Ester Letisia Lonto 5180911309
Ester Letisia Lonto 5180911309
I PEKERJAAN PERSIAPAN
1 Pasir Pasang m3
2 Kapur Mill kg
3 Kerikil / Split m3
4 Pasir urug m3
5 Tanah urug m3
6 Batu kali m3
7 Semen PC kg
8 Kayu kruing papan m3
9 Kayu meranti papan m3
10 Kayu begesteng m3
11 Kayu bengkirai m3
12 Kayu kruing m3
13 Kayu meranti m3
14 Kayu jati perhutani m3
15 Kayu Glugu m3
16 Plepet m'
17 Reng 2/3 kruing m'
18 Reng 2/3 meranti m'
19 Paku usuk kg
20 Paku reng kg
21 Paku eternit kg
22 Besi strip/Baut kg
23 Besi beton kg
24 Bendrat kg
25 Meni kg
26 Genteng paris bh
27 Genteng soka (tipe ..............) bh
28 Genteng beton bh
29 Bubungan paris bh
30 Bubungan beton bh
31 Genteng Keramik glasur (merk ......) bj
32 Bubungan genteng keramik glasur bj
33 Woodplank m'
34 Batu bata bj
35 Granit 60 x 60 (merk ......) m2
36 Step nosing granit 10/60 bj
37 Keramik 40 x 40 (merk ......) m2
38 Keramik 30 x 30 (merk ......) m2
39 Keramik 30x30 anti slip warna (merk ......) m2
40 Keramik dinding 30x60 (merk ......) m2
41 Keramik 20x25 Asia m2
42 Vinyl Parket golden crowl m2
43 Paving block m2
44 Eternit Gel Mini EG/EF lbr
45 Asbes 2,1 M lbr
46 Teakwood 4mm lbr
47 Gypsum Board lbr
48 Amplas lbr
49 Kuas bh
50 Plamur tembok kg
51 Plamur kayu kg
52 Cat Dasar kg
53 Cat Dinding eksterior dulux kg
54 Cat Dinding interior mowilex kg
55 Cat kayu SEIV chasis black 020 kg
56 Cat Genteng NoDrop kg
57 Minyak cat ltr
58 Meni kayu kg
59 Kunci tanam KM bh
60 Engsel pintu bh
61 Engsel jendela bh
62 Slot Pintu Solid bh
63 Slot Kamar Mandi bh
64 Hak Angin RMT bh
65 Handle Pintu bh
66 Kaca tebal 5 mm m2
67 Lem bh
68 PVC 4" wavin D m'
69 PVC 3" wavin D m'
70 PVC 2" wavin D m'
71 PVC 1/2" wavin AW m'
72 PVC 3/4" wavin AW m'
73 Kloset duduk duty monobok bj
74 Kloset jongkok setara Toto bj
75 Kitchen Zinc (merk ......) bj
76 Wastafel gantung (merk ......) bj
77 Seng Bjls 30 m'
78 Galvalum 60 cm m'
79 Batu Palimanan m2
80 Batu Andesit 20/40 m2
81 Batu Andesit susun sirih m2
82 Batu Candi 30/30 m2
83 Batu Templek m2
84 Profil Baja Siku kg
85 Minyak bekisting ltr
86 Plywood 9 mm lbr
150,000.00
20,000.00
185,000.00
190,000.00
125,000.00
185,000.00
57,000.00
23,000.00
35,000.00
55,000.00
37,500.00
40,000.00
15,000.00
175,000.00
11,000.00
5,000.00
40,000.00
45,000.00
14,000.00
15,000.00
17,000.00
35,000.00
63,000.00
15,500.00
20,000.00
11,500.00
2,000.00
9,500.00
10,000.00
15,000.00
9,500.00
9,000.00
34,000.00
723.00
115,000.00
24,000.00
52,000.00
45,000.00
35,000.00
54,000.00
45,000.00
13,000.00
75,000.00
50,400.00
42,000.00
90,000.00
75,000.00
20,000.00
16,700.00
54,000.00
15,000.00
9,000.00
195,000.00
164,000.00
40,000.00
46,700.00
57,000.00
20,000.00
5,000.00
15,000.00
15,000.00
135,000.00
85,000.00
3,950.00
6,500.00
15,000.00
4,500.00
90,000.00
58,000.00
40,000.00
32,500.00
10,000.00
785,000.00
125,000.00
1,575,000.00
450,000.00
47,000.00
30,000.00
155,000.00
90,300.00
115,000.00
110,300.00
80,000.00
8,200.00
8,500.00
98,000.00
PEKERJAAN PERSIAPAN
1 M2 MEMBERSIHKAN LAPANGAN
0.1 Oh Pekerja @ Rp. 62,500.00 = Rp. 6,250.00
0.05 Oh Mandor @ Rp. 80,000.00 = Rp. 4,000.00
PEKERJAAN TANAH
1 M3 URUGAN KEMBALI
0.192 Oh Pekerja @ Rp. 62,500.00 = Rp. 12,000.00
0.019 Oh Mandor @ Rp. 80,000.00 = Rp. 1,520.00
1 M3 URUGAN PASIR
1.2 m3 Pasir Urug @ Rp. 190,000.00 = Rp. 228,000.00
PEKERJAAN PASANGAN
1 M2 PLESTERAN 1 PC : 3 PS TEBAL 15 MM
6.48 kg Semen PC @ Rp. 57,000.00 = Rp. 369,360.00
0.019 m3 Pasir Pasang @ Rp. 150,000.00 = Rp. 2,850.00
1 M2 PLESTERAN 1 PC : 6 PS TEBAL 15 MM
3.68 kg Semen PC @ Rp. 57,000.00 = Rp. 209,760.00
0.023 m3 Pasir Pasang @ Rp. 150,000.00 = Rp. 3,450.00
1 M2 ACIAN
4 kg Semen PC @ Rp. 57,000.00 = Rp. 228,000.00
PEKERJAAN BETON
1 KG PEMBESIAN BETON
1.05 kg Besi beton @ Rp. 63,000.00 = Rp. 66,150.00
0.015 kg Bendrat @ Rp. 15,500.00 = Rp. 232.50
-
0.007 Oh Tukang besi @ Rp. 77,500.00 = Rp. 542.50
0.0007 Oh Kepala tukang besi @ Rp. 77,500.00 = Rp. 54.25
0.007 Oh Pekerja @ Rp. 62,500.00 = Rp. 437.50
0.0003 Oh Mandor @ Rp. 80,000.00 = Rp. 24.00
1 M3 BETON BERTULANG 1:2:3 DENGAN PEMBESIAN 135 KG ( PLAT LUIVEL DAN LISTPLANK )
0.5 Steger beton D.5 @ Rp. 1,176,000.00 = Rp. 588,000.00
0.5 Cetakan beton D.3 @ Rp. 741,250.00 = Rp. 370,625.00
1 Campuran beton D.1 @ Rp. 19,615,930.00 = Rp. 19,615,930.00
135 Pembesian D.2 @ Rp. 67,440.00 = Rp. 9,104,400.00
1 Bongkar dan siram D.4 @ Rp. 187,500.00 = Rp. 187,500.00
1 M3 BETON BERTULANG 1:2:3 DENGAN PEMBESIAN 160 KG ( SLOOF PRAKTIS DAN RINGBALK )
0.5 Cetakan beton D.3 @ Rp. 741,250.00 = Rp. 370,625.00
1 Campuran beton D.1 @ Rp. 19,615,930.00 = Rp. 19,615,930.00
135 Pembesian D.2 @ Rp. 67,440.00 = Rp. 9,104,400.00
1 Bongkar dan siram D.4 @ Rp. 187,500.00 = Rp. 187,500.00
PEKERJAAN ATAP
PEKERJAAN SANITASI
1 M2 PENGECATAN TEMBOK BARU (1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) LUAR
0.1 kg Cat dasar @ Rp. 9,000.00 = Rp. 900.00
0.26 kg Cat penutup 2x @ Rp. 195,000.00 = Rp. 50,700.00
1 M2 PENGECATAN TEMBOK BARU (1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) DALAM
0.1 kg Plamur tembok @ Rp. 54,000.00 = Rp. 5,400.00
0.1 kg Cat dasar @ Rp. 9,000.00 = Rp. 900.00
0.26 kg Cat penutup 2x @ Rp. 164,000.00 = Rp. 42,640.00
0.075 Oh Tukang cat @ Rp. 72,500.00 = Rp. 5,437.50
0.0063 Oh Kepala tukang cat @ Rp. 77,500.00 = Rp. 488.25
0.02 Oh Pekerja @ Rp. 62,500.00 = Rp. 1,250.00
0.0025 Oh Mandor @ Rp. 80,000.00 = Rp. 200.00
1 M2 CAT GENTENG
0.12 kg Cat dasar @ Rp. 46,700.00 = Rp. 5,604.00
0.18 lbr Cat penutup 2x @ Rp. 46,700.00 = Rp. 8,406.00
940.00
28,200.00
37,035.00
13,520.00
228,000.00
19,550.00
5,474,650.00
147,900.00
8,037,100.00
147,900.00
7,414,300.00
147,900.00
3,757,240.00
147,900.00
882,930.00
29,225.00
435,840.00
29,225.00
372,210.00
25,337.50
213,210.00
25,337.50
228,000.00
9,422.50
597,330.00
26,255.00
668,610.00
26,255.00
714,060.00
26,255.00
706,710.00
26,255.00
696,210.00
69,237.50
706,710.00
77,262.50
101,490.00
63,832.50
135,630.00
7,582.50
594,000.00
50,637.50
584,550.00
50,637.50
749,775.00
69,237.50
775,710.00
73,250.00
738,960.00
69,237.50
770,775.00
69,237.50
770,775.00
69,237.50
817,710.00
69,237.50
19,382,850.00
233,087.50
66,382.50
1,058.25
82,000.00
659,250.00
187,500.00
140,750.00
1,035,250.00
36,848,742.50
26,206,592.50
29,278,455.00
N RINGBALK )
29,278,455.00
33,999,255.00
135,000.00
17,380.00
15,000.00
13,035.00
15,000.00
8,690.00
192,500.00
1,982,400.00
7,000.00
267,125.00
19,625.00
267,125.00
41,250.00
2,425,000.00
12,100.00
2,425,000.00
28,200.00
14,675.00
2,382.00
14,675.00
104,950.00
21,325.00
659,150.00
42,650.00
138,200.00
21,325.00
655,650.00
42,650.00
36,647.00
40,412.50
30,147.00
40,412.50
656,150.00
42,650.00
38,100.00
24,930.00
50,000.00
16,072.50
655,400.00
42,650.00
145,800.00
16,224.25
93,960.00
16,224.25
64,800.00
16,224.25
52,650.00
16,224.25
16,200.00
16,224.25
832,100.00
298,877.50
468,500.00
300,300.00
504,000.00
199,750.00
51,600.00
7,375.75
7,375.75
20,250.00
12,497.50
14,010.00
5,320.50
RENCANA ANGGARAN BIAYA
Pekerjaan :
Lokasi :
Luas Bangunan : M2
Tahun Perencanaan : 2020
I PEKERJAAN PERSIAPAN
II PEKERJAAN TANAH
3 Pas. Rolaag bata merah teras dan tangga 1:3(pas.1 bata) M2 0.7
3 M2
keramik roman 40/40:
4 M2
keramik granit china 60/60:
5 m' 42.4
keramik roman 30/30:
Page 47
NO ITEM PEKERJAAN SAT. VOL.
6 M2 42.4
keramik kia ridgeview 30/30:
7 Pas. Batu Candi 30 x 30 trap depan teras M2
1 Pintu P1 M3 0.8800
2 Pintu P2 M4 0.1200
3 Pintu P3 M5
4 Pintu P4 M6
5 Pintu P5 M7
4 Jendela J1R M3
5 Jendela J2R M3
1 Pintu P1 M2 0.8800
Page 48
NO ITEM PEKERJAAN SAT. VOL.
2 Pintu P2 BH 1.0000
3 Pintu P3 BH 1.0000
4 Pintu P4 M2
5 Pintu P5 M2
7 Jendela J1T M2
8 Jendela J1R M2
9 Jendela J2R M2
4 Jurai M3 0.180
1 Pas. Plafon triplek + rangka plafon kayu borneo super 4/6 M2 70.2
Page 49
NO ITEM PEKERJAAN SAT. VOL.
8 Bathup BH 1.00
Page 50
NO ITEM PEKERJAAN SAT. VOL.
2 Pas. bodi pelor kunci pintu utama PU, PJK setara Muller BH
Page 51
NO ITEM PEKERJAAN SAT. VOL.
Page 52
NO ITEM PEKERJAAN SAT. VOL.
3 Taman M2
Jumlah
Page 53
N BIAYA
HARGA
HARGA BOBOT
SATUAN
10,250.00 1,231,500.00
CATATAN :
28,200.00 1,331,766.00
13,520.00 346,112.00
267,100.00 362,895.50
104,780.00 2,373,267.00
102,600.00 20,489,220.00
216,800.00 151,760.00
46,700.00 140,100.00
9,900.00 237,600.00
37,500.00 1,698,750.00
22,800.00 10,155,576.00
94,350.00 3,997,609.50
Page 54
HARGA
HARGA BOBOT
SATUAN
94,350.00 3,997,609.50
58,556,900.00 161,617,044.00
33,999,250.00 59,838,680.00
58,556,900.00 138,779,853.00
7,830,000.00 6,890,400.00
7,830,000.00 939,600.00
7,830,000.00 6,890,400.00
7,830,000.00 939,600.00
7,830,000.00 6,890,400.00
Page 55
HARGA
HARGA BOBOT
SATUAN
557,500.00 557,500.00
441,600.00 441,600.00
227,200.00 1,919,840.00
2,363,000.00 10,296,960.00
4,073,000.00 2,647,450.00
107,250.00 10,725,000.00
4,073,000.00 733,140.00
72,800.00 1,674,400.00
158,600.00 11,133,720.00
256,550.00 769,650.00
22,250.00 1,335,000.00
22,610.00 237,405.00
22,610.00 237,405.00
39,860.00 298,950.00
35,210.00 704,200.00
Page 56
HARGA
HARGA BOBOT
SATUAN
7,248,050.00 7,248,050.00
Page 57
HARGA
HARGA BOBOT
SATUAN
211,500.00 3,384,000.00
193,500.00 580,500.00
97,850.00 97,850.00
290,600.00 581,200.00
63,550.00 254,200.00
65,150.00 1,172,700.00
42,970.00 515,640.00
33,650.00 807,600.00
62,250.00 747,000.00
23,870.00 286,440.00
46,810.00 20,990,540.20
46,810.00 20,990,540.20
48,500.00 446,200.00
48,500.00 1,996,260.00
Page 58
HARGA
HARGA BOBOT
SATUAN
48,500.00 689,400.00
48,500.00 819,650.00
Page 59
HARGA
HARGA BOBOT
SATUAN
Rp. 508,657,351.00
Page 60
ISESUAIKAN SPESIFIKASI BANGUNAN YANG DIHITUNG
Page 61
REKAPITULASI RENCANA ANGGARAN BIAYA
Pekerjaan :
Lokasi :
Luas Bangunan : M2
Tahun Perencanaan : 2020
I PEKERJAAN PERSIAPAN
II PEKERJAAN TANAH
V PEKERJAAN BETON
DIBULATKAN Rp.
Page 62
AYA
BOBOT
Page 63