KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.1634
- Mandor Jam 0.0408
II. BAHAN/MATERIAL
III. PERALATAN
- Excavator 80 - 140 HP Jam 0.0408
- Dump Truck 3,5 Ton Jam 0.1083
- Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 4.8611
- Tukang Batu Jam 2.4306
- Mandor Jam 0.4861
II. BAHAN/MATERIAL
- Batu Belah M3 1.0800
- Semen (PC) Kg 161.2800
- Pasir Pasang M3 0.5059
III. PERALATAN
- Concrete Mixer (0,3 - 0,6 M3) Jam 0.9722
- Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 2,013.91
19,575.00 798.66
SUB JUMLAH I 2,812.57
SUB JUMLAH II
436,643.20 17,815.04
220,032.27 23,829.49
1,000.00 1,000.00
SUB JUMLAH III 42,644.53
SUB JUMLAH (I + II + III) 45,457.10
2,727.43
1,818.28
SUB JUMLAH IV 4,545.71
JUMLAH HARGA (I + II + III + IV) 50,002.80
GA SATUAN PEKERJAAN (DIBULATKAN) 50,000.00
UAN PEKERJAAN
12,325.00 59,913.06
16,675.00 40,530.26
19,575.00 9,515.41
SUB JUMLAH I 109,958.73
230,000.00 248,400.00
1,350.00 217,728.00
175,000.00 88,526.95
SUB JUMLAH II 554,654.95
57,924.65 56,314.34
2,500.00 2,500.00
SUB JUMLAH III 58,814.34
SUB JUMLAH (I + II + III) 723,428.02
43,405.68
28,937.12
SUB JUMLAH IV 72,342.80
JUMLAH HARGA (I + II + III + IV) 795,770.82
GA SATUAN PEKERJAAN (DIBULATKAN) 795,770.00
ANALISA HARGA SATUAN PEKER
I. UPAH/TENAGA KERJA
- Pekerja Jam 1.8750
- Mandor Jam 0.3125
II. BAHAN/MATERIAL
1 Agregat Kasar M3 0.5500
2 Pasir Kg 0.5500
III. PERALATAN
1 Stamper Jam 0.3125
2 Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 23,109.38
19,575.00 6,117.19
SUB JUMLAH I 29,226.57
365,000.00 200,750.00
195,000.00 107,250.00
SUB JUMLAH II 308,000.00
46,918.28 14,661.96
1,000.00 1,000.00
SUB JUMLAH III 15,661.96
SUB JUMLAH (I + II + III) 352,888.53
21,173.31
14,115.54
SUB JUMLAH IV 35,288.85
JUMLAH HARGA (I + II + III + IV) 388,177.38
GA SATUAN PEKERJAAN (DIBULATKAN) 388,170.00
ANALISA HARGA SATUAN PEKER
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.5600
- Tukang Jam 0.2800
- Mandor Jam 0.1400
II. BAHAN/MATERIAL
- Filter Plastik M2 1.0500
III. PERALATAN
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
ANALISA HARGA SATUAN PEKER
I. UPAH/TENAGA KERJA
- Pekerja Jam 1.4000
- Tukang Jam 0.7000
- Mandor Jam 0.3500
II. BAHAN/MATERIAL
- Pipa Porous D. 4" M' 1.0500
- Semen Kg 9.0000
- Pasir Pasang M3 0.0200
- Filter stripe dan lain2 (pada sambungan) Ls 1.0000
III. PERALATAN
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 6,902.00
16,675.00 4,669.00
19,575.00 2,740.50
SUB JUMLAH I 14,311.50
15,000.00 15,750.00
SUB JUMLAH II 15,750.00
1,000.00 1,000.00
SUB JUMLAH III 1,000.00
SUB JUMLAH (I + II + III) 31,061.50
1,863.69
1,242.46
SUB JUMLAH IV 3,106.15
JUMLAH HARGA (I + II + III + IV) 34,167.65
GA SATUAN PEKERJAAN (DIBULATKAN) 34,160.00
-
-
-
-
-
UAN PEKERJAAN
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 17,255.00
16,675.00 11,672.50
19,575.00 6,851.25
SUB JUMLAH I 35,778.75
80,000.00 84,000.00
1,350.00 12,150.00
175,000.00 3,500.00
5,000.00 5,000.00
SUB JUMLAH II 104,650.00
1,000.00 1,000.00
SUB JUMLAH III 1,000.00
SUB JUMLAH (I + II + III) 141,428.75
8,485.73
5,657.15
SUB JUMLAH IV 14,142.88
JUMLAH HARGA (I + II + III + IV) 155,571.63
GA SATUAN PEKERJAAN (DIBULATKAN) 155,570.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.2941
- Mandor Jam 0.0490
II. BAHAN/MATERIAL
III. PERALATAN
- Excavator 80 - 140 HP Jam 0.0490
- Dump Truck 10 Ton Jam 0.1004
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 3,624.78
19,575.00 959.18
SUB JUMLAH I 4,583.96
SUB JUMLAH II -
436,643.20 21,395.52
313,422.60 31,467.63
1,000.00 1,000.00
SUB JUMLAH III 53,863.15
SUB JUMLAH (I + II + III) 58,447.10
3,506.83
2,337.88
SUB JUMLAH IV 5,844.71
JUMLAH HARGA (I + II + III + IV) 64,291.81
GA SATUAN PEKERJAAN (DIBULATKAN) 64,290.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.5767
- Mandor Jam 0.0961
II. BAHAN/MATERIAL
- Urugan Pilihan (untuk backfill) M3 0.5000
III. PERALATAN
- Excavator 80 - 140 HP Jam 0.0961
- Bull Dozer Jam 0.0235
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 7,107.84
19,575.00 1,881.49
SUB JUMLAH I 8,989.33
80,000.00 40,000.00
436,643.20 41,961.41
459,668.20 10,788.25
5,000.00 5,000.00
SUB JUMLAH III 57,749.66
SUB JUMLAH (I + II + III) 106,738.99
6,404.34
4,269.56
SUB JUMLAH IV 10,673.90
JUMLAH HARGA (I + II + III + IV) 117,412.89
GA SATUAN PEKERJAAN (DIBULATKAN) 117,410.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.9464
- Mandor Jam 0.1183
II. BAHAN/MATERIAL
- Urugan Pilihan (untuk backfill) M3 0.5000
- Bahan pengaman Tebing M3 0.2000
III. PERALATAN
- Excavator 80 - 140 HP Jam 0.1183
- Bull Dozer Jam 0.0235
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 11,664.15
19,575.00 2,315.68
SUB JUMLAH I 13,979.83
80,000.00 40,000.00
1,500,000.00 300,000.00
SUB JUMLAH II 340,000.00
436,643.20 51,654.89
459,668.20 10,788.25
5,000.00 5,000.00
SUB JUMLAH III 67,443.14
SUB JUMLAH (I + II + III) 421,422.97
25,285.38
16,856.92
SUB JUMLAH IV 42,142.30
JUMLAH HARGA (I + II + III + IV) 463,565.27
GA SATUAN PEKERJAAN (DIBULATKAN) 463,560.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 1.4196
- Mandor Jam 0.1774
II. BAHAN/MATERIAL
- Urugan Pilihan (untuk backfill) M3 0.5000
- Bahan pengaman Tebing M3 0.3000
III. PERALATAN
- Excavator 80 - 140 HP Jam 0.1774
- Bull Dozer Jam 0.0235
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 17,496.23
19,575.00 3,473.52
SUB JUMLAH I 20,969.75
80,000.00 40,000.00
1,500,000.00 450,000.00
SUB JUMLAH II 490,000.00
436,643.20 77,460.50
459,668.20 10,788.25
5,000.00 5,000.00
SUB JUMLAH III 93,248.76
SUB JUMLAH (I + II + III) 604,218.50
36,253.11
24,168.74
SUB JUMLAH IV 60,421.85
JUMLAH HARGA (I + II + III + IV) 664,640.35
GA SATUAN PEKERJAAN (DIBULATKAN) 664,640.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.8333
- Mandor Jam 0.1667
II. BAHAN/MATERIAL
III. PERALATAN
- Cold Milling Machine Jam 0.1667
- Dump Truck 3,5 Ton Jam 0.3012
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 10,270.83
19,575.00 3,262.50
SUB JUMLAH I 13,533.33
SUB JUMLAH II -
986,819.11 164,469.85
220,032.27 66,273.72
2,500.00 2,500.00
SUB JUMLAH III 233,243.57
SUB JUMLAH (I + II + III) 246,776.90
14,806.61
9,871.08
SUB JUMLAH IV 24,677.69
JUMLAH HARGA (I + II + III + IV) 271,454.59
GA SATUAN PEKERJAAN (DIBULATKAN) 271,450.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 1.6000
- Mandor Jam 0.2000
II. BAHAN/MATERIAL
III. PERALATAN
- Compressor 4000 - 6500 L/M Jam 0.2000
- Jack Hammer Jam 0.2000
- Excavator 80 - 140 HP Jam 0.2000
- Dump Truck 3,5 Ton Jam 0.1071
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 19,720.00
19,575.00 3,915.00
SUB JUMLAH I 23,635.00
SUB JUMLAH II -
181,399.20 36,279.84
52,473.47 10,494.69
436,643.20 87,328.64
220,032.27 23,565.46
2,500.00 2,500.00
SUB JUMLAH III 160,168.63
SUB JUMLAH (I + II + III) 183,803.63
11,028.22
7,352.15
SUB JUMLAH IV 18,380.36
JUMLAH HARGA (I + II + III + IV) 202,183.99
GA SATUAN PEKERJAAN (DIBULATKAN) 202,180.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 1.2000
- Mandor Jam 0.2000
II. BAHAN/MATERIAL
-
III. PERALATAN
- Compressor 4000 - 6500 L/M Jam 0.2000
- Jack Hammer Jam 0.2000
- Excavator 80 - 140 HP Jam 0.2000
- Dump Truck 3,5 Ton Jam 0.3318
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 14,790.00
19,575.00 3,915.00
SUB JUMLAH I 18,705.00
SUB JUMLAH II -
181,399.20 36,279.84
52,473.47 10,494.69
436,643.20 87,328.64
220,032.27 73,006.71
2,500.00 2,500.00
SUB JUMLAH III 209,609.88
SUB JUMLAH (I + II + III) 228,314.88
13,698.89
9,132.60
SUB JUMLAH IV 22,831.49
JUMLAH HARGA (I + II + III + IV) 251,146.37
GA SATUAN PEKERJAAN (DIBULATKAN) 251,140.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.1307
- Mandor Jam 0.0327
II. BAHAN/MATERIAL
- Material Timbunan M3 1.2000
III. PERALATAN
- Excavator 80 - 140 HP Jam 0.0327
- Dump Truck 10 Ton Jam 0.2638
- Motor Grader >100 HP Jam 0.0033
- Vibratory Roller 5 - 8 Ton Jam 0.0095
- Water Tanker 3000 - 4500 Ltr Jam 0.0073
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 1,611.11
19,575.00 639.71
SUB JUMLAH I 2,250.82
40,000.00 48,000.00
436,643.20 14,278.23
313,422.60 82,680.88
435,869.00 1,438.37
229,771.80 2,188.30
227,172.03 1,658.36
1,500.00 1,500.00
SUB JUMLAH III 103,744.14
SUB JUMLAH (I + II + III) 153,994.96
9,239.70
6,159.80
SUB JUMLAH IV 15,399.50
JUMLAH HARGA (I + II + III + IV) 169,394.46
GA SATUAN PEKERJAAN (DIBULATKAN) 169,390.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.1307
- Mandor Jam 0.0327
II. BAHAN/MATERIAL
- Material Pilihan M3 1.2000
III. PERALATAN
- Excavator 80 - 140 HP Jam 0.0327
- Dump Truck 10 Ton Jam 0.2798
- Motor Grader >100 HP Jam 0.0083
- Vibratory Roller 5 - 8 Ton Jam 0.0417
- Water Tanker 3000 - 4500 Ltr Jam 0.0073
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 1,611.11
19,575.00 639.71
SUB JUMLAH I 2,250.82
80,000.00 96,000.00
436,643.20 14,278.23
313,422.60 87,695.64
435,869.00 3,617.71
229,771.80 9,573.82
227,172.03 1,658.36
1,000.00 1,000.00
SUB JUMLAH III 117,823.76
SUB JUMLAH (I + II + III) 216,074.58
12,964.47
8,642.98
SUB JUMLAH IV 21,607.46
JUMLAH HARGA (I + II + III + IV) 237,682.04
GA SATUAN PEKERJAAN (DIBULATKAN) 237,680.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.0146
- Mandor Jam 0.0024
II. BAHAN/MATERIAL
III. PERALATAN
- Motor Grader > 100 Hp Jam 0.0024
- Vibratory Roller 5 - 8 Ton Jam 0.0030
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 179.95
19,575.00 46.98
SUB JUMLAH I 226.93
SUB JUMLAH II -
435,869.00 1,046.09
229,771.80 683.84
150.00 150.00
SUB JUMLAH III 1,879.93
SUB JUMLAH (I + II + III) 2,106.86
126.41
84.27
SUB JUMLAH IV 210.69
JUMLAH HARGA (I + II + III + IV) 2,317.55
GA SATUAN PEKERJAAN (DIBULATKAN) 2,310.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.7000
- Tukang Jam 0.3500
- Mandor Jam 0.0700
II. BAHAN/MATERIAL
- Geotekstile Seperator Kelas 1 M2 1.0500
III. PERALATAN
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 8,627.50
16,675.00 5,836.25
19,575.00 1,370.25
SUB JUMLAH I 15,834.00
25,000.00 26,250.00
208,637.79 3,254.75
2,500.00 2,500.00
2,870.33
1,913.55
SUB JUMLAH IV 4,783.88
JUMLAH HARGA (I + II + III + IV) 52,622.63
GA SATUAN PEKERJAAN (DIBULATKAN) 52,620.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.0698
- Mandor Jam 0.0174
II. BAHAN/MATERIAL
- Agregate Base Kelas A M3 1.2600
III. PERALATAN
- Wheel Loader 1,0 - 1,6 M3 Jam 0.0185
- Dump Truck 10 Ton Jam 0.6820
- Motor Grader >100 HP Jam 0.0069
- Vibratory Roller 5 - 8 Ton Jam 0.0333
- Water Tanker 3000 - 4500 Ltr Jam 0.0073
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
Bahu Jalan)
12,325.00 860.29
19,575.00 340.61
SUB JUMLAH I 1,200.90
285,000.00 359,100.00
386,368.60 7,147.82
313,422.60 213,754.21
435,869.00 3,007.50
229,771.80 7,659.06
227,172.03 1,658.36
1,000.00 1,000.00
SUB JUMLAH III 234,226.95
SUB JUMLAH (I + II + III) 594,527.85
35,671.67
23,781.11
SUB JUMLAH IV 59,452.79
JUMLAH HARGA (I + II + III + IV) 653,980.64
GA SATUAN PEKERJAAN (DIBULATKAN) 653,980.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.0741
- Mandor Jam 0.0185
II. BAHAN/MATERIAL
- Agregate Base Kelas S M3 1.2600
III. PERALATAN
- Wheel Loader 1,0 - 1,6 M3 Jam 0.0185
- Dump Truck 10 Ton Jam 0.6807
- Motor Grader >100 HP Jam 0.0046
- Vibratory Roller 5 - 8 Ton Jam 0.0127
- Water Tanker 3000 - 4500 Ltr Jam 0.0073
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 912.96
19,575.00 362.50
SUB JUMLAH I 1,275.46
250,000.00 315,000.00
386,368.60 7,147.82
313,422.60 213,346.76
435,869.00 2,005.00
229,771.80 2,917.74
227,172.03 1,658.36
500.00 500.00
SUB JUMLAH III 227,575.68
SUB JUMLAH (I + II + III) 543,851.14
32,631.07
21,754.05
SUB JUMLAH IV 54,385.11
JUMLAH HARGA (I + II + III + IV) 598,236.25
GA SATUAN PEKERJAAN (DIBULATKAN) 598,230.00
ANALISA HARGA SATUAN PEKER
I. UPAH/TENAGA KERJA
- Pekerja Jam 7.0000
- Tukang Jam 3.5000
- Mandor Jam 0.3500
SUB JUMLAH I
II. BAHAN/MATERIAL
- Semen Kg 351.4286
- Pasir Beton M3 0.6276
- Aggregat Kasar M3 0.8786
- Kayu Bekisting M3 0.0960
- Paku Kg 0.2500
SUB JUMLAH II
III. PERALATAN
- Excavator Jam 0.0449
- Truck Mixer Jam 0.4616
- Water Tank Truck Jam 0.0417
- Alat Bantu Ls 1.0000
SUB JUMLAH III
SUB JUMLAH (I + II + III)
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 86,275.00
16,675.00 58,362.50
19,575.00 6,851.25
151,488.75
1,350.00 474,428.57
195,000.00 122,372.45
365,000.00 320,678.57
1,500,000.00 144,000.00
17,000.00 4,250.00
1,065,729.59
436,643.20 19,605.28
381,354.81 176,017.42
227,172.03 9,473.07
5,000.00 5,000.00
210,095.77
1,427,314.11
85,638.85
57,092.56
142,731.41
1,570,045.52
1,570,040.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.0698
- Mandor Jam 0.0174
II. BAHAN/MATERIAL
- Agregate Base Kelas A M3 1.2600
III. PERALATAN
- Wheel Loader 1,0 - 1,6 M3 Jam 0.0185
- Dump Truck 10 Ton Jam 0.6820
- Motor Grader >100 HP Jam 0.0022
- Vibratory Roller 5 - 8 Ton Jam 0.0095
- Water Tanker 3000 - 4500 Ltr Jam 0.0073
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 860.29
19,575.00 340.61
SUB JUMLAH I 1,200.90
285,000.00 359,100.00
386,368.60 7,147.82
313,422.60 213,754.21
435,869.00 958.91
229,771.80 2,188.30
227,172.03 1,658.36
500.00 500.00
SUB JUMLAH III 226,207.60
SUB JUMLAH (I + II + III) 586,508.50
35,190.51
23,460.34
SUB JUMLAH IV 58,650.85
JUMLAH HARGA (I + II + III + IV) 645,159.35
GA SATUAN PEKERJAAN (DIBULATKAN) 645,150.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.0500
- Mandor Jam 0.0063
II. BAHAN/MATERIAL
- Asphalt Cement Kg 0.6174
- Karosen Liter 0.4620
III. PERALATAN
- Asphalt Sprayer Jam 0.0063
- Compressor 4500 - 6500 Ltr/Menit Jam 0.0017
- Dump Truck 5 Ton Jam 0.0063
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 616.25
19,575.00 123.32
SUB JUMLAH I 739.57
11,900.00 7,347.06
9,000.00 4,158.00
SUB JUMLAH II 11,505.06
81,624.20 514.23
181,399.20 308.38
220,032.27 1,386.20
50.00 50.00
SUB JUMLAH III 2,258.81
SUB JUMLAH (I + II + III) 14,503.44
870.21
580.14
SUB JUMLAH IV 1,450.34
JUMLAH HARGA (I + II + III + IV) 15,953.78
GA SATUAN PEKERJAAN (DIBULATKAN) 15,950.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.0500
- Mandor Jam 0.0063
II. BAHAN/MATERIAL
- Asphalt Cement Kg 0.8489
- Karosen Liter 0.2415
III. PERALATAN
- Asphalt Sprayer Jam 0.0063
- Compressor 4500 - 6500 Ltr/Menit Jam 0.0017
- Dump Truck 5 Ton Jam 0.0063
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 616.25
19,575.00 123.32
SUB JUMLAH I 739.57
11,900.00 10,101.91
9,000.00 2,173.50
SUB JUMLAH II 12,275.41
81,624.20 514.23
181,399.20 308.38
220,032.27 1,386.20
50.00 50.00
SUB JUMLAH III 2,258.81
SUB JUMLAH (I + II + III) 15,273.79
916.43
610.95
SUB JUMLAH IV 1,527.38
JUMLAH HARGA (I + II + III + IV) 16,801.17
GA SATUAN PEKERJAAN (DIBULATKAN) 16,800.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.6013
- Mandor Jam 0.0501
II. BAHAN/MATERIAL
- Agregat Kasar M3 0.3712
- Agregat Halus M3 0.2719
- Filler Kg 19.8000
- Asphalt Cement Kg 61.9500
III. PERALATAN
- Wheel Loader 1,0 - 1,6 M3 Jam 0.0083
- Asphalt Mixing Plant Jam 0.0208
- Generator Set Jam 0.0208
- Dump Truck 10 Ton Jam 0.4470
- Asphalt Finisher Jam 0.0501
- Tandem Roller 6 - 8 Ton Jam 0.0180
- Tire Roller 8 - 10 Ton Jam 0.0180
- Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 7,411.02
19,575.00 980.71
SUB JUMLAH I 8,391.73
365,000.00 135,488.00
385,000.00 104,700.60
1,350.00 26,730.00
11,900.00 737,205.00
SUB JUMLAH II 1,004,123.60
386,368.60 3,206.86
6,407,922.85 133,284.80
309,078.52 6,428.83
313,422.60 140,099.90
257,036.13 12,877.51
226,063.33 4,069.14
245,121.80 4,412.19
2,500.00 2,500.00
SUB JUMLAH III 306,879.23
SUB JUMLAH (I + II + III) 1,319,394.56
79,163.67
52,775.78
SUB JUMLAH IV 131,939.46
JUMLAH HARGA (I + II + III + IV) 1,451,334.02
GA SATUAN PEKERJAAN (DIBULATKAN) 1,451,330.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.6013
- Mandor Jam 0.0501
II. BAHAN/MATERIAL
- Agregat Kasar M3 0.3699
- Agregat Halus M3 0.2716
- Filler Kg 22.0000
- Asphalt Cement Kg 61.9500
III. PERALATAN
- Wheel Loader 1,0 - 1,6 M3 Jam 0.0083
- Asphalt Mixing Plant Jam 0.0208
- Generator Set Jam 0.0208
- Dump Truck 10 Ton Jam 0.4470
- Asphalt Finisher Jam 0.0501
- Tandem Roller 6 - 8 Ton Jam 0.0225
- Tire Roller 8 - 10 Ton Jam 0.0225
- Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 7,411.02
19,575.00 980.71
SUB JUMLAH I 8,391.73
365,000.00 135,013.50
385,000.00 104,585.15
1,350.00 29,700.00
11,900.00 737,205.00
SUB JUMLAH II 1,006,503.65
386,368.60 3,206.86
6,407,922.85 133,284.80
309,078.52 6,428.83
313,422.60 140,099.90
257,036.13 12,877.51
226,063.33 5,086.42
245,121.80 5,515.24
2,500.00 2,500.00
SUB JUMLAH III 308,999.56
SUB JUMLAH (I + II + III) 1,323,894.94
79,433.70
52,955.80
SUB JUMLAH IV 132,389.49
JUMLAH HARGA (I + II + III + IV) 1,456,284.43
GA SATUAN PEKERJAAN (DIBULATKAN) 1,456,280.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.2083
- Mandor Jam 0.0501
II. BAHAN/MATERIAL
- Agregat Kasar M3 0.3964
- Agregat Halus M3 0.2495
- Filler Kg 17.6000
- Asphalt Cement Kg 60.3750
III. PERALATAN
- Wheel Loader 1,0 - 1,6 M3 Jam 0.0083
- Asphalt Mixing Plant Jam 0.0208
- Generator Set Jam 0.0208
- Dump Truck 10 Ton Jam 0.4470
- Asphalt Finisher Jam 0.0251
- Tandem Roller 6 - 8 Ton Jam 0.0151
- Tire Roller 8 - 10 Ton Jam 0.0151
- Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 2,567.30
19,575.00 980.71
SUB JUMLAH I 3,548.01
365,000.00 144,686.00
385,000.00 96,075.08
1,350.00 23,760.00
11,900.00 718,462.50
SUB JUMLAH II 982,983.58
386,368.60 3,206.86
6,407,922.85 133,284.80
309,078.52 6,428.83
313,422.60 140,099.90
257,036.13 6,451.61
226,063.33 3,413.56
245,121.80 3,701.34
1,500.00 1,500.00
SUB JUMLAH III 298,086.90
SUB JUMLAH (I + II + III) 1,284,618.49
77,077.11
51,384.74
SUB JUMLAH IV 128,461.85
JUMLAH HARGA (I + II + III + IV) 1,413,080.34
GA SATUAN PEKERJAAN (DIBULATKAN) 1,413,080.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.2083
- Mandor Jam 0.0501
II. BAHAN/MATERIAL
- Agregat Kasar M3 0.3964
- Agregat Halus M3 0.2495
- Filler Kg 17.6000
- Asphalt Cement Kg 60.3750
III. PERALATAN
- Wheel Loader 1,0 - 1,6 M3 Jam 0.0083
- Asphalt Mixing Plant Jam 0.0208
- Generator Set Jam 0.0208
- Dump Truck 10 Ton Jam 0.4679
- Asphalt Finisher Jam 0.0251
- Tandem Roller 6 - 8 Ton Jam 0.0181
- Tire Roller 8 - 10 Ton Jam 0.0181
- Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 2,567.30
19,575.00 980.71
SUB JUMLAH I 3,548.01
365,000.00 144,686.00
385,000.00 96,075.08
1,350.00 23,760.00
11,900.00 718,462.50
SUB JUMLAH II 982,983.58
386,368.60 3,206.86
6,407,922.85 133,284.80
309,078.52 6,428.83
313,422.60 146,650.43
257,036.13 6,451.61
226,063.33 4,091.75
245,121.80 4,436.70
2,500.00 2,500.00
SUB JUMLAH III 307,050.98
SUB JUMLAH (I + II + III) 1,293,582.57
77,614.95
51,743.30
SUB JUMLAH IV 129,358.26
JUMLAH HARGA (I + II + III + IV) 1,422,940.83
GA SATUAN PEKERJAAN (DIBULATKAN) 1,422,940.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
II. BAHAN/MATERIAL
- Bahan Anti Pengelupasan Kg 1.0250
III. PERALATAN
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
SUB JUMLAH I -
65,000.00 66,625.00
3,997.50
2,665.00
SUB JUMLAH IV 6,662.50
JUMLAH HARGA (I + II + III + IV) 73,287.50
GA SATUAN PEKERJAAN (DIBULATKAN) 73,280.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 9.7442
- Tukang Jam 4.8721
- Mandor Jam 0.4872
II. BAHAN/MATERIAL
- Semen Kg 492.0000
- Pasir Beton M3 0.4725
- Aggregat Kasar M3 0.7333
- Kayu Bekisting/perancah M3 0.2000
- Paku Kg 2.0000
III. PERALATAN
- Excavator Jam 0.0449
- Truck Mixer Jam 0.4872
- Water Tanker 3000 - 4500 Ltr Jam 0.0461
- Concrete Vibrator Jam 0.1563
- Alat bantu Jam 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 120,097.83
16,675.00 81,242.65
19,575.00 9,537.18
SUB JUMLAH I 210,877.66
1,350.00 664,200.00
195,000.00 92,137.50
365,000.00 267,666.67
1,500,000.00 300,000.00
17,000.00 34,000.00
SUB JUMLAH II 1,358,004.17
436,643.20 19,605.28
381,354.81 185,800.75
227,172.03 10,472.63
41,806.04 6,534.28
5,000.00 5,000.00
SUB JUMLAH III 227,412.94
SUB JUMLAH (I + II + III) 1,796,294.77
107,777.69
71,851.79
SUB JUMLAH IV 179,629.48
JUMLAH HARGA (I + II + III + IV) 1,975,924.25
GA SATUAN PEKERJAAN (DIBULATKAN) 1,975,920.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 9.6709
- Tukang Jam 4.8355
- Mandor Jam 0.4835
II. BAHAN/MATERIAL
- Semen Kg 410.0000
- Pasir Beton M3 0.5250
- Aggregat Kasar M3 0.7333
- Kayu Bekisting/perancah M3 0.2000
- Paku Kg 2.0000
III. PERALATAN
- Excavator Jam 0.0449
- Truck Mixer Jam 0.4835
- Water Tanker 3000 - 4500 Ltr Jam 0.0427
- Concrete Vibrator Jam 0.4835
- Alat bantu Jam 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 119,194.09
16,675.00 80,631.29
19,575.00 9,465.41
SUB JUMLAH I 209,290.79
1,350.00 553,500.00
195,000.00 102,375.00
365,000.00 267,666.67
1,500,000.00 300,000.00
17,000.00 34,000.00
SUB JUMLAH II 1,257,541.67
436,643.20 19,605.28
381,354.81 184,402.59
227,172.03 9,700.25
41,806.04 20,213.22
5,000.00 5,000.00
SUB JUMLAH III 238,921.34
SUB JUMLAH (I + II + III) 1,705,753.80
102,345.23
68,230.15
SUB JUMLAH IV 170,575.38
JUMLAH HARGA (I + II + III + IV) 1,876,329.18
GA SATUAN PEKERJAAN (DIBULATKAN) 1,876,320.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 8.3080
- Tukang Jam 4.1540
- Mandor Jam 0.4616
II. BAHAN/MATERIAL
- Semen Kg 351.4286
- Pasir Beton M3 0.5625
- Aggregat Kasar M3 0.7333
- Kayu Bekisting/perancah M3 0.0500
- Paku Kg 0.5000
SUB JUMLAH II
III. PERALATAN
- Excavator Jam 0.0449
- Truck Mixer Jam 0.4616
- Water Tanker 3000 - 4500 Ltr Jam 0.0417
- Concrete Vibrator Jam 0.4616
- Alat bantu Jam 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 102,396.68
16,675.00 69,268.34
19,575.00 9,035.00
SUB JUMLAH I 180,700.02
1,350.00 474,428.57
195,000.00 109,687.50
365,000.00 267,666.67
1,500,000.00 75,000.00
17,000.00 8,500.00
935,282.74
436,643.20 19,605.28
381,354.81 176,017.42
227,172.03 9,473.07
41,806.04 19,297.67
5,000.00 5,000.00
SUB JUMLAH III 229,393.44
SUB JUMLAH (I + II + III) 1,345,376.20
80,722.57
53,815.05
SUB JUMLAH IV 134,537.62
JUMLAH HARGA (I + II + III + IV) 1,479,913.82
GA SATUAN PEKERJAAN (DIBULATKAN) 1,479,910.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 8.2567
- Tukang Jam 4.1283
- Mandor Jam 0.4587
II. BAHAN/MATERIAL
- Semen Kg 328.0000
- Pasir Beton M3 0.5775
- Aggregat Kasar M3 0.7333
- Kayu Bekisting/perancah M3 0.0500
- Paku Kg 0.5000
III. PERALATAN
- Excavator Jam 0.0449
- Truck Mixer Jam 0.4587
- Water Tanker 3000 - 4500 Ltr Jam 0.0390
- Concrete Vibrator Jam 0.4587
- Alat bantu Jam 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 101,763.63
16,675.00 68,840.11
19,575.00 8,979.14
SUB JUMLAH I 179,582.88
1,350.00 442,800.00
195,000.00 112,612.50
365,000.00 267,666.67
1,500,000.00 75,000.00
17,000.00 8,500.00
SUB JUMLAH II 906,579.17
436,643.20 19,605.28
381,354.81 174,929.24
227,172.03 8,859.71
41,806.04 19,176.43
5,000.00 5,000.00
SUB JUMLAH III 227,570.66
SUB JUMLAH (I + II + III) 1,313,732.71
78,823.96
52,549.31
SUB JUMLAH IV 131,373.27
JUMLAH HARGA (I + II + III + IV) 1,445,105.98
GA SATUAN PEKERJAAN (DIBULATKAN) 1,445,100.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.1400
- Tukang Jam 0.0700
- Mandor Jam 0.0088
II. BAHAN/MATERIAL
- Baja Tulangan U24 Polos Kg 1.1000
- Kawat Beton Kg 0.0200
III. PERALATAN
- Alat bantu Jam 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 1,725.50
16,675.00 1,167.25
19,575.00 171.28
SUB JUMLAH I 3,064.03
12,000.00 13,200.00
18,000.00 360.00
SUB JUMLAH II 13,560.00
500.00 500.00
1,027.44
684.96
SUB JUMLAH IV 1,712.40
JUMLAH HARGA (I + II + III + IV) 18,836.43
GA SATUAN PEKERJAAN (DIBULATKAN) 18,830.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.1400
- Tukang Jam 0.0700
- Mandor Jam 0.0088
II. BAHAN/MATERIAL
- Baja Tulangan U32 Ulir Kg 1.1000
- Kawat Beton Kg 0.0200
III. PERALATAN
- Alat bantu Jam 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 1,725.50
16,675.00 1,167.25
19,575.00 171.28
SUB JUMLAH I 3,064.03
12,500.00 13,750.00
18,000.00 360.00
SUB JUMLAH II 14,110.00
500.00 500.00
1,060.44
706.96
SUB JUMLAH IV 1,767.40
JUMLAH HARGA (I + II + III + IV) 19,441.43
GA SATUAN PEKERJAAN (DIBULATKAN) 19,440.00
ANALISA HARGA SATUAN PEKER
I. UPAH/TENAGA KERJA
- Pekerja Jam 10.5066
- Tukang Jam 5.2533
- Mandor Jam 0.5253
SUB JUMLAH I
II. BAHAN/MATERIAL
- Beton Mutu Sedang dengan fc' = 20 Mpa M3 0.2829
- Baja Tulangan U 32 Ulir Kg 25.4571
- Baja Tulangan U 24 Polos Kg 16.9714
- Casing dll Ls 1.0000
SUB JUMLAH II
III. PERALATAN
- Bore File Machine Jam 0.5253
- Alat bantu Jam 1.0000
SUB JUMLAH III
SUB JUMLAH (I + II + III)
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 129,493.43
16,675.00 87,598.50
19,575.00 10,283.30
227,375.23
1,705,753.80 482,484.65
17,674.03 449,930.31
17,124.03 290,619.25
50,000.00 50,000.00
1,273,034.21
1,044,348.13 548,625.66
10,000.00 10,000.00
558,625.66
2,059,035.10
123,542.11
82,361.40
205,903.51
2,264,938.61
2,264,930.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 6.2500
- Tukang Jam 3.1250
- Mandor Jam 0.6250
II. BAHAN/MATERIAL
- Batu Belah M3 1.1700
- Semen (PC) Kg 176.4000
- Pasir Pasang M3 0.4134
III. PERALATAN
- Concrete Mixer 0,3 - 0,6 M3 Jam 0.6250
- Alat bantu LS 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 77,031.25
16,675.00 52,109.38
19,575.00 12,234.38
SUB JUMLAH I 141,375.01
230,000.00 269,100.00
1,350.00 238,140.00
175,000.00 72,351.56
SUB JUMLAH II 579,591.56
57,924.65 36,202.91
1,500.00 1,500.00
SUB JUMLAH III 37,702.91
SUB JUMLAH (I + II + III) 758,669.48
45,520.17
30,346.78
SUB JUMLAH IV 75,866.95
JUMLAH HARGA (I + II + III + IV) 834,536.43
GA SATUAN PEKERJAAN (DIBULATKAN) 834,530.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 5.6000
- Tukang Jam 2.8000
- Mandor Jam 0.2800
II. BAHAN/MATERIAL
- Batu M3 1.2000
- Kawat Bronjong Galvanis Kg 15.0000
III. PERALATAN
- Alat Bantu LS 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 69,020.00
16,675.00 46,690.00
19,575.00 5,481.00
SUB JUMLAH I 121,191.00
230,000.00 276,000.00
22,000.00 330,000.00
SUB JUMLAH II 606,000.00
2,500.00 2,500.00
43,781.46
29,187.64
SUB JUMLAH IV 72,969.10
JUMLAH HARGA (I + II + III + IV) 802,660.10
GA SATUAN PEKERJAAN (DIBULATKAN) 802,660.00
ANALISA HARGA SATUAN PEKER
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.7000
- Tukang Jam 0.3500
- Mandor Jam 0.0700
II. BAHAN/MATERIAL
- Pipa PVC D. 2" M' 1.1000
- Bahan - Bahan Lainnya Ls 1.0000
III. PERALATAN
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 8,627.50
16,675.00 5,836.25
19,575.00 1,370.25
SUB JUMLAH I 15,834.00
30,000.00 33,000.00
3,300.00 3,300.00
SUB JUMLAH II 36,300.00
1,000.00 1,000.00
SUB JUMLAH III 1,000.00
SUB JUMLAH (I + II + III) 53,134.00
3,188.04
2,125.36
SUB JUMLAH IV 5,313.40
JUMLAH HARGA (I + II + III + IV) 58,447.40
GA SATUAN PEKERJAAN (DIBULATKAN) 58,440.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 1.6000
- Mandor Jam 0.2000
II. BAHAN/MATERIAL
- Agregat Base Kelas A M3 1.2600
III. PERALATAN
- Wheel Loader 1,0 - 1,6 M3 Jam 0.0108
- Dump Truck 3.5 Ton Jam 1.4267
- Pendestrian Roller Jam 0.0577
- Water Tanker 3000 - 4500 Ltr Jam 0.0073
- Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 19,720.00
19,575.00 3,915.00
SUB JUMLAH I 23,635.00
285,000.00 359,100.00
386,368.60 4,172.78
220,032.27 313,920.03
81,742.48 4,716.54
227,172.03 1,658.36
1,500.00 1,500.00
SUB JUMLAH III 325,967.71
SUB JUMLAH (I + II + III) 708,702.71
42,522.16
28,348.11
SUB JUMLAH IV 70,870.27
JUMLAH HARGA (I + II + III + IV) 779,572.98
GA SATUAN PEKERJAAN (DIBULATKAN) 779,570.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 2.3077
- Mandor Jam 0.1923
II. BAHAN/MATERIAL
- Agregat Kasar M3 0.9519
- Agregat Halus M3 0.5852
- Filler Kg 50.7100
- Aspal Kg 139.1644
- Bahan Anti Pengelupasan Kg 0.2783
III. PERALATAN
- Wheel Loader 1,0 - 1,6 M3 Jam 0.0261
- Asphalt Mixing Plant Jam 0.0480
- Generator Set Jam 0.0480
- Dump Truck 10 Ton Jam 1.2942
- Pendestrian Roller Jam 0.1923
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 28,442.31
19,575.00 3,764.42
SUB JUMLAH I 32,206.73
365,000.00 347,430.89
385,000.00 225,293.66
1,350.00 68,458.50
11,900.00 1,656,056.06
65,000.00 18,091.37
SUB JUMLAH II 2,315,330.48
386,368.60 10,084.22
6,407,922.85 307,580.30
309,078.52 14,835.77
313,422.60 405,631.53
81,742.48 15,719.08
500.00 500.00
SUB JUMLAH III 754,350.90
SUB JUMLAH (I + II + III) 3,101,888.11
186,113.29
124,075.52
SUB JUMLAH IV 310,188.81
JUMLAH HARGA (I + II + III + IV) 3,412,076.92
GA SATUAN PEKERJAAN (DIBULATKAN) 3,412,070.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.1600
- Tukang Jam 0.0800
- Mandor Jam 0.0200
II. BAHAN/MATERIAL
1 Gebalan Rumput M2 1.1000
2 Bahan - Bahan Lainnya Ls 1.0000
III. PERALATAN
1 Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 1,972.00
16,675.00 1,334.00
19,575.00 391.50
SUB JUMLAH I 3,697.50
15,000.00 16,500.00
1,500.00 1,500.00
SUB JUMLAH II 18,000.00
750.00 750.00
SUB JUMLAH III 750.00
SUB JUMLAH (I + II + III) 22,447.50
1,346.85
897.90
SUB JUMLAH IV 2,244.75
JUMLAH HARGA (I + II + III + IV) 24,692.25
GA SATUAN PEKERJAAN (DIBULATKAN) 24,690.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.4800
- Tukang Jam 0.1800
- Mandor Jam 0.0600
II. BAHAN/MATERIAL
- Cat Marka Thermoplastic Kg 1.9500
- Minyak Pencair (Thiner) Liter 1.0500
- Blass Bead Kg 0.4500
III. PERALATAN
- Fled Bed Truck Jam 0.0600
- Compressor 4500 - 6500 Ltr/Menit Jam 0.0600
- Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 5,916.00
16,675.00 3,001.50
19,575.00 1,174.50
SUB JUMLAH I 10,092.00
35,000.00 68,250.00
25,000.00 26,250.00
10,000.00 4,500.00
SUB JUMLAH II 99,000.00
208,637.79 12,518.27
181,399.20 10,883.95
1,000.00 1,000.00
SUB JUMLAH III 24,402.22
SUB JUMLAH (I + II + III) 133,494.22
8,009.65
5,339.77
SUB JUMLAH IV 13,349.42
JUMLAH HARGA (I + II + III + IV) 146,843.64
GA SATUAN PEKERJAAN (DIBULATKAN) 146,840.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 1.4000
- Tukang Jam 0.8400
- Mandor Jam 0.2800
II. BAHAN/MATERIAL
- Pelat Rambu Permukaan Pemantul High Intensity Bh 1.0000
Grade
III. PERALATAN
- Fled Bed Truck Jam 0.0558
- Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
Intensity Grade
12,325.00 17,255.00
16,675.00 14,007.00
19,575.00 5,481.00
SUB JUMLAH I 36,743.00
150,000.00 150,000.00
700,000.00 350,000.00
1,345,376.20 21,526.02
25,000.00 25,000.00
SUB JUMLAH II 546,526.02
208,637.79 11,641.99
5,000.00 5,000.00
SUB JUMLAH III 16,641.99
SUB JUMLAH (I + II + III) 599,911.01
35,994.66
23,996.44
SUB JUMLAH IV 59,991.10
JUMLAH HARGA (I + II + III + IV) 659,902.11
GA SATUAN PEKERJAAN (DIBULATKAN) 659,900.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 2.8000
- Tukang Jam 1.4000
- Mandor Jam 0.3500
II. BAHAN/MATERIAL
- Beton K-175 M3 0.0354
- Baja Tulangan Kg 4.6512
- Cat dan material lain Ls 1.0000
III. PERALATAN
- Fled Bed Truck Jam 0.1083
- Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 34,510.00
16,675.00 23,345.00
19,575.00 6,851.25
SUB JUMLAH I 64,706.25
1,345,376.20 47,676.77
12,000.00 55,814.06
10,000.00 10,000.00
SUB JUMLAH II 113,490.83
208,637.79 22,595.47
10,000.00 10,000.00
SUB JUMLAH III 32,595.47
SUB JUMLAH (I + II + III) 210,792.55
12,647.55
8,431.70
SUB JUMLAH IV 21,079.26
JUMLAH HARGA (I + II + III + IV) 231,871.81
GA SATUAN PEKERJAAN (DIBULATKAN) 231,870.00
ANALISA HARGA SATUAN PEKER
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 1.1200
- Tukang Jam 0.2800
- Mandor Jam 0.1400
II. BAHAN/MATERIAL
- Rel Pengaman M' 1.0000
- Beton K-175 M3 0.0929
- Baja Tulangan Kg 4.6452
- Baut dan bahan lain-lainnya Ls 1.0000
III. PERALATAN
- Fled Bed Truck Jam 0.0300
- Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UAN PEKERJAAN
12,325.00 13,804.00
16,675.00 4,669.00
19,575.00 2,740.50
SUB JUMLAH I 21,213.50
550,000.00 550,000.00
1,345,376.20 124,989.54
12,000.00 55,741.82
20,000.00 20,000.00
SUB JUMLAH II 750,731.36
208,637.79 6,259.13
750.00 750.00
SUB JUMLAH III 7,009.13
SUB JUMLAH (I + II + III) 778,953.99
46,737.24
31,158.16
SUB JUMLAH IV 77,895.40
JUMLAH HARGA (I + II + III + IV) 856,849.39
GA SATUAN PEKERJAAN (DIBULATKAN) 856,840.00
ANALISA HARGA SATUAN PEKERJAAN UNTUK PEMELI
KUANTITAS/
NO URAIAN SATUAN
KOEFISIEN
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.3431
- Mandor Jam 0.0572
II. BAHAN/MATERIAL
III. PERALATAN
- Excavator 80 - 140 HP Jam 0.0572
- Dump Truk 5 Ton 0 0.1641
- Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UK PEMELIHARAAN KINERJA JALAN
12,325.00 4,228.71
19,575.00 1,119.69
SUB JUMLAH I 5,348.40
SUB JUMLAH II -
436,643.20 24,975.99
220,032.27 36,107.29
1,500.00 1,500.00
SUB JUMLAH III 62,583.28
SUB JUMLAH (I + II + III) 67,931.68
4,075.90
2,717.27
SUB JUMLAH IV 6,793.17
JUMLAH HARGA (I + II + III + IV) 74,724.85
GA SATUAN PEKERJAAN (DIBULATKAN) 74,720.00
ANALISA HARGA SATUAN PEKERJAAN UNTUK PEMELI
I. UPAH/TENAGA KERJA
- Pekerja Jam 9.7222
- Tukang Batu Jam 4.8611
- Mandor Jam 0.4861
II. BAHAN/MATERIAL
- Batu Belah M3 1.0800
- Semen (PC) Kg 161.2800
- Pasir Pasang M3 0.5059
III. PERALATAN
- Concrete Mixer (0,3 - 0,6 M3) Jam 0.9722
- Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UK PEMELIHARAAN KINERJA JALAN
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 119,826.12
16,675.00 81,058.84
19,575.00 9,515.41
SUB JUMLAH I 210,400.37
230,000.00 248,400.00
1,350.00 217,728.00
175,000.00 88,526.95
SUB JUMLAH II 554,654.95
57,924.65 56,314.34
2,500.00 2,500.00
SUB JUMLAH III 58,814.34
SUB JUMLAH (I + II + III) 823,869.66
49,432.18
32,954.79
SUB JUMLAH IV 82,386.97
JUMLAH HARGA (I + II + III + IV) 906,256.63
GA SATUAN PEKERJAAN (DIBULATKAN) 906,250.00
ANALISA HARGA SATUAN PEKERJAAN UNTUK PEMELI
I. UPAH/TENAGA KERJA
- Pekerja Jam 1.6000
- Mandor Jam 0.2000
II. BAHAN/MATERIAL
- Agregat Base Kelas A M3 1.2600
III. PERALATAN
- Wheel Loader 1,0 - 1,6 M3 Jam 0.0108
- Dump Truck 5 Ton Jam 1.7499
- Pendestrian Roller Jam 0.0577
- Water Tanker 3000 - 4500 Ltr Jam 0.0073
- Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UK PEMELIHARAAN KINERJA JALAN
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 19,720.00
19,575.00 3,915.00
SUB JUMLAH I 23,635.00
285,000.00 359,100.00
386,368.60 4,172.78
220,032.27 385,034.46
81,742.48 4,716.54
227,172.03 1,658.36
5,000.00 5,000.00
SUB JUMLAH III 400,582.14
SUB JUMLAH (I + II + III) 783,317.14
46,999.03
31,332.69
SUB JUMLAH IV 78,331.71
JUMLAH HARGA (I + II + III + IV) 861,648.85
GA SATUAN PEKERJAAN (DIBULATKAN) 861,640.00
ANALISA HARGA SATUAN PEKERJAAN UNTUK PEMELI
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.1111
- Mandor Jam 0.0185
II. BAHAN/MATERIAL
- Agregate Base Kelas S M3 1.2600
III. PERALATAN
- Wheel Loader 1,0 - 1,6 M3 Jam 0.0185
- Dump Truck 5 Ton Jam 1.7190
- Motor Grader >100 HP Jam 0.0046
- Vibratory Roller 5 - 8 Ton Jam 0.0127
- Water Tanker 3000 - 4500 Ltr Jam 0.0073
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UK PEMELIHARAAN KINERJA JALAN
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 1,369.44
19,575.00 362.50
SUB JUMLAH I 1,731.94
250,000.00 315,000.00
386,368.60 7,147.82
220,032.27 378,235.47
435,869.00 2,005.00
229,771.80 2,917.74
227,172.03 1,658.36
2,500.00 2,500.00
SUB JUMLAH III 394,464.39
SUB JUMLAH (I + II + III) 711,196.33
42,671.78
28,447.85
SUB JUMLAH IV 71,119.63
JUMLAH HARGA (I + II + III + IV) 782,315.96
GA SATUAN PEKERJAAN (DIBULATKAN) 782,310.00
ANALISA HARGA SATUAN PEKERJAAN UNTUK PEMELI
I. UPAH/TENAGA KERJA
- Pekerja Jam 2.3077
- Mandor Jam 0.1923
II. BAHAN/MATERIAL
- Agregat Kasar M3 0.9519
- Agregat Halus M3 0.5852
- Filler Kg 50.7100
- Aspal Kg 139.1644
- Bahan Anti Pengelupasan Kg 0.2783
III. PERALATAN
- Wheel Loader 1,0 - 1,6 M3 Jam 0.0261
- Asphalt Mixing Plant Jam 0.0480
- Generator Set Jam 0.0480
- Dump Truck 5 Ton Jam 2.9472
- Pendestrian Roller Jam 0.1923
- Alat Bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UK PEMELIHARAAN KINERJA JALAN
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 28,442.31
19,575.00 3,764.42
SUB JUMLAH I 32,206.73
365,000.00 347,430.89
385,000.00 225,293.66
1,350.00 68,458.50
11,900.00 1,656,056.06
65,000.00 18,091.37
SUB JUMLAH II 2,315,330.48
386,368.60 10,084.22
6,407,922.85 307,580.30
309,078.52 14,835.77
220,032.27 648,479.10
81,742.48 15,719.08
5,000.00 5,000.00
SUB JUMLAH III 1,001,698.47
SUB JUMLAH (I + II + III) 3,349,235.68
200,954.14
133,969.43
SUB JUMLAH IV 334,923.57
JUMLAH HARGA (I + II + III + IV) 3,684,159.25
GA SATUAN PEKERJAAN (DIBULATKAN) 3,684,150.00
ANALISA HARGA SATUAN PEKERJAAN UNTUK PEMELI
I. UPAH/TENAGA KERJA
- Pekerja Jam 6.2500
- Tukang Batu Jam 3.1250
- Mandor Jam 0.6250
II. BAHAN/MATERIAL
- Batu Belah M3 1.1700
- Semen (PC) Kg 176.4000
- Pasir Pasang M3 0.4134
III. PERALATAN
- Concrete Mixer (0,3 - 0,6 M3) Jam 0.6250
- Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
UK PEMELIHARAAN KINERJA JALAN
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 77,031.25
16,675.00 52,109.38
19,575.00 12,234.38
SUB JUMLAH I 141,375.01
230,000.00 269,100.00
1,350.00 238,140.00
175,000.00 72,351.56
SUB JUMLAH II 579,591.56
57,924.65 36,202.91
2,350.00 2,350.00
SUB JUMLAH III 38,552.91
SUB JUMLAH (I + II + III) 759,519.48
45,571.17
30,380.78
SUB JUMLAH IV 75,951.95
JUMLAH HARGA (I + II + III + IV) 835,471.43
GA SATUAN PEKERJAAN (DIBULATKAN) 835,470.00
ANALISA HARGA SATUAN PEKERJAAN UNTUK PEMELI
I. UPAH/TENAGA KERJA
- Pekerja Jam 60.0000
- Mandor Jam 15.0000
II. BAHAN/MATERIAL
III. PERALATAN
SU
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 739,500.00
19,575.00 293,625.00
SUB JUMLAH I 1,033,125.00
SUB JUMLAH II -
2,500.00 2,500.00
SUB JUMLAH III 2,500.00
SUB JUMLAH (I + II + III) 1,035,625.00
62,137.50
41,425.00
103,562.50
JUMLAH HARGA (I + II + III + IV) 1,139,187.50
GA SATUAN PEKERJAAN (DIBULATKAN) 1,139,180.00
RJAAN (SEPANJANG RUAS PEKERJAAN) 333,551,904.00
ANALISA HARGA SATUAN PEKERJAAN UNTUK PEMELIHA
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.7200
- Mandor Jam 0.1200
II. BAHAN/MATERIAL
III. PERALATAN
SU
JUMLAH H
HARGA SATUAN PE
PEMELIHARAAN KINERJA JEMBATAN
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 8,874.00
19,575.00 2,349.00
SUB JUMLAH I 11,223.00
SUB JUMLAH II -
500.00 500.00
SUB JUMLAH III 500.00
SUB JUMLAH (I + II + III) 11,723.00
703.38
468.92
SUB JUMLAH IV 1,172.30
JUMLAH HARGA (I + II + III + IV) 12,895.30
GA SATUAN PEKERJAAN (DIBULATKAN) 12,890.00
ANALISA HARGA SATUAN PEKERJAAN UNTUK PEMELIHA
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.3200
- Tukang Jam 0.6400
- Mandor Jam 0.1600
II. BAHAN/MATERIAL
- Cat Minyak Kg 0.3600
- Tinner Ltr 0.1000
- Bahan-bahan lainnya Ls 1.0000
III. PERALATAN
SU
JUMLAH H
HARGA SATUAN PE
PEMELIHARAAN KINERJA JEMBATAN
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 3,944.00
16,675.00 10,672.00
19,575.00 3,132.00
SUB JUMLAH I 17,748.00
55,000.00 19,800.00
25,000.00 2,500.00
3,345.00 3,345.00
SUB JUMLAH II 25,645.00
1,500.00 1,500.00
SUB JUMLAH III 1,500.00
SUB JUMLAH (I + II + III) 44,893.00
2,693.58
1,795.72
SUB JUMLAH IV 4,489.30
JUMLAH HARGA (I + II + III + IV) 49,382.30
GA SATUAN PEKERJAAN (DIBULATKAN) 49,380.00
ANALISA HARGA SATUAN PEKERJAAN UNTUK PEMELIHA
I. UPAH/TENAGA KERJA
- Pekerja Jam 0.2400
- Tukang Jam 0.4800
- Mandor Jam 0.1200
II. BAHAN/MATERIAL
- Cat Tembok Kg 0.3600
- Bahan-bahan lainnya Ls 1.0000
III. PERALATAN
SU
JUMLAH H
HARGA SATUAN PE
PEMELIHARAAN KINERJA JEMBATAN
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 2,958.00
16,675.00 8,004.00
19,575.00 2,349.00
SUB JUMLAH I 13,311.00
25,000.00 9,000.00
1,350.00 1,350.00
SUB JUMLAH II 10,350.00
1,500.00 1,500.00
SUB JUMLAH III 1,500.00
SUB JUMLAH (I + II + III) 25,161.00
1,509.66
1,006.44
SUB JUMLAH IV 2,516.10
JUMLAH HARGA (I + II + III + IV) 27,677.10
GA SATUAN PEKERJAAN (DIBULATKAN) 27,670.00
ANALISA HARGA SATUAN PEKERJAAN UNTUK PEMELIHA
I. UPAH/TENAGA KERJA
- Pekerja Jam 5.9375
- Tukang Batu Jam 2.9688
- Mandor Jam 0.5938
II. BAHAN/MATERIAL
- Batu Belah M3 1.1700
- Semen (PC) Kg 176.4000
- Pasir Pasang M3 0.4134
III. PERALATAN
- Concrete Mixer (0,3 - 0,6 M3) Jam 0.6250
- Alat bantu Ls 1.0000
SU
JUMLAH H
HARGA SATUAN PE
PEMELIHARAAN KINERJA JEMBATAN
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 73,179.69
16,675.00 49,503.91
19,575.00 11,622.66
SUB JUMLAH I 134,306.26
230,000.00 269,100.00
1,350.00 238,140.00
175,000.00 72,351.56
SUB JUMLAH II 579,591.56
57,924.6493 36,202.91
500.00 500.00
SUB JUMLAH III 36,702.91
SUB JUMLAH (I + II + III) 750,600.73
45,036.04
30,024.03
SUB JUMLAH IV 75,060.07
JUMLAH HARGA (I + II + III + IV) 825,660.80
GA SATUAN PEKERJAAN (DIBULATKAN) 825,660.00
ANALISA HARGA SATUAN PEKERJAAN UNTUK PEMELIHA
I. UPAH/TENAGA KERJA
- Pekerja Jam 2.8000
- Tukang Jam 1.4000
- Mandor Jam 0.7000
II. BAHAN/MATERIAL
- Bahan - bahan Ls 1.0000
III. PERALATAN
- Alat Bantu LS 1.0000
SU
JUMLAH H
HARGA SATUAN PE
ANALISA HARGA SATUAN PEKERJAAN UNTUK PEMELIHA
I. UPAH/TENAGA KERJA
- Pekerja Jam 4.0000
- Tukang Jam 2.0000
- Mandor Jam 1.0000
II. BAHAN/MATERIAL
- Expansion Joint Asphaltic Plug M' 1.0500
- Bahan Lainnya Ls 1.0000
III. PERALATAN
- Concrete Cutter Jam 0.7500
- Alat Bantu LS 1.0000
SU
JUMLAH H
HARGA SATUAN PE
PEMELIHARAAN KINERJA JEMBATAN
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 34,510.00
16,675.00 23,345.00
19,575.00 13,702.50
SUB JUMLAH I 71,557.50
50,000.00 50,000.00
SUB JUMLAH II 50,000.00
1,200.00 1,200.00
3,894.15
2,596.10
SUB JUMLAH IV 6,490.25
JUMLAH HARGA (I + II + III + IV) 71,392.75
GA SATUAN PEKERJAAN (DIBULATKAN) 71,390.00
-
-
-
0
-
PEMELIHARAAN KINERJA JEMBATAN
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 49,300.00
16,675.00 33,350.00
19,575.00 19,575.00
SUB JUMLAH I 102,225.00
1,400,000.00 1,470,000.00
147,000.00 147,000.00
SUB JUMLAH II 1,617,000.00
35,000.00 26,250.00
1,625.00 1,625.00
99,867.00
66,578.00
SUB JUMLAH IV 166,445.00
JUMLAH HARGA (I + II + III + IV) 1,830,895.00
GA SATUAN PEKERJAAN (DIBULATKAN) 1,830,890.00
ANALISA HARGA SATUAN PEKERJAAN UNTUK PEMELIHA
I. UPAH/TENAGA KERJA
- Pekerja Jam 4.2000
- Tukang Jam 2.1000
- Mandor Jam 0.4200
II. BAHAN/MATERIAL
- Pipa Galvanis D.3" Btg 0.1667
- Bahan Lainya Ls 1.0000
III. PERALATAN
- Alat Bantu LS 1.0000
SU
JUMLAH H
HARGA SATUAN PE
PEMELIHARAAN KINERJA JEMBATAN
BIAYA JUMLAH
SATUAN (Rp. / SATUAN)
(Rp)
12,325.00 51,765.00
16,675.00 35,017.50
19,575.00 8,221.50
SUB JUMLAH I 95,004.00
700,000.00 116,690.00
29,172.50 29,172.50
SUB JUMLAH II 145,862.50
1,400.00 1,400.00
9,329.04
6,219.36
SUB JUMLAH IV 15,548.40
JUMLAH HARGA (I + II + III + IV) 171,032.40
GA SATUAN PEKERJAAN (DIBULATKAN) 171,032.00
DAFTAR HARGA SATUAN DASA
Nama Penyedia :
Satuan Kerja :
Paket Pekerjaan :
Panjang Jalan :
Panjang Jembatan :
Prop/Kota/Kab :
No U R A I A N
A UPAH
1 Pekerja
2 Tukang
3 Mandor
4 Operator
5 Pembantu Operator
6 Sopir
7 Pembantu sopir
8 Mekanik
9 Pembantu mekanik
10 Kepala Tukang
DAFTAR HARGA SATUAN DASAR
Nama Penyedia :
Satuan Kerja :
Paket Pekerjaan :
Panjang Jalan :
Panjang Jembatan :
Prop/Kota/Kab :
No U R A I A N
B BAHAN
1 Pasir Beton
2 P a s i r Pasang
3 Batu Belah
4 Batu Kali
5 Agregat Kasar
6 Agregat Halus
7 Filler
8 Aspal Cement
9 Kerosen
10 Semen / PC
11 Cat Marka Thermoplastic
12 Cat Marka Bukan Thermoplastic
13 Bensin
14 Solar
15 Minyak Pelumas / Olie
16 Agregat Base Klas A
17 Agregat Base klas B
18 Agregat Base klas S
19 Kawat Beton
20 Kawat bronjong Galvanis
21 Kawat Las
22 Koral
23 Pelat Rambu Permukaan Pemantul Engineering Grade
24 Pelat Rambu Permukaan Pemantul High Intensity Grade
25 Rel Pengaman
26 Baja Tulangan
27 Baja Prategang
28 Paku
29 Pohon
30 Bahan Anti Pengelupasan
31 Slip Sheet Menbrane
32 Joint Sealant
33 Baja Tulangan U 24 Polos
34 Baja Tulangan U 32 Ulir
35 Baja Tulangan U 39 Ulir
35 Cat Tembok
36 Cat Minyak
37 Wire Mesh
38 Material Timbunan
39 Material Pilihan
40 Material Pilihan Berbutir
DAFTAR HARGA SATUAN DASAR
Nama Penyedia :
Satuan Kerja :
Paket Pekerjaan :
Panjang Jalan :
Panjang Jembatan :
Prop/Kota/Kab :
No U R A I A N
41 Gebalan Rumput
42 Pipa Galvanis D 3"
43 Pipa Cucuran
44 Geotekstile Seperator Kelas 1
45 Filter Plastik
46 Pipa Porous D. 4"
47 Pipa PVC 2"
48 Thinner
49 Glass Bead
50 Multiplek 12 mm
51 Expansion Joint tipe Asphaltic Plug
52 Kayu Cerucuk D. 10 Cm
53 Kayu Untuk Perancah
DAFTAR HARGA SATUAN DASAR P
Nama Penyedia :
Satuan Kerja :
Paket Pekerjaan :
Panjang Jalan :
Panjang Jembatan :
Prop/Kota/Kab :
No U R A I A N
C PERALATAN
1 Asphalt Mixing Plant
2 Asphalt Finisher
3 Asphalt Sprayer
4 Bulldozer 100 - 150 HP
5 Compressor 4500 - 6500 Ltr/Menit
6 Concrete Mixer 0,3 - 0,6 M3
7 Crane 10 - 15 Ton
8 Dump Truck 3,5 Ton
9 Dump Truck 10 Ton
10 Excavator 80 - 140 HP
11 Flat Bed Truck 3 - 4 M3
12 Generator Set
13 Motor Grader >100 HP
14 Track Loader 75 - 100 HP
15 Wheel Loader 1,0 - 1,6 M3
16 Three Wheel Roller 6 - 8 Ton
17 Tandem Roller 6 - 8 Ton
18 Tire Roller 8 - 10 Ton
19 Vibratory Roller 5 - 8 Ton
20 Concrete Vibrator
21 Stone Crusher
22 Water Pump 70 - 100 mm
23 Water Tanker 3000 - 4500 Ltr
24 Pedestrian Roller
25 Stamper
26 Jack Hammer
27 Concerete Pan Mixer/Banching Plant
28 Concrete Pump
29 Trailer 20 Ton
30 Pile Dirver + Hammer
31 Crane on track , 35 ton
32 Welding Set
33 Bore Pile Machine
34 Asphalt Liquid Mixer
35 Truck Mixer
36 Concrete Paver
37 Cold Milling Machine
38 Chain Saw
39 Pick Up Truck
40 Survey Equipment
DAFTAR HARGA SATUAN DASAR UPAH
U R A I A N SATUAN
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
DAFTAR HARGA SATUAN DASAR BAHAN
U R A I A N SATUAN
M3
M3
M3
M3
M3
M3
Kg
Kg
Ltr
Kg
Thermoplastic Kg
Bukan Thermoplastic Kg
Ltr
Ltr
umas / Olie Ltr
M3
M3
M3
Kg
njong Galvanis Kg
Kg
M3
bu Permukaan Pemantul Engineering Grade Bh
bu Permukaan Pemantul High Intensity Grade Bh
M'
Kg
Kg
Kg
Bh
Pengelupasan Kg
M2
Kg
gan U 24 Polos Kg
gan U 32 Ulir Kg
gan U 39 Ulir Kg
Kg
Kg
Kg
M3
M3
lihan Berbutir M3
DAFTAR HARGA SATUAN DASAR BAHAN
U R A I A N SATUAN
M2
Btg
Bh
e Seperator Kelas 1 M2
M2
M'
M'
Ltr
Kg
Lbr
Joint tipe Asphaltic Plug M'
cuk D. 10 Cm M'
M3
DAFTAR HARGA SATUAN DASAR PERALATAN
U R A I A N SATUAN
Jam
Jam
Jam
100 - 150 HP Jam
r 4500 - 6500 Ltr/Menit Jam
Mixer 0,3 - 0,6 M3 Jam
Jam
Jam
Jam
80 - 140 HP Jam
ruck 3 - 4 M3 Jam
Jam
der >100 HP Jam
der 75 - 100 HP Jam
der 1,0 - 1,6 M3 Jam
eel Roller 6 - 8 Ton Jam
ller 6 - 8 Ton Jam
Jam
Roller 5 - 8 Ton Jam
Jam
Jam
mp 70 - 100 mm Jam
ker 3000 - 4500 Ltr Jam
Jam
Jam
Jam
Pan Mixer/Banching Plant Jam
Jam
Jam
Jam
rack , 35 ton Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
AR UPAH
– Padang Tambak
HARGA
SATUAN KETERANGAN
(RP)
– Padang Tambak
HARGA
SATUAN KETERANGAN
(RP)
– Padang Tambak
HARGA
SATUAN KETERANGAN
(RP)
15,000.00 Quary
700,000.00 Lokasi Pekerjaan
105,000.00 Lokasi Pekerjaan
25,000.00 Lokasi Pekerjaan
15,000.00 Lokasi Pekerjaan
80,000.00
30,000.00
25,000.00 Lokasi Pekerjaan
10,000.00 Lokasi Pekerjaan
150,000.00 Lokasi Pekerjaan
1,400,000.00
8,000.00
1,500,000.00 Lokasi Pekerjaan
PERALATAN
– Padang Tambak
HARGA
SATUAN KETERANGAN
(RP)
6,407,922.85
257,036.13
81,624.20
459,668.20
181,399.20
57,924.65
419,744.80
220,032.27
313,422.60
436,643.20
208,637.79
309,078.52
435,869.00
327,644.80
386,368.60
206,488.73
226,063.33
245,121.80
229,771.80
41,806.04
848,484.00
50,098.84
227,172.03
81,742.48
46,918.28
52,473.47
717,234.80
386,464.38
381,354.81
430,163.00
637,409.91
108,099.60
1,044,348.13
51,622.93
381,354.81
105,000.00
986,819.11
36,000.00
90,000.00
36,000.00
URAIAN TEKNIS ANALISA HA
ITEM PEMBAYARAN : 2.1.(1)
JENIS PEKERJAAN : Galian untuk Drainase, Selokan dan s
SATUAN PEMBAYARAN : M3
No URAIAN
I ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi jalan : sedang/baik
4 Jam kerja efektif per-hari
5 Faktor pengembangan bahan
6 Berat volume bahan
1 BAHAN
Tidak ada bahan yang diperlukan
2 ALAT
2.a EXCAVATOR
kapasitas Bucket
Faktor Bucket
Faktor efisiensi alat
Waktu Siklus
- menggali/ memuat
- Lain-lain
Kap.Prod / jam =
Koefisien alat / M3 =
Koefisien alat / M3
URAIAN TEKNIS ANALISA HA
ITEM PEMBAYARAN : 2.1.(1)
JENIS PEKERJAAN : Galian untuk Drainase, Selokan dan s
SATUAN PEMBAYARAN : M3
No URAIAN
2c ALAT BANTU
Diperlukan alat-alat bantu kecil
- Sekop
- Keranjang + Sapu
3 TENAGA
Produksi menentukan : EXCAVATOR
Produksi galian/hari
Kebutuhan tenaga:
- Pekerja
- Mandor
Koefisien tenaga / M3
- Pekerja
- Mandor
No URAIAN
I ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu,pasir dan semen) diterima seluruhnya
di lokasi pekerjaan
4 Jarak rata-rata Base Camp ke lokasi pekerjaan
5 Jam kerja efektif per-hari
6 Perbandingan Pasir & semen
1 BAHAN
1.a Batu ...........> {(Bt x D1 x 1M3):D2} x 1.20
1.b Semen ...........> Sm x {(Mr x D1 x 1M3) :D3}x1.05
x {D5 x (1000)}
1.c Pasir ...........> Ps x {(Mr x D1 x 1M3) : D4} x 1.1
2 ALAT
2a CONCRETE MIXER
Kapasitas Alat
Faktor efisiensi alat
Waktu siklus
- Memuat
- Mengaduk
- Menuang
- Tunggu
Kap.Prod / jam
Koefisien alat / M3 1 : Q1
URAIAN TEKNIS ANALISA HA
ITEM PEMBAYARAN : 2.2.(1)
JENIS PEKERJAAN : Pasangan batu dengan Mortar
SATUAN PEMBAYARAN : M3
No URAIAN
3 TENAGA
Produksi Pas. batu dalam 1 hari
Kebutuhan tenaga:
- Mandor
- Tukang batu
- Pekerja
Koefisien tenaga / M3
- Mandor
- Tukang batu
- Pekerja
No URAIAN
I ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Diameter bagian dalam gorong2
4 Jarak rata-rata Base camp ke lokasi pekerjaan
5 Jam kerja efektif per-hari
6 Tebal gorong-2
1 BAHAN
Untuk mendapatkan 1 m' gorong-gorong diperlukan :
- Beton K-350 = (22/7*((2*tg/100+d)/2)^2)-(22/7*(d/2)^2))*1
- Baja Tulangan (asumsi 125kg/m3)
- Timbunan Porus = {(tp*(0.4+2*tg/100+d+0.4)*1)*1.05}
- Material Pilihan = ((2*tg/100+d+0.3)*(0.4+2*tg/100+d+0.
-(22/7*(0.5*(2*tg/100+d))^2))*1*1.05
2 ALAT
2.a STEMPER (pemadatan lapis dasar)
Kecepatan
Faktor efisiensi alat
Lebar pemadatan
Banyak lintasan
Tebal lapis hamparan
No URAIAN
3 TENAGA
Produksi gorong-gorong perhari
Kebutuhan tenaga:
- Pekerja
- Tukang
- Mandor
Koefisien tenaga / M'
- Pekerja =
- Tukang =
- Mandor =
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.
No URAIAN
No URAIAN
I ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Diameter bagian dalam gorong2
4 Jarak rata-rata Base camp ke lokasi pekerjaan
5 Jam kerja efektif per-hari
6 Tebal gorong-2
1 BAHAN
Untuk mendapatkan 1 m' gorong-gorong diperlukan :
- Beton K-300 = (22/7*((2*tg/100+d)/2)^2)-(22/7*(d/2)^2))*1
- Timbunan Porus = = {(tp*(0.15+2*tg/100+d+0.15)*1)*1.05}
- Material Pilihan = ((2*tg/100+d+0.15)*(0.15+2*tg/100+d+0.15)
-(22/7*(0.5*(2*tg/100+d))^2))*1*1.05
2 ALAT
2.a STEMPER (pemadatan lapis dasar)
Kecepatan
Faktor efisiensi alat
Lebar pemadatan
Banyak lintasan
Tebal lapis hamparan
No URAIAN
3 TENAGA
Produksi gorong-gorong perhari
Kebutuhan tenaga:
- Pekerja
- Tukang
- Mandor
Koefisien tenaga / M'
- Pekerja =
- Tukang =
- Mandor =
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.
No URAIAN
No URAIAN
I ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Lebar Sisi Dalam Saluran
4 Tinggi Sisi Dalam Saluran
5 Tebal Dinding Saluran
6 Jarak rata-rata Base camp ke lokasi pekerjaan
7 Jam kerja efektif per-hari
1 BAHAN
Untuk mendapatkan 1 m' gorong-gorong diperlukan :
- Beton K-350
- Baja Tulangan (asumsi 125kg/m3)
- Timbunan Porus
- Material Pilihan
2 ALAT
2.a STEMPER (pemadatan lapis dasar)
Kecepatan
Faktor efisiensi alat
Lebar pemadatan
Banyak lintasan
Tebal lapis hamparan
No URAIAN
3 TENAGA
Produksi gorong-gorong perhari
Kebutuhan tenaga:
- Pekerja
- Tukang
- Mandor
Koefisien tenaga / M'
- Pekerja =
- Tukang =
- Mandor =
No URAIAN
No URAIAN
I ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu,pasir dan semen)
4 Jarah rata-rata base Camp ke lokasi pekerjaan
5 Jam kerja efektik per-hari
6 Kadar semen (spesifikasi) : - minimum
7 Ukuran Agregat Maksimum
8 Perbandingan air/semen maksimum (spesifikasi)
9 Perbandingan Camp 1.00
2.00
3.00
10 Berta jenis material :
- Beton
- Semen
- Pasir
- Krikil Pecah (Aggregat Kasar)
2 ALAT
2.a CONCRETE MIXER
Kapasitas Alat
Faktor efisiensi alat
Waktu Siklus : (T1 + T2 + T3 + T4)
- Memuat
- Mengaduk
- Menuang
- Tunggu
Kap.Prod / jam =
Koefisien alat / M3 =
URAIAN TEKNIS ANALISA HA
No URAIAN
Kap.Prod / jam =
Koefisien alat / M3 =
3 TENAGA
Produksi Beton dalam 1 hari = Tk x Q1
Kebutuhan tenaga:
- Mandor
- Tukang
- Pekerja
Koefisien tenaga / M3
- Mandor =
- Tukang =
- Pekerja =
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.
No URAIAN
No URAIAN
I ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (Besi & kawat) diterima seluruhnya
di lokasi pekerjaan
4 Jarak rata-rata Base Camp ke lokasi pekerjaan
5 Jam kerja efektif per-hari
6 Faktor kehilangan Besi Tulangan
1 BAHAN
1.a Baja Tulangan
1.b Kawat beton
2 ALAT
2a ALAT BANTU
Diperlukan alat-alat :
- Gunting Potong Baja
- Kunci Pembenngkok Tulangan
- Alat lainnya
3 TENAGA
Produksi Kerja dalam 1 hari
Kebutuhan tenaga:
- Mandor
- Tukang
- Pekerja
Koefisien tenaga / Kg
- Mandor
- Tukang
- Pekerja
No URAIAN
No URAIAN
I ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu dan Pasir) diterima seluruhnya
di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan
5 Jam kerja efektif per-hari
6 Faktor kehilangan material
1. BAHAN
1.a. Batu Belah
1.b. Pasir
2. ALAT
2.a. ALAT BANTU
Diperlukan :
- Gerobak Dorong = 4 buah
- Palu Batu = 2 buah
3. TENAGA
Produksi pasangan batu kosong dalam 1 hari
Kebutuhan tenaga : - Mandor
- Tukang
- Pekerja
Koefisien Tenaga / M3 :
- Mandor
- Tukang
- Pekerja
No URAIAN
No URAIAN
I ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan terpengaruh oleh aliran air tanah
4 Jam kerja efektif per-hari
5 Faktor kehilangan material
6 Material Porous terdiri dari batu pecah dan pasir
1 BAHAN
Material Porous terdiri dari :
- Batu pecah
- Pasir
2 ALAT
2.a STEMPER (pemadatan lapis dasar)
Kecepatan
Faktor efisiensi alat
Lebar pemadatan
Banyak lintasan
3 TENAGA
Produksi yang dapat diselesaikan / hari
Kebutuhan tenaga:
- Pekerja
- Mandor
Koefisien tenaga / M'
- Pekerja =
- Mandor =
URAIAN TEKNIS ANALISA HA
No URAIAN
No U R A I A N
I ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan terpengaruh oleh aliran air tanah
4 Jam kerja efektif per-hari
1 BAHAN
Kebutuhan Filter Plastik / M2
2 ALAT
3 TENAGA
Produksi yang dapat diselesaikan / hari
Kebutuhan tenaga:
- Pekerja
- Tukang
- Mandor
Koefisien tenaga / M2
- Pekerja =
- Tukang =
- Mandor =
No U R A I A N
No U R A I A N
I ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan terpengaruh oleh aliran air tanah
4 Jam kerja efektif per-hari
5 Diameter dalam pipa
6 Material penyaring terdiri dari material porus
7 Penyangga sambungan pipa dengan mortar
1 BAHAN
Diperlukan material :
- Pipa Porous D. 4"
- Mortar (penyangga sambungan pipa) = 2 x (0.5x0.5x0.5)
- Semen
- Pasir
- Filter stripe dan lain2 (pada sambungan)
2 ALAT
3 TENAGA
Produksi yang dapat diselesaikan / hari
Kebutuhan tenaga:
- Pekerja
- Tukang
- Mandor
Koefisien tenaga / M'
- Pekerja =
- Tukang =
- Mandor =
No U R A I A N
No URAIAN
I ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi jalan : sedang/baik
4 Jam kerja efektif per-hari
5 Faktor pengembangan bahan
6 Berat volume tanah (lepas)
1 BAHAN
Tidak ada bahan yang diperlukan
2 ALAT
2.a EXCAVATOR
kapasitas Bucket
Faktor Bucket
Faktor efisiensi alat
Waktu Siklus
- menggali/ memuat
- Lain-lain
Kap.Prod / jam =
Rencana digunakan jumlah alat
Kap.Prod Total / jam =
Koefisien alat / M3 =
Koefisien alat / M3
URAIAN TEKNIS ANALISA HA
ITEM PEMBAYARAN : 3.1.(1a)
JENIS PEKERJAAN : Galian Biasa
SATUAN PEMBAYARAN : M3
No URAIAN
2c ALAT BANTU
Diperlukan alat-alat bantu kecil
- Sekop
- Keranjang + Sapu
3 TENAGA
Produksi menentukan : EXCAVATOR
Produksi Galian /hari =
Kebutuhan tenaga:
- Pekerja
- Mandor
Koefisien tenaga / M3
- Pekerja =
- Mandor =
No URAIAN
I ASUMSI
1 Pekerjaan dilakukan secara mekanik/manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari
5 Faktor pengembangan bahan
6 Berat volume perkerasan aspal (lepas)
1 BAHAN
Tidak diperlukan bahan / material
2 ALAT
2.a COMPRESSOR, JACK HAMMER, EXCAVATOR
Produksi per jam
Koefisien alat / M3 =
Tk 7.00 Jam
Fk 1.20
D 1.40 Ton/M3
(E10)
V 0.85 M3
Fb 0.90
Fa 0.80
Ts1
T1 1.00 Menit
T2 0.25 Menit
Ts1 1.25 Menit
1 : Q1 0.0408 Jam
(E8)
V 5.00 Ton
Fa 0.80 -
v1 25.00 Km/jam
v2 35.00 Km/jam
TS2
= (L : v1) x 60 T1 3.60 Menit
= (L : v2) x 60 T2 2.57 Menit
= (V x 60)/ D x Q1 x Fk T3 7.29 Menit
T4 2.00 Menit
Ts2 15.47 Menit
V x Fa x 60 Q2 9.24 M3/jam
D x Fk x Ts2
= 1 : Q2 0.1083 Jam
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
1.00 Ls
Q1 24.48 M3/jam
= Tk x Q1 Qt 171.36 M3
P 4.00 Orang
M 1.00 Orang
/ M3
bulan
M3
Kontraktor
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
L 5.00 Km
TK 7.00 Jam
: - Volume semen Sm 20.00 %
: - Volume pasir Ps 80.00 %
Bt 60.00 %
Mr 40.00 %
D1 2.40 Ton/M3
D2 1.60 Ton/M3
D3 1.80 Ton/M3
D4 1.67 Ton/M3
D5 1.44 Ton/M3
(E16)
V 300.00 Liter
Fa 0.80
(T1+T2+T3+T4) Ts
T1 4.00 Menit
T2 4.00 Menit
T3 1.00 Menit
T4 5.00 Menit
Ts1 14.00 Menit
V x Fa x 60 Q1 1.0286 M3/Jam
1000 x Ts
2.00 Unit
2.06 M3/Jam
1.00 Ls
= 4 buah
= 4 buah
= 4 buah
= 8 buah
= 3 buah
= Tk x Q1 Qt 14.40 M3
M 1.00 Orang
Tb 5.00 Orang
P 10.00 Orang
/ M3
bulan
M3
0.00
Kontraktor
0.00
0.00
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
d 0.80 M
L 5.00 Km
Tk 7.00 Jam
tg 10.00 Cm
tp 0.18 M
Q1 9.41 M/Jam
(E25)
v 1.00 Km/Jam
Fa 0.80 -
Lb 0.40 M
n 10.00 Lintasan
N 5.00 Lapis
tp 0.10 M
Q1 0.39 M/Jam
(E11)
V 4.00 Buah/M'
Fa 0.80 -
v1 25.00 Km/jam
v2 35.00 Km/jam
TS2
(L : v1) x 60 T1 12.00 Menit
(L : v2) x 60 T2 8.57 Menit
15.00 Menit
Ts 35.57 Menit
1.00 Ls
3 buah
Qt 4.00 M'
P 10.00 Orang
T 2.00 Orang
M 1.00 Orang
bulan
M'
0.00
Kontraktor
0.00
0.00
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
d 0.30 M
L 5.00 Km
Tk 7.00 Jam
tg 6.50 Cm
tp 0.10 M
(E25)
v 1.00 Km/Jam
Fa 0.80 -
Lb 0.40 M
n 10.00 Lintasan
tp 0.10 M
Q1 41.75 M/Jam
(E25)
v 1.00 Km/Jam
Fa 0.80 -
Lb 0.40 M
n 10.00 Lintasan
N 5.00 Lapis
tp 0.10 M
Q1 2.19 M/Jam
(E11)
V 4.00 Buah/M'
Fa 0.80 -
v1 25.00 Km/jam
v2 35.00 Km/jam
TS2
(L : v1) x 60 T1 12.00 Menit
(L : v2) x 60 T2 8.57 Menit
30.00 Menit
Ts 50.57 Menit
1.00 Ls
3 buah
Qt 20.00 M'
P 8.00 Orang
T 4.00 Orang
M 1.00 Orang
bulan
M'
0.00
Kontraktor
0.00
0.00
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
Berbentuk U Type DS 3
l 0.80 M
1.20 M
0.15 M
L 5.00 Km
Tk 7.00 Jam
tp 0.15 M
(EI-716) 0.4200 M3
(M39) 57.7500 Kg
(EI-241) 0.1050 M3
(M09) 0.1200 M3
(E25)
v 1.00 Km/Jam
Fa 0.80 -
Lb 0.40 M
n 10.00 Lintasan
tp 0.10 M
Q1 30.48 M/Jam
(E25)
v 1.00 Km/Jam
Fa 0.80 -
Lb 0.40 M
n 10.00 Lintasan
N 5.00 Lapis
tp 0.10 M
Q1 5.33 M/Jam
Berbentuk U Type DS 3
(E11)
V 4.00 Buah/M'
Fa 0.80 -
v1 25.00 Km/jam
v2 35.00 Km/jam
TS2
(L : v1) x 60 T1 12.00 Menit
(L : v2) x 60 T2 8.57 Menit
15.00 Menit
Ts 35.57 Menit
1.00 Ls
3 buah
Qt 4.00 M'
P 8.00 Orang
T 2.00 Orang
M 1.00 Orang
Berbentuk U Type DS 3
bulan
M'
0.00
Kontraktor
0.00
0.00
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
L 5.00 Km
` Tk 7.00 Jam
Ks1 340.00 Kg/M3
Ag 19.00 Mm
Wcr 0.5
: Semen Sm 16.7 %
: Pasir Ps 33.3 %
: Agregat Kasar Kr 50.0 %
D1 2.400 T/M3
D2 1.250 T/M3
D3 1.440 T/M3
D4 1.525 T/M3
(E06)
V 0.30 M3
Fa 0.80 -
Ts
T1 5.00 Menit
T2 4.00 Menit
T3 1.00 Menit
T4 4.00 Menit
Ts1 14.00 Menit
(E23)
V 4.50 M3/jam
Wc 0.21 M3/jam
pa 100.00 liter/menit
Fa 0.80 -
pa x Fa x 60 Q2 23.41 M3/Jam
1000 x Wc
1 : Q2 0.0427 Jam
1.00 Ls
2 buah
2 buah
2 buah
4 buah
1 buah
Qt 7.20 M3
M 1.00 Orang
T 8.00 Orang
P 15.00 Orang
bulan
M3
0.0000
Kontraktor
0.0000
0.0000
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
L 5.00 Km
TK 7.00 Jam
Fh 1.10 -
1.1000 Kg
0.0200 Kg
1.00 Ls
= 2 buah
= 2 buah
Qt 100.00 Kg
M 1.00 Orang
Tb 2.00 Orang
P 4.00 Orang
/Kg
bulan
Kg
0.0000
Kontraktor
0.0000
0.0000
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
L 5.0 KM
Tk 7.00 jam
Fh 1.10 -
(M06) 1.1000 M3
(M02) 0.4300 M3
1.00 Ls
= 4 buah
= 2 buah
Qt 20.00 M3
- Mandor M 1.00 orang
- Tukang Tb 5.00 orang
- Pekerja P 10.00 orang
/ M3
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
bulan
M3
0.00
Kontraktor
0.00
0.00
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
Tk 7.00 Jam
Fh 1.10
t 0.10 M
Bt 50.00 %
Ps 50.00 %
(M03) 0.5500 M3
(M01) 0.5500 M3
(E25)
v 1.00 Km/Jam
Fa 0.80 -
Lb 0.40 M
n 10.00 Lintasan
Q1 3.2000 M3/Jam
1.00 Ls
3 buah
Qt 22.40 M3
P 6.00 Orang
M 1.00 Orang
/ M'
bulan
M'
0.00
Kontraktor
0.00
0.00
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
Filter Plastik
Tk 7.00 Jam
t 0.15 M
(M23) 1.05 M2
1.00 Ls
Qt 50.00 M2
P 4.00 Orang
T 2.00 Orang
M 1.00 Orang
(Tk x P) : Qt (L01) 0.5600 Jam
(Tk x T) : Qt (L01) 0.2800 Jam
(Tk x M) : Qt (L01) 0.1400 Jam
Filter Plastik
/ M2
bulan
M2
0.00
0.00
Direktur Utama
0.00
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
Tk 7.00 Jam
d 0.10 M
1.00 Ls
Qt 20.00 M'
P 4.00 Orang
T 2.00 Orang
M 1.00 Orang
/ M'
bulan
M'
0.00
0.00
Direktur Utama
0.00
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
Tk 7.00 Jam
Fk 1.20
D 1.40 Ton/M3
L 1.50 Km
(E10)
V 0.85 M3
Fb 0.90
Fa 0.80
Ts1 Menit
T1 1.00 Menit
T2 0.50 Menit
Ts1 1.50 Menit
V x Fb x Fa x60 Q1 20.40 M3/Jam
Ts1 x Fk
1.00 Unit
20.40 M3/Jam
(E08)
V 10.00 Ton
Fa 0.80 -
v1 25.00 Km/jam
v2 35.00 Km/jam
TS2
= (L : v1) x 60 T1 3.60 Menit
= (L : v2) x 60 T2 2.57 Menit
= (V x 60)/ D x Q1 x Fk T3 17.51 Menit
T4 5.00 Menit
Ts2 28.68 Menit
V x Fa x 60 Q2 9.96 M3/jam
D x Fk x Ts2
= 1 : Q2 (E08) 0.1004 Jam
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
1.00 Ls
Q1 20.40 M3/jam
Tk x Q1 Qt 142.80 M3
P 6.00 Orang
M 1.00 Orang
/M3
bulan
M3
0.00
Kontraktor
0.00
0.00
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
Tk 7.00 Jam
Fk 1.20 -
D 1.80 Ton/M3
L 1.50 Km
Q1 4.00 M3/Jam
1 : Q1 0.2500 Jam
(E08)
V 5.00 Ton
Fa 0.80 -
v1 25.00 Km/jam
v2 35.00 Km/jam
TS2
T1 41.67 Menit
= (L : v1) x 60 T2 3.60 Menit
= (L : v2) x 60 T3 2.57 Menit
N PEKERJAAN
KET
N PEKERJAAN
KET
Kontraktor
Direktur Utama
AN PEKERJAAN
KET
N PEKERJAAN
KET
0.00
Kontraktor
0.00
0.00
Direktur Utama
N PEKERJAAN
KET
N PEKERJAAN
KET
N PEKERJAAN
KET
0.00
Kontraktor
0.00
0.00
Direktur Utama
N PEKERJAAN
KET
N PEKERJAAN
KET
N PEKERJAAN
KET
0.00
Kontraktor
0.00
0.00
Direktur Utama
N PEKERJAAN
KET
N PEKERJAAN
KET
N PEKERJAAN
KET
0.00
Kontraktor
0.00
0.00
Direktur Utama
N PEKERJAAN
KET
Berdasarkan
dgn Spesifikasi
N PEKERJAAN
KET
N PEKERJAAN
KET
0.0000
Kontraktor
0.0000
0.0000
Direktur Utama
N PEKERJAAN
KET
N PEKERJAAN
KET
0.0000
Kontraktor
0.0000
0.0000
Direktur Utama
N PEKERJAAN
KET
N PEKERJAAN
KET
0.00
Kontraktor
0.00
0.00
Direktur Utama
N PEKERJAAN
KET
Agregat kasar
N PEKERJAAN
KET
0.00
Kontraktor
0.00
0.00
Direktur Utama
N PEKERJAAN
KET
N PEKERJAAN
KET
N PEKERJAAN
KET
N PEKERJAAN
KET
N PEKERJAAN
KET
N PEKERJAAN
KET
0.00
Kontraktor
0.00
0.00
Direktur Utama
N PEKERJAAN
KET
URAIAN TEKNIS ANALISA HA
ITEM PEMBAYARAN : SKh-1.10.a (1)
: Galian Tanah untuk Saluran Air dan Le
JENIS PEKERJAAN
SATUAN PEMBAYARAN : M3
No URAIAN
I ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi jalan : sedang/baik
4 Jam kerja efektif per-hari
5 Faktor pengembangan bahan
6 Berat volume bahan
1 BAHAN
Tidak ada bahan yang diperlukan
2 ALAT
2.a EXCAVATOR
kapasitas Bucket
Faktor Bucket
Faktor efisiensi alat
Waktu Siklus
- menggali/ memuat
- Lain-lain
Kap.Prod / jam =
Koefisien alat / M3 =
Koefisien alat / M3
URAIAN TEKNIS ANALISA HA
ITEM PEMBAYARAN : SKh-1.10.a (1)
: Galian Tanah untuk Saluran Air dan Le
JENIS PEKERJAAN
SATUAN PEMBAYARAN : M3
No URAIAN
2c ALAT BANTU
Diperlukan alat-alat bantu kecil
- Sekop
- Keranjang + Sapu
3 TENAGA
Produksi menentukan : EXCAVATOR
Produksi galian/hari
Kebutuhan tenaga:
- Pekerja
- Mandor
Koefisien tenaga / M3
- Pekerja
- Mandor
No URAIAN
I ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu,pasir dan semen) diterima seluruhnya
di lokasi pekerjaan
4 Jarak rata-rata Base Camp ke lokasi pekerjaan
5 Jam kerja efektif per-hari
6 Perbandingan Pasir & semen
1 BAHAN
1.a Batu ...........> {(Bt x D1 x 1M3):D2} x 1.20
1.b Semen ...........> Sm x {(Mr x D1 x 1M3) :D3}x1.05
x {D5 x (1000)}
1.c Pasir ...........> Ps x {(Mr x D1 x 1M3) : D4} x 1.1
2 ALAT
2a CONCRETE MIXER
Kapasitas Alat
Faktor efisiensi alat
Waktu siklus
- Memuat
- Mengaduk
- Menuang
- Tunggu
Kap.Prod / jam
Koefisien alat / M3 1 : Q1
URAIAN TEKNIS ANALISA HA
ITEM PEMBAYARAN : 2.2.(1)
JENIS PEKERJAAN : Pasangan batu dengan Mortar
SATUAN PEMBAYARAN : M3
No URAIAN
3 TENAGA
Produksi Pas. batu dalam 1 hari
Kebutuhan tenaga:
- Mandor
- Tukang batu
- Pekerja
Koefisien tenaga / M3
- Mandor
- Tukang batu
- Pekerja
No URAIAN
I ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Diameter bagian dalam gorong2
4 Jarak rata-rata Base camp ke lokasi pekerjaan
5 Jam kerja efektif per-hari
6 Tebal gorong-2
1 BAHAN
Untuk mendapatkan 1 m' gorong-gorong diperlukan :
- Beton K-350 = (22/7*((2*tg/100+d)/2)^2)-(22/7*(d/2)^2))*1
- Baja Tulangan (asumsi 125kg/m3)
- Timbunan Porus = {(tp*(0.4+2*tg/100+d+0.4)*1)*1.05}
- Material Pilihan = ((2*tg/100+d+0.3)*(0.4+2*tg/100+d+0.
-(22/7*(0.5*(2*tg/100+d))^2))*1*1.05
2 ALAT
2.a STEMPER (pemadatan lapis dasar)
Kecepatan
Faktor efisiensi alat
Lebar pemadatan
Banyak lintasan
Tebal lapis hamparan
No URAIAN
3 TENAGA
Produksi gorong-gorong perhari
Kebutuhan tenaga:
- Pekerja
- Tukang
- Mandor
Koefisien tenaga / M'
- Pekerja =
- Tukang =
- Mandor =
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.
No URAIAN
No URAIAN
I ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Diameter bagian dalam gorong2
4 Jarak rata-rata Base camp ke lokasi pekerjaan
5 Jam kerja efektif per-hari
6 Tebal gorong-2
1 BAHAN
Untuk mendapatkan 1 m' gorong-gorong diperlukan :
- Beton K-300 = (22/7*((2*tg/100+d)/2)^2)-(22/7*(d/2)^2))*1
- Timbunan Porus = = {(tp*(0.15+2*tg/100+d+0.15)*1)*1.05}
- Material Pilihan = ((2*tg/100+d+0.15)*(0.15+2*tg/100+d+0.15)
-(22/7*(0.5*(2*tg/100+d))^2))*1*1.05
2 ALAT
2.a STEMPER (pemadatan lapis dasar)
Kecepatan
Faktor efisiensi alat
Lebar pemadatan
Banyak lintasan
Tebal lapis hamparan
No URAIAN
3 TENAGA
Produksi gorong-gorong perhari
Kebutuhan tenaga:
- Pekerja
- Tukang
- Mandor
Koefisien tenaga / M'
- Pekerja =
- Tukang =
- Mandor =
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.
No URAIAN
No URAIAN
I ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Lebar Sisi Dalam Saluran
4 Tinggi Sisi Dalam Saluran
5 Tebal Dinding Saluran
6 Jarak rata-rata Base camp ke lokasi pekerjaan
7 Jam kerja efektif per-hari
1 BAHAN
Untuk mendapatkan 1 m' gorong-gorong diperlukan :
- Beton K-350
- Baja Tulangan (asumsi 125kg/m3)
- Timbunan Porus
- Material Pilihan
2 ALAT
2.a STEMPER (pemadatan lapis dasar)
Kecepatan
Faktor efisiensi alat
Lebar pemadatan
Banyak lintasan
Tebal lapis hamparan
No URAIAN
3 TENAGA
Produksi gorong-gorong perhari
Kebutuhan tenaga:
- Pekerja
- Tukang
- Mandor
Koefisien tenaga / M'
- Pekerja =
- Tukang =
- Mandor =
No URAIAN
No URAIAN
I ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu,pasir dan semen)
4 Jarah rata-rata base Camp ke lokasi pekerjaan
5 Jam kerja efektik per-hari
6 Kadar semen (spesifikasi) : - minimum
7 Ukuran Agregat Maksimum
8 Perbandingan air/semen maksimum (spesifikasi)
9 Perbandingan Camp 1.00
2.00
3.00
10 Berta jenis material :
- Beton
- Semen
- Pasir
- Krikil Pecah (Aggregat Kasar)
2 ALAT
2.a CONCRETE MIXER
Kapasitas Alat
Faktor efisiensi alat
Waktu Siklus : (T1 + T2 + T3 + T4)
- Memuat
- Mengaduk
- Menuang
- Tunggu
Kap.Prod / jam =
Koefisien alat / M3 =
URAIAN TEKNIS ANALISA HA
No URAIAN
Kap.Prod / jam =
Koefisien alat / M3 =
3 TENAGA
Produksi Beton dalam 1 hari = Tk x Q1
Kebutuhan tenaga:
- Mandor
- Tukang
- Pekerja
Koefisien tenaga / M3
- Mandor =
- Tukang =
- Pekerja =
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.
No URAIAN
No URAIAN
I ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (Besi & kawat) diterima seluruhnya
di lokasi pekerjaan
4 Jarak rata-rata Base Camp ke lokasi pekerjaan
5 Jam kerja efektif per-hari
6 Faktor kehilangan Besi Tulangan
1 BAHAN
1.a Baja Tulangan
1.b Kawat beton
2 ALAT
2a ALAT BANTU
Diperlukan alat-alat :
- Gunting Potong Baja
- Kunci Pembenngkok Tulangan
- Alat lainnya
3 TENAGA
Produksi Kerja dalam 1 hari
Kebutuhan tenaga:
- Mandor
- Tukang
- Pekerja
Koefisien tenaga / Kg
- Mandor
- Tukang
- Pekerja
No URAIAN
No URAIAN
I ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu dan Pasir) diterima seluruhnya
di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan
5 Jam kerja efektif per-hari
6 Faktor kehilangan material
1. BAHAN
1.a. Batu Belah
1.b. Pasir
2. ALAT
2.a. ALAT BANTU
Diperlukan :
- Gerobak Dorong = 4 buah
- Palu Batu = 2 buah
3. TENAGA
Produksi pasangan batu kosong dalam 1 hari
Kebutuhan tenaga : - Mandor
- Tukang
- Pekerja
Koefisien Tenaga / M3 :
- Mandor
- Tukang
- Pekerja
No URAIAN
No URAIAN
I ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan terpengaruh oleh aliran air tanah
4 Jam kerja efektif per-hari
5 Faktor kehilangan material
6 Material Porous terdiri dari batu pecah dan pasir
1 BAHAN
Material Porous terdiri dari :
- Batu pecah
- Pasir
2 ALAT
2.a STEMPER (pemadatan lapis dasar)
Kecepatan
Faktor efisiensi alat
Lebar pemadatan
Banyak lintasan
3 TENAGA
Produksi yang dapat diselesaikan / hari
Kebutuhan tenaga:
- Pekerja
- Mandor
Koefisien tenaga / M'
- Pekerja =
- Mandor =
URAIAN TEKNIS ANALISA HA
No URAIAN
No URAIAN
I ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi jalan : sedang/baik
4 Jam kerja efektif per-hari
5 Faktor pengembangan bahan
6 Berat volume tanah (lepas)
1 BAHAN
Tidak ada bahan yang diperlukan
2 ALAT
2.a EXCAVATOR
kapasitas Bucket
Faktor Bucket
Faktor efisiensi alat
Waktu Siklus
- menggali/ memuat
- Lain-lain
Kap.Prod / jam =
Rencana digunakan jumlah alat
Kap.Prod Total / jam =
Koefisien alat / M3 =
Koefisien alat / M3
URAIAN TEKNIS ANALISA HA
ITEM PEMBAYARAN : 3.1.(1a)
JENIS PEKERJAAN : Galian Biasa
SATUAN PEMBAYARAN : M3
No URAIAN
2c ALAT BANTU
Diperlukan alat-alat bantu kecil
- Sekop
- Keranjang + Sapu
3 TENAGA
Produksi menentukan : EXCAVATOR
Produksi Galian /hari =
Kebutuhan tenaga:
- Pekerja
- Mandor
Koefisien tenaga / M3
- Pekerja =
- Mandor =
No URAIAN
I ASUMSI
1 Pekerjaan dilakukan secara mekanik/manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari
5 Faktor pengembangan bahan
6 Berat volume perkerasan aspal (lepas)
1 BAHAN
Tidak diperlukan bahan / material
2 ALAT
2.a COMPRESSOR, JACK HAMMER, EXCAVATOR
Produksi per jam
Koefisien alat / M3 =
Tk 7.00 Jam
Fk 1.20
D 1.40 Ton/M3
(E10)
V 0.85 M3
Fb 0.90
Fa 0.80
Ts1
T1 1.25 Menit
T2 0.50 Menit
Ts1 1.75 Menit
1 : Q1 0.0572 Jam
(E8)
V 5.00 Ton
Fa 0.80 -
v1 25.00 Km/jam
v2 35.00 Km/jam
TS2
= (L : v1) x 60 T1 4.80 Menit
= (L : v2) x 60 T2 3.43 Menit
= (V x 60)/ D x Q1 x Fk T3 10.21 Menit
T4 5.00 Menit
Ts2 23.44 Menit
V x Fa x 60 Q2 6.09 M3/jam
D x Fk x Ts2
= 1 : Q2 0.1641 Jam
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
1.00 Ls
Q1 17.49 M3/jam
= Tk x Q1 Qt 122.40 M3
P 6.00 Orang
M 1.00 Orang
/ M3
bulan
M3
Kontraktor
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
L 5.00 Km
TK 7.00 Jam
: - Volume semen Sm 20.00 %
: - Volume pasir Ps 80.00 %
Bt 60.00 %
Mr 40.00 %
D1 2.40 Ton/M3
D2 1.60 Ton/M3
D3 1.80 Ton/M3
D4 1.67 Ton/M3
D5 1.44 Ton/M3
(E16)
V 300.00 Liter
Fa 0.80
(T1+T2+T3+T4) Ts
T1 4.00 Menit
T2 4.00 Menit
T3 1.00 Menit
T4 5.00 Menit
Ts1 14.00 Menit
V x Fa x 60 Q1 1.0286 M3/Jam
1000 x Ts
2.00 Unit
2.06 M3/Jam
1.00 Ls
= 4 buah
= 4 buah
= 4 buah
= 8 buah
= 3 buah
= Tk x Q1 Qt 14.40 M3
M 1.00 Orang
Tb 10.00 Orang
P 20.00 Orang
/ M3
bulan
M3
0.00
Kontraktor
0.00
0.00
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
d 0.80 M
L 5.00 Km
Tk 7.00 Jam
tg 10.00 Cm
tp 0.18 M
Q1 9.41 M/Jam
(E25)
v 1.00 Km/Jam
Fa 0.80 -
Lb 0.40 M
n 10.00 Lintasan
N 5.00 Lapis
tp 0.10 M
Q1 0.39 M/Jam
(E11)
V 4.00 Buah/M'
Fa 0.80 -
v1 25.00 Km/jam
v2 35.00 Km/jam
TS2
(L : v1) x 60 T1 12.00 Menit
(L : v2) x 60 T2 8.57 Menit
15.00 Menit
Ts 35.57 Menit
1.00 Ls
3 buah
Qt 4.00 M'
P 10.00 Orang
T 2.00 Orang
M 1.00 Orang
bulan
M'
0.00
Kontraktor
0.00
0.00
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
d 0.30 M
L 5.00 Km
Tk 7.00 Jam
tg 6.50 Cm
tp 0.10 M
(E25)
v 1.00 Km/Jam
Fa 0.80 -
Lb 0.40 M
n 10.00 Lintasan
tp 0.10 M
Q1 41.75 M/Jam
(E25)
v 1.00 Km/Jam
Fa 0.80 -
Lb 0.40 M
n 10.00 Lintasan
N 5.00 Lapis
tp 0.10 M
Q1 2.19 M/Jam
(E11)
V 4.00 Buah/M'
Fa 0.80 -
v1 25.00 Km/jam
v2 35.00 Km/jam
TS2
(L : v1) x 60 T1 12.00 Menit
(L : v2) x 60 T2 8.57 Menit
30.00 Menit
Ts 50.57 Menit
1.00 Ls
3 buah
Qt 20.00 M'
P 8.00 Orang
T 4.00 Orang
M 1.00 Orang
bulan
M'
0.00
Kontraktor
0.00
0.00
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
Berbentuk U Type DS 3
l 0.80 M
1.20 M
0.15 M
L 5.00 Km
Tk 7.00 Jam
tp 0.15 M
(EI-716) 0.4200 M3
(M39) 57.7500 Kg
(EI-241) 0.1050 M3
(M09) 0.1200 M3
(E25)
v 1.00 Km/Jam
Fa 0.80 -
Lb 0.40 M
n 10.00 Lintasan
tp 0.10 M
Q1 30.48 M/Jam
(E25)
v 1.00 Km/Jam
Fa 0.80 -
Lb 0.40 M
n 10.00 Lintasan
N 5.00 Lapis
tp 0.10 M
Q1 5.33 M/Jam
Berbentuk U Type DS 3
(E11)
V 4.00 Buah/M'
Fa 0.80 -
v1 25.00 Km/jam
v2 35.00 Km/jam
TS2
(L : v1) x 60 T1 12.00 Menit
(L : v2) x 60 T2 8.57 Menit
15.00 Menit
Ts 35.57 Menit
1.00 Ls
3 buah
Qt 4.00 M'
P 8.00 Orang
T 2.00 Orang
M 1.00 Orang
Berbentuk U Type DS 3
bulan
M'
0.00
Kontraktor
0.00
0.00
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
L 5.00 Km
` Tk 7.00 Jam
Ks1 340.00 Kg/M3
Ag 19.00 Mm
Wcr 0.5
: Semen Sm 16.7 %
: Pasir Ps 33.3 %
: Agregat Kasar Kr 50.0 %
D1 2.400 T/M3
D2 1.250 T/M3
D3 1.440 T/M3
D4 1.525 T/M3
(E06)
V 0.30 M3
Fa 0.80 -
Ts
T1 5.00 Menit
T2 4.00 Menit
T3 1.00 Menit
T4 4.00 Menit
Ts1 14.00 Menit
(E23)
V 4.50 M3/jam
Wc 0.21 M3/jam
pa 100.00 liter/menit
Fa 0.80 -
pa x Fa x 60 Q2 23.41 M3/Jam
1000 x Wc
1 : Q2 0.0427 Jam
1.00 Ls
2 buah
2 buah
2 buah
4 buah
1 buah
Qt 7.20 M3
M 1.00 Orang
T 8.00 Orang
P 15.00 Orang
bulan
M3
0.0000
Kontraktor
0.0000
0.0000
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
L 5.00 Km
TK 7.00 Jam
Fh 1.10 -
1.1000 Kg
0.0200 Kg
1.00 Ls
= 2 buah
= 2 buah
Qt 100.00 Kg
M 1.00 Orang
Tb 2.00 Orang
P 4.00 Orang
/Kg
bulan
Kg
0.0000
Kontraktor
0.0000
0.0000
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
L 5.0 KM
Tk 7.00 jam
Fh 1.10 -
(M06) 1.1000 M3
(M02) 0.4300 M3
1.00 Ls
= 4 buah
= 2 buah
Qt 20.00 M3
- Mandor M 1.00 orang
- Tukang Tb 5.00 orang
- Pekerja P 10.00 orang
/ M3
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
bulan
M3
0.00
Kontraktor
0.00
0.00
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
Tk 7.00 Jam
Fh 1.10
t 0.10 M
Bt 50.00 %
Ps 50.00 %
(M03) 0.5500 M3
(M01) 0.5500 M3
(E25)
v 1.00 Km/Jam
Fa 0.80 -
Lb 0.40 M
n 10.00 Lintasan
Q1 3.2000 M3/Jam
1.00 Ls
3 buah
Qt 22.40 M3
P 6.00 Orang
M 1.00 Orang
/ M'
bulan
M'
0.00
Kontraktor
0.00
0.00
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
Tk 7.00 Jam
Fk 1.20
D 1.40 Ton/M3
L 2.00 Km
(E10)
V 0.85 M3
Fb 0.90
Fa 0.80
Ts1 Menit
T1 1.00 Menit
T2 0.50 Menit
Ts1 1.50 Menit
V x Fb x Fa x60 Q1 20.40 M3/Jam
Ts1 x Fk
1.00 Unit
20.40 M3/Jam
(E08)
V 10.00 Ton
Fa 0.80 -
v1 25.00 Km/jam
v2 35.00 Km/jam
TS2
= (L : v1) x 60 T1 4.80 Menit
= (L : v2) x 60 T2 3.43 Menit
= (V x 60)/ D x Q1 x Fk T3 17.51 Menit
T4 5.00 Menit
Ts2 30.74 Menit
V x Fa x 60 Q2 9.30 M3/jam
D x Fk x Ts2
= 1 : Q2 (E08) 0.1076 Jam
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
1.00 Ls
Q1 20.40 M3/jam
Tk x Q1 Qt 142.80 M3
P 6.00 Orang
M 1.00 Orang
/M3
bulan
M3
0.00
Kontraktor
0.00
0.00
Direktur Utama
TEKNIS ANALISA HARGA SATUAN PEKERJAAN
Tk 7.00 Jam
Fk 1.20 -
D 1.80 Ton/M3
L 2.00 Km
Q1 4.00 M3/Jam
1 : Q1 0.2500 Jam
(E08)
V 5.00 Ton
Fa 0.80 -
v1 25.00 Km/jam
v2 35.00 Km/jam
TS2
T1 41.67 Menit
= (L : v1) x 60 T2 4.80 Menit
= (L : v2) x 60 T3 3.43 Menit
N PEKERJAAN
KET
N PEKERJAAN
KET
Kontraktor
Direktur Utama
AN PEKERJAAN
KET
N PEKERJAAN
KET
0.00
Kontraktor
0.00
0.00
Direktur Utama
N PEKERJAAN
KET
N PEKERJAAN
KET
N PEKERJAAN
KET
0.00
Kontraktor
0.00
0.00
Direktur Utama
N PEKERJAAN
KET
N PEKERJAAN
KET
N PEKERJAAN
KET
0.00
Kontraktor
0.00
0.00
Direktur Utama
N PEKERJAAN
KET
N PEKERJAAN
KET
N PEKERJAAN
KET
0.00
Kontraktor
0.00
0.00
Direktur Utama
N PEKERJAAN
KET
Berdasarkan
dgn Spesifikasi
N PEKERJAAN
KET
N PEKERJAAN
KET
0.0000
Kontraktor
0.0000
0.0000
Direktur Utama
N PEKERJAAN
KET
N PEKERJAAN
KET
0.0000
Kontraktor
0.0000
0.0000
Direktur Utama
N PEKERJAAN
KET
N PEKERJAAN
KET
0.00
Kontraktor
0.00
0.00
Direktur Utama
N PEKERJAAN
KET
Agregat kasar
N PEKERJAAN
KET
0.00
Kontraktor
0.00
0.00
Direktur Utama
N PEKERJAAN
KET
N PEKERJAAN
KET
0.00
Kontraktor
0.00
0.00
Direktur Utama
N PEKERJAAN
KET