polos 71,500.00 5,720.00 5,720.00
0.150 Bh Kunci Tanam 50,000.00 7,500.00 7,500.00
0.060 Lbr Plywood 4 mm 82,500.00 4,950.00 4,950.00
797,910.09 797,910.09

b. Tenaga
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
1.000 Oh Tukang Batu 125,000.00 125,000.00 125,000.00
2.000 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.300 Oh Kepala Tukang 150,000.00 45,000.00 45,000.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
582,500.00 582,500.00

Jumlah 797,910.09 582,500.00 1,380,410.09

1.6 1 M2 Pembuatan Gudang Semen dan Alat - Alat


a. Bahan
1.700 Btg Kayu Gelam dia. 6-8 8,800.00 14,960.00 14,960.00
0.210 M3 Kayu 1,650,000.00 346,500.00 346,500.00
0.300 Kg Paku Biasa 28,500.00 8,550.00 8,550.00
10.500 Kg Semen Portland 1,700.00 17,850.00 17,850.00
0.030 M3 Pasir Beton 118,750.00 3,562.50 3,562.50
0.050 M3 Koral Beton 518,850.62 25,942.53 25,942.53
1.500 Lbr Seng Gelombang BJLS 8,167.50 12,251.25 12,251.25
429,616.28 429,616.28

b. Tenaga
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
0.200 Oh Kepala Tukang 150,000.00 30,000.00 30,000.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
365,000.00 365,000.00

Jumlah 429,616.28 365,000.00 794,616.28

1.7 1 M2 Pembuatan Rumah Jaga/Konstruksi Kayu


a. Bahan
3.000 Btg Kayu Gelam dia. 6-8 8,800.00 26,400.00 26,400.00
0.276 M3 Kayu 1,650,000.00 455,400.00 455,400.00
0.700 Kg Paku Biasa 28,500.00 19,950.00 19,950.00
1 M2 Seng Gelombang BJLS 8,167.50 8,167.50 8,167.50
509,917.50 509,917.50

b. Tenaga
1.500 Oh Tukang Kayu 125,000.00 187,500.00 187,500.00
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
0.150 Oh Kepala Tukang 150,000.00 22,500.00 22,500.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
295,000.00 295,000.00

Jumlah 509,917.50 295,000.00 804,917.50

1.8 1 M2 Membersihkan Lapangan dan Perataan


a. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
15,250.00 15,250.00

Jumlah 15,250.00 15,250.00

1.9 1 M Pembuatan Bedeng Buruh


2

a. Bahan
1.250 Btg Kayu Gelam dia. 6-8 8,800.00 11,000.00 11,000.00
0.186 M3 Kayu 1,650,000 306,900.00 306,900.00
0.300 Kg Paku Biasa 28,500.00 8,550.00 8,550.00
18.000 Kg Semen Portland 1,700.00 30,600.00 30,600.00
0.030 M3 Pasir Beton 118,750.00 3,562.50 3,562.50
0.050 M3 Koral Beton 518,850.62 25,942.53 25,942.53
1 M2 Seng Gelombang BJLS 8,167.50 8,167.50 8,167.50
1.350 Lbr Plywood 4 mm 82,500.00 111,375.00 111,375.00
506,097.53 506,097.53

b. Tenaga
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
0.200 Oh Kepala Tukang 150,000.00 30,000.00 30,000.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
365,000.00 365,000.00

Jumlah 506,097.53 365,000.00 871,097.53

1.10 1 M Pembuatan Bak Adukan Ukuran (40 x 50 x 20) cm


2

a. Bahan
0.036 M3 Kayu Kls. IV 1,650,000 59,400.00 59,400.00
0.080 Kg Paku Biasa 28,500.00 2,280.00 2,280.00
1.000 Btg Kaso 5/7 89,700.00 89,700.00 89,700.00
151,380.00 151,380.00

b. Tenaga
0.300 Oh Tukang Kayu 125,000.00 37,500.00 37,500.00
0.0015 Oh Mandor 150,000.00 225.00 225.00
37,725.00 37,725.00

Jumlah 151,380.00 37,725.00 189,105.00

1.11 1 M Pembuatan Stegger dari Bambu, Ukuran (40 x 50 x 20) cm


2

a. Bahan
1.000 Btg Bambu & 6 - 8 /600 cm 55,000.00 55,000.00 55,000.00
0.250 Kg Tali Ijuk 12,540.00 3,135.00 3,135.00
58,135.00 58,135.00

b. Tenaga
0.017 Oh Tukang Kayu 125,000.00 2,125.00 2,125.00
0.002 Oh Kepala Tukang 150,000.00 300.00 300.00
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.013 Oh Mandor 150,000.00 1,950.00 1,950.00
23,750.00 23,750.00

Jumlah 58,135.00 23,750.00 81,885.00

1.12 1 M Pembuatan Jalan Sementara


2

a. Bahan
0.150 M3 Batu Belah 15/20/Batu Kali 385,000.00 57,750.00 57,750.00
0.090 M3 Batu Pecah 5/7 385,000.00 34,650.00 34,650.00
0.010 M3 Pasir Pasang 118,750.00 1,187.50 1,187.50
93,587.50 93,587.50

b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
85,000.00 85,000.00

Jumlah 93,587.50 85,000.00 178,587.50

1.13 1 M3 Bongkaran Beton Bertulang


a. Tenaga
6.667 Oh Pekerja 77,500.00 516,692.50 516,692.50
0.333 Oh Mandor 150,000.00 49,950.00 49,950.00
566,642.50 566,642.50

Jumlah 566,642.50 566,642.50

1.14 1 M3 Bongkaran Dinding Tembok Bata Merah /Bata lobang


a. Tenaga
6.667 Oh Pekerja 77,500.00 516,692.50 516,692.50
0.033 Oh Mandor 150,000.00 4,950.00 4,950.00
521,642.50 521,642.50

Jumlah 521,642.50 521,642.50

1.15 1 M' Pasang Pagar Kawat Jaring Galvanis Tinggi 1 Meter


a. Bahan
0.434 Lbr Pagar Kawat Jaring 30,800.00 13,367.20 13,367.20
13,367.20 13,367.20

b. Tenaga
0.042 Oh Pekerja 77,500.00 3,255.00 3,255.00
0.004 Oh Kepala Tukang 150,000.00 600.00 600.00
0.042 Oh Tukang 125,000.00 5,250.00 5,250.00
0.002 Oh Mandor 150,000.00 300.00 300.00
9,405.00 9,405.00

Jumlah 13,367.20 9,405.00 22,772.20

1.16 10 M2 Pembersihan Akhir Lapangan


a. Tenaga
0.7500 Oh Pekerja 77,500.00 58,125.00 58,125.00
0.0375 Oh Mandor 150,000.00 5,625.00 5,625.00
63,750.00 63,750.00

Jumlah 63,750.00 63,750.00


Untuk 1 M2 Jumlah 6,375.00 6,375.00

1.17 10 M2 Bongkaran Rangka Atap


a. Tenaga
0.250 Oh Tukang 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
112,500.00 112,500.00

Jumlah 112,500.00 112,500.00


Untuk 1 M2 Jumlah 11,250.00 11,250.00

1.18 1 M3 Bongkaran Kuda-kuda Kayu


a. Tenaga
6.000 Oh Tukang 125,000.00 750,000.00 750,000.00
0.600 Oh Kepala Tukang 150,000.00 90,000.00 90,000.00
4.000 Oh Pekerja 77,500.00 310,000.00 310,000.00
1,150,000.00 1,150,000.00

Jumlah 1,150,000.00 1,150,000.00


Untuk tidak dipakai lagi = 0,5 x Jumlah 575,000.00 575,000.00

1.19 10 M2 Bongkaran Plafond + Rangka


a. Tenaga
0.600 Oh Tukang 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
2.000 Oh Pekerja 77,500.00 155,000.00 155,000.00
239,000.00 239,000.00

Jumlah 239,000.00 239,000.00


Untuk 1 M2 Jumlah 23,900.00 23,900.00

1.20 1 M2 Pasang Cerucup Gelam


a. Bahan
6.000 Btg Gelam dia. 6 - 8 cm 8,800.00 52,800.00 52,800.00
6.000 Btg Gelam dia. 10 - 12 cm 9,900.00 59,400.00 59,400.00
52,800.00 52,800.00
59,400.00 59,400.00
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.019 Oh Mandor 150,000.00 2,850.00 2,850.00
27,650.00 27,650.00

1 M2 Pasang Cerucup Gelam dia. 6-8 cm 52,800.00 27,650.00 80,450.00


1 M2 Pasang Cerucup Gelam dia. 10-12 cm 59,400.00 27,650.00 87,050.00

1.21 1 M' Pasang Turap Gelam


a. Bahan
14.000 Btg Gelam dia. 6 - 8 cm 8,800.00 123,200.00 123,200.00
123,200.00 123,200.00

b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.019 Oh Mandor 150,000.00 2,850.00 2,850.00
27,650.00 27,650.00

1 M' Pasang Turap Gelam dia. 6-8 cm 123,200.00 27,650.00 150,850.00

1.22 1 M2 Pasang Kisdam


a. Bahan
1.250 Kpg Papan Kayu kls IV 18,150.00 22,687.50 22,687.50
0.100 Kg Paku biasa 2"- 5" 28,500.00 2,850.00 2,850.00
2.000 Btg Gelam dia. 10 - 12 cm 8,800.00 17,600.00 17,600.00
43,137.50 43,137.50

b. Tenaga
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.019 Oh Mandor 150,000.00 2,850.00 2,850.00
27,650.00 27,650.00

1 M2 Pasang Kisdam Gelam dia. 6-8 cm 43,137.50 27,650.00 70,787.50

1.23 1 Unit Papan Nama biasa


a. Bahan
1.000 Kpg Papan Kayu kls IV 18,150.00 18,150.00 18,150.00
0.050 Kg Paku biasa 1/2"- 1" 32,500.00 1,625.00 1,625.00
1.000 Lbr Plywood 4 mm 82,500.00 82,500.00 82,500.00
0.800 Kg Cat Minyak Mutu C 44,000.00 35,200.00 35,200.00
137,475.00 137,475.00

b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
1.000 Oh Mandor 150,000.00 150,000.00 150,000.00
174,800.00 174,800.00

1 Unit Papan Nama Biasa 137,475.00 174,800.00 312,275.00

1.24 1 Unit Sewa Scafolding


a. Bahan
1.000 bln Scafolding tg. 1,77 m X 1,77 m 52,241.12 52,241.12 52,241.12
52,241.12 52,241.12

b. Upah Bongkar pasang


1.000 Oh Mandor 150,000.00 150,000.00 150,000.00
150,000.00 150,000.00

1 Unit Sewa Scafolding per bulan 52,241.12 150,000.00 202,241.12

II PEKERJAAN TANAH

2.1 1 M3 Galian Tanah Biasa Sedalam 1 Meter


a. Tenaga
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
- - Tukang Gali - - -
- - Kepala Tukang - - -
0.040 Oh Mandor 150,000.00 6,000.00 6,000.00
37,000.00 37,000.00

Jumlah 37,000.00 37,000.00


2.2 1 M3 Galian Tanah Biasa Sedalam 2 Meter
a. Tenaga
0.526 Oh Pekerja 77,500.00 40,765.00 40,765.00
- - Tukang Gali - - -
- - Kepala Tukang - - -
0.052 Oh Mandor 150,000.00 7,800.00 7,800.00
48,565.00 48,565.00

Jumlah 48,565.00 48,565.00

2.3 1 M Galian Tanah Biasa Sedalam 3 Meter


3

a. Tenaga
0.735 Oh Pekerja 77,500.00 56,962.50 56,962.50
- - Tukang Gali - - -
- - Kepala Tukang - - -
0.073 Oh Mandor 150,000.00 10,950.00 10,950.00
67,912.50 67,912.50

Jumlah 67,912.50 67,912.50


2.4 1 M3 Galian Tanah Keras Sedalam 1 Meter
a. Tenaga
0.625 Oh Pekerja 77,500.00 48,437.50 48,437.50
- - Tukang Gali - - -
- - Kepala Tukang - - -
0.062 Oh Mandor 150,000.00 9,300.00 9,300.00
57,737.50 57,737.50

Jumlah 57,737.50 57,737.50


2.5 1 M3 Galian Tanah Cadas Sedalam 1 Meter
a. Tenaga
1.250 Oh Pekerja 77,500.00 96,875.00 96,875.00
- - Tukang Gali - - -
- - Kepala Tukang - - -
0.125 Oh Mandor 150,000.00 18,750.00 18,750.00
115,625.00 115,625.00

Jumlah 115,625.00 115,625.00

2.6 1 M Galian Tanah Lumpur Sedalam 1 Meter


3

a. Tenaga
0.823 Oh Pekerja 77,500.00 63,782.50 63,782.50
- - Tukang Gali - - -
- - Kepala Tukang - - -
0.083 Oh Mandor 150,000.00 12,450.00 12,450.00
76,232.50 76,232.50

Jumlah 76,232.50 76,232.50

2.7 1 M Pekerjaan Stripping Setinggi 1 Meter


2

a. Tenaga
0.050 Oh Pekerja 77,500.00 3,875.00 3,875.00
- - Tukang Gali - - -
- - Kepala Tukang - - -
0.005 Oh Mandor 150,000.00 750.00 750.00
4,625.00 4,625.00

Jumlah 4,625.00 4,625.00

2.8 1 M Pembuangan Tanah Sejauh 150 meter


3

a. Tenaga
0.516 Oh Pekerja 77,500.00 39,990.00 39,990.00
- - Tukang Gali - - -
- - Kepala Tukang - - -
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
47,490.00 47,490.00

Jumlah 47,490.00 47,490.00


2.9 1 M3 Urugan Kembali
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
a. Tenaga
0.192 Oh Pekerja 77,500.00 14,880.00 14,880.00
- - Tukang Gali - - -
- - Kepala Tukang - - -
0.019 Oh Mandor 150,000.00 2,850.00 2,850.00
17,730.00 17,730.00

Jumlah 17,730.00 17,730.00

2.10 1 M3 Pemadatan Tanah


a. Tenaga
0.500 Oh Pekerja 77,500.00 38,750.00 38,750.00
- - Tukang Gali - - -
- - Kepala Tukang - - -
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
46,250.00 46,250.00

Jumlah 46,250.00 46,250.00

2.11 1 M3 Urugan Pasir


a. Bahan
1.200 M3 Pasir Urug 82,500.00 99,000.00 99,000.00
99,000.00 99,000.00

b. Tenaga
0.300 Oh Pekerja 77,500.00 23,250.00 23,250.00
- - Tukang Gali - - -
- - Kepala Tukang - - -
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
24,750.00 24,750.00

Jumlah 99,000.00 24,750.00 123,750.00


2.12 1 M3 Urugan Sirtu
a. Bahan
1.200 M3 Sirtu 88,000.00 105,600.00 105,600.00
105,600.00 105,600.00
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
- Oh Tukang Gali - - -
- Oh Kepala Tukang - - -
0.025 Oh Mandor 150,000.00 3,750.00 3,750.00
23,125.00 23,125.00

Jumlah 105,600.00 23,125.00 128,725.00

2.13 1 M Urugan Koral


3

a. Bahan
1.200 M3 Koral 518,850.62 622,620.74 622,620.74
622,620.74 622,620.74

b. Tenaga
1.000 M3 Upah dan Pemadatan 6,600.00 6,600.00 6,600.00
6,600.00 6,600.00

Jumlah 622,620.74 6,600.00 629,220.74

2.14 1 M Urugan Tanah


3

a. Bahan
1.2000 M3 Tanah Urug 60,500.00 72,600.00 72,600.00
72,600.00 72,600.00

b. Tenaga
0.3000 Pekerja 77,500.00 23,250.00 23,250.00
0.0330 Mandor 150,000.00 4,950.00 4,950.00
28,200.00 28,200.00

Jumlah 72,600.00 28,200.00 100,800.00

III PEKERJAAN PONDASI


3.1 1 M3 Pasang Pondasi Batu Kali, 1 Pc : 1 Ps
a. Bahan
1.100 M3 Batu Belah 15/20 cm / batu kali 385,000.00 423,500.00 423,500.00
392.000 Kg Semen Portland 1,700.00 666,400.00 666,400.00
0.314 M3 Pasir Pasang 118,750.00 37,287.50 37,287.50
1,127,187.50 1,127,187.50

b. Tenaga
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00

Jumlah 1,127,187.50 211,500.00 1,338,687.50

3.2 1 M3 Pasang Pondasi Batu Kali, 1 Pc : 2 Ps


a. Bahan
1.100 M3 Batu Belah 15/20 cm / batu kali 385,000.00 423,500.00 423,500.00
267.000 Kg Semen Portland 1,700.00 453,900.00 453,900.00
0.427 M3 Pasir Pasang 118,750.00 50,706.25 50,706.25
928,106.25 928,106.25

b. Tenaga
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00
Jumlah 928,106.25 211,500.00 1,139,606.25

3.3 1 M Pasang Pondasi Batu Kali, 1 Pc : 2,5 Ps


3

a. Bahan
1.100 M3 Batu Belah 15/20 cm / batu kali 385,000.00 423,500.00 423,500.00
392.000 Kg Semen Portland 1,700.00 666,400.00 666,400.00
0.314 M3 Pasir Pasang 118,750.00 37,287.50 37,287.50
1,127,187.50 1,127,187.50

b. Tenaga
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00

Jumlah 1,127,187.50 211,500.00 1,338,687.50

3.4 1 M3 Pasang Pondasi Batu Kali, 1 Pc : 3 Ps


a. Bahan
1.100 M3 Batu Belah 15/20 cm / batu kali 385,000.00 423,500.00 423,500.00
202.000 Kg Semen Portland 1,700.00 343,400.00 343,400.00
0.485 M3 Pasir Pasang 118,750.00 57,593.75 57,593.75
824,493.75 824,493.75

b. Tenaga
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00

Jumlah 824,493.75 211,500.00 1,035,993.75


3.5 1 M3 Pasang Pondasi Batu Kali, 1 Pc : 4 Ps
a. Bahan
1.100 M3 Batu Belah 15/20 cm / batu kali 385,000.00 423,500.00 423,500.00
163.000 Kg Semen Portland 1,700.00 277,100.00 277,100.00
0.520 M3 Pasir Pasang 118,750.00 61,750.00 61,750.00
762,350.00 762,350.00
b. Tenaga
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00

Jumlah 762,350.00 211,500.00 973,850.00


3.6 1 M3 Pasang Pondasi Batu Kali, 1 Pc : 5 Ps
a. Bahan
1.100 M3 Batu Belah 15/20 cm / batu kali 385,000.00 423,500.00 423,500.00
136.000 Kg Semen Portland 1,700.00 231,200.00 231,200.00
0.544 M3 Pasir Pasang 118,750.00 64,600.00 64,600.00
719,300.00 719,300.00

b. Tenaga
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00

Jumlah 719,300.00 211,500.00 930,800.00

3.7 1 M3 Pasang Pondasi Batu Kali, 1 Pc : 6 Ps


a. Bahan
1.100 M3 Batu Belah 15/20 cm / batu kali 385,000.00 423,500.00 423,500.00
117.000 Kg Semen Portland 1,700.00 198,900.00 198,900.00
0.561 M3 Pasir Pasang 118,750.00 66,618.75 66,618.75
689,018.75 689,018.75

b. Tenaga
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00

Jumlah 689,018.75 211,500.00 900,518.75


3.8 1 M3 Pasang Pondasi Batu Kali, 1 Pc : 8 Ps
a. Bahan
1.100 M3 Batu Belah 15/20 cm / batu kali 385,000.00 423,500.00 423,500.00
91.000 Kg Semen Portland 1,700.00 154,700.00 154,700.00
0.561 M3 Pasir Pasang 118,750.00 66,618.75 66,618.75
644,818.75 644,818.75

b. Tenaga
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00

Jumlah 644,818.75 211,500.00 856,318.75

3.9 1 M Pasang Pondasi Sumuran & 100 cm


3

a. Bahan
0.450 M3 Batu Belah 15/20 cm / batu kali 385,000.00 173,250.00 173,250.00
280.000 Kg Semen Portland 1,700.00 476,000.00 476,000.00
0.450 M3 Pasir Beton 118,750.00 53,437.50 53,437.50
0.670 M3 Koral Beton 518,850.62 347,629.92 347,629.92
1,050,317.42 1,050,317.42

b. Tenaga
2.380 Oh Pekerja 77,500.00 184,450.00 184,450.00
0.300 Oh Tukang Batu 125,000.00 37,500.00 37,500.00
0.030 Oh Kepala Tukang 150,000.00 4,500.00 4,500.00
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
238,450.00 238,450.00

Jumlah 1,050,317.42 238,450.00 1,288,767.42

3.10 1 M Pembuatan Tiang Pancang (40 x 40) cm, Beton Bertulang


'

a. Bahan
0.019 M3 Pasir Urug 82,500.00 1,567.50 1,567.50
0.094 M3 Pasir Beton 118,750.00 11,162.50 11,162.50
0.150 M3 Koral Beton 518,850.62 77,827.59 77,827.59
60.500 Kg Semen Portland 1,700.00 102,850.00 102,850.00
45.000 Kg Besi Beton 12,075.00 543,375.00 543,375.00
0.900 Kg Kawat Beton 19,800.00 17,820.00 17,820.00
0.032 M3 Kayu Kaso 5/7 1,650,000.00 52,800.00 52,800.00
0.120 Kg Paku 28,500.00 3,420.00 3,420.00
0.090 Ltr Minyak Bekisting 13,200.00 1,188.00 1,188.00
0.240 Kg Plamir Tembok 8,800.00 2,112.00 2,112.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
814,122.59 814,122.59

b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
0.670 Oh Tukang Batu 125,000.00 83,750.00 83,750.00
0.067 Oh Kepala Tukang 150,000.00 10,050.00 10,050.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
178,800.00 178,800.00

Jumlah 814,122.59 178,800.00 992,922.59

3.11 1 M' Pembuatan Tiang Pancang (35 x 35) cm, Beton Bertulang
a. Bahan
0.016 M3 Pasir Urug Darat 82,500.00 1,320.00 1,320.00
0.080 M3 Pasir Beton 118,750.00 9,500.00 9,500.00
0.125 M3 Koral Beton 518,850.62 64,856.33 64,856.33
49.000 Kg Semen Portland 1,700.00 83,300.00 83,300.00
34.500 Kg Besi Beton 12,075.00 416,587.50 416,587.50
0.700 Kg Kawat Beton 19,800.00 13,860.00 13,860.00
0.027 M3 Kayu Kaso 5/7 1,650,000.00 44,550.00 44,550.00
0.120 Kg Paku 28,500.00 3,420.00 3,420.00
0.090 Ltr Minyak Bekisting 13,200.00 1,188.00 1,188.00
0.200 Kg Plamir Tembok 8,800.00 1,760.00 1,760.00
640,341.83 640,341.83

b. Tenaga
0.800 Oh Pekerja 77,500.00 62,000.00 62,000.00
0.500 Oh Tukang Batu 125,000.00 62,500.00 62,500.00
0.050 Oh Kepala Tukang 150,000.00 7,500.00 7,500.00
0.040 Oh Mandor 150,000.00 6,000.00 6,000.00
138,000.00 138,000.00

Jumlah 640,341.83 138,000.00 778,341.83

3.12 1 M3 Pas. Pondasi Batu Bata Ad. 1 : 4


a. Bahan
782 Bh Batu Bata Lobang 850.00 664,700.00 664,700.00
2.024 Zak Semen Portland 72,800.00 147,347.20 147,347.20
0.406 M3 Pasir Pasang 118,750.00 48,212.50 48,212.50
860,259.70 860,259.70

b. Tenaga
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00

Jumlah 860,259.70 211,500.00 1,071,759.70

3.13 1 M Pas. Pondasi Batu Bata Ad. 1 : 2


3

a. Bahan
782 Bh Batu Bata Lobang 850.00 664,700.00 664,700.00
3.296 Zak Semen Portland 72,800.00 239,948.80 239,948.80
0.333 M3 Pasir Pasang 118,750.00 39,543.75 39,543.75
944,192.55 944,192.55

b. Tenaga
0.600 Oh Tukang Batu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
1.500 Oh Pekerja 77,500.00 116,250.00 116,250.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
211,500.00 211,500.00

Jumlah 944,192.55 211,500.00 1,155,692.55

IV PEKERJAAN DINDING
4.1 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 1 Ps
a. Bahan
140 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 192,500.00 192,500.00
64.030 Kg Semen Portland 1,700.00 108,851.00 108,851.00
0.059 M3 Pasir Pasang 118,750.00 7,006.25 7,006.25
308,357.25 308,357.25

b. Tenaga
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
82,875.00 82,875.00

Jumlah 308,357.25 82,875.00 391,232.25


4.2 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 2 Ps
a. Bahan
140 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 192,500.00 192,500.00
43.500 Kg Semen Portland 1,700.00 73,950.00 73,950.00
0.080 M3 Pasir Pasang 118,750.00 9,500.00 9,500.00
275,950.00 275,950.00

b. Tenaga
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
82,875.00 82,875.00

Jumlah 275,950.00 82,875.00 358,825.00

4.3 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 3 Ps


a. Bahan
140 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 192,500.00 192,500.00
32.950 Kg Semen Portland 1,700.00 56,015.00 56,015.00
0.091 M3 Pasir Pasang 118,750.00 10,806.25 10,806.25
259,321.25 259,321.25
b. Tenaga
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
82,875.00 82,875.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

Jumlah 259,321.25 82,875.00 342,196.25

4.4 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 4 Ps


a. Bahan
140 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 192,500.00 192,500.00
26.550 Kg Semen Portland 1,700.00 45,135.00 45,135.00
0.093 M3 Pasir Pasang 118,750.00 11,043.75 11,043.75
248,678.75 248,678.75

b. Tenaga
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
82,875.00 82,875.00

Jumlah 248,678.75 82,875.00 331,553.75

4.5 1 M Pasangan Bata Lobang Tebal 1 Bata, 1 Pc : 4 Ps


2

a. Bahan
117 Bh Bata Lobang 9 x 9 x 19 cm 850.00 99,450.00 99,450.00
26.550 Kg Semen Portland 1,700.00 45,135.00 45,135.00
0.093 M3 Pasir Pasang 118,750.00 11,043.75 11,043.75
155,628.75 155,628.75

b. Tenaga
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
82,875.00 82,875.00

Jumlah 155,628.75 82,875.00 238,503.75

4.6 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 5 Ps


a. Bahan
140 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 192,500.00 192,500.00
22.200 Kg Semen Portland 1,700.00 37,740.00 37,740.00
0.102 M3 Pasir Pasang 118,750.00 12,112.50 12,112.50
242,352.50 242,352.50

b. Tenaga
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
82,875.00 82,875.00

Jumlah 242,352.50 82,875.00 325,227.50

4.7 1 M Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 6 Ps


2

a. Bahan
140 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 192,500.00 192,500.00
22.200 Kg Semen Portland 1,700.00 37,740.00 37,740.00
0.102 M3 Pasir Pasang 118,750.00 12,112.50 12,112.50
242,352.50 242,352.50

b. Tenaga
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
82,875.00 82,875.00

Jumlah 242,352.50 82,875.00 325,227.50

4.8 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 1 Ps


a. Bahan
70 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 96,250.00 96,250.00
27.800 Kg Semen Portland 1,700.00 47,260.00 47,260.00
0.0280 M3 Pasir Pasang 118,750.00 3,325.00 3,325.00
146,835.00 146,835.00
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
41,050.00 41,050.00

Jumlah 146,835.00 41,050.00 187,885.00

4.9 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 2 Ps


a. Bahan
70 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 96,250.00 96,250.00
18.950 Kg Semen Portland 1,700.00 32,215.00 32,215.00
0.0380 M3 Pasir Pasang 118,750.00 4,512.50 4,512.50
132,977.50 132,977.50

b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
41,050.00 41,050.00

Jumlah 132,977.50 41,050.00 174,027.50

4.10 1 M2 Pasangan Bata Lobang Tebal 1/2 Bata, 1 Pc : 2 Ps


a. Bahan
58.5 Bh Bata Lobang 9 x 9 x 19 cm 850.00 49,725.00 49,725.00
18.950 Kg Semen Portland 1,700.00 32,215.00 32,215.00
0.0380 M3 Pasir Pasang 118,750.00 4,512.50 4,512.50
86,452.50 86,452.50

b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
41,050.00 41,050.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

Jumlah 86,452.50 41,050.00 127,502.50

4.11 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 3 Ps


a. Bahan
70 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 96,250.00 96,250.00
14.370 Kg Semen Portland 1,700.00 24,429.00 24,429.00
0.0400 M3 Pasir Pasang 118,750.00 4,750.00 4,750.00
125,429.00 125,429.00

b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
41,050.00 41,050.00

Jumlah 125,429.00 41,050.00 166,479.00

4.12 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 4 Ps


a. Bahan
70 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 96,250.00 96,250.00
11.500 Kg Semen Portland 1,700.00 19,550.00 19,550.00
0.0430 M3 Pasir Pasang 118,750.00 5,106.25 5,106.25
120,906.25 120,906.25

b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
41,050.00 41,050.00

Jumlah 120,906.25 41,050.00 161,956.25

4.13 1 M2 Pasangan Bata Lobang Tebal 1/2 Bata, 1 Pc : 4 Ps


a. Bahan
58.5 Bh Bata Lobang 9 x 9 x 19 cm 850.00 49,725.00 49,725.00
11.500 Kg Semen Portland 1,700.00 19,550.00 19,550.00
0.0430 M3 Pasir Pasang 118,750.00 5,106.25 5,106.25
74,381.25 74,381.25
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
41,050.00 41,050.00

Jumlah 74,381.25 41,050.00 115,431.25

4.14 1 M Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 5 Ps


2

a. Bahan
70 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 96,250.00 96,250.00
9.680 Kg Semen Portland 1,700.00 16,456.00 16,456.00
0.0450 M3 Pasir Pasang 118,750.00 5,343.75 5,343.75
118,049.75 118,049.75
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
41,050.00 41,050.00

Jumlah 118,049.75 41,050.00 159,099.75

4.15 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 6 Ps


a. Bahan
70 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 96,250.00 96,250.00
8.320 Kg Semen Portland 1,700.00 14,144.00 14,144.00
0.0490 M3 Pasir Pasang 118,750.00 5,818.75 5,818.75
116,212.75 116,212.75

b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
41,050.00 41,050.00

Jumlah 116,212.75 41,050.00 157,262.75

4.16 1 M Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 8 Ps


2

a. Bahan
70 Bh Bata Merah 5 x 11 x 22 cm 1,375.00 96,250.00 96,250.00
6.500 Kg Semen Portland 1,700.00 11,050.00 11,050.00
0.050 M3 Pasir Pasang 118,750.00 5,937.50 5,937.50
113,237.50 113,237.50

b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
41,050.00 41,050.00

Jumlah 113,237.50 41,050.00 154,287.50

4.17 1 M Pasang Dinding Roster / Terawang ( 12 x 11 x 24 ) cm


2

a. Bahan
36 Bh Roster / Terawang 4,675.00 168,300.00 168,300.00
12.800 Kg Semen Portland 1,700.00 21,760.00 21,760.00
0.035 M3 Pasir Pasang 118,750.00 4,156.25 4,156.25
194,216.25 194,216.25

b. Tenaga
0.300 Oh Pekerja 77,500.00 23,250.00 23,250.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0150 Oh Mandor 150,000.00 2,250.00 2,250.00
39,500.00 39,500.00

Jumlah 194,216.25 39,500.00 233,716.25


SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

4.18 1 M2 Pasangan Bataco


a. Bahan
12.5 Bh Bataco 10 X 20 X 40 2,860.00 35,750.00 35,750.00
0.0194 Zak Semen Portland (PC) 72,800.00 1,412.32 1,412.32
0.0225 M3 Pasir Pasang 118,750.00 2,671.88 2,671.88
39,834.20 39,834.20

b. Tenaga
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.450 Oh Pekerja 77,500.00 34,875.00 34,875.00
55,875.00 55,875.00

Jumlah 39,834.20 55,875.00 95,709.20

V PEKERJAAN PLESTERAN
5.1 1 M2 Plesteran 1 Pc : 1 Ps, Tebal 15 mm
a. Bahan
12.920 Kg Semen Portland 1,700.00 21,964.00 21,964.00
0.013 M3 Pasir Pasang 118,750.00 1,543.75 1,543.75
23,507.75 23,507.75

b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00

Jumlah 23,507.75 38,000.00 61,507.75

5.2 1 M2 Plesteran 1 Pc : 2 Ps, Tebal 15 mm


a. Bahan
8.520 Kg Semen Portland 1,700.00 14,484.00 14,484.00
0.017 M3 Pasir Pasang 118,750.00 2,018.75 2,018.75
16,502.75 16,502.75

b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00

Jumlah 16,502.75 38,000.00 54,502.75


5.3 1 M2 Plesteran 1 Pc : 3 Ps, Tebal 15 mm
a. Bahan
6.480 Kg Semen Portland 1,700.00 11,016.00 11,016.00
0.019 M3 Pasir Pasang 118,750.00 2,256.25 2,256.25
13,272.25 13,272.25

b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00

Jumlah 13,272.25 38,000.00 51,272.25

5.4 1 M Plesteran 1 Pc : 4 Ps, Tebal 15 mm


2

a. Bahan
5.200 Kg Semen Portland 1,700.00 8,840.00 8,840.00
0.020 M3 Pasir Pasang 118,750.00 2,375.00 2,375.00
11,215.00 11,215.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00

Jumlah 11,215.00 38,000.00 49,215.00

5.5 1 M Plesteran 1 Pc : 5 Ps, Tebal 15 mm


2

a. Bahan
4.320 Kg Semen Portland 1,700.00 7,344.00 7,344.00
0.022 M3 Pasir Pasang 118,750.00 2,612.50 2,612.50
9,956.50 9,956.50

b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00

Jumlah 9,956.50 38,000.00 47,956.50

5.6 1 M Plesteran 1 Pc : 6 Ps, Tebal 15 mm


2

a. Bahan
3.680 Kg Semen Portland 1,700.00 6,256.00 6,256.00
0.023 M3 Pasir Pasang 118,750.00 2,731.25 2,731.25
8,987.25 8,987.25
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00

Jumlah 8,987.25 38,000.00 46,987.25

5.7 1 M2 Plesteran 1 Pc : 8 Ps, Tebal 15 mm


a. Bahan
2.880 Kg Semen Portland 1,700.00 4,896.00 4,896.00
0.024 M3 Pasir Pasang 118,750.00 2,850.00 2,850.00
7,746.00 7,746.00
b. Tenaga
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00

Jumlah 7,746.00 38,000.00 45,746.00

5.8 1 M2 Plesteran 1 Pc : 0,5 Kp : 3 Ps, Tebal 15 mm


a. Bahan
5.760 Kg Semen Portland 1,700.00 9,792.00 9,792.00
0.013 M3 Pasir Pasang 118,750.00 1,543.75 1,543.75
11,335.75 11,335.75

b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00

Jumlah 11,335.75 38,000.00 49,335.75

5.9 1 M2 Plesteran 1 Pc : 3 Kp : 10 Ps, Tebal 15 mm


a. Bahan
1.840 Kg Semen Portland 1,700.00 3,128.00 3,128.00
0.014 M3 Pasir Pasang 118,750.00 1,662.50 1,662.50
4,790.50 4,790.50
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00

Jumlah 4,790.50 38,000.00 42,790.50

5.10 1 M2 Plesteran 0,5 Pc : 1 Kp : 4 Ps, Tebal 15 mm


a. Bahan
3.000 Kg Semen Portland 1,700.00 5,100.00 5,100.00
0.019 M3 Pasir Pasang 118,750.00 2,256.25 2,256.25
7,356.25 7,356.25
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00

Jumlah 7,356.25 38,000.00 45,356.25

5.11 1 M Plesteran 1 Kp : 1 Sm : 1 Ps, Tebal 15 mm


2

a. Bahan
0.009 M3 Semen Merah 41,800.00 376.20 376.20
0.009 M3 Pasir Pasang 118,750.00 1,068.75 1,068.75
1,444.95 1,444.95
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00

Jumlah 1,444.95 38,000.00 39,444.95

5.12 1 M Plesteran 1 Kp : 1 Sm : 2 Ps, Tebal 15 mm


2

a. Bahan
0.007 M3 Semen Merah 41,800.00 292.60 292.60
0.015 M3 Pasir Pasang 118,750.00 1,781.25 1,781.25
2,073.85 2,073.85
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.150 Oh Tukang Batu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
38,000.00 38,000.00

Jumlah 2,073.85 38,000.00 40,073.85

5.13 1 M Plesteran 1 Pc : 2 Ps, Tebal 20 mm


2

a. Bahan
14.280 Kg Semen Portland 1,700.00 24,276.00 24,276.00
0.023 M3 Pasir Pasang 118,750.00 2,731.25 2,731.25
27,007.25 27,007.25

b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
49,250.00 49,250.00

Jumlah 27,007.25 49,250.00 76,257.25

5.14 1 M Plesteran 1 Pc : 3 Ps, Tebal 20 mm


2

a. Bahan
10.800 Kg Semen Portland 1,700.00 18,360.00 18,360.00
0.026 M3 Pasir Pasang 118,750.00 3,087.50 3,087.50
21,447.50 21,447.50

b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
49,250.00 49,250.00

Jumlah 21,447.50 49,250.00 70,697.50


SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
5.15 1 M2 Plesteran 1 Pc : 4 Ps, Tebal 20 mm
a. Bahan
8.680 Kg Semen Portland 1,700.00 14,756.00 14,756.00
0.028 M3 Pasir Pasang 118,750.00 3,325.00 3,325.00
18,081.00 18,081.00

b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
49,250.00 49,250.00

Jumlah 18,081.00 49,250.00 67,331.00

5.16 1 M2 Plesteran 1 Pc : 5 Ps, Tebal 20 mm


a. Bahan
7.290 Kg Semen Portland 1,700.00 12,393.00 12,393.00
0.028 M3 Pasir Pasang 118,750.00 3,325.00 3,325.00
15,718.00 15,718.00
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
49,250.00 49,250.00

Jumlah 15,718.00 49,250.00 64,968.00

5.17 1 M2 Plesteran 1 Pc : 6 Ps, Tebal 20 mm


a. Bahan
6.240 Kg Semen Portland 1,700.00 10,608.00 10,608.00
0.030 M3 Pasir Pasang 118,750.00 3,562.50 3,562.50
14,170.50 14,170.50

b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
49,250.00 49,250.00

Jumlah 14,170.50 49,250.00 63,420.50

5.18 1 M Plesteran 1 Kp : 1 Sm : 2 Ps, Tebal 20 mm


2

a. Bahan
0.009 M3 Semen Merah 41,800.00 376.20 376.20
0.018 M3 Pasir Pasang 118,750.00 2,137.50 2,137.50
2,513.70 2,513.70

b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
49,250.00 49,250.00

Jumlah 2,513.70 49,250.00 51,763.70


5.19 1 M2 Berapen 1 Pc : 5 Ps, Tebal 15 mm
a. Bahan
5.670 Kg Semen Portland 1,700.00 9,639.00 9,639.00
0.023 M3 Pasir Pasang 118,750.00 2,731.25 2,731.25
12,370.25 12,370.25
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.070 Oh Tukang Batu 125,000.00 8,750.00 8,750.00
0.007 Oh Kepala Tukang 150,000.00 1,050.00 1,050.00
0.008 Oh Mandor 150,000.00 1,200.00 1,200.00
22,625.00 22,625.00

Jumlah 12,370.25 22,625.00 34,995.25

5.20 1 M Plesteran Beton 1 Pc : 2 Ps, Tebal 15 mm


2

a. Bahan
9.300 Kg Semen Portland 1,700.00 15,810.00 15,810.00
0.018 M3 Pasir Pasang 118,750.00 2,137.50 2,137.50
17,947.50 17,947.50

b. Tenaga
0.260 Oh Pekerja 77,500.00 20,150.00 20,150.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.013 Oh Mandor 150,000.00 1,950.00 1,950.00
50,100.00 50,100.00

Jumlah 17,947.50 50,100.00 68,047.50

5.21 1 M Plesteran Beton 1 Pc : 3 Ps, Tebal 15 mm


2

a. Bahan
7.070 Kg Semen Portland 1,700.00 12,019.00 12,019.00
0.021 M3 Pasir Pasang 118,750.00 2,493.75 2,493.75
14,512.75 14,512.75
b. Tenaga
0.260 Oh Pekerja 77,500.00 20,150.00 20,150.00
0.200 Oh Tukang Batu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.013 Oh Mandor 150,000.00 1,950.00 1,950.00
50,100.00 50,100.00

Jumlah 14,512.75 50,100.00 64,612.75

5.22 1 M Plesteran Ciprat 1 Pc : 2 Ps


2

a. Bahan
4.320 Kg Semen Portland 1,700.00 7,344.00 7,344.00
0.016 M3 Pasir Pasang 118,750.00 1,900.00 1,900.00
9,244.00 9,244.00
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.015 Oh Mandor 150,000.00 2,250.00 2,250.00
35,625.00 35,625.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

Jumlah 9,244.00 35,625.00 44,869.00

5.23 1 M2 Plesteran Siar Adukan 1 Pc : 2 Ps


a. Bahan
4.320 Kg Semen Portland 1,700.00 7,344.00 7,344.00
0.016 M3 Pasir Pasang 118,750.00 1,900.00 1,900.00
9,244.00 9,244.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.070 Oh Tukang Batu 125,000.00 8,750.00 8,750.00
0.007 Oh Kepala Tukang 150,000.00 1,050.00 1,050.00
0.008 Oh Mandor 150,000.00 1,200.00 1,200.00
22,625.00 22,625.00

Jumlah 9,244.00 22,625.00 31,869.00


5.24 1 M3 Perekat
a. Bahan
10.588 Zak Semen Portland 72,800.00 770,806.40 770,806.40
1.080 M3 Pasir Pasang 118,750.00 128,250.00 128,250.00
899,056.40 899,056.40

Jumlah 899,056.40 899,056.40

5.25 1 M' Plesteran dibentuk Profil uk. 10 x 10 cm


a. Bahan
0.060 Kg Semen Portland 72,800.00 4,368.00 4,368.00
0.024 M3 Pasir Pasang 118,750.00 2,850.00 2,850.00
7,218.00 7,218.00
b. Tenaga
1.200 Oh Tukang Batu 125,000.00 150,000.00 150,000.00
0.120 Oh Kepala Tukang 150,000.00 18,000.00 18,000.00
0.600 Oh Pekerja 77,500.00 46,500.00 46,500.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
219,000.00 219,000.00

Jumlah 7,218.00 219,000.00 226,218.00

VI PEKERJAAN KAYU

6.1 1 M3 Pasang Kusen Pintu dan Jendela K.kls. I (Kayu Jati, Unglen)
a. Bahan
1.100 M3 Kayu Jati, Balok ( Kayu kelas I) 9,075,000.00 9,982,500.00 9,982,500.00
9,982,500.00 9,982,500.00
b. Tenaga
6.000 Oh Pekerja 77,500.00 465,000.00 465,000.00
20.000 Oh Tukang Kayu 125,000.00 2,500,000.00 2,500,000.00
2.000 Oh Kepala Tukang 150,000.00 300,000.00 300,000.00
0.300 Oh Mandor 150,000.00 45,000.00 45,000.00
3,310,000.00 3,310,000.00

Jumlah 9,982,500.00 3,310,000.00 13,292,500.00

6.2 1 M3 Pasang Kusen Pintu dan Jendela Kayu Kls. II


a. Bahan
1.200 M3 Kayu Kelas II+C1434 6,600,000.00 7,920,000.00 7,920,000.00
7,920,000.00 7,920,000.00

b. Tenaga
6.000 Oh Pekerja 77,500.00 465,000.00 465,000.00
18.000 Oh Tukang Kayu 125,000.00 2,250,000.00 2,250,000.00
2.000 Oh Kepala Tukang 150,000.00 300,000.00 300,000.00
0.300 Oh Mandor 150,000.00 45,000.00 45,000.00
3,060,000.00 3,060,000.00

Jumlah 7,920,000.00 3,060,000.00 10,980,000.00

6.3 1 M Pasang Kusen Pintu dan Jendela Kayu Kelas III


3

a. Bahan
1.200 M3 Kayu Kls. III 3,630,000.00 4,356,000.00 4,356,000.00
4,356,000.00 4,356,000.00

b. Tenaga
6.000 Oh Pekerja 77,500.00 465,000.00 465,000.00
18.000 Oh Tukang Kayu 125,000.00 2,250,000.00 2,250,000.00
2.000 Oh Kepala Tukang 150,000.00 300,000.00 300,000.00
0.300 Oh Mandor 150,000.00 45,000.00 45,000.00
3,060,000.00 3,060,000.00

Jumlah 4,356,000.00 3,060,000.00 7,416,000.00

6.4 1 M Pasang Pintu Klam Kayu Kls. III


2

a. Bahan
0.036 M3 Kayu Kls. III 3,630,000.00 130,680.00 130,680.00
0.050 Kg Paku Biasa 2" - 5" 28,500.00 1,425.00 1,425.00
132,105.00 132,105.00

b. Tenaga
0.350 Oh Pekerja 77,500.00 27,125.00 27,125.00
1.050 Oh Tukang Kayu 125,000.00 131,250.00 131,250.00
0.105 Oh Kepala Tukang 150,000.00 15,750.00 15,750.00
0.018 Oh Mandor 150,000.00 2,700.00 2,700.00
176,825.00 176,825.00

Jumlah 132,105.00 176,825.00 308,930.00


6.5 1 M2 Pasang Pintu Klam Kayu Kls. IV
a. Bahan
0.036 M3 Kayu Kls. IV 1,650,000.00 59,400.00 59,400.00
0.050 Kg Paku Biasa 2" - 5" 28,500.00 1,425.00 1,425.00
60,825.00 60,825.00

b. Tenaga
0.350 Oh Pekerja 77,500.00 27,125.00 27,125.00
1.050 Oh Tukang Kayu 125,000.00 131,250.00 131,250.00
0.105 Oh Kepala Tukang 150,000.00 15,750.00 15,750.00
0.018 Oh Mandor 150,000.00 2,700.00 2,700.00
176,825.00 176,825.00

Jumlah 60,825.00 176,825.00 237,650.00

6.6 1 M2 Pasang Pintu Panel Kayu Jati


a. Bahan
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.040 M3 Kayu Jati, Papan 9,075,000.00 363,000.00 363,000.00
363,000.00 363,000.00

b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
2.500 Oh Tukang Kayu 125,000.00 312,500.00 312,500.00
0.250 Oh Kepala Tukang 150,000.00 37,500.00 37,500.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
435,000.00 435,000.00

Jumlah 363,000.00 435,000.00 798,000.00

6.7 1 M2 Pasang Pintu Panel Kayu Kls. II


a. Bahan
0.040 M3 Kayu Kls. II 6,600,000.00 264,000.00 264,000.00
264,000.00 264,000.00

b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
2.500 Oh Tukang Kayu 125,000.00 312,500.00 312,500.00
0.250 Oh Kepala Tukang 150,000.00 37,500.00 37,500.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
435,000.00 435,000.00

Jumlah 264,000.00 435,000.00 699,000.00

6.8 1 M2 Pasang Pintu dan Jendela Kaca Kayu Jati


a. Bahan
0.035 M3 Kayu Jati, 9,075,000.00 317,625.00 317,625.00
317,625.00 317,625.00

b. Tenaga
0.800 Oh Pekerja 77,500.00 62,000.00 62,000.00
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
0.200 Oh Kepala Tukang 150,000.00 30,000.00 30,000.00
0.040 Oh Mandor 150,000.00 6,000.00 6,000.00
348,000.00 348,000.00

Jumlah 317,625.00 348,000.00 665,625.00

6.9 1 M2 Pasang Pintu dan Jendela Kaca Kayu Kls. II


a. Bahan
0.035 M3 Kayu Kls. II 6,600,000.00 231,000.00 231,000.00
231,000.00 231,000.00

b. Tenaga
0.800 Oh Pekerja 77,500.00 62,000.00 62,000.00
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
0.200 Oh Kepala Tukang 150,000.00 30,000.00 30,000.00
0.040 Oh Mandor 150,000.00 6,000.00 6,000.00
348,000.00 348,000.00

Jumlah 231,000.00 348,000.00 579,000.00

6.10 1 M2 Pasang Pintu dan Jendela Kaca Kayu Kls. III


a. Bahan
0.035 M3 Kayu Kls. III 3,630,000.00 127,050.00 127,050.00
127,050.00 127,050.00

b. Tenaga
0.800 Oh Pekerja 77,500.00 62,000.00 62,000.00
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
0.200 Oh Kepala Tukang 150,000.00 30,000.00 30,000.00
0.040 Oh Mandor 150,000.00 6,000.00 6,000.00
348,000.00 348,000.00

Jumlah 127,050.00 348,000.00 475,050.00

6.11 1 M2 Pasang Pintu dan Jendela Jalusi Kayu Jati


a. Bahan
0.064 M3 Kayu Jati, Papan 9,075,000.00 580,800.00 580,800.00
580,800.00 580,800.00

b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
3.000 Oh Tukang Kayu 125,000.00 375,000.00 375,000.00
0.300 Oh Kepala Tukang 150,000.00 45,000.00 45,000.00
0.300 Oh Mandor 150,000.00 45,000.00 45,000.00
542,500.00 542,500.00

Jumlah 580,800.00 542,500.00 1,123,300.00

6.12 1 M2 Pasang Pintu dan Jendela Jalusi Kayu Kls. II


a. Bahan
0.064 M3 Kayu Kls. II 6,600,000.00 422,400.00 422,400.00
422,400.00 422,400.00

b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
3.000 Oh Tukang Kayu 125,000.00 375,000.00 375,000.00
0.300 Oh Kepala Tukang 150,000.00 45,000.00 45,000.00
0.500 Oh Mandor 150,000.00 75,000.00 75,000.00
572,500.00 572,500.00

Jumlah 422,400.00 572,500.00 994,900.00

6.13 1 M2 Pasang Pintu Plywood Rangkap, Rangka Kayu Jati


a. Bahan
0.0196 M3 Kayu Jati, Papan 9,075,000.00 177,870.00 177,870.00
0.030 Kg Paku Biasa /2" - 1"
1
32,500.00 975.00 975.00
0.300 Ltr Lem Kayu 22,000.00 6,600.00 6,600.00
1.000 Lbr Plywood 4' x 8' x 4 mm 82,500.00 82,500.00 82,500.00
267,945.00 267,945.00
b. Tenaga
0.600 Oh Pekerja 77,500.00 46,500.00 46,500.00
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
0.200 Oh Kepala Tukang 150,000.00 30,000.00 30,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
331,000.00 331,000.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

Jumlah 267,945.00 331,000.00 598,945.00

6.14 1 M2 Pasang Pintu Plywood Rangkap, Rangka Kayu Kls. II


a. Bahan
0.0196 M3 Kayu Kls. II 6,600,000.00 129,360.00 129,360.00
0.030 Kg Paku Biasa /2" - 1"
1
32,500.00 975.00 975.00
0.300 Ltr Lem Kayu 22,000.00 6,600.00 6,600.00
1.000 Lbr Plywood 4' x 8' x 4 mm 82,500.00 82,500.00 82,500.00
219,435.00 219,435.00

b. Tenaga
0.600 Oh Pekerja 77,500.00 46,500.00 46,500.00
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
0.200 Oh Kepala Tukang 150,000.00 30,000.00 30,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
331,000.00 331,000.00
Jumlah 219,435.00 331,000.00 550,435.00

6.15 1 M Daun Pintu Plywood Sungkay rangkap, kayu kls. II


2

a. Bahan
0.0196 M3 Kayu Kelas II 6,600,000.00 129,360.00 129,360.00
1.000 Lbr Plywood Sungkai 3 mm 121,000.00 121,000.00 121,000.00
0.300 Ltr Lem Kayu 22,000.00 6,600.00 6,600.00
0.030 Kg Paku Biasa /2" - 1"
1
32,500.00 975.00 975.00
257,935.00 257,935.00
b. Tenaga
2.000 Oh Tukang Kayu 125,000.00 250,000.00 250,000.00
0.200 Oh Kepala Tukang 150,000.00 30,000.00 30,000.00
0.600 Oh Pekerja 77,500.00 46,500.00 46,500.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
331,000.00 331,000.00

Jumlah 257,935.00 331,000.00 588,935.00

6.16 1 M3 Pasang Konstruksi Kuda-kuda Kayu Jati


a. Bahan
1.100 M3 Kayu Jati, Balok 9,075,000.00 9,982,500.00 9,982,500.00
15.000 Kg Besi Strip 11,000.00 165,000.00 165,000.00
0.800 Kg Paku Biasa 2" - 5" 28,500.00 22,800.00 22,800.00
10,170,300.00 10,170,300.00
b. Tenaga
4.000 Oh Pekerja 77,500.00 310,000.00 310,000.00
12.000 Oh Tukang Kayu 125,000.00 1,500,000.00 1,500,000.00
1.200 Oh Kepala Tukang 150,000.00 180,000.00 180,000.00
0.200 Oh Mandor 150,000.00 30,000.00 30,000.00
2,020,000.00 2,020,000.00

Jumlah 10,170,300.00 2,020,000.00 12,190,300.00

6.17 1 M Pasang Konstruksi Kuda-kuda Kayu Kls. II


3

a. Bahan
1.100 M3 Kayu Kelas II, Balok 6,600,000.00 7,260,000.00 7,260,000.00
15 Kg Besi Strip 11,000.00 165,000.00 165,000.00
0.800 Kg Paku Biasa 2" - 5" 28,500.00 22,800.00 22,800.00
7,447,800.00 7,447,800.00
b. Tenaga
4.000 Oh Pekerja 77,500.00 310,000.00 310,000.00
12.000 Oh Tukang Kayu 125,000.00 1,500,000.00 1,500,000.00
1.200 Oh Kepala Tukang 150,000.00 180,000.00 180,000.00
0.200 Oh Mandor 150,000.00 30,000.00 30,000.00
2,020,000.00 2,020,000.00

Jumlah 7,447,800.00 2,020,000.00 9,467,800.00

6.18 1 M3 Pasang Konstruksi Kuda-kuda Kayu Kls. III


a. Bahan
1.100 M3 Kayu Kls. III, Balok 3,630,000.00 3,993,000.00 3,993,000.00
15.000 Kg Besi Strip 11,000.00 165,000.00 165,000.00
0.800 Kg Paku Biasa 2" - 5" 28,500.00 22,800.00 22,800.00
4,180,800.00 4,180,800.00
b. Tenaga
4.000 Oh Pekerja 77,500.00 310,000.00 310,000.00
12.000 Oh Tukang Kayu 125,000.00 1,500,000.00 1,500,000.00
1.200 Oh Kepala Tukang 150,000.00 180,000.00 180,000.00
0.200 Oh Mandor 150,000.00 30,000.00 30,000.00
2,020,000.00 2,020,000.00

Jumlah 4,180,800.00 2,020,000.00 6,200,800.00

6.19 1 M Pasang Kaso + Reng Genteng Kayu Kls. III


2

a. Bahan
0.012 M3 Kayu Kelas III, Untuk genteng kodok/biasa 3,630,000.00 43,560.00 43,560.00
0.014 M3 Kayu Kelas III, untuk genteng beton/keramik 3,630,000.00 50,820.00 50,820.00
0.150 Kg Paku Biasa 2" - 5" 28,500.00 4,275.00 4,275.00
kayu kls. III, untuk genteng kodok/biasa 47,835.00 47,835.00
kayu kls. III, untuk genteng beton 55,095.00 55,095.00

b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.005 Oh Mandor 150,000.00 750.00 750.00
22,500.00 22,500.00
kayu kls. III, untuk genteng kodok/biasa 47,835.00 22,500.00 70,335.00
kayu kls. III, untuk genteng beton 55,095.00 22,500.00 77,595.00

6.20 1 M2 Pasang Kaso + Reng Genteng Kayu Kls. II


a. Bahan
0.012 M3 Kayu Kelas II, Untuk genteng kodok/biasa 6,600,000.00 79,200.00 79,200.00
0.014 M3 Kayu Kelas II, untuk genteng beton/keramik 6,600,000.00 92,400.00 92,400.00
0.150 Kg Paku Biasa 2" - 5" 28,500.00 4,275.00 4,275.00
kayu kls. II, untuk genteng kodok/biasa 83,475.00 83,475.00
kayu kls. II, untuk genteng beton 96,675.00 96,675.00
b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.005 Oh Mandor 150,000.00 750.00 750.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
22,500.00 22,500.00
kayu kls. II, untuk genteng kodok/biasa 83,475.00 22,500.00 105,975.00
kayu kls. II, untuk genteng beton 96,675.00 22,500.00 119,175.00

6.21 1 M2 Pasang Kaso + Reng Atap Sirap,seng/asbes Kayu Kls. II


a. Bahan
0.0165 M3 Kayu Kls. II, untuk sirap 6,600,000.00 108,900.00 108,900.00
0.0100 M3 Kayu Kls. II, untuk seng dan asbes 6,600,000.00 66,000.00 66,000.00
0.200 Kg Paku Biasa 2" - 5" 28,500.00 5,700.00 5,700.00
kayu kls. II, untuk sirap 114,600.00 114,600.00
kayu kls. II, untuk seng/asbes 71,700.00 71,700.00
b. Tenaga
0.120 Oh Pekerja 77,500.00 9,300.00 9,300.00
0.120 Oh Tukang Kayu 125,000.00 15,000.00 15,000.00
0.012 Oh Kepala Tukang 150,000.00 1,800.00 1,800.00
0.006 Oh Mandor 150,000.00 900.00 900.00
27,000.00 27,000.00
kayu kls. II, untuk sirap 114,600.00 27,000.00 141,600.00
kayu kls. II, untuk seng/asbes 71,700.00 27,000.00 98,700.00

6.22 1 M2 Pasang Kaso + Reng Atap Sirap,seng/asbes Kayu Kls. III


a. Bahan
0.0165 M3 Kayu Kls. III, Untuk sirap 3,630,000.00 59,895.00 59,895.00
0.0100 M3 Kayu Kls. III, untuk seng dan asbes 3,630,000.00 36,300.00 36,300.00
0.200 Kg Paku Biasa 2" - 5" 28,500.00 5,700.00 5,700.00
kayu kls. III, untuk sirap 65,595.00 65,595.00
kayu kls. III, untuk seng/asbes 42,000.00 42,000.00
b. Tenaga
0.120 Oh Pekerja 77,500.00 9,300.00 9,300.00
0.120 Oh Tukang Kayu 125,000.00 15,000.00 15,000.00
0.012 Oh Kepala Tukang 150,000.00 1,800.00 1,800.00
0.006 Oh Mandor 150,000.00 900.00 900.00
27,000.00 27,000.00
kayu kls. III, untuk sirap 65,595.00 27,000.00 92,595.00
kayu kls. III, untuk seng/asbes 42,000.00 27,000.00 69,000.00

6.23 1 M2 Pasang Rangka Langit-langit (1,00 x 1,00) m, Kayu Jati


a. Bahan
0.012 M3 Kayu Jati, Unglen 9,075,000.00 108,900.00 108,900.00
0.100 Kg Paku Biasa 2" - 5" 28,500.00 2,850.00 2,850.00
111,750.00 111,750.00

b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.250 Oh Tukang Kayu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
57,875.00 57,875.00

Jumlah 111,750.00 57,875.00 169,625.00

6.24 1 M Pasang Rangka Langit-langit (1,00 x 1,00) m, Kayu Kls. II


2

a. Bahan
0.012 M3 Kayu Kls. II 6,600,000.00 79,200.00 79,200.00
0.100 Kg Paku Biasa 2" - 5" 28,500.00 2,850.00 2,850.00
82,050.00 82,050.00

b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.250 Oh Tukang Kayu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
57,875.00 57,875.00

Jumlah 82,050.00 57,875.00 139,925.00

6.25 1 M2 Pasang Rangka Langit-langit (1,00 x 1,00) m, Kayu Kls. III


a. Bahan
0.012 M3 Kayu Kls. III, Balok 3,630,000.00 43,560.00 43,560.00
0.100 Kg Paku Biasa 2" - 5" 28,500.00 2,850.00 2,850.00
46,410.00 46,410.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.250 Oh Tukang Kayu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
57,875.00 57,875.00

Jumlah 46,410.00 57,875.00 104,285.00

6.26 1 M Pasang Rangka Langit-langit (30 x 60) cm, Kayu Jati


2

a. Bahan
0.023 M3 Kayu Jati, Balok 9,075,000.00 208,725.00 208,725.00
0.150 Kg Paku Biasa 2" - 5" 28,500.00 4,275.00 4,275.00
213,000.00 213,000.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.300 Oh Tukang Kayu 125,000.00 37,500.00 37,500.00
0.030 Oh Kepala Tukang 150,000.00 4,500.00 4,500.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
59,000.00 59,000.00

Jumlah 213,000.00 59,000.00 272,000.00

6.27 1 M Pasang Rangka Langit-langit (30 x 60) cm, Kayu Kls. II


2

a. Bahan
0.023 M3 Kayu Kls. II 6,600,000.00 151,800.00 151,800.00
0.150 Kg Paku Biasa 2" - 5" 28,500.00 4,275.00 4,275.00
156,075.00 156,075.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.300 Oh Tukang Kayu 125,000.00 37,500.00 37,500.00
0.030 Oh Kepala Tukang 150,000.00 4,500.00 4,500.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
59,000.00 59,000.00

Jumlah 156,075.00 59,000.00 215,075.00

6.28 1 M2 Pasang Rangka Langit-langit (30 x 60) m, Kayu Kls. III


a. Bahan
0.023 M3 Kayu Kls. III 3,630,000.00 83,490.00 83,490.00
0.150 Kg Paku Biasa 2" - 5" 28,500.00 4,275.00 4,275.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
87,765.00 87,765.00

b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.300 Oh Tukang Kayu 125,000.00 37,500.00 37,500.00
0.030 Oh Kepala Tukang 150,000.00 4,500.00 4,500.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
59,000.00 59,000.00

Jumlah 87,765.00 59,000.00 146,765.00

6.29 1 M2 Pasang Rangka Langit-langit (30 x 30) cm, Kayu Jati


a. Bahan
0.027 M3 Kayu Jati, Balok 9,075,000.00 245,025.00 245,025.00
0.200 Kg Paku Biasa 2" - 5" 28,500.00 5,700.00 5,700.00
250,725.00 250,725.00

b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.350 Oh Tukang Kayu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
70,250.00 70,250.00

Jumlah 250,725.00 70,250.00 320,975.00

6.30 1 M2 Pasang Rangka Langit-langit (30 x 30) cm, Kayu Kls. II


a. Bahan
0.027 M3 Kayu Kls. II 6,600,000.00 178,200.00 178,200.00
0.200 Kg Paku Biasa 2" - 5" 28,500.00 5,700.00 5,700.00
183,900.00 183,900.00

b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.350 Oh Tukang Kayu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
70,250.00 70,250.00

Jumlah 183,900.00 70,250.00 254,150.00

6.31 1 M2 Pasang Rangka Langit-langit (30 x 30) m, Kayu Kls. III


a. Bahan
0.027 M3 Kayu Kls. III 3,630,000.00 98,010.00 98,010.00
0.200 Kg Paku Biasa 2" - 5" 28,500.00 5,700.00 5,700.00
103,710.00 103,710.00
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.350 Oh Tukang Kayu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
70,250.00 70,250.00

Jumlah 103,710.00 70,250.00 173,960.00

6.32 1 M' Pasang Lisplang Ukuran (3 x 20) cm, Kayu Jati


a. Bahan
0.0072 M3 Kayu Jati, Papan 9,075,000.00 65,340.00 65,340.00
0.050 Kg Paku Biasa 2" - 5" 28,500.00 1,425.00 1,425.00
66,765.00 66,765.00
b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.0050 Oh Mandor 150,000.00 750.00 750.00
37,250.00 37,250.00

Jumlah 66,765.00 37,250.00 104,015.00

6.33 1 M' Pasang Lisplang Ukuran (3 x 20) cm, Kayu Kls. II


a. Bahan
0.0072 M3 Kayu Kls. II 6,600,000.00 47,520.00 47,520.00
0.050 Kg Paku Biasa 2" - 5" 28,500.00 1,425.00 1,425.00
48,945.00 48,945.00

b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.0050 Oh Mandor 150,000.00 750.00 750.00
37,250.00 37,250.00

Jumlah 48,945.00 37,250.00 86,195.00

6.34 1 M' Pasang Lisplang Ukuran (3 x 30) cm, Kayu Jati


a. Bahan
0.011 M3 Kayu Jati, Papan 9,075,000.00 99,825.00 99,825.00
0.050 Kg Paku Biasa 2" - 5" 28,500.00 1,425.00 1,425.00
101,250.00 101,250.00
b. Tenaga
0.110 Oh Pekerja 77,500.00 8,525.00 8,525.00
0.220 Oh Tukang Kayu 125,000.00 27,500.00 27,500.00
0.022 Oh Kepala Tukang 150,000.00 3,300.00 3,300.00
0.005 Oh Mandor 150,000.00 750.00 750.00
40,075.00 40,075.00

Jumlah 101,250.00 40,075.00 141,325.00

6.35 1 M' Pasang Lisplang Ukuran (3 x 30) cm, Kayu Kls. II


a. Bahan
0.011 M3 Kayu Kls. II 6,600,000.00 72,600.00 72,600.00
0.050 Kg Paku Biasa 2" - 5" 28,500.00 1,425.00 1,425.00
74,025.00 74,025.00

b. Tenaga
0.110 Oh Pekerja 77,500.00 8,525.00 8,525.00
0.220 Oh Tukang Kayu 125,000.00 27,500.00 27,500.00
0.022 Oh Kepala Tukang 150,000.00 3,300.00 3,300.00
0.005 Oh Mandor 150,000.00 750.00 750.00
40,075.00 40,075.00

Jumlah 74,025.00 40,075.00 114,100.00


SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

6.36 1 M' Pasang Lisplang Ukuran 2 x (3 x 20) cm, Kayu Kls.II


a. Bahan
0.0145 M3 Kayu Kls.II 6,600,000.00 95,700.00 95,700.00
0.060 Kg Paku Biasa 2" - 5" 28,500.00 1,710.00 1,710.00
97,410.00 97,410.00

b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.250 Oh Tukang Kayu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
57,875.00 57,875.00

Jumlah 97,410.00 57,875.00 155,285.00

6.37 1 M' Pasang Lisplang Ukuran 2 x (2 x 20) cm, Kayu Kls. II


a. Bahan
0.0086 M3 Kayu Kls. II 6,600,000.00 56,760.00 56,760.00
0.060 Kg Paku Biasa 2" - 5" 28,500.00 1,710.00 1,710.00
58,470.00 58,470.00

b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
29,250.00 29,250.00

Jumlah 58,470.00 29,250.00 87,720.00

6.38 1 M' Pasang Lisplang Ukuran 2 x (2 x 20) cm, Kayu Kls. III
a. Bahan
0.0088 M3 Kayu Kls. III 3,630,000.00 31,944.00 31,944.00
0.060 Kg Paku Biasa 2" - 5" 28,500.00 1,710.00 1,710.00
33,654.00 33,654.00

b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
29,250.00 29,250.00

Jumlah 33,654.00 29,250.00 62,904.00

6.39 1 M Pasang Rangka Dinding Pemisah + Papan Kayu Kls. II


2

a. Bahan
0.0195 M3 Kayu Kls. II, Balok 6,600,000.00 128,700.00 128,700.00
0.007 M3 Kayu Kls.II, Papan 6,600,000.00 46,200.00 46,200.00
0.100 Kg Paku Biasa 2" - 5" 28,500.00 2,850.00 2,850.00
177,750.00 177,750.00

b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.450 Oh Tukang Kayu 125,000.00 56,250.00 56,250.00
0.045 Oh Kepala Tukang 150,000.00 6,750.00 6,750.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
85,875.00 85,875.00

Jumlah 177,750.00 85,875.00 263,625.00

6.40 1 M Pasang Rangka Dinding Pemisah + Papan Kayu Kls. III


2

a. Bahan
0.0195 M3 Kayu Kls. III, Balok 3,630,000.00 70,785.00 70,785.00
0.007 M3 Kayu Kls. III, Papan 3,630,000.00 25,410.00 25,410.00
0.100 Kg Paku Biasa 2" - 5" 28,500.00 2,850.00 2,850.00
99,045.00 99,045.00

b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.450 Oh Tukang Kayu 125,000.00 56,250.00 56,250.00
0.045 Oh Kepala Tukang 150,000.00 6,750.00 6,750.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
85,875.00 85,875.00

Jumlah 99,045.00 85,875.00 184,920.00

6.41 1 M Pasang Dinding Pemisah Teakwood Rangkap, Rangka Kayu kls. II


2

a. Bahan
0.0195 M3 Kayu Kls. II, Balok 6,600,000.00 128,700.00 128,700.00
0.007 M3 Kayu Kls. II, Papan 6,600,000.00 46,200.00 46,200.00
0.100 Kg Paku Biasa 2" - 5" 28,500.00 2,850.00 2,850.00
177,750.00 177,750.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.450 Oh Tukang Kayu 125,000.00 56,250.00 56,250.00
0.045 Oh Kepala Tukang 150,000.00 6,750.00 6,750.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
85,875.00 85,875.00

Jumlah 177,750.00 85,875.00 263,625.00

6.42 1 M Pasang Dinding Pemisah Plywood Rangkap, Rangka Kayu Kelas III
2

a. Bahan
0.0195 M3 Kayu Kelas III, Balok 3,630,000.00 70,785.00 70,785.00
0.007 M3 Kayu Kelas III, Papan 3,630,000.00 25,410.00 25,410.00
0.100 Kg Paku Biasa 2" - 5" 28,500.00 2,850.00 2,850.00
0.560 Ltr Lem Kayu 22,000.00 12,320.00 12,320.00
1.000 Lbr Plywood 4' x 8' x 4 mm 82,500.00 82,500.00 82,500.00
193,865.00 193,865.00

b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.600 Oh Tukang Kayu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
101,000.00 101,000.00

Jumlah 193,865.00 101,000.00 294,865.00


SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

6.43 1 M2 Pasang Dinding Lambriziring Dari Papan Jati


a. Bahan
0.007 M3 Kayu Jati, Balok 9,075,000.00 63,525.00 63,525.00
0.100 Kg Paku Biasa 2" - 5" 28,500.00 2,850.00 2,850.00
0.150 Kg Paku Skrup 3,5" 63,500.00 9,525.00 9,525.00
75,900.00 75,900.00
b. Tenaga
0.600 Oh Pekerja 77,500.00 46,500.00 46,500.00
1.800 Oh Tukang Kayu 125,000.00 225,000.00 225,000.00
0.180 Oh Kepala Tukang 150,000.00 27,000.00 27,000.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
303,000.00 303,000.00

Jumlah 75,900.00 303,000.00 378,900.00


6.44 1 M2 Pasang Plywood Tebal 4 mm, Untuk Dinding
a. Bahan
0.400 Lbr Plywood 4' x 8' x 4 mm 82,500.00 33,000.00 33,000.00
0.050 Kg Paku Biasa /2" - 1"
1
32,500.00 1,625.00 1,625.00
34,625.00 34,625.00
b. Tenaga
0.025 Oh Pekerja 77,500.00 1,937.50 1,937.50
0.075 Oh Tukang Kayu 125,000.00 9,375.00 9,375.00
0.0075 Oh Kepala Tukang 150,000.00 1,125.00 1,125.00
0.0013 Oh Mandor 150,000.00 195.00 195.00
12,632.50 12,632.50

Jumlah 34,625.00 12,632.50 47,257.50

6.45 1 M' Pasang List Plafond Kayu Profil


a. Bahan
1.050 M' Kayu Profil kecil 2,750.00 2,887.50 2,887.50
1.050 M' Kayu Profil sedang 3,850.00 4,042.50 4,042.50
1.050 M' Kayu Profil besar 8,250.00 8,662.50 8,662.50
Kayu Profil kecil 2,887.50 2,887.50
Kayu Profil sedang 4,042.50 4,042.50
Kayu Profil besar 8,662.50 8,662.50
b. Tenaga
0.021 Oh Pekerja 77,500.00 1,627.50 1,627.50
0.021 Oh Tukang Kayu 125,000.00 2,625.00 2,625.00
0.002 Oh Kepala Tukang 150,000.00 300.00 300.00
0.001 Oh Mandor 150,000.00 150.00 150.00
4,702.50 4,702.50

Kayu Profil kecil 2,887.50 4,702.50 7,590.00


Kayu Profil sedang 4,042.50 4,702.50 8,745.00
Kayu Profil Besar 8,662.50 4,702.50 13,365.00

6.46 1 M2 Pasang Interior Display lapis plywood Sungkay + politur


a. Bahan
0.36 Kpg Plywood Sungkay 3 mm 121,000.00 43,560.00 43,560.00
0.36 Kpg Plywood 4 mm 82,500.00 29,700.00 29,700.00
0.600 Kg Lem Vinyl 9,350.00 5,610.00 5,610.00
0.150 Ltr Politur dasar 53,900.00 8,085.00 8,085.00
0.372 Ltr Politur jadi 58,300.00 21,687.60 21,687.60
2.000 Lbr Amplas 3,850.00 7,700.00 7,700.00
0.220 Kg Paku Biasa 28,500.00 6,270.00 6,270.00
122,612.60 122,612.60
b. Tenaga
0.145 Oh Tukang Cat 125,000.00 18125 18,125.00
0.008 Oh Kepala Tukang 150,000.00 1200 1,200.00
0.110 Oh Pekerja 77,500.00 8525 8,525.00
0.005 Oh Mandor 150,000.00 750 750.00
28,600.00 28,600.00

122,612.60 28,600.00 151,212.60

6.47 1 M2 Pasang lapis plywood Sungkay tanpa rangka, politur dan lis profil
a. Bahan
0.36 Kpg Plywood Sungkay 3 mm 121,000.00 43,560.00 43,560.00
0.050 Kg Paku 1/2" - 1 " 32,500.00 1,625.00 1,625.00
45,185.00 45,185.00
b. Tenaga
0.075 Oh Tukang Kayu 125,000.00 9,375.00 9,375.00
0.0075 Oh Kepala Tukang 150,000.00 1,125.00 1,125.00
0.025 Oh Pekerja 77,500.00 1,937.50 1,937.50
0.0013 Oh Mandor 150,000.00 195.00 195.00
12,632.50 12,632.50
45,185.00 12,632.50 57,817.50

6.48 1 M2 Pasang lapis plywood Sungkay + list kayu, tanpa rangka dan politur
a. Bahan
0.36 Kpg Plywood Sungkay 3 mm 121,000.00 43,560.00 43,560.00
0.250 LS List kayu 2,750.00 687.50 687.50
0.150 Kg Paku 1/2" - 2 " 32,500.00 4,875.00 4,875.00
2.000 Lbr Amplas 3,850.00 7,700.00 7,700.00
56,822.50 56,822.50
b. Tenaga
0.096 Oh Tukang Kayu 125,000.00 12,000.00 12,000.00
0.010 Oh Kepala Tukang 150,000.00 1,425.00 1,425.00
0.046 Oh Pekerja 77,500.00 3,565.00 3,565.00
0.0023 Oh Mandor 150,000.00 345.00 345.00
17,335.00 17,335.00

56,822.50 17,335.00 74,157.50

6.49 1 M Pasangan Interior display + lapis jati dipolitur


2

Bahan
0.36 Kpg Plywood Jati 3 mm 121,000.00 43,560.00 43,560.00
0.36 Kpg Plywood 20 mm 278,000.00 100,080.00 100,080.00
0.600 Kg Lem Vinyl 9,350.00 5,610.00 5,610.00
0.150 Ltr Politur dasar 53,900.00 8,085.00 8,085.00
0.372 Ltr Politur jadi 58,300.00 21,687.60 21,687.60
2.000 Lbr Amplas 3,850.00 7,700.00 7,700.00
0.220 Kg Paku 28,500.00 6,270.00 6,270.00
192,992.60 192,992.60
Tenaga
0.025 Oh Pekerja 77,500.00 1,937.50 1,937.50
0.135 Oh Tukang Kayu 125,000.00 16,875.00 16,875.00
0.024 Oh Kepala Tukang 150,000.00 3,525.00 3,525.00
0.0038 Oh Mandor 150,000.00 570.00 570.00
22,907.50 22,907.50
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
192,992.60 22,907.50 215,900.10

6.50 1 M2 Dinding Sekat Teakwood 4 mm, Rangkap + Rangka Kayu kls. II


a. Bahan
0.0195 M3 Kayu Kelas II 6,600,000.00 128,700.00 128,700.00
2.000 M2 Teakwood 4 mm 51,500.00 103,000.00 103,000.00
0.100 Kg Paku Biasa 2"-5" 28,500.00 2,850.00 2,850.00
0.050 Kg Paku Plywood 32,500.00 1,625.00 1,625.00
236,175.00 236,175.00

b. Tenaga
0.450 Oh Tukang Kayu 125,000.00 56,250.00 56,250.00
0.0450 Oh Kepala Tukang 150,000.00 6,750.00 6,750.00
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.075 Oh Mandor 150,000.00 11,250.00 11,250.00
85,875.00 85,875.00

Jumlah 236,175.00 85,875.00 322,050.00

6.51 1 M2 Dinding pemisah Plywood Sungkai rangkap + rangka kayu kls. II


a. Bahan
0.0195 M3 Kayu Kelas II 6,600,000.00 128,700.00 128,700.00
0.0070 M3 Kayu Kelas II, Papan 3,630,000.00 25,410.00 25,410.00
0.100 Kg Paku Biasa 2"-5" 28,500.00 2,850.00 2,850.00
1.000 Lbr Plywood Sungkai 121,000.00 121,000.00 121,000.00
0.050 Kg Paku Plywood 32,500.00 1,625.00 1,625.00
279,585.00 279,585.00
b. Tenaga
0.600 Oh Tukang Kayu 125,000.00 75,000.00 75,000.00
0.0600 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
101,000.00 101,000.00

Jumlah 279,585.00 101,000.00 380,585.00

VII PEKERJAAN BETON

7.1 1 M3 Membuat Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr


a. Bahan
218 Kg Semen Portland 1,700.00 370,600.00 370,600.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.870 M3 Koral Beton 518,850.62 451,400.04 451,400.04
883,750.04 883,750.04
b. Tenaga
1.650 Oh Pekerja 77,500.00 127,875.00 127,875.00
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
174,875.00 174,875.00

Jumlah 883,750.04 174,875.00 1,058,625.04

7.2 1 M3 Membuat Beton Tumbuk, 1 Pc : 3 Ps : 6 Kr


a. Bahan
197.000 Kg Semen Portland 1,700.00 334,900.00 334,900.00
0.470 M3 Pasir Beton 118,750.00 55,812.50 55,812.50
0.940 M3 Koral Beton 518,850.62 487,719.58 487,719.58
878,432.08 878,432.08

b. Tenaga
1.650 Oh Pekerja 77,500.00 127,875.00 127,875.00
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
174,875.00 174,875.00

Jumlah 878,432.08 174,875.00 1,053,307.08

7.3 1 M3 Membuat Beton Tumbuk, 1 Pc : 4 Ps : 6 Kr


a. Bahan
173.000 Kg Semen Portland 1,700.00 294,100.00 294,100.00
0.570 M3 Pasir Beton 118,750.00 67,687.50 67,687.50
0.870 M3 Koral Beton 518,850.62 451,400.04 451,400.04
813,187.54 813,187.54

b. Tenaga
1.650 Oh Pekerja 77,500.00 127,875.00 127,875.00
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
174,875.00 174,875.00

Jumlah 813,187.54 174,875.00 988,062.54

7.4 1 M2 Membuat Lantai Kerja Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr, Tebal 5 cm


a. Bahan
10.000 Kg Semen Portland 1,700.00 17,000.00 17,000.00
0.026 M3 Pasir Beton 118,750.00 3,087.50 3,087.50
0.044 M3 Koral Beton 518,850.62 22,829.43 22,829.43
42,916.93 42,916.93
b. Tenaga
1.150 Oh Pekerja 77,500.00 89,125.00 89,125.00
0.020 Oh Tukang Batu 125,000.00 2,500.00 2,500.00
0.002 Oh Kepala Tukang 150,000.00 300.00 300.00
0.006 Oh Mandor 150,000.00 900.00 900.00
92,825.00 92,825.00

Jumlah 42,916.93 92,825.00 135,741.93

7.5 1 M Membuat
3
Beton Tak Bertulang, 1 Pc : 2 Ps : 3 Kr
a. Bahan
232.000 Kg Semen Portland 1,700.00 394,400.00 394,400.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
860,853.48 860,853.48
b. Tenaga
1.650 Oh Pekerja 77,500.00 127,875.00 127,875.00
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
174,875.00 174,875.00

Jumlah 860,853.48 174,875.00 1,035,728.48

7.6 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 2 Ps : 4 Kr


a. Bahan
280.000 Kg Semen Portland 1,700.00 476,000.00 476,000.00
0.450 M3 Pasir Beton 118,750.00 53,437.50 53,437.50
0.900 M3 Koral Beton 518,850.62 466,965.56 466,965.56
996,403.06 996,403.06

b. Tenaga
1.650 Oh Pekerja 77,500.00 127,875.00 127,875.00
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
174,875.00 174,875.00

Jumlah 996,403.06 174,875.00 1,171,278.06

7.7 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 2 Ps : 2,5 Kr


a. Bahan
352.000 Kg Semen Portland 1,700.00 598,400.00 598,400.00
0.560 M3 Pasir Beton 118,750.00 66,500.00 66,500.00
0.700 M3 Koral Beton 518,850.62 363,195.43 363,195.43
1,028,095.43 1,028,095.43

b. Tenaga
1.650 Oh Pekerja 77,500.00 127,875.00 127,875.00
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
174,875.00 174,875.00

Jumlah 1,028,095.43 174,875.00 1,202,970.43

7.8 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 1,5 Ps : 3 Kr


a. Bahan
357.000 Kg Semen Portland 1,700.00 606,900.00 606,900.00
0.420 M3 Pasir Beton 118,750.00 49,875.00 49,875.00
0.540 M3 Koral Beton 518,850.62 280,179.33 280,179.33
936,954.33 936,954.33
b. Tenaga
1.650 Oh Pekerja 77,500.00 127,875.00 127,875.00
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
174,875.00 174,875.00

Jumlah 936,954.33 174,875.00 1,111,829.33

7.9 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 1,5 Ps : 2,5 Kr


a. Bahan
386.000 Kg Semen Portland 1,700.00 656,200.00 656,200.00
0.470 M3 Pasir Beton 118,750.00 55,812.50 55,812.50
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
1,116,715.98 1,116,715.98

b. Tenaga
1.650 Oh Pekerja 77,500.00 127,875.00 127,875.00
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
174,875.00 174,875.00

Jumlah 1,116,715.98 174,875.00 1,291,590.98

7.10 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 1 Ps : 2 Kr


a. Bahan
479.000 Kg Semen Portland 1,700.00 814,300.00 814,300.00
0.370 M3 Pasir Beton 118,750.00 43,937.50 43,937.50
0.740 M3 Koral Beton 518,850.62 383,949.46 383,949.46
1,242,186.96 1,242,186.96
b. Tenaga
1.650 Oh Pekerja 77,500.00 127,875.00 127,875.00
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
174,875.00 174,875.00

Jumlah 1,242,186.96 174,875.00 1,417,061.96

7.11 1 M3 Membuat Tiang Pancang Prestressed Beton


a. Bahan
440.000 Kg Semen Portland 1,700.00 748,000.00 748,000.00
0.500 M3 Pasir Beton 118,750.00 59,375.00 59,375.00
0.800 M3 Koral Beton Pecah Split 518,850.62 415,080.50 415,080.50
2.460 Gln Rapidrant - - -
1,222,455.50 1,222,455.50
b. Tenaga
1.650 Oh Pekerja 77,500.00 127,875.00 127,875.00
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.080 Oh Mandor 150,000.00 12,000.00 12,000.00
174,875.00 174,875.00

Jumlah 1,222,455.50 174,875.00 1,397,330.50

7.12 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 2 Ps : 3 Split


a. Bahan
336.000 Kg Semen Portland 1,700.00 571,200.00 571,200.00
0.540 M3 Pasir Beton 118,750.00 64,125.00 64,125.00
0.810 M3 Koral Beton Pecah Split 518,850.62 420,269.00 420,269.00
1,055,594.00 1,055,594.00
b. Tenaga
2.000 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
1.000 Oh Mandor 150,000.00 150,000.00 150,000.00
354,000.00 354,000.00

Jumlah 1,055,594.00 354,000.00 1,409,594.00

7.13 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 2 Ps : 4 Split


a. Bahan
291.000 Kg Semen Portland 1,700.00 494,700.00 494,700.00
0.470 M3 Pasir Beton 118,750.00 55,812.50 55,812.50
0.930 M3 Koral Beton pecah Split 518,850.62 482,531.08 482,531.08
1,033,043.58 1,033,043.58

b. Tenaga
2.000 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
1.000 Oh Mandor 150,000.00 150,000.00 150,000.00
354,000.00 354,000.00

Jumlah 1,033,043.58 354,000.00 1,387,043.58

7.14 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 1,5 Ps : 3 Split


a. Bahan
367.000 Kg Semen Portland 1,700.00 623,900.00 623,900.00
0.440 M3 Pasir Beton 118,750.00 52,250.00 52,250.00
0.880 M3 Koral Beton 2/3 Split 518,850.62 456,588.55 456,588.55
1,132,738.55 1,132,738.55

b. Tenaga
2.000 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
1.000 Oh Mandor 150,000.00 150,000.00 150,000.00
354,000.00 354,000.00

Jumlah 1,132,738.55 354,000.00 1,486,738.55

7.15 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 1,5 Ps : 2,5 Split


a. Bahan
400.000 Kg Semen Portland 1,700.00 680,000.00 680,000.00
0.480 M3 Pasir Beton 118,750.00 57,000.00 57,000.00
0.800 M3 Koral Beton 2/3 Split 518,850.62 415,080.50 415,080.50
1,152,080.50 1,152,080.50

b. Tenaga
2.000 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
1.000 Oh Mandor 150,000.00 150,000.00 150,000.00
354,000.00 354,000.00

Jumlah 1,152,080.50 354,000.00 1,506,080.50

7.16 1 M Membuat
3
Beton Tak Bertulang, 1 Pc : 1 Ps : 1 Split
a. Bahan
615.000 Kg Semen Portland 1,700.00 1,045,500.00 1,045,500.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.520 M3 Koral Beton Pecah Split 518,850.62 269,802.32 269,802.32
1,377,052.32 1,377,052.32

b. Tenaga
2.000 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
1.000 Oh Mandor 150,000.00 150,000.00 150,000.00
354,000.00 354,000.00

Jumlah 1,377,052.32 354,000.00 1,731,052.32

7.17 1 M Membuat
3
Beton Kedap Air dengan Strorox - 100
a. Bahan
400.000 Kg Semen Portland 1,700.00 680,000.00 680,000.00
0.480 M3 Pasir Beton 118,750.00 57,000.00 57,000.00
0.800 M3 Koral Beton 2/3 363,000.00 290,400.00 290,400.00
1.200 Kg Strorox - 100 - - -
1,027,400.00 1,027,400.00

b. Tenaga
2.000 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
1.000 Oh Mandor 150,000.00 150,000.00 150,000.00
354,000.00 354,000.00

Jumlah

7.18 1 Kg Pembesian dengan Besi Polos atau Besi Ulir


a. Bahan
1.050 Kg Besi Beton ( Polos / Ulir ) 12,075.00 12,678.75 12,678.75
0.015 Kg Kawat Beton 19,800.00 297.00 297.00
12,975.75 12,975.75

b. Tenaga
0.007 Oh Pekerja 77,500.00 542.50 542.50
0.007 Oh Tukang Besi 125,000.00 875.00 875.00
0.0007 Oh Kepala Tukang 150,000.00 105.00 105.00
0.0003 Oh Mandor 150,000.00 45.00 45.00
1,567.50 1,567.50

Jumlah 12,975.75 1,567.50 14,543.25

7.19 1 Kg Kabel Presstressed Polos / Strands


a. Bahan
1.050 Kg Besi Presstressed Polos - - -
0.010 Kg Kawat Beton 19,800.00 198.00 198.00
198.00 198.00

b. Tenaga
0.005 Oh Pekerja 77,500.00 387.50 387.50
0.005 Oh Tukang Besi 125,000.00 625.00 625.00
0.0005 Oh Kepala Tukang 150,000.00 75.00 75.00
0.0003 Oh Mandor 150,000.00 45.00 45.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
1,132.50 1,132.50

Jumlah

7.20 1 M2 Pasang Bekisting Untuk Pondasi


a. Bahan
0.040 M3 Kayu Kls. IV 1,650,000.00 66,000.00 66,000.00
0.300 Kg Paku Biasa 2"- 5" 28,500.00 8,550.00 8,550.00
74,550.00 74,550.00

b. Tenaga
0.300 Oh Pekerja 77,500.00 23,250.00 23,250.00
0.260 Oh Tukang Kayu 125,000.00 32,500.00 32,500.00
0.026 Oh Kepala Tukang 150,000.00 3,900.00 3,900.00
0.005 Oh Mandor 150,000.00 750.00 750.00
60,400.00 60,400.00

Jumlah 74,550.00 60,400.00 134,950.00

7.21 1 M2 Pasang Bekisting Untuk Sloof


a. Bahan
0.045 M3 Kayu Kls. IV 1,650,000.00 74,250.00 74,250.00
0.300 Kg Paku Biasa 2"- 5" 28,500.00 8,550.00 8,550.00
82,800.00 82,800.00

b. Tenaga
0.300 Oh Pekerja 77,500.00 23,250.00 23,250.00
0.260 Oh Tukang Kayu 125,000.00 32,500.00 32,500.00
0.026 Oh Kepala Tukang 150,000.00 3,900.00 3,900.00
0.005 Oh Mandor 150,000.00 750.00 750.00
60,400.00 60,400.00

Jumlah 82,800.00 60,400.00 143,200.00

7.22 1 M2 Pasang Bekisting Untuk Kolom (Untuk bangunan gedung)


a. Bahan
0.040 M3 Kayu Kls. IV 1,650,000.00 66,000.00 66,000.00
0.400 Kg Paku Biasa 2"- 5" 28,500.00 11,400.00 11,400.00
0.015 M3 Balok Kayu Kls. IV 1,650,000.00 24,750.00 24,750.00
2.000 Btg Kayu Gelam dia. 6-8 cm 8,800.00 17,600.00 17,600.00
119,750.00 119,750.00
b. Tenaga
0.300 Oh Pekerja 77,500.00 23,250.00 23,250.00
0.330 Oh Tukang Kayu 125,000.00 41,250.00 41,250.00
0.033 Oh Kepala Tukang 150,000.00 4,950.00 4,950.00
0.006 Oh Mandor 150,000.00 900.00 900.00
70,350.00 70,350.00

Jumlah 119,750.00 70,350.00 190,100.00

7.23 1 M2 Pasang Bekisting Untuk Kolom (Jerambah Beton)


a. Bahan
0.020 M3 Kayu Kls. IV 1,650,000.00 33,000.00 33,000.00
0.500 Btg Hek 9,900.00 4,950.00 4,950.00
0.200 Kg Paku Biasa 2"- 5" 28,500.00 5,700.00 5,700.00
43,650.00 43,650.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.165 Oh Tukang Kayu 125,000.00 20,625.00 20,625.00
0.017 Oh Kepala Tukang 150,000.00 2,475.00 2,475.00
0.003 Oh Mandor 150,000.00 450.00 450.00
35,175.00 35,175.00

Jumlah 43,650.00 35,175.00 78,825.00

7.24 1 M Pasang Bekisting Untuk Balok (Untuk bangunan gedung)


2

a. Bahan
0.040 M3 Kayu Kls. IV 1,650,000.00 66,000.00 66,000.00
0.400 Kg Paku Biasa 2"- 5" 28,500.00 11,400.00 11,400.00
0.018 M3 Balok Kayu Kls. IV 1,650,000.00 29,700.00 29,700.00
2.000 Btg Kayu Gelam dia. 6-8 cm 8,800.00 17,600.00 17,600.00
124,700.00 124,700.00
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.330 Oh Tukang Kayu 125,000.00 41,250.00 41,250.00
0.033 Oh Kepala Tukang 150,000.00 4,950.00 4,950.00
0.006 Oh Mandor 150,000.00 900.00 900.00
71,900.00 71,900.00

Jumlah 124,700.00 71,900.00 196,600.00

7.25 1 M Pasang Bekisting Untuk Balok (Jerambah Beton)


2

a. Bahan
0.020 M3 Kayu Kls. IV 1,650,000.00 33,000.00 33,000.00
0.500 Btg Hek 9,900.00 4,950.00 4,950.00
2.000 Btg Kayu Gelam dia. 6-8 cm 8,800.00 17,600.00 17,600.00
0.200 Kg Paku Biasa 2"- 5" 28,500.00 5,700.00 5,700.00
61,250.00 61,250.00
b. Tenaga
0.160 Oh Pekerja 77,500.00 12,400.00 12,400.00
0.165 Oh Tukang Kayu 125,000.00 20,625.00 20,625.00
0.017 Oh Kepala Tukang 150,000.00 2,475.00 2,475.00
0.003 Oh Mandor 150,000.00 450.00 450.00
35,950.00 35,950.00

Jumlah 61,250.00 35,950.00 97,200.00

7.26 1 M Pasang Bekisting Untuk Lantai, plat dak (untuk bangunan gedung)
2

a. Bahan
0.040 M3 Kayu Kls. IV 1,650,000.00 66,000.00 66,000.00
0.400 Kg Paku Biasa 2"- 5" 28,500.00 11,400.00 11,400.00
0.015 M3 Balok Kayu Kls.IV 1,650,000.00 24,750.00 24,750.00
6.000 Btg Kayu Gelam dia. 6-8 cm 8,800.00 52,800.00 52,800.00
154,950.00 154,950.00
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.330 Oh Tukang Batu 125,000.00 41,250.00 41,250.00
0.033 Oh Kepala Tukang 150,000.00 4,950.00 4,950.00
0.006 Oh Mandor 150,000.00 900.00 900.00
71,900.00 71,900.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

Jumlah 154,950.00 71,900.00 226,850.00

7.27 1 M2 Pasang Bekisting Untuk Lantai ( jerambah beton)


a. Bahan
1.500 Kpg Papan Kayu Kls IV 18,150.00 27,225.00 27,225.00
0.200 Kg Paku Biasa 2"- 5" 28,500.00 5,700.00 5,700.00
2.000 Btg Kayu Gelam dia. 6-8 cm 8,800.00 17,600.00 17,600.00
50,525.00 50,525.00
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.330 Oh Tukang Batu 125,000.00 41,250.00 41,250.00
0.033 Oh Kepala Tukang 150,000.00 4,950.00 4,950.00
0.006 Oh Mandor 150,000.00 900.00 900.00
71,900.00 71,900.00

Jumlah 50,525.00 71,900.00 122,425.00

7.28 1 M2 Pasang Bekisting Untuk Dinding


a. Bahan
0.030 M3 Kayu Kls. IV 1,650,000.00 49,500.00 49,500.00
0.400 Kg Paku Biasa 2"- 5" 28,500.00 11,400.00 11,400.00
0.020 M3 Balok Kayu Kls.IV 1,650,000.00 33,000.00 33,000.00
3.000 Btg Kayu Gelam dia. 6-8 cm 8,800.00 26,400.00 26,400.00
4.000 Bh Formtie / Penjaga Jarak Bekisting / Spacer 0.00 0.00 0.00
120,300.00 120,300.00

b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.330 Oh Tukang Kayu 125,000.00 41,250.00 41,250.00
0.033 Oh Kepala Tukang 150,000.00 4,950.00 4,950.00
0.006 Oh Mandor 150,000.00 900.00 900.00
71,900.00 71,900.00

Jumlah 120,300.00 71,900.00 192,200.00

7.29 1 M2 Pasang Bekisting Untuk Tangga


a. Bahan
0.030 M3 Kayu Kls. IV 1,650,000.00 49,500.00 49,500.00
0.400 Kg Paku Biasa 2"- 5" 28,500.00 11,400.00 11,400.00
0.015 M3 Balok Kayu Kls. IV 1,650,000.00 24,750.00 24,750.00
2 Btg Kayu Gelam dia. 6-8 cm 8,800.00 17,600.00 17,600.00
103,250.00 103,250.00
b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.330 Oh Tukang Kayu 125,000.00 41,250.00 41,250.00
0.033 Oh Kepala Tukang 150,000.00 4,950.00 4,950.00
0.006 Oh Mandor 150,000.00 900.00 900.00
71,900.00 71,900.00
Jumlah 103,250.00 71,900.00 175,150.00

7.30 1 M3 Beton Ready Mix K 175 dengan pengangkutan


a. Bahan
1.0 M3 Beton Ready Mix K 175 935,000.00 953,700.00 953,700.00
953,700.00 953,700.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
1 Ls Pengangkutan dan mobilisasi mobil Pick up 15,583.33 15,583.33 15,583.33
199,170.88 199,170.88

Jumlah 953,700.00 199,170.88 1,152,870.88

7.31 1 M3 Beton Ready Mix K 175 tanpa pengangkutan


a. Bahan
1.0 M3 Beton Ready Mix K 175 935,000.00 953,700.00 953,700.00
953,700.00 953,700.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
183,587.55 183,587.55
Jumlah 953,700.00 183,587.55 1,137,287.55

7.32 1 M3 Beton Ready Mix K 225 dengan pengangkutan


a. Bahan
1.0 M3 Beton Ready Mix K 225 990,000.00 1,009,800.00 1,009,800.00
1,009,800.00 1,009,800.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
1 Ls Pengangkutan dan mobilisasi mobil Pick up 15,583.33 15,583.33 15,583.33
199,170.88 199,170.88
Jumlah 1,009,800.00 199,170.88 1,208,970.88

7.33 1 M3 Beton Ready Mix K 225 tanpa pengangkutan


a. Bahan
1.0 M3 Beton Ready Mix K 225 990,000.00 1,009,800.00 1,009,800.00
1,009,800.00 1,009,800.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
183,587.55 183,587.55

Jumlah 1,009,800.00 183,587.55 1,193,387.55

7.34 1 M Beton Ready Mix K 250 dengan pengangkutan


3

a. Bahan
1.0 M3 Beton Ready Mix K 250 1,045,000.00 1,065,900.00 1,065,900.00
1,065,900.00 1,065,900.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
1 Ls Pengangkutan dan mobilisasi mobil Pick up 15,583.33 15,583.33 15,583.33
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
199,170.88 199,170.88

Jumlah 1,065,900.00 199,170.88 1,265,070.88

7.35 1 M3 Beton Ready Mix K 250 tanpa pengangkutan


a. Bahan
1.0 M3 Beton Ready Mix K 250 1,045,000.00 1,065,900.00 1,065,900.00
1,065,900.00 1,065,900.00

b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
183,587.55 183,587.55

Jumlah 1,065,900.00 183,587.55 1,249,487.55


7.36 1 M3 Beton Ready Mix K 275 dengan pengangkutan
a. Bahan
1.0 M3 Beton Ready Mix K 275 1,100,000.00 1,122,000.00 1,122,000.00
1,122,000.00 1,122,000.00

b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
1 Ls Pengangkutan dan mobilisasi mobil Pick up 15,583.33 15,583.33 15,583.33
199,170.88 199,170.88

Jumlah 1,122,000.00 199,170.88 1,321,170.88

7.37 1 M3 Beton Ready Mix K 275 tanpa pengangkutan


a. Bahan
1.0 M3 Beton Ready Mix K 275 1,100,000.00 1,122,000.00 1,122,000.00
1,122,000.00 1,122,000.00

b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
183,587.55 183,587.55

Jumlah 1,122,000.00 183,587.55 1,305,587.55

7.38 1 M Beton Ready Mix K 300 dengan pengangkutan


3

a. Bahan
1.0 M3 Beton Ready Mix K 300 1,155,000.00 1,178,100.00 1,178,100.00
1,178,100.00 1,178,100.00

b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
1 Ls Pengangkutan dan mobilisasi mobil Pick up 15,583.33 15,583.33 15,583.33
199,170.88 199,170.88

Jumlah 1,178,100.00 199,170.88 1,377,270.88

7.39 1 M Beton Ready Mix K 300 tanpa pengangkutan


3

a. Bahan
1.0 M3 Beton Ready Mix K 300 1,155,000.00 1,178,100.00 1,178,100.00
1,178,100.00 1,178,100.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
183,587.55 183,587.55

Jumlah 1,178,100.00 183,587.55 1,361,687.55

7.40 1 M3 Beton Ready Mix K 350 dengan pengangkutan


a. Bahan
1.0 M3 Beton Ready Mix K 350 1,100,000.00 1,122,000.00 1,122,000.00
1,122,000.00 1,122,000.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
1 Ls Pengangkutan dan mobilisasi mobil Pick up 15,583.33 15,583.33 15,583.33
199,170.88 199,170.88

Jumlah 1,122,000.00 199,170.88 1,321,170.88

7.41 1 M3 Beton Ready Mix K 350 tanpa pengangkutan


a. Bahan
1.0 M3 Beton Ready Mix K 350 1,100,000.00 1,122,000.00 1,122,000.00
1,122,000.00 1,122,000.00

b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
183,587.55 183,587.55

Jumlah 1,122,000.00 183,587.55 1,305,587.55

7.42 1 M' Pasang Kayu Mal Bekisting untuk Beton Ready Mix jalan
a. Bahan
0.5 Kpg Papan Kayu Kls. IV 18,150.00 9,075.00 9,075.00
0.200 Kg Paku Biasa 2"- 5" 28,500.00 5,700.00 5,700.00
0.009 M3 Balok Kayu Kls. IV 1,650,000.00 14,850.00 14,850.00
29,625.00 29,625.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
b. Tenaga
0.160 Oh Pekerja 77,500.00 12,400.00 12,400.00
0.165 Oh Tukang Kayu 125,000.00 20,625.00 20,625.00
0.0165 Oh Kepala Tukang 150,000.00 2,475.00 2,475.00
0.003 Oh Mandor 150,000.00 450.00 450.00
35,950.00 35,950.00

Jumlah 29,625.00 35,950.00 65,575.00


7.43 1 M3 Membuat Beton dengan Mutu K 225
a. Bahan
388 Kg Semen Portland 1,700.00 659,600.00 659,600.00
0.650 M3 Pasir Beton 118,750.00 77,187.50 77,187.50
0.650 M3 Koral Beton 518,850.62 337,252.90 337,252.90
1,074,040.40 1,074,040.40
b. Tenaga
6 Oh Pekerja 77,500.00 465,000.00 465,000.00
1 Oh Tukang Batu 125,000.00 0.166667 125,000.00 125,000.00
0.100 Oh Kepala Tukang 150,000.00 0.016667 15,000.00 15,000.00
0.300 Oh Mandor 150,000.00 0.0500 45,000.00 45,000.00
650,000.00 650,000.00

Jumlah 1,074,040.40 650,000.00 1,724,040.40

7.44 1 M3 Membuat Beton dengan Mutu K 275


a. Bahan
400 Kg Semen Portland 1,700.00 680,000.00 680,000.00
0.400 M3 Pasir Beton 118,750.00 47,500.00 47,500.00
0.820 M3 Koral Beton 518,850.62 425,457.51 425,457.51
1,152,957.51 1,152,957.51
b. Tenaga
6 Oh Pekerja 77,500.00 465,000.00 465,000.00
1 Oh Tukang Batu 125,000.00 125,000.00 125,000.00
0.100 Oh Kepala Tukang 150,000.00 15,000.00 15,000.00
0.300 Oh Mandor 150,000.00 45,000.00 45,000.00
650,000.00 650,000.00

Jumlah 1,152,957.51 650,000.00 1,802,957.51

7.45 1 M Pasang Jembatan Cor


2

a. Bahan
0.0264 M3 Kayu Kls. IV 1,650,000.00 43,560.00 43,560.00
0.600 Kg Paku Biasa 2"- 5" 28,500.00 17,100.00 17,100.00
0.500 Btg Kayu Gelam dia. 6-8 cm 8,800.00 4,400.00 4,400.00
65,060.00 65,060.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.050 Oh Tukang Kayu 125,000.00 6,250.00 6,250.00
0.005 Oh Kepala Tukang 150,000.00 750.00 750.00
0.007 Oh Mandor 150,000.00 1,050.00 1,050.00
19,675.00 19,675.00

Jumlah 65,060.00 19,675.00 84,735.00

7.46 1 M3 Membuat Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting )


a. Bahan
0.200 M3 Kayu Kls. IV 1,650,000.00 330,000.00 330,000.00
1.500 Kg Paku Biasa 2"- 5" 28,500.00 42,750.00 42,750.00
150 Kg Besi Beton Polos 12,075.00 1,811,250.00 1,811,250.00
2.250 Kg Kawat Beton 19,800.00 44,550.00 44,550.00
323 Kg Semen Portland 1,700.00 549,100.00 549,100.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
3,244,103.48 3,244,103.48

b. Tenaga
3.900 Oh Pekerja 77,500.00 302,250.00 302,250.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
1.040 Oh Tukang Kayu 125,000.00 130,000.00 130,000.00
1.050 Oh Tukang Besi 125,000.00 131,250.00 131,250.00
0.245 Oh Kepala Tukang 150,000.00 36,750.00 36,750.00
0.165 Oh Mandor 150,000.00 24,750.00 24,750.00
668,750.00 668,750.00

Jumlah 3,244,103.48 668,750.00 3,912,853.48

7.47 1 M3 Membuat Sloof Beton Bertulang ( 200 Kg Besi + Bekisting )


a. Bahan
0.270 M3 Kayu Kls. IV 1,650,000.00 445,500.00 445,500.00
2.000 Kg Paku Biasa 2"- 5" 28,500.00 57,000.00 57,000.00
200 Kg Besi Beton Polos 12,075.00 2,415,000.00 2,415,000.00
3.000 Kg Kawat Beton 19,800.00 59,400.00 59,400.00
323 Kg Semen Portland 1,700.00 549,100.00 549,100.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
3,992,453.48 3,992,453.48
b. Tenaga
4.850 Oh Pekerja 77,500.00 375,875.00 375,875.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
1.560 Oh Tukang Kayu 125,000.00 195,000.00 195,000.00
1.400 Oh Tukang Besi 125,000.00 175,000.00 175,000.00
0.331 Oh Kepala Tukang 150,000.00 49,650.00 49,650.00
0.170 Oh Mandor 150,000.00 25,500.00 25,500.00
864,775.00 864,775.00

Jumlah 3,992,453.48 864,775.00 4,857,228.48

7.48 1 M3 Membuat Kolom Beton Bertulang ( 300 Kg Besi + Bekisting )


a. Bahan
0.400 M3 Kayu Kls. IV 1,650,000.00 660,000.00 660,000.00
4.000 Kg Paku Biasa 2"- 5" 28,500.00 114,000.00 114,000.00
300 Kg Besi Beton Polos 12,075.00 3,622,500.00 3,622,500.00
4.500 Kg Kawat Beton 19,800.00 89,100.00 89,100.00
323 Kg Semen Portland 1,700.00 549,100.00 549,100.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
0.150 M3 Kayu Balok Kls. IV 1,650,000.00 247,500.00 247,500.00
20 Btg Kayu Gelam dia. 6-8 cm 8,800.00 176,000.00 176,000.00
5,924,653.48 5,924,653.48

b. Tenaga
7.300 Oh Pekerja 77,500.00 565,750.00 565,750.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
3.300 Oh Tukang Kayu 125,000.00 412,500.00 412,500.00
2.100 Oh Tukang Besi 125,000.00 262,500.00 262,500.00
0.570 Oh Kepala Tukang 150,000.00 85,500.00 85,500.00
0.250 Oh Mandor 150,000.00 37,500.00 37,500.00
1,407,500.00 1,407,500.00

Jumlah 5,924,653.48 1,407,500.00 7,332,153.48

7.49 1 M3 Membuat Kolom Beton Bertulang ( 200 Kg Besi + Bekisting )


a. Bahan
0.400 M3 Kayu Kls. IV 1,650,000.00 660,000.00 660,000.00
4.000 Kg Paku Biasa 2"- 5" 28,500.00 114,000.00 114,000.00
200 Kg Besi Beton Polos 12,075.00 2,415,000.00 2,415,000.00
4.500 Kg Kawat Beton 19,800.00 89,100.00 89,100.00
232 Kg Semen Portland 1,700.00 394,400.00 394,400.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
0.150 M3 Kayu Balok Kls. IV 1,650,000.00 247,500.00 247,500.00
20 Btg Kayu Gelam dia. 6-8 cm 8,800.00 176,000.00 176,000.00
4,562,453.48 4,562,453.48

b. Tenaga
7.300 Oh Pekerja 77,500.00 565,750.00 565,750.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
3.300 Oh Tukang Kayu 125,000.00 412,500.00 412,500.00
2.100 Oh Tukang Besi 125,000.00 262,500.00 262,500.00
0.570 Oh Kepala Tukang 150,000.00 85,500.00 85,500.00
0.250 Oh Mandor 150,000.00 37,500.00 37,500.00
1,407,500.00 1,407,500.00

Jumlah 4,562,453.48 1,407,500.00 5,969,953.48

7.50 1 M3 Membuat Kolom Beton Bertulang ( 100 Kg Besi + Bekisting )


a. Bahan
0.400 M3 Kayu Kls. IV 1,650,000.00 660,000.00 660,000.00
4.000 Kg Paku Biasa 2"- 5" 28,500.00 114,000.00 114,000.00
100 Kg Besi Beton Polos 12,075.00 1,207,500.00 1,207,500.00
4.500 Kg Kawat Beton 19,800.00 89,100.00 89,100.00
232 Kg Semen Portland 1,700.00 394,400.00 394,400.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
0.150 M3 Kayu Balok Kls. IV 1,650,000.00 247,500.00 247,500.00
20 Btg Kayu Gelam dia. 6-8 cm 8,800.00 176,000.00 176,000.00
3,354,953.48 3,354,953.48

b. Tenaga
7.300 Oh Pekerja 77,500.00 565,750.00 565,750.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
3.300 Oh Tukang Kayu 125,000.00 412,500.00 412,500.00
2.100 Oh Tukang Besi 125,000.00 262,500.00 262,500.00
0.570 Oh Kepala Tukang 150,000.00 85,500.00 85,500.00
0.250 Oh Mandor 150,000.00 37,500.00 37,500.00
1,407,500.00 1,407,500.00
Jumlah 3,354,953.48 1,407,500.00 4,762,453.48

7.51 1 M3 Membuat Balok Beton Bertulang ( 200 Kg Besi + Bekisting )


a. Bahan
0.320 M3 Kayu Kls. IV 1,650,000.00 528,000.00 528,000.00
3.200 Kg Paku Biasa 2"- 5" 28,500.00 91,200.00 91,200.00
200 Kg Besi Beton Polos 12,075.00 2,415,000.00 2,415,000.00
3 Kg Kawat Beton 19,800.00 59,400.00 59,400.00
232 Kg Semen Portland 1,700.00 394,400.00 394,400.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
0.140 M3 Kayu Balok Kls. IV 1,650,000.00 231,000.00 231,000.00
16 Btg Kayu Gelam dia. 6-8 cm 8,800.00 140,800.00 140,800.00
4,326,253.48 4,326,253.48

b. Tenaga
5.960 Oh Pekerja 77,500.00 461,900.00 461,900.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
2.800 Oh Tukang Kayu 125,000.00 350,000.00 350,000.00
1.400 Oh Tukang Besi 125,000.00 175,000.00 175,000.00
0.455 Oh Kepala Tukang 150,000.00 68,250.00 68,250.00
0.208 Oh Mandor 150,000.00 31,200.00 31,200.00
1,130,100.00 1,130,100.00

Jumlah 4,326,253.48 1,130,100.00 5,456,353.48

7.52 1 M Membuat Balok Beton Bertulang ( 150 Kg Besi + Bekisting )


3

a. Bahan
0.320 M3 Kayu Kls. IV 1,650,000.00 528,000.00 528,000.00
3.200 Kg Paku Biasa 2"- 5" 28,500.00 91,200.00 91,200.00
150 Kg Besi Beton Polos 12,075.00 1,811,250.00 1,811,250.00
2.250 Kg Kawat Beton 19,800.00 44,550.00 44,550.00
232 Kg Semen Portland 1,700.00 394,400.00 394,400.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
0.120 M3 Kayu Balok Kls. IV 1,650,000.00 198,000.00 198,000.00
32 Btg Kayu Gelam dia. 6-8 cm 8,800.00 281,600.00 281,600.00
3,815,453.48 3,815,453.48

b. Tenaga
5.800 Oh Pekerja 77,500.00 449,500.00 449,500.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
2.800 Oh Tukang Kayu 125,000.00 350,000.00 350,000.00
1.050 Oh Tukang Besi 125,000.00 131,250.00 131,250.00
0.420 Oh Kepala Tukang 150,000.00 63,000.00 63,000.00
0.185 Oh Mandor 150,000.00 27,750.00 27,750.00
1,065,250.00 1,065,250.00

Jumlah 3,815,453.48 1,065,250.00 4,880,703.48

7.53 1 M Membuat
3
Balok Beton Bertulang ( 100 Kg Besi + Bekisting )
a. Bahan
0.320 M3 Kayu Kls. IV 1,650,000.00 528,000.00 528,000.00
3.200 Kg Paku Biasa 2"- 5" 28,500.00 91,200.00 91,200.00
110 Kg Besi Beton Polos 12,075.00 1,328,250.00 1,328,250.00
2.250 Kg Kawat Beton 19,800.00 44,550.00 44,550.00
232 Kg Semen Portland 1,700.00 394,400.00 394,400.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
0.120 M3 Kayu Balok Kls. IV 1,650,000.00 198,000.00 198,000.00
32 Btg Kayu Gelam dia. 6-8 cm 8,800.00 281,600.00 281,600.00
3,332,453.48 3,332,453.48

b. Tenaga
5.800 Oh Pekerja 77,500.00 449,500.00 449,500.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
2.800 Oh Tukang Kayu 125,000.00 350,000.00 350,000.00
1.050 Oh Tukang Besi 125,000.00 131,250.00 131,250.00
0.420 Oh Kepala Tukang 150,000.00 63,000.00 63,000.00
0.185 Oh Mandor 150,000.00 27,750.00 27,750.00
1,065,250.00 1,065,250.00

Jumlah 3,332,453.48 1,065,250.00 4,397,703.48

7.54 1 M3 Membuat Dinding Beton Bertulang ( 150 Kg Besi + Bekisting )


a. Bahan
0.240 M3 Kayu Kls. IV 1,650,000.00 396,000.00 396,000.00
3.200 Kg Paku Biasa 2"- 5" 28,500.00 91,200.00 91,200.00
150.000 Kg Besi Beton Polos 12,075.00 1,811,250.00 1,811,250.00
2.250 Kg Kawat Beton 19,800.00 44,550.00 44,550.00
232.000 Kg Semen Portland 1,700.00 394,400.00 394,400.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
0.160 M3 Kayu Balok Kls. IV 1,650,000.00 264,000.00 264,000.00
24.000 Btg Kayu Gelam dia. 6-8 cm 8,800.00 211,200.00 211,200.00
3,679,053.48 3,679,053.48

b. Tenaga
5.600 Oh Pekerja 77,500.00 434,000.00 434,000.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
2.640 Oh Tukang Kayu 125,000.00 330,000.00 330,000.00
1.050 Oh Tukang Besi 125,000.00 131,250.00 131,250.00
0.400 Oh Kepala Tukang 150,000.00 60,000.00 60,000.00
0.193 Oh Mandor 150,000.00 28,950.00 28,950.00
1,027,950.00 1,027,950.00

Jumlah 3,679,053.48 1,027,950.00 4,707,003.48

7.55 1 M3 Membuat 1/2 Dinding Beton Bertulang ( 100 Kg Besi + Bekisting)


a. Bahan
0.120 M3 Kayu Kls. IV 1,650,000.00 198,000.00 198,000.00
3.200 Kg Paku Biasa 2"- 5" 28,500.00 91,200.00 91,200.00
100.000 Kg Besi Beton Polos 12,075.00 1,207,500.00 1,207,500.00
1.250 Kg Kawat Beton 19,800.00 24,750.00 24,750.00
232.000 Kg Semen Portland 1,700.00 394,400.00 394,400.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
2,382,303.48 2,382,303.48

b. Tenaga
5.600 Oh Pekerja 91,300.00 511,280.00 511,280.00
0.350 Oh Tukang Batu 47,300.00 16,555.00 16,555.00
2.640 Oh Tukang Kayu 47,300.00 124,872.00 124,872.00
1.050 Oh Tukang Besi 47,300.00 49,665.00 49,665.00
0.400 Oh Kepala Tukang 7,150.00 2,860.00 2,860.00
0.193 Oh Mandor 66,000.00 12,738.00 12,738.00
717,970.00 717,970.00

Jumlah 2,382,303.48 717,970.00 3,100,273.48

7.56 1 M Membuat Tangga Beton Bertulang ( 200 Kg Besi + Bekisting )


3

a. Bahan
0.250 M3 Kayu Kls. IV 1,650,000.00 412,500.00 412,500.00
3.000 Kg Paku Biasa 2"- 5" 28,500.00 85,500.00 85,500.00
200.000 Kg Besi Beton Polos 12,075.00 2,415,000.00 2,415,000.00
3.000 Kg Kawat Beton 19,800.00 59,400.00 59,400.00
232.000 Kg Semen Portland 1,700.00 394,400.00 394,400.00
0.520 M3 Pasir Beton 118,750.00 61,750.00 61,750.00
0.780 M3 Koral Beton 518,850.62 404,703.48 404,703.48
0.105 M3 Kayu Balok Kls. IV 1,650,000.00 173,250.00 173,250.00
14.000 Btg Kayu Gelam dia. 6-8 cm 8,800.00 123,200.00 123,200.00
4,129,703.48 4,129,703.48
b. Tenaga
5.600 Oh Pekerja 77,500.00 434,000.00 434,000.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
2.300 Oh Tukang Kayu 125,000.00 287,500.00 287,500.00
1.400 Oh Tukang Besi 125,000.00 175,000.00 175,000.00
0.405 Oh Kepala Tukang 150,000.00 60,750.00 60,750.00
0.202 Oh Mandor 150,000.00 30,300.00 30,300.00
1,031,300.00 1,031,300.00

Jumlah 4,129,703.48 1,031,300.00 5,161,003.48

7.57 1 M' Membuat Kolom Penguat Beton Bertulang ( 11 x 11 ) cm + bekisting (kolom praktis)
a. Bahan
0.002 M3 Kayu Kls. IV 1,650,000.00 3,300.00 3,300.00
0.010 Kg Paku Biasa 2"- 5" 28,500.00 285.00 285.00
3.000 Kg Besi Beton Polos 12,075.00 36,225.00 36,225.00
0.450 Kg Kawat Beton 19,800.00 8,910.00 8,910.00
4.000 Kg Semen Portland 1,700.00 6,800.00 6,800.00
0.006 M3 Pasir Beton 118,750.00 712.50 712.50
0.009 M3 Koral Beton 518,850.62 4,669.66 4,669.66
60,902.16 60,902.16
b. Tenaga
0.060 Oh Pekerja 77,500.00 4,650.00 4,650.00
0.020 Oh Tukang Batu 125,000.00 2,500.00 2,500.00
0.020 Oh Tukang Kayu 125,000.00 2,500.00 2,500.00
0.020 Oh Tukang Besi 125,000.00 2,500.00 2,500.00
0.006 Oh Kepala Tukang 150,000.00 900.00 900.00
0.003 Oh Mandor 150,000.00 450.00 450.00
13,500.00 13,500.00

Jumlah 60,902.16 13,500.00 74,402.16

7.58 1 M' Membuat Ring Balok Beton Bertulang ( 10 x 15 ) cm


a. Bahan
0.003 M3 Kayu Kls. IV 1,650,000.00 4,950.00 4,950.00
0.020 Kg Paku Biasa 2"- 5" 28,500.00 570.00 570.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
3.600 Kg Besi Beton Polos 12,075.00 43,470.00 43,470.00
0.050 Kg Kawat Beton 19,800.00 990.00 990.00
5.500 Kg Semen Portland 1,700.00 9,350.00 9,350.00
0.009 M3 Pasir Beton 118,750.00 1,068.75 1,068.75
0.015 M3 Koral Beton 518,850.62 7,782.76 7,782.76
68,181.51 68,181.51
b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.033 Oh Tukang Batu 125,000.00 4,125.00 4,125.00
0.033 Oh Tukang Kayu 125,000.00 4,125.00 4,125.00
0.033 Oh Tukang Besi 125,000.00 4,125.00 4,125.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.005 Oh Mandor 150,000.00 750.00 750.00
22,375.00 22,375.00
Jumlah 68,181.51 22,375.00 90,556.51

7.59 1 M2 Pasang Bekisting Untuk Lantai, plat dak dengan plywood 4 mm


a. Bahan
0.040 M3 Kayu Kls. IV 1,650,000.00 66,000.00 66,000.00
0.400 Kg Paku Biasa 2"- 5" 28,500.00 11,400.00 11,400.00
0.015 M3 Balok Kayu Kls.IV 1,650,000.00 24,750.00 24,750.00
0.350 Lbr Plywood 4 mm 82,500.00 28,875.00 28,875.00
6.000 Btg Kayu Gelam dia. 6-8 cm 8,800.00 52,800.00 52,800.00
183,825.00 183,825.00

b. Tenaga
0.320 Oh Pekerja 77,500.00 24,800.00 24,800.00
0.330 Oh Tukang Batu 125,000.00 41,250.00 41,250.00
0.033 Oh Kepala Tukang 150,000.00 4,950.00 4,950.00
0.006 Oh Mandor 150,000.00 900.00 900.00
71,900.00 71,900.00

Jumlah 183,825.00 71,900.00 255,725.00

7.60 1 M3 Beton Ready Mix K-175 untuk Kolom, Balok, Plat Lantai, tangga dengan Concrete Pump (belalai)
a. Bahan
1.020 M3 Beton Ready Mix K-175 935,000.00 953,700.00 953,700.00
953,700.00 953,700.00

b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
0.16667 M3 Concrete Pump 409,815.23 68,303.91 68,303.91
251,891.46 251,891.46

Jumlah 953,700.00 251,891.46 1,205,591.46

7.61 1 M Beton Ready Mix K-175 untuk Kolom, Balok, Plat Lantai, tangga tanpa Concrete Pump (belalai)
3

a. Bahan
1.020 M3 Beton Ready Mix K-175 935,000.00 953,700.00 953,700.00
953,700.00 953,700.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
183,587.55 183,587.55

Jumlah 953,700.00 183,587.55 1,137,287.55

7.62 1 M3 Beton Ready Mix K-225 untuk Kolom, Balok, Plat Lantai, tangga dengan Concrete Pump (belalai)
a. Bahan
1.020 M3 Beton Ready Mix K-225 990,000.00 1,009,800.00 1,009,800.00
1,009,800.00 1,009,800.00

b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
0.16667 M3 Concrete Pump 409,815.23 68,303.91 68,303.91
251,891.46 251,891.46

Jumlah 1,009,800.00 251,891.46 1,261,691.46

7.63 1 M Beton Ready Mix K-225 untuk Kolom, Balok, Plat Lantai, tangga tanpa Concrete Pump (belalai)
3

a. Bahan
1.020 M3 Beton Ready Mix K-225 990,000.00 1,009,800.00 1,009,800.00
1,009,800.00 1,009,800.00
b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
183,587.55 183,587.55

Jumlah 1,009,800.00 183,587.55 1,193,387.55

7.64 1 M3 Beton Ready Mix K-275 untuk Kolom, Balok, Plat Lantai, tangga dengan Concrete Pump (belalai)
a. Bahan
1.020 M3 Beton Ready Mix K-275 1,100,000.00 1,122,000.00 1,122,000.00
1,122,000.00 1,122,000.00

b. Tenaga
2 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.1667 Oh Tukang batu 125,000.00 20,837.50 20,837.50
0.00167 Oh Kepala Tukang 150,000.00 250.05 250.05
0.050 Oh Mandor 150,000.00 7,500.00 7,500.00
0.16667 M3 Concrete Pump 409,815.23 68,303.91 68,303.91
251,891.46 251,891.46

Jumlah 1,122,000.00 251,891.46 1,373,891.46

VIII PEKERJAAN PENUTUP ATAP

8.1 1 M2 Pasang Atap Genteng Kodok


a. Bahan
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
25.000 Bh Genteng Kodok 1,100.00 27,500.00 27,500.00
27,500.00 27,500.00

b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.075 Oh Tukang Kayu 125,000.00 9,375.00 9,375.00
0.008 Oh Kepala Tukang 150,000.00 1,200.00 1,200.00
0.008 Oh Mandor 150,000.00 1,200.00 1,200.00
23,400.00 23,400.00

Jumlah 27,500.00 23,400.00 50,900.00

8.2 1 M2 Pasang Atap Genteng keramik biasa bergalzur


a. Bahan
18 Bh Genteng Keramik biasa/lokal 8,800.00 158,400.00 158,400.00
158,400.00 158,400.00

b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.075 Oh Tukang Kayu 125,000.00 9,375.00 9,375.00
0.008 Oh Kepala Tukang 150,000.00 1,200.00 1,200.00
0.008 Oh Mandor 150,000.00 1,200.00 1,200.00
23,400.00 23,400.00

Jumlah 158,400.00 23,400.00 181,800.00

8.3 1 M2 Pasang Atap Genteng keramik KIA Natural / sejenis


a. Bahan
15 Bh Genteng Keramik KIA Natural atau sejenis 13,200.00 198,000.00 198,000.00
198,000.00 198,000.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.075 Oh Tukang Kayu 125,000.00 9,375.00 9,375.00
0.008 Oh Kepala Tukang 150,000.00 1,200.00 1,200.00
0.008 Oh Mandor 150,000.00 1,200.00 1,200.00
23,400.00 23,400.00

Jumlah 198,000.00 23,400.00 221,400.00

8.4 1 M2 Pasang Atap Genteng keramik KIA Berwarna / sejenis


a. Bahan
15 Bh Genteng Keramik KIA Warna atau sejenis 18,700.00 280,500.00 280,500.00
280,500.00 280,500.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.075 Oh Tukang Kayu 125,000.00 9,375.00 9,375.00
0.008 Oh Kepala Tukang 150,000.00 1,200.00 1,200.00
0.008 Oh Mandor 150,000.00 1,200.00 1,200.00
23,400.00 23,400.00

Jumlah 280,500.00 23,400.00 303,900.00

8.5 1 M' Pasang Bubung Genteng Kodok


a. Bahan
5.000 Bh Genteng Bubung Kodok 4,400.00 22,000.00 22,000.00
8.000 Kg Semen Portland 1,700.00 13,600.00 13,600.00
0.032 M3 Pasir Pasang 118,750.00 3,800.00 3,800.00
39,400.00 39,400.00
b. Tenaga
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.002 Oh Mandor 150,000.00 300.00 300.00
59,300.00 59,300.00

Jumlah 39,400.00 59,300.00 98,700.00

8.6 1 M' Pasang Bubung Genteng Keramik biasa berglazzur


a. Bahan
4.000 Bh Genteng Bubung Keramik lokal 11,000.00 44,000.00 44,000.00
8.000 Kg Semen Portland 1,700.00 13,600.00 13,600.00
0.032 M3 Pasir Pasang 118,750.00 3,800.00 3,800.00
61,400.00 61,400.00

b. Tenaga
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.002 Oh Mandor 150,000.00 300.00 300.00
59,300.00 59,300.00

Jumlah 61,400.00 59,300.00 120,700.00

8.7 1 M' Pasang Bubung Genteng Keramik KIA Natural atau sejenis
a. Bahan
3.000 Bh Genteng Bubung Keramik KIA Natural atau sejenis 22,000.00 66,000.00 66,000.00
8.000 Kg Semen Portland 1,700.00 13,600.00 13,600.00
0.032 M3 Pasir Pasang 118,750.00 3,800.00 3,800.00
83,400.00 83,400.00

b. Tenaga
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.002 Oh Mandor 150,000.00 300.00 300.00
59,300.00 59,300.00

Jumlah 83,400.00 59,300.00 142,700.00

8.8 1 M' Pasang Bubung Genteng Keramik KIA Warna atau sejenis
a. Bahan
3.000 Bh Genteng Bubung Keramik KIA Warna atau sejenis 27,500.00 82,500.00 82,500.00
8.000 Kg Semen Portland 1,700.00 13,600.00 13,600.00
0.032 M3 Pasir Pasang 118,750.00 3,800.00 3,800.00
99,900.00 99,900.00

b. Tenaga
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.002 Oh Mandor 150,000.00 300.00 300.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
59,300.00 59,300.00

Jumlah 99,900.00 59,300.00 159,200.00

8.9 1 M2 Pasang Roof Light Fibreglass Polycarbon


a. Bahan
1.000 M2 Fiber warna Polycarbon 88,000.00 88,000.00 88,000.00
0.050 Kg Paku Biasa /2" - 1"
1
32,500.00 1,625.00 1,625.00
89,625.00 89,625.00

b. Tenaga
0.140 Oh Pekerja 77,500.00 10,850.00 10,850.00
0.067 Oh Tukang Kayu 125,000.00 8,375.00 8,375.00
0.007 Oh Kepala Tukang 150,000.00 1,050.00 1,050.00
0.007 Oh Mandor 150,000.00 1,050.00 1,050.00
21,325.00 21,325.00

Jumlah 89,625.00 21,325.00 110,950.00

8.10 1 M2 Pasang Atap Asbes Gelombang kecil lbr 0,8 tbl 4 mm


a. Bahan
1.100 M2 Asbes Gelombang kecil lebar 80 cm 27,500.00 30,250.00 30,250.00
0.120 Kg Paku Pancing 24,200.00 2,904.00 2,904.00
33,154.00 33,154.00

b. Tenaga
0.140 Oh Pekerja 77,500.00 10,850.00 10,850.00
0.067 Oh Tukang Kayu 125,000.00 8,375.00 8,375.00
0.007 Oh Kepala Tukang 150,000.00 1,050.00 1,050.00
0.007 Oh Mandor 150,000.00 1,050.00 1,050.00
21,325.00 21,325.00

Jumlah 33,154.00 21,325.00 54,479.00

8.11 1 M2 Pasang Atap Asbes Gelombang kecil lbr 1,05 tbl 4 mm


a. Bahan
1.100 M2 Asbes Gelombang kecil lebar 105 cm 35,200.00 38,720.00 38,720.00
0.120 Kg Paku Pancing 24,200.00 2,904.00 2,904.00
41,624.00 41,624.00

b. Tenaga
0.140 Oh Pekerja 77,500.00 10,850.00 10,850.00
0.067 Oh Tukang Kayu 125,000.00 8,375.00 8,375.00
0.007 Oh Kepala Tukang 150,000.00 1,050.00 1,050.00
0.007 Oh Mandor 150,000.00 1,050.00 1,050.00
21,325.00 21,325.00

Jumlah 41,624.00 21,325.00 62,949.00

8.12 1 M2 Pasang Atap Onduline


a. Bahan
1.100 M2 Onduline gel. 75 X 200 cm 74,800.00 82,280.00 82,280.00
0.120 Kg Paku Pancing 24,200.00 2,904.00 2,904.00
85,184.00 85,184.00

b. Tenaga
0.140 Oh Pekerja 77,500.00 10,850.00 10,850.00
0.067 Oh Tukang Kayu 125,000.00 8,375.00 8,375.00
0.007 Oh Kepala Tukang 150,000.00 1,050.00 1,050.00
0.007 Oh Mandor 150,000.00 1,050.00 1,050.00
21,325.00 21,325.00

Jumlah 85,184.00 21,325.00 106,509.00

8.13 1 M2 Pasang Atap Asbes Gelombang besar lbr 1,05 tbl 4 mm


a. Bahan
1.100 M2 Asbes Gelombang besar lebar 105 cm 38,500.00 42,350.00 42,350.00
0.120 Kg Paku Pancing 24,200.00 2,904.00 2,904.00
45,254.00 45,254.00

b. Tenaga
0.140 Oh Pekerja 77,500.00 10,850.00 10,850.00
0.067 Oh Tukang Kayu 125,000.00 8,375.00 8,375.00
0.007 Oh Kepala Tukang 150,000.00 1,050.00 1,050.00
0.007 Oh Mandor 150,000.00 1,050.00 1,050.00
21,325.00 21,325.00

Jumlah 45,254.00 21,325.00 66,579.00

8.14 1 M' Pasang Bubung/nok Asbes Gelombang kecil


a. Bahan
1.100 M' Bubung Asbes Gelombang Kecil 25,850.00 28,435.00 28,435.00
6.000 Bh Paku Asbes 660.00 3,960.00 3,960.00
32,395.00 32,395.00

b. Tenaga
0.084 Oh Pekerja 77,500.00 6,510.00 6,510.00
0.125 Oh Tukang Kayu 125,000.00 15,625.00 15,625.00
0.013 Oh Kepala Tukang 150,000.00 1,950.00 1,950.00
0.004 Oh Mandor 150,000.00 600.00 600.00
24,685.00 24,685.00

Jumlah 32,395.00 24,685.00 57,080.00

8.15 1 M' Pasang Bubung/Nok Asbes Gelombang besar


a. Bahan
1.100 M' Bubung Asbes Gelombang Besar 26,400.00 29,040.00 29,040.00
6.000 Bh Paku Asbes 660.00 3,960.00 3,960.00
33,000.00 33,000.00

b. Tenaga
0.084 Oh Pekerja 77,500.00 6,510.00 6,510.00
0.125 Oh Tukang Kayu 125,000.00 15,625.00 15,625.00
0.013 Oh Kepala Tukang 150,000.00 1,950.00 1,950.00
0.004 Oh Mandor 150,000.00 600.00 600.00
24,685.00 24,685.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

Jumlah 33,000.00 24,685.00 57,685.00

8.16 1 M2 Pasang Atap Beton Cisangkan


a. Bahan
17 Bh Genteng Beton Cisangkan 8,250.00 140,250.00 140,250.00
0.030 Kg Paku Biasa 2" - 5" 28,500.00 855.00 855.00
141,105.00 141,105.00

b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
31,000.00 31,000.00

Jumlah 141,105.00 31,000.00 172,105.00

8.17 1 M2 Pasang Atap Genteng Beton


a. Bahan
11 Bh Genteng Beton 6,270.00 68,970.00 68,970.00
0.030 Kg Paku Biasa 2" - 5" 28,500.00 855.00 855.00
69,825.00 69,825.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
31,000.00 31,000.00

Jumlah 69,825.00 31,000.00 100,825.00

8.18 1 M Pasang Atap Genteng Metal biasa (77 cm X 88 cm)


2

a. Bahan
1.020 M2 Genteng Metal 40,700.00 41,514.00 41,514.00
0.200 Kg Paku Biasa 2" - 5" 28,500.00 5,700.00 5,700.00
47,214.00 47,214.00

b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.001 Oh Mandor 150,000.00 150.00 150.00
29,650.00 29,650.00

Jumlah 47,214.00 29,650.00 76,864.00

8.19 1 M2 Pasang Atap Genteng Metal Zincalume


a. Bahan
1.020 M2 Genteng Metal 176,000.00 179,520.00 179,520.00
0.200 Kg Paku Biasa 2" - 5" 28,500.00 5,700.00 5,700.00
185,220.00 185,220.00

b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.001 Oh Mandor 150,000.00 150.00 150.00
29,650.00 29,650.00

Jumlah 185,220.00 29,650.00 214,870.00

8.20 1 M2 Pasang Atap Genteng Metal Zincalume berpasir mutu A


a. Bahan
1.020 M2 Genteng Metal Zincalume berpasir 93,500.00 95,370.00 95,370.00
0.200 Kg Paku Biasa 2" - 5" 28,500.00 5,700.00 5,700.00
101,070.00 101,070.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.001 Oh Mandor 150,000.00 150.00 150.00
29,650.00 29,650.00

Jumlah 101,070.00 29,650.00 130,720.00

8.21 1 M2 Pasang Atap Genteng Metal Warna


a. Bahan
1.020 M2 Genteng Metal warna 44,000.00 44,880.00 44,880.00
0.200 Kg Paku Biasa 2" - 5" 28,500.00 5,700.00 5,700.00
50,580.00 50,580.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.001 Oh Mandor 150,000.00 150.00 150.00
29,650.00 29,650.00

Jumlah 50,580.00 29,650.00 80,230.00

8.22 1 M2 Pasang Atap Genteng Metal Zincalume berpasir mutu B


a. Bahan
1.020 M2 Genteng Metal Zincalume 66,000.00 67,320.00 67,320.00
berpasir kualitas biasa
0.200 Kg Paku Biasa 2" - 5" 28,500.00 5,700.00 5,700.00
73,020.00 73,020.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.001 Oh Mandor 150,000.00 150.00 150.00
29,650.00 29,650.00

Jumlah 73,020.00 29,650.00 102,670.00

8.23 1 M' Pasang Nok Genteng Beton


a. Bahan
3.500 Bh Nok Genteng Beton 6,600.00 23,100.00 23,100.00
0.050 Kg Paku Biasa 2" - 5" 28,500.00 1,425.00 1,425.00
10.800 Kg Semen Abu-abu 1,700.00 18,360.00 18,360.00
0.032 M3 Pasir Pasang 118,750.00 3,800.00 3,800.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
1.000 Kg Semen Warna 17,500.00 17,500.00 17,500.00
64,185.00 64,185.00

b. Tenaga
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.020 Oh Mandor 150,000.00 3,000.00 3,000.00
62,000.00 62,000.00

Jumlah 64,185.00 62,000.00 126,185.00

8.24 1 M' Pasang Nok Genteng Beton Cisangkan


a. Bahan
5.000 Bh Nok Genteng Beton 6,600.00 33,000.00 33,000.00
0.050 Kg Paku Biasa 2" - 5" 28,500.00 1,425.00 1,425.00
10.800 Kg Semen Abu-abu 1,700.00 18,360.00 18,360.00
0.032 M3 Pasir Pasang 118,750.00 3,800.00 3,800.00
1.000 Kg Semen Warna 17,500.00 17,500.00 17,500.00
74,085.00 74,085.00

b. Tenaga
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.020 Oh Mandor 150,000.00 3,000.00 3,000.00
62,000.00 62,000.00

Jumlah 74,085.00 62,000.00 136,085.00

8.25 1 M' Pasang Nok Genteng Metal


a. Bahan
1.100 Bh Nok Genteng Metal 33,000.00 36,300.00 36,300.00
0.050 Kg Paku Biasa /2" - 1"
1
32,500.00 1,625.00 1,625.00
37,925.00 37,925.00

b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.150 Oh Tukang Kayu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.013 Oh Mandor 150,000.00 1,950.00 1,950.00
42,325.00 42,325.00

Jumlah 37,925.00 42,325.00 80,250.00

8.26 1 M Pasang Atap Seng Gelombang


2

a. Bahan
1.020 M2 Seng Gelombang BJLS 8,167.50 8,330.85 8,330.85
0.020 Kg Paku Biasa /2" - 1"
1
32,500.00 650.00 650.00
8,980.85 8,980.85

b. Tenaga
0.120 Oh Pekerja 77,500.00 9,300.00 9,300.00
0.060 Oh Tukang Kayu 125,000.00 7,500.00 7,500.00
0.006 Oh Kepala Tukang 150,000.00 900.00 900.00
0.006 Oh Mandor 150,000.00 900.00 900.00
18,600.00 18,600.00

Jumlah 8,980.85 18,600.00 27,580.85

8.27 1 M' Pasang Atap Nok Seng


a. Bahan
1 M' Seng Plat BJLS 33 cm X 100 cm 14,520.00 14,520.00 14,520.00
0.040 Kg Paku Biasa /2" - 1"
1
32,500.00 1,300.00 1,300.00
15,820.00 15,820.00

b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.070 Oh Tukang Kayu 125,000.00 8,750.00 8,750.00
0.008 Oh Kepala Tukang 150,000.00 1,200.00 1,200.00
0.006 Oh Mandor 150,000.00 900.00 900.00
22,475.00 22,475.00

Jumlah 15,820.00 22,475.00 38,295.00

8.28 1 M2 Pasang Atap Aluminium


a. Bahan
1.050 M2 Atap Alluminium Gelombang Tebal 0,5 110,000.00 115,500.00 115,500.00
0.020 Kg Paku Hak Panjang 15 cm 63,500.00 1,270.00 1,270.00
116,770.00 116,770.00

b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.750 Oh Tukang Kayu 125,000.00 93,750.00 93,750.00
0.008 Oh Kepala Tukang 150,000.00 1,200.00 1,200.00
0.006 Oh Mandor 150,000.00 900.00 900.00
107,475.00 107,475.00

Jumlah 116,770.00 107,475.00 224,245.00

8.29 1 M' Pasang Nok Aluminium


a. Bahan
1.200 M' Nok Standar 33,000.00 39,600.00 39,600.00
0.040 Kg Paku Hak Panjang 15 cm 63,500.00 2,540.00 2,540.00
42,140.00 42,140.00

b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
1.000 Oh Tukang Kayu 125,000.00 125,000.00 125,000.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
135,750.00 135,750.00

Jumlah 42,140.00 135,750.00 177,890.00

8.30 1 M2 Pasang Aluminium Foil / Sisalation


a. Bahan
1.050 M2 Sisalation / Alluminium Foil 20,350.00 21,367.50 21,367.50
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
21,367.50 21,367.50
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.050 Oh Tukang Kayu 125,000.00 6,250.00 6,250.00
0.005 Oh Kepala Tukang 150,000.00 750.00 750.00
0.008 Oh Mandor 150,000.00 1,200.00 1,200.00
19,825.00 19,825.00

Jumlah 21,367.50 19,825.00 41,192.50

8.31 1 M3 Gording, Sako, Kitau, Blandar kayu Kelas II


(F1) a. Bahan
1.100 M3 Kayu Kelas II 6,600,000.00 7,260,000.00 7,260,000.00
0.250 Kg Paku 28,500.00 7,125.00 7,125.00
7,267,125.00 7,267,125.00
b. Tenaga
15.000 Oh Tukang 125,000.00 1,875,000.00 1,875,000.00
1.500 Oh Kepala Tukang 150,000.00 225,000.00 225,000.00
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.250 Oh Mandor 150,000.00 37,500.00 37,500.00
2,145,250.00 2,145,250.00

Jumlah 7,267,125.00 2,145,250.00 9,412,375.00

8.32 1 M3 Gording, Sako, Kitau, Blandar kayu Kelas III


(F1) a. Bahan
1.100 M3 Kayu Kelas III 3,630,000.00 3,993,000.00 3,993,000.00
0.250 Kg Paku 28,500.00 7,125.00 7,125.00
4,000,125.00 4,000,125.00
b. Tenaga
15.000 Oh Tukang 125,000.00 1,875,000.00 1,875,000.00
1.500 Oh Kepala Tukang 150,000.00 225,000.00 225,000.00
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.250 Oh Mandor 150,000.00 37,500.00 37,500.00
2,145,250.00 2,145,250.00

Jumlah 4,000,125.00 2,145,250.00 6,145,375.00

8.33 1 M2 Rangka atap baja ringan "Superdyma" Al-Magnesium


a. Bahan
2.100 M' Smartruss C 75.100 24,750.00 51,975.00 51,975.00
1.200 M' Smartruss C 75.75 20,680.00 24,816.00 24,816.00
6.200 M' Reng U T S 40 17,930.00 111,166.00 111,166.00
30 Buah Srew / Dynabolt 2,090.00 62,700.00 62,700.00
0.030 M' Valery Gutter Talang Jurai 137,940.00 4,138.20 4,138.20
0.700 M' Strap Bracing 18,700.00 13,090.00 13,090.00
267,885.20 267,885.20
b. Tenaga
0.100 Oh Tukang Terampil 125,000.00 12,500.00 12,500.00
0.100 Oh Tukang biasa 77,500.00 7,750.00 7,750.00
0.050 Oh Kepala Tukang 150,000.00 7,500.00 7,500.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
29,250.00 29,250.00

Jumlah 267,885.20 29,250.00 297,135.20

IX PEKERJAAN LANGIT-LANGIT
9.1 1 M2 Langit-langit Asbes/Eternit ( 1,00 x 1,00 ) m, Tebal 2,7 mm
a. Bahan
1.100 Lbr Asbes/Eternit Tebal 2,7 mm 25,300.00 27,830.00 27,830.00
0.010 Kg Paku 32,500.00 325.00 325.00
28,155.00 28,155.00
b. Tenaga
0.030 Oh Pekerja 77,500.00 2,325.00 2,325.00
0.070 Oh Tukang Kayu 125,000.00 8,750.00 8,750.00
0.007 Oh Kepala Tukang 150,000.00 1,050.00 1,050.00
0.0015 Oh Mandor 150,000.00 225.00 225.00
12,350.00 12,350.00

Jumlah 28,155.00 12,350.00 40,505.00

9.2 1 M Langit-langit Asbes / Eternit ( 1,00 x 1,00 ) m, Tebal 3,5 mm


2

a. Bahan
1.100 Lbr Asbes / Eternit Tebal 3,5 mm 29,700.00 32,670.00 32,670.00
0.010 Kg Paku 32,500.00 325.00 325.00
32,995.00 32,995.00
b. Tenaga
0.030 Oh Pekerja 77,500.00 2,325.00 2,325.00
0.070 Oh Tukang Kayu 125,000.00 8,750.00 8,750.00
0.007 Oh Kepala Tukang 150,000.00 1,050.00 1,050.00
0.0015 Oh Mandor 150,000.00 225.00 225.00
12,350.00 12,350.00

Jumlah 32,995.00 12,350.00 45,345.00

9.3 1 M Langit-langit Kalsiboard ( 1,20 x 2,40 ) m, Tebal 3,5 mm


2

a. Bahan
0.360 Kpg Kalsiboard Tebal 3,5 mm 72,800.00 26,208.00 26,208.00
0.010 Kg Paku 32,500.00 325.00 325.00
26,533.00 26,533.00

b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0035 Oh Mandor 150,000.00 525.00 525.00
19,950.00 19,950.00

Jumlah 26,533.00 19,950.00 46,483.00

9.4 1 M2 Langit-langit Kalsiboard ( 1,20 x 2,40 ) m, Tebal 4,5 mm


a. Bahan
0.360 Kpg Kalsiboard Tebal 4,5 mm 78,500.00 28,260.00 28,260.00
0.010 Kg Paku 32,500.00 325.00 325.00
28,585.00 28,585.00

b. Tenaga

0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00


SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00

0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00

0.0035 Oh Mandor 150,000.00 525.00 525.00

19,950.00 19,950.00

Jumlah 28,585.00 19,950.00 48,535.00

9.5 1
a.M Langit-langit
Bahan
2
0.012 Kg
0.060 Asbes/Eternit,
M3 Paku
Kayu Rangka Kayu Kls. II
Kls. II, Balok
Biasa 6,600,000.00
28,500.00 79,200.00
1,710.00 79,200.00
1,710.00
1.100 M2 Asbes / Eternit tebal 2,7 mm 25,300.00 27,830.00 27,830.00
1.100 M2 Asbes / Eternit tebal 3,5 mm 29,700.00 32,670.00 32,670.00
Tebal 2,7 mm 108,740.00 108,740.00
Tebal 3,5 mm 113,580.00 113,580.00

b. Tenaga
0.180 Oh Pekerja 77,500.00 13,950.00 13,950.00
0.320 Oh Tukang Kayu 125,000.00 40,000.00 40,000.00
0.032 Oh Kepala Tukang 150,000.00 4,800.00 4,800.00
0.009 Oh Mandor 150,000.00 1,350.00 1,350.00
60,100.00 60,100.00

1 M2 Eternit tebal 2,7 mm, rangka kayu kls. II 108,740.00 60,100.00 168,840.00
1 M2 Eternit tebal 3,5 mm, rangka kayu kls. II 113,580.00 60,100.00 173,680.00

9.6 1 M2 Langit-langit Asbes/Eternit, Rangka Kayu Kls. III


a. Bahan
0.012 M3 Kayu Kls. III, Balok 3,630,000.00 43,560.00 43,560.00
0.060 Kg Paku Biasa 28,500.00 1,710.00 1,710.00
1.100 M2 Asbes / Eternit tebal 2,7 mm 25,300.00 27,830.00 27,830.00
1.100 M2 Asbes / Eternit tebal 3,5 mm 29,700.00 32,670.00 32,670.00
Tebal 2,7 mm 73,100.00 73,100.00
Tebal 3,5 mm 77,940.00 77,940.00

b. Tenaga
0.180 Oh Pekerja 77,500.00 13,950.00 13,950.00
0.320 Oh Tukang Kayu 125,000.00 40,000.00 40,000.00
0.032 Oh Kepala Tukang 150,000.00 4,800.00 4,800.00
0.009 Oh Mandor 150,000.00 1,350.00 1,350.00
60,100.00 60,100.00

1 M2 Eternit tebal 2,7 mm, rangka kayu kls. III 73,100.00 60,100.00 133,200.00
1 M2 Eternit tebal 3,5 mm, rangka kayu kls. III 77,940.00 60,100.00 138,040.00

9.7 1 M2 Langit-langit Kalsiboard, Rangka Kayu Kls. II


a. Bahan
0.012 M3 Kayu Kls. II, Balok 6,600,000.00 79,200.00 79,200.00
0.060 Kg Paku Biasa 28,500.00 1,710.00 1,710.00
0.360 Kpg Kalsiboard tebal 3,5 mm 72,800.00 26,208.00 26,208.00
0.360 Kpg Kalsiboard tebal 4,5 mm 78,500.00 28,260.00 28,260.00
Tebal 3,5 mm 107,118.00 107,118.00
Tebal 4,5 mm 109,170.00 109,170.00
b. Tenaga
0.270 Oh Pekerja 77,500.00 20,925.00 20,925.00
0.400 Oh Tukang Kayu 125,000.00 50,000.00 50,000.00
0.040 Oh Kepala Tukang 150,000.00 6,000.00 6,000.00
0.0135 Oh Mandor 150,000.00 2,025.00 2,025.00
78,950.00 78,950.00

1 M2 Kalsiboard tebal 3,5 mm, rangka kayu kls. II 107,118.00 78,950.00 186,068.00
1 M2 Kalsiboard tebal 4,5 mm, rangka kayu kls. II 109,170.00 78,950.00 188,120.00

9.8 1 M2 Langit-langit Kalsiboard, Rangka Kayu Kls. III


a. Bahan
0.012 M3 Kayu Kls. III, Balok 3,630,000.00 43,560.00 43,560.00
0.060 Kg Paku Biasa 28,500.00 1,710.00 1,710.00
0.360 Kpg Kalsiboard tebal 3,5 mm 72,800.00 26,208.00 26,208.00
0.360 Kpg Kalsiboard tebal 4,5 mm 78,500.00 28,260.00 28,260.00
Tebal 3,5 mm 71,478.00 71,478.00
Tebal 4,5 mm 73,530.00 73,530.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
b. Tenaga
0.270 Oh Pekerja 77,500.00 20,925.00 20,925.00
0.400 Oh Tukang Kayu 125,000.00 50,000.00 50,000.00
0.040 Oh Kepala Tukang 150,000.00 6,000.00 6,000.00
0.0135 Oh Mandor 150,000.00 2,025.00 2,025.00
78,950.00 78,950.00

1 M2 Kalsiboard tebal 3,5 mm, rangka kayu kls. III 71,478.00 78,950.00 150,428.00
1 M2 Kalsiboard tebal 4,5 mm, rangka kayu kls. III 73,530.00 78,950.00 152,480.00

9.9 1 M2 Langit-langit Plywood ( 120 x 240 ) cm, Tebal 3 mm


a. Bahan
0.360 Lbr Plywood 4' x 8' x 3 mm 52,700.00 18,972.00 18,972.00
0.030 Kg Paku 32,500.00 975.00 975.00
19,947.00 19,947.00

b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0035 Oh Mandor 150,000.00 525.00 525.00
19,950.00 19,950.00

Jumlah 19,947.00 19,950.00 39,897.00

9.10 1 M2 Langit-langit Plywood ( 120 x 240 ) cm, Tebal 4 mm


a. Bahan
0.360 Lbr Plywood 4' x 8' x 4 mm 82,500.00 29,700.00 29,700.00
0.030 Kg Paku 32,500.00 975.00 975.00
30,675.00 30,675.00

b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0035 Oh Mandor 150,000.00 525.00 525.00
19,950.00 19,950.00

Jumlah 30,675.00 19,950.00 50,625.00

9.11 1 M2 Langit-langit Plywood ( 120 x 240 ) cm, Tebal 6 mm


a. Bahan
0.360 Lbr Plywood 4' x 8' x 6 mm 102,800.00 37,008.00 37,008.00
0.030 Kg Paku 32,500.00 975.00 975.00
37,983.00 37,983.00

b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0035 Oh Mandor 150,000.00 525.00 525.00
19,950.00 19,950.00

Jumlah 37,983.00 19,950.00 57,933.00

9.12 1 M2 Langit-langit Plywood ( 120 x 240 ) cm, Tebal 9 mm


a. Bahan
0.360 Lbr Plywood 4' x 8' x 9 mm 148,500.00 53,460.00 53,460.00
0.030 Kg Paku 32,500.00 975.00 975.00
54,435.00 54,435.00
b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0035 Oh Mandor 150,000.00 525.00 525.00
19,950.00 19,950.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
Jumlah 54,435.00 19,950.00 74,385.00

9.13 1 M2 Langit-langit Plywood ( 120 x 240 ) cm, Tebal 12 mm


a. Bahan
0.360 Lbr Plywood 4' x 8' x 12 mm 189,600.00 68,256.00 68,256.00
0.030 Kg Paku 32,500.00 975.00 975.00
69,231.00 69,231.00

b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0035 Oh Mandor 150,000.00 525.00 525.00
19,950.00 19,950.00

Jumlah 69,231.00 19,950.00 89,181.00

9.14 1 M2 Langit-langit Teakwood (120 X 240), Tebal 3 mm


a. Bahan
1.000 M2 Teakwood 4' x 8' x 3 mm 43,800.00 43,800.00 43,800.00
0.030 Kg Paku 32,500.00 975.00 975.00
44,775.00 44,775.00

b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0035 Oh Mandor 150,000.00 525.00 525.00
19,950.00 19,950.00

Jumlah 44,775.00 19,950.00 64,725.00

9.15 1 M2 Langit-langit Teakwood ( 120 x 240 ) cm, Tebal 4 mm


a. Bahan
1.000 M2 Teakwood 4' x 8' x 4 mm 51,500.00 51,500.00 51,500.00
0.030 Kg Paku 32,500.00 975.00 975.00
52,475.00 52,475.00

b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0035 Oh Mandor 150,000.00 525.00 525.00
19,950.00 19,950.00

Jumlah 52,475.00 19,950.00 72,425.00

9.16 1 M2 Langit-langit Plywood + Rangka Kayu Kls. II


a. Bahan
0.012 M3 Kayu Kls.II, Balok 6,600,000.00 79,200.00 79,200.00
0.060 Kg Paku Biasa 2" - 5" 28,500.00 1,710.00 1,710.00
0.360 Lbr Plywood 4' x 8' x 3 mm 52,700.00 18,972.00 18,972.00
0.360 Lbr Plywood 4' x 8' x 4 mm 82,500.00 29,700.00 29,700.00
0.360 Lbr Plywood 4' x 8' x 6 mm 102,800.00 37,008.00 37,008.00
0.360 Lbr Plywood 4' x 8' x 9 mm 148,500.00 53,460.00 53,460.00
0.360 Lbr Plywood 4' x 8' x 12 mm 189,600.00 68,256.00 68,256.00
Tebal 3 mm 99,882.00 99,882.00
Tebal 4 mm 110,610.00 110,610.00
Tebal 6 mm 117,918.00 117,918.00
Tebal 9 mm 134,370.00 134,370.00
Tebal 12 mm 149,166.00 149,166.00

b. Tenaga
0.270 Oh Pekerja 77,500.00 20,925.00 20,925.00
0.400 Oh Tukang Kayu 125,000.00 50,000.00 50,000.00
0.040 Oh Kepala Tukang 150,000.00 6,000.00 6,000.00
0.0135 Oh Mandor 150,000.00 2,025.00 2,025.00
78,950.00 78,950.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

1 M2 Plywood tebal 3 mm, rangka kayu kls. II 99,882.00 78,950.00 178,832.00


1 M2 Plywood tebal 4 mm, rangka kayu kls. II 110,610.00 78,950.00 189,560.00
1 M2 Plywood tebal 6 mm, rangka kayu kls. II 117,918.00 78,950.00 196,868.00
1 M2 Plywood tebal 9 mm, rangka kayu kls. II 134,370.00 78,950.00 213,320.00
1 M2 Plywood tebal 12 mm, rangka kayu kls. II 149,166.00 78,950.00 228,116.00

9.17 1 M2 Langit-langit Plywood + Rangka Kayu Kls. III


a. Bahan
0.012 M3 Kayu Kls.III, Balok 3,630,000.00 43,560.00 43,560.00
0.060 Kg Paku Biasa 2" - 5" 28,500.00 1,710.00 1,710.00
0.360 Lbr Plywood 4' x 8' x 3 mm 52,700.00 18,972.00 18,972.00
0.360 Lbr Plywood 4' x 8' x 4 mm 82,500.00 29,700.00 29,700.00
0.360 Lbr Plywood 4' x 8' x 6 mm 102,800.00 37,008.00 37,008.00
0.360 Lbr Plywood 4' x 8' x 9 mm 148,500.00 53,460.00 53,460.00
0.360 Lbr Plywood 4' x 8' x 12 mm 189,600.00 68,256.00 68,256.00
Tebal 3 mm 64,242.00 64,242.00
Tebal 4 mm 74,970.00 74,970.00
Tebal 6 mm 82,278.00 82,278.00
Tebal 9 mm 98,730.00 98,730.00
Tebal 12 mm 113,526.00 113,526.00
b. Tenaga
0.270 Oh Pekerja 77,500.00 20,925.00 20,925.00
0.400 Oh Tukang Kayu 125,000.00 50,000.00 50,000.00
0.040 Oh Kepala Tukang 150,000.00 6,000.00 6,000.00
0.0135 Oh Mandor 150,000.00 2,025.00 2,025.00
78,950.00 78,950.00

1 M2 Plywood tebal 3 mm, rangka kayu kls. III 64,242.00 78,950.00 143,192.00
1 M2 Plywood tebal 4 mm, rangka kayu kls. III 74,970.00 78,950.00 153,920.00
1 M2 Plywood tebal 6 mm, rangka kayu kls. III 82,278.00 78,950.00 161,228.00
1 M2 Plywood tebal 9 mm, rangka kayu kls. III 98,730.00 78,950.00 177,680.00
1 M2 Plywood tebal 12 mm, rangka kayu kls. III 113,526.00 78,950.00 192,476.00

9.18 1 M2 Langit-langit Lat Kayu Jati


a. Bahan
0.024 M3 Kayu Jati, Papan 9,075,000.00 217,800.00 217,800.00
0.010 Kg Paku 28,500.00 285.00 285.00
0.050 Kg Paku Sekrup 63,500.00 3,175.00 3,175.00
218,085.00 218,085.00

b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.600 Oh Tukang Kayu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
101,000.00 101,000.00

Jumlah 218,085.00 101,000.00 319,085.00

9.19 1 M2 Langit-langit Soft Board


a. Bahan
0.350 Lbr Soft Board 4' x 8' x 4 mm 74,250.00 25,987.50 25,987.50
0.030 Kg Paku Biasa 32,500.00 975.00 975.00
25,987.50 25,987.50
b. Tenaga
0.600 Oh Pekerja 77,500.00 46,500.00 46,500.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.003 Oh Mandor 150,000.00 450.00 450.00
60,950.00 60,950.00

Jumlah 25,987.50 60,950.00 86,937.50

9.20 1 M' List Langit-langit Gypsum


a. Bahan
1.100 M' List Gypsum Besar 32,800.00 36,080.00 36,080.00
1.100 M' List Gypsum Kecil 17,500.00 19,250.00 19,250.00
0.010 Kg Paku Gypsum 35,000.00 350.00 350.00
List Gypsum besar 36,430.00 36,430.00
List Gypsum kecil 19,600.00 19,600.00
b. Tenaga
0.050 Oh Pekerja 77,500.00 3,875.00 3,875.00
0.050 Oh Tukang Kayu 125,000.00 6,250.00 6,250.00
0.005 Oh Kepala Tukang 150,000.00 750.00 750.00
0.003 Oh Mandor 150,000.00 450.00 450.00
11,325.00 11,325.00

List Gypsum Besar 36,430.00 11,325.00 47,755.00


List Gypsum Kecil 19,600.00 11,325.00 30,925.00

9.21 1 M2 Langit-langit Gypsum Board, Tebal 9 mm


a. Bahan
0.364 Lbr Gypsum Board ( 120 x 240 x 9 ) mm 82,900.00 30,175.60 30,175.60
0.300 Kg Cornes 7,700.00 2,310.00 2,310.00
0.025 roll Textile Tape 7,535.00 188.38 188.38
0.110 Kg Paku Sekrup 63,500.00 6,985.00 6,985.00
0.060 Kg Paku Biasa 2" - 5" 28,500.00 1,710.00
0.040 Kg Paku Gypsum 35,000.00 1,400.00
42,768.98 39,658.98
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.050 Oh Tukang Kayu 125,000.00 6,250.00 6,250.00
0.005 Oh Kepala Tukang 150,000.00 750.00 750.00
0.005 Oh Mandor 150,000.00 750.00 750.00
15,500.00 15,500.00

Jumlah 42,768.98 15,500.00 58,268.98

9.22 1 M2 Langit-langit Gypsum Board 9 mm + Rangka Kayu


a. Bahan
0.012 M3 Kayu Kls.III, Balok 3,630,000.00 43,560.00 43,560.00
0.012 M3 Kayu Kls.II, Balok 6,600,000.00 79,200.00 79,200.00
0.300 Kg Cornes 7,700.00 2,310.00 2,310.00
0.025 roll Textile Tape 7,535.00 188.38 188.38
0.110 Kg Paku Sekrup 63,500.00 6,985.00 6,985.00
0.060 Kg Paku Biasa 2" - 5" 28,500.00 1,710.00 1,710.00
0.040 Kg Paku Gypsum 35,000.00 1,400.00 1,400.00
0.364 Lbr Gypsum Board x 9 mm 82,900.00 30,175.60 30,175.60
Kayu Kls.II, Balok 121,968.98 121,968.98
Kayu Kls.III, Balok 86,328.98 86,328.98

b. Tenaga
0.260 Oh Pekerja 77,500.00 20,150.00 20,150.00
0.400 Oh Tukang Kayu 125,000.00 50,000.00 50,000.00
0.040 Oh Kepala Tukang 150,000.00 6,000.00 6,000.00
0.0130 Oh Mandor 150,000.00 1,950.00 1,950.00
78,100.00 78,100.00

1 M2 Gypsum Board 9 mm, rangka kayu kls. III 86,328.98 78,100.00 164,428.98
1 M2 Gypsum Board 9 mm, rangka kayu kls. II 121,968.98 78,100.00 200,068.98

9.23 1 M2 Langit-langit Gypsum Board 9 mm + Rangka besi hollow


a. Bahan
2.500 Btg Besi hollow galvanis 2/4 27,500.00 68,750.00 68,750.00
0.300 Kg Cornes 7,700.00 2,310.00 2,310.00
0.025 roll Textile Tape 7,535.00 188.38 188.38
0.110 Kg Paku Sekrup 63,500.00 6,985.00 6,985.00
0.060 Kg Paku Biasa 2" - 5" 28,500.00 1,710.00 1,710.00
0.040 Kg Paku Gypsum 35,000.00 1,400.00 1,400.00
0.364 Lbr Gypsum Board x 9 mm 82,900.00 30,175.60 30,175.60
111,518.98 111,518.98
b. Tenaga
0.260 Oh Pekerja 77,500.00 20,150.00 20,150.00
0.400 Oh Tukang Kayu 125,000.00 50,000.00 50,000.00
0.040 Oh Kepala Tukang 150,000.00 6,000.00 6,000.00
0.0130 Oh Mandor 150,000.00 1,950.00 1,950.00
78,100.00 78,100.00

1 M2 Gypsum Board 9 mm, rangka besi hollow 2/4 galvanis 111,518.98 78,100.00 189,618.98

X PEKERJAAN SANITASI

10.1 Memasang 1 Buah Kloset Duduk / Monoblok


a. Bahan
1 Bh Kloset Duduk / Monoblok 594,000.00 594,000.00 594,000.00
Perlengkapan ( 6 % Harga Kloset ) 35,640.00 35,640.00
629,640.00 629,640.00
b. Tenaga
3.300 Oh Pekerja 77,500.00 255,750.00 255,750.00
1.100 Oh Tukang Batu 125,000.00 137,500.00 137,500.00
0.001 Oh Kepala Tukang 150,000.00 150.00 150.00
0.160 Oh Mandor 150,000.00 24,000.00 24,000.00
417,400.00 417,400.00

Jumlah 629,640.00 417,400.00 1,047,040.00

10.2 Memasang 1 Buah Kloset Jongkok Porselen


a. Bahan
1 Bh Kloset Jongkok Porselen 176,000.00 176,000.00 176,000.00
6 Kg Semen Portland 1,700.00 10,200.00 10,200.00
0.010 M3 Pasir Pasang 118,750.00 1,187.50 1,187.50
187,387.50 187,387.50

b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
1.500 Oh Tukang Batu 125,000.00 187,500.00 187,500.00
1.500 Oh Kepala Tukang 150,000.00 225,000.00 225,000.00
0.160 Oh Mandor 150,000.00 24,000.00 24,000.00
514,000.00 514,000.00

Jumlah 187,387.50 514,000.00 701,387.50

10.3 Memasang 1 Buah Kloset Jongkok Teraso


a. Bahan
1 Bh Kloset Jongkok Teraso 35,200.00 35,200.00 35,200.00
7 Bh Bata Merah/kecil 5 x 10x 20 cm 1,375.00 9,625.00 9,625.00
6 Kg Semen Portland 1,700.00 10,200.00 10,200.00
0.010 M3 Pasir Pasang 118,750.00 1,187.50 1,187.50
56,212.50 56,212.50

b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
1.500 Oh Tukang Batu 125,000.00 187,500.00 187,500.00
0.300 Oh Kepala Tukang 150,000.00 45,000.00 45,000.00
0.110 Oh Mandor 150,000.00 16,500.00 16,500.00
326,500.00 326,500.00

Jumlah 56,212.50 326,500.00 382,712.50

10.4 Memasang 1 Buah Urinoir


a. Bahan
1 Bh Urinoir mutu A 181,500.00 181,500.00 181,500.00
Perlengkapan ( 30 % Harga Urinoir ) 54,450.00 54,450.00
6 Kg Semen Portland 1,700.00 10,200.00 10,200.00
0.010 M3 Pasir Pasang 118,750.00 1,187.50 1,187.50
247,337.50 247,337.50
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

b. Tenaga
1.000 Oh Pekerja 77,500.00 77,500.00 77,500.00
1.000 Oh Tukang Batu 125,000.00 125,000.00 125,000.00
0.100 Oh Kepala Tukang 150,000.00 15,000.00 15,000.00
0.100 Oh Mandor 150,000.00 15,000.00 15,000.00
232,500.00 232,500.00

Jumlah 247,337.50 232,500.00 479,837.50

10.5 Memasang 1 Buah Wastafel


a. Bahan
1 Bh Wastafel 335,000.00 335,000.00 335,000.00
Perlengkapan ( 12 % Harga Wastafel ) 40,200.00 40,200.00
6 Kg Semen Portland 1,700.00 10,200.00 10,200.00
0.010 M3 Pasir Pasang 118,750.00 1,187.50 1,187.50
386,587.50 386,587.50

b. Tenaga
1.200 Oh Pekerja 77,500.00 93,000.00 93,000.00
1.450 Oh Tukang Batu 125,000.00 181,250.00 181,250.00
0.150 Oh Kepala Tukang 150,000.00 22,500.00 22,500.00
0.100 Oh Mandor 150,000.00 15,000.00 15,000.00
311,750.00 311,750.00

Jumlah 386,587.50 311,750.00 698,337.50

10.6 Memasang 1 Buah Bak Mandi Teraso Volume 0,30 m3


a. Bahan
1 Bh Bak Teraso 198,000.00 198,000.00 198,000.00
6 Kg Semen Portland 1,700.00 10,200.00 10,200.00
0.010 M3 Pasir Pasang 118,750.00 1,187.50 1,187.50
209,387.50 209,387.50

b. Tenaga
2.100 Oh Pekerja 77,500.00 162,750.00 162,750.00
0.750 Oh Tukang Batu 125,000.00 93,750.00 93,750.00
0.070 Oh Kepala Tukang 150,000.00 10,500.00 10,500.00
0.110 Oh Mandor 150,000.00 16,500.00 16,500.00
283,500.00 283,500.00

Jumlah 209,387.50 283,500.00 492,887.50

10.7 Memasang 1 Buah Bak Mandi Fibreglass Volume 0,30 m3


a. Bahan
1.000 Bh Bak Fibreglass 198,000.00 198,000.00 198,000.00
Perlengkapan ( 18 % Harga Bak Fibreglass ) 35,640.00 35,640.00
233,640.00 233,640.00

b. Tenaga
1.800 Oh Pekerja 77,500.00 139,500.00 139,500.00
2.700 Oh Tukang Batu 125,000.00 337,500.00 337,500.00
0.540 Oh Kepala Tukang 150,000.00 81,000.00 81,000.00
0.110 Oh Mandor 150,000.00 16,500.00 16,500.00
574,500.00 574,500.00

Jumlah 233,640.00 574,500.00 808,140.00

10.8 Memasang 1 Buah Bak Mandi Porselin Batu Bata Volume 0,30 m3
a. Bahan
0.400 M3 Batu Bata 638,500.00 255,400.00 255,400.00
120 Kg Semen Portland 1,700.00 204,000.00 204,000.00
0.300 M3 Pasir Pasang 118,750.00 35,625.00 35,625.00
360 Bh Porselen ( 11 x 11 ) cm 770.00 277,200.00 277,200.00
6 Kg Semen Nat 17,500.00 105,000.00 105,000.00
877,225.00 877,225.00

b. Tenaga
6 Oh Pekerja 77,500.00 465,000.00 465,000.00
3 Oh Tukang Batu 125,000.00 375,000.00 375,000.00
0.300 Oh Kepala Tukang 150,000.00 45,000.00 45,000.00
0.300 Oh Mandor 150,000.00 45,000.00 45,000.00
930,000.00 930,000.00

Jumlah 877,225.00 930,000.00 1,807,225.00

10.9 Memasang 1 Buah Bak Beton Volume 1 m3 Air


a. Bahan
0.900 M3 Beton 1 : 1,5 : 2,5 1,506,080.50 1,355,472.45 1,355,472.45
180 Kg Besi Beton 12,075.00 2,173,500.00 2,173,500.00
8 M3 Kayu Cetakan - - -
5 M2 Ubin Porselen 12,100.00 60,500.00 60,500.00
Perlengkapan ( 10 % Harga Total Bahan ) 153,025.55 153,025.55
3,742,498.00 3,742,498.00

b. Tenaga
3.500 Oh Pekerja 77,500.00 271,250.00 271,250.00
4.500 Oh Tukang Batu 125,000.00 562,500.00 562,500.00
0.900 Oh Kepala Tukang 150,000.00 135,000.00 135,000.00
0.900 Oh Mandor 150,000.00 135,000.00 135,000.00
1,103,750.00 1,103,750.00

Jumlah 3,742,498.00 1,103,750.00 4,846,248.00

10.10 Memasang 1 Buah Bak Fibreglass Volume 1 m3 Air


a. Bahan
1 Bh Bak Fibreglass 198,000.00 198,000.00 198,000.00
Perlengkapan ( 12 % Harga Bak Fibreglass ) 23,760.00 23,760.00
221,760.00 221,760.00

b. Tenaga
3.000 Oh Pekerja 77,500.00 232,500.00 232,500.00
4.500 Oh Tukang Batu 125,000.00 562,500.00 562,500.00
0.900 Oh Kepala Tukang 150,000.00 135,000.00 135,000.00
0.900 Oh Mandor 150,000.00 135,000.00 135,000.00
1,065,000.00 1,065,000.00

Jumlah 221,760.00 1,065,000.00 1,286,760.00


SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

10.11 Memasang 1 M' Pipa Penyalur Air Limbah Jenis Pipa Tanah, dia. 15 cm

a. Bahan
1.600 M' Pipa Tanah (Paralon) dia. 15 cm 136,125.00 217,800.00 217,800.00
0.680 Kg Semen Portland 1,700.00 1,156.00 1,156.00
0.013 M3 Pasir Pasang 118,750.00 1,543.75 1,543.75
0.011 M3 Pasir Urug 82,500.00 907.50 907.50
221,407.25 221,407.25
b. Tenaga
0.060 Oh Pekerja 77,500.00 4,650.00 4,650.00
0.030 Oh Tukang Batu 125,000.00 3,750.00 3,750.00
0.003 Oh Kepala Tukang 150,000.00 450.00 450.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
9,225.00 9,225.00
Jumlah 221,407.25 9,225.00 230,632.25

10.12 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata Ukuran (30 x 30)
cm, Tinggi 35 cm
a. Bahan
0.145 M3 Batu Bata 638,500.00 92,582.50 92,582.50
44.000 Kg Semen Portland 1,700.00 74,800.00 74,800.00
0.070 M3 Pasir Pasang 118,750.00 8,312.50 8,312.50
0.070 M3 Batu Kerikil 440,000.00 30,800.00 30,800.00
1.600 Kg Besi Beton 12,075.00 19,320.00 19,320.00
0.060 M3 Pasir Beton 118,750.00 7,125.00 7,125.00
232,940.00 232,940.00

b. Tenaga
3.200 Oh Pekerja 77,500.00 248,000.00 248,000.00
1.015 Oh Tukang Batu 125,000.00 126,875.00 126,875.00
0.0015 Oh Kepala Tukang 150,000.00 225.00 225.00
0.016 Oh Mandor 150,000.00 2,400.00 2,400.00
377,500.00 377,500.00

Jumlah 232,940.00 377,500.00 610,440.00

10.13 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata Ukuran (45 x 45)
cm, Tinggi 50 cm
a. Bahan
0.250 M3 Batu Bata 638,500.00 159,625.00 159,625.00
77.000 Kg Semen Portland 1,700.00 130,900.00 130,900.00
0.130 M3 Pasir Pasang 118,750.00 15,437.50 15,437.50
0.020 M3 Batu Kerikil 440,000.00 8,800.00 8,800.00
2.600 Kg Besi Beton 12,075.00 31,395.00 31,395.00
0.090 M3 Pasir Beton 118,750.00 10,687.50 10,687.50
356,845.00 356,845.00
b. Tenaga
1.420 Oh Pekerja 77,500.00 110,050.00 110,050.00
0.473 Oh Tukang Batu 125,000.00 59,125.00 59,125.00
0.047 Oh Kepala Tukang 150,000.00 7,050.00 7,050.00
0.071 Oh Mandor 150,000.00 10,650.00 10,650.00
186,875.00 186,875.00

Jumlah 356,845.00 186,875.00 543,720.00

10.14 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata Ukuran (60 x 60)
cm, Tinggi 65 cm
a. Bahan
0.371 M3 Batu Bata 638,500.00 236,883.50 236,883.50
114.000 Kg Semen Portland 1,700.00 193,800.00 193,800.00
0.184 M3 Pasir Pasang 118,750.00 21,850.00 21,850.00
0.033 M3 Batu Kerikil 440,000.00 14,520.00 14,520.00
4.850 Kg Besi Beton 12,075.00 58,563.75 58,563.75
0.120 M3 Pasir Beton 118,750.00 14,250.00 14,250.00
539,867.25 539,867.25

b. Tenaga
2.160 Oh Pekerja 77,500.00 167,400.00 167,400.00
0.720 Oh Tukang Batu 125,000.00 90,000.00 90,000.00
0.100 Oh Tukang Gali 125,000.00 12,500.00 12,500.00
0.072 Oh Kepala Tukang 150,000.00 10,800.00 10,800.00
0.108 Oh Mandor 150,000.00 16,200.00 16,200.00
296,900.00 296,900.00

Jumlah 539,867.25 296,900.00 836,767.25

10.15 Memasang 1 m' Pipa Galvanis Dia. /2"


1

a. Bahan
1.200 M' Pipa Galvanis 20,350.00 24,420.00 24,420.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 7,122.50 7,122.50
31,542.50 31,542.50

b. Tenaga
0.054 Oh Pekerja 77,500.00 4,185.00 4,185.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.027 Oh Mandor 150,000.00 4,050.00 4,050.00
20,835.00 20,835.00

Jumlah 31,542.50 20,835.00 52,377.50

10.16 Memasang 1 m' Pipa Galvanis Dia. /4"


3

a. Bahan
1.200 M' Pipa Galvanis 25,740.00 30,888.00 30,888.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 9,009.00 9,009.00
39,897.00 39,897.00

b. Tenaga
0.054 Oh Pekerja 77,500.00 4,185.00 4,185.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.027 Oh Mandor 150,000.00 4,050.00 4,050.00
20,835.00 20,835.00

Jumlah 39,897.00 20,835.00 60,732.00

10.17 Memasang 1 m' Pipa Galvanis Dia. 1"


a. Bahan
1.200 M' Pipa Galvanis 32,092.50 38,511.00 38,511.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 11,232.38 11,232.38
49,743.38 49,743.38
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

b. Tenaga
0.054 Oh Pekerja 77,500.00 4,185.00 4,185.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.027 Oh Mandor 150,000.00 4,050.00 4,050.00
20,835.00 20,835.00

Jumlah 49,743.38 20,835.00 70,578.38

10.18 Memasang 1 m' Pipa Galvanis Dia. 1 /2"


1

a. Bahan
1.200 M' Pipa Galvanis 45,870.00 55,044.00 55,044.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 16,054.50 16,054.50
71,098.50 71,098.50

b. Tenaga
0.108 Oh Pekerja 77,500.00 8,370.00 8,370.00
0.180 Oh Tukang Batu 125,000.00 22,500.00 22,500.00
0.018 Oh Kepala Tukang 150,000.00 2,700.00 2,700.00
0.0054 Oh Mandor 150,000.00 810.00 810.00
34,380.00 34,380.00

Jumlah 71,098.50 34,380.00 105,478.50

10.19 Memasang 1 m' Pipa Galvanis Dia. 3"


a. Bahan
1.200 M' Pipa Galvanis 119,350.00 143,220.00 143,220.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 41,772.50 41,772.50
184,992.50 184,992.50

b. Tenaga
0.108 Oh Pekerja 77,500.00 8,370.00 8,370.00
0.180 Oh Tukang Batu 125,000.00 22,500.00 22,500.00
0.018 Oh Kepala Tukang 150,000.00 2,700.00 2,700.00
0.0054 Oh Mandor 150,000.00 810.00 810.00
34,380.00 34,380.00

Jumlah 184,992.50 34,380.00 219,372.50

10.20 Memasang 1 m' Pipa Galvanis Dia. 4"


a. Bahan
1.200 M' Pipa Galvanis 155,540.00 186,648.00 186,648.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 54,439.00 54,439.00
241,087.00 241,087.00
b. Tenaga
0.135 Oh Pekerja 77,500.00 10,462.50 10,462.50
0.225 Oh Tukang Batu 125,000.00 28,125.00 28,125.00
0.0225 Oh Kepala Tukang 150,000.00 3,375.00 3,375.00
0.0068 Oh Mandor 150,000.00 1,020.00 1,020.00
42,982.50 42,982.50

Jumlah 241,087.00 42,982.50 284,069.50

10.21 Memasang 1 m' Pipa PVC Tipe AW Dia. /2"


1

a. Bahan
1.200 M' Pipa PVC 6,850.00 8,220.00 8,220.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 2,397.50 2,397.50
10,617.50 10,617.50
b. Tenaga
0.036 Oh Pekerja 77,500.00 2,790.00 2,790.00
0.060 Oh Tukang Batu 125,000.00 7,500.00 7,500.00
0.006 Oh Kepala Tukang 150,000.00 900.00 900.00
0.0018 Oh Mandor 150,000.00 270.00 270.00
11,460.00 11,460.00

Jumlah 10,617.50 11,460.00 22,077.50

10.22 Memasang 1 m' Pipa PVC Tipe AW Dia. /4"


3

a. Bahan
1.200 M' Pipa PVC 7,900.00 9,480.00 9,480.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 2,765.00 2,765.00
12,245.00 12,245.00
b. Tenaga
0.036 Oh Pekerja 77,500.00 2,790.00 2,790.00
0.060 Oh Tukang Batu 125,000.00 7,500.00 7,500.00
0.006 Oh Kepala Tukang 150,000.00 900.00 900.00
0.0018 Oh Mandor 150,000.00 270.00 270.00
11,460.00 11,460.00

Jumlah 12,245.00 11,460.00 23,705.00

10.23 Memasang 1 m' Pipa PVC Tipe AW Dia. 1"


a. Bahan
1.200 M' Pipa PVC 9,800.00 11,760.00 11,760.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 3,430.00 3,430.00
15,190.00 15,190.00
b. Tenaga
0.036 Oh Pekerja 77,500.00 2,790.00 2,790.00
0.060 Oh Tukang Batu 125,000.00 7,500.00 7,500.00
0.006 Oh Kepala Tukang 150,000.00 900.00 900.00
0.0018 Oh Mandor 150,000.00 270.00 270.00
11,460.00 11,460.00

Jumlah 15,190.00 11,460.00 26,650.00

10.24 Memasang 1 m' Pipa PVC Tipe AW Dia. 1 /2"


1

a. Bahan
1.200 M' Pipa PVC 16,900.00 20,280.00 20,280.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 5,915.00 5,915.00
26,195.00 26,195.00
b. Tenaga
0.036 Oh Pekerja 77,500.00 2,790.00 2,790.00
0.060 Oh Tukang Batu 125,000.00 7,500.00 7,500.00
0.006 Oh Kepala Tukang 150,000.00 900.00 900.00
0.0018 Oh Mandor 150,000.00 270.00 270.00
11,460.00 11,460.00

Jumlah 26,195.00 11,460.00 37,655.00


SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

10.25 Memasang 1 m' Pipa PVC Tipe AW Dia. 2"


a. Bahan
1.200 M' Pipa PVC 20,150.00 24,180.00 24,180.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 7,052.50 7,052.50
31,232.50 31,232.50

b. Tenaga
0.054 Oh Pekerja 77,500.00 4,185.00 4,185.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.0027 Oh Mandor 150,000.00 405.00 405.00
17,190.00 17,190.00

Jumlah 31,232.50 17,190.00 48,422.50

10.26 Memasang 1 m' Pipa PVC Tipe AW Dia. 3"


a. Bahan
1.200 M' Pipa PVC 38,700.00 46,440.00 46,440.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 13,545.00 13,545.00
59,985.00 59,985.00
b. Tenaga
0.081 Oh Pekerja 77,500.00 6,277.50 6,277.50
0.135 Oh Tukang Batu 125,000.00 16,875.00 16,875.00
0.0135 Oh Kepala Tukang 150,000.00 2,025.00 2,025.00
0.0041 Oh Mandor 150,000.00 615.00 615.00
25,792.50 25,792.50

Jumlah 59,985.00 25,792.50 85,777.50

10.27 Memasang 1 m' Pipa PVC Tipe AW Dia. 4"


a. Bahan
1.200 M' Pipa PVC 59,500.00 71,400.00 71,400.00
Perlengkapan ( 35 % Harga Pipa Galvanis ) 20,825.00 20,825.00
92,225.00 92,225.00

b. Tenaga
0.081 Oh Pekerja 77,500.00 6,277.50 6,277.50
0.135 Oh Tukang Batu 125,000.00 16,875.00 16,875.00
0.0135 Oh Kepala Tukang 150,000.00 2,025.00 2,025.00
0.0041 Oh Mandor 150,000.00 615.00 615.00
25,792.50 25,792.50

Jumlah 92,225.00 25,792.50 118,017.50

10.28 Memasang 1 Buah Bak Cuci Piring Stainless Steel


a. Bahan
1 Bh Bak Cuci Stainless Steel 212,300.00 212,300.00 212,300.00
1 Set Kran air+ Asesories 25,000.00 25,000.00 25,000.00
237,300.00 237,300.00
b. Tenaga
0.030 Oh Pekerja 77,500.00 2,325.00 2,325.00
0.300 Oh Tukang Batu 125,000.00 37,500.00 37,500.00
0.030 Oh Kepala Tukang 150,000.00 4,500.00 4,500.00
0.0015 Oh Mandor 150,000.00 225.00 225.00
44,550.00 44,550.00

Jumlah 237,300.00 44,550.00 281,850.00

10.29 Memasang 1 Buah Bak Cuci Piring Teraso


a. Bahan
1 Bh Bak Cuci Teraso 357,500.00 357,500.00 357,500.00
1 Set Kran air+ Asesories 25,000.00 25,000.00 25,000.00
20 Kg Semen Portland 1,700.00 34,000.00 34,000.00
0.050 M3 Pasir pasang 118,750.00 5,937.50 5,937.50
422,437.50 422,437.50
b. Tenaga
0.050 Oh Pekerja 77,500.00 3,875.00 3,875.00
0.500 Oh Tukang Batu 125,000.00 62,500.00 62,500.00
0.050 Oh Kepala Tukang 150,000.00 7,500.00 7,500.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
74,250.00 74,250.00

Jumlah 422,437.50 74,250.00 496,687.50

10.30 Memasang 1 Buah Kran Dia. /4" atau /2"


3 1

a. Bahan
1.000 Bh Kran Air 23,800.00 23,800.00 23,800.00
0.025 Bh Seal Tape 5,500.00 137.50 137.50
23,937.50 23,937.50

b. Tenaga
0.010 Oh Pekerja 77,500.00 775.00 775.00
0.100 Oh Tukang Batu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.005 Oh Mandor 150,000.00 750.00 750.00
15,525.00 15,525.00

Jumlah 23,937.50 15,525.00 39,462.50

10.31 1 Bh Septiktank 1,5 m x 2,0 m x 1 m dan Resapan


10.5 M3 Galian Tanah 37,000.00 388,500.00 388,500.00
2.625 M3 Urugan Kembali 17,730.00 46,541.25 46,541.25
8.400 M2 Pas. Batu Bata 1 : 3 342,196.25 2,874,448.50 2,874,448.50
0.300 M3 Beton Tumbuk 1 : 3 : 5 1,058,625.04 317,587.51 317,587.51
13.5 M2 Plesteran 1 : 2 54,502.75 735,787.13 735,787.13
0.2 M3 Plat Beton bertulang (besi 100kg,1/2 dinding)1 : 2 : 3 3,100,273.48 620,054.70 620,054.70
1 Bh Pipa Hawa 2" 20,000.00 20,000.00 20,000.00

Resapan
0.750 M3 Koral Beton 518,850.62 389,137.97 389,137.97
1 M3 Pasir Pasang 118,750.00 118,750.00 118,750.00
4 M' Pipa dia. 4" 59,500.00 238,000.00 238,000.00
2 Bh Buis Beton dia. 50 cm 75,000.00 150,000.00 150,000.00
10 Kg Ijuk 9,900.00 99,000.00 99,000.00
5,997,807.05 5,997,807.05

Jumlah 5,997,807.05 5,997,807.05

XI PEKERJAAN BESI DAN ALUMINIUM

11.1 1 Kg Pasang besi WF dan Rangka Atap Baja


a. Bahan
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
1.100 Kg Besi Profil WF 11,542.65 12,696.92 12,696.92
0.080 Kg Meni Besi 46,200.00 3,696.00 3,696.00
16,392.92 16,392.92

b. Tenaga
0.006 Oh Tukang Besi 125,000.00 750.00 750.00
0.060 Oh Pekerja 77,500.00 4,650.00 4,650.00
0.006 Oh Kepala Tukang 150,000.00 900.00 900.00
0.0003 Oh Mandor 150,000.00 45.00 45.00
6,345.00 6,345.00

Jumlah 16,392.92 6,345.00 22,737.92

11.2 1 Kg Pasang besi CNP,INP,L dan Rangka Atap Baja


a. Bahan
1.100 Kg Besi CNP,INP dan L 16,500.00 18,150.00 18,150.00
0.080 Kg Meni Besi 46,200.00 3,696.00 3,696.00
21,846.00 21,846.00
b. Tenaga
0.006 Oh Tukang 125,000.00 750.00 750.00
0.006 Oh Kepala Tukang 150,000.00 900.00 900.00
0.06 Oh Pekerja 77,500.00 4,650.00 4,650.00
0.0003 Oh Mandor 150,000.00 45.00 45.00
6,345.00 6,345.00

Jumlah 21,846.00 6,345.00 28,191.00

11.3 1 m2 Pasang Pintu Besi Baja


a. Bahan
1.000 M2 Pintu Besi Baja 2,145,000.00 2,145,000.00 2,145,000.00
2,145,000.00 2,145,000.00

b. Tenaga
0.650 Oh Tukang Besi Konstruksi 125,000.00 81,250.00 81,250.00
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.065 Oh Kepala Tukang 150,000.00 9,750.00 9,750.00
0.032 Oh Mandor 150,000.00 4,800.00 4,800.00
146,175.00 146,175.00

Jumlah 2,145,000.00 146,175.00 2,291,175.00

11.4 1 m2 Pasang Jendela Besi


a. Bahan
1.000 M2 Jendela Besi 330,000.00 330,000.00 330,000.00
330,000.00 330,000.00

b. Tenaga
1.050 Oh Tukang Besi Konstruksi 125,000.00 131,250.00 131,250.00
1.050 Oh Pekerja 77,500.00 81,375.00 81,375.00
0.105 Oh Kepala Tukang 150,000.00 15,750.00 15,750.00
0.00525 Oh Mandor 150,000.00 787.50 787.50
229,162.50 229,162.50

Jumlah 330,000.00 229,162.50 559,162.50

11.5 1 m Pasang Pintu Lipat


2

a. Bahan
1.000 M2 Pintu Lipat 418,000.00 418,000.00 418,000.00
418,000.00 418,000.00
b. Tenaga
1.050 Oh Tukang Besi Konstruksi 125,000.00 131,250.00 131,250.00
1.050 Oh Pekerja 77,500.00 81,375.00 81,375.00
0.105 Oh Kepala Tukang 150,000.00 15,750.00 15,750.00
0.0052 Oh Mandor 150,000.00 780.00 780.00
229,155.00 229,155.00

Jumlah 418,000.00 229,155.00 647,155.00

11.6 1 m2 Pasang Pintu Sunscreen Alluminium


a. Bahan
1.000 M2 Sunscreen Alluminium 412,500.00 412,500.00 412,500.00
412,500.00 412,500.00

b. Tenaga
0.800 Oh Tukang Besi Konstruksi 125,000.00 100,000.00 100,000.00
0.080 Oh Pekerja 77,500.00 6,200.00 6,200.00
0.080 Oh Kepala Tukang 150,000.00 12,000.00 12,000.00
0.004 Oh Mandor 150,000.00 600.00 600.00
118,800.00 118,800.00

Jumlah 412,500.00 118,800.00 531,300.00

11.7 1 m Pasang Sunscreen Besi Holo 30/30


2

a. Bahan
1.000 Btg Besi Holo 30/30 154,000.00 154,000.00 154,000.00
154,000.00 154,000.00
b. Tenaga
0.800 Oh Tukang Besi Konstruksi 125,000.00 100,000.00 100,000.00
0.080 Oh Pekerja 77,500.00 6,200.00 6,200.00
0.080 Oh Kepala Tukang 150,000.00 12,000.00 12,000.00
0.004 Oh Mandor 150,000.00 600.00 600.00
118,800.00 118,800.00

Jumlah 154,000.00 118,800.00 272,800.00

11.8 1 m Pasang Rolling Door


2

a. Bahan
1.000 M2 Roll Door 643,500.00 643,500.00 643,500.00
643,500.00 643,500.00

b. Tenaga
1.500 Oh Tukang Besi Konstruksi 125,000.00 187,500.00 187,500.00
1.050 Oh Pekerja 77,500.00 81,375.00 81,375.00
0.105 Oh Kepala Tukang 150,000.00 15,750.00 15,750.00
0.0052 Oh Mandor 150,000.00 780.00 780.00
285,405.00 285,405.00

Jumlah 643,500.00 285,405.00 928,905.00

11.9 1 m2 Pasang Pintu Alluminium


a. Bahan
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
1.000 M2 Pintu Alluminium 704,000.00 704,000.00 704,000.00
704,000.00 704,000.00

b. Tenaga
1.050 Oh Tukang Besi Konstruksi 125,000.00 131,250.00 131,250.00
1.050 Oh Pekerja 77,500.00 81,375.00 81,375.00
0.105 Oh Kepala Tukang 150,000.00 15,750.00 15,750.00
0.0052 Oh Mandor 150,000.00 780.00 780.00
229,155.00 229,155.00

Jumlah 704,000.00 229,155.00 933,155.00

11.10 1 m2 Pasang Hordeng Vertikals Blinds


Bahan
1.000 M2 Vertikals Blinds 104,500.00 104,500.00 104,500.00
104,500.00 104,500.00

b. Tenaga
0.350 Oh Tukang Kayu 125,000.00 43,750.00 43,750.00
0.350 Oh Pekerja 77,500.00 27,125.00 27,125.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.00175 Oh Mandor 150,000.00 262.50 262.50
76,387.50 76,387.50

Jumlah 104,500.00 76,387.50 180,887.50

11.11 1 m2 Pasang Hordeng Horizontal Blinds (aluminium)


Bahan
1.000 M2 Horizontal Blinds 101,200.00 101,200.00 101,200.00
101,200.00 101,200.00

b. Tenaga
0.350 Oh Tukang Kayu 125,000.00 43,750.00 43,750.00
0.350 Oh Pekerja 77,500.00 27,125.00 27,125.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.00175 Oh Mandor 150,000.00 262.50 262.50
76,387.50 76,387.50

Jumlah 101,200.00 76,387.50 177,587.50

11.12 1 m2 Pasang Terali Besi Strip


a. Bahan
11.500 M' Besi Strip 2 x 3 5,500.00 63,250.00 63,250.00
63,250.00 63,250.00

b. Tenaga
1.200 Oh Tukang Las 125,000.00 150,000.00 150,000.00
1.200 Oh Pekerja 77,500.00 93,000.00 93,000.00
0.012 Oh Kepala Tukang 150,000.00 1,800.00 1,800.00
0.00060 Oh Mandor 150,000.00 90.00 90.00
244,890.00 244,890.00

Jumlah 63,250.00 244,890.00 308,140.00

11.13 1 m Pasang Kawat Harmonika


2

a. Bahan
1.100 M2 Kawat Harmonika 42,900.00 47,190.00 47,190.00
0.020 Kg Paku Biasa /2" - 1"
1
32,500.00 650.00 650.00
0.0018 M3 Kayu Kls.III, Papan 3,630,000.00 6,534.00 6,534.00
54,374.00 54,374.00

b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0005 Oh Mandor 150,000.00 75.00 75.00
21,825.00 21,825.00

Jumlah 54,374.00 21,825.00 76,199.00

11.14 1 m Pasang Kawat Nyamuk


2

a. Bahan
1.100 M2 Kawat Nyamuk 19,800.00 21,780.00 21,780.00
0.020 Kg Paku Biasa /2" - 1"
1
32,500.00 650.00 650.00
0.0018 M3 Kayu Kls.III, Papan 3,630,000.00 6,534.00 6,534.00
28,964.00 28,964.00

b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0005 Oh Mandor 150,000.00 75.00 75.00
21,825.00 21,825.00

Jumlah 28,964.00 21,825.00 50,789.00


11.15 1 m2 Pasang Kawat Kassa
a. Bahan
1.100 M2 Kawat Kassa 16,500.00 18,150.00 18,150.00
0.020 Kg Paku Biasa /2" - 1"
1
32,500.00 650.00 650.00
0.0018 M3 Kayu Kls.III, Papan 3,630,000.00 6,534.00 6,534.00
25,334.00 25,334.00

b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0005 Oh Mandor 150,000.00 75.00 75.00
21,825.00 21,825.00

Jumlah 25,334.00 21,825.00 47,159.00

11.16 1 m Pasang Kawat Burung


2

a. Bahan
1.100 M2 Kawat Burung 22,000.00 24,200.00 24,200.00
0.020 Kg Paku Biasa /2" - 1"
1
32,500.00 650.00 650.00
0.0018 M3 Kayu Kls.III, Papan 3,630,000.00 6,534.00 6,534.00
31,384.00 31,384.00
b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0005 Oh Mandor 150,000.00 75.00 75.00
21,825.00 21,825.00

Jumlah 31,384.00 21,825.00 53,209.00

11.17 1 m2 Pasang Jendela Nako dan Tralis


a. Bahan
1.100 M2 Jendela Nako 148,500.00 163,350.00 163,350.00
0.020 Kg Paku Biasa /2" - 1" atau Sekrup
1
32,500.00 650.00 650.00
0.025 Kg Besi Strip 11,000.00 275.00 275.00
164,275.00 164,275.00
b. Tenaga
0.200 Oh Pekerja 77,500.00 15,500.00 15,500.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.001 Oh Mandor 150,000.00 150.00 150.00
43,650.00 43,650.00

Jumlah 164,275.00 43,650.00 207,925.00

11.18 1 m' Pasang Talang Datar, Seng BJLS


a. Bahan
0.500 Lbr Seng Plat 3' x 6' bjls 116,600.00 58,300.00 58,300.00
0.015 Kg Paku Biasa /2" - 1"
1
32,500.00 487.50 487.50
0.0096 M3 Kayu Kls.III, Papan 3,630,000.00 34,848.00 34,848.00
0.250 Kg Flincote / Meni Besi 46,200.00 11,550.00 11,550.00
105,185.50 105,185.50

b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.400 Oh Tukang Kayu 125,000.00 50,000.00 50,000.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.00125 Oh Mandor 150,000.00 187.50 187.50
65,562.50 65,562.50

Jumlah 105,185.50 65,562.50 170,748.00

11.19 1 m' Pasang Talang Miring, Seng BJLS


a. Bahan
0.500 Lbr Seng Plat 3' x 6' bjls 116,600.00 58,300.00 58,300.00
0.015 Kg Paku Biasa /2" - 1"
1
32,500.00 487.50 487.50
0.019 M3 Kayu Kls.III, Papan 3,630,000.00 68,970.00 68,970.00
0.300 Kg Flincote / Meni Besi 46,200.00 13,860.00 13,860.00
141,617.50 141,617.50

b. Tenaga
0.040 Oh Pekerja 77,500.00 3,100.00 3,100.00
0.400 Oh Tukang Kayu 125,000.00 50,000.00 50,000.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.00125 Oh Mandor 150,000.00 187.50 187.50
57,037.50 57,037.50

Jumlah 141,617.50 57,037.50 198,655.00

11.20 1 m' Pasang Talang /2 Lingkaran Dia. 10 cm, Seng BJLS


1

a. Bahan
0.300 Lbr Seng Plat 3' x 6' bjls 116,600.00 34,980.00 34,980.00
0.100 Kg Paku Biasa /2" - 1"
1
32,500.00 3,250.00 3,250.00
0.019 M3 Kayu Kls.III, Papan 3,630,000.00 68,970.00 68,970.00
0.500 Kg Besi Strip 11,000.00 5,500.00 5,500.00
112,700.00 112,700.00

b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
0.250 Oh Tukang Kayu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.00125 Oh Mandor 150,000.00 187.50 187.50
46,812.50 46,812.50

Jumlah 112,700.00 46,812.50 159,512.50

XII PEKERJAAN KUNCI DAN KACA

12.1 1 Buah Pasang Kunci Tanam mutu B


a. Bahan
1.000 Bh Kunci Tanam mutu B 168,500.00 168,500.00 168,500.00
168,500.00 168,500.00

b. Tenaga
0.060 Oh Pekerja 77,500.00 4,650.00 4,650.00
0.600 Oh Tukang Kayu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.003 Oh Mandor 150,000.00 450.00 450.00
89,100.00 89,100.00

Jumlah 168,500.00 89,100.00 257,600.00

12.2 1 Buah Pasang Kunci Tanam Biasa


a. Bahan
1.000 Bh Kunci Tanam Biasa 50,000.00 50,000.00 50,000.00
50,000.00 50,000.00
b. Tenaga
0.010 Oh Pekerja 77,500.00 775.00 775.00
0.500 Oh Tukang Kayu 125,000.00 62,500.00 62,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.005 Oh Mandor 150,000.00 750.00 750.00
65,525.00 65,525.00

Jumlah 50,000.00 65,525.00 115,525.00

12.3 1 Buah Pasang Kunci Tanam Kamar Mandi


a. Bahan
1.000 Bh Kunci Tanam Kamar Mandi 38,600.00 38,600.00 38,600.00
38,600.00 38,600.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

b. Tenaga
0.005 Oh Pekerja 77,500.00 387.50 387.50
0.500 Oh Tukang Kayu 125,000.00 62,500.00 62,500.00
0.005 Oh Kepala Tukang 150,000.00 750.00 750.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
64,012.50 64,012.50

Jumlah 38,600.00 64,012.50 102,612.50

12.4 1 Buah Pasang Engsel Pintu


a. Bahan
1.000 Bh Engsel Pintu 19,800.00 19,800.00 19,800.00
19,800.00 19,800.00

b. Tenaga
0.015 Oh Pekerja 77,500.00 1,162.50 1,162.50
0.150 Oh Tukang Kayu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.00075 Oh Mandor 150,000.00 112.50 112.50
22,275.00 22,275.00

Jumlah 19,800.00 22,275.00 42,075.00

12.5 1 Buah Pasang Engsel Jendela Kuningan


a. Bahan
1.000 Bh Engsel Kuningan Jendela 33,000.00 33,000.00 33,000.00
33,000.00 33,000.00
b. Tenaga
0.010 Oh Pekerja 77,500.00 775.00 775.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0005 Oh Mandor 150,000.00 75.00 75.00
14,850.00 14,850.00

Jumlah 33,000.00 14,850.00 47,850.00

12.6 1 Buah Pasang Engsel Angin


a. Bahan
1.000 Bh Engsel Angin 19,800.00 19,800.00 19,800.00
19,800.00 19,800.00
b. Tenaga
0.020 Oh Pekerja 77,500.00 1,550.00 1,550.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
31,050.00 31,050.00

Jumlah 19,800.00 31,050.00 50,850.00


12.7 1 Buah Pasang Kait Angin
a. Bahan
1.000 Bh Kait Angin 16,500.00 16,500.00 16,500.00
16,500.00 16,500.00
b. Tenaga
0.015 Oh Pekerja 77,500.00 1,162.50 1,162.50
0.150 Oh Tukang Kayu 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.00075 Oh Mandor 150,000.00 112.50 112.50
22,275.00 22,275.00

Jumlah 16,500.00 22,275.00 38,775.00

12.8 1 Buah Pasang Door Closer


a. Bahan
1.000 Bh Door Closer 264,000.00 264,000.00 264,000.00
264,000.00 264,000.00

b. Tenaga
0.050 Oh Pekerja 77,500.00 3,875.00 3,875.00
0.500 Oh Tukang Kayu 125,000.00 62,500.00 62,500.00
0.050 Oh Kepala Tukang 150,000.00 7,500.00 7,500.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
74,250.00 74,250.00

Jumlah 264,000.00 74,250.00 338,250.00

12.9 1 Buah Pasang Kunci Selot


a. Bahan
1.000 Bh Kunci Selot 14,300.00 14,300.00 14,300.00
14,300.00 14,300.00
b. Tenaga
0.020 Oh Pekerja 77,500.00 1,550.00 1,550.00
0.200 Oh Tukang Kayu 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.001 Oh Mandor 150,000.00 150.00 150.00
29,700.00 29,700.00

Jumlah 14,300.00 29,700.00 44,000.00

12.10 1 Buah Pasang Pegangan Pintu / Door Holder


a. Bahan
1.000 Bh Door Holder 33,000.00 33,000.00 33,000.00
33,000.00 33,000.00
b. Tenaga
0.050 Oh Pekerja 77,500.00 3,875.00 3,875.00
0.500 Oh Tukang Kayu 125,000.00 62,500.00 62,500.00
0.050 Oh Kepala Tukang 150,000.00 7,500.00 7,500.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
74,250.00 74,250.00

Jumlah 33,000.00 74,250.00 107,250.00

12.11 1 Buah Pasang Door Stop


a. Bahan
1.000 Bh Door Stop 24,200.00 24,200.00 24,200.00
24,200.00 24,200.00
b. Tenaga
0.010 Oh Pekerja 77,500.00 775.00 775.00
0.100 Oh Tukang Kayu 125,000.00 12,500.00 12,500.00
0.010 Oh Kepala Tukang 150,000.00 1,500.00 1,500.00
0.0005 Oh Mandor 150,000.00 75.00 75.00
14,850.00 14,850.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

Jumlah 24,200.00 14,850.00 39,050.00

12.12 1 Buah Pasang Rel Pintu Dorong


a. Bahan
1.000 Bh Rel Pintu Dorong 264,000.00 264,000.00 264,000.00
264,000.00 264,000.00
b. Tenaga
0.060 Oh Pekerja 77,500.00 4,650.00 4,650.00
0.600 Oh Tukang Kayu 125,000.00 75,000.00 75,000.00
0.060 Oh Kepala Tukang 150,000.00 9,000.00 9,000.00
0.003 Oh Mandor 150,000.00 450.00 450.00
89,100.00 89,100.00

Jumlah 264,000.00 89,100.00 353,100.00

12.13 1 Buah Pasang Kunci Lemari


a. Bahan
1.000 Bh Kunci Lemari 8,800.00 8,800.00 8,800.00
8,800.00 8,800.00
b. Tenaga
0.025 Oh Pekerja 77,500.00 1,937.50 1,937.50
0.250 Oh Tukang Kayu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.00125 Oh Mandor 150,000.00 187.50 187.50
37,125.00 37,125.00

Jumlah 8,800.00 37,125.00 45,925.00

12.14 1 m2 Pasang Kaca, Tebal 3 mm


a. Bahan
1.100 M2 Kaca Tebal 3 mm 71,500.00 78,650.00 78,650.00
78,650.00 78,650.00
b. Tenaga
0.015 Oh Pekerja 77,500.00 1,162.50 1,162.50
0.150 Oh Tukang Kayu/kaca 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.00075 Oh Mandor 150,000.00 112.50 112.50
22,275.00 22,275.00

Jumlah 78,650.00 22,275.00 100,925.00

12.15 1 m2 Pasang Kaca, Tebal 5 mm


a. Bahan
1.100 M2 Kaca Tebal 5 mm 121,000.00 133,100.00 133,100.00
133,100.00 133,100.00

b. Tenaga
0.015 Oh Pekerja 77,500.00 1,162.50 1,162.50
0.150 Oh Tukang Kayu/kaca 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.00075 Oh Mandor 150,000.00 112.50 112.50
22,275.00 22,275.00

Jumlah 133,100.00 22,275.00 155,375.00

12.16 1 m Pasang Kaca, Tebal 8 mm


2

a. Bahan
1.100 M2 Kaca Polos 220,000.00 242,000.00 242,000.00
242,000.00 242,000.00

b. Tenaga
0.0165 Oh Pekerja 77,500.00 1,278.75 1,278.75
0.165 Oh Tukang Kayu/kaca 125,000.00 20,625.00 20,625.00
0.0165 Oh Kepala Tukang 150,000.00 2,475.00 2,475.00
0.0008 Oh Mandor 150,000.00 120.00 120.00
24,498.75 24,498.75

Jumlah 242,000.00 24,498.75 266,498.75


12.17 1 m2 Pasang Kaca Buram, Tebal 12 mm
a. Bahan
1.100 M2 Kaca Buram 429,000.00 471,900.00 471,900.00
0.050 Kg Sealent 45,000.00 2,250.00 2,250.00
474,150.00 474,150.00

b. Tenaga
0.025 Oh Pekerja 77,500.00 1,937.50 1,937.50
0.250 Oh Tukang Kayu/kaca 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.00125 Oh Mandor 150,000.00 187.50 187.50
37,125.00 37,125.00

Jumlah 474,150.00 37,125.00 511,275.00

12.18 1 m Pasang Kaca Cermin, Tebal 3 mm


2

a. Bahan
1.100 M2 Kaca Cermin Tebal 3 mm 136,400.00 150,040.00 150,040.00
150,040.00 150,040.00

b. Tenaga
0.015 Oh Pekerja 77,500.00 1,162.50 1,162.50
0.150 Oh Tukang Kayu/kaca 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.00075 Oh Mandor 150,000.00 112.50 112.50
22,275.00 22,275.00

Jumlah 150,040.00 22,275.00 172,315.00

12.19 1 m Pasang Kaca Cermin, Tebal 5 mm


2

a. Bahan
1.100 M2 Kaca Cermin Tebal 5 mm 212,300.00 233,530.00 233,530.00
233,530.00 233,530.00

b. Tenaga
0.015 Oh Pekerja 77,500.00 1,162.50 1,162.50
0.150 Oh Tukang Kayu/kaca 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.00075 Oh Mandor 150,000.00 112.50 112.50
22,275.00 22,275.00

Jumlah 233,530.00 22,275.00 255,805.00


SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
12.20 1 m2 Pasang Kaca Patri, Tebal 5 mm
a. Bahan
1.100 M2 Kaca Patri 1,760,000.00 1,936,000.00 1,936,000.00
1,936,000.00 1,936,000.00

b. Tenaga
0.015 Oh Pekerja 77,500.00 1,162.50 1,162.50
0.150 Oh Tukang Kayu/kaca 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.00075 Oh Mandor 150,000.00 112.50 112.50
22,275.00 22,275.00

Jumlah 1,936,000.00 22,275.00 1,958,275.00

12.21 1 Set Pekerjaan Pasang Jendela Kaca Nako Biasa


a. Bahan
1 Set Bingkai Nako 15,400.00 15,400.00 15,400.00
1 Set Kaca Nako 6 daun 59,400.00 59,400.00 59,400.00
1 Set Kaca Nako 8 daun 68,200.00 68,200.00 68,200.00
Nako 6 daun 74,800.00 74,800.00
Nako 8 daun 83,600.00 83,600.00
b. Tenaga
0.015 Oh Pekerja 77,500.00 1,162.50 1,162.50
0.150 Oh Tukang Kayu/kaca 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.00075 Oh Mandor 150,000.00 112.50 112.50
22,275.00 22,275.00

Nako 6 daun 74,800.00 22,275.00 97,075.00


Nako 8 daun 83,600.00 22,275.00 105,875.00

12.22 1 Set Pekerjaan Pasang Jendela Kaca Nako Rayben


a. Bahan
1 Set Bingkai Naco 15,400.00 15,400.00 15,400.00
1 Set Kaca Naco 6 daun Rayben 59,400.00 59,400.00 59,400.00
1 Set Kaca Naco 8 daun Rayben 67,100.00 67,100.00 67,100.00
Nako 6 daun 74,800.00 74,800.00
Nako 8 daun 82,500.00 82,500.00

b. Tenaga
0.015 Oh Pekerja 77,500.00 1,162.50 1,162.50
0.150 Oh Tukang Kayu/kaca 125,000.00 18,750.00 18,750.00
0.015 Oh Kepala Tukang 150,000.00 2,250.00 2,250.00
0.00075 Oh Mandor 150,000.00 112.50 112.50
22,275.00 22,275.00

Nako 6 daun Rayben 74,800.00 22,275.00 97,075.00


Nako 8 daun Rayben 82,500.00 22,275.00 104,775.00

XIII PEKERJAAN PENUTUP LANTAI DAN DINDING

13.1 1 m2 Pasang Lantai Granito Ukuran 40 x 40 cm


a. Bahan
6.930 Bh Ubin Granito 40 x 40 cm 48,400.00 335,412.00 335,412.00
9.800 Kg Semen Portland 1,700.00 16,660.00 16,660.00
0.0215 M3 Pasir Pasang 118,750.00 2,553.13 2,553.13
1.300 Kg Semen Warna 17,500.00 22,750.00 22,750.00
377,375.13 377,375.13
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.120 Oh Tukang Batu 125,000.00 15,000.00 15,000.00
0.012 Oh Kepala Tukang 150,000.00 1,800.00 1,800.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
38,050.00 38,050.00

Jumlah 377,375.13 38,050.00 415,425.13

13.2 1 m Pasang Lantai Granito Ukuran 30 x 30 cm


2

a. Bahan
11.870 Bh Ubin Granito 30 x 30 cm 22,550.00 267,668.50 267,668.50
10.000 Kg Semen Portland 1,700.00 17,000.00 17,000.00
0.0215 M3 Pasir Pasang 118,750.00 2,553.13 2,553.13
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
313,471.63 313,471.63
b. Tenaga
0.260 Oh Pekerja 77,500.00 20,150.00 20,150.00
0.125 Oh Tukang Batu 125,000.00 15,625.00 15,625.00
0.0125 Oh Kepala Tukang 150,000.00 1,875.00 1,875.00
0.013 Oh Mandor 150,000.00 1,950.00 1,950.00
39,600.00 39,600.00

Jumlah 313,471.63 39,600.00 353,071.63

13.3 1 m Pasang Lantai Ubin Teralux Marmer Ukuran 60 x 60 cm


2

a. Bahan
3.000 Bh Ubin Teralux Marmer 60 x 60 cm 94,400.00 283,200.00 283,200.00
8.190 Kg Semen Portland 1,700.00 13,923.00 13,923.00
0.045 M3 Pasir Pasang 118,750.00 5,343.75 5,343.75
1.000 Kg Semen Warna 17,500.00 17,500.00 17,500.00
319,966.75 319,966.75

b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.120 Oh Tukang Batu 125,000.00 15,000.00 15,000.00
0.0120 Oh Kepala Tukang 150,000.00 1,800.00 1,800.00
0.0125 Oh Mandor 150,000.00 1,875.00 1,875.00
38,050.00 38,050.00

Jumlah 319,966.75 38,050.00 358,016.75

13.4 1 m Pasang Lantai Ubin Teralux Marmer Ukuran 40 x 40 cm


2

a. Bahan
6.250 Bh Ubin Teralux Marmer 40 x 40 cm 52,800.00 330,000.00 330,000.00
8.800 Kg Semen Portland 1,700.00 14,960.00 14,960.00
0.0215 M3 Pasir Pasang 118,750.00 2,553.13 2,553.13
1.300 Kg Semen Warna 17,500.00 22,750.00 22,750.00
370,263.13 370,263.13

b. Tenaga
0.672 Oh Pekerja 77,500.00 52,080.00 52,080.00
0.224 Oh Tukang Batu 125,000.00 28,000.00 28,000.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.022 Oh Kepala Tukang 150,000.00 3,300.00 3,300.00
0.034 Oh Mandor 150,000.00 5,100.00 5,100.00
88,480.00 88,480.00

Jumlah 370,263.13 88,480.00 458,743.13

13.5 1 m2 Pasang Lantai Ubin Teralux Marmer Ukuran 30 x 30 cm


a. Bahan
11.870 Bh Ubin Teralux Marmer 30 x 30 cm 27,801.18 330,000.00 330,000.00
10.000 Kg Semen Portland 1,700.00 17,000.00 17,000.00
0.0215 M3 Pasir Pasang 118,750.00 2,553.13 2,553.13
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
375,803.13 375,803.13

b. Tenaga
0.700 Oh Pekerja 77,500.00 54,250.00 54,250.00
0.340 Oh Tukang Batu 125,000.00 42,500.00 42,500.00
0.034 Oh Kepala Tukang 150,000.00 5,100.00 5,100.00
0.035 Oh Mandor 150,000.00 5,250.00 5,250.00
107,100.00 107,100.00

Jumlah 375,803.13 107,100.00 482,903.13

13.6 1 m' Pasang Plint Ubin Teraso Ukuran 10 x 30 cm


a. Bahan
3.530 Bh Plint Ubin Teraso 10 x 30 cm 935.00 3,300.55 3,300.55
1.560 Kg Semen Portland 1,700.00 2,652.00 2,652.00
0.003 M3 Pasir Pasang 118,750.00 356.25 356.25
0.190 Kg Semen Warna 17,500.00 3,325.00 3,325.00
9,633.80 9,633.80

b. Tenaga
0.080 Oh Pekerja 77,500.00 6,200.00 6,200.00
0.040 Oh Tukang Batu 125,000.00 5,000.00 5,000.00
0.004 Oh Kepala Tukang 150,000.00 600.00 600.00
0.004 Oh Mandor 150,000.00 600.00 600.00
12,400.00 12,400.00

Jumlah 9,633.80 12,400.00 22,033.80

13.7 1 m' Pasang Plint Ubin Teraso Ukuran 10 x 40 cm


a. Bahan
2.650 Bh Plint Ubin Teraso 10 x 40 cm 962.50 2,550.63 2,550.63
1.200 Kg Semen Portland 1,700.00 2,040.00 2,040.00
0.003 M3 Pasir Pasang 118,750.00 356.25 356.25
0.100 Kg Semen Warna 17,500.00 1,750.00 1,750.00
6,696.88 6,696.88

b. Tenaga
0.800 Oh Pekerja 77,500.00 62,000.00 62,000.00
0.040 Oh Tukang Batu 125,000.00 5,000.00 5,000.00
0.004 Oh Kepala Tukang 150,000.00 600.00 600.00
0.004 Oh Mandor 150,000.00 600.00 600.00
68,200.00 68,200.00

Jumlah 6,696.88 68,200.00 74,896.88


13.8 1 m' Pasang Plint Ubin Granito Ukuran 10 x 40 cm
a. Bahan
2.650 Bh Plint Ubin Granito 10 x 40 cm 12,100.00 32,065.00 32,065.00
1.200 Kg Semen Portland 1,700.00 2,040.00 2,040.00
0.003 M3 Pasir Pasang 118,750.00 356.25 356.25
0.100 Kg Semen Warna 17,500.00 1,750.00 1,750.00
36,211.25 36,211.25

b. Tenaga
0.060 Oh Pekerja 77,500.00 4,650.00 4,650.00
0.030 Oh Tukang Batu 125,000.00 3,750.00 3,750.00
0.003 Oh Kepala Tukang 150,000.00 450.00 450.00
0.003 Oh Mandor 150,000.00 450.00 450.00
9,300.00 9,300.00

Jumlah 36,211.25 9,300.00 45,511.25

13.9 1 m Pasang Plint Ubin Granito Ukuran 10 x 30 cm


'

a. Bahan
3.330 Bh Plint Ubin Granito 10 x 30 cm 7,516.67 25,030.50 25,030.50
1.650 Kg Semen Portland 1,700.00 2,805.00 2,805.00
0.0032 M3 Pasir Pasang 118,750.00 380.00 380.00
0.100 Kg Semen Warna 17,500.00 1,750.00 1,750.00
29,965.50 29,965.50

b. Tenaga
0.900 Oh Pekerja 77,500.00 69,750.00 69,750.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.0045 Oh Mandor 150,000.00 675.00 675.00
83,025.00 83,025.00

Jumlah 29,965.50 83,025.00 112,990.50

13.10 1 m' Pasang Plint Ubin Teralux Marmer Ukuran 10 x 60 cm


a. Bahan
1.700 Bh Plint Ubin Teralux Marmer 10 x 60 cm 15,733.33 26,746.67 26,746.67
1.650 Kg Semen Portland 1,700.00 2,805.00 2,805.00
0.0032 M3 Pasir Pasang 118,750.00 380.00 380.00
0.100 Kg Semen Warna 17,500.00 1,750.00 1,750.00
31,681.67 31,681.67

b. Tenaga
0.900 Oh Pekerja 77,500.00 69,750.00 69,750.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.0045 Oh Mandor 150,000.00 675.00 675.00
83,025.00 83,025.00

Jumlah 31,681.67 83,025.00 114,706.67

13.11 1 m' Pasang Plint Ubin Teralux Marmer Ukuran 10 x 40 cm


a. Bahan
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
2.500 Bh Plint Ubin Teralux Marmer 10 x 40 cm 13,200.00 33,000.00 33,000.00
1.650 Kg Semen Portland 1,700.00 2,805.00 2,805.00
0.0032 M3 Pasir Pasang 118,750.00 380.00 380.00
0.100 Kg Semen Warna 17,500.00 1,750.00 1,750.00
37,935.00 37,935.00
b. Tenaga
0.900 Oh Pekerja 77,500.00 69,750.00 69,750.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.0045 Oh Mandor 150,000.00 675.00 675.00
83,025.00 83,025.00

Jumlah 37,935.00 83,025.00 120,960.00

13.12 1 m' Pasang Plint Ubin Teralux Marmer Ukuran 10 x 30 cm


a. Bahan
3.330 Bh Plint Ubin Teralux Marmer 10 x 30 cm 9,267.06 30,859.31 30,859.31
1.650 Kg Semen Portland 1,700.00 2,805.00 2,805.00
0.0032 M3 Pasir Pasang 118,750.00 380.00 380.00
0.100 Kg Semen Warna 17,500.00 1,750.00 1,750.00
35,794.31 35,794.31

b. Tenaga
0.900 Oh Pekerja 77,500.00 69,750.00 69,750.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.0045 Oh Mandor 150,000.00 675.00 675.00
83,025.00 83,025.00

Jumlah 35,794.31 83,025.00 118,819.31

13.13 1 m2 Pasang Lantai Keramik Artistik Ukuran 10 x 20 cm


a. Bahan
50 Bh Ubin Keramik Artistik 10 x 20 cm 6,100.00 305,000.00 305,000.00
11.380 Kg Semen Portland 1,700.00 19,346.00 19,346.00
0.042 M3 Pasir Pasang 118,750.00 4,987.50 4,987.50
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
355,583.50 355,583.50

b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00

Jumlah 355,583.50 101,550.00 457,133.50

13.14 1 m Pasang Lantai Keramik Artistik Ukuran 10 x 10 cm


2

a. Bahan
50 Bh Ubin Keramik Artistik 10 x 10 cm 6,100.00 305,000.00 305,000.00
11.380 Kg Semen Portland 1,700.00 19,346.00 19,346.00
0.042 M3 Pasir Pasang 118,750.00 4,987.50 4,987.50
2.000 Kg Semen Warna 17,500.00 35,000.00 35,000.00
364,333.50 364,333.50

b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00

Jumlah 364,333.50 101,550.00 465,883.50

13.15 1 m Pasang Lantai Keramik Artistik Ukuran 5 x 20 cm


2

a. Bahan
100 Bh Ubin Keramik Artistik 5 x 20 cm 6,100.00 610,000.00 610,000.00
11.380 Kg Semen Portland 1,700.00 19,346.00 19,346.00
0.042 M3 Pasir Pasang 118,750.00 4,987.50 4,987.50
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
660,583.50 660,583.50
b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00

Jumlah 660,583.50 101,550.00 762,133.50

13.16 1 m Pasang Plint Keramik Artistik Ukuran 10 x 20 cm


2

a. Bahan
5 Bh Plint Keramik Artistik 10 x 20 cm 6,100.00 30,500.00 30,500.00
1.650 Kg Semen Portland 1,700.00 2,805.00 2,805.00
0.0032 M3 Pasir Pasang 118,750.00 380.00 380.00
0.100 Kg Semen Warna 17,500.00 1,750.00 1,750.00
35,435.00 35,435.00

b. Tenaga
0.090 Oh Pekerja 77,500.00 6,975.00 6,975.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.0045 Oh Mandor 150,000.00 675.00 675.00
20,250.00 20,250.00

Jumlah 35,435.00 20,250.00 55,685.00

13.17 1 m Pasang Plint Keramik Artistik Ukuran 10 x 10 cm


2

a. Bahan
5 Bh Plint Keramik Artistik 10 x 10 cm 6,100.00 30,500.00 30,500.00
1.650 Kg Semen Portland 1,700.00 2,805.00 2,805.00
0.0032 M3 Pasir Pasang 118,750.00 380.00 380.00
0.120 Kg Semen Warna 17,500.00 2,100.00 2,100.00
35,785.00 35,785.00

b. Tenaga
0.090 Oh Pekerja 77,500.00 6,975.00 6,975.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.0045 Oh Mandor 150,000.00 675.00 675.00
20,250.00 20,250.00

Jumlah 35,785.00 20,250.00 56,035.00

13.18 1 m2 Pasang Plint Keramik Artistik Ukuran 5 x 20 cm


a. Bahan
5 Bh Plint Keramik Artistik 5 x 20 cm 6,100.00 30,500.00 30,500.00
0.850 Kg Semen Portland 1,700.00 1,445.00 1,445.00
0.0022 M3 Pasir Pasang 118,750.00 261.25 261.25
0.080 Kg Semen Warna 17,500.00 1,400.00 1,400.00
33,606.25 33,606.25

b. Tenaga
0.090 Oh Pekerja 77,500.00 6,975.00 6,975.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.0045 Oh Mandor 150,000.00 675.00 675.00
20,250.00 20,250.00

Jumlah 33,606.25 20,250.00 53,856.25

13.19 1 m2 Pasang Lantai Keramik Ukuran 10 x 20 cm


a. Bahan
50 Bh Ubin Keramik 10 x 20 cm 860.00 43,000.00 43,000.00
11.380 Kg Semen Portland 1,700.00 19,346.00 19,346.00
0.042 M3 Pasir Pasang 118,750.00 4,987.50 4,987.50
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
93,583.50 93,583.50

b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00

Jumlah 93,583.50 101,550.00 195,133.50

13.20 1 m2 Pasang Lantai Keramik Ukuran 20 x 20 cm


a. Bahan
25 Bh Ubin Keramik 20 x 20 cm 1,700.00 42,500.00 42,500.00
11.380 Kg Semen Portland 1,700.00 19,346.00 19,346.00
0.042 M3 Pasir Pasang 118,750.00 4,987.50 4,987.50
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
93,083.50 93,083.50

b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00

Jumlah 93,083.50 101,550.00 194,633.50

13.21 1 m2 Pasang Lantai Keramik Ukuran 15 x 20 cm


a. Bahan
35 Bh Ubin Keramik 15 x 20 cm 1,857.14 65,000.00 65,000.00
11.380 Kg Semen Portland 1,700.00 19,346.00 19,346.00
0.042 M3 Pasir Pasang 118,750.00 4,987.50 4,987.50
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
115,583.50 115,583.50

b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00

Jumlah 115,583.50 101,550.00 217,133.50

13.22 1 m Pasang Lantai Keramik Warna Ukuran 30 x 30 cm


2

a. Bahan
11.11 Bh Ubin Keramik Warna 30 x 30 cm 5,981.82 66,458.00 66,458.00
11.380 Kg Semen Portland 1,700.00 19,346.00 19,346.00
0.042 M3 Pasir Pasang 118,750.00 4,987.50 4,987.50
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
117,041.50 117,041.50

b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00

Jumlah 117,041.50 101,550.00 218,591.50

13.23 1 m Pasang Lantai Keramik Putih Ukuran 30 x 30 cm


2

a. Bahan
11.11 Bh Ubin Keramik Putih 30 x 30 cm 5,590.91 62,115.00 62,115.00
11.380 Kg Semen Portland 1,700.00 19,346.00 19,346.00
0.042 M3 Pasir Pasang 118,750.00 4,987.50 4,987.50
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
112,698.50 112,698.50

b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00

Jumlah 112,698.50 101,550.00 214,248.50

13.24 1 m2 Pasang Lantai Keramik Warna Ukuran 40 x 40 cm


a. Bahan
6.25 Bh Keramik Warna 40 x 40 cm mutu C 9,152.00 57,200.00 57,200.00
6.25 Bh Keramik Warna 40 x 40 cm mutu B 14,266.67 89,166.67 89,166.67
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
11.380 Kg Semen Portland 1,700.00 19,346.00 19,346.00
0.042 M3 Pasir Pasang 118,750.00 4,987.50 4,987.50
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
Mutu C 107,783.50 107,783.50
Mutu B 139,750.17 139,750.17
b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00

Mutu C , Jumlah 107,783.50 101,550.00 209,333.50


Mutu B , Jumlah 139,750.17 101,550.00 241,300.17

13.25 1 m' Pasang Plint Keramik


a. Bahan
3 Bh Plint Keramik Putih 10 x 30 cm 1,863.64 5,590.91 5,590.91
3 Bh Plint Keramik Warna 10 x 30 cm 1,993.94 5,981.82 5,981.82
2.5 Bh Plint Keramik Warna 10 x 40 cm mutu C 3,660.80 9,152.00 9,152.00
2.5 Bh Plint Keramik Warna 10 x 40 cm mutu B 5,706.67 14,266.67 14,266.67
0.850 Kg Semen Portland 1,700.00 1,445.00 1,445.00
0.0022 M3 Pasir Pasang 118,750.00 261.25 261.25
0.080 Kg Semen Warna 17,500.00 1,400.00 1,400.00
Plint keramik putih 10 X 30 cm 8,697.16 8,697.16
Plint keramik Warna 10 X 30 cm 9,088.07 9,088.07
Plint keramik Warna 10 X 40 cm, mutu C 12,258.25 12,258.25
Plint keramik Warna 10 X 40 cm, mutu B 17,372.92 17,372.92

b. Tenaga
0.090 Oh Pekerja 77,500.00 6,975.00 6,975.00
0.090 Oh Tukang Batu 125,000.00 11,250.00 11,250.00
0.009 Oh Kepala Tukang 150,000.00 1,350.00 1,350.00
0.0045 Oh Mandor 150,000.00 675.00 675.00
20,250.00 20,250.00

Plint keramik putih 10 X 30 cm 8,697.16 20,250.00 28,947.16


Plint keramik Warna 10 X 30 cm 9,088.07 20,250.00 29,338.07
Plint keramik Warna 10 X 40 cm, mutu C 12,258.25 20,250.00 32,508.25
Plint keramik Warna 10 X 40 cm, mutu B 17,372.92 20,250.00 37,622.92

13.26 1 m2 Pasang Lantai Marmer


a. Bahan
1.052 M2 Marmer 330,000.00 347,160.00 347,160.00
14.150 Kg Semen Portland 1,700.00 24,055.00 24,055.00
0.039 M3 Pasir Pasang 118,750.00 4,631.25 4,631.25
2.000 Kg Semen Warna 17,500.00 35,000.00 35,000.00
410,846.25 410,846.25
b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00
Jumlah 410,846.25 101,550.00 512,396.25

13.27 1 m Pasang Lantai Karpet 6 mm


2

a. Bahan
1.050 M2 Carpet 6 mm 82,500.00 86,625.00 86,625.00
0.350 Kg Lem Vinyl 9,350.00 3,272.50 3,272.50
89,897.50 89,897.50

b. Tenaga
0.170 Oh Pekerja 77,500.00 13,175.00 13,175.00
0.170 Oh Tukang Batu 125,000.00 21,250.00 21,250.00
0.017 Oh Kepala Tukang 150,000.00 2,550.00 2,550.00
0.0085 Oh Mandor 150,000.00 1,275.00 1,275.00
38,250.00 38,250.00
Jumlah 89,897.50 38,250.00 128,147.50

13.28 1 m2 Pasang dinding Wallpaper


a. Bahan
1.020 M2 Wallpaper 308,000.00 314,160.00 314,160.00
0.350 Kg Lem Vinyl 9,350.00 3,272.50 3,272.50
317,432.50 317,432.50

b. Tenaga
0.170 Oh Pekerja 77,500.00 13,175.00 13,175.00
0.170 Oh Tukang Batu 125,000.00 21,250.00 21,250.00
0.017 Oh Kepala Tukang 150,000.00 2,550.00 2,550.00
0.0085 Oh Mandor 150,000.00 1,275.00 1,275.00
38,250.00 38,250.00
Jumlah 317,432.50 38,250.00 355,682.50

13.29 1 m2 Pasang Lantai Parquet Jati


a. Bahan
1.050 M2 Parquet Jati 423,500.00 444,675.00 444,675.00
0.600 Kg Lem Vinyl 9,350.00 5,610.00 5,610.00
450,285.00 450,285.00

b. Tenaga
0.650 Oh Pekerja 77,500.00 50,375.00 50,375.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.0325 Oh Mandor 150,000.00 4,875.00 4,875.00
104,250.00 104,250.00

Jumlah 450,285.00 104,250.00 554,535.00

13.30 1 m2 Pasang Dinding Porselin 10 x 10 cm, putih


a. Bahan
100 Bh Porselin 11 x 11 cm, Putih 770.00 77,000.00 77,000.00
9.300 Kg Semen Abu-abu 1,700.00 15,810.00 15,810.00
0.018 M3 Pasir Pasang 118,750.00 2,137.50 2,137.50
1.500 Kg Semen Puith 2,850.00 4,275.00 4,275.00
99,222.50 99,222.50

b. Tenaga
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.500 Oh Tukang Batu 125,000.00 62,500.00 62,500.00
0.050 Oh Kepala Tukang 150,000.00 7,500.00 7,500.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
122,550.00 122,550.00
Jumlah 99,222.50 122,550.00 221,772.50

13.31 1 m2 Pasang Dinding Porselin 10 x 10 cm, Warna


a. Bahan
100 Bh Porselin 11 x 11 cm warna 1,100.00 110,000.00 110,000.00
9.300 Kg Semen Abu-abu 1,700.00 15,810.00 15,810.00
0.018 M3 Pasir Pasang 118,750.00 2,137.50 2,137.50
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
154,197.50 154,197.50

b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.500 Oh Tukang Batu 125,000.00 62,500.00 62,500.00
0.050 Oh Kepala Tukang 150,000.00 7,500.00 7,500.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
122,550.00 122,550.00

Jumlah 154,197.50 122,550.00 276,747.50

13.32 1 m2 Pasang Dinding Marmer


a. Bahan
1.020 M2 Marmer 330,000.00 336,600.00 336,600.00
2.000 Bh Paku Pancing 60 x 230 - - -
12.440 Kg Semen Abu-abu 1,700.00 21,148.00 21,148.00
0.025 M3 Pasir Pasang 118,750.00 2,968.75 2,968.75
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
386,966.75 386,966.75
b. Tenaga
0.720 Oh Pekerja 77,500.00 55,800.00 55,800.00
0.650 Oh Tukang Batu 125,000.00 81,250.00 81,250.00
0.065 Oh Kepala Tukang 150,000.00 9,750.00 9,750.00
0.035 Oh Mandor 150,000.00 5,250.00 5,250.00
152,050.00 152,050.00

Jumlah 386,966.75 152,050.00 539,016.75

13.33 1 m2 Pasang Dinding Batu Tempel Hitam/Kali + anti lumut (vernis)


a. Bahan
1.050 M2 Batu Tempel Hitam 102,300.00 107,415.00 107,415.00
0.100 Kg Anti Lumut/Vernis batu 71,500.00 7,150.00 7,150.00
11.750 Kg Semen Abu-abu 1,700.00 19,975.00 19,975.00
0.035 M3 Pasir Pasang 118,750.00 4,156.25 4,156.25
138,696.25 138,696.25

b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00

Jumlah 138,696.25 101,550.00 240,246.25

13.34 1 m Pasang Dinding Batu Candi Hitam + anti lumut (vernis)


2

a. Bahan
1.050 M2 Batu Candi hitam 247,500.00 259,875.00 259,875.00
0.100 Kg Anti Lumut/Vernis batu 71,500.00 7,150.00 7,150.00
11.750 Kg Semen Abu-abu 1,700.00 19,975.00 19,975.00
0.035 M3 Pasir Pasang 118,750.00 4,156.25 4,156.25
291,156.25 291,156.25

b. Tenaga
0.620 Oh Pekerja 77,500.00 48,050.00 48,050.00
0.350 Oh Tukang Batu 125,000.00 43,750.00 43,750.00
0.035 Oh Kepala Tukang 150,000.00 5,250.00 5,250.00
0.030 Oh Mandor 150,000.00 4,500.00 4,500.00
101,550.00 101,550.00

Jumlah 291,156.25 101,550.00 392,706.25

13.35 1 m Pasang Dinding batu Alam / Palimanan + anti lumut(vernis)


2

a. Bahan
1.020 M2 Batu alam/Palimanan 184,800.00 188,496.00 188,496.00
0.100 Kg Anti Lumut/Vernis batu 71,500.00 7,150.00 7,150.00
12.440 Kg Semen Abu-abu 1,700.00 21,148.00 21,148.00
0.025 M3 Pasir Pasang 118,750.00 2,968.75 2,968.75
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
246,012.75 246,012.75
b. Tenaga
0.720 Oh Pekerja 77,500.00 55,800.00 55,800.00
0.650 Oh Tukang Batu 125,000.00 81,250.00 81,250.00
0.065 Oh Kepala Tukang 150,000.00 9,750.00 9,750.00
0.035 Oh Mandor 150,000.00 5,250.00 5,250.00
152,050.00 152,050.00

Jumlah 246,012.75 152,050.00 398,062.75

13.36 1 m2 Pasang Dinding batu Alam/KarangPilang + anti lumut(vernis)


a. Bahan
1.020 M2 Batu alam/KarangPilang 653,400.00 666,468.00 666,468.00
0.100 Kg Anti Lumut/Vernis batu 71,500.00 7,150.00 7,150.00
12.440 Kg Semen Abu-abu 1,700.00 21,148.00 21,148.00
0.025 M3 Pasir Pasang 118,750.00 2,968.75 2,968.75
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
723,984.75 723,984.75
b. Tenaga
0.720 Oh Pekerja 77,500.00 55,800.00 55,800.00
0.650 Oh Tukang Batu 125,000.00 81,250.00 81,250.00
0.065 Oh Kepala Tukang 150,000.00 9,750.00 9,750.00
0.035 Oh Mandor 150,000.00 5,250.00 5,250.00
152,050.00 152,050.00

Jumlah 723,984.75 152,050.00 876,034.75


SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

13.37 1 m2 Pasang Dinding batu Alam/Andesit + anti lumut(vernis)


a. Bahan
1.020 M2 Batu alam/Andesit(garis-garis) 209,000.00 213,180.00 213,180.00
0.100 Kg Anti Lumut/Vernis batu 71,500.00 7,150.00 7,150.00
12.440 Kg Semen Abu-abu 1,700.00 21,148.00 21,148.00
0.025 M3 Pasir Pasang 118,750.00 2,968.75 2,968.75
1.500 Kg Semen Warna 17,500.00 26,250.00 26,250.00
270,696.75 270,696.75
b. Tenaga
0.720 Oh Pekerja 77,500.00 55,800.00 55,800.00
0.650 Oh Tukang Batu 125,000.00 81,250.00 81,250.00
0.065 Oh Kepala Tukang 150,000.00 9,750.00 9,750.00
0.035 Oh Mandor 150,000.00 5,250.00 5,250.00
152,050.00 152,050.00

Jumlah 270,696.75 152,050.00 422,746.75

13.38 1 m2 plint Kayu 2 x 10 cm


a. Bahan
0.0024 M3 Kayu Jati Papan 9,075,000.00 21,780.00 21,780.00
0.050 Kg Paku Skrup 3,5" 63,500.00 3,175.00 3,175.00
24,955.00 24,955.00

b. Tenaga
0.120 Oh Pekerja 77,500.00 9,300.00 9,300.00
0.120 Oh Tukang Batu 125,000.00 15,000.00 15,000.00
0.012 Oh Kepala Tukang 150,000.00 1,800.00 1,800.00
0.006 Oh Mandor 150,000.00 900.00 900.00
27,000.00 27,000.00

Jumlah 24,955.00 27,000.00 51,955.00

13.39 1 m2 Pas. Lantai Batu Bata Diplester


a. Bahan
58.5 Bh Bata Lobang 9 x 9 x 19 cm 850.00 49,725.00 49,725.00
70.0 Bh Bata Lobang 5 x 11 x 22 cm 1,375.00 96,250.00 96,250.00
0.2480 Zak Semen Portland (PC) 72,800.00 18,054.40 18,054.40
0.047 M3 Pasir Pasang 118,750.00 5,581.25 5,581.25
73,360.65 73,360.65
119,885.65 119,885.65
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.160 Oh Tukang Batu 125,000.00 20,000.00 20,000.00
0.076 Oh Kepala Tukang 150,000.00 11,400.00 11,400.00
0.0250 Oh Mandor 150,000.00 3,750.00 3,750.00
54,525.00 54,525.00
Bata lobang 73,360.65 54,525.00 127,885.65
Bata merah/kecil 119,885.65 54,525.00 174,410.65

13.40 1 m2 Pas. Coneblock, tebal 8 cm


a. Bahan
50 Bh Conblock 8 cm biasa, 10 X 20 cm 2,695.00 134,750.00 134,750.00
50 Bh Conblock 8 cm Warna, 10 X 20 cm 3,300.00 165,000.00 165,000.00
0.10 M3 Pasir Pasang 118,750.00 11,875.00 11,875.00
Coneblock biasa 8 cm 146,625.00 146,625.00
Coneblock warna 8 cm 176,875.00 176,875.00

b. Tenaga
0.3500 Oh Pekerja 77,500.00 27,125.00 27,125.00
0.0175 Oh Mandor 150,000.00 2,625.00 2,625.00
29,750.00 29,750.00

Coneblock biasa, tbl 8 cm 146,625.00 29,750.00 176,375.00


Coneblock warna, tbl. 8 cm 176,875.00 29,750.00 206,625.00

13.41 1 m2 Pas. Coneblock, tebal 6 cm


a. Bahan
50 Bh Coneblock 6 cm biasa, 10 X 20 cm 1,980.00 99,000.00 99,000.00
50 Bh Coneblock 6 cm Warna, 10 X 20 cm 2,640.00 132,000.00 132,000.00
0.1000 M3 Pasir Pasang 118,750.00 11,875.00 11,875.00
110,875.00 110,875.00
143,875.00 143,875.00
b. Tenaga
0.3500 Oh Pekerja 77,500.00 27,125.00 27,125.00
0.0175 Oh Mandor 150,000.00 2,625.00 2,625.00
29,750.00 29,750.00

Coneblock biasa 6 cm 110,875.00 29,750.00 140,625.00


Coneblock warna 6 cm 143,875.00 29,750.00 173,625.00

13.42 1 m2 Pas. Lantai Mozaik 30/30


a. Bahan
11.100 Bh Mozaik uk. 30 x 30 8,250.00 91,575.00 91,575.00
0.096 Zak Semen Portland (PC) 72,800.00 6,988.80 6,988.80
0.050 M3 Perekat 899,056.40 44,952.82 44,952.82
143,516.62 143,516.62
b. Tenaga
0.250 Oh Tukang Batu 125,000.00 31,250.00 31,250.00
0.025 Oh Kepala Tukang 150,000.00 3,750.00 3,750.00
0.500 Oh Pekerja 77,500.00 38,750.00 38,750.00
0.025 Oh Mandor 150,000.00 3,750.00 3,750.00
77,500.00 77,500.00

Jumlah 143,516.62 77,500.00 221,016.62

XIV PEKERJAAN PENGECATAN

14.1 1 m2 Mengikis / Mengerok Permukaan Cat Tembok Lama


a. Bahan
0.050 Kg Soda Api 33,000.00 1,650.00 1,650.00
1,650.00 1,650.00

b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
Oh Tukang Cat 125,000.00 0.00 0.00
Oh Kepala Tukang 150,000.00 0.00 0.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
12,000.00 12,000.00

Jumlah 1,650.00 12,000.00 13,650.00

14.2 1 m Mencuci bidang permukaan tembok yang pernah di cat


2

a. Bahan
0.050 Kg Sabun 12,320.00 616.00 616.00
616.00 616.00

b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
Oh Tukang Cat 125,000.00 0.00 0.00
Oh Kepala Tukang 150,000.00 0.00 0.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
12,000.00 12,000.00

Jumlah 616.00 12,000.00 12,616.00

14.3 1 m Mengerok karat cat lama permukaan baja dengan cara manual
2

a. Bahan
0.050 Kg Sabun 12,320.00 616.00 616.00
616.00 616.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
Oh Tukang Cat 125,000.00 0.00 0.00
Oh Kepala Tukang 150,000.00 0.00 0.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
12,000.00 12,000.00

Jumlah 616.00 12,000.00 12,616.00

14.4 1 m Menyabun Permukaan Tembok Lama


2

a. Bahan
0.050 Kg Sabun 12,320.00 616.00 616.00
616.00 616.00
b. Tenaga
0.150 Oh Pekerja 77,500.00 11,625.00 11,625.00
Oh Tukang Cat 125,000.00 0.00 0.00
Oh Kepala Tukang 150,000.00 0.00 0.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
12,000.00 12,000.00

Jumlah 616.00 12,000.00 12,616.00

14.5 1 m Mendempul dan Menggosok Kayu


2

a. Bahan
0.080 Kg Dempul Jadi 22,000.00 1,760.00 1,760.00
0.020 Kg Minyak Cat 6,600.00 132.00 132.00
0.010 Kg Batu Apung 2,000.00 20.00 20.00
1,912.00 1,912.00
b. Tenaga
0.040 Oh Pekerja 77,500.00 3,100.00 3,100.00
0.040 Oh Tukang Cat 125,000.00 5,000.00 5,000.00
0.004 Oh Kepala Tukang 150,000.00 600.00 600.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
9,075.00 9,075.00

Jumlah 1,912.00 9,075.00 10,987.00

14.6 1 m2 Pengecatan Bidang Kayu Lama


a. Bahan
0.150 Kg Plamir 23,300.00 3,495.00 3,495.00
0.170 Kg Cat Dasar 48,500.00 8,245.00 8,245.00
0.170 Kg Cat Penutup 90,200.00 15,334.00 15,334.00
27,074.00 27,074.00
b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.075 Oh Tukang Cat 125,000.00 9,375.00 9,375.00
0.0075 Oh Kepala Tukang 150,000.00 1,125.00 1,125.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
16,300.00 16,300.00

Jumlah 27,074.00 16,300.00 43,374.00

14.7 1 m2 Pengecatan Bidang Kayu Baru ( 1 Lapis Plamir, 1 lapis Cat


Dasar, 2 Lapis Cat Penutup )
a. Bahan
0.200 Kg Cat Meni 40,700.00 8,140.00 8,140.00
0.150 Kg Plamir 23,300.00 3,495.00 3,495.00
0.170 Kg Cat Dasar 48,500.00 8,245.00 8,245.00
0.260 Kg Cat Penutup 2 Kali 90,200.00 23,452.00 23,452.00
43,332.00 43,332.00
b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.009 Oh Tukang Cat 125,000.00 1,125.00 1,125.00
0.006 Oh Kepala Tukang 150,000.00 900.00 900.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
7,825.00 7,825.00
Jumlah 43,332.00 7,825.00 51,157.00

14.8 1 m2 Pengecatan Bidang Kayu Baru ( 1 Lapis Plamir, 1 lapis Cat


Dasar, 3 Lapis Cat Penutup )
a. Bahan
0.200 Kg Cat Meni 40,700.00 8,140.00 8,140.00
0.150 Kg Plamir 23,300.00 3,495.00 3,495.00
0.170 Kg Cat Dasar 48,500.00 8,245.00 8,245.00
0.350 Kg Cat Penutup 2 Kali 90,200.00 31,570.00 31,570.00
51,450.00 51,450.00

b. Tenaga
0.070 Oh Pekerja 77,500.00 5,425.00 5,425.00
0.105 Oh Tukang Cat 125,000.00 13,125.00 13,125.00
0.004 Oh Kepala Tukang 150,000.00 600.00 600.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
19,525.00 19,525.00

Jumlah 51,450.00 19,525.00 70,975.00

14.9 1 m Pelaburan Bidang Kayu dengan Politur


2
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
a. Bahan
0.150 Ltr Politur 53,900.00 8,085.00 8,085.00
0.372 Ltr Politur Jadi 58,300.00 21,687.60 21,687.60
2.000 Lbr Ampelas 3,850.00 7,700.00 7,700.00
37,472.60 37,472.60
b. Tenaga
Oh Pekerja 77,500.00 0.00 0.00
0.060 Oh Tukang Cat 125,000.00 7,500.00 7,500.00
0.016 Oh Kepala Tukang 150,000.00 2,400.00 2,400.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
10,275.00 10,275.00
Jumlah 37,472.60 10,275.00 47,747.60

14.10 1 m Pelaburan Bidang Kayu dengan Cat Residu dan Ter


2

a. Bahan
0.350 Ltr Residu atau Ter 49,500.00 17,325.00 17,325.00
17,325.00 17,325.00

b. Tenaga
0.100 Oh Pekerja 77,500.00 7,750.00 7,750.00
Oh Tukang Cat 125,000.00 0.00 0.00
Oh Kepala Tukang 150,000.00 0.00 0.00
0.006 Oh Mandor 150,000.00 900.00 900.00
8,650.00 8,650.00

Jumlah 17,325.00 8,650.00 25,975.00

14.11 1 m Pelaburan Bidang Kayu dengan Vernis


2

a. Bahan
0.150 Ltr Vernis 27,500.00 4,125.00 4,125.00
0.050 Kg Dempul 22,000.00 1,100.00 1,100.00
0.100 Lbr Ampelas 3,850.00 385.00 385.00
0.010 Bh Kuas 13,750.00 137.50 137.50
5,747.50 5,747.50

b. Tenaga
0.160 Oh Pekerja 77,500.00 12,400.00 12,400.00
0.160 Oh Tukang Cat 125,000.00 20,000.00 20,000.00
0.016 Oh Kepala Tukang 150,000.00 2,400.00 2,400.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
35,175.00 35,175.00

Jumlah 5,747.50 35,175.00 40,922.50

14.12 1 m Pengecatan Tembok Baru ( 1 Lapis Plamir, 1 lapis Cat


2

Dasar, 2 Lapis Cat Penutup )


a. Bahan
0.100 Kg Plamir 8,800.00 880.00 880.00
0.100 Kg Cat Dasar 48,500.00 4,850.00 4,850.00
0.260 Kg Cat Penutup 2 Kali, mutu C 13,750.00 3,575.00 3,575.00
0.260 Kg Cat Penutup 2 Kali, mutu B 28,600.00 7,436.00 7,436.00
0.260 Kg Cat Penutup 2 Kali, mutu B anti lumut/jamur 30,250.00 7,865.00 7,865.00
0.260 Kg Cat Penutup 2 Kali, mutu A anti lumut/jamur 104,500.00 27,170.00 27,170.00
Cat Mutu C 9,305.00 9,305.00
Cat Mutu B 13,166.00 13,166.00
Cat Mutu B, anti lumut/jamur 13,595.00 13,595.00
Cat Mutu A, anti lumut/jamur 32,900.00 32,900.00
b. Tenaga
0.020 Oh Pekerja 77,500.00 1,550.00 1,550.00
0.063 Oh Tukang Cat 125,000.00 7,875.00 7,875.00
0.0063 Oh Kepala Tukang 150,000.00 945.00 945.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
10,745.00 10,745.00

Cat Tembok/plafond Mutu C 9,305.00 10,745.00 20,050.00


Cat tembok/plafond Mutu B 13,166.00 10,745.00 23,911.00
Cat tembok/plafond Mutu B, anti lumut/jamur 13,595.00 10,745.00 24,340.00
Cat tembok/plafond Mutu A, anti lumut/jamur 32,900.00 10,745.00 43,645.00

14.13 1 m Pengecatan Tembok Lama ( 1 lapis Cat Dasar, 2 Lapis cat


2

Penutup )
a. Bahan
0.120 Kg Cat Dasar 48,500.00 5,820.00 5,820.00
0.180 Kg Cat Penutup 2 Kali, mutu C 13,750.00 2,475.00 2,475.00
0.180 Kg Cat Penutup 2 Kali, mutu B 28,600.00 5,148.00 5,148.00
0.180 Kg Cat Penutup 2 Kali, Mutu B, anti lumut/jamur 30,250.00 5,445.00 5,445.00
Cat Mutu C 8,295.00 8,295.00
Cat Mutu B 11,265.00 11,265.00
Cat Mutu B, anti lumut/jamur 10,770.00 10,770.00

b. Tenaga
0.028 Oh Pekerja 77,500.00 2,170.00 2,170.00
0.042 Oh Tukang Cat 125,000.00 5,250.00 5,250.00
0.0042 Oh Kepala Tukang 150,000.00 630.00 630.00
0.0025 Oh Mandor 150,000.00 375.00 375.00
8,425.00 8,425.00

Cat Tembok/plafond Mutu C 8,295.00 8,425.00 16,720.00


Cat tembok/plafond Mutu B 11,265.00 8,425.00 19,690.00
Cat tembok/plafond Mutu B, anti lumut/jamur 10,770.00 8,425.00 19,195.00

14.14 1 m Pengecatan Permukaan Baja dengan Meni Besi


2

a. Bahan
0.100 Kg Meni Besi 46,200.00 4,620.00 4,620.00
0.010 Bh Kuas 13,750.00 137.50 137.50
4,757.50 4,757.50

b. Tenaga
0.020 Oh Pekerja 77,500.00 1,550.00 1,550.00
0.200 Oh Tukang Cat 125,000.00 25,000.00 25,000.00
0.020 Oh Kepala Tukang 150,000.00 3,000.00 3,000.00
0.010 Oh Mandor 150,000.00 1,500.00 1,500.00
31,050.00 31,050.00

Jumlah 4,757.50 31,050.00 35,807.50

14.15 1 m Pengecatan Permukaan Baja dengan Meni Besi dan perancah


2

a. Bahan
0.100 Kg Meni Besi 46,200.00 4,620.00 4,620.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.010 Bh Kuas 13,750.00 137.50 137.50
0.002 M3 Perancah Kayu/Gelam dia. 8 319,000.00 638.00 638.00
5,395.50 5,395.50
b. Tenaga
0.250 Oh Pekerja 77,500.00 19,375.00 19,375.00
0.225 Oh Tukang Cat 125,000.00 28,125.00 28,125.00
0.0225 Oh Kepala Tukang 150,000.00 3,375.00 3,375.00
0.0075 Oh Mandor 150,000.00 1,125.00 1,125.00
52,000.00 52,000.00

Jumlah 5,395.50 52,000.00 57,395.50

14.16 10 m Cat Semprot minyak Chames Stones ( 1/2 Ducco )


2

a. Bahan
7.560 Kg Cat Kilat 44,000.00 332,640.00 332,640.00
5.320 Ltr Thinner 13,200.00 70,224.00 70,224.00
5 Kg Ross Polac 30,800.00 154,000.00 154,000.00
4 Kg Isamu 52,800.00 211,200.00 211,200.00
4 Kg Epoxi 55,000.00 220,000.00 220,000.00
4 Lbr Amplas Niken 7,150.00 28,600.00 28,600.00
1 Ls Alat Bantu / Compressor 5,500.00 5,500.00 5,500.00
1,022,164.00 1,022,164.00

b. Tenaga
8.000 Oh Tukang Cat 125,000.00 1,000,000.00 1,000,000.00
0.800 Oh Kepala Tukang 150,000.00 120,000.00 120,000.00
4.000 Oh Pekerja 77,500.00 310,000.00 310,000.00
0.200 Oh Mandor 150,000.00 30,000.00 30,000.00
1,460,000.00 1,460,000.00

Jumlah 1,022,164.00 1,460,000.00 2,482,164.00


Untuk 1 M2 Jumlah 102,216.40 146,000.00 248,216.40

14.17 1 M Cat tembok/Plafond Chames Stone (berkerikil)


2

a. Bahan
0.466 Kg Cat Tembok mutu B, anti lumut/jamur 30,250.00 14,096.50 14,096.50
0.100 Kg Epoxi 55,000.00 5,500.00 5,500.00
0.233 Kg Mill 36,300.00 8,457.90 8,457.90
1.000 Ls Alat Bantu / Compressor 550.00 550.00 550.00
28,604.40 28,604.40
b. Tenaga
0.524 Oh Tukang Cat 125,000.00 65,440.00 65,440.00
0.080 Oh Kepala Tukang 150,000.00 12,000.00 12,000.00
0.400 Oh Pekerja 77,500.00 31,000.00 31,000.00
0.020 Oh Mandor 150,000.00 3,000.00 3,000.00
111,440.00 111,440.00
Jumlah 28,604.40 111,440.00 140,044.40

14.18 10 m Cat Melamic


2

a. Bahan
1.500 Kg Wood Filler ( dempul) 35,200.00 52,800.00 52,800.00
1.500 Kg Wood Stain ( pewarna) 66,000.00 99,000.00 99,000.00
1.500 Kg Sanding Sealer ( Cat dasar ) 41,800.00 62,700.00 62,700.00
2.400 Kg Melamic Clear 66,000.00 158,400.00 158,400.00
2 Ltr Thinner 43,500.00 87,000.00 87,000.00
6 Lbr Amplas Niken 7,150.00 42,900.00 42,900.00
1 Ls Alat Bantu / Compressor 5,500.00 5,500.00 5,500.00
508,300.00 508,300.00

b. Tenaga
12 Oh Tukang Cat 125,000.00 1,500,000.00 1,500,000.00
1.200 Oh Kepala Tukang 150,000.00 180,000.00 180,000.00
2.000 Oh Pekerja 77,500.00 155,000.00 155,000.00
0.100 Oh Mandor 150,000.00 15,000.00 15,000.00
1,850,000.00 1,850,000.00

Jumlah 508,300.00 1,850,000.00 2,358,300.00


Untuk 1 M2 Jumlah
Jumlah 50,830.00 185,000.00 235,830.00

XV PEKERJAAN INSTALASI LISTRIK GEDUNG

15.1 1 Titik Pemasangan Saklar Lampu


a. Bahan
3 btg Pipa listrik 5/8" 6,600.00 19,800.00 19,800.00
24 m' Kabel NYA 1,5 mm 4,290.00 102,960.00 102,960.00
3 Buah T Duss 1,320.00 3,960.00 3,960.00
4 Buah L Bow 2,750.00 11,000.00 11,000.00
3 Buah Las dop 550.00 1,650.00 1,650.00
1 Buah Saklar Ganda 14,850.00 14,850.00 14,850.00
24 Buah Klem biasa 154.00 3,696.00 3,696.00
1 Buah Mangkok 1,980.00 1,980.00 1,980.00
1 Buah Fitting 9,900.00 9,900.00 9,900.00
169,796.00 169,796.00

b. Upah
1.000 ls Tukang Instalasi listrik 93,500.00 93,500.00 93,500.00
93,500.00 93,500.00

Jumlah 169,796.00 93,500.00 263,296.00

15.2 1 Titik Pemasangan Stop Kontak Biasa


a. Bahan
2 btg Pipa listrik 5/8" 6,600.00 13,200.00 13,200.00
15 m' Kabel NYA 2,5 mm 5,720.00 85,800.00 85,800.00
1 Buah T Duss 1,320.00 1,320.00 1,320.00
1 Buah L Bow 2,750.00 2,750.00 2,750.00
2 Buah Las dop 550.00 1,100.00 1,100.00
1 Buah Stop kontak biasa 6,600.00 6,600.00 6,600.00
16 Buah Klem biasa 154.00 2,464.00 2,464.00
1 Buah Mangkok 1,980.00 1,980.00 1,980.00
115,214.00 115,214.00

b. Upah
1.000 ls Tukang Instalasi listrik 93,500.00 93,500.00 93,500.00
93,500.00 93,500.00

Jumlah 115,214.00 93,500.00 208,714.00

15.3 1 Titik Pemasangan Stop Kontak AC


a. Bahan
25 m' Kabel NYM 2 X 2,5 mm 14,300.00 357,500.00 357,500.00
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
1 Buah Stop kontak AC 82,500.00 82,500.00 82,500.00
50 Buah Klem biasa 154.00 7,700.00 7,700.00
447,700.00 447,700.00

b. Upah
1.000 ls Tukang Instalasi listrik 93,500.00 93,500.00 93,500.00
93,500.00 93,500.00

Jumlah 447,700.00 93,500.00 541,200.00

15.4 1 Titik Pemasangan MCB


a. Bahan
3 btg Pipa listrik 5/8" 6,600.00 19,800.00 19,800.00
15 m' Kabel NYA 2,5 mm 5,720.00 85,800.00 85,800.00
1 Buah T Duss 1,320.00 1,320.00 1,320.00
2 Buah L Bow 2,750.00 5,500.00 5,500.00
24 Buah Klem biasa 154.00 3,696.00 3,696.00
1 Buah MCB 48,400.00 48,400.00 48,400.00
164,516.00 164,516.00

b. Upah
1.000 ls Tukang Instalasi listrik 93,500.00 93,500.00 93,500.00
93,500.00 93,500.00

Jumlah 164,516.00 93,500.00 258,016.00

Taksir Laburan Aspal 1,8 Kg / M2 + Tabur Pasir


a. Bahan
2,900.00 Kg Aspal bitumen 10,353.40 30,024,860.00 30,024,860.00
43.00 M3 Pasir pasang 118,750.00 5,106,250.00 5,106,250.00
0.50 Unit Alat bantu 82,485.98 41,242.99 41,242.99
300.00 Liter Minyak aspal 6,050.00 1,815,000.00 1,815,000.00
36,987,352.99 36,987,352.99
b. Tenaga
10.00 Oh Pekerja 71,500.00 715,000.00 715,000.00
2.00 Oh Operator/masinis 165,000.00 330,000.00 330,000.00
2.00 Oh Sopir terampil 110,000.00 220,000.00 220,000.00
1.00 Oh Mandor 121,000.00 121,000.00 121,000.00
4.00 Oh Pekerja terlatih 82,500.00 330,000.00 330,000.00
1,716,000.00 1,716,000.00
c. Peralatan
5.00 Set Mesin gilas roda karet 247,500.00 1,237,500.00 1,237,500.00
5.00 Set Spayer, selfprop 154,000.00 770,000.00 770,000.00
10.00 Set Dump truck 343,200.00 3,432,000.00 3,432,000.00
5,439,500.00 5,439,500.00

Jumlah 36,987,352.99 7,155,500.00 44,142,852.99


Untuk 1 M2 18,392.86
18,392.80

Palembang, 26 Februari 2014


CV. HABIBI PUTRA PRATAMA

SOFIAN HASAN
Direktur
DAFTAR HARGA SATUAN UPAH, BAHAN BANGUNAN DAN PERALATAN
TAHUN 2014 SEMESTER I

HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)

A UPAH
1 Kepala Tukang Oh 150,000.00
###
2 Tukang Oh 125,000.00
###
3 Mandor Oh 150,000.00
###
4 Pekerja Tidak Terlatih Oh 77,500.00
###
4 Pekerja Terlatih Oh 90,000.00
###
5 Masinis Oh 90,000.00
###
5 Operator Oh 165,000.00
###
6 Sopir Oh 110,000.00
###
7 Pembantu Masinis / Operator Oh 82,500.00
###
8 Supervisor Oh 82,500.00
###
9 Pemasak Aspal Oh 49,500.00
###
8 Penjaga Oh 44,000.00
###
9 Pembantu sopir Oh 82,500.00
###
10 Mekanik Oh 148,500.00
###
11 Surveyor Oh 82,500.00
###

B BAHAN/MATERIAL
1 Agregat halus m3 518,850.62
###
2 Agregat Kasar m3 518,850.62
###
3 Agregat kelas A m3 459,250.00
###
4 Agregat kelas B m3 399,300.00
###
5 Agregat kelas C m3 477,400.00
###
6 Aluminium Foil m2 20,350.00
###
7 Alcubond m2 715,000.00
###
8 Amplas Biasa Lbr 3,850.00
###
9 Amplas Niken Lbr 7,150.00
###
10 Atap Aluminium Zink Coated (seng) tebal 0,25 mm Lbr 47,300.00
###
11 Atap Aluminium Zink Coated (seng) tebal 0,3 mm Lbr 66,000.00
###
12 Atap Aluminium Zink Coated (seng) tebal 0,4 mm Lbr 91,300.00
###
13 Atap Aluminium Zincalume, tebal 0,25 mm Lbr 68,200.00
###
14 Atap Aluminium Zincalume, tebal 0,3 mm Lbr 68,750.00
###
15 Atap Aluminium Zincalume, tebal 0,4 mm Lbr 83,600.00
###
16 Atap Aluminium Gelombang tebal 0,5 mm Lbr 110,000.00
###
17 Atap Fiber warna"Polycarbonat" tbl. 4-5 mm m2 88,000.00
###
18 Atap Genteng Beton Lokal buah 4,620.00
###
19 Atap Genteng Beton buah 6,270.00
###
20 Atap Genteng Beton Cisangkan buah 8,250.00
###
21 Atap Genteng Buleleng buah 2,530.00
###
22 Atap Genteng Keramik biasa berglazur buah 8,800.00
###
23 Atap Genteng Keramik Berglazur Natural buah 13,200.00
###
24 Atap Genteng Keramik sejenis Berglazur warna buah 18,700.00
###
25 Atap Genteng Metal Biasa (88 cm X 77 cm) m2 40,700.00
###
26 Atap Genteng Metal Warna (120 cm X 76 cm) m2 44,000.00
###
27 Atap Genteng Metal Zincalume 2x4 (38,5 cm X 80cm) m2 176,000.00
###
28 Atap Genteng Metal Zincalume berpasir (77cmX100cm) m2 93,500.00
###
29 Atap Genteng Metal Zincalume berpasir biasa m2 66,000.00
###
30 Atap Genteng Kodok buah 1,100.00
###
31 Atap Onduline m2 74,800.00
###
32 Asbes polos 100 x 100 tbl = 4 mm Lbr 26,400.00
###
33 Asbes Gelombang Kecil, lebar 80 cm m2 27,500.00
###
34 Asbes Gelombang Kecil, lebar 105 cm m2 35,200.00
###
35 Asbes Gelombang Besar, lebar 105 cm m2 38,500.00
###
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
36 Asbes Gelombang motif genteng m2 36,850.00
###
37 Aspal Curah kg 13,200.00
###
38 Aspal Drum kg 13,200.00
###
39 Aquaproof kg 346,000.00
###
40 Bak Cuci Stainless Steel buah 212,300.00
###
41 Bak Cuci Teraso buah 357,500.00
###
42 Bak Fibreglass buah 198,000.00
###
43 Bak Teraso buah 198,000.00
###
44 Bambu dia. 6-8 cm/6m Btg 55,000.00
###
45 Batako buah 2,860.00
###
46 Batu Andesit hitam kecoklatan m2 209,000.00
###
47 Batu alam kecoklatan (Sangarong) m2 203,500.00
###
48 Batu Bata lobang m3 638,500.00
###
1 Aspal Bitumen kg 10,353.40
49 Batu Bata Kecil buah 1,375.00
###
2 Batu Bata Lobang buah 850.00
###
3 Batu Candi hitam m2 247,500.00
###
4 Batu Kali m3 385,000.00
###
5 Batu Kali tempel m2 102,300.00
###
6 Batu Karang Pilang m2 653,400.00
###
7 Batu Kerikil m3 440,000.00
###
3 Batu Koral beton m3 518,850.62
###
4 Batu Koral Jagung m3 363,000.00
###
5 Batu Krokos m3 431,200.00
###
6 Batu Palimanan kuning/hijau m2 184,800.00
###
7 Batu Palimanan kuning/hijau + bevel m2 184,800.00
###
8 Batu Pecah 0.5 - 1 (screen) m3 495,000.00
###
9 Batu Abu 0.00 - 0.5 (filler) m3 500,500.00
###
10 Batu Pecah 1.3 - 1.9 (spilt) m3 518,850.62
###
63 Batu Pecah 1 cm - 2 cm m3 357,500.00
###
11 Batu Pecah 2/3 m3 518,850.62
###
12 Batu Pecah 3/5 m3 508,750.00
###
13 Batu Pecah 5/7 m3 385,000.00
###
14 Batu Marmer m2 330,000.00
###
15 Batu Roster / Terawang biasa buah 4,675.00
###
16 Besi dia. 5 mm Batang 24,200.00
###
17 Besi dia. 6 mm KS Batang 27,500.00
###
18 Besi dia. 8 mm KS TI Batang 56,100.00
###
19 Besi dia. 10 mm KS TI Batang 88,000.00
###
20 Besi dia. 12 mm KS TI Batang 121,000.00
###
21 Besi dia. 14 mm KS TI Batang 203,500.00
###
22 Besi dia. 16 mm KS TI Batang 195,000.00
###
23 Besi dia. 19 mm KS TI Batang 302,500.00
###
4 Besi Beton Polos kg 12,075.00
###
5 Besi Baja Profil WF, I dan H kg 11,542.65
###
6 Besi Baja Konstruksi ( CNP, INP,dan besi L) kg 16,500.00
###
7 Besi Beam Clamp dan Plat Siku m2 24,750.00
###
8 Besi Hollow baja 20 X 40, tb. 2mm Batang 154,000.00
###
9 Besi Hollow baja 40 X 40, tb. 2mm Batang 176,000.00
###
10 Besi Hollow baja 30 X 60, tb. 2mm Batang 209,000.00
###
11 Besi Hollow Plafond 2 X 4 Batang 27,500.00
###
12 Besi Strip kg 11,000.00
###
13 Besi Strip 2 X 3 M' 5,500.00
###
14 Beton Ready Mix K - 125 m3 880,000.00
###
15 Beton Ready Mix K - 175 m3 935,000.00
###
2 Beton Ready Mix K - 225 m3 990,000.00
###
3 Beton Ready Mix K - 250 m3 1,045,000.00
###
4 Beton Ready Mix K - 275 m3 1,100,000.00
###
5 Beton Ready Mix K - 300 m3 1,155,000.00
###
6 Beton Ready Mix K - 350 m3 1,100,000.00
###
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
7 Beton Ready Mix K - 400 m4 1,265,000.00
###
8 Bubungan Asbes Gelombang Besar m' 26,400.00
###
9 Bubungan Asbes Gelombang Kecil m' 25,850.00
###
10 Bubungan/Nok Genteng Beton Buah 6,600.00
###
11 Bubungan Genteng Buleleng Buah 5,720.00
###
12 Bubungan/ Nok genteng Keramik biasa berglazur Buah 11,000.00
###
13 Bubungan/Nok genteng Keramik sejenis berglazur Buah 22,000.00
###
14 Bubungan gtg Keramik sejenis warna berglazur Buah 27,500.00
###
15 Bubungan/Nok Genteng Metal/aluminium M' 33,000.00
###
16 Bubungan Genteng Kodok Buah 4,400.00
###
17 Cat Dasar kg 48,500.00
###
18 Cat Antara kg 27,500.00
###
19 Cat Kayu dan Besi Anti Rayap kg 49,500.00
###
20 Cat Khusus Glossy dan Quick Drying kg 33,000.00
###
3 Cat Minyak warna (biasa) mutu C kg 44,000.00
###
4 Cat Minyak mutu B kg 68,700.00
###
5 Cat Minyak Semprot kg 46,200.00
###
6 Cat Meni Besi kg 40,700.00
###
7 Cat Meni Besi /kayu/ Flincote kg 46,200.00
###
8 Cat Penutup kg 90,200.00
###
9 Cat Tembok mutu C (Vinotex,Q-Luc, dan sejenis) kg 13,750.00
###
10 Cat Tembok mutu B (Catylax,vinilex, dan sejenis) kg 28,600.00
###
11 Cat Tembok mutu B, Anti Lumut dan Jamur kg 30,250.00
###
12 Cat Tembok mutu A (Mowilex,Kemtone,Dulux,dll) kg 104,500.00
###
13 Closed Duduk Setara (sejenis standar KIA) unit 605,000.00
###
14 Closed Duduk Standar (sejenis Ex.TOTOC721FV1) unit 2,892,000.00
###
15 Closed Duduk Halmar unit 3,520,000.00
###
16 Closed Duduk mutu C unit 2,062,500.00
###
17 Closed Duduk mutu A unit 4,840,000.00
###
18 Closed Duduk mutu B unit 2,992,000.00
###
19 Closed Duduk standar unit 2,530,000.00
###
20 Closet Duduk / Monoblok bh 594,000.00
###
21 Closet Jongkok Porselen / biasa buah 176,000.00
###
6 Minyak solar untuk industri / Minyak aspal liter 6,050.00
22 Closet Jongkok Teraso buah 35,200.00
###
23 Closed Jongkok Standart / sejenis (mutu B) unit 198,000.00
###
24 Closed Jongkok sejenis ( mutu A) Unit 297,000.00
###
25 Shower Spray TX 403 SV 3 buah 357,500.00
###
26 Coneblock biasa tebal 6 cm buah 1,980.00
###
27 Coneblock warna tebal 6 cm buah 2,640.00
###
28 Coneblock biasa tebal 8 cm buah 2,695.00
###
29 Coneblock warna tebal 8 cm buah 3,300.00
###
30 Cornice (bubuk Semen putih utk gypsum) kg 7,700.00
###
31 Dempul Jadi kg 22,000.00
###
32 Dempul Ross Polac kg 30,800.00
###
33 Dempul Isamu kg 52,800.00
###
34 Dolken Kayu dia. 8 - 10/400 cm m3 319,000.00
###
35 Door Closer buah 264,000.00
###
36 Door Holder buah 33,000.00
###
37 Door Stoper buah 33,000.00
###
38 Door Stop buah 24,200.00
###
39 Ember hitam buah 7,150.00
###
40 Engsel Biasa buah 19,800.00
###
41 Engsel Kuningan 4" buah 33,000.00
###
42 Engsel Pintu buah 19,800.00
###
43 Epoxi kg 55,000.00
###
44 Eternit 100 x 100 tebal 2,7 mm Lbr 25,300.00
###
45 Eternit 100 x 100 tebal 3,5 mm Lbr 29,700.00
###
46 Filler m3 1,375.00
###
47 Fitting plafond listrik buah 9,900.00
###
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
48 Glass Block buah 26,400.00
###
49 Grendel/Slot Tanam 4" buah 82,500.00
###
50 Grendel biasa buah 17,600.00
###
51 Gypsum Board ( 120 x 240 x 9 ) mm lbr 82,900.00
###
52 Hordeng Horizontal Blind (aluminium) m2 101,200.00
###
53 Hordeng Vertikal Blind m3 104,500.00
###
54 Ijuk Kg 9,900.00
###
55 Jendela Aluminium + Kaca Reyband 5 mm m2 902,000.00
###
56 Jendela Besi m2 330,000.00
###
57 Jendela Bingkai Nako 100 cm X 70 cm Unit 99,000.00
###
58 Jendela Bingkai Nako m2 148,500.00
###
59 Kabel NYA 1,5 mm m' 4,290.00
###
60 Kabel NYA 2,5 mm m' 5,720.00
###
61 Kabel NYA 4.0 mm m' 6,600.00
###
62 Kabel NYM 2 X 1,5 mm m' 11,000.00
###
63 Kabel NYM 2 X 2,5 mm m' 14,300.00
###
64 Kabel NYM 2 X 4,0 mm m' 19,800.00
###
65 Kaca Cermin 3 mm m2 136,400.00
###
66 Kaca Cermin 5 mm m2 212,300.00
###
67 Kaca Patri m2 1,760,000.00
###
68 Kaca Bening 3 mm m2 71,500.00
###
69 Kaca Bening 4 mm m2 82,500.00
###
70 Kaca Bening 5 mm m2 121,000.00
###
71 Kaca Bening 8 mm m2 220,000.00
###
72 Kaca Bening 10 mm m2 260,700.00
###
73 Kaca Buram 12 mm m2 429,000.00
###
74 Kaca Rayband 5 mm m2 110,000.00
###
75 Kaca Buram/Es 5 mm m2 118,800.00
###
76 Bingkai Kaca Nako Set 15,400.00
###
77 Kaca Naco 6 daun Set 59,400.00
###
78 Kaca Naco 8 daun Set 68,200.00
###
79 Kaca Naco Rayben 5 mm, 6 daun Set 59,400.00
###
80 Kaca Naco Rayben 5 mm, 8 daun Set 67,100.00
###
81 Kait angin Jendela Buah 16,500.00
###
82 Kalsiboard 3,5 mm (120 cm X 240 cm) Kpg 72,800.00
###
83 Kalsiboard 4,5 mm (120 cm X 240 cm) Kpg 78,500.00
###
84 Kapur kg 6,600.00
###
85 Karpet tebal 6 mm m2 82,500.00
###
7 Kawat Beton kg 19,800.00
###
8 Kawat Burung m2 22,000.00
###
9 Kawat Duri m' 16,500.00
###
10 Kawat Harmonika m2 42,900.00
###
11 Kawat Jaring pagar lbr 30,800.00
###
12 Kawat Kassa m2 16,500.00
###
13 Kawat Las Dos 110,000.00
###
14 Kawat Nyamuk m2 19,800.00
###
15 Kawat Seng Polos kg 20,900.00
###
16 Kayu Gelam dia. 6-8 btg 8,800.00
###
17 Kayu Gelam dia. 10-12 btg 9,900.00
###
18 Kayu Hek btg 9,900.00
###
19 Kayu Lis 1/3 m' 11,550.00
###
20 Kayu Lis 1/4 m' 12,650.00
###
21 Kayu Lis Profil kecil m' 2,750.00
###
22 Kayu Lis Profil sedang m' 3,850.00
###
23 Kayu Lis Profil besar m' 8,250.00
###
24 Kayu Mosaik 30 x 30 cm Buah 6,875.00
###
25 Kayu Kaso 5/7 kelas III (Meranti dan sejenis) Btg 89,700.00
###
26 Kayu Kelas I (Unglen, Jati) m3 9,075,000.00
###
27 Kayu Kelas II (Petanang dan sejenis) m3 6,600,000.00
###
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
28 Kayu Kelas III (Meranti dan sejenis) m3 3,630,000.00
###
29 Kayu Papan 3/20 Kls. III m3 3,630,000.00
###
4 Kayu Kelas IV (Racuk dan sejenis) m3 1,650,000.00
###
5 Kayu Papan kelas IV keping 18,150.00
###
6 Kayu Racuk m3 1,980,000.00
###
7 Kayu Reng btg 37,500.00
###
8 Keramik lantai/dinding 20 x 20/25 cm putih polos Kotak 63,800.00
###
Keramik lantai/dinding 20 x 20/25 cm putih polos buah 2,552.00
###
9 Keramik lantai 20 x 20 cm warna, mutu C Kotak 57,200.00
###
Keramik lantai 20 x 20 cm warna, mutu C buah 2,288.00
###
10 Keramik lantai 20 x 20 cm warna, mutu B Kotak 68,200.00
###
Keramik lantai 20 x 20 cm warna, mutu B buah 2,728.00
###
11 Keramik dinding 20 x 25 cm warna Kotak 65,000.00
###
Keramik dinding 20 x 25 cm warna buah 3,250.00
###
12 Keramik lantai 20 x 25 cm warna, mutu B Kotak 67,300.00
###
Keramik lantai 20 x 25 cm warna, mutu B buah 3,365.00
###
13 Keramik lantai 30 x 30 cm warna Kotak 65,800.00
###
Keramik lantai 30 x 30 cm warna buah 5,981.82
###
14 Keramik lantai 30 x 30 cm putih polos Kotak 61,500.00
###
Keramik lantai 30 x 30 cm putih polos buah 5,590.91
###
15 Keramik lantai 40 x 40 cm warna mutu C Kotak 57,200.00
###
Keramik lantai 40 x 40 cm warna mutu C buah 9,152.00
###
16 Keramik lantai 40 x 40 cm warna mutu B Kotak 85,600.00
###
Keramik lantai 40 x 40 cm warna mutu B buah 14,266.67
###
17 Keramik lantai motif kayu (kasar) mutu A Kotak 118,700.00
###
18 Klem Talang Paralon Buah 19,783.33
###
19 Klem kabel listrik biasa Buah 154.00
###
20 Klem kabel listrik Buah 3,300.00
###
21 Korosin Ltr 2,200.00
###
22 Kran Air buah 23,800.00
###
23 Kuas 3"-4" buah 13,750.00
###
24 Kunci Gembok buah 9,350.00
###
25 Kunci Lemari buah 8,800.00
###
26 Kunci Pintu Kamar Tidur (Hotel) buah 440,000.00
###
27 Kunci Pintu KM/WC (lux) buah 385,000.00
###
28 Kunci Selot buah 14,300.00
###
29 Kunci Tanam biasa mutu C buah 50,000.00
###
30 Kunci Tanam 2 slaag biasa buah 96,800.00
###
31 Kunci Tanam 2 slaag mutu B buah 168,500.00
###
32 Kunci Tanam Kamar Mandi buah 38,600.00
###
33 L.bow listrik buah 2,750.00
###
34 Lampu Down Light buah 46,750.00
###
35 Lampu Hologen 50 watt buah 13,750.00
###
36 Lampu Hologen 150 watt buah 27,500.00
###
37 Lampu Hologen Box buah 110,000.00
###
38 Lampu TL 10 Watt buah 7,700.00
###
39 Lampu TL 20 Watt buah 11,000.00
###
40 Lampu TL 40 Watt (bambu) buah 115,500.00
###
41 Lampu Pijar 25 Watt Putih buah 5,500.00
###
42 Lampu Pijar 40 Watt Putih buah 6,050.00
###
43 Lantai Granit 30/30 Buah 22,550.00
###
44 Lantai Granit 40/40 Buah 48,400.00
###
45 Lantai Granit 60/60 Buah 128,700.00
###
46 Lantai Kayu Panil Gracewood m2 387,750.00
###
47 Las dop listrik Buah 550.00
###
48 Lem Kayu ltr 22,000.00
###
49 Lem Vinyl Kg 9,350.00
###
50 List Gypsum Besar m' 32,800.00
###
51 List Gypsum Kecil m' 17,500.00
###
52 Mangkok Saklar listrik Buah 1,980.00
###
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
53 MCB Buah 48,400.00
###
54 MCB Box isi 4 grup Buah 27,500.00
###
55 MCB Box isi 8 grup Buah 60,500.00
###
56 Melamic Clear kg 66,000.00
###
57 Melamic Gloss/dop (Finishing) kg 66,000.00
###
58 Mill kg 36,300.00
###
59 Minyak Bekisting liter 13,200.00
###
60 Minyak Cat liter 6,600.00
###
61 Minyak solar untuk industri / Minyak aspal liter 0.00
62 Minyak Gardan liter 0.00
63 Minyak Hidrolik liter 0.00
64 Minyak Selinder liter 0.00
65 Mozaik kayu lantai Uk. 30 x 30 cm buah 8,250.00
###
66 Pagar BRC, uk. 240 cm X 120 cm, dia. 5,5 mm Unit 379,500.00
###
67 Pagar BRC, uk. 240 cm X 90 cm, dia. 6 mm Unit 412,500.00
###
6 Paku Biasa bermacam ukuran 2" - 5" kg 28,500.00
###
4 Paku Biasa 1/2" - 1" kg 32,500.00
###
4 Paku Sumbat buah 660.00
###
4 Paku Beton buah 770.00
###
4 Paku Gypsum kg 35,000.00
###
4 Paku Seng,Asbes kg 24,200.00
###
4 Paku Asbes buah 660.00
###
4 Paku Sekrup 3,5" Kg 63,500.00
###
4 Paku Sekrup 3,5" buah 685.00
###
4 Parquet Jati m2 423,500.00
###
7 Pasir Beton / Pasang m3 118,750.00
###
8 Pasir Urug m3 82,500.00
###
9 Pewarna nat Bks 11,000.00
###
10 Pintu Alluminium m2 704,000.00
###
11 Pintu Besi Baja m2 2,145,000.00
###
12 Pintu Lipat m2 418,000.00
###
13 Pintu PVC lengkap + pemasangan Unit 231,000.00
###
14 Pipa besi medium 2 mm & 1/2", pjg 6 m M' 20,350.00
###
15 Pipa besi medium 2 mm & 3/4", pjg 6 m M' 25,740.00
###
16 Pipa besi medium 2 mm & 1", pjg 6 m M' 32,092.50
###
17 Pipa besi medium 2 mm & 1,5", pjg 6 m M' 45,870.00
###
18 Pipa besi medium 2 mm & 2", pjg 6 m M' 57,750.00
###
19 Pipa besi medium 2 mm & 2,5", pjg 6 m M' 75,350.00
###
20 Pipa besi medium 2 mm & 3", pjg 6 m M' 119,350.00
###
21 Pipa besi medium 2 mm & 4", pjg 6 m M' 155,540.00
###
22 Pipa paralon listrik 5/8" Btg 6,600.00
###
23 Pipa PVC & 1/2" mutu A (Wavin dan sejenis) M' 6,850.00
###
24 Pipa PVC biasa & 1/2" mutu B M' 5,250.00
###
25 Pipa PVC & 3/4" mutu A (Wavin dan sejenis) M' 7,900.00
###
26 Pipa PVC & 3/4" mutu B M' 6,650.00
###
27 Pipa PVC & 1" mutu A (Wavin dan sejenis) M' 9,800.00
###
28 Pipa PVC & 1" mutu B M' 7,200.00
###
29 Pipa PVC & 1.5" mutu A (Wavin dan sejenis) M' 16,900.00
###
30 Pipa PVC & 1.5" mutu B M' 9,950.00
###
31 Pipa PVC & 2" mutu A ( Wavin dan sejenis) M' 20,150.00
###
32 Pipa PVC & 2" mutu B M' 14,050.00
###
33 Pipa PVC & 3" mutu A (Wavin dan sejenis) M' 38,700.00
###
34 Pipa PVC & 3" mutu B M' 26,500.00
###
35 Pipa PVC & 4" mutu A ( Wavin dan sejenis) M' 59,500.00
###
36 Pipa PVC & 4" mutu B M' 38,000.00
###
37 Pipa PVC & 6" (15 cm) mutu A (Wavin dan sejenis) M' 136,125.00
###
38 Pipa Stainless 2", tebal 1 mm M' 82,500.00
###
39 Pipa Stainless 2", tebal 0.8 mm M' 73,920.00
###
40 Pipa Stainless 2,5", tebal 1 mm M' 104,720.00
###
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
41 Pipa Stainless 2,5", tebal 1.2 mm M' 92,400.00
###
42 Plamir Tembok kg 8,800.00
###
43 Plamir Kayu kg 23,300.00
###
44 Plat stainless, tebal 1 mm, uk. 244 cm X 122 cm Lbr 1,870,000.00
###
45 Plint keramik 10 x 30 cm warna buah 4,400.00
###
46 Plint keramik 10 x 40 cm warna buah 14,520.00
###
47 Plint Ubin PC Abu-abu 15 x 20 cm buah 880.00
###
48 Plint Ubin PC Abu-abu 10 x 30 cm buah 935.00
###
49 Plint Ubin PC Abu-abu 10 x 40 cm buah 962.50
###
50 Plywood warna/Jabarwood Lbr 121,000.00
###
51 Plywood Jati 3 mm Lbr 121,000.00
###
52 Plywood Sungkay 3 mm/ megatick Lbr 121,000.00
###
53 Plywood 3 mm Lbr 52,700.00
###
14 Plywood 4 mm Lbr 82,500.00
###
15 Plywood 6 mm Lbr 102,800.00
###
16 Plywood 9 mm Lbr 148,500.00
###
17 Plywood 12 mm Lbr 189,600.00
###
18 Plywood 20 mm Lbr 278,000.00
###
19 Politur dasar ltr 53,900.00
###
20 Politur Jadi ltr 58,300.00
###
21 Porselin Putih Uk. 10 x 10 cm buah 770.00
###
22 Porselin Warna Uk. 10 x 10 cm buah 1,100.00
###
23 Rangka Atap baja ringan untuk atap genteng, genteng m2 313,500.00
###
keramik, beton, dll + pemasangan 0.00
24 Rangka Atap baja ringan untuk atap seng metal, atap m2 237,820.00
###
asbes, aluminium, sirap, dll + pemasangan 0.00
25 Rangka Atap baja ringan bentuk joglo/bertumpuk/ m2 309,870.00
###
khusus + pemasangan 0.00
26 Rangka Atap baja ringan "Pryda" untuk atap Pelana, m2 281,050.00
###
Metal dan keramik + pemasangan 0.00
27 Rangka Atap baja ringan "Pryda" untuk atap Perisai, m2 309,870.00
###
Metal dan keramik + pemasangan 0.00
28 Rangka Atap baja ringan "Pryda" untuk atap Joglo, m2 360,360.00
###
Metal dan keramik + pemasangan 0.00
29 Rel Pintu Dorong Unit 264,000.00
###
30 Rolling Door Standar, t=4 mm, (minimal pas. 7 M2) m2 643,500.00
###
31 Rolling Door Standar, t=5 mm, (minimal pas. 7 M2) m2 693,000.00
###
32 Sanding Sealer Impra (Cat dasar) Kg 41,800.00
###
33 Seal Tape buah 5,500.00
###
34 Semen ( 50 kg ) Zak 72,800.00
###
15 Semen Portland ( PC ) kg 1,700.00
###
16 Semen Putih (40 kg) Zak 98,300.00
###
17 Semen Putih Kg 2,850.00
###
18 Semen Merah m3 41,800.00
###
19 Semen Nat kg 17,500.00
###
20 Seng Gelombang, lebar 70 cm m2 8,167.50
###
21 Seng Plat 120 cm X 240 cm lbr 116,600.00
###
22 Seng Plat 33 cm M' 14,520.00
###
23 Seng Plat 38 cm M' 20,350.00
###
24 Seng Plat 45 cm M' 22,000.00
###
25 Seng Plat 55 cm M' 28,600.00
###
26 Seng Plat 88 cm M' 36,300.00
###
27 Seng Plat 92 cm M' 38,500.00
###
28 Sabun Kg 12,320.00
###
29 Soda Api Kg 33,000.00
###
30 Soft Board ( 120 x 240 ) mm lbr 74,250.00
###
31 Saklar Tunggal biasa Buah 6,600.00
###
32 Saklar Ganda biasa Buah 14,850.00
###
33 Saklar Tunggal National Buah 23,800.00
###
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
34 Saklar Ganda National Buah 38,500.00
###
35 Scafolding tg 1,77 m X 1,77 m Unit 880,000.00
###
36 Roda Scafolding 4 buah Unit 467,500.00
###
37 Smartruss Aluminium Magnesium 0.00
- Lysaght Smartruss C 75.100 M' 24,750.00
###
- Lysaght Smartruss C 75.75 M' 20,680.00
###
- Reng U T S 40 M' 17,930.00
###
- Screw / Dynabolt Buah 2,090.00
###
- Valery Gutter Talang Jurai M' 137,940.00
###
- Strap Bracing M' 13,750.00
###
38 Stop Kontak biasa Buah 18,700.00
###
39 Stop kontak AC Buah 82,500.00
###
40 Sunscreen Aluminium M2 412,500.00
###
41 T.Duss listrik Buah 1,320.00
###
42 Talang Paralon, pjg 4 m btg 52,800.00
###
43 Tali Ijuk Kg 12,540.00
###
44 Ijuk m3 26,400.00
###
45 Tanah Liat/Urug m3 55,000.00
###
46 Tanah Puru m3 60,500.00
###
47 Tanah Sirtu m3 88,000.00
###
48 Taekwood 3 mm m2 43,800.00
###
49 Taekwood 4 mm biasa m2 51,500.00
###
50 Ter / Residu liter 49,500.00
###
51 Textil Tape roll 7,535.00
###
52 Thinner biasa Liter 13,200.00
###
53 Thinner Cat Glossy (Cobra dan sejenis) Liter 43,500.00
###
54 Urinoir buah 154,000.00
###
55 Urinoir mutu A unit 181,500.00
###
56 Vernis ltr 27,500.00
###
57 Vernis Batu Kg 71,500.00
###
58 Wallpaper m2 308,000.00
###
59 Wastafel biasa buah 335,000.00
###
60 Wastafel Halmar unit 468,000.00
###
61 Wastafel mutu A unit 635,000.00
###
62 Wood Filler Impra (dempul) Klg 35,200.00
###
63 Wood Stain Impra (cat pewarna) Klg 66,000.00
###

C PERALATAN
1 Alat Bantu jam 82,485.98
1 Asphalt Finisher jam 929,341.99
###
2 Asphalt Mixing Plant jam 8,248,597.50
###
3 Asphalt Sprayer jam 85,785.41
###
4 Compresor jam 219,962.60
###
5 Concrete Mixer jam 230,960.73
###
6 Concrete Pump jam 409,815.23
###
7 Concrete Vibrator jam 223,134.59
###
2 Dump Truck 3,5 Ton jam 343,141.66
###
3 Dump Truck 10 Ton jam 384,934.55
###
3 Excavator jam 659,887.80
###
4 Filter jam 43,992.52
###
5 Genset jam 274,953.25
###
6 Grader jam 1,099,813.00
###
7 Loader jam 1,099,813.00
###
8 Pneumatic Tired Roller jam 247,457.93
###
9 Tandem Roller jam 1,099,813.00
###
10 Flatbed Truck 3,5 ton jam 247,457.93
###
11 Water Tank Truck jam 274,953.25
###
12 Generator jam 575,692.09
###
HRG SATUAN
NO URAIAN SATUAN
(RUPIAH)
13 Alat Bantu jam 82,485.98
###
14 Roller 3 roda jam 1,099,813.00
###
3 Sprayer, Selfprof jam 153,973.82
###
4 Buldozer jam 734,020.31
###
5 Scaffolding 177cm X 177 cm, Tg. 177 cm Set/Bulan 52,241.12
###
6 Stone Crusher (Pemecah batu) jam 948,444.82
###
7 Pengaduk beton jam 109,981.30
###
8 Stemper jam 26,395.51
###
E 9 Roller, Vibrator Pneu jam 1,099,813.00
###
10 Water Pump jam 274,953.25
###

Palembang, 26 Februari 2014


CV. HABIBI PUTRA PRATAMA

SOFIAN HASAN
Direktur
JADWAL PELAKSANAAN

PROYEK : PT. BANK MANDIRI (Persero) Tahun 2014


PEKERJAAN : REHAB TOILET PRIA DAN TOILET WANITA LANTAI II
LOKASI : KANTOR BANK MANDIRI CABANG CINDE JL. JEND. SUDIRMAN

NO. URAIAN PEKERJAAN BOBOT MINGGU


1 2 (%) 1 2 3 4 5 6 7 8 9 10 11 12

I PEKERJAAN PENDAHULUAN
1 Survey Pengukuran 0.29 0.29
2 Pembersihan Lokasi 0.96 0.32 0.64

3 Papan Nama Proyek 0.18 0.18

II PEKERJAAN JALAN SETAPAK


1 Urugan Pasir 3.73 2.78 0.62 0.62 -0.29

2 Pas. Maal 5.62 1.41 4.22

3 Pek. Cor Beton Ready Mix K. 225 78.06 8.67 13.01 14.19 15.61 14.19 9.40 2.97

4 Labur Aspal 1.8 kg/m2 + tabur pasir 10.03 3.34 4.01 2.67

III PEKERJAAN LAIN - LAIN


1 Administrasi Photo 0.71 0.18 0.18 0.18 0.18

2 Asbuilt Drawing 0.18 0.18

3 Pembersihan Akhir 0.24 0.24

PROGRES MINGGUAN 100.00 0.79 2.22 4.39 11.46 13.01 14.19 15.61 14.19 9.58 6.94 4.63 2.97
KOMULATIF PROGRES MINGGUAN 0.00 0.79 3.01 7.41 18.86 31.87 46.07 61.68 75.87 85.46 92.39 97.03 100.00

4.5454545455
#N/A #N/A #N/A #N/A

Palembang, 26 Februari 2014


CV. HABIBI PUTRA PRATAMA

SOFIAN HASAN
Direktur
1.20

1.00

0.80

0.60

0.40

0.20

-
0.29 0.29
DAFTAR HARGA SATUAN UPAH DAN BAHAN
SURVEY PER JULI 2013

HARGA
NO URAIAN SATUAN
PASAR (Rp)

A UPAH
1 Kepala Tukang Oh 110,000.00
2 Tukang Oh 90,000.00
3 Mandor Oh 90,000.00
4 Pekerja Tidak Terlatih Oh 65,000.00
5 Pekerja Terlatih Oh 75,000.00

B BAHAN/MATERIAL
1 Agregat Halus m3 422,500.00
2 Agregat Kasar m3 400,000.00
3 Agregat Kelas A m3 380,000.00
4 Agregat Kelas B m3 367,500.00
5 Agregat Kelas C m3 337,500.00
6 Aluminium Foil m2 17,000.00
7 Alcubond m2 622,500.00
8 Amplas Biasa Lbr 3,000.00
9 Amplas Niken Lbr 6,000.00
10 Atap Aluminium Zink Coated (seng) tebal 0,25 mm Lbr 45,000.00
11 Atap Aluminium Zink Coated (seng) tebal 0,3 mm Lbr 57,000.00
12 Atap Aluminium Zink Coated (seng) tebal 0,4 mm Lbr 80,000.00
13 Atap Aluminium Zincalume, tebal 0,25 mm Lbr 59,000.00
14 Atap Aluminium Zincalume, tebal 0,3 mm Lbr 61,000.00
15 Atap Aluminium Zincalume, tebal 0,4 mm Lbr 74,000.00
16 Atap Aluminium Gelombang tebal 0,5 mm Lbr 98,000.00
17 Atap Fiber warna"Polycarbonat" tbl. 4-5 mm m2 77,500.00
18 Atap Genteng Beton Lokal buah 4,000.00
19 Atap Genteng Beton buah 5,450.00
20 Atap Genteng Beton Cisangkan buah 7,000.00
21 Atap Genteng Buleleng buah 2,150.00
22 Atap Genteng Keramik biasa berglazur buah 7,700.00
23 Atap Genteng Keramik Berglazur Natural buah 9,700.00
24 Atap Genteng Keramik sejenis Berglazur warna buah 14,500.00
25 Atap Genteng Metal Biasa (88 cm X 77 cm) m2 34,000.00
26 Atap Genteng Metal Warna (120 cm X 76 cm) m2 35,000.00
27 Atap Genteng Metal Zincalume 2x4 (38,5 cm X 80cm) m2 152,000.00
28 Atap Genteng Metal Zincalume berpasir (77cmX100cm) m2 82,000.00
29 Atap Genteng Metal Zincalume berpasir biasa m2 56,000.00
30 Atap Genteng Kodok buah 900.00
31 Atap Onduline m2 64,000.00
32 Asbes polos 100 x 100 tbl = 4 mm Lbr 22,800.00
33 Asbes Gelombang Kecil, lebar 80 cm m2 22,000.00
34 Asbes Gelombang Kecil, lebar 105 cm m2 25,000.00
35 Asbes Gelombang Besar, lebar 105 cm m2 29,000.00
36 Asbes Gelombang motif genteng m2 27,000.00
37 Aquaproof kg 52,500.00
38 Bak Cuci Stainless Steel buah 245,000.00
39 Bak Cuci Teraso buah 185,000.00
40 Bak Fibreglass buah 220,000.00
41 Bak Teraso buah 180,000.00
42 Bambu dia. 6-8 cm/6m Btg 50,000.00
43 Batako buah 2,250.00
44 Batu Andesit hitam kecoklatan m2 170,000.00
45 Batu alam kecoklatan (Sangarong) m2 170,000.00
46 Batu Bata lobang m3 470,000.00
47 Batu Bata Kecil buah 875.00
48 Batu Bata Lobang buah 650.00
49 Batu Candi hitam m2 215,000.00
50 Batu Kali m3 375,000.00
HARGA
NO URAIAN SATUAN
PASAR (Rp)
51 Batu Kali tempel m2 85,000.00
52 Batu Karang Pilang m2 576,000.00
53 Batu Kerikil m3 400,000.00
54 Batu Koral beton m3 390,000.00
55 Batu Koral Jagung m3 330,000.00
56 Batu Krokos m3 392,000.00
57 Batu Palimanan kuning/hijau m2 168,000.00
58 Batu Palimanan kuning/hijau + bevel m2 168,000.00
59 Batu Pecah 0.5 - 1 (screen) m3 408,800.00
60 Batu Abu 0.00 - 0.5 (filler) m3 385,000.00
61 Batu Pecah 1.3 - 1.9 (spilt) m3 420,000.00
62 Batu Pecah 2/3 m3 425,000.00
63 Batu Pecah 3/5 m3 470,000.00
64 Batu Pecah 5/7 m3 425,000.00
65 Batu Marmer m2 288,960.00
66 Batu Roster / Terawang biasa buah 4,100.00
67 Besi dia. 5 mm Batang 20,500.00
68 Besi dia. 6 mm KS Batang 23,000.00
69 Besi dia. 8 mm KS TI Batang 49,000.00
70 Besi dia. 10 mm KS TI Batang 78,000.00
71 Besi dia. 12 mm KS TI Batang 110,000.00
72 Besi dia. 14 mm KS TI Batang 175,000.00
73 Besi dia. 16 mm KS TI Batang 192,000.00
74 Besi dia. 19 mm KS TI Batang 260,000.00
75 Besi Beton Polos kg 14,000.00
76 Besi Baja Profil WF, I dan H kg 14,500.00
77 Besi Baja Konstruksi ( CNP, INP,dan besi L) kg 13,500.00
78 Besi Beam Clamp dan Plat Siku m2 22,500.00
79 Besi Hollow baja 20 X 40, tb. 2mm Batang 120,000.00
80 Besi Hollow baja 40 X 40, tb. 2mm Batang 140,000.00
81 Besi Hollow baja 30 X 60, tb. 2mm Batang 170,000.00
82 Besi Hollow Plafond 2 X 4 Batang 23,500.00
83 Besi Strip kg 9,000.00
84 Besi Strip 2 X 3 M' 4,000.00
85 Beton Ready Mix K - 125 m3 800,000.00
86 Beton Ready Mix K - 175 m3 850,000.00
87 Beton Ready Mix K - 225 m3 900,000.00
88 Beton Ready Mix K - 250 m3 950,000.00
89 Beton Ready Mix K - 275 m3 1,000,000.00
90 Beton Ready Mix K - 300 m3 1,050,000.00
91 Beton Ready Mix K - 350 m3 1,100,000.00
92 Beton Ready Mix K - 400 m3 1,150,000.00
93 Bubungan Asbes Gelombang Besar m' 22,750.00
94 Bubungan Asbes Gelombang Kecil m' 21,000.00
95 Bubungan/Nok Genteng Beton Buah 6,000.00
96 Bubungan Genteng Buleleng Buah 5,200.00
97 Bubungan/ Nok genteng Keramik biasa berglazur Buah 8,500.00
98 Bubungan/Nok genteng Keramik sejenis berglazur Buah 18,500.00
99 Bubungan gtg Keramik sejenis warna berglazur Buah 25,000.00
100 Bubungan/Nok Genteng Metal/aluminium M' 30,000.00
101 Bubungan Genteng Kodok Buah 4,000.00
102 Cat Dasar kg 30,000.00
103 Cat Antara kg 23,000.00
104 Cat Kayu dan Besi Anti Rayap kg 25,000.00
105 Cat Khusus Glossy dan Quick Drying kg 26,500.00
106 Cat Minyak warna (biasa) mutu C kg 38,000.00
107 Cat Minyak mutu B kg 46,000.00
108 Cat Minyak Semprot kg 40,000.00
109 Cat Meni Besi kg 21,000.00
110 Cat Meni Besi /kayu/ Flincote kg 21,000.00
111 Cat Penutup kg 82,000.00
112 Cat Tembok mutu C (Vinotex,Q-Luc, dan sejenis) kg 12,000.00
HARGA
NO URAIAN SATUAN
PASAR (Rp)
113 Cat Tembok mutu B (Catylax,vinilex, dan sejenis) kg 21,000.00
114 Cat Tembok mutu B, Anti Lumut dan Jamur kg 23,000.00
115 Cat Tembok mutu A (Mowilex,Kemtone,Dulux,dll) kg 90,000.00
116 Closed Duduk Setara (sejenis standar KIA) unit 530,000.00
117 Closed Duduk Standar (sejenis Ex.TOTOC721FV1) unit 2,100,000.00
118 Closed Duduk Halmar unit 3,062,000.00
119 Closed Duduk mutu C unit 1,780,000.00
120 Closed Duduk mutu A unit 4,270,000.00
121 Closed Duduk mutu B unit 2,593,000.00
122 Closed Duduk standar unit 2,151,000.00
123 Closet Duduk / Monoblok bh 500,000.00
124 Closet Jongkok Porselen / biasa buah 145,000.00
125 Closet Jongkok Teraso buah 25,000.00
126 Closed Jongkok Standart / sejenis (mutu B) unit 165,000.00
127 Closed Jongkok sejenis ( mutu A) Unit 200,000.00
128 Shower Spray TX 403 SV 3 buah 325,000.00
129 Coneblock biasa tebal 6 cm buah 1,450.00
130 Coneblock warna tebal 6 cm buah 1,650.00
131 Coneblock biasa tebal 8 cm buah 1,900.00
132 Coneblock warna tebal 8 cm buah 2,200.00
133 Cornice (bubuk Semen putih utk gypsum) kg 6,000.00
134 Dempul Jadi kg 18,000.00
135 Dempul Ross Polac kg 25,000.00
136 Dempul Isamu kg 46,000.00
137 Dolken Kayu dia. 8 - 10/400 cm m3 275,000.00
138 Door Closer buah 240,000.00
139 Door Holder buah 30,000.00
140 Door Stoper buah 300,000.00
141 Door Stop buah 22,000.00
142 Ember hitam buah 6,500.00
143 Engsel Biasa buah 16,000.00
144 Engsel Kuningan 4" buah 27,000.00
145 Engsel Pintu buah 16,000.00
146 Epoxi kg 48,000.00
147 Eternit 100 x 100 tebal 2,7 mm Lbr 21,000.00
148 Eternit 100 x 100 tebal 3,5 mm Lbr 24,000.00
149 Filler m3 185,000.00
150 Fitting plafond listrik buah 8,500.00
151 Glass Block buah 22,500.00
152 Grendel/Slot Tanam 4" buah 72,500.00
153 Grendel biasa buah 14,500.00
154 Gypsum Board ( 120 x 240 x 9 ) mm lbr 60,000.00
155 Hordeng Horizontal Blind (aluminium) m2 92,000.00
156 Hordeng Vertikal Blind m3 95,000.00
157 Ijuk Kg 8,500.00
158 Jendela Aluminium + Kaca Reyband 5 mm m2 750,000.00
159 Jendela Besi m2 300,000.00
160 Jendela Bingkai Nako 100 cm X 70 cm Unit 87,700.00
161 Jendela Bingkai Nako m2 105,000.00
162 Kabel NYA 1,5 mm m' 3,800.00
163 Kabel NYA 2,5 mm m' 4,300.00
164 Kabel NYA 4.0 mm m' 5,300.00
165 Kabel NYM 2 X 1,5 mm m' 6,000.00
166 Kabel NYM 2 X 2,5 mm m' 8,500.00
167 Kabel NYM 2 X 4,0 mm m' 15,000.00
168 Kaca Cermin 3 mm m2 120,000.00
169 Kaca Cermin 5 mm m2 185,000.00
170 Kaca Patri m2 1,350,000.00
171 Kaca Bening 3 mm m2 62,000.00
172 Kaca Bening 4 mm m2 72,000.00
173 Kaca Bening 5 mm m2 100,000.00
174 Kaca Bening 8 mm m2 185,000.00
HARGA
NO URAIAN SATUAN
PASAR (Rp)
175 Kaca Bening 10 mm m2 225,000.00
176 Kaca Buram 12 mm m2 377,500.00
177 Kaca Rayband 5 mm m2 90,000.00
178 Kaca Buram/Es 5 mm m2 100,000.00
179 Bingkai Kaca Nako Set 14,000.00
180 Kaca Naco 6 daun Set 54,000.00
181 Kaca Naco 8 daun Set 62,000.00
182 Kaca Naco Rayben 5 mm, 6 daun Set 47,000.00
183 Kaca Naco Rayben 5 mm, 8 daun Set 60,000.00
184 Kait angin Jendela Buah 15,000.00
185 Kalsiboard 3,5 mm (120 cm X 240 cm) Kpg 55,000.00
186 Kalsiboard 4,5 mm (120 cm X 240 cm) Kpg 58,000.00
187 Kapur kg 6,000.00
188 Karpet tebal 6 mm m2 74,500.00
189 Kawat Beton kg 26,000.00
190 Kawat Burung m2 20,000.00
191 Kawat Duri m' 15,000.00
192 Kawat Harmonika m2 39,000.00
193 Kawat Jaring pagar lbr 28,000.00
194 Kawat Kassa m2 15,000.00
195 Kawat Las Dos 100,000.00
196 Kawat Nyamuk m2 18,000.00
197 Kawat Seng Polos kg 19,000.00
198 Kayu Gelam dia. 6-8 btg 8,000.00
199 Kayu Gelam dia. 10-12 btg 9,000.00
200 Kayu Hek btg 9,000.00
201 Kayu Lis 1/3 m' 10,500.00
202 Kayu Lis 1/4 m' 11,500.00
203 Kayu Lis Profil kecil m' 2,500.00
204 Kayu Lis Profil sedang m' 3,500.00
205 Kayu Lis Profil besar m' 7,500.00
206 Kayu Mosaik 30 x 30 cm Buah 6,250.00
207 Kayu Kaso 5/7 kelas III (Meranti dan sejenis) Btg 55,000.00
208 Kayu Kelas I (Unglen, Jati) m3 8,250,000.00
209 Kayu Kelas II (Petanang dan sejenis) m3 6,000,000.00
210 Kayu Kelas III (Meranti dan sejenis) m3 3,300,000.00
211 Kayu Papan 3/20 Kls. III m3 3,300,000.00
212 Kayu Kelas IV (Racuk dan sejenis) m3 1,500,000.00
213 Kayu Papan kelas IV keping 16,500.00
214 Kayu Racuk m3 1,650,000.00
215 Kayu Reng btg 30,000.00
216 Keramik lantai/dinding 20 x 20/25 cm putih polos Kotak 58,000.00
Keramik lantai/dinding 20 x 20/25 cm putih polos buah 2,320.00
217 Keramik lantai 20 x 20 cm warna, mutu C Kotak 52,000.00
Keramik lantai 20 x 20 cm warna, mutu C buah 2,080.00
218 Keramik lantai 20 x 20 cm warna, mutu B Kotak 62,000.00
Keramik lantai 20 x 20 cm warna, mutu B buah 2,480.00
219 Keramik dinding 20 x 25 cm warna Kotak 68,000.00
Keramik dinding 20 x 25 cm warna buah 3,400.00
220 Keramik lantai 20 x 25 cm warna, mutu B Kotak 46,600.00
Keramik lantai 20 x 25 cm warna, mutu B buah 2,330.00
221 Keramik lantai 30 x 30 cm warna Kotak 48,000.00
Keramik lantai 30 x 30 cm warna buah 4,320.43
222 Keramik lantai 30 x 30 cm putih polos Kotak 48,000.00
Keramik lantai 30 x 30 cm putih polos buah 4,320.43
223 Keramik lantai 40 x 40 cm warna mutu C Kotak 52,000.00
Keramik lantai 40 x 40 cm warna mutu C buah 8,320.00
224 Keramik lantai 40 x 40 cm warna mutu B Kotak 65,000.00
Keramik lantai 40 x 40 cm warna mutu B buah 10,400.00
225 Keramik lantai motif kayu (kasar) mutu A Kotak 50,000.00
226 Klem Talang Paralon Buah 2,750.00
227 Klem kabel listrik biasa Buah 140.00
HARGA
NO URAIAN SATUAN
PASAR (Rp)
228 Klem kabel listrik Buah 3,000.00
229 Korosin Ltr 2,000.00
230 Kran Air buah 10,000.00
231 Kuas 3"-4" buah 12,500.00
232 Kunci Gembok buah 8,500.00
233 Kunci Lemari buah 8,000.00
234 Kunci Pintu Kamar Tidur (Hotel) buah 400,000.00
235 Kunci Pintu KM/WC (lux) buah 350,000.00
236 Kunci Selot buah 13,000.00
237 Kunci Tanam biasa mutu C buah 25,000.00
238 Kunci Tanam 2 slaag biasa buah 65,000.00
239 Kunci Tanam 2 slaag mutu B buah 90,000.00
240 Kunci Tanam Kamar Mandi buah 27,000.00
241 L.bow listrik buah 2,500.00
242 Lampu Down Light buah 42,500.00
243 Lampu Hologen 50 watt buah 12,500.00
244 Lampu Hologen 150 watt buah 25,000.00
245 Lampu Hologen Box buah 100,000.00
246 Lampu TL 10 Watt buah 7,000.00
247 Lampu TL 20 Watt buah 10,000.00
248 Lampu TL 40 Watt (bambu) buah 105,000.00
249 Lampu Pijar 25 Watt Putih buah 5,000.00
250 Lampu Pijar 40 Watt Putih buah 5,500.00
251 Lantai Granit 30/30 Buah 20,500.00
252 Lantai Granit 40/40 Buah 44,000.00
253 Lantai Granit 60/60 Buah 117,000.00
254 Lantai Kayu Panil Gracewood m2 352,500.00
255 Las dop listrik Buah 500.00
256 Lem Kayu ltr 20,000.00
257 Lem Vinyl Kg 8,500.00
258 List Gypsum Besar m' 22,000.00
259 List Gypsum Kecil m' 12,000.00
260 Mangkok Saklar listrik Buah 1,800.00
261 MCB Buah 44,000.00
262 MCB Box isi 4 grup Buah 25,000.00
263 MCB Box isi 8 grup Buah 55,000.00
264 Melamic Clear kg 60,000.00
265 Melamic Gloss/dop (Finishing) kg 60,000.00
266 Mill kg 33,000.00
267 Minyak Bekisting liter 12,000.00
268 Minyak Cat liter 6,000.00
269 Minyak solar untuk industri / Minyak aspal liter
270 Minyak Gardan liter
271 Minyak Hidrolik liter
272 Minyak Selinder liter
273 Mozaik kayu lantai Uk. 30 x 30 cm buah 7,500.00
274 Pagar BRC, uk. 240 cm X 120 cm, dia. 5,5 mm Unit 345,000.00
275 Pagar BRC, uk. 240 cm X 90 cm, dia. 6 mm Unit 375,000.00
276 Paku Biasa bermacam ukuran 2" - 5" kg 15,000.00
277 Paku Biasa 1/2" - 1" kg 18,000.00
278 Paku Sumbat buah 600.00
279 Paku Beton buah 700.00
280 Paku Gypsum kg 25,000.00
281 Paku Seng,Asbes kg 22,000.00
282 Paku Asbes buah 600.00
283 Paku Sekrup 3,5" Kg 45,000.00
284 Paku Sekrup 3,5" buah 450.00
285 Parquet Jati m2 385,000.00
286 Pasir Beton / Pasang m3 95,000.00
287 Pasir Urug m3 100,000.00
288 Pewarna nat Bks 10,000.00
289 Pintu Alluminium m2 640,000.00
HARGA
NO URAIAN SATUAN
PASAR (Rp)
290 Pintu Besi Baja m2 1,950,000.00
291 Pintu Lipat m2 380,000.00
292 Pintu PVC lengkap Unit 210,000.00
293 Pipa besi medium 2 mm & 1/2", pjg 6 m M' 18,500.00
294 Pipa besi medium 2 mm & 3/4", pjg 6 m M' 23,400.00
295 Pipa besi medium 2 mm & 1", pjg 6 m M' 29,175.00
296 Pipa besi medium 2 mm & 1,5", pjg 6 m M' 41,700.00
297 Pipa besi medium 2 mm & 2", pjg 6 m M' 52,500.00
298 Pipa besi medium 2 mm & 2,5", pjg 6 m M' 68,500.00
299 Pipa besi medium 2 mm & 3", pjg 6 m M' 108,500.00
300 Pipa besi medium 2 mm & 4", pjg 6 m M' 141,400.00
301 Pipa paralon listrik 5/8" Btg 6,000.00
302 Pipa PVC & 1/2" mutu A (Wavin dan sejenis) M' 4,000.00
303 Pipa PVC biasa & 1/2" mutu B M' 3,750.00
304 Pipa PVC & 3/4" mutu A (Wavin dan sejenis) M' 5,500.00
305 Pipa PVC & 3/4" mutu B M' 4,600.00
306 Pipa PVC & 1" mutu A (Wavin dan sejenis) M' 7,500.00
307 Pipa PVC & 1" mutu B M' 4,750.00
308 Pipa PVC & 1.5" mutu A (Wavin dan sejenis) M' 13,000.00
309 Pipa PVC & 1.5" mutu B M' 8,000.00
310 Pipa PVC & 2" mutu A ( Wavin dan sejenis) M' 16,375.00
311 Pipa PVC & 2" mutu B M' 10,500.00
312 Pipa PVC & 3" mutu A (Wavin dan sejenis) M' 32,125.00
313 Pipa PVC & 3" mutu B M' 17,500.00
314 Pipa PVC & 4" mutu A ( Wavin dan sejenis) M' 52,000.00
315 Pipa PVC & 4" mutu B M' 30,000.00
316 Pipa PVC & 6" (15 cm) mutu A (Wavin dan sejenis) M' 123,750.00
317 Pipa Stainless 2", tebal 1 mm M' 75,000.00
318 Pipa Stainless 2", tebal 0.8 mm M' 67,200.00
319 Pipa Stainless 2,5", tebal 1 mm M' 95,200.00
320 Pipa Stainless 2,5", tebal 1.2 mm M' 84,000.00
321 Plamir Tembok kg 8,000.00
322 Plamir Kayu kg 17,000.00
323 Plat stainless, tebal 1 mm, uk. 244 cm X 122 cm Lbr 1,700,000.00
324 Plint keramik 10 x 30 cm warna buah 4,000.00
325 Plint keramik 10 x 40 cm warna buah 13,200.00
326 Plint Ubin PC Abu-abu 15 x 20 cm buah 800.00
327 Plint Ubin PC Abu-abu 10 x 30 cm buah 850.00
328 Plint Ubin PC Abu-abu 10 x 40 cm buah 875.00
329 Plywood warna/Jabarwood Lbr 110,000.00
330 Plywood Jati 3 mm Lbr 110,000.00
331 Plywood Sungkay 3 mm/ megatick Lbr 110,000.00
332 Plywood 3 mm Lbr 42,000.00
333 Plywood 4 mm Lbr 68,000.00
334 Plywood 6 mm Lbr 88,000.00
335 Plywood 9 mm Lbr 125,000.00
336 Plywood 12 mm Lbr 160,000.00
337 Plywood 20 mm Lbr 210,000.00
338 Politur dasar ltr 49,000.00
339 Politur Jadi ltr 53,000.00
340 Porselin Putih Uk. 10 x 10 cm buah 700.00
341 Porselin Warna Uk. 10 x 10 cm buah 1,000.00
342 Rangka Atap baja ringan untuk atap genteng, genteng m2 285,000.00
keramik, beton, dll + pemasangan
343 Rangka Atap baja ringan untuk atap seng metal, atap m2 216,200.00
asbes, aluminium, sirap, dll + pemasangan
344 Rangka Atap baja ringan bentuk joglo/bertumpuk/ m2 281,700.00
khusus + pemasangan
345 Rangka Atap baja ringan "Pryda" untuk atap Pelana, m2 255,500.00
Metal dan keramik + pemasangan
346 Rangka Atap baja ringan "Pryda" untuk atap Perisai, m2 281,700.00
Metal dan keramik + pemasangan
HARGA
NO URAIAN SATUAN
PASAR (Rp)
347 Rangka Atap baja ringan "Pryda" untuk atap Joglo, m2 327,600.00
Metal dan keramik + pemasangan
348 Rel Pintu Dorong Unit 240,000.00
349 Rolling Door Standar, t=4 mm, (minimal pas. 7 M2) m2 585,000.00
350 Rolling Door Standar, t=5 mm, (minimal pas. 7 M2) m2 630,000.00
351 Sanding Sealer Impra (Cat dasar) Kg 38,000.00
352 Seal Tape buah 3,500.00
353 Semen ( 50 kg ) Zak 68,000.00
354 Semen Portland ( PC ) kg 1,750.00
355 Semen Putih (40 kg) Zak 85,000.00
356 Semen Putih Kg 2,000.00
357 Semen Merah m3 38,000.00
358 Semen Nat Bks 12,000.00
359 Seng Gelombang, lebar 70 cm m2 7,425.00
360 Seng Plat 120 cm X 240 cm lbr 96,250.00
361 Seng Plat 33 cm M' 13,200.00
362 Seng Plat 38 cm M' 17,600.00
363 Seng Plat 45 cm M' 18,000.00
364 Seng Plat 55 cm M' 20,440.00
365 Seng Plat 88 cm M' 31,360.00
366 Seng Plat 92 cm M' 31,360.00
367 Sabun Kg 11,200.00
368 Soda Api Kg 30,000.00
369 Soft Board ( 120 x 240 ) mm lbr 67,500.00
370 Saklar Tunggal biasa Buah 6,000.00
371 Saklar Ganda biasa Buah 8,250.00
372 Saklar Tunggal National Buah 15,500.00
373 Saklar Ganda National Buah 23,500.00
374 Scafolding tg 1,77 m X 1,77 m Unit 700,000.00
375 Roda Scafolding 4 buah Unit 425,000.00
376 Smartruss/baja ringan sejenis Aluminium Magnesium
- Lysaght Smartruss/sejenis C 75.100 M' 22,500.00
- Lysaght Smartruss/sejenis C 75.75 M' 18,800.00
- Reng U T S 40 M' 16,300.00
- Screw / Dynabolt Buah 1,900.00
- Valery Gutter Talang Jurai M' 125,400.00
- Strap Bracing M' 12,500.00
377 Stop Kontak biasa Buah 17,000.00
378 Stop kontak AC Buah 65,000.00
379 Sunscreen Aluminium M2 375,000.00
380 T.Duss listrik Buah 1,000.00
381 Talang Paralon, pjg 4 m btg 47,000.00
382 Tali Ijuk Kg 11,400.00
383 Ijuk m3 24,000.00
384 Tanah Liat/Urug m3 57,000.00
385 Tanah Puru m3 62,500.00
386 Tanah Sirtu m3 80,000.00
387 Taekwood 3 mm m2 33,000.00
388 Taekwood 4 mm biasa m2 36,000.00
389 Ter / Residu liter 4,100.00
390 Textil Tape roll 6,850.00
391 Thinner biasa Liter 12,000.00
392 Thinner Cat Glossy (Cobra dan sejenis) Liter 25,000.00
393 Urinoir buah 120,000.00
394 Urinoir mutu A unit 1,500,000.00
395 Vernis ltr 24,000.00
396 Vernis Batu Kg 65,000.00
397 Wallpaper m2 75,000.00
398 Wastafel biasa buah 265,000.00
399 Wastafel Halmar unit 280,000.00
400 Wastafel mutu A unit 450,000.00
401 Wood Filler Impra (dempul) Klg 32,000.00
HARGA
NO URAIAN SATUAN
PASAR (Rp)
402 Wood Stain Impra (cat pewarna) Klg 60,000.00

C PERALATAN
1 Compresor jam
2 Concrete Mixer jam
3 Concrete Pump jam
4 Concrete Vibrator jam
5 Dump Truck jam
6 Excavator jam
7 Filter jam
8 Genset jam
9 Grader jam
10 Loader jam
11 Pneumatic Tired Roller jam
12 Tandem Roller jam
13 Flatbed Truck 3,5 ton jam
14 Water Tank Truck jam
15 Generator jam
16 Alat Bantu jam
17 Roller 3 roda jam
18 Sprayer, Selfprof jam
19 Buldozer jam
20 Scaffolding 177cm X 177 cm, Tg. 177 cm Set/Bulan
21 Stone Crusher (Pemecah batu) jam
22 Pengaduk beton jam
23 Stemper jam
24 Roller, Vibrator Pneu jam
25 Water Pump jam

D SERVICE
1 AC Window/Split/Multi Ls
2 Dispenser Ls
3 Kulkas/Freezer Ls
4 Kompor Gas 2T Ls
5 Kompor Gas 4T Ls
6 Mesin Cuci Ls
7 Pompa Air Ls
8 Instalasi listrik Ls

Palembang, Juli 2013

Tim Survey,

Nama Tanda tangan

1. Poppy Augustina L, ST., MT ………………………………

2. Isrok, ST ………………………………

3. Dedi Sumaryanto, ST, MT ………………………………

4. Andrei Prima Novriansyah, ST, MT ………………………………

5. Ade Abdillah, Amd ………………………………

6. Putri Irli Anggiadini, ST ………………………………


Daftar Analisa Pekerjaan Taksir Tahun 2013 Semester II

DAFTAR ANALISA PEKERJAAN TAKSIR


TAHUN 2013 SEMESTER I
SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

1 1 M2 PAS. DINDING SKAT ALUMINIUM HITAM + KACA


a. Bahan
1.00 m2 Kaca Ryben Tebal 5 mm 155,000.00 155,000.00 155,000.00
4.00 m' Kusen aluminium 4" hitam 60,000.00 240,000.00 240,000.00
Ls 75,000.00 75,000.00 75,000.00
470,000.00 470,000.00
b. Upah
1.00 Ls Tukang dinding skat 138,250.00 138,250.00
138,250.00 138,250.00

Jumlah 470,000.00 138,250.00 608,250.00

2 1 SET PAS. ENGSEL TANAM KUSEN ALUMINIUM


a Bahan
1.00 set Engsel tanam 200,000.00 200,000.00 200,000.00
Ls Kelengkapan lain-lain 15,000.00 15,000.00 15,000.00
215,000.00 215,000.00

b. Upah
1.00 Ls Tukang engsel tanam 125,000.00 125,000.00
125,000.00 125,000.00

Jumlah 215,000.00 125,000.00 340,000.00

3 1 BUAH PAS. CLOSED DUDUK


a Bahan
1.00 Bh Closed Duduk (standar Toto dan sejenis) 2,892,000.00 2,892,000.00 2,892,000.00
Ls Kelengkapan lainnya 150,000.00 150,000.00 150,000.00
3,042,000.00 3,042,000.00

b. Upah
1.00 Ls Tukang Pasang Closed Duduk 125,000.00 125,000.00 125,000.00
125,000.00 125,000.00

Jumlah 3,042,000.00 125,000.00 3,167,000.00

4 1 BUAH PAS. PINTU PVC + KUSEN TYPE B


a Bahan
1.00 Bh Pintu PVC + kusen 500,000.00 500,000.00 500,000.00
1.00 Set Engsel 11,000.00 11,000.00 11,000.00
1.00 Bh Kunci 24,750.00 24,750.00 24,750.00
535,750.00 535,750.00

b. Upah
1.00 Ls Tukang Pasang 65,000.00 65,000.00
65,000.00 65,000.00

Jumlah 535,750.00 65,000.00 600,750.00

5 1 M2 PAS. KACA FILM SUN GLASS KOTAK


a Bahan
1.00 m2 Kaca film sun glass kotak 300,000.00 300,000.00 300,000.00
Ls Alat bantu 7,500.00 7,500.00 7,500.00
307,500.00 307,500.00

b. Upah
1.00 Ls Tukang Kaca film 55,000.00 55,000.00
55,000.00 55,000.00

Jumlah 307,500.00 55,000.00 362,500.00

6 1 BUAH PAS. SARINGAN AIR


a Bahan
1.00 bh Saringan air 17,000.00 17,000.00 17,000.00
17,000.00 17,000.00

b. Upah
1.00 Oh Tukang saringan air 5,000.00 5,000.00
5,000.00 5,000.00

Jumlah 17,000.00 5,000.00 22,000.00

- 83 -
Daftar Analisa Pekerjaan Taksir Tahun 2013 Semester II

SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

7 1 BUAH PAS. PINTU PANEL LAPIS SUNGKAI + LIST STAINLIS


a Bahan
1.60 bh Pintu panel (SNI. 6.7) 699,000.00 1,118,400.00 1,118,400.00
1.12 kpg Sungkai (SNI 6.46) 151,212.60 169,358.11 169,358.11
4.80 m' List steinlis 100,000.00 480,000.00 480,000.00
0.10 kg Paku plywood 32,500.00 3,250.00 3,250.00
3.20 m2 Plituran (SNI. 14.9) 47,747.60 152,792.32 152,792.32
1.00 bh Kunci (SNI 12.1) 257,600.00 257,600.00 257,600.00
3.00 bh Engsel (SNI 12.4) 42,075.00 126,225.00 126,225.00
2,307,625.43 2,307,625.43

b. Upah
1.00 Ls Pekerja + tukang 65,000.00 65,000.00

Jumlah 2,307,625.43 65,000.00 2,372,625.43

8 PAS. LIST PLAFON 1/4 / M'


a Bahan
1.00 m' List plafon 1/4 3,500.00 3,500.00 3,500.00
3,500.00 3,500.00

b. Upah
1.00 Ls Pekerja 750.00 750.00

Jumlah 3,500.00 750.00 4,250.00

9 PAS. PINTU PVC TYPE C/ BUAH


a Bahan
1.00 bh Pintu PVC 300,000.00 300,000.00 300,000.00
1.00 bh Kunci 11,000.00 11,000.00 11,000.00
3.00 bh Engsel 24,750.00 74,250.00 74,250.00
385,250.00 385,250.00

b. Upah
1.00 Ls Pekerja pintu 55,000.00 75,000.00 75,000.00
75,000.00 75,000.00

Jumlah 385,250.00 75,000.00 460,250.00

10 PAS. KUSEN DAN JENDELA ALUMINIUM


a Bahan
1.00 set Kusen dan jendela aluminium 1,232,000.00 1,232,000.00 1,232,000.00
1,232,000.00 1,232,000.00

b. Upah
1.00 Ls Tukang 431,200.00 431,200.00
431,200.00 431,200.00

Jumlah 1,232,000.00 431,200.00 1,663,200.00

11 1 M' PAS. LISTPLANK WOODPLANK


a Bahan
1.00 m' Woodplank 22,000.00 22,000.00 22,000.00
Ls Peralatan kecil 1,500.00 1,500.00 1,500.00
23,500.00 23,500.00

b. Upah
1.00 Oh Pekerja 7,000.00 7,000.00
7,000.00 7,000.00

Jumlah 23,500.00 7,000.00 30,500.00

12 1 M3 PAS. HURUF NAMA KANTOR


a Bahan
1.00 m' Plat stainless 77,500.00 77,500.00 77,500.00
1.00 Perlengkapan 30% 23,250.00 23,250.00 23,250.00
100,750.00 100,750.00

b. Upah
0.15 Oh Pekerja 55,000.00 8,250.00 8,250.00
0.03 Oh Kepala tukang 99,000.00 2,970.00 2,970.00
0.0252 Oh Mandor 99,000.00 2,650.00 2,650.00
13,870.00 13,870.00

Jumlah 100,750.00 13,870.00 114,620.00

13 PAS. PAPAN NAMA DAN PLAT BESI


a Bahan
1.00 Ls Besi T=2mm 750,000.00 750,000.00 750,000.00
1.00 Perlengkapan 30% 262,500.00 262,500.00 262,500.00
1.00 Besi siku 40x40x4mm 245,000.00 245,000.00 245,000.00
1.00 Perlengkapan 35% 85,750.00 85,750.00 85,750.00
2.00 Btg Besi siku 245,000.00 490,000.00 490,000.00

- 84 -
Daftar Analisa Pekerjaan Taksir Tahun 2013 Semester II

SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
1,833,250.00 1,833,250.00

b. Upah
3.00 Oh Pekerja 77,500.00 232,500.00 232,500.00
1.00 Oh Kepala tukang 150,000.00 150,000.00 150,000.00
0.9048 Oh Mandor 150,000.00 135,720.00 135,720.00
518,220.00 518,220.00

Jumlah 1,833,250.00 518,220.00 2,351,470.00

14 PAS. TIANG PROFIL TERAS


a Bahan
1.00 Tiang profil 225,000.00 225,000.00 225,000.00
1.00 Perlengkapan 30% 75,000.00 75,000.00 75,000.00
300,000.00 300,000.00

b. Upah
3.00 Oh Pekerja 77,500.00 232,500.00 232,500.00
3.00 Oh Kepala tukang 150,000.00 450,000.00 450,000.00
0.7619 Oh Mandor 150,000.00 80,000.00 80,000.00
762,500.00 762,500.00

Jumlah 300,000.00 762,500.00 1,062,500.00

15 1 M2 PAS. DINDING SEKAT + JENDELA ALUMINIUM


a Bahan
1.00 m2 Kaca tebal 5mm 121,000.00 121,000.00 121,000.00
4.00 m' Rangka aluminium 60,000.00 240,000.00 240,000.00
361,000.00 361,000.00

b. Upah
0.80 Oh Pekerja 77,500.00 62,000.00 62,000.00
2.00 Oh Tukang 82,500.00 165,000.00 165,000.00
0.20 Oh Kepala tukang 150,000.00 30,000.00 30,000.00
0.040 Oh Mandor 150,000.00 6,000.00 6,000.00
263,000.00 263,000.00

Jumlah 361,000.00 263,000.00 624,000.00

16 1 M2 PAS. PINTU KACA RANGKA ALUMINIUM + KUSEN


a Bahan
1.10 m2 Kaca tebal 5mm 121,000.00 121,000.00 121,000.00
8.60 m' Rangka aluminium 60,000.00 516,000.00 516,000.00
637,000.00 637,000.00

b. Upah
0.80 Oh Pekerja 77,500.00 62,000.00 62,000.00
2.00 Oh Tukang 82,500.00 165,000.00 165,000.00
0.20 Oh Kepala tukang 150,000.00 30,000.00 30,000.00
0.040 Oh Mandor 150,000.00 6,000.00 6,000.00
263,000.00 263,000.00

Jumlah 637,000.00 263,000.00 900,000.00

17 1 LBG KUSEN PINTU KAYU+ RAAM


a Bahan
1.00 lbg Kusen pintu kayu (kulim) + raam 850,000.00 850,000.00 850,000.00

b. Upah 75,000.00 75,000.00 75,000.00

Jumlah 850,000.00 75,000.00 925,000.00

18 1 LBG KUSEN PINTU KAYU TANPA RAAM


a Bahan
1.00 lbg Kusen pintu kayu (kulim) tanpa raam 600,000.00 600,000.00 600,000.00

b. Upah 60,000.00 60,000.00 60,000.00

Jumlah 600,000.00 60,000.00 660,000.00

19 1 BUAH PINTU KAYU (MERAWAN) PANEL


a Bahan
1.00 bh Pintu kayu (merawan) panel 1,100,000.00 1,100,000.00 1,100,000.00

b. Upah 110,000.00 110,000.00 110,000.00

Jumlah 1,100,000.00 110,000.00 1,210,000.00

20 1 BUAH PINTU KAYU (MEDANG) PANEL


a Bahan

- 85 -
Daftar Analisa Pekerjaan Taksir Tahun 2013 Semester II

SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
1.00 bh Pintu kayu (medang) panel 900,000.00 900,000.00 900,000.00

b. Upah 75,000.00 75,000.00 75,000.00

Jumlah 900,000.00 75,000.00 975,000.00

21 1 BUAH DAUN JENELA KACA KAYU MERAWAN PANJANG


a Bahan
1.00 bh Daun jendela kaca kayu merawan panjang 550,000.00 550,000.00 550,000.00

b. Upah 60,000.00 60,000.00 60,000.00

Jumlah 550,000.00 60,000.00 610,000.00

22 1 BUAH DAUN JENELA KACA KAYU MERAWAN SEDANG


a Bahan
1.00 bh Daun jendela kaca kayu merawan sedang 440,000.00 440,000.00 440,000.00

b. Upah 44,000.00 44,000.00 44,000.00

Jumlah 440,000.00 44,000.00 484,000.00

23 1 BUAH DAUN JENELA KACA KAYU MEDANG PANJANG


a Bahan
1.00 bh Daun jendela kaca kayu medang panjang 450,000.00 450,000.00 450,000.00

b. Upah 45,000.00 45,000.00 45,000.00

Jumlah 450,000.00 45,000.00 495,000.00

24 1 BUAH DAUN JENELA KACA KAYU MEDANG SEDANG


a Bahan
1.00 bh Daun jendela kaca kayu medang sedang 400,000.00 400,000.00 400,000.00

b. Upah 40,000.00 40,000.00 40,000.00

Jumlah 400,000.00 40,000.00 440,000.00

25 1 BUAH PINTU PLYWOOD + RANGKA DOBEL


a Bahan
1.00 Bh Pintu plywood + rangka dobel 440,000.00 440,000.00 440,000.00

b. Upah 40,000.00 40,000.00 40,000.00

Jumlah 440,000.00 40,000.00 480,000.00

26 1 BUAH ROSTER KAYU UKURAN 35X35 CM


a Bahan
1.00 Bh Roster kayu ukuran 35x35 cm 110,000.00 110,000.00 110,000.00

b. Upah 11,000.00 11,000.00 11,000.00

Jumlah 110,000.00 11,000.00 121,000.00

27 1 BH VENTILASI KAYU + KACA WC UK. 40 x 30 CM


a Bahan
1.00 bh Ventilasi kayu + kaca wc uk. 40 x 30 cm 140,000.00 140,000.00 140,000.00

b. Upah 14,000.00 14,000.00 14,000.00

Jumlah 140,000.00 14,000.00 154,000.00

28 1 M2 PINTU FOLDING GATE (MIN. 7 M2)


a Bahan
1.00 M2 Pintu folding gate tebal 0,5mm 600,000.00 600,000.00 600,000.00
1.00 M2 Pintu folding gate tebal 0,8mm 670,000.00 670,000.00 670,000.00
1.00 M2 Pintu folding gate tebal 1,2mm 940,000.00 940,000.00 940,000.00

29 1 M2 ALKABON + RANGKA + PASANGAN


a Bahan + Upah pasangan

- 86 -
Daftar Analisa Pekerjaan Taksir Tahun 2013 Semester II

SATUAN HARGA
NO. Harga Jumlah Harga Jumlah Jumlah
URAIAN Satuan Bahan Tenaga Bahan+Tenaga
Analisa
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
1.00 M2 Alkabon + Rangka + Pasangan 550,000.00 550,000.00 550,000.00

30 1 m2 PAS. CONEBLOCK WARNA SEGI ENAM


a. Bahan
44 Bh Coneblock Warna segi enam 2,640.00 116,160.00 116,160.00
0.1000 M3 Pasir Pasang 118,750.00 11,875.00 11,875.00
128,035.00 128,035.00

b. Tenaga
0.3500 Oh Pekerja 55,000.00 19,250.00 19,250.00
0.0175 Oh Mandor 99,000.00 1,732.50 1,732.50
20,982.50 20,982.50

Pas. Coneblock warna segi enam 128,035.00 20,982.50 149,017.50

Mengetahui/ Menyetujui :
Kepala Dinas Pekerjaan Umum
Cipta Karya dan Perumahan Kota Palembang

Ir. HJ. ANA HERYANA, MT


NIP. 19610926 199303 2 002

- 87 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II

REKAPITULASI HARGA SATUAN UPAH DAN BAHAN BANGUNAN


TAHUN ANGGARAN 2013 SEMESTER I

Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3

I PEKERJAAN PERSIAPAN

1.1 1 M' Pagar Sementara dari Kayu Tinggi 2 Meter Rp 222,823.41

1.2 1 M' Pagar Sementara dari Seng Gelombang Tinggi 2 Meter Rp 231,139.41

1.3 1 M' Pagar Sementara dari Kawat Duri Tinggi 1,8 Meter Rp 485,923.41

1.4 1 M' Pengukuran dan Pemasangan Bouwplank Rp 68,280.00

1.5 1 M2 Pembuatan Kantor Sementara, Dengan Lantai Plesteran Rp 1,380,410.09

1.6 1 M2 Pembuatan Gudang Semen dan Alat - Alat Rp 794,616.28

1.7 1 M2 Pembuatan Rumah Jaga/Konstruksi Kayu Rp 804,917.50

1.8 1 M2 Membersihkan Lapangan dan Perataan Rp 15,250.00

1.9 1 M2 Pembuatan Bedeng Buruh Rp 871,097.53

1.10 1 M2 Pembuatan Bak Adukan Ukuran (40 x 50 x 20) cm Rp 189,105.00

1.11 1 M2 Pembuatan Stegger dari Bambu, Ukuran (40 x 50 x 20) cm Rp 81,885.00

1.12 1 M2 Pembuatan Jalan Sementara Rp 178,587.50

1.13 1 M3 Bongkaran Beton Bertulang Rp 566,642.50

1.14 1 M3 Bongkaran Dinding Tembok Bata Merah /Bata lobang Rp 521,642.50

1.15 1 M' Pasang Pagar Kawat Jaring Galvanis Tinggi 1 Meter Rp 22,772.20

1.16 10 M2 Pembersihan Akhir Lapangan = 1 M2 Rp 6,375.00

1.17 10 M2 Bongkaran Rangka Atap = 1 M2 Rp 11,250.00

1.18 1 M3 Bongkaran Kuda-kuda Kayu Rp 575,000.00

1.19 10 M2 Bongkaran Plafond + Rangka = 1 M2 Rp 23,900.00

1.20 1 M2 Pasang Cerucup Gelam dia. 6-8 cm = 1 M2 Rp 80,450.00


1 M2 Pasang Cerucup Gelam dia. 10-12 cm = 1 M2 Rp 87,050.00

1.21 1 M' Pasang Turap Gelam = 1 M' Rp 150,850.00

1.22 1 M2 Pasang Kisdam Gelam dia. 6-8 cm = 1 M' Rp 70,787.50

1.23 1 Unit Papan Nama biasa = 1 Unit Rp 312,275.00

1.24 1 Unit Sewa Scafolding per bulan = 1 Unit Rp 202,241.12

II PEKERJAAN TANAH

2.1 1 M3 Galian Tanah Biasa Sedalam 1 Meter Rp 37,000.00

2.2 1 M3 Galian Tanah Biasa Sedalam 2 Meter Rp 48,565.00

2.3 1 M3 Galian Tanah Biasa Sedalam 3 Meter Rp 67,912.50

- 88 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II

Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3

2.4 1 M3 Galian Tanah Keras Sedalam 1 Meter Rp 57,737.50

2.5 1 M3 Galian Tanah Cadas Sedalam 1 Meter Rp 115,625.00

2.6 1 M3 Galian Tanah Lumpur Sedalam 1 Meter Rp 76,232.50

2.7 1 M2 Pekerjaan Stripping Setinggi 1 Meter Rp 4,625.00

2.8 1 M3 Pembuangan Tanah Sejauh 150 meter Rp 47,490.00

2.9 1 M3 Urugan Kembali Rp 17,730.00

2.10 1 M3 Pemadatan Tanah Rp 46,250.00

2.11 1 M3 Urugan Pasir Rp 123,750.00

2.12 1 M3 Urugan Sirtu Rp 128,725.00

2.13 1 M3 Urugan Koral Rp 629,220.74

2.14 1 M3 Urugan Tanah Rp 100,800.00

III PEKERJAAN PONDASI

3.1 1 M3 Pasang Pondasi Batu Kali, 1 Pc : 1 Ps Rp 1,338,687.50

3.2 1 M3 Pasang Pondasi Batu Kali, 1 Pc : 2 Ps Rp 1,139,606.25

3.3 1 M3 Pasang Pondasi Batu Kali, 1 Pc : 2,5 Ps Rp 1,338,687.50

3.4 1 M3 Pasang Pondasi Batu Kali, 1 Pc : 3 Ps Rp 1,035,993.75

3.5 1 M3 Pasang Pondasi Batu Kali, 1 Pc : 4 Ps Rp 973,850.00

3.6 1 M3 Pasang Pondasi Batu Kali, 1 Pc : 5 Ps Rp 930,800.00

3.7 1 M3 Pasang Pondasi Batu Kali, 1 Pc : 6 Ps Rp 900,518.75

3.8 1 M3 Pasang Pondasi Batu Kali, 1 Pc : 8 Ps Rp 856,318.75

3.9 1 M3 Pasang Pondasi Sumuran & 100 cm Rp 1,288,767.42

3.10 1 M' Pembuatan Tiang Pancang (40 x 40) cm, Beton Bertulang Rp 992,922.59

3.11 1 M' Pembuatan Tiang Pancang (35 x 35) cm, Beton Bertulang Rp 778,341.83

3.12 1 M3 Pas. Pondasi Batu Bata Ad. 1 : 4 Rp 1,071,759.70

3.13 1 M3 Pas. Pondasi Batu Bata Ad. 1 : 2 Rp 1,155,692.55

IV PEKERJAAN DINDING

4.1 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 1 Ps Rp 391,232.25

4.2 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 2 Ps Rp 358,825.00

4.3 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 3 Ps Rp 342,196.25

4.4 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 4 Ps Rp 331,553.75

4.5 1 M2 Pasangan Bata Lobang Tebal 1 Bata, 1 Pc : 4 Ps Rp 238,503.75

- 89 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II

Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3

4.6 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 5 Ps Rp 325,227.50

4.7 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 6 Ps Rp 325,227.50

4.8 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 1 Ps Rp 187,885.00

4.9 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 2 Ps Rp 174,027.50

4.10 1 M2 Pasangan Bata Lobang Tebal 1/2 Bata, 1 Pc : 2 Ps Rp 127,502.50

4.11 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 3 Ps Rp 166,479.00

4.12 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 4 Ps Rp 161,956.25

4.13 1 M2 Pasangan Bata Lobang Tebal 1/2 Bata, 1 Pc : 4 Ps Rp 115,431.25

4.14 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 5 Ps Rp 159,099.75

4.15 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 6 Ps Rp 157,262.75

4.16 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 8 Ps Rp 154,287.50

4.17 1 M2 Pasang Dinding Roster / Terawang ( 12 x 11 x 24 ) cm Rp 233,716.25

4.18 1 M2 Pasangan Bataco Rp 95,709.20

V PEKERJAAN PLESTERAN

5.1 1 M2 Plesteran 1 Pc : 1 Ps, Tebal 15 mm Rp 61,507.75

5.2 1 M2 Plesteran 1 Pc : 2 Ps, Tebal 15 mm Rp 54,502.75

5.3 1 M2 Plesteran 1 Pc : 3 Ps, Tebal 15 mm Rp 51,272.25

5.4 1 M2 Plesteran 1 Pc : 4 Ps, Tebal 15 mm Rp 49,215.00

5.5 1 M2 Plesteran 1 Pc : 5 Ps, Tebal 15 mm Rp 47,956.50

5.6 1 M2 Plesteran 1 Pc : 6 Ps, Tebal 15 mm Rp 46,987.25

5.7 1 M2 Plesteran 1 Pc : 8 Ps, Tebal 15 mm Rp 45,746.00

5.8 1 M2 Plesteran 1 Pc : 0,5 Kp : 3 Ps, Tebal 15 mm Rp 49,335.75

5.9 1 M2 Plesteran 1 Pc : 3 Kp : 10 Ps, Tebal 15 mm Rp 42,790.50

5.10 1 M2 Plesteran 0,5 Pc : 1 Kp : 4 Ps, Tebal 15 mm Rp 45,356.25

5.11 1 M2 Plesteran 1 Kp : 1 Sm : 1 Ps, Tebal 15 mm Rp 39,444.95

5.12 1 M2 Plesteran 1 Kp : 1 Sm : 2 Ps, Tebal 15 mm Rp 40,073.85

5.13 1 M2 Plesteran 1 Pc : 2 Ps, Tebal 20 mm Rp 76,257.25

5.14 1 M2 Plesteran 1 Pc : 3 Ps, Tebal 20 mm Rp 70,697.50

5.15 1 M2 Plesteran 1 Pc : 4 Ps, Tebal 20 mm Rp 67,331.00

5.16 1 M2 Plesteran 1 Pc : 5 Ps, Tebal 20 mm Rp 64,968.00

- 90 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II

Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
5.17 1 M2 Plesteran 1 Pc : 6 Ps, Tebal 20 mm Rp 63,420.50

5.18 1 M2 Plesteran 1 Kp : 1 Sm : 2 Ps, Tebal 20 mm Rp 51,763.70

5.19 1 M2 Berapen 1 Pc : 5 Ps, Tebal 15 mm Rp 34,995.25

5.20 1 M2 Plesteran Beton 1 Pc : 2 Ps, Tebal 15 mm Rp 68,047.50

5.21 1 M2 Plesteran Beton 1 Pc : 3 Ps, Tebal 15 mm Rp 64,612.75

5.22 1 M2 Plesteran Ciprat 1 Pc : 2 Ps Rp 44,869.00

5.23 1 M2 Plesteran Siar Adukan 1 Pc : 2 Ps Rp 31,869.00

5.24 1 M3 Perekat Rp 899,056.40

5.25 1 M' Plesteran dibentuk Profil uk. 10 x 10 cm Rp 226,218.00

VI PEKERJAAN KAYU

6.1 1 M3 Pasang Kusen Pintu dan Jendela K.kls. I (Kayu Jati, Unglen) Rp 13,292,500.00

6.2 1 M3 Pasang Kusen Pintu dan Jendela Kayu Kls. II Rp 10,980,000.00

6.3 1 M3 Pasang Kusen Pintu dan Jendela Kayu Kelas III Rp 7,416,000.00

6.4 1 M2 Pasang Pintu Klam Kayu Kls. III Rp 308,930.00

6.5 1 M2 Pasang Pintu Klam Kayu Kls. IV Rp 237,650.00

6.6 1 M2 Pasang Pintu Panel Kayu Jati Rp 798,000.00

6.7 1 M2 Pasang Pintu Panel Kayu Kls. II Rp 699,000.00

6.8 1 M2 Pasang Pintu dan Jendela Kaca Kayu Jati Rp 665,625.00

6.9 1 M2 Pasang Pintu dan Jendela Kaca Kayu Kls. II Rp 579,000.00

6.10 1 M2 Pasang Pintu dan Jendela Kaca Kayu Kls. III Rp 475,050.00

6.11 1 M2 Pasang Pintu dan Jendela Jalusi Kayu Jati Rp 1,123,300.00

6.12 1 M2 Pasang Pintu dan Jendela Jalusi Kayu Kls. II Rp 994,900.00

6.13 1 M2 Pasang Pintu Plywood Rangkap, Rangka Kayu Jati Rp 598,945.00

6.14 1 M2 Pasang Pintu Plywood Rangkap, Rangka Kayu Kls. II Rp 550,435.00

6.15 1 M2 Daun Pintu Plywood Sungkay rangkap, kayu kls. II Rp 588,935.00

6.16 1 M3 Pasang Konstruksi Kuda-kuda Kayu Jati Rp 12,190,300.00

6.17 1 M3 Pasang Konstruksi Kuda-kuda Kayu Kls. II Rp 9,467,800.00

6.18 1 M3 Pasang Konstruksi Kuda-kuda Kayu Kls. III Rp 6,200,800.00

6.19 1 M2 Pasang Kaso + Reng Genteng Kayu Kls. III Genteng kodok Rp 70,335.00
Genteng beton Rp 77,595.00

6.20 1 M2 Pasang Kaso + Reng Genteng Kayu Kls. II Genteng kodok Rp 105,975.00

- 91 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II

Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
Genteng beton Rp 119,175.00

6.21 1 M2 Pasang Kaso + Reng Atap Sirap,seng/asbes Kayu Kls. II Atap sirap Rp 141,600.00
Atap seng/asbes Rp 98,700.00

6.22 1 M2 Pasang Kaso + Reng Atap Sirap,seng/asbes Kayu Kls. III Atap sirap Rp 92,595.00
Atap seng/asbes Rp 69,000.00

6.23 1 M2 Pasang Rangka Langit-langit (1,00 x 1,00) m, Kayu Jati Rp 169,625.00

6.24 1 M2 Pasang Rangka Langit-langit (1,00 x 1,00) m, Kayu Kls. II Rp 139,925.00

6.25 1 M2 Pasang Rangka Langit-langit (1,00 x 1,00) m, Kayu Kls. III Rp 104,285.00

6.26 1 M2 Pasang Rangka Langit-langit (30 x 60) cm, Kayu Jati Rp 272,000.00

6.27 1 M2 Pasang Rangka Langit-langit (30 x 60) cm, Kayu Kls. II Rp 215,075.00

6.28 1 M2 Pasang Rangka Langit-langit (30 x 60) m, Kayu Kls. III Rp 146,765.00

6.29 1 M2 Pasang Rangka Langit-langit (30 x 30) cm, Kayu Jati Rp 320,975.00

6.30 1 M2 Pasang Rangka Langit-langit (30 x 30) cm, Kayu Kls. II Rp 254,150.00

6.31 1 M2 Pasang Rangka Langit-langit (30 x 30) m, Kayu Kls. III Rp 173,960.00

6.32 1 M' Pasang Lisplang Ukuran (3 x 20) cm, Kayu Jati Rp 104,015.00

6.33 1 M' Pasang Lisplang Ukuran (3 x 20) cm, Kayu Kls. II Rp 86,195.00

6.34 1 M' Pasang Lisplang Ukuran (3 x 30) cm, Kayu Jati Rp 141,325.00

6.35 1 M' Pasang Lisplang Ukuran (3 x 30) cm, Kayu Kls. II Rp 114,100.00

6.36 1 M' Pasang Lisplang Ukuran 2 x (3 x 20) cm, Kayu Kls.II Rp 155,285.00

6.37 1 M' Pasang Lisplang Ukuran 2 x (2 x 20) cm, Kayu Kls. II Rp 87,720.00

6.38 1 M' Pasang Lisplang Ukuran 2 x (2 x 20) cm, Kayu Kls. III Rp 62,904.00

6.39 1 M2 Pasang Rangka Dinding Pemisah + Papan Kayu Kls. II Rp 263,625.00

6.40 1 M2 Pasang Rangka Dinding Pemisah + Papan Kayu Kls. III Rp 184,920.00

6.41 1 M2 Pasang Dinding Pemisah Teakwood Rangkap, Rangka Kayu kls. II Rp 263,625.00

6.42 1 M2 Pasang Dinding Pemisah Plywood Rangkap, Rangka Kayu Kelas III Rp 294,865.00

6.43 1 M2 Pasang Dinding Lambriziring Dari Papan Jati Rp 378,900.00

6.44 1 M2 Pasang Plywood Tebal 4 mm, Untuk Dinding Rp 47,257.50

6.45 1 M' Pasang List Plafond Kayu Profil Kayu Profil Kecil Rp 7,590.00
Kayu Profil Sedang Rp 8,745.00
Kayu Profil Besar Rp 13,365.00

6.46 1 M2 Pasang Interior Display lapis plywood Sungkay + politur Rp 151,212.60

6.47 1 M2 Pasang lapis plywood Sungkay tanpa rangka, politur dan lis profil Rp 57,817.50

- 92 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II

Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
6.48 1 M2 Pasang lapis plywood Sungkay + list kayu, tanpa rangka dan politur Rp 74,157.50

6.49 1 M2 Pasangan Interior display + lapis jati dipolitur Rp 215,900.10

6.50 1 M2 Dinding Sekat Teakwood 4 mm, Rangkap + Rangka Kayu kls. II Rp 322,050.00

6.51 1 M2 Dinding pemisah Plywood Sungkai rangkap + rangka kayu kls. II Rp 380,585.00

VII PEKERJAAN BETON

7.1 1 M3 Membuat Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr Rp 1,058,625.04

7.2 1 M3 Membuat Beton Tumbuk, 1 Pc : 3 Ps : 6 Kr Rp 1,053,307.08

7.3 1 M3 Membuat Beton Tumbuk, 1 Pc : 4 Ps : 6 Kr Rp 988,062.54

7.4 1 M2 Membuat Lantai Kerja Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr, Tebal 5 cm Rp 135,741.93

7.5 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 2 Ps : 3 Kr Rp 1,035,728.48

7.6 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 2 Ps : 4 Kr Rp 1,171,278.06

7.7 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 2 Ps : 2,5 Kr Rp 1,202,970.43

7.8 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 1,5 Ps : 3 Kr Rp 1,111,829.33

7.9 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 1,5 Ps : 2,5 Kr Rp 1,291,590.98

7.10 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 1 Ps : 2 Kr Rp 1,417,061.96

7.11 1 M3 Membuat Tiang Pancang Prestressed Beton Rp 1,397,330.50

7.12 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 2 Ps : 3 Split Rp 1,409,594.00

7.13 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 2 Ps : 4 Split Rp 1,387,043.58

7.14 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 1,5 Ps : 3 Split Rp 1,486,738.55

7.15 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 1,5 Ps : 2,5 Split Rp 1,506,080.50

7.16 1 M3 Membuat Beton Tak Bertulang, 1 Pc : 1 Ps : 1 Split Rp 1,731,052.32

7.17 1 M3 Membuat Beton Kedap Air dengan Strorox - 100

7.18 1 Kg Pembesian dengan Besi Polos atau Besi Ulir Rp 14,543.25

7.19 1 Kg Kabel Presstressed Polos / Strands

7.20 1 M2 Pasang Bekisting Untuk Pondasi Rp 134,950.00

7.21 1 M2 Pasang Bekisting Untuk Sloof Rp 143,200.00

7.22 1 M2 Pasang Bekisting Untuk Kolom (Untuk bangunan gedung) Rp 190,100.00

7.23 1 M2 Pasang Bekisting Untuk Kolom (Jerambah Beton) Rp 78,825.00

7.24 1 M2 Pasang Bekisting Untuk Balok (Untuk bangunan gedung) Rp 196,600.00

7.25 1 M2 Pasang Bekisting Untuk Balok (Jerambah Beton) Rp 97,200.00

7.26 1 M2 Pasang Bekisting Untuk Lantai, plat dak (untuk bangunan gedung) Rp 226,850.00

7.27 1 M2 Pasang Bekisting Untuk Lantai ( jerambah beton) Rp 122,425.00

- 93 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II

Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3

7.28 1 M2 Pasang Bekisting Untuk Dinding Rp 192,200.00

7.29 1 M2 Pasang Bekisting Untuk Tangga Rp 175,150.00

7.30 1 M3 Beton Ready Mix K 175 dengan pengangkutan Rp 1,152,870.88

7.31 1 M3 Beton Ready Mix K 175 tanpa pengangkutan Rp 1,137,287.55

7.32 1 M3 Beton Ready Mix K 225 dengan pengangkutan Rp 1,208,970.88

7.33 1 M3 Beton Ready Mix K 225 tanpa pengangkutan Rp 1,193,387.55

7.34 1 M3 Beton Ready Mix K 250 dengan pengangkutan Rp 1,265,070.88

7.35 1 M3 Beton Ready Mix K 250 tanpa pengangkutan Rp 1,249,487.55

7.36 1 M3 Beton Ready Mix K 275 dengan pengangkutan Rp 1,321,170.88

7.37 1 M3 Beton Ready Mix K 275 tanpa pengangkutan Rp 1,305,587.55

7.38 1 M3 Beton Ready Mix K 300 dengan pengangkutan Rp 1,377,270.88

7.39 1 M3 Beton Ready Mix K 300 tanpa pengangkutan Rp 1,361,687.55

7.40 1 M3 Beton Ready Mix K 350 dengan pengangkutan Rp 1,321,170.88

7.41 1 M3 Beton Ready Mix K 350 tanpa pengangkutan Rp 1,305,587.55

7.42 1 M' Pasang Kayu Mal Bekisting untuk Beton Ready Mix jalan Rp 65,575.00

7.43 1 M3 Membuat Beton dengan Mutu K 225 Rp 1,724,040.40

7.44 1 M3 Membuat Beton dengan Mutu K 275 Rp 1,802,957.51

7.45 1 M2 Pasang Jembatan Cor Rp 84,735.00

7.46 1 M3 Membuat Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting ) Rp 3,912,853.48

7.47 1 M3 Membuat Sloof Beton Bertulang ( 200 Kg Besi + Bekisting ) Rp 4,857,228.48

7.48 1 M3 Membuat Kolom Beton Bertulang ( 300 Kg Besi + Bekisting ) Rp 7,332,153.48

7.49 1 M3 Membuat Kolom Beton Bertulang ( 200 Kg Besi + Bekisting ) Rp 5,969,953.48

7.50 1 M3 Membuat Kolom Beton Bertulang ( 100 Kg Besi + Bekisting ) Rp 4,762,453.48

7.51 1 M3 Membuat Balok Beton Bertulang ( 200 Kg Besi + Bekisting ) Rp 5,456,353.48

7.52 1 M3 Membuat Balok Beton Bertulang ( 150 Kg Besi + Bekisting ) Rp 4,880,703.48

7.53 1 M3 Membuat Balok Beton Bertulang ( 100 Kg Besi + Bekisting ) Rp 4,397,703.48

7.54 1 M3 Membuat Dinding Beton Bertulang ( 150 Kg Besi + Bekisting ) Rp 4,707,003.48

7.55 1 M3 Membuat 1/2 Dinding Beton Bertulang ( 100 Kg Besi + Bekisting) Rp 3,100,273.48

7.56 1 M3 Membuat Tangga Beton Bertulang ( 200 Kg Besi + Bekisting ) Rp 5,161,003.48

7.57 1 M' Membuat Kolom Penguat Beton Bertulang ( 11 x 11 ) cm + bekisting (kolom praktis) Rp 74,402.16

7.58 1 M' Membuat Ring Balok Beton Bertulang ( 10 x 15 ) cm Rp 90,556.51

7.59 1 M2 Pasang Bekisting Untuk Lantai, plat dak dengan plywood 4 mm Rp 255,725.00

- 94 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II

Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3

7.60 1 M3 Beton Ready Mix K-175 untuk Kolom, Balok, Plat Lantai, tangga dengan Concrete Pump (belalai Rp 1,205,591.46

7.61 1 M3 Beton Ready Mix K-175 untuk Kolom, Balok, Plat Lantai, tangga tanpa Concrete Pump (belalai) Rp 1,137,287.55

7.62 1 M3 Beton Ready Mix K-225 untuk Kolom, Balok, Plat Lantai, tangga dengan Concrete Pump (belalai Rp 1,261,691.46

7.63 1 M3 Beton Ready Mix K-225 untuk Kolom, Balok, Plat Lantai, tangga tanpa Concrete Pump (belalai) Rp 1,193,387.55

7.64 1 M3 Beton Ready Mix K-275 untuk Kolom, Balok, Plat Lantai, tangga dengan Concrete Pump (belalai Rp 1,373,891.46

VIII PEKERJAAN PENUTUP ATAP

8.1 1 M2 Pasang Atap Genteng Kodok Rp 50,900.00

8.2 1 M2 Pasang Atap Genteng keramik biasa bergalzur Rp 181,800.00

8.3 1 M2 Pasang Atap Genteng keramik KIA Natural / sejenis Rp 221,400.00

8.4 1 M2 Pasang Atap Genteng keramik KIA Berwarna / sejenis Rp 303,900.00

8.5 1 M' Pasang Bubung Genteng Kodok Rp 98,700.00

8.6 1 M' Pasang Bubung Genteng Keramik biasa berglazzur Rp 120,700.00

8.7 1 M' Pasang Bubung Genteng Keramik KIA Natural atau sejenis Rp 142,700.00

8.8 1 M' Pasang Bubung Genteng Keramik KIA Warna atau sejenis Rp 159,200.00

8.9 1 M2 Pasang Roof Light Fibreglass Polycarbon Rp 110,950.00

8.10 1 M2 Pasang Atap Asbes Gelombang kecil lbr 0,8 tbl 4 mm Rp 54,479.00

8.11 1 M2 Pasang Atap Asbes Gelombang kecil lbr 1,05 tbl 4 mm Rp 62,949.00

8.12 1 M2 Pasang Atap Onduline Rp 106,509.00

8.13 1 M2 Pasang Atap Asbes Gelombang besar lbr 1,05 tbl 4 mm Rp 66,579.00

8.14 1 M' Pasang Bubung/nok Asbes Gelombang kecil Rp 57,080.00

8.15 1 M' Pasang Bubung/Nok Asbes Gelombang besar Rp 57,685.00

8.16 1 M2 Pasang Atap Beton Cisangkan Rp 172,105.00

8.17 1 M2 Pasang Atap Genteng Beton Rp 100,825.00

8.18 1 M2 Pasang Atap Genteng Metal biasa (77 cm X 88 cm) Rp 76,864.00

8.19 1 M2 Pasang Atap Genteng Metal Zincalume Rp 214,870.00

8.20 1 M2 Pasang Atap Genteng Metal Zincalume berpasir mutu A Rp 130,720.00

8.21 1 M2 Pasang Atap Genteng Metal Warna Rp 80,230.00

8.22 1 M2 Pasang Atap Genteng Metal Zincalume berpasir mutu B Rp 102,670.00

8.23 1 M' Pasang Nok Genteng Beton Rp 126,185.00

8.24 1 M' Pasang Nok Genteng Beton Cisangkan Rp 136,085.00

8.25 1 M' Pasang Nok Genteng Metal Rp 80,250.00

- 95 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II

Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
8.26 1 M2 Pasang Atap Seng Gelombang Rp 27,580.85

8.27 1 M' Pasang Atap Nok Seng Rp 38,295.00

8.28 1 M2 Pasang Atap Aluminium Rp 224,245.00

8.29 1 M' Pasang Nok Aluminium Rp 177,890.00

8.30 1 M2 Pasang Aluminium Foil / Sisalation Rp 41,192.50

8.31 1 M3 Gording, Sako, Kitau, Blandar kayu Kelas II Rp 9,412,375.00

8.32 1 M3 Gording, Sako, Kitau, Blandar kayu Kelas III Rp 6,145,375.00

8.33 1 M2 Rangka atap baja ringan "Superdyma" Al-Magnesium Rp 297,135.20

IX PEKERJAAN LANGIT-LANGIT

9.1 1 M2 Langit-langit Asbes/Eternit ( 1,00 x 1,00 ) m, Tebal 2,7 mm Rp 40,505.00

9.2 1 M2 Langit-langit Asbes / Eternit ( 1,00 x 1,00 ) m, Tebal 3,5 mm Rp 45,345.00

9.3 1 M2 Langit-langit Kalsiboard ( 1,20 x 2,40 ) m, Tebal 3,5 mm Rp 46,483.00

9.4 1 M2 Langit-langit Kalsiboard ( 1,20 x 2,40 ) m, Tebal 4,5 mm Rp 48,535.00

9.5 1 M2 Langit-langit Asbes/Eternit, Rangka Kayu Kls. II Tebal 2,7 mm Rp 168,840.00


Tebal 3,5 mm Rp 173,680.00

9.6 1 M2 Langit-langit Asbes/Eternit, Rangka Kayu Kls. III Tebal 2,7 mm Rp 133,200.00
Tebal 3,5 mm Rp 138,040.00

9.7 1 M2 Langit-langit Kalsiboard, Rangka Kayu Kls. II Tebal 3,5 mm Rp 186,068.00


Tebal 4,5 mm Rp 188,120.00

9.8 1 M2 Langit-langit Kalsiboard, Rangka Kayu Kls. III Tebal 3,5 mm Rp 150,428.00
Tebal 4,5 mm Rp 152,480.00

9.9 1 M2 Langit-langit Plywood ( 120 x 240 ) cm, Tebal 3 mm Rp 39,897.00

9.10 1 M2 Langit-langit Plywood ( 120 x 240 ) cm, Tebal 4 mm Rp 50,625.00

9.11 1 M2 Langit-langit Plywood ( 120 x 240 ) cm, Tebal 6 mm Rp 57,933.00

9.12 1 M2 Langit-langit Plywood ( 120 x 240 ) cm, Tebal 9 mm Rp 74,385.00

9.13 1 M2 Langit-langit Plywood ( 120 x 240 ) cm, Tebal 12 mm Rp 89,181.00

9.14 1 M2 Langit-langit Teakwood (120 X 240), Tebal 3 mm Rp 64,725.00

9.15 1 M2 Langit-langit Teakwood ( 120 x 240 ) cm, Tebal 4 mm Rp 72,425.00

9.16 1 M2 Langit-langit Plywood + Rangka Kayu Kls. II Tebal 3 mm Rp 178,832.00


Tebal 4 mm Rp 189,560.00
Tebal 6 mm Rp 196,868.00
Tebal 9 mm Rp 213,320.00
Tebal 12 mm Rp 228,116.00

9.17 1 M2 Langit-langit Plywood + Rangka Kayu Kls. III Tebal 3 mm Rp 143,192.00


Tebal 4 mm Rp 153,920.00
Tebal 6 mm Rp 161,228.00
Tebal 9 mm Rp 177,680.00
Tebal 12 mm Rp 192,476.00

- 96 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II

Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3

9.18 1 M2 Langit-langit Lat Kayu Jati Rp 319,085.00

9.19 1 M2 Langit-langit Soft Board Rp 86,937.50

9.20 1 M' List Langit-langit Gypsum Gypsum besar Rp 47,755.00


Gypsum kecil Rp 30,925.00

9.21 1 M2 Langit-langit Gypsum Board, Tebal 9 mm Rp 58,268.98

9.22 1 M2 Langit-langit Gypsum Board 9 mm + Rangka Kayu kayu kelas II Rp 200,068.98


kayu kelas III Rp 164,428.98

9.23 1 M2 Langit-langit Gypsum Board 9 mm + Rangka besi hollow Rp 189,618.98

X PEKERJAAN SANITASI

10.1 Memasang 1 Buah Kloset Duduk / Monoblok Rp 1,047,040.00

10.2 Memasang 1 Buah Kloset Jongkok Porselen Rp 701,387.50

10.3 Memasang 1 Buah Kloset Jongkok Teraso Rp 382,712.50

10.4 Memasang 1 Buah Urinoir Rp 479,837.50

10.5 Memasang 1 Buah Wastafel Rp 698,337.50

10.6 Memasang 1 Buah Bak Mandi Teraso Volume 0,30 m3 Rp 492,887.50

10.7 Memasang 1 Buah Bak Mandi Fibreglass Volume 0,30 m3 Rp 808,140.00

10.8 Memasang 1 Buah Bak Mandi Porselin Batu Bata Volume 0,30 m3 Rp 1,807,225.00

10.9 Memasang 1 Buah Bak Beton Volume 1 m3 Air Rp 4,846,248.00

10.10 Memasang 1 Buah Bak Fibreglass Volume 1 m3 Air Rp 1,286,760.00

10.11 Memasang 1 M' Pipa Penyalur Air Limbah Jenis Pipa Tanah, dia. 15 cm Rp 230,632.25

10.12 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata Ukuran (30 x 30) cm, Tinggi 35 cm Rp 610,440.00

10.13 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata Ukuran (45 x 45) cm, Tinggi 50 cm Rp 543,720.00

10.14 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata Ukuran (60 x 60) cm, Tinggi 65 cm Rp 836,767.25

10.15 Memasang 1 m' Pipa Galvanis Dia. 1/2" Rp 52,377.50

10.16 Memasang 1 m' Pipa Galvanis Dia. 3/4" Rp 60,732.00

10.17 Memasang 1 m' Pipa Galvanis Dia. 1" Rp 70,578.38

10.18 Memasang 1 m' Pipa Galvanis Dia. 11/2" Rp 105,478.50

10.19 Memasang 1 m' Pipa Galvanis Dia. 3" Rp 219,372.50

10.20 Memasang 1 m' Pipa Galvanis Dia. 4" Rp 284,069.50

10.21 Memasang 1 m' Pipa PVC Tipe AW Dia. 1/2" Rp 22,077.50

10.22 Memasang 1 m' Pipa PVC Tipe AW Dia. 3/4" Rp 23,705.00

- 97 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II

Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3

10.23 Memasang 1 m' Pipa PVC Tipe AW Dia. 1" Rp 26,650.00

10.24 Memasang 1 m' Pipa PVC Tipe AW Dia. 11/2" Rp 37,655.00

10.25 Memasang 1 m' Pipa PVC Tipe AW Dia. 2" Rp 48,422.50

10.26 Memasang 1 m' Pipa PVC Tipe AW Dia. 3" Rp 85,777.50

10.27 Memasang 1 m' Pipa PVC Tipe AW Dia. 4" Rp 118,017.50

10.28 Memasang 1 Buah Bak Cuci Piring Stainless Steel Rp 281,850.00

10.29 Memasang 1 Buah Bak Cuci Piring Teraso Rp 496,687.50

10.30 Memasang 1 Buah Kran Dia. 3/4" atau 1/2" Rp 39,462.50

10.31 1 Bh Septiktank 1,5 m x 2,0 m x 1 m dan Resapan Rp 5,997,807.05

XI PEKERJAAN BESI DAN ALUMINIUM

11.1 1 Kg Pasang besi WF dan Rangka Atap Baja Rp 22,737.92

11.2 1 Kg Pasang besi CNP,INP,L dan Rangka Atap Baja Rp 28,191.00

11.3 1 m2 Pasang Pintu Besi Baja Rp 2,291,175.00

11.4 1 m2 Pasang Jendela Besi Rp 559,162.50

11.5 1 m2 Pasang Pintu Lipat Rp 647,155.00

11.6 1 m2 Pasang Pintu Sunscreen Alluminium Rp 531,300.00

11.7 1 m2 Pasang Sunscreen Besi Holo 30/30 Rp 272,800.00

11.8 1 m2 Pasang Rolling Door Rp 928,905.00

11.9 1 m2 Pasang Pintu Alluminium Rp 933,155.00

11.10 1 m2 Pasang Hordeng Vertikals Blinds Rp 180,887.50

11.11 1 m2 Pasang Hordeng Horizontal Blinds (aluminium) Rp 177,587.50

11.12 1 m2 Pasang Terali Besi Strip Rp 308,140.00

11.13 1 m2 Pasang Kawat Harmonika Rp 76,199.00

11.14 1 m2 Pasang Kawat Nyamuk Rp 50,789.00

11.15 1 m2 Pasang Kawat Kassa Rp 47,159.00

11.16 1 m2 Pasang Kawat Burung Rp 53,209.00

11.17 1 m2 Pasang Jendela Nako dan Tralis Rp 207,925.00

11.18 1 m' Pasang Talang Datar, Seng BJLS Rp 170,748.00

11.19 1 m' Pasang Talang Miring, Seng BJLS Rp 198,655.00

11.20 1 m' Pasang Talang 1/2 Lingkaran Dia. 10 cm, Seng BJLS Rp 159,512.50

XII PEKERJAAN KUNCI DAN KACA

- 98 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II

Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
12.1 1 Buah Pasang Kunci Tanam mutu B Rp 257,600.00

12.2 1 Buah Pasang Kunci Tanam Biasa Rp 115,525.00

12.3 1 Buah Pasang Kunci Tanam Kamar Mandi Rp 102,612.50

12.4 1 Buah Pasang Engsel Pintu Rp 42,075.00

12.5 1 Buah Pasang Engsel Jendela Kuningan Rp 47,850.00

12.6 1 Buah Pasang Engsel Angin Rp 50,850.00

12.7 1 Buah Pasang Kait Angin Rp 38,775.00

12.8 1 Buah Pasang Door Closer Rp 338,250.00

12.9 1 Buah Pasang Kunci Selot Rp 44,000.00

12.10 1 Buah Pasang Pegangan Pintu / Door Holder Rp 107,250.00

12.11 1 Buah Pasang Door Stop Rp 39,050.00

12.12 1 Buah Pasang Rel Pintu Dorong Rp 353,100.00

12.13 1 Buah Pasang Kunci Lemari Rp 45,925.00

12.14 1 m2 Pasang Kaca, Tebal 3 mm Rp 100,925.00

12.15 1 m2 Pasang Kaca, Tebal 5 mm Rp 155,375.00

12.16 1 m2 Pasang Kaca, Tebal 8 mm Rp 266,498.75

12.17 1 m2 Pasang Kaca Buram, Tebal 12 mm Rp 511,275.00

12.18 1 m2 Pasang Kaca Cermin, Tebal 3 mm Rp 172,315.00

12.19 1 m2 Pasang Kaca Cermin, Tebal 5 mm Rp 255,805.00

12.20 1 m2 Pasang Kaca Patri, Tebal 5 mm Rp 1,958,275.00

12.21 1 Set Pekerjaan Pasang Jendela Kaca Nako Biasa Nako 6 daun Rp 97,075.00
Nako 8 daun Rp 105,875.00
12.22 1 Set Pekerjaan Pasang Jendela Kaca Nako Rayben
Nako 6 daun, rayben Rp 97,075.00
Nako 8 daun, rayben Rp 104,775.00

XIII PEKERJAAN PENUTUP LANTAI DAN DINDING

13.1 1 m2 Pasang Lantai Granito Ukuran 40 x 40 cm Rp 415,425.13

13.2 1 m2 Pasang Lantai Granito Ukuran 30 x 30 cm Rp 353,071.63

13.3 1 m2 Pasang Lantai Ubin Teralux Marmer Ukuran 60 x 60 cm Rp 358,016.75

13.4 1 m2 Pasang Lantai Ubin Teralux Marmer Ukuran 40 x 40 cm Rp 458,743.13

13.5 1 m2 Pasang Lantai Ubin Teralux Marmer Ukuran 30 x 30 cm Rp 482,903.13

13.6 1 m' Pasang Plint Ubin Teraso Ukuran 10 x 30 cm Rp 22,033.80

13.7 1 m' Pasang Plint Ubin Teraso Ukuran 10 x 40 cm Rp 74,896.88

- 99 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II

Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
13.8 1 m' Pasang Plint Ubin Granito Ukuran 10 x 40 cm Rp 45,511.25

13.9 1 m' Pasang Plint Ubin Granito Ukuran 10 x 30 cm Rp 112,990.50

13.10 1 m' Pasang Plint Ubin Teralux Marmer Ukuran 10 x 60 cm Rp 114,706.67

13.11 1 m' Pasang Plint Ubin Teralux Marmer Ukuran 10 x 40 cm Rp 120,960.00

13.12 1 m' Pasang Plint Ubin Teralux Marmer Ukuran 10 x 30 cm Rp 118,819.31

13.13 1 m2 Pasang Lantai Keramik Artistik Ukuran 10 x 20 cm Rp 457,133.50

13.14 1 m2 Pasang Lantai Keramik Artistik Ukuran 10 x 10 cm Rp 465,883.50

13.15 1 m2 Pasang Lantai Keramik Artistik Ukuran 5 x 20 cm Rp 762,133.50

13.16 1 m2 Pasang Plint Keramik Artistik Ukuran 10 x 20 cm Rp 55,685.00

13.17 1 m2 Pasang Plint Keramik Artistik Ukuran 10 x 10 cm Rp 56,035.00

13.18 1 m2 Pasang Plint Keramik Artistik Ukuran 5 x 20 cm Rp 53,856.25

13.19 1 m2 Pasang Lantai Keramik Ukuran 10 x 20 cm Rp 195,133.50

13.20 1 m2 Pasang Lantai Keramik Ukuran 20 x 20 cm Rp 194,633.50

13.21 1 m2 Pasang Lantai Keramik Ukuran 15 x 20 cm Rp 217,133.50

13.22 1 m2 Pasang Lantai Keramik Warna Ukuran 30 x 30 cm Rp 218,591.50

13.23 1 m2 Pasang Lantai Keramik Putih Ukuran 30 x 30 cm Rp 214,248.50

13.24 1 m2 Pasang Lantai Keramik Warna Ukuran 40 x 40 cm Mutu C Rp 209,333.50


Mutu B Rp 241,300.17

13.25 1 m' Pasang Plint Keramik


Plint keramik putih 10 X 30 cm Rp 28,947.16
Plint keramik Warna 10 X 30 cm Rp 29,338.07
Plint keramik Warna 10 X 40 cm, mutu C Rp 32,508.25
Plint keramik Warna 10 X 40 cm, mutu B Rp 37,622.92

13.26 1 m2 Pasang Lantai Marmer Rp 512,396.25

13.27 1 m2 Pasang Lantai Karpet 6 mm Rp 128,147.50

13.28 1 m2 Pasang dinding Wallpaper Rp 355,682.50

13.29 1 m2 Pasang Lantai Parquet Jati Rp 554,535.00

13.30 1 m2 Pasang Dinding Porselin 10 x 10 cm, putih Rp 221,772.50

13.31 1 m2 Pasang Dinding Porselin 10 x 10 cm, Warna Rp 276,747.50

13.32 1 m2 Pasang Dinding Marmer Rp 539,016.75

13.33 1 m2 Pasang Dinding Batu Tempel Hitam/Kali + anti lumut (vernis) Rp 240,246.25

13.34 1 m2 Pasang Dinding Batu Candi Hitam + anti lumut (vernis) Rp 392,706.25

13.35 1 m2 Pasang Dinding batu Alam / Palimanan + anti lumut(vernis) Rp 398,062.75

13.36 1 m2 Pasang Dinding batu Alam/KarangPilang + anti lumut(vernis) Rp 876,034.75

- 100 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II

Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
13.37 1 m2 Pasang Dinding batu Alam/Andesit + anti lumut(vernis) Rp 422,746.75

13.38 1 m2 plint Kayu 2 x 10 cm Rp 51,955.00

13.39 1 m2 Pas. Lantai Batu Bata Diplester Bata Lobang Rp 127,885.65


Bata Merah/Kecil Rp 174,410.65

13.40 1 m2 Pas. Coneblock, tebal 8 cm Biasa, tbl. 8 cm Rp 176,375.00


Warna, tbl. 8 cm Rp 206,625.00
Warna Segienam, tbl. 8 cm Rp -

13.41 1 m2 Pas. Coneblock, tebal 6 cm Biasa, tbl. 6 cm Rp 140,625.00


Warna, tbl. 6 cm Rp 99,000.00

13.42 1 m2 Pas. Lantai Mozaik 30/30 Rp 221,016.62

XIV PEKERJAAN PENGECATAN

14.1 1 m2 Mengikis / Mengerok Permukaan Cat Tembok Lama Rp 13,650.00

14.2 1 m2 Mencuci bidang permukaan tembok yang pernah di cat Rp 12,616.00

14.3 1 m2 Mengerok karat cat lama permukaan baja dengan cara manual Rp 12,616.00

14.4 1 m2 Menyabun Permukaan Tembok Lama Rp 12,616.00

14.5 1 m2 Mendempul dan Menggosok Kayu Rp 10,987.00

14.6 1 m2 Pengecatan Bidang Kayu Lama Rp 43,374.00

14.7 1 m2 Pengecatan Bidang Kayu Baru ( 1 Lapis Plamir, 1 lapis Cat Rp 51,157.00
Dasar, 2 Lapis Cat Penutup )

14.8 1 m2 Pengecatan Bidang Kayu Baru ( 1 Lapis Plamir, 1 lapis Cat Rp 70,975.00
Dasar, 3 Lapis Cat Penutup )

14.9 1 m2 Pelaburan Bidang Kayu dengan Politur Rp 47,747.60

14.10 1 m2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter Rp 25,975.00

14.11 1 m2 Pelaburan Bidang Kayu dengan Vernis Rp 40,922.50

14.12 1 m2 Pengecatan Tembok Baru ( 1 Lapis Plamir, 1 lapis Cat Cat mutu C Rp 20,050.00
Dasar, 2 Lapis Cat Penutup ) Cat mutu B Rp 23,911.00
Cat Mutu B Anti lumut/jamur Rp 24,340.00
Cat Mutu A Anti lumut/jamur Rp 43,645.00

14.13 1 m2 Pengecatan Tembok Lama ( 1 lapis Cat Dasar, 2 Lapis cat Cat mutu C Rp 16,720.00
Penutup ) Cat mutu B Rp 19,690.00
Cat Mutu B Anti lumut/jamur Rp 19,195.00

14.14 1 m2 Pengecatan Permukaan Baja dengan Meni Besi Rp 35,807.50

14.15 1 m2 Pengecatan Permukaan Baja dengan Meni Besi dan perancah Rp 57,395.50

14.16 10 m2 Cat Semprot minyak Chames Stones ( 1/2 Ducco ) = Untuk 1 M2 Rp 248,216.40

14.17 1 M2 Cat tembok/Plafond Chames Stone (berkerikil) Rp 140,044.40

14.18 10 m2 Cat Melamic = Untuk 1 M2 Rp 235,830.00

XV PEKERJAAN INSTALASI LISTRIK GEDUNG

- 101 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II

Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
15.1 1 Titik Pemasangan Saklar Lampu = Untuk 1 Titik Rp 263,296.00

15.2 1 Titik Pemasangan Stop Kontak Biasa = Untuk 1 Titik Rp 208,714.00

15.3 1 Titik Pemasangan Stop Kontak AC = Untuk 1 Titik Rp 541,200.00

15.4 1 Titik Pemasangan MCB = Untuk 1 Titik Rp 258,016.00

PEKERJAAN TAKSIR

1 1 M2 PAS. DINDING SKAT ALUMINIUM HITAM + KACA Rp 608,250.00

2 1 SET PAS. ENGSEL TANAM KUSEN ALUMINIUM Rp 340,000.00

3 1 BUAH PAS. CLOSED DUDUK Rp 3,167,000.00

4 1 BUAH PAS. PINTU PVC + KUSEN TYPE B Rp 600,750.00

5 1 M2 PAS. KACA FILM SUN GLASS KOTAK Rp 362,500.00

6 1 BUAH PAS. SARINGAN AIR Rp 22,000.00

7 1 BUAH PAS. PINTU PANEL LAPIS SUNGKAI + LIST STAINLIS Rp 2,372,625.43

8 PAS. LIST PLAFON 1/4 / M' Rp 4,250.00

9 PAS. PINTU PVC TYPE C/ BUAH Rp 460,250.00

10 PAS. KUSEN DAN JENDELA ALUMINIUM Rp 1,663,200.00

11 1 M' PAS. LISTPLANK WOODPLANK Rp 30,500.00

12 1 M3 PAS. HURUF NAMA KANTOR Rp 114,620.00

13 PAS. PAPAN NAMA DAN PLAT BESI Rp 2,351,470.00

14 PAS. TIANG PROFIL TERAS Rp 1,062,500.00

15 1 M2 PAS. DINDING SEKAT + JENDELA ALUMINIUM Rp 624,000.00

16 1 M2 PAS. PINTU KACA RANGKA ALUMINIUM + KUSEN Rp 900,000.00

17 1 LBG KUSEN PINTU KAYU+ RAAM Rp 925,000.00

18 1 LBG KUSEN PINTU KAYU TANPA RAAM Rp 660,000.00

19 1 BUAH PINTU KAYU (MERAWAN) PANEL Rp 1,210,000.00

20 1 BUAH PINTU KAYU (MEDANG) PANEL Rp 975,000.00

21 1 BUAH DAUN JENELA KACA KAYU MERAWAN PANJANG Rp 610,000.00

22 1 BUAH DAUN JENELA KACA KAYU MERAWAN SEDANG Rp 484,000.00

23 1 BUAH PINTU PLYWOOD + RANGKA DOBEL Rp 480,000.00

24 1 BUAH ROSTER KAYU UKURAN 35X35 CM Rp 121,000.00

25 1 BH VENTILASI KAYU + KACA WC UK. 40 x 30 CM Rp 154,000.00

26 1 M2 PINTU FOLDING GATE (MIN. 7 M2)


Pintu folding gate tebal 0,8mm Rp 600,000.00
Pintu folding gate tebal 0,8mm Rp 670,000.00

- 102 -
Rekapitulasi Harga Satuan Upah dan Bahan Bangunan TA. 2013 Semester II

Nomor
URAIAN HARGA SATUAN
Analisa
1 2 3
Pintu folding gate tebal 1,2mm Rp 940,000.00

27 1 M2 ALKABON + RANGKA + PASANGAN Rp 550,000.00

28 1 m2 PAS. CONEBLOCK WARNA SEGI ENAM Rp 149,017.50

- 103 -