Luas Lantai = 28 m2
Luas Tembok Kamar = 8.75 m2 1.31 m3
Cat = 65.25 m2
BAHAN
Batu belah = 0.72 m3 1.00 m3
Semen Portlan = 465.78 kg 466.00 kg
Pasir = 2.12 m3 3.00 m3
Kayu kelas III = 0.03 m3 1.00 m3
Paku 5 cm – 12 cm = 0.19 kg 1.00 kg
Minyak bekisting = 0.00 0.00
Besi beton polos = 40.20 kg 41.00 kg
Kawat beton = 0.58 kg 1.00 kg
Kerikil = 0.15 m3 1.00 m3
Kayu kelas III = 0.02 m3 1.00 m3
Bata merah = 612.50 bh 613.00 bh
Keramik 60x60 = 86.80 bh 87.00 bh
Semen warna = 42.00 kg 42.00 kg
Plamuur = 6.53 kg 7.00 kg
Cat dasar = 6.53 kg 7.00 kg
Cat penutup = 16.97 kg 17.00 kg
Volume
Harga Satuan Jumlah
URAIAN Satuan
(Rp)
Total
( Rp )
a d f h=cxf
1. BAHAN
1.1 Batu belah 1.00 m3 250,000 250,000
1.2 Semen Portlan 10.00 Zak 62,000 620,000
1.3 Pasir 3.00 m3 300,000 900,000
1.4 Kayu kelas III 1.00 m3 -
1.5 Paku 5 cm – 12 cm 1.00 kg 20,000 20,000
1.6 Minyak bekisting - - -
1.7 Besi beton polos 41.00 kg 11,000 451,000
1.8 Kawat beton 1.00 kg 15,000 15,000
1.9 Kerikil 1.00 m3 300,000 300,000
1.10 Kayu kelas III 1.00 m3 -
1.11 Bata merah 613.00 bh 700 429,100
1.12 Keramik 60x60 87.00 bh 5,000 435,000
1.13 Semen warna 42.00 kg 10,000 420,000
1.14 Plamuur 7.00 kg 20,000 140,000
1.15 Cat dasar 7.00 kg 23,000 161,000
1.16 Cat penutup 17.00 kg 23,000 391,000
Sub Total 1) 4,532,100
3. UPAH
3.1 Pekerja 16.00 HOK 55,000.00 880,000
3.2 Mandor 1.00 HOK 65,000.00 65,000
3.3 Tukang Batu 6.00 HOK 65,000.00 390,000
3.4 Kepala Tukang 1.00 HOK 65,000.00 65,000
3.5 Tukang kayu 1.00 HOK 65,000.00 65,000
3.6 Tukang besi 1.00 HOK 65,000.00 65,000
3.7 Tukang cat 5.00 HOK 65,000.00 325,000
Sub Total 2) 1,855,000
TOTAL 6,387,100