REKAPITULASI RENCANA ANGGARAN BIAYA

NO URAIAN PEKERJAAN JUMLAH BOBOT

I PEKERJAAN PERSIAPAN Rp18.160.406,25 4,33%

II PEKERJAAN PONDASI DAN BETON Rp169.328.404,00 40,40%

III PEKERJAAN PASANGAN DAN PLESTERAN Rp80.220.195,00 19,14%

IV PEKERJAAN KERAMIK LANTAI DAN DINDING Rp23.539.817,40 5,62%

V PEKERJAAN ATAP Rp12.249.955,66 2,92%

VI PEKERJAAN PLAFOND Rp20.062.270,00 4,79%

VII PEKERJAAN KUSEN, PINTU DAN JENDELA Rp18.453.734,50 4,40%

VIII PEKERJAAN AKSESORIS PINTU DAN JENDELA Rp8.637.280,00 2,06%

IX PEKERJAAN SANITAIR Rp8.316.000,00 1,98%

X PEKERJAAN INSTALASI AIR Rp14.436.506,50 3,44%

XI PEKERJAAN INSTALASI LISTRIK Rp12.613.450,00 3,01%

XII PEKERJAAN PENGECATAN Rp33.074.199,10 7,89%


JUMLAH TOTAL Rp419.092.218,41 100,00%