PERHITUNGAN PERUBAHAN VOLUME PEKERJAAN

SNVT PENGEMBANGAN KAWASAN PERMUKIMAN PERKOTAAN PROVINSI JAWA TENGAH


PAKET : PKA-P-06
PEKERJAAN : PENINGKATAN KUALITAS PERMUKIMAN KUMUH KAWASAN KETANGGUNGAN
DESA : BULAKELOR
KECAMATAN : KETANGGUNGAN
KABUPATEN : KAB.BREBES
TAHUN ANGGARAN : 2015

KONTRAK SEMULA PEKERJAAN KURANG PEKERJAAN TAMBAH KONTRAK MENJADI


NO. VOLUME
VOL SAT HARGA SAT JUMLAH HARGA VOL SAT JML HARGA VOL SAT JML HARGA SAT JML HARGA
P ( M') L (M') JML

I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00 1.00 Ls 1,000,000.00
2 Pengukuran/ Uitzet Bouwplank 1.00 Ls 1,500,000.00 1,500,000.00 1.00 Ls 1,500,000.00
3 Papan Nama Proyek 1.00 Ls 500,000.00 500,000.00 1.00 Ls 500,000.00
4 Sewa Gudang / Barak Kerja 1.00 Ls 1,000,000.00 1,000,000.00 1.00 Ls 1,000,000.00
5 Administrasi dan Dokumentasi 1.00 Ls 1,500,000.00 1,500,000.00 1.00 Ls 1,500,000.00
6 Uji Laboratorium 1.00 Ls 2,000,000.00 2,000,000.00 1.00 Ls 2,000,000.00
Jumlah I 7,500,000.00 ### 7,500,000.00
II PEKERJAAN JALAN
A. KELURAHAN BULAKELOR
1 Jalan Paving K.300 t= 8 cm P = 885.00 m' L = 3.00 m' 2,655.00 m2 131,522.50 349,192,237.50 m2 1.00 m2 131,522.50 886.00 3.00 ### m2
2,658.00 349,586,805.00
2 Kansteen 10/12.5x30x50 P 885.00 m' 1,770.00 m' 74,771.00 132,344,670.00 m' 2.00 m' 74,771.00 886.00 ### m'
1,772.00 132,494,212.00
R Jalan 9.00 m2 131,522.50 1,183,702.50 m2 m2 m2 1,183,702.50

Jl.RT.2 RW.4 ###


1 Jalan Paving K.300 t= 8 cm P = 94.00 m' L = 3.00 m' 282.00 m2 131,522.50 37,089,345.00 3.00 m2 394,567.50 m2 ### m2
2 Kansteen 10/12.5x30x50 P 94.00 m' 188.00 m' 74,771.00 14,056,948.00 6.00 m' 448,626.00 m' ### m'

1 Jalan Paving K.225 t= 6 cm P = 91.00 L = 2.80 108,982.50 m2 - m2 91.00 2.80 ### m2


254.80 27,768,741.00
2 Kansteen 10x20x50 P = 182.00 62,328.00 m' - m' 182.00 ### m'
364.00 22,687,392.00

Jl.RT.2 RW.4
1 Jalan Paving K.225 t= 6 cm P = 93.00 m' L = 1.80 m' 167.40 m2 108,982.50 18,243,670.50 m2 4.50 m2 490,421.25 97.50 1.80 175.50 m2 19,126,428.75
2 Kansteen 10x20x50 P 93.00 m' 186.00 m' 62,328.00 11,593,008.00 m' 9.00 m' 560,952.00 195.00 390.00 m' 24,307,920.00

JL.RT.1 RW.2
1 Jalan Paving K.225 t= 6 cm P = 94.00 m' L = 2.50 m' 235.00 m2 108,982.50 25,610,887.50 m2 12.00 m2 1,307,790.00 106.00 2.50 265.00 m2 28,880,362.50
2 Kansteen 10x20x50 P 94.00 m' 188.00 m' 62,328.00 11,717,664.00 m' 24.00 m' 1,495,872.00 212.00 212.00 m' 13,213,536.00

JL.RT.1 RW.2
1 Jalan Paving K.300 t= 8 cm P = 93.00 m' L = 3.00 m' 279.00 m2 131,522.50 36,694,777.50 m2 16.50 m2 2,170,121.25 m2
2 Kansteen 10/12.5x30x50 P 93.00 m' 186.00 m' 74,771.00 13,907,406.00 m' 33.00 m' 2,467,443.00 m'

1 Jalan Paving K.300 t= 8 cm P = 109.50 L = 3.00 108,982.50 m2 m2 109.50 3.00 328.50 m2 35,800,751.25
2 Kansteen 10/12.5x30x50 P = 219.00 62,328.00 m' m' 219.00 219.00 m' 13,649,832.00

JL.RT.1 RW.2
1 Jalan Paving K.300 t= 8 cm P = 92.50 m' L = 3.00 m' 277.50 m2 131,522.50 36,497,493.75 m2 13.00 m2 1,709,792.50 m2
2 Kansteen 10/12.5x30x50 P 92.50 m' 185.00 m' 74,771.00 13,832,635.00 m' 26.00 m' 1,944,046.00 m'

1 Jalan Paving K.300 t= 8 cm P = 105.50 L = 3.00 108,982.50 m2 m2 105.50 3.00 316.50 m2 34,492,961.25
2 Kansteen 10/12.5x30x50 P = 211.00 62,328.00 m' m' 211.00 211.00 m' 13,151,208.00

Jumlah II 701,964,445.25 843,193.50 1,257,666.75 577,155,201.25

PEKERJAAN LAIN LAIN


1 Batu Petunjuk Komponen A 1.00 bh 1,500,000.00 1,500,000.00 1.00 bh 1,500,000.00
2 Batu Petunjuk Komponen B 5.00 bh 1,000,000.00 5,000,000.00 5.00 bh 5,000,000.00
Jumlah III 6,500,000.00 6,500,000.00
Jumlah 715,964,445.25 843,193.50 1,257,666.75 591,155,201.25
Dibulatkan 715,900,000.00 800,000.00 1,200,000.00 591,100,000.00
PPn 71,590,000.00 80,000.00 120,000.00 59,110,000.00
Total 787,490,000.00 880,000.00 1,320,000.00 650,210,000.00

Dibuat Oleh : TIM EVALUASI KONTRAK


Disetujui Oleh : KONTRAKTOR PELAKSANA
KONSULTAN PENGAWAS CV. CAKRA MANUNGGAL 1. Guntur Herlambang Nugroho, ST 1. ……………………….
CV. CAHYA KARYA UTAMA Ketua
2. Bambang Pudjo L, Bsc 2. ……………………….
Sekretaris
3. Nani Suhartini, BE 3. ……………………….
Anggota
4. Andri Eka Febrianto, ST 4. ……………………….
HENDRO WIBOWO,ST KISWADI PRASETIA, S.Si Anggota
TEAM LEADER DIREKTUR 5. Rudi Dwi Sulistyo 5. ……………………….
Anggota

DANA TURAH = 124,809,244.00

HARGA PAVING + KANSTEEN/m'


305,151.00
124,656.00
MASIH ADA SISA PANJANG JALAN PAVING
429,807.00 290.38 m