Perencanaan Gelagar Memanjang

Data Jembatan
Jarak Antar Gelagar = 275 cm
S = 1975 mm
Tebal Pelat Lantai = 210 mm
Panjang Bentang = 33 m
Tebal Trotoar = 0.1 m

Data Material Beton


Mutu Beton, fc' = 30 MPa
Ec = 25742.96 MPa

Data Baja
Mutu Baja BJ41, fy = 250 MPa fu = 410 MPa
Es = 200000 MPa
Profil WF :900.300.16.26
d= 1800 mm As = 615.04 cm^2
bf = 600 mm Ix = 54974935 cm^4
tw = 16 mm Iy = 100859.53 cm^4
tf = 28 mm W= 482.81 kg/m

ANALISIS STRUKTUR
Beban Mati Primer
Berat sendiri WF = W = 4.83 kN/m
Pelat beton = ts x S x BJ Beton = 12.978 kN/m
Qd = 17.81 kN/m
*Gaya Momen :
Md = 1/8 q L^2 = 2423.85 kN/m
*Gaya Lintang :
Vd = 1/2 q L = 293.80 kN

Beban Mati Sekunder


Berat Trotoar = 1.32 kN/m
Berat Sambungan = 10% * Berat WF = 0.48 kN/m
Berat Bekisting = W_bekisting * jarak antar gelag= 1.38 kN/m
Qds = 3.18 kN/m
*Gaya Momen :
Mds = 1/8 q L^2 = 432.58 kN/m
*Gaya Lintang :
Vds = 1/2 q L = 52.43 kN

Beban Lalu Lintas


*Beban T
Faktor Beban Dinamis FBD = 0.4
Beban truk pada lantai jembatan T= 500 kN
Beban Truk (1+FBD) x T = Ptt = 112.5 kN

Momen
Mtt = 1/4 Ptt L = 928.125 kN.m
Lintang
Vtt = 1/2 Ptt = 56.25 kN

*Beban D
Beban Terbagi Rata BTR (q) = 9.95 kPa
Beban Garis Terpusat BGT (p) = 49 kN/m

Perhitungan untuk satu Gelagar


BTR qTD = 19.66 kN/m
BGT pTD = 96.78 kN/m

Momen
Mtd = 1/8 qTD L^2 + 1/4 pTD L = 3474.64 kN.m
Lintang
Vtd = 1/2 qTD L + 1/2 pTD = 372.78 kN

Momen Total
Mu total = 1.8 Md + 2 Mds + 2 Mtt + 2 Mtd
Mu total = 14033.62 kN.m

Lintang Total
Vu total = 1.8 Vd + 2 Vds + 2 Vtt + 2 Vtd
Vu total = 1491.77 kN.m

ANALISIS GELAGAR
1. Kondisi Sebelum Komposit
Beban Mati
Berat sendiri WF = W = 4.83 kN/m
Pelat beton = ts x S x BJ Beton = 12.978 kN/m
Berat Trotoar = 1.32 kN/m
Berat Sambungan = 10% * Berat WF = 0.48 kN/m
Berat Bekisting = W_bekisting * S = 1.38 kN/m
q_total = 20.98 kN/m

Momen Lentur
M_Maks = 1/8 q L^2 = 2856.43 kN.m
= 2856429358.2 N.mm

Tegangan yang terjadi pada gelagar baja


* Tepi atas flens atas profil WF
f_sa = M_maks (d/2) = 4.68 MPa
Ix

* Tepi bawah flens bawah profil WF


f_sb = = 4.68 MPa

Lendutan
*Lendutan maksimum terjadi ditengah bentang dipikul gelagar baja
δ= 5 x q x L^4 = 2.95 mm
384 x Es x Ix

2.Kondisi Komposit
Beban Pekerja
Qp = Qp x S = 9.875 kN/m

Momen Lentur
M_Maks = 1/8 x Qp x L^4 = 1344.23 kN/m
M_Total = 4200.66 kN/m

Garis Netral Penampang Komposit


*Lebar Efektif
B_Eff = L / 5 = 6.6 m
B_Eff = S = 1.975 m
B_Eff = 12 x ts = 2.52 m
B_Eff = minimum = 1.975 m

*Modulus Ratio
n= Es / Ec = 7.77

*Lebar Eq Baja
Lc = B_Eff / n = 0.254
= 26 cm

*Letak garis netral komposit


Ac = 546 cm^2
As = 615.04 cm^2
A_total = 1161.04 cm^2

Statis momen kesisi atas pelat beton


A_total x Ya = (Ac x ts/2) + (As x (d/2+ts))
Ya = 63.74 cm

Statis momen kesisi bawah pelat beton


A_total x Yb = (Ac x (ts/2+d)) + (As x (d/2))
Yb = 137.26 cm

Kontrol :
Ya + Yb = ts + d
201 = 201 (ok)

Momen Inersia Penampang Komposit


* Penampang baja Eq
Luas Penampang baja Eq. Ac = 546 cm^2
Inersia thd baja sendiri Ioc = 1/12 x Lc x ts^3 = 25467.75 cm^4
Letak pusat berat penampang baja Eq thd g.netral
d1 = Ya - (ts/2) = 126.76 cm
Inersia penampang baja Eq. thd g.netral komposit
Ic = Ioc + (Ac x d1^2) = 8798917.244254 cm^4

Momen Inersia Profil Wf 900.300.16.26


Luas profil As = 615.04 cm^2
Inersia thd sendiri Ios = Ix = 54974935 cm^4
Pusat berat WF thd g.netral komposit
d2 = Yb (d/2) = 47.26 cm
Inersia WF thd g.netral
Is = Ios + As x d2^2 = 56348744.6 cm^4

Momen Inersia Penampang Komposit


I = Ic + Is = 65147661.81 cm^4

Tegangan pada penampang komposit


*Pada tepi atas pelat beton
F_ca = M x Ya = 0.529 MPa
nXI

*Pada tepi bawah pelat beton


F_cb = M x (Ya-ts) = 0.512 MPa
I

*Pada tepi atas flens atas WF


F_sa = M x (Ya-ts) = 3.974 MPa
I

*Pada tepi bawah flens atas WF


F_sa = M x Yb = 8.851 MPa
I

Jumlah tegangan penampang komposit


*Tepi atas flens atas WF
fsa = 8.65 MPa

*Tepi bawah flens bawah WF


fsb = 13.527 MPa

Lendutan
*Lendutan tambahan akibat beban pekerja
δ= 5 x q x L^4 = 1.387 mm
384 x Es x Ix
δ total = 4.33 mm

Analisa Kekuatan Desain Gelagar


Kontrol penampang
*Web
λ= h / tw ≤ 1680 / √fy
109 ≤ 106.25 (penampang tidak kompak)

*Flens
λ= b / 2 tf ≤ 170/ √fy
10.714 ≤ 32.13 (penampang kompak)

Kontrol kuat lentur nominal


Dari perhit. sebelumnya :
Mu _ sebelum komposit = 2856.43 kN.m
Mu _ komposit = 4200.66 kN.m

Penampang Kompak
Mn = Mp = Zx x fy
Mn = Mp = 7441064000 N.mm
Mn = Mp = 7441.06 kN.m

*Kontrol kuat lentur nominal sebelum komposit


Mu ≤ φ.Mn
2856.43 ≤ 6696.9576 (ok)

*Kontrol kuat lentur nominal komposit


Mu ≤ φ.Mn
4200.66 ≤ 6696.9576 (ok)

*Kontrol Lendutan
Lendutan Izin
δ_izin = 33 mm

Lendutan sebelum komposit =


δ= 2.95 mm < 33 mm (ok)
Lendutan setelah komposit =
δ= 4.33 mm < 33 mm (ok)

Kontrol Kapasitas geser vertikal


Vu ≤ Φ Vn
1491770 N ≤ 0.6 x fy x Aw N
1491770 N ≤ 4320000 N (ok)

Garis netral plastis


* Kekuatan pada pelat lantai
Ac = b_eff x ts = 414750 mm^2
C= 0.85 x f'c x Ac = 10576125 N

*Kontrol kuat tarik gelagar


T= As x fy = 15376000 N

*Tinggi daerah tekan


a= C
0.85 x fc' x be
a= 305.31 mm

d1 = 957.35 mm
d2 = 0.00
d3 = 900.00

*Kuat Lentur
Ms = Cxd = 19643531250 N.mm
Mu = Φ Ms = 17679178125 N.mm

Mu _ total < Mu
14033.62 kN.m < 17679.18 kN.m (ok)

Perhitungan Shear Connector


Jarak antara shear connector :
* 600 mm
* 2 ts = 420 mm
* 400 mm
diambil jarak antar shear connector ; 400 mm

Tinggi minimum shear connector 75 mm


jarak antar paku dengan ujung flens gelagar ≥ 25 mm
diameter paku shear connector ;
* 1.5 x jika pelat memikul tegangan tarik
* 2.0 x jika tidak terdapat tegangan tarik
Gaya geser horizontal akibat komposit penuh
Vh = T = 15376000 N
digunakan stud 1/2" x 5 cm, Asc = 267.4 mm^2
Qn = 0.5 x Asc x √(fc' x Ec) = 117495.51 N
Asc x fu = 109634 N
dipakai, Qn = 109634 N

Jumlah stud yang dibutuhkan


N_stud = Vh / Qn = 140.24846 buah
dipakai, = 154

Jarak pemasangan stud


S= L/N = 214.28571 mm
dipasang = 200 mm

Kontrol jarak pemasangan stud


Smin < S < Smax
76.2 < 200 < 800 (OK)