Harga Jumlah
No. Jenis Pekerjaan Volume Satuan Kode Analisa Satuan Harga Satuan
(Rp) (Rp)
1 2 3 4 5 6 7
A PEKERJAAN STRUKTUR
I PEKERJAAN PENDAHULUAN
1
1 Pengukuran dan Pemasangan Bowplank 118.00 m A.2.2.1.4 65,113.39 7,683,379.90
2 Biaya Penyelenggara SMK3 Kontruksi 1.00 lsm Analisa Ls 31,226,500.00 31,226,500.00
SUB JUMLAH A.I 38,909,879.90
II PEKERJAAN PONDASI
1 Galian Tanah Pondasi 51.20 m3 A.2.3.1.1 82,225.00 4,209,920.00
2 Pemancangan Cerucuk dia. 10 - 3 m 1,200.00 m1 A.3.2.1.12 17,281.71 20,738,049.75
3
3 Lap. Pasir Urug 7.68 m A.2.3.1.11 262,114.60 2,013,040.13
4 Lap. Lantai Kerja 2.56 m3 A.4.1.1.4 1,245,769.50 3,189,169.92
5 Pondasi
2
- Bekisting 204.80 m A.4.1.1.20.a 123,667.48 25,327,098.93
- Pembesian 1,950.87 kg A.4.1.1.17 22,029.61 42,976,898.43
- Beton K-225 10.24 m3 A.4.1.1.7.a 1,539,172.37 15,761,125.06
6 Kolom Pondasi 20/20
- Bekisting 123.80 m2 A.4.1.1.20.a 123,667.48 15,310,033.44
- PEmbesian 1,094.66 kg A.4.1.1.17 22,029.61 24,114,918.04
3
- Beton K-225 6.19 m A.4.1.1.7.a 1,539,172.37 9,527,476.97
7 Urugan Tanah Kembali 40.96 m3 A.2.3.1.9 59,950.00 2,455,552.00
SUB JUMLAH A.II 165,623,282.66
2 Sloof 15/30
- Bekisting Balok 204.75 m2 A.4.1.1.21.a 123,667.48 25,320,915.56
- Plastik Cor 204.75 m2 U&B 3,450.15 706,418.21
- Pembesian 2,336.15 kg A.4.1.1.17 22,029.61 51,464,465.22
- Beton K-225 ( Fc 19,3 Mpa ) 12.29 m3 A.4.1.1.7.a 1,539,172.37 18,916,428.42
9 Kolom praktis
- Bekisting Kolom 16.00 m2 A.4.1.1.22 332,168.51 5,314,696.20
- Pembesian 137.25 kg A.4.1.1.17 22,029.61 3,023,468.03
3
- Beton K-225 ( Fc 19,3 Mpa ) 0.37 m A.4.1.1.7.a 1,444,175.84 534,345.06
10 Plat Lantai
- Bekisting 455.95 m2 A.4.1.1.24.a 98,384.74 44,858,425.24
- Pembesian 2,087.66 kg A.4.1.1.19 25,677.59 53,606,080.67
3
- Beton K-225 ( Fc 19,3 Mpa ) 65.24 m A.4.1.1.7.a 1,539,172.37 100,415,605.38
B PEKERJAAN TANGGA
1 Tangga Naik Selasar
2
- Bekisting Tangga 4.64 m A.4.1.1.26 245,918.55 1,141,062.07
- Pembesian 101.01 kg A.4.1.1.17 22,029.61 2,225,166.49
- Beton K-175 ( Fc 14,5 Mpa ) 1.63 m3 A.4.1.1.5.a 1,444,175.84 2,356,894.96
c PEKERJAAN ATAP
1 - Rangka Baja Ringan 795.28 m2 U&B 212,019.75 168,615,702.16
- Atap Spandek 795.28 m2 A.4.5.2.32.a 120,871.41 96,126,614.94
- Perabung 70.76 m1 A.4.5.2.37 94,283.75 6,671,518.15
1
- Lisplank 146.40 m A.4.6.1.21 103,499.95 15,152,393.06
SUB JUMLAH A.III 821,533,412.02
TOTAL PEKERJAAN STRUKTUR 1,026,066,574.58
B PEKERJAAN ARSITEKTUR
I PEKERJAAN DINDING
1 Pas. Dinding Batako 437.46 m2 A.4.4.1.17.b 114,780.45 50,211,853.91
2
2 Pas. Plesteran 1:3 1,018.93 m A.4.4.2.3 75,206.94 76,630,608.52
3 Pas. Dinding Keramik 20x25 Cm 33.00 m2 A.4.4.3.54.a 274,681.27 9,064,481.90
4 Pas. Dinding Sekat Partisi 35.00 m' ------ 1,500,000.00 52,500,000.00
SUB JUMLAH B.I 188,406,944.33
II PEKERJAAN LANTAI
2
1 Pas. Lantai Keramik 40x40 Cm Unpolised 430.79 m A.4.4.3.34.d 173,501.25 74,742,602.12
2 Pas. Lantai Keramik WC 20x20 Cm Unpolised 27.81 m2 A.4.4.3.54.a 274,681.27 7,638,886.11
SUB JUMLAH B.II 82,381,488.23
III PEKERJAAN PLAFON
2
1 Rangka plafond Holow (ruangan dan kaki atap) 569.69 m - 122,850.00 69,986,416.50
2
2 Pas. Plafond Gypsum 9 mm (Ruangan) 432.35 m A.4.5.1.7 50,524.06 21,844,075.61
2
3 Pas. Plafond GRC Wet Area 4 mm Rangka Metal Furing 137.34 m A.4.5.1.7.a 162,977.13 22,383,279.45
4 Pas. Profil Gypsum 152.00 m' A.4.5.1.9.a 39,619.83 6,022,213.78
SUB JUMLAH B.III 120,235,985.34
IV PEKERJAAN PINTU, JENDELA DAN VENTILASI
Pintu :
1 PV1 140x210 cm 5.00 Unit
- Kusen kayu klas I Uk : 5/10 0.20 m3 A.4.6.1.2 8,254,582.88 1,650,916.58
- Pintu panel kayu klas I 14.23 m2 A.4.6.1.5.b 761,794.19 10,840,331.36
- Set Kunci pintu uk.besar 5.00 Unit A.4.6.2.2.a 236,502.75 1,182,513.75
- Engsel pintu 30.00 Bh A.4.6.2.5 43,065.28 1,291,958.25
- Slot Pintu 20.00 Bh A.4.6.2.11.a 96,666.08 1,933,321.50
- Kaca T.5 mm Pada Pintu 0.47 m2 A.4.6.2.17 184,024.94 86,491.72
- Handel Pintu 20.00 Bh - 96,666.08 1,933,321.50
- Ventilasi Sisir kayu klas I L = 17,14 1.72 m2 - 282,000.00 485,040.00
Jendela :
1 JV1 5.00 Unit
- Kusen kayu klas I 0.19 m3 A.4.6.1.2 8,254,582.88 1,568,370.75
2
- Kaca T.5 mm ( Kaca Mati ) 2.10 m A.4.6.2.17 184,024.94 386,452.37
- Ventilasi Sisir kayu klas I L = 17,14 3.30 m2 - 282,000.00 930,600.00
Ventilasi :
1 Ventilasi V1 7.00 Unit U&B 400,000.00 2,800,000.00