JADWAL WAKTU PELAKSANAAN PEKERJAAN

Pekerjaan : PEMBANGUNAN RUMAH SUSUN INSTITUT TEKNOLOGI DEL, KAB. TOBA SAMOSIR

Tahun Anggaran : APBN TAHUN 2019

Lokasi : INSTITUT TEKNOLOGI DEL, KAB. TOBA SAMOSIR

JANGKA WAKTU PELAKSANAAN = 133 H

NO. URAIAN PEKERJAAN JUMLAH BOBOT Agustus September Oktober


HARGA 1 2 3 4 5 6 7 8 9 10
21-28/8 29 - 04/9 05 - 11/9 12 - 18/9 19 - 25/9 26 - 2/10 3 - 9/10 10 - 16/10 17 - 23/10 24 - 30/10
I. PEKERJAAN PERSIAPAN
1.1 PEKERJAAN PERSIAPAN
1. A . PEKERJAAN PERSIAPAN STANDART 187,936,270.38 1.629 0.326 0.326
1. B . KESELAMATAN KERJA ( K3 ) 49,400,000.00 0.428 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023

II. PEKERJAAN STRUKTUR


2.A1 PEKERJAAN STRUKTUR STANDART
1 Pekerjaan Struktur Lantai Dasar elv. -0.05 m 729,047,112.50 6.320 0.500 1.940 1.940 1.940
2 Pekerjaan Struktur Lantai 2 elv. +3.55 m 1,035,151,528.02 8.974 2.243 2.243 2.243
3 Pekerjaan Struktur Lantai 3 elv. +6.95 m 981,242,584.97 8.506 2.127
4 Pekerjaan Struktur Ringbalk & Lantai Rooftank elv. +13.75 m 359,979,106.96 3.121
5 Pekerjaan Struktur Ringbalk elv. +16.61 m 67,871,244.95 0.588
6 Pekerjaan Struktur Canopy Beton
A Komponen Canopy beton Lt. dasar 37,819,688.49 0.328 0.082
B Komponen Canopy beton Lt. 2 14,146,431.62 0.123
C Komponen Canopy beton Lt. 3 37,077,019.69 0.321
7 Pekerjaan Struktur Atap 301,680,500.00 2.615
2.A2 PEKERJAAN ARSITEKTUR STANDART
A.1. PEKERJAAN LANTAI
I LANTAI DASAR 223,314,773.88 1.936 0.484 0.484
II LANTAI DUA 157,576,049.03 1.366
III LANTAI TIGA 154,789,419.03 1.342
IV LANTAI DAK 9,897,157.65 0.086
PEKERJAAN DINDING
A.2.A. PEKERJAAN PASANGAN DINDING DAN PLESTERAN
I LANTAI DASAR 507,786,490.66 4.402 0.489 0.489 0.489
II LANTAI DUA 512,219,968.84 4.440 0.555
III LANTAI TIGA 632,421,043.80 5.482
A.2.B. PEKERJAAN KUSEN PINTU / JENDELA + ASSESORIES
I LANTAI DASAR 238,787,470.24 2.070
II LANTAI DUA 276,586,657.12 2.398
III LANTAI TIGA 283,619,385.12 2.459
A.3. PEKERJAAN PLAFOND
I LANTAI DASAR 132,112,749.06 1.145
II LANTAI DUA 131,589,750.31 1.141
III LANTAI TIGA 152,767,246.51 1.324
A.4. PEKERJAAN PENUTUP ATAP
I ATAP 278,145,448.54 2.411
A.5. PEKERJAAN UTILITAS
I LANTAI DASAR 104,384,929.00 0.905 0.129 0.129
II LANTAI DUA 120,119,249.00 1.041
III LANTAI TIGA 120,119,249.00 1.041
A.6. PEKERJAAN FINISHING
A.6.A. PEKERJAAN PENGECATAN
I LANTAI DASAR 81,389,361.77 0.706
II LANTAI DUA 72,521,037.33 0.629
III LANTAI TIGA 93,895,903.05 0.814
2.A3 PEKERJAAN MEKANIKAL DAN ELEKTRIKAL STANDAR
A.1. PEKERJAAN INSTALASI PLAMBING
I INSTALASI AIR BERSIH 50,181,107.00 0.435 0.048
II INSTALASI AIR KOTOR & AIR BEKAS 54,824,346.00 0.475
III INSTALASI AIR HUJAN 14,437,346.00 0.125
IV INSTALASI VENT 6,961,600.00 0.060 Kurva
A.2. PEKERJAAN INSTALASI ELEKTRIKAL Rencana
I PEKERJAAN PANEL 69,900,000.00 0.606
II PEKERJAAN INSTALASI KABEL FEEDER 71,641,469.08 0.621
III PEKERJAAN KABEL LADDER (RAK KABEL) 85,891,911.00 0.745
IV PEKERJAAN ARMATUR LAMPU, SAKLAR & STOP KONTAK 85,814,454.00 0.744
V PEKERJAAN INSTALASI FINAL 131,630,042.00 1.141 31.277
VI PEKERJAAN SISTEM PENTANAHAN 17,961,600.00 0.156
VII PEKERJAAN PENANGKAL PETIR 33,996,240.00 0.295
28.017
II.2 PEKERJAAN STRUKTUR NON STANDART
2.2.1 PEKERJAAN STRUKTUR BAWAH 1,359,393,217.98 11.784 0.500 1.090 1.915 2.100 2.180 2.000 2.000 25.037
2.2.2 PEKERJAAN STRUKTUR GROUND WATER TANK & RUMAH POMPA 248,396,955.32 2.153
D PEKERJAAN STRUKTUR SEPTITANK (STP) 2 BH 41,554,089.47 0.360 23.066
2.B2 PEKERJAAN ARSITEKTUR NON STANDART
21.204
B.1. PEK. PERKERASAN KELILING BAGIAN LUAR BANGUNAN 296,207,149.20 2.568
B.2. PEKERJAAN DRAINASE KELILING BAGIAN LUAR BANGUNAN 19.729
18.896
I DRAINASE LUAR/SEKELILING BANGUNAN 106,866,952.85 0.926 Kurva
II BAK KONTROL 3,765,786.64 0.033 Realisasi 16.404
B.3. PEKERJAAN GROUND TANK DAN R. POMPA DI LUAR BANGUNAN 42,245,766.40 0.366
B.4 PEKERJAAN PAVING BLOCK LANTAI PARKIR SELASAR 103,297,432.85 0.895 14.708
B.5 PEKERJAAN LAIN - LAIN 34,256,000.00 0.297 13.244 0.059
B.6 Pengadaan dan pemasangan CCTV 23,950,000.00 0.208
B. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDAR 10.746
B.1. PEKERJAAN PEMADAM KEBAKARAN 9.656
I INSTALASI FIRE EXTINGUISHER 13,900,000.00 0.120 8.223
B.2 PEKERJAAN VENTILASI UDARA 61,585,159.00 0.534
B.3. PEKERJAAN INSTALASI ELEKTRONIK 6.615
6.020
I PEKERJAAN FIRE ALARM 50,185,898.00 0.435
B.4. PEKERJAAN SARANA DAN PRASARANA LINGKUNGAN (LUAR BANGUNAN) 3.695 3.898
I PEKERJAAN INSTALASI PLAMBING 348,763,072.19 3.023
1.681 1.961
II PENYAMBUNGAN DAYA PLN 85,250,000.00 0.739
0.848
III PEKERJAAN INSTALASI KABEL FEEDER 7,186,680.00 0.062
-0.000

Total Bobot 11,535,439,101.47 100.00


Progress Rencana Mingguan 0.848 1.113 1.937 2.123 2.203 2.523 3.963 5.021 5.308 6.240
Progress Rencana Komulatif Mingguan - 0.848 1.961 3.898 6.020 8.223 10.746 14.708 19.729 25.037 31.277
Progress Realisisasi Komulatif Mingguan - 1.681 3.695 6.615 9.656 13.24 16.40 18.90 21.20 23.066 28.02
Deviasi 0.832 1.734 2.717 3.635 5.021 5.658 4.187 1.475 (1.971) (3.260)

Disetujui oleh:
Direksi Teknis
SNVT Penyediaan Perumahaan
Provinsi Sumatera Utara

Medy Juliana, S.T


NIP. 19850715 201001 2 030
ELAKSANAAN PEKERJAAN

JANGKA WAKTU PELAKSANAAN = 133 HARI KALENDER


Nopember Desember
11 12 13 14 15 16 17 18 19 KET.
31 - 6/11 7 - 13/11 14 - 20/11 21 - 27/11 28 - 04/12 05 - 11/12 12 - 18/12 19 - 25/12 26-31/12

99.977 100.000

0.326 0.326 0.326


0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023

93.551

2.243
2.127 2.127 2.127
1.040 1.040 1.040
0.196 0.196 0.196
85.633
0.082 0.082 0.082
0.031 0.031 0.031 0.031
0.080 0.080 0.080 0.080
0.872 0.872 0.872

0.484 0.484
0.342 0.342 0.342 0.342 76.675
0.335 0.335 0.335 0.335
0.043 0.043

0.489 0.489 0.489 0.489 0.489 0.489


0.555 0.555 0.555 0.555 0.555 0.555 0.555
0.783 0.783 0.783 0.783 0.783 0.783 0.783
66.543
0.518 0.518 0.518 0.518
0.480 0.480
0.492
0.480
0.492
0.480
0.492
0.480
0.492 0.492
P
0.286 0.286 0.286 0.286 H
0.285 0.285
0.441
0.285
0.441
0.285
0.441 O
0.80456.058 0.804 0.804

0.129 0.129 0.129 0.129 0.129


0.149 0.149 0.149 0.149 0.149 0.149 0.149
0.208 0.208 0.208 0.208 0.208

0.235 0.235 0.235


47.165 0.210 0.210 0.210
45.670 0.271 0.271 0.271
45.670

0.048 0.048 0.048 0.048 0.048 0.048 0.048 0.048


0.059 0.059 0.059 0.059 0.059 0.059 0.059 0.059
0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016
0.00838.718 0.008 0.008 0.008 0.008 0.008 0.008 0.008
37.788
0.087 0.087 0.087 0.087 0.087 0.087 0.087
0.089 0.089 0.089 0.089 0.089 0.089 0.089
0.106 0.106 0.106 0.106 0.106 0.106 0.106
32.351 0.106 0.106 0.106 0.106 0.106 0.106 0.106
31.277 0.163 0.163 0.163 0.163 0.163 0.163 0.163
0.031 0.031 0.031 0.031 0.031
0.059 0.059 0.059 0.059 0.059
28.017

25.037
0.718 0.718 0.718
23.066 0.072 0.072 0.072 0.072 0.072
21.204
0.642 0.642 0.642 0.642
19.729
18.896
0.309 0.309 0.309
0.033
16.404
0.183 0.183
14.708 0.298 0.298 0.298
4 0.059 0.059 0.059 0.059
0.104 0.104
10.746

0.020 0.020 0.020 0.020 0.020 0.020


0.089 0.089 0.089 0.089 0.089 0.089

0.073 0.073 0.073 0.073 0.073 0.073

0.605 0.605 0.605 0.605 0.605


0.370 0.370
0.016 0.016 0.016 0.016

7.441 6.952 10.389 10.485 10.132 8.958 7.918 6.426 0.023


38.718 45.670 56.058 66.543 76.675 85.633 93.551 99.977 100.000
32.35 37.79 47.17
(6.367) (7.882) (8.893)

Medan, 20 November 2019


Dibuat oleh Kontraktor Pelaksana
PT. Laris Trio Bersaudara

Mentor Hasibuan, S.T


Site Manager
JADWAL PENGADAAN BAHAN

Pekerjaan
Lokasi
Kabupaten

MINGGU
NO. NAMA BAHAN TOTAL SATUAN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
A TIMBUNAN / PASIR
1 Pasir Timbun 31.70 M3 31.70
2 Pasir Pasang 116.93 M3 1.35 14.62 14.62 14.62 14.62 14.62 14.62
3 Pasir Beton 66.66 M3 6.67 6.67 6.67 6.67 6.67 6.67 6.67 6.67 6.67 6.67
B BAHAN PEREKAT
1 Portland Semen (PC) 51,741.55 Kg 315.00 3,449.44 3,449.44 3,449.44 3,449.44 3,449.44 3,449.44 3,449.44 3,449.44 3,449.44 3,449.44 3,449.44 3,449.44
2 Semen Warna 1,136.78 Kg
3 Semen Putih 18.00 Kg
4 Lem Kayu 19.72 Kg
5 Lem Kuning 41.21 Kg
C BATU / BATU BATA
1 Batu Pecah 2 -3 cm 110.21 M3 11.02 11.02 11.02 11.02 11.02 11.02 11.02 11.02 11.02 11.02
2 Batu Bata Biasa 29,964.20 Bh 270.00 9,988.07 9,988.07 9,718.07
3 Cone Block # 8 cm 5,030.08 Bh
4 Koral 1.35 m3 1.35
D KAYU
1 Kayu papan/broti ( setara kayu kuat kelas 2 ) 3.56 M3 1.78 1.78
2 Kayu papan/broti ( setara kayu kuat kelas 3 ) 38.12 M3 1.62 3.81 3.81 3.81 3.81 3.81 3.81 3.81 3.81 3.81 2.19
3 Rangka utama (main tee) 11,182.20 Btg
4 Rangka silang (cross tee) 21,399.19 Btg
5 rangka kedinding (wall angle) 10,829.89 Btg
6 Penggantung (adjustable hanger clip) 18,228.40 Bh
7 Pengikat (suspension rod) 3mm x 2400 mm 12,943.75 Bh
8 Braket sudut (angle bracket) 18,228.40 Bh
9 Kayu Dolken / Kayu Laut Ø 7.5 - 10 / 400 cm 1,447.72 Btg 144.77 144.77 144.77 144.77 144.77 144.77 144.77 144.77 144.77 144.77
10 Profil gipsum 4" 540.00 M'
11 Profil gipsum 2" 629.91 M'
12 Triplek 9 mm 176.20 Lbr 17.62 17.62 17.62 17.62 17.62 17.62 17.62 17.62 17.62 17.62
13 Gibsum Board uk. 120 x 240 cm tebal 9 mm 339.19 Lbr
14 GRC Board 6 mm 15.95 M2
15 Listplank GRC 24.40 Lbr
16 Triplek 4 mm 0.54 Lbr 0.54
E BESI / ALUMINIUM
1 Besi beton ulir 11,529.35 Kg 1,152.93 1,152.93 1,152.93 1,152.93 1,152.93 1,152.93 1,152.93 1,152.93 1,152.93 1,152.93
2 Besi Profil 1,208.37 Kg 9.90
3 Pintu Besi 8.42 M2 8.42
4 Kawat Besi Beton 188.62 Kg 18.86 18.86 18.86 18.86 18.86 18.86 18.86 18.86 18.86 18.86
5 Pintu swing coklat + kaca polos 8 mm,floor hinge Dorma BTS 84 8.00 Unit
6 Paku Biasa 253.73 Kg 7.65 25.37 25.37 25.37 25.37 25.37 25.37 25.37 25.37 25.37 17.72
7 Paku skrup 356.96 Kg 81.62 81.62 81.62
8 Jendela Aluminium coklat (60x120)cm + kaca polos 5 mm 56.00 Unit
9 Frame Aluminium Hollow 3,168.83 m'
10 Alumunium Composite Panel ( ACP ) 426.57 m2
11 Dinabolt dia.10 mm 3,250.08 Bh
12 Seallent 975.02 m'
13 Kosen aluminium 4" (coklat) 429.44 m'
14 Besi Hollow Galvanis 15.95 m2
15 Paku ramset 18,228.40 Bh
16 Paku beton 21,399.19 Bh
F PENUTUP LANTAI DAN DINDING
1 Keramik 20 x 20 cm 667.50 Bh
2 Keramik 20 x 25 cm 1,629.60 Bh
3 Granit 60 x 60 cm 1,910.03 Bh
4 Cone Block # 8 cm 5,030.08 Bh
5 Vinyl 15x92 cm (3.3 m2 / kotak) 21.86 Kotak

MINGGU
NO. NAMA BAHAN TOTAL SATUAN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

G PENUTUP ATAP
1 Atap Genteng Metal 0.30 951.15 Lbr
2 Rangka atap baja ringan 932.50 m2 310.83 310.83
3 Rabung Atap Genteng Metal 0.30 128.98 M'
4 Seng Pelat 3' x 6' BJLS 35 112.03 Lbr
5 Seng gelombang 7 kaki BJLS 20 13.50 Lbr 13.50
6 Aluminium Foil 932.50 m2
H PENGUNCI, PENGGANTUNG DAN KACA
1 Kunci Tanam 4" 15.00 Bh 2.00
2 Kunci Lock besar uk.4" 7.00 Bh
3 Handle ( pegangan jendela biasa ) 7.00 Bh
4 Engsel Pintu Nyilon 4" 30.00 Psg
5 Engsel Jendela Nyilon 3" 7.00 Psg
6 Hak Angin biasa 7.00 Psg
7 Pegangan pintu/Door Holder 11.00 Bh
8 Grendel Pintu / Jendela 3" 7.00 Bh
9 Kaca Polos tebal 5 mm 56.91 M2 0.72
10 Kaca Polos tebal 8 mm 41.80 M2
11 Jendela naco + rangka 7.49 m2 1.80
12 Door Closer 9.00 Bh
13 Stiker Sunblas 26.35 M2
I CAT TEMBOK / MINYAK
1 Cat Dasar 333.15 Kg
2 Cat Tembok Setara Vinilex 820.06 Kg
3 Cat Minyak / Perak (setara Bee Brand ) 59.45 Kg
4 Cat Menie Besi 1.68 Kg
5 Cat Menie kayu 27.65 Kg
6 Plamir 198.10 Kg
7 Terpentin ( Minyak Cat) 9.68 Kg
8 Minyak Bekisting 170.84 Ltr 17.08 17.08 17.08 17.08 17.08 17.08 17.08 17.08 17.08 17.08
9 Tepung Gybsum 159.64 Kg
10 Dempul 6.38 Kg
11 Amplas / kertas pasir 50.00 Lbr
12 Kuas 20.00 Bh
13 Flincote 54.12 Kg
J SANITASI / PIPA
1 Klosed Jongkok setara TOTO 4.00 Bh
2 Kran Air lokal 7.00 Bh
3 Floor Drain Ø 4" 5.00 Bh
4 Urinoir 3.00 Bh
5 Pipa PVC Tipe AW Ø 1/2" 34.80 M'
6 Pipa PVC Tipe AW Ø 4" 477.44 M'
7 Seal Tape 5.00 Bh
8 Wastafel setara TOTO 3.00 Bh
9 Bak cuci piring Stainles Steel 2 lobang koplet 1.00 unit
10 Klosed duduk setara TOTO 1.00 Bh
K LISTRIK / ACSESORIES
1 Lampu Down Light komplet 71.00 Set
2 Stop Kontak Tanam 25.00 Bh
3 Saklar Tunggal 19.00 Bh
4 Saklar dobel 14.00 Bh
5 Lampu Baret 8.00 Unit
6 Instalasi Listrik titik api / Lampu nyala 105.00 Ttk 13.00 13.00
7 Kabel NYM 3x2,5 mm 945.00 M' 117.00 117.00
8 Conduit 315.00 Btg 39.00 39.00
+ 3Hr
16 17 18 19 20 21

14.62 13.27

3,449.44 3,449.44 3,134.44


378.93 378.93 378.93
9.00 9.00
9.86 9.86
20.61 20.61

2,515.04 2,515.04

5,591.10 5,591.10
10,699.60 10,699.60
5,414.95 5,414.95
9,114.20 9,114.20
6,471.88 6,471.88
9,114.20 9,114.20

270.00 270.00
314.95 314.95

169.60 169.60
7.98 7.98
12.20 12.20

241.67 241.67 241.67 241.67 231.77

4.00 4.00

37.37 37.37 37.37


28.00 28.00
633.77 633.77 633.77 633.77 633.77
85.31 85.31 85.31 85.31 85.31
650.02 650.02 650.02 650.02 650.02
195.00 195.00 195.00 195.00 195.00
143.15 143.15 143.15
7.98 7.98
9,114.20 9,114.20
10,699.60 10,699.60

333.75 333.75
814.80 814.80
636.68 636.68 636.68
2,515.04 2,515.04
10.93 10.93

+ 3Hr
16 17 18 19 20 21

475.58 475.58
310.83
64.49 64.49
56.01 56.01

466.25 466.25

3.75 3.75 2.75 2.75


1.75 1.75 1.75 1.75
1.75 1.75 1.75 1.75
7.50 7.50 7.50 7.50
1.75 1.75 1.75 1.75
1.75 1.75 1.75 1.75
2.75 2.75 2.75 2.75
1.75 1.75 1.75 1.75
14.23 14.23 14.23 13.51
10.45 10.45 10.45 10.45
1.87 1.87 0.97 0.97
2.25 2.25 2.25 2.25
6.59 6.59 6.59 6.59

166.57 166.57
410.03 410.03
29.72 29.72
1.68
27.65
99.05 99.05
9.68
79.82 79.82
3.19 3.19
25.00 25.00
10.00 10.00
27.06 27.06

2.00 2.00
4.00 3.00
3.00 2.00
1.50 1.50
17.40 17.40
238.72 238.72
2.50 2.50
2.00 1.00
1.00
1.00

35.50 35.50
13.00 12.00
10.00 9.00
7.00 7.00
4.00 4.00
40.00 39.00
355.50 355.50
118.50 118.50
JADWAL PENGGUNAAN PERALATAN

Pekerjaan : Pembangunan PSD Permukiman Perdesaan Potensial Pariwisata Kawasan Muara


Lokasi : Kecamatan Muara Kabupaten Tapanuli Utara
Kabupaten : 2019

MINGGU
NO. NAMA ALAT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 Pick Up 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 Mesin Molen 2 2 2 2 2 2 2 2 2 2 2 2
3 Scafolding 20 20 20 20 20 20 20 20 20 20
4 Kereta Sorong 4 4 4 4 4 4 4 4 4 4 4 4 4 4
5 Mesin Las + Genset 1 1
6 Mesin Bor Tangan 2 2
7 Mesin Potong Keramik
8 VibratorConcrete 2 2 2 2 2 2 2 2 2 2 2 2
9 Water Pump 1 1
+ 3Hr
16 17 18 19 20 21

1 1 1 1 1 1
2 2 2
20 20 20 20 20 20
4 4 4 4 4 4
1 1 1 1 1
2 2 2 2 2
2 2 2
2 2 2