Anda di halaman 1dari 2

OPNAME PEKERJAAN BORONGAN

MANDOR : IMAM ASROFI


PERIODE : 3 Agustus 2018 s/d 16 Agustus 2018

NO URAIAN PEKERJAAN SATUAN VOLUME QUANTITY HARGA JUMLAH


KONTRAK S/D MINGGU S/D MINGGU SATUAN HARGA
MINGGU INI
LALU INI
I Kantong Lumpur

1 Besi Ulir D 13 kg 9,128.78 9,128.78 1,400.00 12,780,297.60

2 Perataan tanah m2 120.00 120.00 3,000.00 360,000.00

3 Pengecoran Beton K-225 m3 136.00 136.00 75,000.00 10,200,000.00

4 Pemasangan Water Stop m1 19.00 19.00 5,000.00 95,000.00

5 Pemasangan Bekisting Dinding Kantong lumpur m2 13.00 13.00 25,000.00 325,000.00

6 Pengecoran Beton K-225 Dinding Kantong Lumpur m2 12.90 12.90 75,000.00 967,500.00

7 Pengecoran Lantai Kerja K-100 m2 704.50 704.50 10,000.00 7,045,000.00

8 Pemasangan Bekisting Stopcor m1 150.60 150.60 2,500.00 376,500.00

9 Pemasangan Bekisting Block out m2 18.00 18.00 5,000.00 90,000.00

II Rehab Saluran Induk Mengker

1 Bekisting Precast Frame Saluran Induk Mengker Type 1 m2 81.04 81.04 25,000.00 2,026,000.00

2 Bekisting Precast Frame Saluran Induk Mengker Type 2 m2 57.24 57.24 25,000.00 1,431,000.00

5 Bekisting Precast Frame Saluran Induk Mengker Type 3 m2 149.70 149.70 25,000.00 3,742,500.00

6 Besi Ulir D13 (Precast Frame Pas. Batu Sal. Mengker Type 1) kg 1,228.03 1,228.03 1,400.00 1,719,244.80

7 Besi Ulir D13 (Precast Frame Pas. Batu Sal. Mengker Type 2) kg 823.68 823.68 1,400.00 1,153,152.00

8 Besi Ulir D13 (Precast Frame Pas. Batu Sal. Mengker Type 3) kg 2,043.72 2,043.72 1,400.00 2,861,214.72

9 Besi Polos P10 (Precast Frame Pas. Batu Sal. Mengker Type 1) kg 331.70 331.70 1,400.00 464,378.88

10 Besi Polos P10 (Precast Frame Pas. Batu Sal. Mengker Type 2) kg 228.04 228.04 1,400.00 319,260.48
11 Besi Polos P10 (Precast Frame Pas. Batu Sal. Mengker Type 3) kg 1,700.71 1,700.71 1,400.00 2,380,996.80

12 Pengecoran Precast Frame Saluran Induk Mengker Type 1 m3 8.18 8.18 75,000.00 613,800.00

13 Pengecoran Precast Frame Saluran Induk Mengker Type 2 m3 5.76 5.76 75,000.00 432,000.00

14 Pengecoran Precast Frame Saluran Induk Mengker Type 3 m3 18.44 18.44 75,000.00 1,382,760.00

15 Perapihan dan perataan Tanah m2 250.66 250.66 3,000.00 751,980.00

16 Pekerjaan Pasangan Batu m3 62.69 62.69 125,000.00 7,836,250.00

17 Pekerjaan Siaran m2 427.36 427.36 10,000.00 4,273,600.00

18 Pekerjaan Lantai Kerja Beton K-100 m2 109.72 109.72 10,000.00 1,097,200.00

19 Pemasangan Beton precast Frame m3 32.06 32.06 25,000.00 801,500.00

20 Pekerjaan Bronjong bh 144.00 144.00 60,000.00 8,640,000.00

Jumlah 74,166,135.28

Bogor, 19 Agustus 2018


disetujui diketahui, diperiksa diajukan

Ir. HERY MARDIONO WELLI JULI PUTRA GEA M. SOLIKHIN IMAM ASROFI
Project Manager Pelaksana Teknik Dept. Mandor