ID Task Task Name Duration Start 29 Mar '20 05 Apr '20 12 Apr '20

Mode S M T W T F S S M T W T F S S M T
1 1 Rumah Type 48 82 days Tue 31/03/20
2 1.1 Persiapan lahan 3 days Tue 31/03/20
3 1.1.1 Pembersihan lahan 2 days Tue 31/03/20
4 1.1.2 Pemasangan gudang peralatan dan amterial 1 day Thu 02/04/20
5 1.1.3 Pengukuran lahan dan pemasangan bowplank 1 day Thu 02/04/20
6 1.2 Pekerjaan Struktural 5 days Tue 31/03/20
7 1.2.1 Pekerjaan Galian Tanah 1 day Tue 31/03/20
8 1.2.2 Pekerjaan Pembuatan Lantai Kerja 1 day Wed 01/04/20
9 1.2.3 Pekerjaan Pembesian 1 day Thu 02/04/20
10 1.2.4 Pemasangan Bekisting 1 day Thu 02/04/20
11 1.2.5 Pengecoran Pondasi Tapak 1 day Fri 03/04/20
12 1.2.6 Pekerjaan urugan tanah kembali 1 day Mon 06/04/20
13 1.3 PEKERJAAN BETON 21 days Tue 07/04/20
14 1.3.1 Pekerjaan Pemasangan Sloof 15/20 3 days Tue 07/04/20
15 1.3.1.1 Pekerjaan Pemasangan Tulangan Sloof 1 day Tue 07/04/20
16 1.3.1.2 Pekerjaan Pemasangan Bekisting 1 day Tue 07/04/20
17 1.3.1.3 Pekerjaan Pengecoran Sloof 2 days Wed 08/04/20
18 1.3.2 Pekerjaan Pembuatan Kolom 5 days Thu 09/04/20
19 1.3.2.1 Pekerjaan Pemasangan Tulangan Kolom 2 days Fri 10/04/20
20 1.3.2.2 Pekerjaan Pemasangan Bekisting 1 day Tue 14/04/20
21 1.3.2.3 Pekerjaan Pengecoran Kolom 2 days Wed 15/04/20
22 1.3.3 Pembuatan Ring Balok 5 days Fri 17/04/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: zzzz yey
Summary Manual Summary Rollup Progress
Date: Wed 01/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start 29 Mar '20 05 Apr '20 12 Apr '20
Mode S M T W T F S S M T W T F S S M T
23 1.3.4 Pengecoran Plat Lantai 5 days Fri 24/04/20
24 1.3.5 Pengecoran Rabat Beton 3 days Fri 01/05/20
25 1.4 PEKERJAAN DINDING DAN LANTAI 16 days Wed 06/05/20
26 1.4.1 Pemasangan Dinding Batu Bata 7 days Wed 06/05/20
27 1.4.2 Pekerjaan Plesteran 3 days Fri 15/05/20
28 1.4.3 Pekerjaan Acian 3 days Wed 20/05/20
29 1.4.4 Pemasangan keramik dan nat 3 days Mon 25/05/20
30 1.4.4.1 Pemasangan keramik ukuran 30cm x 30cm 1 day Mon 25/05/20
31 1.4.4.2 Pemasangan keramik ukuran 40cm x 40cm 3 days Mon 25/05/20
32 1 day
1.4.4.3 Pemasangan keramik KM/WC ukuran 20cm x 20cm Mon 25/05/20
33 1.5 PEKERJAAN ATAP DAN PLAFOND 42 days Tue 26/05/20
34 1.5.1 Pemasangan rangka atap 1 day Tue 26/05/20
35 1.5.2 Pemasangan penutup atap 5 days Wed 27/05/20
36 1.5.2.1 pekerjaan gording 1 day Wed 27/05/20
37 1.5.2.2 Pekerjaan Kaso + Reng 1 day Wed 27/05/20
38 1.5.2.3 Pemasangan genteng beton 4 days Thu 28/05/20
39 1.5.2.4 Pemasangan nok genteng dan bubungan 1 day Tue 02/06/20
40 1.5.3 Pemasangan lisplank 1 day Wed 03/06/20
41 1.5.4 Pemasangan Plafond 1 day Tue 31/03/20
42 1.5.4.1 Pemasangan rangka Plafond 1 day Wed 03/06/20
43 1.5.4.2 Pekerjaan Plafond 3 days Thu 04/06/20
44 1.5.4.3 Pekerjaan Lis Pinggir Plafond 1 day Mon 08/06/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: zzzz yey
Summary Manual Summary Rollup Progress
Date: Wed 01/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration Start 29 Mar '20 05 Apr '20 12 Apr '20
Mode S M T W T F S S M T W T F S S M T
45 1.6 PEKERJAAN JENDELA DAN PINTU 1 day Tue 31/03/20
46 1.6.1 Pemasangan Pintu 1 day Tue 31/03/20
47 1.6.1.1 Pemasangan Kusen Pintu 1 day Thu 14/05/20
48 1.6.1.2 Pemasangan Pintu 1 day Mon 08/06/20
49 1.6.2 Pemasangan Jendela 19 days Thu 14/05/20
50 1.6.2.1 Pemasangan Kusen Jendela 1 day Thu 14/05/20
51 1.6.2.2 Pemasangan Jendela 1 day Tue 09/06/20
52 1.6.3 Pemasangan engsel 1 day Wed 10/06/20
53 1.6.4 Pemasangan kunci tanam 1 day Wed 10/06/20
54 1.6.5 Pemasangan Grendel Pintu 1 day Wed 10/06/20
55 1.6.6 Pemasangan jendela 1 day Wed 10/06/20
56 1.6.7 Pemasangan kait angin 1 day Wed 10/06/20
57 1.6.8 Pemasangan Kaca jendela 1 day Wed 10/06/20
58 1.6.9 Pemasangan spring knip 1 day Wed 10/06/20
59 1.7 PEKERJAAN PENGECETAN 5 days Thu 11/06/20
60 1.7.1 Pengecatan dinding interior 3 days Thu 11/06/20
61 1.7.2 Pengecatan kusen 2 days Mon 15/06/20
62 1.7.2.1 Kusen Pintu 1 day Tue 16/06/20
63 1.7.2.2 Kusen Jendela 1 day Tue 16/06/20
64 1.7.3 Pengecatan Pintu 1 day Tue 16/06/20
65 1.7.4 Pengecetan Plafond 2 days Tue 16/06/20
66 1.7.5 Pengecetan ListPlank 1 day Tue 16/06/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: zzzz yey
Summary Manual Summary Rollup Progress
Date: Wed 01/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task Task Name Duration Start 29 Mar '20 05 Apr '20 12 Apr '20
Mode S M T W T F S S M T W T F S S M T
67 1.8 PEKERJAAN ELECTRICAL, PLUMBING, DAN 5 days Tue
MECHANICAL 31/03/20
68 1.8.1 Pemasangan Stop Kontak 1 day Fri 15/05/20
69 1.8.2 Pemasangan Titik Lampu 1 day Wed 27/05/20
70 1.8.3 Pemasangan Sakelar 1 day Mon 18/05/20
71 1.8.4 Instalasi Pipa Air Bersih 3 days Tue 31/03/20
72 2 days3/4"
1.8.4.1 Pemasangan Pipa Air Bersih PVC tipe AW diameter Fri 01/05/20
73 1.8.5 Instalasi Pipa Pembuangan 3 days Tue 31/03/20
74 1.8.5.1 Pemasangan Pipa Air PVC tipe DW diameter 3"2 days Fri 01/05/20
75 1.8.5.2 Pemasangan Kran Air 1 day Mon 04/05/20
76 1.8.6 Pemasangan Kloset 1 day Fri 01/05/20
77 1.8.7 Pemasangan Kitchen Sink 1 day Fri 01/05/20
78 1.8.8 Pemasangan Wastafel 1 day Fri 01/05/20
79 1.8.9 Pemasangan Shower 1 day Fri 01/05/20
80 1.8.10 Pemasangan Floor Drain 1 day Fri 01/05/20
81 1.8.11 Pembuatan Septic Tank 4 days Fri 24/04/20
82 1.8.12 Pekerjaan Galian 11 days Wed 01/04/20
83 1.8.12.1 Pengecoran Septic Tank 1 day Wed 01/04/20
84 1.8.12.2 Pekerjaan Urugan Kembali 1 day Wed 15/04/20
85 1.8.13 Pemasangan Pompa Air 1 day Tue 31/03/20
86 1.9 PEKERJAAN FINISHING 3 days Tue 31/03/20
87 1.9.1 Pembersihan akhir 2 days Wed 01/04/20
88 1.9.2 Pembuatan taman 3 days Tue 31/03/20
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: zzzz yey
Summary Manual Summary Rollup Progress
Date: Wed 01/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
12 Apr '20 19 Apr '20 26 Apr '20 03 May '20 10 May '20 17 May '20 24 May '20 31 May '20
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: zzzz yey
Summary Manual Summary Rollup Progress
Date: Wed 01/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
12 Apr '20 19 Apr '20 26 Apr '20 03 May '20 10 May '20 17 May '20 24 May '20 31 May '20
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: zzzz yey
Summary Manual Summary Rollup Progress
Date: Wed 01/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
12 Apr '20 19 Apr '20 26 Apr '20 03 May '20 10 May '20 17 May '20 24 May '20 31 May '20
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: zzzz yey
Summary Manual Summary Rollup Progress
Date: Wed 01/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
12 Apr '20 19 Apr '20 26 Apr '20 03 May '20 10 May '20 17 May '20 24 May '20 31 May '20
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: zzzz yey
Summary Manual Summary Rollup Progress
Date: Wed 01/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8
'20 07 Jun '20 14 Jun '20 21 Jun '20 28 Jun '20 05 Jul '20 12 Jul '20 19 Jul '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: zzzz yey
Summary Manual Summary Rollup Progress
Date: Wed 01/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9
'20 07 Jun '20 14 Jun '20 21 Jun '20 28 Jun '20 05 Jul '20 12 Jul '20 19 Jul '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: zzzz yey
Summary Manual Summary Rollup Progress
Date: Wed 01/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 10
'20 07 Jun '20 14 Jun '20 21 Jun '20 28 Jun '20 05 Jul '20 12 Jul '20 19 Jul '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: zzzz yey
Summary Manual Summary Rollup Progress
Date: Wed 01/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 11
'20 07 Jun '20 14 Jun '20 21 Jun '20 28 Jun '20 05 Jul '20 12 Jul '20 19 Jul '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: zzzz yey
Summary Manual Summary Rollup Progress
Date: Wed 01/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 12