I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 241.50 m2 1,800.00
2 Mobilisasi Proyek 1.00 Ls
3 Air Kerja 3.00 bln
4 Listrik Kerja 3.00 bln
5 Gudang dan Los Kerja 20.00 m2 70,000.00
6 Koordinasi keamanan proyek 3.00 bln 1,000,000.00
7 Pembersihan selama proyek 3.00 bln 500,000.00
8 Direksi Keet 1.00 Ls
9 Pekerjaan Uitzet & bouwplank 49.00 ml 7,500.00
Sub Total :
Sub Total :
Sub Total :
Sub total :
V PEKERJAAN ATAP
1 Pekerjaan Kuda - kuda baja ringan 136.84 m2 34,000.00
2 Alluminium Foil 136.84 m2
3 Penutup atap dengan genteng Kanmuri Milenio 136.84 m2
4 Nok Genteng Kanmuri Milenia Warna Natural 29.65 ml
5 Lisplank kayu 49.00 ml
Sub total :
VI PEKERJAAN DINDING :
1 Pekerjaan Pasangan Dinding Bata 157.74 m2 17,750.00
2 Plesteran + acian dinding bata 315.48 m2 25,500.00
Sub total :
Sub total :
Sub Total :
IX PEKERJAAN PLAFOND :
1 Pekerjaan Plafond Gypsum 9 mm, rk Hollow 142.00 m2 25,000.00
2 Pekerjaan tali air plafond gypsum 165.00 m' 7,500.00
Sub total :
X PEKERJAAN CAT :
1 Pekerjaan cat dinding dalam vinilex 198.87 m2 6,750.00
2 Pekerjaan cat dinding luar wheatersield 159.25 m2 6,750.00
3 Pekerjaan cat plafond vinilex 142.00 m2 6,750.00
4 Pekerjaan cat list plafond Vinilex 165.00 m' 3,200.00
Sub total :
XI PEKERJAAN ME :
Sub total :
Sub total :
Sub total :
Fee Kontraktor 10 %
Total :
Total Upah Harga Satuan Total Harga
15,654,000.00
15,306,524.50
85,914,755.50
102,000.00 35,000.00 3,570,000.00
3,570,000.00
4,652,441.00 140,000.00 19,157,110.00
- 55,000.00 7,526,007.50
- 135,000.00 18,472,927.50
- 72,000.00 2,134,800.00
- 85,000.00 4,165,000.00
51,455,845.00
27,762,240.00
- 5,500,000.00 4,840,000.00
- 1,150,000.00 4,968,000.00
- 875,000.00 5,040,000.00
- 550,000.00 10,422,500.00
- 400,000.00 1,200,000.00
26,470,500.00
19,488,602.00
18,110,580.00
10,970,252.50
550,000.00 175,000.00 1,750,000.00
110,000.00 200,000.00 400,000.00
220,000.00 175,000.00 700,000.00
90,000.00 125,000.00 250,000.00
150,000.00 125,000.00 375,000.00
275,000.00 36,000.00 180,000.00
110,000.00 40,000.00 80,000.00
220,000.00 40,000.00 160,000.00
150,000.00 150,000.00 300,000.00
225,000.00 125,000.00 375,000.00
- 2,500,000.00 2,500,000.00
500,000.00 3,000,000.00 3,000,000.00
55,000.00 300,000.00 300,000.00
10,370,000.00
26,431,800.00
311,505,099.50
31,150,509.95
54,333,545.00 342,655,609.45
Project : Rumah Tinggal Kedoya
Page 11 of 40
Total
Rounded
Total
Rounded
Total
Rounded
Total
Rounded
UNIT PRICE ANALYSIS Page 13 of 40
Project : Rumah Tinggal Kedoya
Scope of work : Lean Concrete
Unit : cum
Unit Price : 803,400
No. Description Unit Quantity Price (Rp.)
1 PC zak 6.700 65,000
2 Sand Concrete cum 0.48 230,000
3 Aggregate ( Split ) cum 0.75 210,000
4 Labour Pouring cum 1.00 100,000
Total
Rounded
Total
Rounded
Total
Rounded
UNIT PRICE ANALYSIS Page 14 of 40
Project : Rumah Tinggal Kedoya
Scope of work : Rebar
Unit : kg
Unit Price : 10,940
No. Description Unit Quantity Price (Rp.)
1 Round Bar kg 1.05 8,800
2 Tie Wire kg 0.02 15,000
3 Labour kg 1.00 1,400
Total
Rounded
Total
Rounded
Total
Rounded
UNIT PRICE ANALYSIS Page 15 of 40
Project : Rumah Tinggal Kedoya
Scope of work : Smoother ( 2 mm thk )
Unit : sqm
Unit Price : 19,500
No. Description Unit Quantity Price (Rp.)
1 PC zak 0.10 65,000
2 Labour sqm 1.00 13,000
Total
Rounded
Total
Rounded
Total
Rounded
UNIT PRICE ANALYSIS Page 16 of 40
Project : Rumah Tinggal Kedoya
Scope of work : Form Work 9 mm ( 4x used )
Unit : sqm
Unit Price : 107,470
No. Description Unit Quantity Price (Rp.)
1 Timber cum 0.016 3,100,000
2 Plywood 9 mm sheet 0.167 110,000
3 Nail kg 0.3 15,000
4 Labour sqm 1.00 35,000
Total
Rounded
Total
Rounded
Total
Rounded
Total
Rounded
Total
Rounded
UNIT PRICE ANALYSIS
Project : Rumah Tinggal Kedoya Page 18 of 40
Scope of work : Ceramic Wall Tile 20 x 20
Unit : sqm
Unit Price : 121,000
No. Description Unit Quantity Price (Rp.)
1 PC zak 0.188 65,000
2 Sand River cum 0.022 230,000
3 Cement Grouting kg 0.162 22,500
4 Ceramic Cutting Tools day 0.027 50,000
5 Labour sqm 1.00 20,000
6 Wall Tile Ceramic 20 x 20 sqm 1.05 75,000
Total
Rounded
Total
Rounded
Total
Rounded
UNIT PRICE ANALYSIS Page 19 of 40
Project : Rumah Tinggal Kedoya
Scope of work : Hollow Steel frame for Partition 40 x 40 mm
Unit : sqm
Unit Price : 56,600
No. Description Unit Quantity Price (Rp.)
1 Hollow frame m1 1.250 35,000
2 Sekrup dus 0.057 15,000
3 Labour sqm 1.00 12,000
Total
Rounded
Total
Rounded
Total
Rounded
UNIT PRICE ANALYSIS
Project : Rumah Tinggal Kedoya Page 20 of 40
Scope of work : GRC Sheet 9mm
Unit : sqm
Unit Price : 37,990
No. Description Unit Quantity Price (Rp.)
1 Kalsiboard Sheet sheet 0.357 70,000
2 Nail ( Sekrup ) dus 0.043 15,000
3 Compound kg 0.246 3,000
4 Textile Compound roll 0.350 7,500
5 Labour sqm 1.00 9,000
Total
Rounded
Total
Rounded
Total
Rounded
UNIT PRICE ANALYSIS Page 21 of 40
Project : Rumah Tinggal Kedoya
Scope of work : Ceiling Plywood 3,8 mm thk
Unit : sqm
Unit Price : 32,650
No. Description Unit Quantity Price (Rp.)
1 Plywood 3,8 mm thk sheet 0.37 55,000
2 Plywood nail kg 0.015 20,000
3 Labour sqm 1.00 12,000
Total
Rounded
Total
Rounded
Total
Rounded
UNIT PRICE ANALYSIS
Project : Rumah Tinggal Kedoya Page 22 of 40
Scope of work : Window Glass Openable + Tralis 2400 x 1200 ( 4 hole )
Unit : nos
Unit Price : 4,732,530
No. Description Unit Quantity Price (Rp.)
1 Timber Frame Meranti m 11.88 45,000
2 Window Glass sqm 2.88 180,000
3 Glass t = 5 mm thk sqm 2.88 110,000
4 Timber List m 28.80 15,000
5 Hinges nos 8.00 15,000
6 Ironmongeries lot 4.00 15,000
7 Timber Frame Painting m 11.88 16,200
8 Window Painting m 14.40 16,200
9 Tralis nos 1.00 2,000,000
10 Labour nos 1.00 325,000
Total
Rounded
Total
Rounded
UNIT PRICE ANALYSIS
Project : Rumah Tinggal Kedoya Page 23 of 40
Scope of work : Window Fix Glass 400 x 800
Unit : nos
Unit Price : 342,200
No. Description Unit Quantity Price (Rp.)
1 Timber Frame Meranti m 2.84 45,000
2 Glass t = 5 mm thk sqm 0.64 110,000
3 Timber List m 3.20 15,000
4 Timber Frame Painting m 2.84 16,200
5 Labour nos 1.00 50,000
Total
Rounded
Total
Rounded
Total
Rounded
Total
Dibulatkan
Page 25 of 40
296,000
296,000
36,000
36,000
3,140
3,140
864,000
864,000
Page 27 of 40
803,400
803,400
685,700
685,700
808,750
808,750
Page 28 of 40
10,940
10,940
89,485
89,000
27,150
27,150
Page 29 of 40
19,500
19,500
191,910
191,910
145,600
145,600
Page 30 of 40
107,470
107,470
4,326,200
4,326,200
4,107,400
4,107,400
2,996,900
2,996,900
118,534
118,500
Page 32 of 40
121,034
121,000
650,050
650,000
33,516
33,510
Page 33 of 40
56,605
56,600
65,250
65,250
34,643
34,640
Page 34 of 40
37,998
37,990
58,250
58,250
63,855
63,850
Page 35 of 40
32,650
32,650
1,527,220
1,527,220
2,620,840
2,620,840
Page 36 of 40
4,732,536
4,732,530
1,312,472
1,312,470
Page 37 of 40
342,208
342,200
7,395,000
7,395,000
53,550
53,550
156,885
156,800
Urugan Pasir
org Tukang 0.35 80,000 28,000
org Pembantu Tukang 0.02 65,000 1,300
29,300
a
Urugan kembali
org Tukang 0.23 80,000 18,400
org Pembantu Tukang 0.02 65,000 1,300
19,700
Plesteran
org Tukang 0.08 80,000 6,400
org Pembantu Tukang 0.16 65,000 10,400
16,800
Keramik
org Tukang 0.13 80,000 10,400
org Pembantu Tukang 0.24 65,000 15,600
26,000
Plint Keramik
org Tukang 0.1 80,000 8,000
org Pembantu Tukang 0.17 65,000 11,050
19,050
Plafond Gypsum
org Tukang 0.05 80,000 4,000
org Pembantu Tukang 0.1 65,000 6,500
10,500
Cat
Org Tukang 0.06 80,000 4,800
Org Pembantu Tukang 0.03 65,000 1,950
6,750