Anda di halaman 1dari 8

RENCANA ANGGARAN BIAYA

PROYEK : RENOVASI RUMAH


LOKASI : PEDAN, KLATEN
TAHUN : 2017
RAB

No. URAIAN PEKERJAAN Volume HARGA SATUAN JUMLAH HARGA

I PEKERJAAN BONGKARAN
1 Bongkaran pasangan bata 8.64 m2 27,857.50 240,688.80
2 Bobokan jalur kabel 40.00 m' 10,000.00 400,000.00
Bongkaran boven 5.00 bh 50,000.00 250,000.00
JUMLAH I 640,688.80
II PEKERJAAN PASANGANN DAN PLESTERAN
1 Pasangan hebel 1pc : 3ps Trasram 18.00 m2 84,427.50 1,519,695.00
2 Pasangan hebel 1pc : 8ps 27.45 m2 78,357.50 2,150,913.38
Pasangan hebel 1pc : 8ps (tambahan kamar) 15.00 m2 78,357.50 1,175,362.50
3 Plesteran 1pc : 3ps Trasram 18.00 m2 43,761.00 787,698.00
4 Plesteran 1pc : 8ps 54.90 m2 40,521.00 2,224,602.90
Plesteran 1pc : 8ps (tambahan kamar) 30.00 m2 40,521.00 1,215,630.00
5 Acian 54.90 m2 24,480.00 1,343,952.00
Acian (tambahan kamar) 30.00 m2 24,480.00 734,400.00
6 Sponengan 112.20 m' 9,588.00 1,075,773.60
7 Meja dapur beton 1pc : 2ps : 3kr 1.00 ls 500,000.00 500,000.00
JUMLAH II 12,728,027.38
III PEKERJAAN KERAMIK
1 Keramik KM/WC 25 x 25 9.00 m2 184,378.33 1,659,405.00
2 Keramik KM/WC 25 x 50 20.40 m2 138,455.00 2,824,482.00
3 Keramik mushola 9.00 m2 154,755.00 1,392,795.00
4 Keramik meja dapur 3.85 m2 154,755.00 595,806.75
Keramik dinding meja dapur 3.60 m2 138,455.00 498,438.00
Karpet mushola 9.00 m' 100,000.00 900,000.00
JUMLAH III 6,472,488.75
IV PEKERJAAN SANITASI DAN PLUMBING
1 Bathup + aksesories 1.00 unt 4,500,000.00 4,500,000.00
2 Kloset duduk + aksesories 1.00 unt 2,848,872.50 2,848,872.50
3 Jet shower 1.00 unt 250,000.00 250,000.00
4 Kran shower (panas dingin) 1.00 unt 750,000.00 750,000.00
Kran tembok (panas dingin) 1.00 unt 650,000.00 650,000.00
6 Kran wudhu 1.00 bh 45,000.00 45,000.00
Tempat tisu 1.00 bh 64,000.00 64,000.00
Tempat handuk 1.00 bh 210,000.00 210,000.00
Water heater + aksesories 1.00 bh 2,650,000.00 2,650,000.00
7 Floordrain steinlees 1.00 bh 75,000.00 75,000.00
8 Kichen zink 1.00 unt 750,000.00 750,000.00
Kran leher angsa 1.00 unt 250,000.00 250,000.00
9 Pipa air bersih 3/4" 32.00 m' 19,370.90 619,868.80
10 Pipa air kotor 4" 20.00 m' 93,139.20 1,862,784.00
Pipa air kotor 1 1/4" 4.00 m' 22,195.00 88,780.00
JUMLAH IV 15,525,525.30
V PEKERJAAN PARTISI DAN PINTU RANGKA ALLUMUNIUM
1 Partisi 2 muka gipsum board 9mm rangka metal stud 99.43 m2 170,000.00 16,903,100.00
2 Kusen pinru dan jendela Allumunium 4" 48.70 m' 110,000.00 5,357,000.00
Daun pintu multipleks lapis HPL rangka allumunium (P01) lengkap
3 3.00 unt 1,650,000.00 4,950,000.00
dengan aksesories

4 Daun pintu allumunium KM/WC (P02) lengkap dengan aksesories 1.00 unt 1,050,000.00 1,050,000.00

5 Daun jendela kaca rangka allumunium lengkap dengan aksesories 8.00 unt 850,000.00 6,800,000.00

6 Daun pintu multipleks lapis HPL rangka allumunium (Pj) lengkap 1.00 unt 2,750,000.00 2,750,000.00
dengan aksesories
Perbaikan lis plafond 112.00 m 18,000.00 2,016,000.00
JUMLAH V 37,810,100.00
VI PEKERJAAN LISTRIK
1 Instalasi titik lampu 18.00 ttk 185,000.00 3,330,000.00
2 Instalasi titik stop kontak 10.00 ttk 225,000.00 2,250,000.00
3 Lampu SL 18 watt 16.00 bh 55,000.00 880,000.00
4 Saklar tunggal 6.00 bh 48,000.00 288,000.00
5 Saklar ganda 3.00 bh 54,000.00 162,000.00
6 Stop kontak 8.00 bh 54,000.00 432,000.00
Stop kontak AC 3.00 bh 65,000.00 195,000.00
MCB Panel 1.00 unt 500,000.00 500,000.00
Pemakaian kabel lama 1.00 unt (500,000.00) (500,000.00)
JUMLAH VI 7,537,000.00
No. URAIAN PEKERJAAN Volume HARGA SATUAN JUMLAH HARGA

VII PEKERJAAN PENGECATAN


1 Cat tembok 454.00 m2 27,736.50 12,592,371.00
2 Cat partisi 198.86 m2 27,736.50 5,515,680.39
JUMLAH VII 18,108,051.39
JUMLAH TOTAL 100,698,490.62

DIBULATKAN 100,698,000.00

TERBILANG : SERATUS JUTA ENAM RATUS SEMBILAN PULUH DELAPAN RIBU RUPIAH.
BORONGAN SIPIL

PROYEK RENOVASI RUMAH PEDAN


LOKASI PEDAN KLATEN

No. URAIAN VOLUME HARGA SATUAN

1 Persiapan 1.00 ls 500,000.00


2 Pasang Habel 60.45 m2 25,000.00
3 Plester aci 120.90 m2 27,000.00
4 Openingan 34.00 m' 20,000.00
5 Keramik (+ keramik meja dapur) 45.85 m2 35,000.00
6 Pasang buthup + aksesories 1.00 unt 500,000.00
7 Pasang Koset duduk+aksesories 1.00 unt 150,000.00
8 Pasang Water Heater+aksesories 1.00 unt 150,000.00
9 Pasang pipa 3/4" 22.00 m' 5,000.00
10 Pasang pipa 4" 16.00 m' 6,000.00
11 Cat 652.86 m2 5,000.00
12 Pasang kitcen zing +aksesories 1.00 unt 100,000.00
13 Meja dapur 1.00 unt 350,000.00

JUMLAH

RENCANA ANGGARAN PELAKSANAAN

No. URAIAN PEKERJAAN VOLUME HARGA SATUAN


(Rp.)

1 Upah borongan
2 semen lemkra 2.00 zak 171,000.00
3 Bathup + aksesories 1.00 unt 3,500,000.00
4 Kloset duduk + aksesories 1.00 unt 2,000,000.00
5 Water haatar 1.00 unt 2,250,000.00
6 Jet shower 1.00 unt 200,000.00
7 Kran shower 2.00 unt 650,000.00
8 Bak mandi 1.00 unt 100,000.00
9 Kran wudhu 1.00 unt 75,000.00
10 Floordrain steinlees 1.00 unt 85,000.00
11 Kichen zink 1.00 unt 650,000.00
12 Pipa air bersih 3/4" 10.00 btg 27,000.00
13 Pipa air kotor 4" 4.00 btg 111,000.00
14 Kne dll 1.00 ls 100,000.00
15 cat 12.00 peil 500,000.00
16 hebel 4.00 m3 850,000.00
17 semen 20.00 m3 40,000.00
18 pasir 3.00 rit 900,000.00
19 Keramik 25x25 9.00 m2 54,000.00
20 Keramik 25x50 21.00 m2 82,000.00
21 Keramik 40x40 11.00 m2 62,000.00
22 Keramik 60x60 2.00 m2 64,000.00
23 Keramik 20x25 4.00 m2 64,000.00
24 MCB +BOX 1.00 unt 350,000.00
25 Saklar tunggal 8.00 bh 45,000.00
26 Saklar ganda 5.00 bh 47,500.00
27 Stop kontak 8.00 bh 47,500.00
28 Kanbel NYM 2x2.5 1.00 roll 450,000.00
29 Stop kontak ac 3.00 bh 57,000.00
30 Lampu sl 20.00 bh 45,000.00
31 karpet 9.00 m' 100,000.00
32 list plafond 45.00 btg 20,000.00

JUMLAH
JUMLAH HARGA

500,000.00
1,511,250.00
3,264,300.00
680,000.00
1,604,750.00
500,000.00
150,000.00
150,000.00
110,000.00
96,000.00
3,264,300.00
100,000.00
350,000.00

12,280,600.00 7,500,000 4,780,600

JUMLAH HARGA
(Rp.)

45,201,500.00
342,000.00
3,500,000.00
2,000,000.00
2,250,000.00
200,000.00
1,300,000.00
100,000.00
75,000.00
85,000.00
650,000.00
270,000.00
444,000.00
100,000.00
6,000,000.00
3,400,000.00
800,000.00
2,700,000.00
486,000.00
1,722,000.00
682,000.00
128,000.00
256,000.00
350,000.00
360,000.00
237,500.00
380,000.00
450,000.00
171,000.00
900,000.00
900,000.00
900,000.00

77,340,000.00
BORONGAN PARTISI & KUSEN

PROYEK RENOVASI RUMAH PEDAN


LOKASI PEDAN KLATEN

No. URAIAN VOLUME HARGA SATUAN

1 Partisi 2 muka gipsum board 9mm rangka metal stud 99.43 m2 130,000.00
2 Kusen pinru dan jendela Allumunium 4" 47.00 m' 90,000.00
Daun pintu multipleks lapis HPL rangka allumunium
3 (P01) lengkap dengan aksesories 3.00 unt 1,850,000.00
Daun pintu allumunium KM/WC (P02) lengkap
4 dengan aksesories 1.00 unt 1,250,000.00
Daun jendela kaca rangka allumunium lengkap
5 dengan aksesories 8.00 unt 650,000.00
6 Pasang list plafond 95.00 m' 5,000.00
1 Instalasi titik lampu 16.00 ttk 25,000.00
2 Instalasi titik stop kontak 8.00 ttk 25,000.00
3 Lampu SL 18 watt 16.00 bh 5,000.00
4 Saklar tunggal 8.00 bh 15,000.00
5 Saklar ganda 5.00 bh 15,000.00
6 Stop kontak 8.00 bh 15,000.00
7 MCB Panel 1.00 unt 150,000.00
8 Selot Pintu & aksesories 1.00 unt 1,000,000.00

JUMLAH
JUMLAH HARGA

12,925,900.00
4,230,000.00

5,550,000.00

1,250,000.00

5,200,000.00
475,000.00
400,000.00
200,000.00
80,000.00
120,000.00
75,000.00
120,000.00
150,000.00 1,620,000.00
1,000,000.00

31,775,900.00 22,000,000 9,775,900