B = Bentang
Tb = Tinggi Balok
Lb = Lebar Balok
K = Ukura Kolom
tp = Tebal Plat Lantai
Ba = Balok Anak
Pk = Panjang Kolom
Lk = Lebar Kolom
Tb = 1/12 x B m
= 0.08 x - m <==== "B" Harus Diisi
= - m ====> digunakan mm
Ba = 1/15 x B m
= 0.07 x - m
= - m
tp = 1/40 x B m
= 0.025 x - m
= - m
Tulangan Kolom
Lk = Luas Kolom
Ltk = Luas Tulangan Minimal Kolom
LTt = Luas Total Tulangan
rt = Jari-Jari Tulangan
Lk = P x L mm
= 500.0 x 380.00 mm
= 190,000 mm²
Lt = 1% x Lk mm
= 0.01 x 190,000 mm²
= 1,900 mm²
3.1415927 121
Digunakan besi Ø 16.00 mm 3.1415927 64
D 16.00 mm
Jumlah Tulangan n 10.00 btg
LTt = π x rt² xn
= 3.14 x 64.00 x 10
= 2,010.62 mm² > Lt Ok
Tulangan Balok
Lb = Luas Balok
Lt = Luas Tulangan Minimal Balok
υ = Kuat baja Rencana
au = Faktor reduksi balok (0.9)
LTt = Luas Total Tulangan
rt = Jari-Jari Tulangan
Lb = P x L mm
= - x - mm
= - mm²
Lt = 12 : υ x au x Lb
= 12 : 410 x 0.9 x -
= -
726
768