JADWAL PELAKSANAAN PEKERJAAN ADDENDUM - 01

PAKET : REHABILITASI JALAN MAMEH - WINDESI + JEMBATAN KAYU

NOMOR KONTRAK : 09/HK.02.03/RHB MAWIN JK/PPK IV. 01/2017 NOMOR SPMK : HK.01.24/SPMK/RHB MAWIN JK/PPK IV.01/09
TANGGAL KONTRAK : 19 APRIL 2017 TANGGAL SPMK : 19 APRIL 2017
NILAI KONTRAK : Rp 14.512.881.000,00
( Empat Belas Milyar Lima Ratus Dua Belas Juta Delapan Ratus Delapan Puluh Satu Ribu Rupiah )
termasuk PPN
PENYEDIA JASA : PT. TUNAS PAPUA JAYA - PT. ELUZAI ABDALOUSEH, JO
TAHUN ANGGARAN : 2017

7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 3 7 7 7 7 7 7 7 7
WAKTU PELAKSANAAN
PROCENT
BOBOT APRIL MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER
NO. URAIAN PEKERJAAN VOLUME SAT.
(%) 19-23 24-30 01-07 08-14 15-21 22-28 29-04 05-11 12-18 19-25 26-02 03-09 10-16 17-23 24-30 31-06 07-13 14-20 21-27 28-03 04-10 11-17 18-24 25-01 02-08 09-15 16-22 23-29 30-05 06-12 13-14
(%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

DEVISI. I UMUM 100


1.2 Mobilisasi 1.00 LS 2.95 0.52 0.52 0.52 0.52 0.44 0.44

1.7.18 (1) Struktur Jembatan Kayu Kelas I 336.43 M3 16.20 1.01 1.01 1.01 1.01 1.01 1.01 1.01 1.01 1.01 1.01 1.01 1.01 1.01 1.01 1.01 1.01

1.7.18 (2) Struktur Lantai Jembatan Kayu Kelas I 129.99 M3 6.53 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54

DIVISI. II DRAINASE
REALISASI 50
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air 14,062.50 M3 5.80 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39

RENCANA ADDENDUM - 01
DIVISI. III PEKERJAAN TANAH
3.1.(1a) Galian Biasa 362.50 M3 0.15 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01

3.2.(1b) Timbunan Biasa dari galian 6,702.38 M3 6.96 RENCANA KONTRAK AWAL 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58

3.2.(2a) Timbunan Pilihan dari sumber galian 17,662.50 M3 54.17 1.81 1.81 3.61 3.61 3.61 3.61 3.61 3.61 3.61 3.61 3.61 3.61 3.61 3.61 3.61 3.61

3.3.(1) Penyiapan Badan Jalan 106,650.00 M2 1.69 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09

3.4.(1) Pembersihan dan Pengupasan Lahan 5,000.00 M2 5.55 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40

0
JUMLAH 100.00
PROGRES RENCANA MINGGUAN 0.517 0.517 0.517 0.517 1.012 1.012 1.412 1.412 1.412
KONTRAK
PROGRES KOMULATIF MINGGUAN - 0.568 1.137 1.705 2.274 3.389 4.503 6.391 8.278 10.165
PROGRES RENCANA MINGGUAN 0.52 0.52 0.52 0.52 1.01 1.01 1.41 1.41 1.41 1.90 2.44 3.02 3.02 4.83 4.83 6.63 6.63 6.63 6.62 6.62 5.61 5.22 4.68 3.70 3.70 3.70 3.70 3.70 3.61 0.44 0.44
ADDENDUM - 01
PROGRES KOMULATIF MINGGUAN 0.517 1.034 1.550 2.067 3.080 4.092 5.504 6.915 8.327 10.224 12.665 15.686 18.707 23.534 28.361 34.993 41.625 48.257 54.877 61.497 67.104 72.325 77.001 80.701 84.402 88.102 91.802 95.503 99.114 99.557 100.000
PROGRES MINGGUAN 0.65 0.65 0.69 0.64 1.87 2.92 3.05
PROGRES KOMULATIF MINGGUAN - - 0.65 1.30 1.99 2.63 4.50 7.42 10.47
DEVIASI MINGGUAN 0 -0.57 -1.14 -1.06 -0.97 -1.40 -1.87 -1.89 -0.86 0.30

Satker Pelaksanaan Jalan Nasional Wilayah IV Konsultan Pengawas Manokwari, 19 Juni 2017
Provinsi Papua Barat (Bintuni) PT. PORTAL ENGINEERING PERKASA, KSO Penyedia Jasa
Pejabat Pembuat Komitmen IV. 01 PT. JASA MITRA MANUNGGAL PT. TUNAS PAPUA JAYA - PT. ELUZAI ABDALOUSEH, JO

H E R M A N, ST Ir. TEHUH SETYADI SECAR KHOMAN K. RO'SON


NIP. 19790101 200912 1 001 Supervision Engineer Kuasa JO