~ Diketahui :
~ L = 20 m
~ L1 = 1.1 m
~ t2 = 7 m
~ α = 35 o
~ Jarak kuda-kuda = 4 m
~ Desakan angin = 65 Kg/cm2
~ Bahan penutup atap = Spandek
~ PERHITUNGAN GORDING
Perhitungan
☺ panjang batang
Dik :
~ Panjang Batang = 22 m
~ Jarak Kap = 4 m
~ Tinggi Atap = 7 m
~ σ Angin = 65 Kg/m2
~ Jenis Atap = Spandek
7 12.3
☺ Tg α = ☺ Tg β =
11 11
= 0.6364 m = 1.1182 m
β = 9.7259 o
= 9o 43' 39,28'
α = 29.744 o
- 9.7259 o
= 20.0181
A S1 C
S21 = AL2 + AC2 - 2 . AL . AC . Cos 20.0181
= ( 1.253 ) 2
+ ( 1.0000 )
2
- 2 . 1.2527 . 1.0000 . 0.9396
= 1.569 - 2.35407384
= -0.785
= 0.7000 m
S11 S21
S2 D
A S1 C
M
S12 S24
L S22 S23
S11 S21 E
S2 D S3
A S1 C
S24 = AM2 + AE2 - 2 . AM . AE . Cos 20.0181
= ( 2.5054 ) 2
+ ( 1.0000 )2
- 2 . 2.5054 . 1.0000 . 0.9396
= 7.28 - 4.70814768
= 2.569
= 2.0668 m
N
S13
M S26
L S23
S11 S22 S4 F
S21 S2 D S3
E
A S1 C
S26 = AN2 + AF2 - 2 . AN . AF . Cos 20.0181
= ( 3.7581 ) 2
+ ( 1.0000 )2
- 2 . 3.7581 . 1.0000 . 0.9396
= 15.12 - 7.06222152
= 8.061
= 2.5104 m
O
S14
N
S13 S28
M S26 S27
L S23 S5 G
S11 S22 S4 F
S21 S2 D S3
E
A S1 C
S28 = AO2 + AG2 - 2 . AN . AG . Cos 20.0181
= ( 5.0108 ) 2
+ ( 1.0000 )
2
- 2 . 5.0108 . 1.0000 . 0.9396
= 26.11 - 9.41629536
= 16.692
= 3.0511 m
S1 dan S10 m
BATANG BAWAH
S2 dan S9 m
S3 dan S8 m
S4 dan S7 m
S5 dan S6 m
S29 3.5
BATANG DIAGONAL
S22 dan S36 1.7949
PERHITUNGAN BEBAN
☺ Beban Mati
Jarak kap/kuda-kuda = 4 m
Berat Atap seng Gelombang (g) = 10 Kg/m2
Keimiringan Atap (α) = 35 o
Perhitungan Beban
qx1 = q . Sin 35 Dimana q = 10 . Jarak Gording
= 13.9188889 . 0.5735 = 10 . 1.392
= 7.9825 Kg/m = 13.91889
qy1 = q . Cos 35
= 13.9188889 . 0.8191
= 11.4009619 Kg/m
☺ Beban Angin
Tekanan tiup angin di laut dan tepi laut sampai sejauh 5 km dari tepi pantai harus diambil
minimum 40 Kg/m2
Koefisien angin tekan
C1 = 0.02 . α - 0.4
= 0.02 . 35 - 0.4
= 0.3
Perhitungan Beban
qy2 = C1 . Jarak Gording . Desakan angin (w)
= 0.3 . 1.392 . 65
= 27.1418 Kg/m
Mx2 = 0
☺ Beban Hidup
Beban Hidup ( P ) diambil 100 kg
Px3 = P . Sin 35
= 100 . 0.5735
= 57.3500 Kg/m
Py3 = P . Cos 35
= 100 . 0.8191
= 81.91 Kg/m
☺ Beban Gording
Berat Gording digunakan profil CNP 16 dengan berat 18.8 kg
b
e
q sin α
h q q Cos α
Perhitungan Beban
qx4 = q . Sin 35
= 18.8 . 0.5735
= 10.7818 Kg/m
qy4 = q . Cos 35
= 18.8 . 0.8191
= 15.39908 Kg/m
r
d
e b/2
My = 135.5100838 kgm
= 13551.00838 kgcm
Kontrol tegangan
Dengan mutu baja st 34 diperoleh σa = 1400 Kg/cm2
Karena digunakan profil CNP 16
maka dari tabel baja diperoleh :
Wx = 116
Wy = 18.3
Mx My
σ ytd = +
Wx Wy
10990.67878 13551.008
= +
116 18.3
= 94.74723084 + 740.49226
= 835.2394919 < 1400 Kg/cm2
Kontrol tegangan
Dari tabel profil baja untuk profil diperoleh
Ix = 925 cm
Iy = 85.3 cm
qx1 = 10.002 kg/m
qy1 = 17.504 kg/m
Px3 = 20.004 kg/m
Py = 35.008 kg/m
E = 2.1 . 10.6 kg/m
Lendutan yang terjadi diakibatkan oleh beban mati (beban merata ) dan beban hidup ( beban terpusat )
dimana lendutan ini harus lebih kecil dari lendutan yang diizinkan ( f ) penjumlahan lendutan yang
diakibatkan oleh beban didfasarkan arah sumbu
Ledutan searah sumbu x
5 . qx . L4 Px . L3
fx = +
384 . E . Iy 48 . E . Iy
5 . 0.10002 . 400 4 20.004 400 3
= +
384 . 2.1 . 10 .6
. 85.3 48 . 2.1 . 10.6 . 85.3
12802560000 1280256000
= +
68785920000 8598240000
= 0.1861 + 0.1488974
= 0.3350 cm
PERHITUNGAN KUDA-KUDA
☺ Beban Atap ( Pa )
Digunakan atap seng asbes dengan berat sendiri = 10 Kg/m2
Pa = qa . C . Jarak gording
= 10 . 4 . 1.392
= 55.67555556 kg
☺ Beban Gording ( Pb )
Dalam hal ini digunakan profil yang telah memenuhi syarat yaitu profil CNP 16
qb = 18.8 kg/m. Maka beban gording adalah
Pb = qb . C .
= 18.8 . 4
= 75.2 kg
☺ Berat kuda-kuda
Dalam menentukan berat kuda-kuda untuk tiap titik simpul dengan reumus empiris
( L + 2 s/d 5 ) L . C
Pk =
n-1
( 20 + 5 ) 20 . 4
=
11 - 1
= 200
Jadi beban tetap yang terjadi pada titik simpul L, M N O P Q R S T
Pt = Pa + Pb + Pk
= 55.67555556 + 75.2 + 200
= 330.8755556 kg
PTP
PTO PTQ
P
PTN
Q
O PTR
PTM PTS
N R
PTL M
PTA
L
G
E F H I
D J
C
A
Pembebanan Untuk Muatan Tetap
RA
☺ Beban Hidup
Untuk Tiap Tiap Titik Simpul = 100 kg
11 . P
RA = RB =
2
11 . 100
=
2
= 550 Kg
PP
PO PQ
P
PN
Q
O PR
PM PS
N R
PL M
PA
L
G
E F H I
D J
C
A
Pembebanan Untuk Muatan Hidup
RA
☺ Beban Hidup
Tekanan angin kiri ( w ) = 60 Kg/m2
Angin Tekan
Nilai koefisien yang digunakan C1 = 0.194
Beban yang bekerja adalah :
WtA = 0.194 . 60 . 4 . ( 1/2 . 1.253 )
= 29.162856
Angin Isap
Nilai koefisien yang digunakan C1 = -0.4
Beban yang bekerja adalah :
WiP = -0.4 . 60 . 4 . ( 1/2 . 1.253 )
= -60.1296
WIP WTP
WIO WTQ
P
WIN
Q
O WTR
WIM WTS
N R
WIL M
WIA
L
G
E F H I
D J
C
A
RA
Angin Isap
Nilai koefisien yang digunakan C2 = -0.4
Beban yang bekerja adalah :
WiP = -0.4 . 60 . 4 . ( 1/2 . 1.253 )
= -60.1296
PTP
PTO PTQ
P
PTN
Q
O PTR
PTM PTS
N R
PTL M
PTA
L
G
E F H I
D J
C
A
MUATAN TETAP
RA
PP
PO PQ
P
PN
Q
O PR
PM PS
N R
PL M
PA
L
G
E F H I
D J
C
A
MUATAN HIDUP
RA
WIP WTP
WIO WTQ
P
WIN
Q
O WTR
WIM WTS
N R
WIL M
WIA
L
G
E F H I
D J
D J
C
A
ANGIN KANAN
RA
WTP WIP
WTO WIQ
P
WTN
Q
O WIR
WTM WIS
N R
WTL M
WTA
L
G
E F H I
D J
C
A
ANGIN KIRI
RA
WTL 58.3257
WTM 58.3257
WTN 58.3257
WTO 58.3257
WTP 29.1629
WIP -60.1296
WIQ
ANGIN ISAP
-120.2592
WIR -120.2592
WIS -120.2592
WIT -120.2592
WIB -60.1296
WTB 29.1629
ANGIN TEKAN
ANGIN TEKAN
WTT 58.3257
WTS 58.3257
WTR 58.3257
WTQ 58.3257
WTP 29.1629
WIP -60.1296
WIO
ANGIN ISAP
-120.2592
WIN -120.2592
WIM -120.2592
WIL -120.2592
WIA -60.1296
MENDIMENSI BATANG
A. Batang Atas
Digunakan profil tersususn yang sama untuk semua batang atas. Jadi yang meentukan adalah gaya
batang Max pada batang atas.
Dik : P Max = 4950 Kg = 4.95 ton
LK = 1.2527 m = Lx = Ly = 125.27 cm
σa = 1200 Kg/m
Lk 125.27
λx = = = 64.57216495 αx = 0.3926
ix 1.94
Lk 125.27
λy = = = 64.57216495 αy = 0.3926
iy 1.94
191.25702 191.25702
Iy fiktif = = = 8.6935009091 = 2.9485 cm
2 . F 2 . 11
Ly 125.27
λy fiktif = = = 42.48644212 αy fik = 0.6843
iy fik 2.9485
Jadi untuk memenuhi agar profil tersusun yangkita gunakan dapat menerima beban tersusun, maka
batang atau panjang tekuk diperpendek dengan memberi koppel.
Py = αy fik . αy1 . F . σa
Py
αy1 =
αy fik . F . σa
4950
=
0.6843 .( 2 . 11 ) . 1200
4950
=
18065.52
= 0.2740
dari tabel didapat λy1 = 124.3
Ly1 = λy 1 - iy 1
= 124.3 - 1.94
= 122.360
125.27
Banyaknya tegangan "n" =
122.360
= 1.0238 dipakai 3 lapangan
σtk = αy fik . α1 . σa
= 0.6843 . 0.8198 . 1200
= 673.186968 Kg/m2
Perhitungan Koppel
Profil 65 . 65 . 9 dengan Ø baut = 2 cm Tebal Plat Koppel f
Pada saat terjadinya bahaya tekuk akan terjadi gaya geser dalam arah memanjang sebesar
D . LK
L =
2 . a
D = 0.015 . P
= 0.015 . 4950
= 74.25 kg
74.25 . 41.756667
L =
4.86
= 637.9490741 kg
C1 2 d
C h 5 d
C1 2 d
C1 = Ø . 2 C = Ø . 5
= 2 . 2 = 2 . 5
= 4 cm = 10 cm
Mmax = L . 1/2 . ln
= 637.9490741 . 1/2 [ ( 2 . w )+ t ]
= 637.9490741 . 1/2 [ 2 . 4.6 ) + 1 ]
= 3253.540278
I Bruto = 1/12 . b . h3
= 1/12 . 0.5 . 18 3
= 243 cm4
I perlemahan = 2 . d . b ( C/2 )2
= 2 . 2 . 0.5 ( ### / 2 )2
= 50
I netto 193
Wn = = = 21.4444444444 cm3
1/2 h 1/2 . ###
Tegangan yang terjadi
Mmax 3253.5403
T = = = 151.719 < σa = 1200
Wn 21.4444
Lk 305.1139
λx = = = 179.4787647 αx = 0.1346
ix 1.7
Lk 305.1139
λy = = = 179.4787647 αy = 0.1346
iy 1.7
28.5727032 28.5727032
Iy fiktif = = = 3.7694859103 = 1.9415 cm
2 . F 2 . 3.8
Ly 305.1139
λy fiktif = = = 157.1523686 αy fik = 0.6843
iy fik 1.9415
Jadi untuk memenuhi agar profil tersusun yangkita gunakan dapat menerima beban tersusun, maka
batang atau panjang tekuk diperpendek dengan memberi koppel.
Py = αy fik . αy1 . F . σa
Py
αy1 =
αy fik . F . σa
1043
=
0.6843 .( 2 . 3.79 ) . 1200
1043
=
6224.3928
= 0.168
dari tabel didapat λy1 = 158.5
Ly1 = λy 1 - iy 1
= 158.5 - 1.7
= 156.800
305.1139
Banyaknya tegangan "n" =
156.800
= 1.9459 dipakai 3 lapangan
σtk = αy fik . α1 . σa
= 0.6843 . 0.516 . 1200
= 423.71856 Kg/m2
Perhitungan Koppel
Profil 40 . 40 . 5 dengan Ø baut = 1.1 cm Tebal plat koppel
Pada saat terjadinya bahaya tekuk akan terjadi gaya geser dalam arah memanjang sebesar
D . LK
L =
2 . a
D = 0.015 . P
= 0.015 . 1043
= 15.645 kg
15.645 . 101.70463
L =
3.32
= 479.2677676 kg
C1 2 d
C h 5 d
C1 2 d
C1 = Ø . 2 C = Ø . 5
= 1.1 . 2 = 1.1 . 5
= 2.2 cm = 5.5 cm
Mmax = L . 1/2 . ln
= 479.2677676 . 1/2 [ ( 2 . w )+ t ]
= 479.2677676 . 1/2 [ 2 . 2.83 ) + 1 ]
= 1595.961666
I Bruto = 1/12 . b . h3
= 1/12 . 0.5 . 15 3
= 140.625 cm4
I perlemahan = 2 . d . b ( C/2 )2
= 2 . 1.1 . 0.5 ( 5.5 / 2 )2
= 8.31875
I netto 132.30625
Wn = = = 17.640833333 cm3
1/2 h 1/2 . 15
C Batang Vertikal
Digunakan profil tersususn yang sama untuk semua batang atas. Jadi yang meentukan adalah gaya
batang Max pada batang atas.
Dik : P ekstrim = 2356 Kg
LK = 3.5 m
σa = 1200 Kg/m
Dalam mendefinisikan batang tarik digunakan luas penampang bersih ( F netto) dan tegangan tarik yang
diizinkan maximal 0.75 x Tegangan dasar
σtk = 0.75 . 1600 kg/cm2
= 1200 kg/cm2
2356
Fperlu =
1200
= 1.9633 cm2
Untuk profil 45 . 45 . 5 dengan perlemahan baut Ø 1.4 cm dengan data Sbb:
Ix : Iy = 7.83 Cm4 Y
ix : iy = 1.35 Cm
t = 0.5 Cm2
Fb = 4.3 Cm X
Sehingga Fnetto = Fb - n . t . d
= 4.3 - 2 . 0.5 . 1.4
= 2.9 > 1.9633
2356
σ ytd =
2.9
B Batang Bawah
Digunakan profil tersususn yang sama untuk semua batang atas. Jadi yang meentukan adalah gaya
batang Max pada batang atas.
Dik : P ekstrim = 4356 Kg
LK = m m
σa = 1200 Kg/m
Dalam mendefinisikan batang tarik digunakan luas penampang bersih ( F netto) dan tegangan tarik yang
diizinkan maximal 0.75 x Tegangan dasar
σtk = 0.75 . 1600 kg/cm2
= 1200 kg/cm2
4356
Fperlu =
1200
= 3.6300 cm2
Untuk profil 65 . 65 . 11 dengan perlemahan 2 baut Ø 2 cm dengan data sebagai be
Ix : Iy = 48.8 Cm4 Y
ix : iy = 1.91 Cm
t = 1.1 Cm2
Fb = 13.2 Cm X
Sehingga Fnetto = Fp - n . t' . d
= 13.2 - 2 . 1.1 . 1.4
= 10.12 > 3.6300
4356
σ ytd = = 430.4347826
10.12
PERHITUNGAN SAMBUNGAN
4.5 9 4.5
e = 1.93
w = 3.5
c = w - e = 3.5 - 1.93 = 1.57 Cm
t = 10 cm
Untuk 1 Baut
P 4950
N = = = 2475 Kg
2 2
Gaya Maksimum yang diterima 1 Baut
R = V 2 + N 2
= 777.15 2 + 2475 2
= 6729587.1225
= 2594.144777
Tegangan Desak yang terjadi
R
σ s =
dmin . d
2594.144777
=
1 . 2
= 1441.1915 Kg/cm2
σs = 2 . σa
= 2 . 1200
= 2400 Kg/cm2
Batang No.1
65 . 65 . 11
P = 4356 Kg
Sambungan bertampang Dua tebal plat buhul d min = 1 cm
Lawan tebal profil 2 . 1.1 = 2.2 cm
Harga batas
q = 1.6 dmin = 1.6 . 1 = 1.6 < Ø baut = 2.2 cm
Jadi perhitungan berdasarkan desakan
Pds = dmin . d . σa
= 1 . ( 2 . 2 ) . 1200
= 5280 Kg
5.5 11 5.5
e = 2
w = 3.5
c = w - e = 3.5 - 2 = 1.5 Cm
t = 10 cm
Sambungan dalam keadaan seimbang
P . c
V =
t
4356 1.5
=
10
= 653.4
Untuk 1 Baut
P 4356
N = = = 2178 Kg
2 2
σs = 2 . σa
= 2 . 1200
= 2400 Kg/cm2
4.5 9 4.5
e = 1.93
w = 3.5
c = w - e = 3.5 - 1.93 = 1.57 Cm
t = 10 cm
Untuk 1 Baut
P 4420
N = = = 2210 Kg
2 2
σs = 2 . σa
= 2 . 1200
= 2400 Kg/cm2
Batang No.22
40 . 40 . 5
P = 624 Kg
Sambungan bertampang Dua tebal plat buhul d min = 1 cm
Lawan tebal profil 2 . 0.5 = 1 cm
Harga batas
q = 1.6 dmin = 1.6 . 1 = 1.6 < Ø baut = 1 cm
Jadi perhitungan berdasarkan desakan
Pds = dmin . d . σa
= 1 . ( 2 . 1 ) . 1200
= 2400 Kg
2.5 5 2.5
e = 1.16
w = 2.2
c = w - e = 2.2 - 1.16 = 1.04 Cm
t = 10 cm
σs = 2 . σa
= 2 . 1200
= 2400 Kg/cm2
4.5 9 4.5
e = 1.93
w = 3.5
c = w - e = 3.5 - 1.93 = 1.57 Cm
t = 10 cm
Untuk 1 Baut
P 3890
N = = = 1945 Kg
2 2
Gaya Maksimum yang diterima 1 Baut
R = V 2 + N 2
= 610.73 2 + 1945 2
= 4156016.1329
= 2038.630946
Tegangan Desak yang terjadi
R
σ s =
dmin . d
2038.630946
=
1 . 2
= 1132.5727 Kg/cm2
σs = 2 . σa
= 2 . 1200
= 2400 Kg/cm2
Batang No.24
40 . 40 . 5
P = 706 Kg
Sambungan bertampang Dua tebal plat buhul d min = 1 cm
Lawan tebal profil 2 . 0.5 = 1 cm
Harga batas
q = 1.6 dmin = 1.6 . 1 = 1.6 < Ø baut = 1.1 cm
Karena q > Diameter baut
Jadi perhitungan berdasarkan desakan
Pgs = 2 . 1/4 . π . d2 . σ
= 2 . 1/4 . 3.14 . 1.1 2 . ( 0.8 . 1200 )
= 1823.712
e = 1.16
w = 2.2
c = w - e = 2.2 - 1.16 = 1.04 Cm
t = 10 cm
Untuk 1 Baut
P 706
N = = = 353 Kg
2 2
Gaya Maksimum yang diterima 1 Baut
R = V 2 + N 2
= 73.424 2 + 353 2
= 130000.083776
= 360.5552
σs = 2 . σa
= 2 . 1200
= 2400 Kg/cm2
3.5 7 3.5
e = 1.28
w = 2.5
c = w - e = 2.5 - 1.28 = 1.22 Cm
t = 10 cm
Untuk 1 Baut
P 168
N = = = 84 Kg
2 2
σs = 2 . σ
= 2 . 1200
= 2400 Kg/cm2
Batang No.3
65 . 65 . 11
P = 3886 Kg
Sambungan bertampang Dua tebal plat buhul d min = 1 cm
Lawan tebal profil 2 . 1.1 = 2.2 cm
Harga batas
q = 1.6 dmin = 1.6 . 1 = 1.6 < Ø baut = 2 cm
Jadi perhitungan berdasarkan desakan
Pds = dmin . d . σa
= 1 . ( 2 . 2 ) . 1200
= 4800 Kg
5 10 5
e = 2
w = 3.5
c = w - e = 3.5 - 2 = 1.5 Cm
t = 10 cm
Sambungan dalam keadaan seimbang
P . c
V =
t
3886 1.5
=
10
= 582.9
Untuk 1 Baut
P 3886
N = = = 1943 Kg
2 2
σs = 2 . σa
= 2 . 1200
= 2400 Kg/cm2
3.5 7 3.5
e = 1.28
w = 2.5
c = w - e = 2.5 - 1.28 = 1.22 Cm
t = 10 cm
Untuk 1 Baut
P 486
N = = = 243 Kg
2 2
σs = 2 . σa
= 2 . 1200
= 2400 Kg/cm2
Batang No.4
65 . 65 . 11
P = 3416 Kg
Sambungan bertampang Dua tebal plat buhul d min = 1 cm
Lawan tebal profil 2 . 1.1 = 2.2 cm
Harga batas
q = 1.6 dmin = 1.6 . 1 = 1.6 < Ø baut = 2 cm
Jadi perhitungan berdasarkan desakan
Pds = dmin . d . σa
= 1 . ( 2 . 2 ) . 1200
= 4800 Kg
5 10 5
e = 2
w = 3.5
c = w - e = 3.5 - 2 = 1.5 Cm
t = 10 cm
σs = 2 . σa
= 2 . 1200
= 2400 Kg/cm2
5 10 5
e = 1.93
w = 3.5
c = w - e = 3.5 - 1.93 = 1.57 Cm
t = 10 cm
σs = 2 . σa
= 2 . 1200
= 2400 Kg/cm2
Batang No.26
40 . 40 . 5
P = 861 Kg
Sambungan bertampang Dua tebal plat buhul d min = 1 cm
Lawan tebal profil 2 . 1 = 2 cm
Harga batas
q = 1.6 dmin = 1.6 . 1 = 1.6 < Ø baut = 1.1 cm
Karena q > Diameter baut
Jadi perhitungan berdasarkan geser
Pgs = 2 . 1/4 . π . d2 . σ
= 2 . 1/4 . 3.14 . 1.1 2 . ( 0.8 . 1200 )
= 1823.712
Banyaknya baut yang digunakan
P 861
N = = = 0.4721 Digunakan 2 baut
Pds 1823.712
e = 1.16
w = 2.2
c = w - e = 2.2 - 1.16 = 1.04 Cm
t = 10 cm
Sambungan dalam keadaan seimbang
P . c
V =
t
861 1.04
=
10
= 89.544
Untuk 1 Baut
P 861
N = = = 430.5 Kg
2 2
σs = 2 . σa
= 2 . 1200
= 2400 Kg/cm2
5 10 5
e = 1.93
w = 3.5
c = w - e = 3.5 - 1.93 = 1.57 Cm
t = 10 cm
Untuk 1 Baut
P 2824
N = = = 1412 Kg
2 2
σs = 2 . σa
= 2 . 1200
= 2400 Kg/cm2
Batang No.28
40 . 40 . 5
P = 1043 Kg
Sambungan bertampang Dua tebal plat buhul d min = 1 cm
Lawan tebal profil 2 . 0.5 = 1 cm
Harga batas
q = 1.6 dmin = 1.6 . 1 = 1.6 < Ø baut = 1.1 cm
Karena q > Diameter baut
Jadi perhitungan berdasarkan geser
Pgs = 2 . 1/4 . π . d2 . σ
= 2 . 1/4 . 3.14 . 1.1 2
. ( 0.8 . 1200 )
= 1823.712
Banyaknya baut yang digunakan
P 1043
N = = = 0.5719 Digunakan 2 baut
Pds 1823.712
e = 2
w = 3.5
c = w - e = 3.5 - 2 = 1.5 Cm
t = 10 cm
Untuk 1 Baut
P 1043
N = = = 521.5 Kg
2 2
σs = 2 . σa
= 2 . 1200
= 2400 Kg/cm2
3.5 7 3.5
e = 1.28
w = 2.5
c = w - e = 2.5 - 1.28 = 1.22 Cm
t = 10 cm
Untuk 1 Baut
P 720
N = = = 360 Kg
2 2
Batang No.5
65 . 65 . 11
P = 2942 Kg
Sambungan bertampang Dua tebal plat buhul d min = 1 cm
Lawan tebal profil 2 . 1.1 = 2.2 cm
Harga batas
q = 1.6 dmin = 1.6 . 1 = 1.6 < Ø baut = 2 cm
Jadi perhitungan berdasarkan desakan
Pds = dmin . d . σa
= 1 . ( 2 . 2 ) . 1200
= 4800 Kg
5 10 5
e = 2
w = 3.5
c = w - e = 3.5 - 2 = 1.5 Cm
t = 10 cm
Untuk 1 Baut
P 2942
N = = = 1471 Kg
2 2
σs = 2 . σa
= 2 . 1200
= 2400 Kg/cm2
3.5 7 3.5
e = 1.28
w = 2.5
c = w - e = 2.5 - 1.28 = 1.22 Cm
t = 10 cm
Untuk 1 Baut
P 2354
N = = = 1177 Kg
2 2
Gaya Maksimum yang diterima 1 Baut
R = V 2 + N 2
= 287.188 2 + 1177 2
= 1467805.947344
= 1211.530415
σs = 2 . σa
= 2 . 1200
= 2400 Kg/cm2
Reaksi perletakan yang paling besar adalah juga akibat Beban Sendiri + beban berguna. Jadi =
RAmax = RABeban Sendiri + RABeban Hidup
= 1691.977778 + 1100
= 2791.977778 Kg
Terkanan konstruksi kap ( kuda-kuda) diteruskan pada plat kaki dengan melalui baja sudut kaki,
sedangkan pada kedua sisi siku pada profil siku yang mendatar diikat dengan bujur sangkar.
D
F =
T
1063.9926
=
0.7 1200
= 1.266657848 cm2
F = 1/4 . π . d2 4 . F
d =
π
4 .1.2666578
=
3.14
= 1.6135768768
= 1.2703
tp . h 1/2 h - tp . Ø1 . xi - tp . Ø2 . xii
Titik Berat =
Fnetto
1 . 24 . 1/2 24 - 1 . 2 . 3.66 - 1 . 2
=
20.0
258
=
20.0
= 12.9 cm
y = 1/2 . h
= 1/2 . 24
= 12 cm
e = Titik Berat - y
= 12.9 - 12
= 0.900
I Bruto = 1/2 . t . h3 + t . h . e2
= 1/2 . 1 . 24 3 + 1 . ### . 0.9 2
= 6931.44 cm4
I netto
wn =
1/2 . h
7071.4224
=
12
= 589.2852 cm3
tp . h 1/2 h - tp . Ø1 . xi - tp . Ø2 . xii
Titik Berat =
Fnetto
1 . 19.35 . 1/2 19.35 - 1 . 2 . 3.6 - 1 . 1.4
=
16.0
166.15125
=
16.0
= 10.41700627 cm
I Bruto = 1/2 . t . h3
= 1/2 . 1 . 19.35 3
= 3622.538 cm4
I netto
wn =
1/2 . h
3696.450188
=
9.675
= 382.0620349 cm3
I Bruto = 1/2 . t . h3
= 1/2 . 1 . 18.75 3
= 3295.898 cm4
I netto
wn =
1/2 . h
3370.492575
=
9.375
= 359.519208 cm3
tp . h 1/2 h - tp . Ø1 . xi - tp . Ø2 . xii
Titik Berat =
Fnetto
1 . 21.60 . 1/2 21.60 - 1 . 2 . 3.36 - 1 . 1.4
=
18.200
211.44
=
18.200
= 11.61758242 cm
I Bruto = 1/2 . t . h3
= 1/2 . 1 . 21.60 3
= 5038.848 cm4
I netto
wn =
1/2 . h
5151.348
=
10.8
= 476.9766667 cm3
tp . h 1/2 h - tp . Ø1 . xi - tp . Ø2 . xii
Titik Berat =
Fnetto
1 . 20.45 . 1/2 20.45 - 1 . 2 . 3.7 - 1 . 1.1
=
17.350
189.82125
=
17.350
= 10.94070605 cm
I Bruto = 1/2 . t . h3
= 1/2 . 1 . 20.45 3
= 4276.121 cm4
I netto
wn =
1/2 . h
4361.6355
=
10.225
= 426.5658191 cm3
tp . h 1/2 h - tp . Ø1 . xi - tp . Ø2 . xii
Titik Berat =
Fnetto
1 . 21.60 . 1/2 21.60 - 1 . 2 . 3.9 - 1 . 1.4
=
18.200
210.36
=
18.200
= 11.55824176 cm
I Bruto = 1/2 . t . h3
= 1/2 . 1 . 21.60 3
= 5038.848 cm4
tp . h 1/2 h - tp . Ø1 . xi - tp . Ø2 . xii
Titik Berat =
Fnetto
1 . 20.55 . 1/2 20.55 - 1 . 2 . 3.6 - 1 . 1.1
=
17.450
192.07125
=
17.450
= 11.00694842 cm
I Bruto = 1/2 . t . h3
= 1/2 . 1 . 20.55 3
= 4339.158 cm4
I Perlemahan = tp . Ø1 ( h/2 - xi )2 + tp . Ø2 ( h/2 - xii )2
= 1 . 2 ( 20.55 /2 - 3.6 )2 + 1 . 1.1 ( 20.55
= 89.4144375 cm4
I netto
wn =
1/2 . h
4428.572625
=
10.275
= 431.004635 cm3
tp . h 1/2 h - tp . Ø1 . xi - tp . Ø2 . xii
Titik Berat =
Fnetto
1 . 21.60 . 1/2 21.60 - 1 . 2 . 5.25 - 1 . 1.4
=
=
18.200
207.24
=
18.200
= 11.38681319 cm
I Bruto = 1/2 . t . h3
= 1/2 . 1 . 21.60 3
= 5038.848 cm4
I netto
wn =
1/2 . h
5100.579
=
10.8
= 472.2758333 cm3
tp . h 1/2 h - tp . Ø1 . xi - tp . Ø2 . xii
Titik Berat =
Fnetto
1 . 23.40 . 1/2 23.40 - 1 . 2 . 3.5 - 1 . 1.4
=
20.000
251.38
=
20.000
= 12.569 cm
I Bruto = 1/2 . t . h3
= 1/2 . 1 . 23.40 3
= 6406.452 cm4
I netto
wn =
1/2 . h
6541.618
=
11.7
= 559.1126496 cm3
tp . h 1/2 h - tp . Ø1 . xi - tp . Ø2 . xii
Titik Berat =
Fnetto
1 . 21.90 . 1/2 21.90 - 1 . 2 . 3.45 - 1 . 1.4
=
18.500
218.205
=
18.500
= 11.79486486 cm
I Bruto = 1/2 . t . h3
= 1/2 . 1 . 21.90 3
= 5251.730 cm4
I netto
wn =
1/2 . h
5364.513
=
10.95
= 489.909863 cm3
tp . h 1/2 h - tp . Ø1 . xi - tp . Ø2 . xii
Titik Berat =
Fnetto
1 . 20.70 . 1/2 20.70 - 1 . 2 . 3.75 - 1 . 1.1
=
17.600
195.855
=
17.600
= 11.128125 cm
I Bruto = 1/2 . t . h3
= 1/2 . 1 . 20.70 3
= 4434.872 cm4
I netto
wn =
1/2 . h
4522.21425
=
10.35
= 436.928913 cm3
m
4
12.3 m
,55,56,57,58,59,60 adalah :
18,19,20 adalah :
uyhjgh
najang Batang
1.2527
1.2527
1.2527
1.2527
1.2527
0.7
1.4
2.1
2.1
2.8
3.5
1.7949
2.0668
2.5104
3.0511
Jarak Gording
r1
X
r1
b/2
85.3
925
16 dengan berat
P
55.6755556
150.4
200
406.075556
406.075556 )]
PTS
S
PTT
T
PTB
J K
RB
PS
S
PT
T
PB
J K
B
RB
1.253 )
1.253 )
1.253 )
1.253 )
1.253 )
1.253 )
1.253 )
1.253 )
WTS
S WTT
T
WTB
J K
RB
1.253 )
1.253 )
1.253 )
1.253 )
1.253 )
1.253 )
1.253 )
1.253 )
PTS
S
PTT
T
PTB
J K
RB
PS
S
PT
T
PB
J K
RB
WTS
S WTT
T
WTB
J K
J K
RB
WIS
S WIT
T
WIB
J K
RB
65
e
###
maka
= 0.5 cm
40
e
###
a
maka
f = 0.5 cm
dengan data Sbb:
dengan data sebagai berikut
1 cm
1 cm
4420 Kg
1 cm
1 cm
3890 Kg
1 cm
168 Kg
1 cm
486 Kg
1 cm
3360 Kg
1 cm
2824 Kg
1 cm
720 Kg
at buhul d min = 1 cm
1 cm
2354 Kg
n berguna. Jadi =
2.3 cm
2 . 11.34
24 /2 - 11.34 )2
1.4 . 9.90
19.35 /2 - 9.9 )2
1.1 . 10.80
18.75 /2 - 10.8 )2
1.4 . 10.80
21.60 /2 - 10.8 )2
1.1 . 10.80
20.45 /2 - 10.8 )2
1.4 . 10.80
21.60 /2 - 10.8 )2
1.1 . 10.80
20.55 /2 - 10.8 )2
1.4 . 11.10
21.60 /2 - 11.1 )2
1.4 . 11.00
23.40 /2 - 11 )2
1.4 . 10.50
21.90 /2 - 10.5 )2
1.1 . 9.90
20.70 /2 - 9.9 )2