Type 220 Ok Fix-Akhmad - Ikram
Type 220 Ok Fix-Akhmad - Ikram
IV PEKERJAAN ARSITEKTUR
Makassar,..........................2019
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : PEMBANGUNAN RUMAH TYPE 220
LOKASI : AEROHOME ESTATE, BIRINGKANAYA
TAHUN : 2020
I PEKERJAAN PERSIAPAN
1 Pek. Pengukuran Dan Bouwplank 1.00 Ls Rp 500,000.00 Rp 500,000.00
Rp 500,000.00
II PEKERJAAN TANAH DAN STRUKTUR BAWAH
1 Pek. Tanah Dan Pondasi Batu Gunung
- Pek. Galian Tanah Pondasi Batu Gunung 159.44 m3 Rp 45,500.00 Rp 7,254,633.75
- Pek. Urugan Kembali Bekas Galian 68.29 m3 Rp 22,750.00 Rp 1,553,643.00
- Pek. Urugan Pasir Alas Pondasi 8.40 m3 Rp 196,700.00 Rp 1,652,280.00
- Pek. Batu Kosong Pondasi 16.80 m3 Rp 173,750.00 Rp 2,919,000.00
- Pek. Pondasi Batu Gunung, Camp. 1pc : 4ps 61.97 m3 Rp 462,050.00 Rp 28,633,700.55
Rp 42,013,257.30
Rp 38,296,176.49
Rp 80,309,433.79
Rp 17,009,545.30
2 Pekerjaan Kolom Beton Lt. 1
- Pek. Kolom Beton K1, Uk. 15 x 40 Cm 17.00 Bh
- Pek. Cor Beton (Readymix) (Beton K2225) 3.69 m3 Rp 760,000.00 Rp 2,806,224.00
- Pek. Penulangan Beton (min fy = 400 Mpa) 1,177.47 Kg Rp 10,214.00 Rp 12,026,644.75
- Pek. Bekisting 2x Pemakaian 67.69 m2 Rp 53,710.00 Rp 3,635,844.74
Rp 18,468,713.49
Rp 38,823,907.44
Rp 12,994,987.15
B PEKERJAAN STRUKTUR BETON LANTAI II (DUA)
1 Pekerjaan Ringbalk Lt. 2
- Pek. Ringbalk, RB Uk. 15 x 25 cm
- Pek. Cor Beton (Readymix) (Beton K225) 3.92 m3 Rp 760,000.00 Rp 2,975,400.00
- Pek. Penulangan Beton (min fy = 400 Mpa) 1,189.55 Kg Rp 10,214.00 Rp 12,150,067.79
- Pek. Penulangan Beton (min fy = 240 Mpa) 604.13 Kg Rp 10,214.00 Rp 6,170,563.39
- Pek. Bekisting 2x Pemakaian 65.25 m2 Rp 53,710.00 Rp 3,504,577.50
- Pek. Ringbalk, RB Uk. 15 x 20 cm
- Pek. Cor Beton (Readymix) (Beton K225) 1.20 m3 Rp 760,000.00 Rp 912,000.00
- Pek. Penulangan Beton (min fy = 240 Mpa) 324.12 Kg Rp 10,214.00 Rp 3,310,540.63
- Pek. Bekisting 2x Pemakaian 22.00 m2 Rp 53,710.00 Rp 1,181,620.00
Rp 30,204,769.31
Rp 169,226,230.16
Page 2
NO. URAIAN PEKERJAAN VOL SAT. HARGA SAT. JUMLAH HARGA
IV PEKERJAAN ARSITEKTUR
A PEKERJAAN BETON ARSIEKTUR
1 Pekerjaan Beton Arsitektur Lantai 1 (Satu)
- Pek. Kolom Praktis KP1, Uk. 15 x 15 Cm 15.00 bh
- Pek. Cor Beton (Beton K175) 1.40 m3 Rp 625,000.00 Rp 875,390.63
- Pek. Penulangan Beton (min fy = 300 Mpa) 219.53 Kg Rp 10,214.00 Rp 2,242,289.23
- Pek. Penulangan Beton (min fy = 200 Mpa) 180.11 Kg Rp 10,214.00 Rp 1,839,643.54
- Pek. Bekisting 3x Pemakaian 37.35 m2 Rp 53,710.00 Rp 2,006,068.50
Rp 19,498,704.51
Rp 74,511,360.00
C PEKERJAAN KUSEN, PINTU, JENDELA DAN VENTILASI
1 Pekerjaan Kusen, Pintu Dan Jendela
- Pek. Pintu Type PJ1 2.00 Bh
- Kusen Aluminium 4" 12.00 m' Rp 147,450.00 Rp 1,769,400.00
- Bingkai Aluminium Rangka Bingkai Pintu Aluminium 20.52 m' Rp 89,430.00 Rp 1,835,103.60
- Daun Pintu Panel ACP m2 Rp 250,000.00 Rp 700,000.00
- Pas. Kaca Tebal 5mm (Kaca Mati) 2.80 m2 Rp 121,250.00 Rp 1,455,000.00
- Flooring Engsel 12.00 bh Rp 184,660.00 Rp 369,320.00
- Handel Pintu ex Deckson 2.00 Set Rp 185,110.00 Rp 370,220.00
- Kunci Pintu ex Deckson 2.00 buah Rp 234,070.00 Rp -
D PEKERJAAN PLAFOND
1 Pekerjaan Plafond Lantai I (Dasar)
- Pek. Rangka Plafond Besi Hollow, Modul Uk. 60 x 60 Cm 107.00 m2 Rp 60,420.00 Rp 6,464,940.00
(Hollow Galvanize, Uk. 4/4 Dan Uk. 2/4 Cm)
- Pek. Plafond Gypsumboard t:9mm 92.00 m2 Rp 55,000.00 Rp 5,060,000.00
- Pek. Plafond GRC/Kalsyboard, Tbl. 4mm 15.00 m2 Rp 65,000.00 Rp 975,000.00
Rp 12,499,940.00
2 Pekerjaan Plafond Lantai II (Dua)
- Pek. Rangka Plafond Besi Hollow, Modul Uk. 60 x 60 Cm 100.00 m2 Rp 60,420.00 Rp 6,042,000.00
(Hollow Galvanize, Uk. 4/4 Dan Uk. 2/4 Cm)
- Pek. Plafond Gypsumboard t:9mm 85.00 m2 Rp 55,000.00 Rp 4,675,000.00
- Pek. Plafond GRC/Kalsyboard, Tbl. 4mm 15.00 m2 Rp 65,000.00 Rp 975,000.00
Rp 11,692,000.00
Page 3
NO. URAIAN PEKERJAAN VOL SAT. HARGA SAT. JUMLAH HARGA
E PEKERJAAN PENGECATAN
1 Pekerjaan Pengecatan Lantai I (Dasar)
- Pek. Pengecatan Dinding ex Dulux/Propan 559.59 m2 Rp 32,110.00 Rp 17,968,563.34
- Pek. Pengecatan Plafond 107.00 m2 Rp 32,110.00 Rp 3,435,770.00
Rp 21,404,333.34
2 Pekerjaan Pengecatan Lantai II (Dua)
- Pek. Pengecatan Dinding ex Dulux/Propan 792.00 m2 Rp 32,110.00 Rp 25,431,120.00
- Pek. Pengecatan Plafond 100.00 m2 Rp 32,110.00 Rp 3,211,000.00
Rp 28,642,120.00
G PEKERJAAN ATAP
1 Pekerjaan Konstruksi Kap Atap
- Pek. Konstruksi Penutup Atap Flat 167.00 m2 Rp 92,820.00 Rp 15,500,940.00
- Pek. Rangka Atap Baja Ringan 167.00 m2 Rp 58,500.00 Rp 9,769,500.00
- Pek. Nok Atap 44.00 m1 Rp 35,000.00 Rp 1,540,000.00
- Pek. Lesplank, Uk. 2/20 55.00 m1 Rp 40,000.00 Rp 2,200,000.00
Rp 29,010,440.00
Rp 424,148,980.85
V PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
1 PEKERJAAN ELEKTRIKAL
Pekerjaan Panel
- Panel Utama (PU MDB) 1.00 Set Rp 4,000,000.00 Rp 4,000,000.00
Rp 53,849,660.00
VI PEKERJAAN LAIN-LAIN
1 Pembersihan Akhir Lokasi 1.00 ls Rp 500,000.00 Rp 500,000.00
Rp 500,000.00
Page 4
RENCANA JADWAL PELAKSANAAN
PEKERJAAN : PEMBANGUNAN RUMAH TYPE 220
TAHUN : 2020
1 Pek. Tanah Dan Pondasi Batu Gunung Rp 42,013,257 1.73 2.02 2.02
5.77
2 Pek. Tanah Dan Pondasi Poer/Pile Cab Rp 38,296,176 2.63 2.63
5.26
III PEKERJAAN STRUKTUR ATAS GEDUNG 80
BOBOT RENCANA (%) 1.80 2.02 4.65 6.62 5.05 8.80 6.57 9.26 10.01 10.76 10.22 6.34 5.46 5.27 3.98 3.19
KUMULATIF RENCANA 1.80 3.82 8.46 15.09 20.14 28.94 35.51 44.77 54.78 65.54 75.75 82.10 87.56 92.83 96.81 100.00
MASA
PEMELIHARAAN
180 Hari
Kalender