REKAPITULASI

NAMA PEKERJAAAN : Pembangunan Ruang Ibadah SD Muhammadiyah Sinabang


LOKASI : Kab. Simeulue
SUMBER DANA : APBA-P
TAHUN ANGGARAN : 2014

No Uraian Pekerjaan Jumlah Biaya

I PEKERJAAN PERSIAPAN 2,150,000.00


II PEKERJAAN TANAH DAN PONDASI 16,060,426.67
III PEKERJAAAN BETON BERTULANG 71,650,268.28
IV PEKERJAAN PASANGAN DAN PLESTERAN 21,283,892.00
V PEKERJAAN LANTAI 20,477,287.50
VI PEKERJAAN ATAP DAN PLAFOND 61,583,261.24
VII PEKERJAAN PINTU, JENDELA DAN KUNCI 16,151,589.80
VIII PEKERJAAN PENGECATAN 14,196,490.00
IX PEKERJAAN INSTALASI LISTRIK 4,838,000.00
X PEKERJAAN LAIN-LAIN 700,000.00

JUMLAH Rp 229,091,215.49

PPN + PPh 10% Rp 22,909,121.55

TOTAL Rp 252,000,337.04

DIBULATKAN Rp 252,000,000.00

Terbilang : Dua Ratus Lima Puluh Dua Juta Rupiah

Simeulue, 24 Juli 2014


CV. RIVIA

JIKO JASMI
Direktur
JADWAL WAKTU PELAKSANAAN PEKERJAAN (KURVA-S)

PEKERJAAN : Pembangunan Ruang Ibadah SD Muhammadiyah Sinabang


LOKASI : Kab. Simeulue

Harga Jumlah MASA PELAKSANAAN


Bobot
No. Item Pekerjaan Volume Satuan Pekerjaan KET.
(%) AGUSTUS / SEPTEMBER SEPTEMBER / OKTOBER OKTOBER / NOPEMBER NOPEMBER / DESEMBER
( Rp. ) ( Rp. )
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
I. Pekerjaan Persiapan
Persiapan & Pembersihan Lapangan 1.00 Paket 500,000.00 500,000.00 0.22 0.22 100%
Pengukuran dan pemasangan bowplank 1.00 Paket 500,000.00 500,000.00 0.22 0.22
Papan Nama Proyek 1.00 Paket 300,000.00 300,000.00 0.13 0.13
Administrasi dan Dokumentasi 1.00 Paket 850,000.00 850,000.00 0.37 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
II. PEKERJAAN TANAH DAN PONDASI
Galian Tanah Pondasi 38.00 M3 43,000.00 1,634,000.00 0.71 0.71 90%
Urugan Kembali Bekas Galian 12.67 M3 19,000.00 240,666.67 0.11 0.11
Urugan Pasir Alas Pondasi 2.00 M3 149,200.00 298,400.00 0.13 0.13
Pasangan Batu Kosong / Aanstamping 4.00 M3 277,200.00 1,108,800.00 0.48 0.48
Pasangan Pondasi Batu Gunung 17.00 M3 618,300.00 10,511,100.00 4.59 1.53 1.53 1.53
Pondasi Bata Rolag 1 Pc : 2 PP (Trasraam) Teras 23.40 M2 96,900.00 2,267,460.00 0.99 0.99
III. PEKERJAAN BETON BERTULANG
Sloof Beton uk. 20/25 cm 2.50 M3 5,263,500.00 13,158,750.00 5.74 1.91 1.91 1.91
Plat Dack T=08 cm 1.33 M3 6,511,400.00 8,641,930.08 3.77 1.89 1.89
Kolom 20/20 cm 3.60 M3 8,764,000.00 31,550,400.00 13.77 3.44 3.44 3.44 3.44
80%
Ring Balok & Balok uk. 15/18 cm 1.62 M3 6,947,300.00 11,254,626.00 4.91 1.64 1.64 1.64
Kolom Fasade Jendela (Bingkai) uk. 13/13 cm 1.01 M3 6,947,300.00 7,044,562.20 3.08 1.03 1.03 1.03
IV. PEKERJAAN PASANGAN DAN PLESTERAN
Pasangan Trasraam Bata 1 PC : 2 PP 19.00 M2 96,900.00 1,841,100.00 0.80 0.80
Plesteran trasraam Bata 1 PC : 2 PP 38.00 M2 49,700.00 1,888,600.00 0.82 0.82
Pasangan Dinding Bata 1 PC : 4 PP 93.32 M2 88,100.00 8,221,492.00 3.59 1.20 1.20 1.20
Plesteran Dinding Bata 1 PC : 4 PP 239.30 M2 39,000.00 9,332,700.00 4.07 2.04 2.04
V. PEKERJAAN LANTAI 70%
Pekerjaan Timbunan dan Urugan
Timbunan Tanah bawah Lantai 27.50 M3 85,600.00 2,354,000.00 1.03 1.03
Urugan Pasir Bawah Lantai 6.88 M3 149,200.00 1,025,750.00 0.45 0.45
Pekerjaan Keramik
Rabat Beton dibawah Lantai Keramik 3.44 M3 692,600.00 2,380,812.50 1.04 1.04
Keramik Lantai 40 x 40 cm (Polished) 77.38 M2 190,200.00 14,716,725.00 6.42 2.14 2.14 2.14
VI. PEKERJAAN ATAP DAN PLAFOND 60%
Ranga Kuda-kuda Baja Ringan 109.35 M2 220,500.00 24,112,413.39 10.53 2.63 2.63 2.63 2.63
Atap Seng Genteng Metal 109.35 M2 120,000.00 13,122,401.85 5.73 1.91 1.91 1.91
Kubah Steinlessteel Fabrikasi 1.00 Unit 5,000,000.00 5,000,000.00 2.18 Kurva Realisasi 1.09 1.09
Listplank Papan + Pengecatan 47.90 M 40,000.00 1,916,000.00 0.84 0.84
Plafond Gypsum 107.81 M2 52,000.00 5,606,120.00 2.45 1.22 1.22
Rangka Plafond Puring 107.81 M2 94,600.00 10,198,826.00 4.45 2.23 2.23
Profil Gypsum 108.50 M' 15,000.00 1,627,500.00 0.71 0.71
VII. PEKERJAAN PINTU,JENDELA DAN KUNCI 50%
Pintu Type P1 (3 Unit)
- Kosen Kayu Kelas II 0.17 M3 6,953,700.00 1,193,254.92 0.52 0.52
- Daun Pintu Kayu P1 Uk.60x210 cm 6.00 Lembar 800,000.00 4,800,000.00 2.10 2.10
- Kunci Pintu Standar 3.00 Set 84,500.00 253,500.00 0.11 0.11
- Engsel Pintu 18.00 Buah 37,300.00 671,400.00 0.29 0.29
Jendela Type J1 (12 Unit)
- Kosen Kayu Kelas II 0.55 M3 6,953,700.00 3,850,959.06 1.68 1.68
- Daun Jendela Uk. 60x180 cm 12.00 Lembar 250,000.00 3,000,000.00 1.31 1.31 40%
- Engsel Jendela 24.00 Buah 20,200.00 484,800.00 0.21 0.21
- Grendel Jendela 12.00 Buah 32,400.00 388,800.00 0.17 0.17
- Hak Penahan Angin Jendela 12.00 Buah 27,300.00 327,600.00 0.14 0.14
- Tarikan Jendela 12.00 Buah 27,300.00 327,600.00 0.14 0.14
Jendela Type V1 (2 Unit)
- Kosen Kayu Kelas II 0.03 M3 6,953,700.00 198,875.82 0.09 0.09
- Daun Jendela Uk. 60x180 cm 2.00 Lembar 200,000.00 400,000.00 0.17 0.17
30%
- Engsel Jendela Ventilasi 4.00 Buah 20,200.00 80,800.00 0.04 0.04
- Grendel Jendela Ventilasi 2.00 Buah 32,400.00 64,800.00 0.03 0.03
30%

- Hak Penahan Angin Jendela/Ventilasi 2.00 Buah 27,300.00 54,600.00 0.02 0.02
- Tarikan Jendela/Ventilasi 2.00 Buah 27,300.00 54,600.00 0.02 0.02
VIII. PEKERJAAN PENGECATAN
Cat Tembok 3 x (L/D) 277.30 M2 24,500.00 6,793,850.00 2.97 1.48 1.48
Cat Plafond 107.81 M2 40,000.00 4,312,400.00 1.88 1.88
Cat Mengkilat kosen dan Daun Pintu/Jendela 77.26 M2 40,000.00 3,090,240.00 1.35 1.35
20%
IX. PEKERJAAN INSTALASI LISTRIK
Pemasukan Listrik 6 Ampere + Grounding 1.00 Ls 2,500,000.00 2,500,000.00 1.09 Kurva Rencana 1.09
Zekering Kast Lokal 2 Group 1.00 Buah 250,000.00 250,000.00 0.11 0.11
Armatur
Lampu HE 18 Watt 4.00 Buah 42,000.00 168,000.00 0.07 0.07
Lampu TL 2x20 Watt 4.00 Buah 50,000.00 200,000.00 0.09 0.09
Saklar lampu Merk Panasonik
Saklar 1 Seri + Instalasi
10%
Saklar 1 Seri + Instalasi 6.00 Buah 15,000.00 90,000.00 0.04 0.04
Instalasi Titik Penerangan, Instalasi termasuk Kabel NYA 2, 8.00 Buah 110,000.00 880,000.00 0.38 0.38
mm Dalam Pipa PVC Fitting Lampu dan Kelengkapan
Instalasi (terpasang)
Stop Kontak + Instalasi Titik Stop Kontak, Termasuk Kabel 6.00 Buah 125,000.00 750,000.00 0.33 0.33
NYA 2,5 mm Dalam Pipa PVC, Kotak Kontak dan Kelengkapan
Instalasi (terpasang)
XI. PEKERJAAN LAIN-LAIN
Pembersihan Akhir 1.00 Ls 700,000.00 700,000.00 0.31 0.31

0%
Total Harga Dan Bobot 229,091,215.49 100.00

Progres rencana Mingguan 1.30 2.17 1.55 3.47 2.04 7.21 5.49 8.73 10.95 9.26 11.22 10.99 8.65 6.88 8.41 1.69
Progres Rencana Kumulatif Mingguan ( % ) 1.30 3.47 5.02 8.49 10.53 17.75 23.23 31.96 42.91 52.17 63.38 74.37 83.02 89.90 98.31 100.00

Kemajuan Pekerjaan (%) #REF! #REF! #REF! #REF! #REF! #REF! - - - - - - - - - -


Deviasi (%) #REF! #REF! #REF! #REF! #REF! #REF! - - - - - - - - - -

Diperiksa Oleh, Dibuat Oleh,


Konsultan Pengawas Kontraktor Pelaksana
CV. PATI UTAMA KONSULTAN CV. RIVIA

FACHRURRAZI, ST HANIF, ST
Pengawas Lapangan Site Manager
BILL OF QUANTITY (BoQ)
NAMA PEKERJAAAN : Pembangunan Ruang Ibadah SD Muhammadiyah Sinabang
LOKASI : Kab. Simeulue
SUMBER DANA : APBA-P
TAHUN ANGGARAN : 2014

Harga Satuan Jumlah Harga


NO URAIAN PEKERJAAN VOLUME SAT. ANALISA
(Rp) (Rp)
1 2 3 4 5 6 7
I. PEKERJAAN PERSIAPAN
1 Persiapan & Pembersihan Lapangan 1.00 Paket Taksir 500,000.00 Rp 500,000
2 Pengukuran dan pemasangan bowplank 1.00 Paket Taksir 500,000.00 Rp 500,000
3 Papan Nama Proyek 1.00 Paket Taksir 300,000.00 Rp 300,000
4 Administrasi dan Dokumentasi 1.00 Paket Taksir 850,000.00 Rp 850,000
Sub Jumlah Rp 2,150,000
II. PEKERJAAN TANAH DAN PONDASI
1 Galian Tanah Pondasi 38.00 M3 SNI 2835:2007-6.1 43,000.00 Rp 1,634,000
2 Urugan Kembali Bekas Galian 12.67 M3 SNI 2835:2007-6.9 19,000.00 Rp 240,667
3 Urugan Pasir Alas Pondasi 2.00 M3 SNI 2835:2007-6.11 149,200.00 Rp 298,400
4 Pasangan Batu Kosong / Aanstamping 4.00 M 3
SNI 2836:2007-6.9 277,200.00 Rp 1,108,800
5 Pasangan Pondasi Batu Gunung 17.00 M3 SNI 2836:2007-6.1 618,300.00 Rp 10,511,100
6 Pondasi Bata Rolag 1 Pc : 2 PP (Trasraam) Teras 23.40 M2 SNI 6897-2007-6.7 96,900.00 Rp 2,267,460
Sub Jumlah Rp 16,060,427
III. PEKERJAAN BETON BERTULANG
1 Sloof Beton uk. 20/25 cm 2.50 M3 SUPLEMEN 16 5,263,500.00 Rp 13,158,750
2 Plat Dack T=08 cm 1.33 M3 SUPLEMEN 34 6,511,400.00 Rp 8,641,930
3 Kolom 20/20 cm 3.60 M3 SUPLEMEN 12 8,764,000.00 Rp 31,550,400
4 Ring Balok & Balok uk. 15/18 cm 1.62 M3 SUPLEMEN 28 6,947,300.00 Rp 11,254,626
5 Kolom Fasade Jendela (Bingkai) uk. 13/13 cm 1.01 M3 SUPLEMEN 23 6,947,300.00 Rp 7,044,562
Sub Jumlah Rp 71,650,268
IV. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasangan Trasraam Bata 1 PC : 2 PP 19.00 M2 SNI 6897-2007-6.7 96,900.00 Rp 1,841,100
2 Plesteran trasraam Bata 1 PC : 2 PP 38.00 M2 SNI 2837-2007.6.2 49,700.00 Rp 1,888,600
3 Pasangan Dinding Bata 1 PC : 4 PP 93.32 M2 SNI 6897-2007-6.9 88,100.00 Rp 8,221,492
4 Plesteran Dinding Bata 1 PC : 4 PP 239.30 M2 SNI 2837-2007.6.4 39,000.00 Rp 9,332,700
Sub Jumlah Rp 21,283,892
V. PEKERJAAN LANTAI
Pekerjaan Timbunan dan Urugan
1 Timbunan Tanah bawah Lantai 27.50 M3 SNI 2835:2007-6.16 85,600.00 Rp 2,354,000
2 Urugan Pasir Bawah Lantai 6.88 M3 SNI 2835:2007-6.11 149,200.00 Rp 1,025,750
Pekerjaan Keramik
1 Rabat Beton dibawah Lantai Keramik 3.44 M3 SNI 7394:2007-6.2 692,600.00 Rp 2,380,813
2 Keramik Lantai 40 x 40 cm (Polished) 77.38 M2 SNI DT-91-0012-2007-6.64 190,200.00 Rp 14,716,725
Sub Jumlah Rp 20,477,288
Harga Satuan Jumlah Harga
NO URAIAN PEKERJAAN VOLUME SAT. ANALISA
(Rp) (Rp)
1 2 3 4 5 6 7
VI. PEKERJAAN ATAP DAN PLAFOND
1 Ranga Kuda-kuda Baja Ringan 109.35 M2 SNI DT-91-0014-2007-6.20 220,500.00 Rp 24,112,413
2 Atap Seng Genteng Metal 109.35 M2 1 M2 120,000.00 Rp 13,122,402
3 Kubah Steinlessteel Fabrikasi 1.00 Unit Taksir 5,000,000.00 Rp 5,000,000
4 Listplank Papan + Pengecatan 47.90 M Taksir 40,000.00 Rp 1,916,000
5 Plafond Gypsum 107.81 M2 SNI DT-91-0013-2007-6.7 52,000.00 Rp 5,606,120
6 Rangka Plafond Puring 107.81 M2 SNI DT-91-0011-2007-6.19.a 94,600.00 Rp 10,198,826
7 Profil Gypsum 108.50 M' Taksir 15,000.00 Rp 1,627,500
Sub Jumlah Rp 61,583,261
VII. PEKERJAAN PINTU,JENDELA DAN KUNCI
1 Pintu Type P1 (3 Unit)
- Kosen Kayu Kelas II 0.17 M3 SNI DT-91-0011-2007-6.2 6,953,700.00 Rp 1,193,255
- Daun Pintu Kayu P1 Uk.60x210 c 6.00 Lembar Taksir 800,000.00 Rp 4,800,000
- Kunci Pintu Standar 3.00 Set RSNI T-30-2007-B.2 84,500.00 Rp 253,500
- Engsel Pintu 18.00 Buah RSNI T-30-2007-B.5 37,300.00 Rp 671,400

2 Jendela Type J1 (12 Unit)


- Kosen Kayu Kelas II 0.55 M3 SNI DT-91-0011-2007-6.2 6,953,700.00 Rp 3,850,959
- Daun Jendela Uk. 60x180 cm 12.00 Lembar Taksir 250,000.00 Rp 3,000,000
- Engsel Jendela 24.00 Buah RSNI T-30-2007-B.6 20,200.00 Rp 484,800
- Grendel Jendela 12.00 Buah RSNI T-30-2007-B.25 32,400.00 Rp 388,800
- Hak Penahan Angin Jendela 12.00 Buah RSNI T-30-2007-B.9 27,300.00 Rp 327,600
- Tarikan Jendela 12.00 Buah RSNI T-30-2007-B.26 27,300.00 Rp 327,600

3 Jendela Type V1 (2 Unit)


- Kosen Kayu Kelas II 0.03 M3 SNI DT-91-0011-2007-6.2 6,953,700.00 Rp 198,876
- Daun Jendela Uk. 60x180 cm 2.00 Lembar Taksir 200,000.00 Rp 400,000
- Engsel Jendela Ventilasi 4.00 Buah RSNI T-30-2007-B.6 20,200.00 Rp 80,800
- Grendel Jendela Ventilasi 2.00 Buah RSNI T-30-2007-B.25 32,400.00 Rp 64,800
- Hak Penahan Angin Jendela/Venti 2.00 Buah RSNI T-30-2007-B.9 27,300.00 Rp 54,600
- Tarikan Jendela/Ventilasi 2.00 Buah RSNI T-30-2007-B.26 27,300.00 Rp 54,600
Sub Jumlah Rp 16,151,590
Harga Satuan Jumlah Harga
NO URAIAN PEKERJAAN VOLUME SAT. ANALISA
(Rp) (Rp)
1 2 3 4 5 6.00 7
VIII. PEKERJAAN PENGECATAN
1 Cat Tembok 3 x (L/D) 277.30 M2 PT. T-38-2007-C-B14 24,500.00 Rp 6,793,850
2 Cat Plafond 107.81 M2 PT. T-38-2007-C-B8 40,000.00 Rp 4,312,400
3 Cat Mengkilat kosen dan Daun Pintu/Jendela 77.26 M 2
PT. T-38-2007-C-B8 40,000.00 Rp 3,090,240
Sub Jumlah Rp 14,196,490
IX. PEKERJAAN INSTALASI LISTRIK
1 Pemasukan Listrik 6 Ampere + Grounding 1.00 Ls Taksir 2,500,000.00 Rp 2,500,000
2 Zekering Kast Lokal 2 Group 1.00 Buah Taksir 250,000.00 Rp 250,000
3 Armatur
Lampu HE 18 Watt 4.00 Buah Taksir 42,000.00 Rp 168,000
Lampu TL 2x20 Watt 4.00 Buah Taksir 50,000.00 Rp 200,000
4 Saklar lampu Merk Panasonik
Saklar 1 Seri + Instalasi 6.00 Buah Taksir 15,000.00 Rp 90,000
5 Instalasi Titik Penerangan, Instalasi termasuk Kabe 8.00 Buah Taksir 110,000.00 Rp 880,000
mm Dalam Pipa PVC Fitting Lampu dan Kelengkapan
Instalasi (terpasang)
6 Stop Kontak + Instalasi Titik Stop Kontak, Termasu 6.00 Buah Taksir 125,000.00 Rp 750,000
NYA 2,5 mm Dalam Pipa PVC, Kotak Kontak dan Kelengkapan
Instalasi (terpasang)

Sub Jumlah Rp 4,838,000


XI. PEKERJAAN LAIN-LAIN
1 Pembersihan Akhir 1.000 Ls Taksir 700,000.00 Rp 700,000
Sub Jumlah Rp 700,000
VOLUME PEKERJAAN

I. PEKERJAAN PERSIAPAN

1 Persiapan & Pembersihan Lapangan = Ls


2 Pengukuran & Pemasangan Bowplank

Horizontal
19
19
38 Panjang = 38 m

3 Pengukuran & Pemasangan Bowplank = Ls

II. PEKERJAAN TANAH DAN PONDASI


1 Galian Tanah Pondasi
Vertikal Horizontal Atas = 0.80 m
2.5 2.5 Bawah = 0.80 m
7.5 7.5 Tinggi = 0.95 m
3 4 Panjang = 50 m
3 7.5 Volume = 38 m3
7.5 2.5
2.5

26 24
50

2 Urugan Kembali Bekas Galian


SNI-2008 >>1/3 Galian Volume = 12.6667 m3

3 Urugan Pasir Alas Pondasi


Lebar = 0.80 m
Tinggi = 0.05 m
Panjang = 50 m
Volume = 2 m3

4 Pasangan Batu Kosong Anstamping


Lebar = 0.80 m
Tinggi = 0.10 m
Panjang = 50 m
Volume = 4 m3
5 Pasangan Pondasi Batu Gunung
Atas = 0.25 m
Bawah = 0.60 m
Tinggi = 0.80 m
Panjang = 50 m
Volume = 17 m3

6 Pondasi Bata Rolag 1 Pc : 2 PP (Trasraam) Teras

Panjang Tinggi Luas A Satuan


36 0.4 14.40 M2
7.5 0.6 4.50 M2
7.5 0.6 4.50 M2

Total 23.40 M2

III PEKERJAAN BETON BERTULANG

1 Sloof Beton Uk. 20/25 cm

Panjang b (m) h (m) V (m3) Satuan


26 1.3 m3
24 1.2 m3
0 m3
0.2 0.25
0 m3
0 m3

Total 2.5 m3

2 Kolom Praktis Uk. 13/13 cm


Panjang Jumlah (n) b (m) h (m) Volume Satuan
2 4 0.13 0.13 0.1352 m3
m3

Total 0.1352 m3
3 Kolom Struktur Uk. 20/20 cm
Panjang Jumlah (n) b (m) h (m) Volume Satuan
4.5 20 0.20 0.20 3.6 m3
m3

Total 3.6 m3

4 Reng Balok & Balok Uk. 15/18 cm

Panjang b (m) h (m) V (m3) Satuan


10 0.27 m3
18 0.486 m3
25 0.675 m3
0.15 0.18
7 0.189 m3
0 m3

Total 1.62 m3

5 Kolom Fasade Jendela (Bingkai) Uk. 13/13 cm

Panjang b (m) h (m) V (m3) Satuan


60 1.014 m3
0 m3
0 m3
0.13 0.13
0 m3
0 m3

Total 1.014 m3

6 Plat Dack T=08 cm


Panjang Jumlah (n) b (m) h (m) Volume Satuan
3.5 3 1.58 0.08 1.3272 m3
m3

Total 1.3272 m3
IV PEKERJAAN PASANGAN DAN PLASTERAN

1 Pasangan Trasraam Bata 1 PC : 2 PP


Panjang Tinggi Luas A Satuan
30 0.4 12.00 M2
4 0.4 1.60 M2
13.5 0.4 5.40 M2
0.4 0.00 M2

Total 19.00 M2

2 Plesteran trasraam Bata 1 PC : 2 PP

Total 38.00 M2

3 Pasangan Bata 1 PC : 4 PP
Panjang Tinggi Luas A Satuan
15 3.4 51.00 M2
15 3.4 51.00 M2
4 3.4 13.60 M2
13.5 0.3 4.05 M2

Total 119.65 M2 Vol pintu dan Jendela = 26,33 M2

4 Plesteran trasraam Bata 1 PC : 4 PP

Total 239.30 M2

V PEKERJAAN LANTAI

1 Penimbunan Tanah Bawah Lantai


Panjang Lebar (m) Tinggi (m) Volume Satuan
2.50 2.00 0.40 2.00 m3
7.5 7.5 0.40 22.50 m3
7.5 1 0.40 3.00 m3
Total 27.50 m3
2 Urugan Pasir Bawah Lantai

Panjang Lebar (m) Tinggi (m) Volume Satuan


2.50 2.00 0.10 0.50 m3
7.5 7.5 0.10 5.63
7.5 1 0.10 0.75
Total 6.88 m3

3 Rabat Beton Di Bawah Lantai Keramik


Panjang Lebar (m) Tinggi (m) Volume Satuan
2.50 2.00 0.05 0.25 m3
7.5 7.5 0.05 2.81
7.5 1 0.05 0.38
Total 3.44 m3

4 Keramik Lantai 40cmx40cm

Panjang Lebar Luas A Satuan


7.5 7.5 56.25 M2
2 2.5 5.00 M2
7.5 1 7.50 M2
7.5 0.7 5.25 M2
7.5 0.45 3.38 M2
Total 77.38 M2

VI PEKERJAAN ATAP DAN PLAFOND

1 Atap Genteng Metal

Panjang Lebar Luas A Satuan


4.7 1.8 8.46 M2
8.8 9.8 86.24 M2
M2
M2

Total 109.35 M2 Sudah Terproyeksi Dengan Cos 30*

2 Rangka Kuda-Kuda Baja Ringan


Panjang Lebar Luas A Satuan
Total 109.35 M2

3 Lisplank Papan

Panjang Satuan
9.8 M
9.8 M
9.8 M
9.8 M
4 M
4.7 M
47.9 M

4 Plafond Gypsum

Panjang Lebar Luas A Satuan


9.9 9.9 98.01 M2
2 4.9 9.80 M2
0.00 M2
0.00 M2
0.00 M2
0.00 M2
0.00 M2
Total 107.81 M2

5 Rangka Furing Plafond Gypsum

Panjang Lebar Luas A Satuan


Total 107.81 M2

6 Profil Gypsum

Panjang Satuan
9.9 M
9.9 M
9.9 M
9.9 M
15 M
15 M
15 M
15 M
4 M
4.9 M
108.5 M

VII PEKERJAAN KUSEN PINTU & JENDELA

1 Pintu Type P1 (3 Unit)


Panjang Satuan Jumlah Volume Satuan
2.3 M
2.3 M
1.3 M
1.3 M
1.3 M
0.3 M
8.8 M 3 26.4 M
0.1716 m3

2 Jendela Type J1 (12 Unit)

Panjang Satuan Jumlah Volume Satuan


1.2 M
0.7 M
0.7 M
0.7 M
1.8 M
1.8 M
0.2 M
7.1 M 12 85.2 M
0.5538 m3

3 Ventilasi Type V1 (2 Unit)

Panjang Satuan Jumlah Volume Satuan


0.6 M
0.6 M
0.4 M
0.4 M
0.2 M
M
M
2.2 M 2 4.4 M
0.0286 m3

VIII PEKERJAAN PENGECATAN

1 Cat Tembok 3x (L/D)

Total 277.30 M2

2 Cat Plafond

Total 107.81 M2
3 Cat Mengkilap Kayu Daun Pintu Dan Jendela

Total 77.26 M2
ANALISA HARGA SATUAN

URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

PEKERJAAN PERSIAPAN
RSNI T-12-2007-B8
1 M2 MEMBERSIHKAN LAPANGAN DAN PERALATAN
0.100 Oh Pekerja @ Rp 55,000.00 Rp 5,500.00
0.050 Oh Mandor @ Rp 70,000.00 Rp 3,500.00
Jumlah Rp 9,000.00
Dibulatkan Rp 9,000.00

SNI-03-2835-6.14
1 M3 PEMBONGKARAN DNDING TEMBOK BATA
6.667 Oh Pekerja @ Rp 55,000.00 Rp 366,685.00
0.033 Oh Mandor @ Rp 70,000.00 Rp 2,310.00
Jumlah Rp 368,995.00
Dibulatkan Rp 368,900.00

PEKERJAAN TANAH
SNI 2835:2007-6.1
1 M3 GALIAN TANAH BIASA SEDALAM 1 M'
0.750 Oh Pekerja @ Rp 55,000.00 Rp 41,250.00
0.025 Oh Mandor @ Rp 70,000.00 Rp 1,750.00
Jumlah Rp 43,000.00
Dibulatkan Rp 43,000.00

SNI 2835:2007-6.2
1 M3 GALIAN TANAH BIASA SEDALAM 2 M'
0.900 Oh Pekerja @ Rp 55,000.00 Rp 49,500.00
0.045 Oh Mandor @ Rp 70,000.00 Rp 3,150.00
Jumlah Rp 52,650.00
Dibulatkan Rp 52,600.00

SNI 2835:2007-6.3
1 M3 GALIAN TANAH BIASA SEDALAM 3 M'
1.050 Oh Pekerja @ Rp 55,000.00 Rp 57,750.00
0.067 Oh Mandor @ Rp 70,000.00 Rp 4,690.00
Jumlah Rp 62,440.00
Dibulatkan Rp 62,400.00

SNI 2835:2007-6.4
1 M3 GALIAN TANAH KERAS SEDALAM 1 M'
1.000 Oh Pekerja @ Rp 55,000.00 Rp 55,000.00
0.032 Oh Mandor @ Rp 70,000.00 Rp 2,240.00
Jumlah Rp 57,240.00
Dibulatkan Rp 57,200.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

SNI 2835:2007-6.5
1 M3 GALIAN TANAH CADAS SEDALAM 1 M'
1.500 Oh Pekerja @ Rp 55,000.00 Rp 82,500.00
0.060 Oh Mandor @ Rp 70,000.00 Rp 4,200.00
Jumlah Rp 86,700.00
Dibulatkan Rp 86,700.00

SNI 2835:2007-6.6
1 M3 GALIAN TANAH LUMPUR SEDALAM 1 M'
1.200 Oh Pekerja @ Rp 55,000.00 Rp 66,000.00
0.045 Oh Mandor @ Rp 70,000.00 Rp 3,150.00
Jumlah Rp 69,150.00
Dibulatkan Rp 69,100.00

SNI 2835:2007-6.9
1 M3 URUGAN TANAH KEMBALI
0.333 Oh Pekerja @ Rp 55,000.00 Rp 18,315.00
0.011 Oh Mandor @ Rp 70,000.00 Rp 770.00
Jumlah Rp 19,085.00
Dibulatkan Rp 19,000.00

SNI 2835:2007-6.10
1 M3 PEMADATAN TANAH (PER 20 cm)
0.500 Oh Pekerja @ Rp 55,000.00 Rp 27,500.00
0.050 Oh Mandor @ Rp 70,000.00 Rp 3,500.00
Jumlah Rp 31,000.00
Dibulatkan Rp 31,000.00

SNI 2835:2007-6.11
1 M3 MENGURUG PASIR URUG
1.200 M3 Pasir urug @ Rp 110,000.00 Rp 132,000.00
0.300 Oh Pekerja @ Rp 55,000.00 Rp 16,500.00
0.010 Oh Mandor @ Rp 70,000.00 Rp 700.00
Jumlah Rp 149,200.00
Dibulatkan Rp 149,200.00
SNI 2835:2007-6.16
1 M3 MENGURUG TANAH TIMBUN
1.200 M3 Tanah Urug @ Rp 57,000.00 Rp 68,400.00
0.300 Oh Pekerja @ Rp 55,000.00 Rp 16,500.00
0.010 Oh Mandor @ Rp 70,000.00 Rp 700.00
Jumlah Rp 85,600.00
Dibulatkan Rp 85,600.00

PEKERJAAN PONDASI
SNI 2836:2007-6.1
1 M3 PASANGAN PONDASI BATU BELAH, CAMP 1 Pc : 3 PP
1.200 M3 Batu Belah 15 cm/20 cm @ Rp 130,000.00 Rp 156,000.00
202.000 Kg Semen Portland @ Rp 1,275.00 Rp 257,550.00
0.485 M3 Pasir Pasang @ Rp 130,000.00 Rp 63,050.00
1.500 Oh Pekerja @ Rp 55,000.00 Rp 82,500.00
0.750 Oh Tukang Batu @ Rp 65,000.00 Rp 48,750.00
0.075 Oh Kepala Tukang @ Rp 70,000.00 Rp 5,250.00
0.075 Oh Mandor @ Rp 70,000.00 Rp 5,250.00
Jumlah Rp 618,350.00
Dibulatkan Rp 618,300.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

SNI 2836:2007-6.2
1 M3 PASANGAN PONDASI BATU BELAH, CAMP 1 Pc : 4 PP
1.200 M3 Batu Belah 15 cm/20 cm @ Rp 130,000.00 Rp 156,000.00
163.000 Kg Semen Portland @ Rp 1,275.00 Rp 207,825.00
0.520 M3 Pasir Pasang @ Rp 130,000.00 Rp 67,600.00
1.500 Oh Pekerja @ Rp 55,000.00 Rp 82,500.00
0.750 Oh Tukang Batu @ Rp 65,000.00 Rp 48,750.00
0.075 Oh Kepala Tukang @ Rp 70,000.00 Rp 5,250.00
0.075 Oh Mandor @ Rp 70,000.00 Rp 5,250.00
Jumlah Rp 573,175.00
Dibulatkan Rp 573,100.00

SNI 2836:2007-6.9
1 M3 PASANGAN BATU KOSONG (AANSTAMPING)
1.200 M3 Batu Belah 15 cm/20 cm @ Rp 130,000.00 Rp 156,000.00
0.432 M3 Pasir Urug @ Rp 110,000.00 Rp 47,520.00
0.780 Oh Pekerja @ Rp 55,000.00 Rp 42,900.00
0.390 Oh Tukang Batu @ Rp 65,000.00 Rp 25,350.00
0.039 Oh Kepala Tukang @ Rp 70,000.00 Rp 2,730.00
0.039 Oh Mandor @ Rp 70,000.00 Rp 2,730.00
Jumlah Rp 277,230.00
Dibulatkan Rp 277,200.00

SNI DT-91-0007-2007-6.10
1 M3 PONDASI BETON CYCLOPEN, 60% Beton Campuran 1 Pc : 2 Pb : 3 Kr dan 40% Batu Belah
0.312 M3 Pasir Beton @ Rp 130,000.00 Rp 40,560.00
0.480 M3 Batu Belah 15 cm/20 cm @ Rp 130,000.00 Rp 62,400.00
0.468 M3 Kerikl Beton @ Rp 110,000.00 Rp 51,480.00
194.000 Kg Semen Portland @ Rp 1,275.00 Rp 247,350.00
3.000 Oh Pekerja @ Rp 55,000.00 Rp 165,000.00
0.850 Oh Tukang Batu @ Rp 65,000.00 Rp 55,250.00
0.085 Oh Kepala Tukang @ Rp 70,000.00 Rp 5,950.00
0.150 Oh Mandor @ Rp 70,000.00 Rp 10,500.00
Jumlah Rp 638,490.00
Dibulatkan Rp 638,400.00

PEKERJAAN BETON
SNI 7394:2007-6.1
Membuat 1 M3 beton mutu f'c = 7,4 Mpa (K 100), Slump (12 ± 2 ) cm, w/c = 0,87
247.000 Kg Semen Portland @ Rp 1,275.00 Rp 314,925.00
869.000 Kg Pasir Beton @ Rp 130.00 Rp 112,970.00
999.000 Kg Kerikil @ Rp 110.00 Rp 109,890.00
215.000 Liter Air @ Rp 25.00 Rp 5,375.00
1.650 Oh Pekerja @ Rp 55,000.00 Rp 90,750.00
0.275 Oh Tukang Batu @ Rp 65,000.00 Rp 17,875.00
0.028 Oh Kepala Tukang @ Rp 70,000.00 Rp 1,960.00
0.083 Oh Mandor @ Rp 70,000.00 Rp 5,810.00
Jumlah Rp 659,555.00
Dibulatkan Rp 659,500.00

SNI 7394:2007-6.2
Membuat 1 M3 beton mutu f'c = 9,8 Mpa (K 125), Slump (12 ± 2 ) cm, w/c = 0,78
276.000 Kg Semen Portland @ Rp 1,275.00 Rp 351,900.00
828.000 Kg Pasir Beton @ Rp 130.00 Rp 107,640.00
1012.000 Kg Kerikil @ Rp 110.00 Rp 111,320.00
215.000 Liter Air @ Rp 25.00 Rp 5,375.00
1.650 Oh Pekerja @ Rp 55,000.00 Rp 90,750.00
0.275 Oh Tukang Batu @ Rp 65,000.00 Rp 17,875.00
0.028 Oh Kepala Tukang @ Rp 70,000.00 Rp 1,960.00
0.083 Oh Mandor @ Rp 70,000.00 Rp 5,810.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

Jumlah Rp 692,630.00
Dibulatkan Rp 692,600.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

SNI 7394:2007-6.3
Membuat 1 M3 beton mutu f'c = 12,2 Mpa (K 150), Slump (12 ± 2 ) cm, w/c = 0,72
299.000 Kg Semen Portland @ Rp 1,275.00 Rp 381,225.00
799.000 Kg Pasir Beton @ Rp 130.00 Rp 103,870.00
1017.000 Kg Kerikil @ Rp 110.00 Rp 111,870.00
215.000 Liter Air @ Rp 25.00 Rp 5,375.00
1.650 Oh Pekerja @ Rp 55,000.00 Rp 90,750.00
0.275 Oh Tukang Batu @ Rp 65,000.00 Rp 17,875.00
0.028 Oh Kepala Tukang @ Rp 70,000.00 Rp 1,960.00
0.083 Oh Mandor @ Rp 70,000.00 Rp 5,810.00
Jumlah Rp 718,735.00
Dibulatkan Rp 718,700.00

SNI 7394:2007-6.4
Membuat 1 M3 lantai kerja beton mutu f'c = 7,4 Mpa (K 100), Slump (3-6) cm, w/c = 0,87
230.000 Kg Semen Portland @ Rp 1,275.00 Rp 293,250.00
893.000 Kg Pasir Beton @ Rp 130.00 Rp 116,090.00
1027.000 Kg Kerikil @ Rp 110.00 Rp 112,970.00
200.000 Liter Air @ Rp 25.00 Rp 5,000.00
1.200 Oh Pekerja @ Rp 55,000.00 Rp 66,000.00
0.200 Oh Tukang Batu @ Rp 65,000.00 Rp 13,000.00
0.020 Oh Kepala Tukang @ Rp 70,000.00 Rp 1,400.00
0.060 Oh Mandor @ Rp 70,000.00 Rp 4,200.00
Jumlah Rp 611,910.00
Dibulatkan Rp 611,900.00

SNI 7394:2007-6.5
Membuat 1 M3 beton mutu f'c = 14,5 Mpa (K 175), Slump (12 ± 2) cm, w/c = 0,66
326.000 Kg Semen Portland @ Rp 1,275.00 Rp 415,650.00
760.000 Kg Pasir Beton @ Rp 130.00 Rp 98,800.00
1029.000 Kg Kerikil @ Rp 110.00 Rp 113,190.00
215.000 Liter Air @ Rp 25.00 Rp 5,375.00
1.650 Oh Pekerja @ Rp 55,000.00 Rp 90,750.00
0.275 Oh Tukang Batu @ Rp 65,000.00 Rp 17,875.00
0.028 Oh Kepala Tukang @ Rp 70,000.00 Rp 1,960.00
0.083 Oh Mandor @ Rp 70,000.00 Rp 5,810.00
Jumlah Rp 749,410.00
Dibulatkan Rp 749,400.00

SNI 7394:2007-6.6
Membuat 1 M3 beton mutu f'c = 16,9 Mpa (K 200), Slump (12 ± 2) cm, w/c = 0,61
352.000 Kg Semen Portland @ Rp 1,275.00 Rp 448,800.00
731.000 Kg Pasir Beton @ Rp 130.00 Rp 95,030.00
1031.000 Kg Kerikil @ Rp 110.00 Rp 113,410.00
215.000 Liter Air @ Rp 25.00 Rp 5,375.00
1.650 Oh Pekerja @ Rp 55,000.00 Rp 90,750.00
0.275 Oh Tukang Batu @ Rp 65,000.00 Rp 17,875.00
0.028 Oh Kepala Tukang @ Rp 70,000.00 Rp 1,960.00
0.083 Oh Mandor @ Rp 70,000.00 Rp 5,810.00
Jumlah Rp 779,010.00
Dibulatkan Rp 779,000.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

SNI 7394:2007-6.7
Membuat 1 M3 beton mutu f'c = 19,3 Mpa (K 225), Slump (12 ± 2) cm, w/c = 0,58
371.000 Kg Semen Portland @ Rp 1,275.00 Rp 473,025.00
698.000 Kg Pasir Beton @ Rp 130.00 Rp 90,740.00
1047.000 Kg Kerikil @ Rp 110.00 Rp 115,170.00
215.000 Liter Air @ Rp 25.00 Rp 5,375.00
1.650 Oh Pekerja @ Rp 55,000.00 Rp 90,750.00
0.275 Oh Tukang Batu @ Rp 65,000.00 Rp 17,875.00
0.028 Oh Kepala Tukang @ Rp 70,000.00 Rp 1,960.00
0.083 Oh Mandor @ Rp 70,000.00 Rp 5,810.00
Jumlah Rp 800,705.00
Dibulatkan Rp 800,700.00
SNI 7394:2007-6.8
Membuat 1 M3 beton mutu f'c = 21,7 Mpa (K 250), Slump (12 ± 2) cm, w/c = 0,56
384.000 Kg Semen Portland @ Rp 1,275.00 Rp 489,600.00
692.000 Kg Pasir Beton @ Rp 130.00 Rp 89,960.00
1039.000 Kg Kerikil @ Rp 110.00 Rp 114,290.00
215.000 Liter Air @ Rp 25.00 Rp 5,375.00
1.650 Oh Pekerja @ Rp 55,000.00 Rp 90,750.00
0.275 Oh Tukang Batu @ Rp 65,000.00 Rp 17,875.00
0.028 Oh Kepala Tukang @ Rp 70,000.00 Rp 1,960.00
0.083 Oh Mandor @ Rp 70,000.00 Rp 5,810.00
Jumlah Rp 815,620.00
Dibulatkan Rp 815,600.00

SNI 7394:2007-6.9
Membuat 1 M3 beton mutu f'c = 24,0 Mpa (K 275), Slump (12 ± 2) cm, w/c = 0,53
406.000 Kg Semen Portland @ Rp 1,275.00 Rp 517,650.00
684.000 Kg Pasir Beton @ Rp 130.00 Rp 88,920.00
1026.000 Kg Kerikil @ Rp 110.00 Rp 112,860.00
215.000 Liter Air @ Rp 25.00 Rp 5,375.00
1.650 Oh Pekerja @ Rp 55,000.00 Rp 90,750.00
0.275 Oh Tukang Batu @ Rp 65,000.00 Rp 17,875.00
0.028 Oh Kepala Tukang @ Rp 70,000.00 Rp 1,960.00
0.083 Oh Mandor @ Rp 70,000.00 Rp 5,810.00
Jumlah Rp 841,200.00
Dibulatkan Rp 841,200.00

SNI 7394:2007-6.10
Membuat 1 M3 beton mutu f'c = 26,4 Mpa (K 300), Slump (12 ± 2) cm, w/c = 0,52
413.000 Kg Semen Portland @ Rp 1,275.00 Rp 526,575.00
681.000 Kg Pasir Beton @ Rp 130.00 Rp 88,530.00
1021.000 Kg Kerikil @ Rp 110.00 Rp 112,310.00
215.000 Liter Air @ Rp 25.00 Rp 5,375.00
1.650 Oh Pekerja @ Rp 55,000.00 Rp 90,750.00
0.275 Oh Tukang Batu @ Rp 65,000.00 Rp 17,875.00
0.028 Oh Kepala Tukang @ Rp 70,000.00 Rp 1,960.00
0.083 Oh Mandor @ Rp 70,000.00 Rp 5,810.00
Jumlah Rp 849,185.00
Dibulatkan Rp 849,100.00

SNI 7394:2007-6.11
Membuat 1 M3 beton mutu f'c = 28,8 Mpa (K 325), Slump (12 ± 2) cm, w/c = 0,49
439.000 Kg Semen Portland @ Rp 1,275.00 Rp 559,725.00
670.000 Kg Pasir Beton @ Rp 130.00 Rp 87,100.00
1006.000 Kg Kerikil @ Rp 110.00 Rp 110,660.00
215.000 Liter Air @ Rp 25.00 Rp 5,375.00
2.100 Oh Pekerja @ Rp 55,000.00 Rp 115,500.00
0.350 Oh Tukang Batu @ Rp 65,000.00 Rp 22,750.00
0.035 Oh Kepala Tukang @ Rp 70,000.00 Rp 2,450.00
0.105 Oh Mandor @ Rp 70,000.00 Rp 7,350.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

Jumlah Rp 910,910.00
Dibulatkan Rp 910,900.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

SNI 7394:2007-6.12
Membuat 1 M3 beton mutu f'c = 31,2 Mpa (K 350), Slump (12 ± 2) cm, w/c = 0,48
448.000 Kg Semen Portland @ Rp 1,275.00 Rp 571,200.00
667.000 Kg Pasir Beton @ Rp 130.00 Rp 86,710.00
1000.000 Kg Kerikil @ Rp 110.00 Rp 110,000.00
215.000 Liter Air @ Rp 25.00 Rp 5,375.00
2.100 Oh Pekerja @ Rp 55,000.00 Rp 115,500.00
0.350 Oh Tukang Batu @ Rp 65,000.00 Rp 22,750.00
0.035 Oh Kepala Tukang @ Rp 70,000.00 Rp 2,450.00
0.105 Oh Mandor @ Rp 70,000.00 Rp 7,350.00
Jumlah Rp 921,335.00
Dibulatkan Rp 921,300.00

SNI 7394:2007-6.17
Pembesian 10 kg dengan besi polos atau besi ulir
10.500 Kg Besi Beton polos / ulir @ Rp 20,000.00 Rp 210,000.00
0.150 Kg Kawat Beton @ Rp 20,000.00 Rp 3,000.00
0.070 Oh Pekerja @ Rp 55,000.00 Rp 3,850.00
0.070 Oh Tukang Besi @ Rp 65,000.00 Rp 4,550.00
0.007 Oh Kepala Tukang @ Rp 70,000.00 Rp 490.00
0.004 Oh Mandor @ Rp 70,000.00 Rp 280.00
Jumlah Rp 222,170.00
Untuk Per 1 Kg.................................... Rp 22,217.00
Dibulatkan Rp 22,200.00

SNI 7394:2007-6.20
1 M2 BEKISTING UNTUK PONDASI
0.040 M3 Kayu Kelas III @ Rp 3,200,000.00 Rp 128,000.00
0.300 Kg Paku 5 cm - 10 cm @ Rp 17,000.00 Rp 5,100.00
0.100 Ltr Minyak Bekisting @ Rp 50,000.00 Rp 5,000.00
0.520 Oh Pekerja @ Rp 55,000.00 Rp 28,600.00
0.260 Oh Tukang Kayu @ Rp 65,000.00 Rp 16,900.00
0.026 Oh Kepala Tukang @ Rp 70,000.00 Rp 1,820.00
0.026 Oh Mandor @ Rp 70,000.00 Rp 1,820.00
Jumlah Rp 187,240.00
Digunakan 2 x Pakai........................... Rp 93,620.00
Dibulatkan Rp 93,600.00

SNI 7394:2007-6.21
1 M2 BEKISTING UNTUK SLOOF
0.045 M3 Kayu Kelas III @ Rp 3,200,000.00 Rp 144,000.00
0.300 Kg Paku 2" - 5 " @ Rp 17,000.00 Rp 5,100.00
0.100 Ltr Minyak Bekisting @ Rp 50,000.00 Rp 5,000.00
0.520 Oh Pekerja @ Rp 55,000.00 Rp 28,600.00
0.260 Oh Tukang Kayu @ Rp 65,000.00 Rp 16,900.00
0.026 Oh Kepala Tukang @ Rp 70,000.00 Rp 1,820.00
0.026 Oh Mandor @ Rp 70,000.00 Rp 1,820.00
Jumlah Rp 203,240.00
Digunakan 2 x Pakai........................... Rp 101,620.00
Dibulatkan Rp 101,600.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

SNI 7394:2007-6.22
1 M2 BEKISTING UNTUK KOLOM
0.040 M3 Kayu Kelas III @ Rp 3,200,000.00 Rp 128,000.00
0.400 Kg Paku 5 cm - 12 cm @ Rp 17,000.00 Rp 6,800.00
0.200 Ltr Minyak Bekisting @ Rp 50,000.00 Rp 10,000.00
0.015 M3 Balok Kayu Klas II @ Rp 4,000,000.00 Rp 60,000.00
0.350 Lembar Plywood Tebal 9 mm @ Rp 130,000.00 Rp 45,500.00
2.000 Batang Dolken Kayu Galam, Ø 8-10 Panjang 4 m @ Rp 200,000.00 Rp 400,000.00
0.660 Oh Pekerja @ Rp 55,000.00 Rp 36,300.00
0.330 Oh Tukang Kayu @ Rp 65,000.00 Rp 21,450.00
0.033 Oh Kepala tukang @ Rp 70,000.00 Rp 2,310.00
0.033 Oh Mandor @ Rp 70,000.00 Rp 2,310.00
Jumlah Rp 712,670.00
Digunakan 2 x Pakai........................... Rp 356,335.00
Dibulatkan Rp 356,300.00

SNI 7394:2007-6.23
MEMASANG M2 BEKISTING UNTUK BALOK
0.040 M3 Kayu Kelas III @ Rp 3,200,000.00 Rp 128,000.00
0.400 Kg Paku 5 cm - 12 cm @ Rp 17,000.00 Rp 6,800.00
0.200 Ltr Minyak Bekisting @ Rp 50,000.00 Rp 10,000.00
0.018 M3 Balok Kayu Klas II @ Rp 4,000,000.00 Rp 72,000.00
0.350 Lembar Plywood Tebal 9 mm @ Rp 130,000.00 Rp 45,500.00
2.000 Batang Dolken Kayu Galam, Ø 8-10 Panjang 4 m @ Rp 200,000.00 Rp 400,000.00
0.660 Oh Pekerja @ Rp 55,000.00 Rp 36,300.00
0.330 Oh Tukang Kayu @ Rp 65,000.00 Rp 21,450.00
0.033 Oh Kepala tukang @ Rp 70,000.00 Rp 2,310.00
0.033 Oh Mandor @ Rp 70,000.00 Rp 2,310.00
Jumlah Rp 724,670.00
Digunakan 2 x Pakai........................... Rp 362,335.00
Dibulatkan Rp 362,300.00

SNI 7394:2007-6.24
MEMASANG M2 BEKISTING UNTUK PLAT LANTAI
0.040 M3 Kayu Kelas III @ Rp 3,200,000.00 Rp 128,000.00
0.400 Kg Paku 5 cm - 12 cm @ Rp 17,000.00 Rp 6,800.00
0.200 Ltr Minyak Bekisting @ Rp 50,000.00 Rp 10,000.00
0.015 M3 Balok Kayu Klas II @ Rp 4,000,000.00 Rp 60,000.00
0.350 Lembar Plywood Tebal 9 mm @ Rp 130,000.00 Rp 45,500.00
6.000 Batang Dolken Kayu Galam, Ø 8-10 Panjang 4 m @ Rp 200,000.00 Rp 1,200,000.00
0.660 Oh Pekerja @ Rp 55,000.00 Rp 36,300.00
0.330 Oh Tukang Kayu @ Rp 65,000.00 Rp 21,450.00
0.033 Oh Kepala tukang @ Rp 70,000.00 Rp 2,310.00
0.033 Oh Mandor @ Rp 70,000.00 Rp 2,310.00
Jumlah Rp 1,512,670.00
Digunakan 2 x Pakai........................... Rp 756,335.00
Dibulatkan Rp 756,300.00

SNI 7394:2007-6.25
MEMASANG M2 BEKISTING UNTUK DINDING
0.030 M3 Kayu Kelas III @ Rp 3,200,000.00 Rp 96,000.00
0.400 Kg Paku 5 cm - 12 cm @ Rp 15,000.00 Rp 6,000.00
0.200 Ltr Minyak Bekisting @ Rp 50,000.00 Rp 10,000.00
0.020 M3 Balok Kayu Klas II @ Rp 4,000,000.00 Rp 80,000.00
0.350 Lembar Plywood Tebal 9 mm @ Rp 130,000.00 Rp 45,500.00
3.000 Batang Dolken Kayu Galam, Ø 8-10 Panjang 4 m @ Rp 200,000.00 Rp 600,000.00
4.000 Bh Formite/Penjaga Jarak Bekisting/Spacer @ Rp 500.00 Rp 2,000.00
0.660 Oh Pekerja @ Rp 55,000.00 Rp 36,300.00
0.330 Oh Tukang Kayu @ Rp 65,000.00 Rp 21,450.00
0.033 Oh Kepala tukang @ Rp 70,000.00 Rp 2,310.00
0.033 Oh Mandor @ Rp 70,000.00 Rp 2,310.00
Jumlah Rp 901,870.00
Digunakan 2 x Pakai........................... Rp 450,935.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

Dibulatkan Rp 450,900.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

SNI 7394:2007-6.26
MEMASANG M2 BEKISTING UNTUK TANGGA
0.030 M3 Kayu Kelas III @ Rp 3,200,000.00 Rp 96,000.00
0.400 Kg Paku 5 cm - 12 cm @ Rp 15,000.00 Rp 6,000.00
0.150 Ltr Minyak Bekisting @ Rp 50,000.00 Rp 7,500.00
0.015 M3 Balok Kayu Klas II @ Rp 4,000,000.00 Rp 60,000.00
0.350 Lembar Plywood Tebal 9 mm @ Rp 130,000.00 Rp 45,500.00
2.000 Batang Dolken Kayu Galam, Ø 8-10 Panjang 4 m @ Rp 200,000.00 Rp 400,000.00
4.000 Bh Formite/Penjaga Jarak Bekisting/Spacer @ Rp 500.00 Rp 2,000.00
0.660 Oh Pekerja @ Rp 55,000.00 Rp 36,300.00
0.330 Oh Tukang Kayu @ Rp 65,000.00 Rp 21,450.00
0.033 Oh Kepala tukang @ Rp 70,000.00 Rp 2,310.00
0.033 Oh Mandor @ Rp 70,000.00 Rp 2,310.00
Jumlah Rp 679,370.00
Digunakan 2 x Pakai........................... Rp 339,685.00
Dibulatkan Rp 339,600.00

SNI 7394:2007-6.28
MEMASANG 1 M3 PONDASI BETON BERTULANG (150 kg Besi + Bekisting)
0.200 M3 Kayu Kelas III (Papan) @ Rp 3,600,000.00 Rp 720,000.00
1.500 Kg Paku 5 cm - 12 cm @ Rp 15,000.00 Rp 22,500.00
0.400 Ltr Minyak Bekisting @ Rp 50,000.00 Rp 20,000.00
157.000 Kg Besi Beton Polos @ Rp 20,000.00 Rp 3,140,000.00
2.250 Kg Kawat Beton @ Rp 1,275.00 Rp 2,868.75
336.000 Kg Semen Portland @ Rp 1,830.00 Rp 614,880.00
0.540 M3 Pasir Beton @ Rp 150,000.00 Rp 81,000.00
0.810 M3 Kerikil @ Rp 110,000.00 Rp 89,100.00
5.300 Oh Pekerja @ Rp 62,000.00 Rp 328,600.00
0.275 Oh Tukang Batu @ Rp 85,000.00 Rp 23,375.00
1.300 Oh Tukang Kayu @ Rp 85,000.00 Rp 110,500.00
1.050 Oh Tukang Besi @ Rp 85,000.00 Rp 89,250.00
0.262 Oh Kepala tukang @ Rp 105,000.00 Rp 27,510.00
0.265 Oh Mandor @ Rp 80,000.00 Rp 21,200.00
Jumlah Rp 5,290,783.75
Dibulatkan Rp 5,290,700.00

SNI 7394:2007-6.29
MEMASANG 1 M3 PONDASI BETON BERTULANG (2000 kg Besi + Bekisting)
0.270 M3 Kayu Kelas III (Papan) @ Rp 3,600,000.00 Rp 972,000.00
2.000 Kg Paku 5 cm - 12 cm @ Rp 15,000.00 Rp 30,000.00
0.600 Ltr Minyak Bekisting @ Rp 50,000.00 Rp 30,000.00
210.000 Kg Besi Beton Polos @ Rp 20,000.00 Rp 4,200,000.00
3.000 Kg Kawat Beton @ Rp 1,275.00 Rp 3,825.00
336.000 Kg Semen Portland @ Rp 1,830.00 Rp 614,880.00
0.540 M3 Pasir Beton @ Rp 150,000.00 Rp 81,000.00
0.810 M3 Kerikil @ Rp 110,000.00 Rp 89,100.00
5.650 Oh Pekerja @ Rp 62,000.00 Rp 350,300.00
0.275 Oh Tukang Batu @ Rp 85,000.00 Rp 23,375.00
1.560 Oh Tukang Kayu @ Rp 85,000.00 Rp 132,600.00
1.400 Oh Tukang Besi @ Rp 85,000.00 Rp 119,000.00
0.323 Oh Kepala tukang @ Rp 105,000.00 Rp 33,915.00
0.283 Oh Mandor @ Rp 80,000.00 Rp 22,640.00
Jumlah Rp 6,702,635.00
Dibulatkan Rp 6,702,600.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

SNI-3435-6.37
1 M3 PASANG BEGESTING UNTUK PENYANGGA STURT WERK
0.0260 M3 Kayu Kelas III (Begesting) @ Rp 3,600,000.00 Rp 93,600.00
0.6000 Kg Paku 5 cm - 12 cm @ Rp 15,000.00 Rp 9,000.00
0.5000 Btg Kayu Perancah @ Rp 200,000.00 Rp 100,000.00
6.0000 Oh Pekerja @ Rp 62,000.00 Rp 372,000.00
1.0000 Oh Tukang Kayu @ Rp 85,000.00 Rp 85,000.00
0.1000 Oh Kepala tukang @ Rp 105,000.00 Rp 10,500.00
0.3000 Oh Mandor @ Rp 80,000.00 Rp 24,000.00
Jumlah Rp 694,100.00
Digunakan 2 x Pakai........................... Rp 347,050.00
Dibulatkan Rp 347,000.00

Pekerjaan Lain - Lain


Membongkar dan Menyiram Beton
1.000 Ls Membongkar dan Menyiram Beton @ Rp 62,000.00 Rp 62,000.00
Jumlah Rp 62,000.00

REKAPITULASI PEKERJAAN BETON

SUPLEMEN 11
1 M3 BETON BERTULANG
Kolom Praktis Uk. 13/13
1.0000 M3 Beton Cor SNI 7394:2008-6.8 @ Rp 815,600.00 Rp 815,600.00
206.6000 Kg Pembesian SNI 7394:2008-6.17 @ Rp 22,200.00 Rp 4,586,520.00
15.3800 M2 Begisting SNI 7394:2008-6.22 @ Rp 356,300.00 Rp 5,479,894.00
1.0000 Ls Membongkar dan Menyiram Pekerjaan Lain-Lain @ Rp 62,000.00 Rp 62,000.00
Jumlah Rp 10,944,014.00
Dibulatkan Rp 10,944,000.00

SUPLEMEN 12
1 M3 BETON BERTULANG
Kolom Uk. 20/20
1.0000 M3 Beton Cor K225 SNI 7394:2008-6.8 @ Rp 800,700.00 Rp 800,700.00
195.4200 Kg Pembesian SNI 7394:2008-6.17 @ Rp 22,200.00 Rp 4,338,324.00
10.0000 M2 Begisting SNI 7394:2008-6.22 @ Rp 356,300.00 Rp 3,563,000.00
1.0000 Ls Membongkar dan Menyiram Pekerjaan Lain-Lain @ Rp 62,000.00 Rp 62,000.00
Jumlah Rp 8,764,024.00
Dibulatkan Rp 8,764,000.00

SUPLEMEN 16
1 M3 BETON BERTULANG
Balok Sloof uk. 20/25
1.0000 M3 Beton Cor SNI 7394:2008-6.8 @ Rp 815,600.00 Rp 815,600.00
151.8000 Kg Pembesian SNI 7394:2008-6.17 @ Rp 22,200.00 Rp 3,369,960.00
10.0000 M2 Begisting SNI 7394:2008-6.21 @ Rp 101,600.00 Rp 1,016,000.00
1.0000 Ls Membongkar dan Menyiram Pekerjaan Lain-Lain @ Rp 62,000.00 Rp 62,000.00
Jumlah Rp 5,263,560.00
Dibulatkan Rp 5,263,500.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

SUPLEMEN 23
1 M3 BETON BERTULANG
Balok Sloof / Ring /Latei Uk.13/13
1.0000 M3 Beton Cor SNI 7394:2008-6.8 @ Rp 815,600.00 Rp 815,600.00
243.0600 Kg Pembesian SNI 7394:2008-6.17 @ Rp 22,200.00 Rp 5,395,932.00
4.0000 M2 Begisting SNI 7394:2008-6.21 @ Rp 101,600.00 Rp 406,400.00
1.0000 Ls Membongkar dan Menyiram Pekerjaan Lain-Lain @ Rp 62,000.00 Rp 62,000.00
Jumlah Rp 6,679,932.00
Dibulatkan Rp 6,679,900.00

SUPLEMEN 28
1 M3 BETON BERTULANG
Balok Ring Uk. 15/18
1.0000 M3 Beton Cor SNI 7394:2008-6.8 @ Rp 815,600.00 Rp 815,600.00
164.6100 Kg Pembesian SNI 7394:2008-6.17 @ Rp 22,200.00 Rp 3,654,342.00
6.6670 M2 Begisting SNI 7394:2008-6.23 @ Rp 362,300.00 Rp 2,415,454.10
1.0000 Ls Membongkar dan Menyiram Pekerjaan Lain-Lain @ Rp 62,000.00 Rp 62,000.00
Jumlah Rp 6,947,396.10
Dibulatkan Rp 6,947,300.00

SUPLEMEN 32
1 M3 BETON BERTULANG
Balok Lintel 13/15
1.0000 M3 Beton Cor SNI 7394:2008-6.8 @ Rp 815,600.00 Rp 815,600.00
188.9800 Kg Pembesian SNI 7394:2008-6.17 @ Rp 22,200.00 Rp 4,195,356.00
15.3000 M2 Begisting SNI 7394:2008-6.23 @ Rp 362,300.00 Rp 5,543,190.00
1.0000 Ls Membongkar dan Menyiram Pekerjaan Lain-Lain @ Rp 62,000.00 Rp 62,000.00
Jumlah Rp 10,616,146.00
Dibulatkan Rp 10,616,100.00

SUPLEMEN 34
1 M3 BETON BERTULANG
Plat Luifel / Plat kanopy t. 0,8 cm
1.0000 M3 Beton Cor SNI 7394:2008-6.8 @ Rp 815,600.00 Rp 815,600.00
133.1000 Kg Pembesian SNI 7394:2008-6.17 @ Rp 22,200.00 Rp 2,954,820.00
5.0000 M2 Begisting SNI 7394:2008-6.23 @ Rp 362,300.00 Rp 1,811,500.00
2.5000 Ls Sturt werk SNI-3435-6.37 @ Rp 347,000.00 Rp 867,500.00
1.0000 Ls Membongkar dan Menyiram Pekerjaan Lain-Lain @ Rp 62,000.00 Rp 62,000.00
Jumlah Rp 6,511,420.00
Dibulatkan Rp 6,511,400.00

SUPLEMEN 35
1 M3 BETON BERTULANG
Plat Luifel / Plat kanopy t.0,80 cm
1.0000 M3 Beton Cor SNI 7394:2008-6.8 @ Rp 815,600.00 Rp 815,600.00
105.1700 Kg Pembesian SNI 7394:2008-6.17 @ Rp 22,200.00 Rp 2,334,774.00
5.0000 M2 Begisting SNI 7394:2008-6.23 @ Rp 362,300.00 Rp 1,811,500.00
2.5000 Ls Sturt werk SNI-3435-6.37 @ Rp 347,000.00 Rp 867,500.00
1.0000 Ls Membongkar dan Menyiram Pekerjaan Lain-Lain @ Rp 62,000.00 Rp 62,000.00
Jumlah Rp 5,891,374.00
Dibulatkan Rp 5,891,300.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

PEKERJAAN DINDING
SNI 6897-2007-6.7
1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA ADUKAN 1 Pc : 2 PP
0.038 M3 Pasir Pasang @ Rp 130,000.00 Rp 4,940.00
70.000 Buah Batu Bata @ Rp 550.00 Rp 38,500.00
18.950 Kg Semen Portland @ Rp 1,275.00 Rp 24,161.25
0.300 Oh Pekerja @ Rp 62,000.00 Rp 18,600.00
0.100 Oh Tukang Batu @ Rp 85,000.00 Rp 8,500.00
0.010 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,050.00
0.015 Oh Mandor @ Rp 80,000.00 Rp 1,200.00
Jumlah Rp 96,951.25
Dibulatkan Rp 96,900.00

SNI 6897-2007-6.9
1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA ADUKAN 1 Pc : 4 PP
0.043 M3 Pasir Pasang @ Rp 130,000.00 Rp 5,590.00
70.000 Buah Batu Bata @ Rp 550.00 Rp 38,500.00
11.500 Kg Semen Portland @ Rp 1,275.00 Rp 14,662.50
0.300 Oh Pekerja @ Rp 62,000.00 Rp 18,600.00
0.100 Oh Tukang Batu @ Rp 85,000.00 Rp 8,500.00
0.010 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,050.00
0.015 Oh Mandor @ Rp 80,000.00 Rp 1,200.00
Jumlah Rp 88,102.50
Dibulatkan Rp 88,100.00

PEKERJAAN PLESTERAN
SNI 2837-2007.6.2
MEMASANG 1 M2 PLESTERAN 1 Pc : 2 PP : TEBAL 15 mm
0.020 M3 Pasir Pasang @ Rp 130,000.00 Rp 2,600.00
10.224 Kg Semen Portland @ Rp 1,275.00 Rp 13,035.60
0.300 Oh Pekerja @ Rp 62,000.00 Rp 18,600.00
0.150 Oh Tukang Batu @ Rp 85,000.00 Rp 12,750.00
0.015 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,575.00
0.015 Oh Mandor @ Rp 80,000.00 Rp 1,200.00
Jumlah Rp 49,760.60
Dibulatkan Rp 49,700.00

SNI 2837-2007.6.4
MEMASANG 1 M2 PLESTERAN 1 Pc : 4 PP : TEBAL 15 mm
0.024 M3 Pasir Pasang @ Rp 130,000.00 Rp 3,120.00
6.240 Kg Semen Portland @ Rp 1,275.00 Rp 7,956.00
0.200 Oh Pekerja @ Rp 62,000.00 Rp 12,400.00
0.150 Oh Tukang Batu @ Rp 85,000.00 Rp 12,750.00
0.015 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,575.00
0.015 Oh Mandor @ Rp 80,000.00 Rp 1,200.00
Jumlah Rp 39,001.00
Dibulatkan Rp 39,000.00

PEKERJAAN KAYU
SNI DT-91-0011-2007-6.2
MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU, KAYU KELAS - II/III
1.200 M3 Bahan Kayu Kelas - II @ Rp 4,000,000.00 Rp 4,800,000.00
1.000 Kg Lem kayu @ Rp 20,000.00 Rp 20,000.00
1.250 Kg Paku Biasa 10 cm @ Rp 15,000.00 Rp 18,750.00
6.000 Oh Pekerja @ Rp 62,000.00 Rp 372,000.00
18.000 Oh Tukang Kayu @ Rp 85,000.00 Rp 1,530,000.00
1.800 Oh Kepala Tukang @ Rp 105,000.00 Rp 189,000.00
0.300 Oh Mandor @ Rp 80,000.00 Rp 24,000.00
Jumlah Rp 6,953,750.00
Dibulatkan Rp 6,953,700.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

SNI DT-91-0011-2007-6.5
MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU KELAS II
0.040 M3 Papan Kayu Kelas II @ Rp 4,000,000.00 Rp 160,000.00
0.500 Kg Lem kayu @ Rp 20,000.00 Rp 10,000.00
1.000 Oh Pekerja @ Rp 62,000.00 Rp 62,000.00
3.000 Oh Tukang Kayu @ Rp 85,000.00 Rp 255,000.00
0.300 Oh Kepala Tukang @ Rp 105,000.00 Rp 31,500.00
0.050 Oh Mandor @ Rp 80,000.00 Rp 4,000.00
Jumlah Rp 522,500.00
Dibulatkan Rp 522,500.00

SNI DT-91-0011-2007-6.6
MEMBUAT DAN MEMASANG 1 M2 PINTU dan JENDELA KACA, KAYU KELAS II
0.024 M3 Papan Kayu Kelas II @ Rp 4,000,000.00 Rp 96,000.00
0.300 Kg Lem kayu @ Rp 20,000.00 Rp 6,000.00
0.800 Oh Pekerja @ Rp 62,000.00 Rp 49,600.00
2.400 Oh Tukang Kayu @ Rp 85,000.00 Rp 204,000.00
0.240 Oh Kepala Tukang @ Rp 105,000.00 Rp 25,200.00
0.040 Oh Mandor @ Rp 80,000.00 Rp 3,200.00
Jumlah Rp 384,000.00
Dibulatkan Rp 384,000.00

SNI DT-91-0011-2007-6.19.a
MEMASANG 1 M2 RANGKA FURING t=0,4 mm
4.000 M' Rangka Furing 0,4 @ Rp 12,500.00 Rp 50,000.00
0.115 Kg Skrup @ Rp 6,000.00 Rp 690.00
0.150 Oh Pekerja @ Rp 62,000.00 Rp 9,300.00
0.300 Oh Tukang Kayu @ Rp 85,000.00 Rp 25,500.00
0.030 Oh Kepala Tukang @ Rp 105,000.00 Rp 3,150.00
0.075 Oh Mandor @ Rp 80,000.00 Rp 6,000.00
Jumlah Rp 94,640.00
Dibulatkan Rp 94,600.00

SNI DT-91-0011-2007-6.22
MEMASANG 1 M' LISTPLANK UKURAN 3 x 30 cm
0.011 M3 Papan Kayu Kelas - I @ Rp 5,000,000.00 Rp 55,000.00
0.050 Kg Paku Biasa 5 cm - 7 cm @ Rp 15,000.00 Rp 750.00
0.100 Oh Pekerja @ Rp 62,000.00 Rp 6,200.00
0.200 Oh Tukang Kayu @ Rp 85,000.00 Rp 17,000.00
0.025 Oh Kepala Tukang @ Rp 105,000.00 Rp 2,625.00
0.005 Oh Mandor @ Rp 80,000.00 Rp 400.00
Jumlah Rp 81,975.00
Dibulatkan Rp 81,900.00

IX. PEKERJAAN PENUTUP LANTAI DAN DINDING


SNI DT-91-0012-2007-6.36
MEMASANG 1 M2 LANTAI KERAMIK 20 x 20 cm UNPOLISHED
26.500 Buah Keramik 20 x 20 cm Unpolished @ Rp 3,500.00 Rp 92,750.00
10.400 Kg Semen Portland @ Rp 1,275.00 Rp 13,260.00
0.045 M3 Pasir Pasang @ Rp 130,000.00 Rp 5,850.00
1.620 Kg Semen Warna @ Rp 2,400.00 Rp 3,888.00
0.700 Oh Pekerja @ Rp 62,000.00 Rp 43,400.00
0.350 Oh Tukang Batu @ Rp 85,000.00 Rp 29,750.00
0.035 Oh Kepala Tukang @ Rp 105,000.00 Rp 3,675.00
0.035 Oh Mandor @ Rp 80,000.00 Rp 2,800.00
Jumlah Rp 195,373.00
Dibulatkan Rp 195,300.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

SNI DT-91-0012-2007-6.54
1 M2 DINDING KERAMIK 20 x 25 cm POLISHED
20.000 Buah Keramik 20 x 25 cm Polished @ Rp 5,000.00 Rp 100,000.00
9.300 Kg Semen Portland @ Rp 1,275.00 Rp 11,857.50
0.018 M3 Pasir Pasang @ Rp 130,000.00 Rp 2,340.00
1.940 Kg Semen Warna @ Rp 2,400.00 Rp 4,656.00
0.600 Oh Pekerja @ Rp 62,000.00 Rp 37,200.00
0.450 Oh Tukang Batu @ Rp 85,000.00 Rp 38,250.00
0.045 Oh Kepala Tukang @ Rp 105,000.00 Rp 4,725.00
0.03 Oh Mandor @ Rp 80,000.00 Rp 2,400.00
Jumlah Rp 201,428.50
Dibulatkan Rp 201,400.00

SNI DT-91-0012-2007-6.64
MEMASANG 1 M2 LANTAI KERAMIK 40 x 40 cm POLISHED
6.250 Buah Keramik 40 x 40 cm Polished @ Rp 15,000.00 Rp 93,750.00
10.000 Kg Semen Portland @ Rp 1,275.00 Rp 12,750.00
0.045 M3 Pasir Pasang @ Rp 130,000.00 Rp 5,850.00
1.500 Kg Semen Warna @ Rp 2,400.00 Rp 3,600.00
0.620 Oh Pekerja @ Rp 62,000.00 Rp 38,440.00
0.350 Oh Tukang Batu @ Rp 85,000.00 Rp 29,750.00
0.035 Oh Kepala Tukang @ Rp 105,000.00 Rp 3,675.00
0.03 Oh Mandor @ Rp 80,000.00 Rp 2,400.00
Jumlah Rp 190,215.00
Dibulatkan Rp 190,200.00

SNI DT-91-0013-2007-6.7
MEMASANG 1 M2 LANGIT-LANGIT GYPSUMBOARD TEBAL 9 mm
0.364 Lbr GypsumBoard T.9 mm @ Rp 87,000.00 Rp 31,668.00
0.110 Kg Paku Sekrup @ Rp 6,000.00 Rp 660.00
0.100 Oh Pekerja @ Rp 62,000.00 Rp 6,200.00
0.100 Oh Tukang @ Rp 85,000.00 Rp 8,500.00
0.010 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,050.00
0.050 Oh Mandor @ Rp 80,000.00 Rp 4,000.00
Jumlah Rp 52,078.00
Dibulatkan Rp 52,000.00

SNI DT-91-0014-2007-6.11
MEMASANG 1 M' KUSEN ALUMUNIUM
1.100 M1 Profil Alumunium @ Rp 22,000.00 Rp 24,200.00
2.000 Bh Skrup fixer @ Rp 400.00 Rp 800.00
0.060 Tub Sealant @ Rp 4,000.00 Rp 240.00
0.043 Oh Pekerja @ Rp 62,000.00 Rp 2,666.00
0.043 Oh Tukang @ Rp 85,000.00 Rp 3,655.00
0.004 Oh Kepala Tukang @ Rp 105,000.00 Rp 420.00
0.002 Oh Mandor @ Rp 80,000.00 Rp 160.00
Jumlah Rp 32,141.00
Dibulatkan Rp 32,100.00

RSNI T-15-2002-B.2
1 BUAH KLOSET JONGKOK PORSELEN
1.000 Buah Kloset Jongkok Porselen @ Rp 153,000.00 Rp 153,000.00
0.010 M3 Pasir Pasang @ Rp 130,000.00 Rp 1,300.00
6.000 Kg Semen Portland @ Rp 1,275.00 Rp 7,650.00
1.000 Oh Pekerja @ Rp 62,000.00 Rp 62,000.00
1.500 Oh Tukang @ Rp 85,000.00 Rp 127,500.00
1.500 Oh Kepala Tukang @ Rp 105,000.00 Rp 157,500.00
0.160 Oh Mandor @ Rp 80,000.00 Rp 12,800.00
Jumlah Rp 521,750.00
Dibulatkan Rp 521,700.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

RSNI T-15-2002-B.26
Memasang 1 M' Pipa PVC Tipe AW Ø 3/4"
1.100 M' Pipa PVC Tipe AWØ 3/4" @ Rp 45,000.00 Rp 49,500.00
25.000 % Harga Pipa untuk Perlengkapan @ Rp 11,250.00 Rp 281,250.00
0.036 Oh Pekerja @ Rp 62,000.00 Rp 2,232.00
0.060 Oh Tukang @ Rp 85,000.00 Rp 5,100.00
0.006 Oh Kepala Tukang @ Rp 105,000.00 Rp 630.00
0.0018 Oh Mandor @ Rp 80,000.00 Rp 144.00
Jumlah Rp 338,856.00
Dibulatkan Rp 338,800.00

RSNI T-15-2002-B.31
Memasang 1 M' Pipa PVC Tipe AW Ø 3"
1.200 M' Pipa PVC Tipe AWØ 3" @ Rp 151,000.00 Rp 181,200.00
30.000 % Harga Pipa untuk Perlengkapan @ Rp 45,300.00 Rp 1,359,000.00
0.081 Oh Pekerja @ Rp 62,000.00 Rp 5,022.00
0.135 Oh Tukang @ Rp 85,000.00 Rp 11,475.00
0.0135 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,417.50
0.0041 Oh Mandor @ Rp 80,000.00 Rp 328.00
Jumlah Rp 1,558,442.50
Dibulatkan Rp 1,558,400.00

RSNI T-15-2002-B.32
Memasang 1 M' Pipa PVC Tipe AW Ø 4"
1.200 M' Pipa PVC Tipe AW Ø 4" @ Rp 213,000.00 Rp 255,600.00
35.000 % Harga Pipa untuk Perlengkapan @ Rp 74,550.00 Rp 2,609,250.00
0.081 Oh Pekerja @ Rp 62,000.00 Rp 5,022.00
0.135 Oh Tukang @ Rp 85,000.00 Rp 11,475.00
0.0135 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,417.50
0.0041 Oh Mandor @ Rp 80,000.00 Rp 328.00
Jumlah Rp 2,883,092.50
Dibulatkan Rp 2,883,000.00

RSNI T-15-2002-B.35
Memasang 1 Buah Kran Ø 3/4" Atau Ø 1/2"
1.000 Buah Kran Air @ Rp 20,000.00 Rp 20,000.00
0.025 Buah Seal Tape @ Rp 5,900.00 Rp 147.50
0.010 Oh Pekerja @ Rp 62,000.00 Rp 620.00
0.100 Oh Tukang @ Rp 85,000.00 Rp 8,500.00
0.010 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,050.00
0.005 Oh Mandor @ Rp 80,000.00 Rp 400.00
Jumlah Rp 30,717.50
Dibulatkan Rp 30,700.00

RSNI T-15-2002-B.36
Memasang 1 Buah Floor Drain
1.000 Buah Floor Drain @ Rp 21,000.00 Rp 21,000.00
0.010 Oh Pekerja @ Rp 62,000.00 Rp 620.00
0.100 Oh Tukang @ Rp 85,000.00 Rp 8,500.00
0.010 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,050.00
0.005 Oh Mandor @ Rp 80,000.00 Rp 400.00
Jumlah Rp 31,570.00
Dibulatkan Rp 31,500.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

PEKERJAAN RANGKA KUDA-KUDA DAN ATAP


SNI DT-91-0014-2007-6.20
1 M2 RANGKA KUDA -KUDA ALUZING 55% ALUMINIUM (ZINCALUME) UNTUK GENTENG METAL
4.260 M1 Profil C 75.75 Panjang 6 M1 @ Rp 22,000.00 Rp 93,720.00
4.930 M1 Reng U 0.5 Panjang 6 M' @ Rp 9,000.00 Rp 44,370.00
14.000 Buah Baut Truss Ukuran 12 (14 x 20) @ Rp 2,000.00 Rp 28,000.00
11.000 Buah Baut Reng Ukuran 10 (16 x 16 ) @ Rp 2,500.00 Rp 27,500.00
0.140 Oh Pekerja @ Rp 62,000.00 Rp 8,680.00
0.100 Oh Tukang @ Rp 85,000.00 Rp 8,500.00
0.040 Oh Kepala Tukang @ Rp 105,000.00 Rp 4,200.00
0.070 Oh Mandor @ Rp 80,000.00 Rp 5,600.00
Jumlah Rp 220,570.00
Dibulatkan Rp 220,500.00

SNI - 03 - 3436 - 2007 - 6.1


1 M2 Atap Seng Genteng Metal
1.020 Lbr Atap seng Genteng Metal 0,25 @ Rp 78,500.00 Rp 80,070.00
9.000 Buah Screw/Baut Seng Metal 1,5" @ Rp 2,000.00 Rp 18,000.00
0.200 Oh Pekerja @ Rp 62,000.00 Rp 12,400.00
0.100 Oh Tukang @ Rp 85,000.00 Rp 8,500.00
0.010 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,050.00
0.001 Oh Mandor @ Rp 80,000.00 Rp 80.00
Jumlah Rp 120,100.00
Dibulatkan Rp 120,100.00

SNI - 03 - 3436 - 2007 - 6.2


1 M' Nok Genteng Metal
1.100 Lbr Rabung Seng Genteng Metal 0,25 @ Rp 51,000.00 Rp 56,100.00
9.000 Buah Screw/Baut Seng Metal 1,5" @ Rp 2,000.00 Rp 18,000.00
0.250 Oh Pekerja @ Rp 62,000.00 Rp 15,500.00
0.150 Oh Tukang @ Rp 85,000.00 Rp 12,750.00
0.015 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,575.00
0.013 Oh Mandor @ Rp 80,000.00 Rp 1,040.00
Jumlah Rp 104,965.00
Dibulatkan Rp 104,900.00

PEKERJAAN KUNCI DAN KACA


RSNI T-30-2007-B.2
1 BUAH KUNCI TANAM BIASA
1.000 Buah Kunci Tanam @ Rp 40,000.00 Rp 40,000.00
0.010 Oh Pekerja @ Rp 62,000.00 Rp 620.00
0.500 Oh Tukang @ Rp 85,000.00 Rp 42,500.00
0.010 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,050.00
0.0050 Oh Mandor @ Rp 80,000.00 Rp 400.00
Jumlah Rp 84,570.00
Dibulatkan Rp 84,500.00

RSNI T-30-2007-B.5
1 BUAH ENGSEL PINTU
1.000 Buah Engsel Pintu @ Rp 22,000.00 Rp 22,000.00
0.015 Oh Pekerja @ Rp 62,000.00 Rp 930.00
0.150 Oh Tukang @ Rp 85,000.00 Rp 12,750.00
0.015 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,575.00
0.00075 Oh Mandor @ Rp 80,000.00 Rp 60.00
Jumlah Rp 37,315.00
Dibulatkan Rp 37,300.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

RSNI T-30-2007-B.6
1 BUAH ENGSEL JENDELA KUPU-KUPU
1.000 Buah Engsel Jendela @ Rp 10,000.00 Rp 10,000.00
0.010 Oh Pekerja @ Rp 62,000.00 Rp 620.00
0.100 Oh Tukang @ Rp 85,000.00 Rp 8,500.00
0.010 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,050.00
0.0005 Oh Mandor @ Rp 80,000.00 Rp 40.00
Jumlah Rp 20,210.00
Dibulatkan Rp 20,200.00

RSNI T-30-2007-B.9
1 BUAH KAIT ANGIN JENDELA
1.000 Buah Kait Angin @ Rp 12,000.00 Rp 12,000.00
0.015 Oh Pekerja @ Rp 62,000.00 Rp 930.00
0.150 Oh Tukang @ Rp 85,000.00 Rp 12,750.00
0.015 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,575.00
0.00075 Oh Mandor @ Rp 80,000.00 Rp 60.00
Jumlah Rp 27,315.00
Dibulatkan Rp 27,300.00
RSNI T-30-2007-B.26
1 BUAH HAK TARIKAN JENDELA
1.000 Buah Tarikan Jendela @ Rp 12,000.00 Rp 12,000.00
0.015 Oh Pekerja @ Rp 62,000.00 Rp 930.00
0.150 Oh Tukang @ Rp 85,000.00 Rp 12,750.00
0.015 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,575.00
0.00075 Oh Mandor @ Rp 80,000.00 Rp 60.00
Jumlah Rp 27,315.00
Dibulatkan Rp 27,300.00

RSNI T-30-2007-B.25
1 BUAH GRENDEL JENDELA
1.000 Buah Pacok Jendela @ Rp 12,000.00 Rp 12,000.00
0.020 Oh Pekerja @ Rp 62,000.00 Rp 1,240.00
0.200 Oh Tukang @ Rp 85,000.00 Rp 17,000.00
0.020 Oh Kepala Tukang @ Rp 105,000.00 Rp 2,100.00
0.00075 Oh Mandor @ Rp 80,000.00 Rp 60.00
Jumlah Rp 32,400.00
Dibulatkan Rp 32,400.00

RSNI T-30-200-B.17
1 M2 Pasang Kaca Tebal 5 mm
1.100 Buah Pacok Jendela @ Rp 140,000.00 Rp 154,000.00
0.015 Oh Pekerja @ Rp 62,000.00 Rp 930.00
0.150 Oh Tukang @ Rp 85,000.00 Rp 12,750.00
0.015 Oh Kepala Tukang @ Rp 105,000.00 Rp 1,575.00
0.00075 Oh Mandor @ Rp 80,000.00 Rp 60.00
Jumlah Rp 169,315.00
Dibulatkan Rp 169,300.00
PEKERJAAN PENGECATAN
PT. T-38-2000-C-B8
1 M2 PENGECATAN BIDANG KAYU
0.200 Kg Cat Menie @ Rp 30,000.00 Rp 6,000.00
0.150 Kg Plamir @ Rp 40,000.00 Rp 6,000.00
0.170 Kg Cat Dasar @ Rp 35,000.00 Rp 5,950.00
0.260 Kg Cat Kayu/Minyak @ Rp 50,000.00 Rp 13,000.00
0.070 Oh Pekerja @ Rp 62,000.00 Rp 4,340.00
0.009 Oh Tukang @ Rp 85,000.00 Rp 765.00
0.006 Oh Kepala Tukang @ Rp 105,000.00 Rp 630.00
0.0025 Oh Mandor @ Rp 80,000.00 Rp 200.00
Jumlah Rp 36,885.00
Dibulatkan Rp 36,800.00
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA

PT. T-38-2000-C-B14
1 M2 PENGECATAN TEMBOK BARU
0.100 Kg Plamir @ Rp 40,000.00 Rp 4,000.00
0.100 Kg Cat Dasar @ Rp 35,000.00 Rp 3,500.00
0.260 Kg Cat Tembok @ Rp 30,000.00 Rp 7,800.00
0.020 Kg Pekerja @ Rp 62,000.00 Rp 1,240.00
0.063 Oh Tukang @ Rp 85,000.00 Rp 5,355.00
0.0063 Oh Kepala Tukang @ Rp 105,000.00 Rp 661.50
0.0025 Oh Mandor @ Rp 80,000.00 Rp 200.00
Jumlah Rp 22,756.50
Dibulatkan Rp 22,700.00
DAFTAR HARGA SATUAN DASAR UPAH DAN BAHAN
A. HARGA SATUAN DASAR UPAH
MERK/MODEL/
NO URAIAN SATUAN HARGA SATUAN
UKURAN
1 Buruh Lapangan Kurang Terlatih Hari Rp 55,000.00
2 Buruh Lapangan Tak Terlatih Hari Rp 55,000.00
3 Buruh Lapangan Terlatih Hari Rp 60,000.00
4 Pekerja Hari Rp 55,000.00
5 Kepala Tukang Hari Rp 70,000.00
6 Tukang Hari Rp 65,000.00
7 Mandor Hari Rp 70,000.00

B. MATERIAL / BAHAN BANGUNAN


MERK/MODEL/
NO URAIAN SATUAN HARGA SATUAN
UKURAN
1 Air Liter Rp 25.00
2 Tanah Timbunan (Pilihan) M3 Rp 85,000.00
3 Batu Bata Buah Rp 550.00
4 Batu Gunung M3 Rp 130,000.00
5 Batu Kali 15 - 20 Cm M3 Rp 130,000.00
6 Baut Truss Ukuran 12 ( 14 x 20 ) Buah Rp 2,000.00
7 Baut Reng Ukuran 10 ( 16 x 16 ) Buah Rp 2,500.00
8 Baut Seng Metal / Screw 1,5 " Buah Rp 2,000.00
9 Besi Beton polos 12 mm Kg Rp 20,000.00
10 Besi Beton polos 10 mm Kg Rp 20,000.00
11 Besi Beton polos 9 mm Kg Rp 20,000.00
12 Besi Beton polos 8 mm Kg Rp 20,000.00
13 Besi Beton polos 6 mm Kg Rp 20,000.00
14 Cat Dasar Kg Rp 35,000.00
15 Cat Kayu Mengkilat Kg Rp 50,000.00
16 Cat Meni (Besi) Kg Rp 30,000.00
17 Cat Meni (Kayu) Kg Rp 30,000.00
18 Cat Minyak (Avian) Kg Rp 50,000.00
19 Cat Tembok Kg Rp 30,000.00
20 Engsel Bak Besi Buah Rp 10,000.00
21 Engsel Biasa 3" Buah Rp 10,000.00
22 Engsel Biasa 4" Buah Rp 22,000.00
23 Engsel Kunngan 3" Buah Rp 10,000.00
24 Engsel Kuningan 4" Buah Rp 22,000.00
25 Engsel lokal Buah Rp 22,000.00
26 Engsel Pintu Besi Buah Rp 25,000.00
27 Floordrain Buah Rp 21,000.00
28 Profil C 75.75 Panjang 6 M' M' Rp 22,000.00
29 Genteng Metal M2 Rp 78,500.00
30 Gypsum Board Lembar Rp 87,000.00
31 Kaca Bening uk 3 mm M2 Rp 120,000.00
32 Kaca Bening uk 5 mm M2 Rp 140,000.00
33 Kawat Beton Kg Rp 20,000.00
34 Kayu Klas I (Damar Laut/Seumantok/Ulin dll) M3 Rp 5,000,000.00
35 Kayu Rangka Klas II (Kemper / Kruing, dll) M3 Rp 4,000,000.00
36 Kayu Klas III (Sembarang keras/dll) M3 Rp 3,200,000.00
37 Kayu Terocok (kayu Laut) M3 Rp 3,000,000.00
38 Kayu Untuk perancah M3 Rp 2,000,000.00
39 Kayu Dolken / Tiang Perancah Batang Rp 200,000.00
40 Keramik Ikad 20 x 20 (Polished) Bh Rp 3,500.00
41 Keramik Ikad 20 x 20 (Unpolished) Bh Rp 3,500.00
42 Keramik Ikad 20 x 25 Bh Rp 5,000.00
43 Keramik Ikad 30 x 30 (Polished) Bh Rp 8,000.00
44 Keramik Ikad 30 x 30 (unPolished) Bh Rp 8,000.00
45 Keramik Ikad 40 x 40 (Polished) Bh Rp 15,000.00
MERK/MODEL/
NO URAIAN SATUAN HARGA SATUAN
UKURAN
46 Keramik Ikad 40 x 40 (Unpolished) Bh Rp 15,000.00
47 Kerikil Bersih / Kerikil Beton M3 Rp 110,000.00
48 Kerikil Bersih / Kerikil Beton Kg Rp 110.00
49 Klosed Jongkok Buah Rp 153,000.00
50 Kunci Tanam Buah Rp 40,000.00
51 Kran Air Buah Rp 20,000.00
52 Lem Kayu Kg Rp 20,000.00
53 Minyak Bekisting Ltr Rp 50,000.00
54 Multipleks 4 mm Lbr Rp 75,000.00
55 Multipleks 6 mm Lbr Rp 110,000.00
56 Multipleks 9 mm Lbr Rp 130,000.00
57 Paku Beton 8 cm Kotak Rp 15,000.00
58 Paku Kayu kg Rp 15,000.00
59 Paku 1 " kg Rp 15,000.00
60 Paku 1,5" kg Rp 15,000.00
61 Paku 2" kg Rp 15,000.00
62 Paku 4" kg Rp 15,000.00
63 Paku Trpleks kg Rp 19,500.00
64 Paku Skrup kg Rp 6,000.00
65 Pasir Pasangan / Pasir Ayak Untuk Beton M3 Rp 130,000.00
66 Pasir Pasangan / Pasir Ayak Untuk Beton kg Rp 130.00
67 Pasir Urug M3 Rp 110,000.00
68 Plamir Tembok Kg Rp 40,000.00
69 Pipa PVC 1" (AW) Btg Rp 75,000.00
70 Pipa PVC 1/2" (AW) Btg Rp 45,000.00
71 Pipa PVC 2" (AW) Btg Rp 159,000.00
72 Pipa PVC 3" (AW) Btg Rp 151,000.00
73 Pipa PVC 3/4" (AW) Btg Rp 45,000.00
74 Pipa PVC 4" (AW) Btg Rp 213,000.00
75 Profil Alumunium Btg Rp 22,000.00
76 Reng U 0.5 Panjang 6 M' M' Rp 9,000.00
77 Rabung Seng Genteng Metal 0,25 Lbr Rp 51,000.00
78 Rangka Furing 0,4 M2 Rp 12,500.00
79 Sealtape Bh Rp 5,900.00
80 Semen Warna Zak Rp 110,000.00
81 Semen Padang/Cibinong @ 50 kg Zak Rp 80,000.00
82 Semen portland @ 40 kg Zak Rp 51,000.00
83 Semen portland @ 40 kg Kg Rp 1,275.00
84 Semen Warna 50Kg Zak Rp 120,000.00
85 Semen Warna Kg Rp 2,400.00
86 Tanah Urug M3 Rp 57,000.00
87 Pasir Pasang M3 Rp 130,000.00
89 Batu Belah 15 cm/20 cm M3 Rp 130,000.00
90 Formite/Penjaga Jarak Bekisting/Spacer bh Rp 500.00
91 Pana Kayu Klas I M3 Rp 5,000,000.00
92 Papn Kayu Klas II M3 Rp 4,000,000.00
93 Sekrup Fisher bh Rp 400.00
94 Sealant bh Rp 4,000.00
95 Tarikan Jendela bh Rp 12,000.00
96 Pacok Jendela bh Rp 12,000.00
97 Kait Angin bh Rp 12,000.00
98 Formite/Penjaga Jarak Bekisting/Spacer Bh Rp 500.00
99 Kayu Kelas III (Papan) M3 Rp 3,600,000.00
ANALISA TEKNIS
PEKERJAAN : Pembangunan Ruang Ibadah SD Muhammadiyah Sinabang
LOKASI : Kab. Simeulue

I. PEKERJAAN PERSIAPAN
1. Persiapan & Pembersihan Lapangan
Volume pekerjaan = 1.00 Paket
Tenaga kerja yang digunakan = Man Power
1 Mandor
2 Pekerja
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 1.00 M2/Orang/Hari
Produksi per hari = 1.00 x 1.00 = 1 Paket
Waktu dibutuhkan = 1.0 : 1 = 1.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Tidak Ada Bahan / Material Kerja
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

2 Pengukuran dan pemasangan bowplank


Volume pekerjaan = 1.00 Paket
Tenaga kerja yang digunakan = Man Power
1 Mandor
2 Pekerja
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 1.00 M2/Orang/Hari
Produksi per hari = 1.00 x 1.00 = 1 Paket
Waktu dibutuhkan = 1.0 : 1 = 1.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Tidak Ada Bahan / Material Kerja
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

3 Papan Nama Proyek


Volume pekerjaan = 1.00 Paket
Tenaga kerja yang digunakan = Man Power
1 Mandor
2 Pekerja
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 1.00 M2/Orang/Hari
Produksi per hari = 1.00 x 1.00 = 1 Paket
Waktu dibutuhkan = 1.0 : 1 = 1.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Tidak Ada Bahan / Material Kerja
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

4 Administrasi dan Dokumentasi


Volume pekerjaan = 1.00 Paket
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = Taksir
Produksi per hari = Taksir
Waktu dibutuhkan = 120.0 Hari = 16 Minggu
Jumlah Pemakaian Bahan = Kebutuhan Administrasi Dan Dokumentasi
Jumlah Pemakaian Alat = Tidak Ada

II. PEKERJAAN TANAH DAN PONDASI


1 Galian Tanah Pondasi
Volume pekerjaan = 38.00 M3
Tenaga kerja yang digunakan = Man Power
1 Pekerja 0.75 OH
2 Mandor 0.025 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 3.00 M3/Orang/Hari
Produksi per hari = 2.00 x 3.00 = 6 M3
Waktu dibutuhkan = 38.0 : 6 = 6.33 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Tidak Ada Bahan / Material Kerja
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)
2 Urugan Kembali Bekas Galian
Volume pekerjaan = 12.67 M3
Tenaga kerja yang digunakan = Man Power
1 Pekerja 0.333 OH
2 Mandor 0.011 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 2.00 M3/Orang/Hari
Produksi per hari = 2.00 x 2.00 = 4 M3
Waktu dibutuhkan = 12.7 : 4 = 3.17 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Tidak Ada Bahan / Material Kerja
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

3 Urugan Pasir Alas Pondasi


Volume pekerjaan = 2.00 M3
Tenaga kerja yang digunakan = Man Power
1 Pekerja 0.300 OH
2 Mandor 0.010 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 3.00 M3/Orang/Hari
Produksi per hari = 2.00 x 3.00 = 6 M3
Waktu dibutuhkan = 2.0 : 6 = 0.33 Hari = 1 Minggu
Jumlah Pemakaian Bahan =
1 Pasir urug = 2.40 M3
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

4 Pasangan Batu Kosong / Aanstamping


Volume pekerjaan = 4.00 M3
Tenaga kerja yang digunakan = Man Power
1 Pekerja 0.780 OH
2 Tukang Batu 0.390 OH
3 Kepala Tukang 0.039 OH
4 Mandor 0.039 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 2.00 M3/Orang/Hari
Produksi per hari = 2.00 x 2.00 = 4 M3
Waktu dibutuhkan = 4.0 : 4 = 1.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan =
1 Batu Belah 15 cm/20 cm = 4.80 M3
2 Pasir Urug = 1.73 M3
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

5 Pasangan Pondasi Batu Gunung


Volume pekerjaan = 17.00 M3
Tenaga kerja yang digunakan = Man Power
1 Pekerja 1.500 OH
2 Tukang Batu 0.750 OH
3 Kepala Tukang 0.075 OH
4 Mandor 0.075 OH
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 0.86 M3/Orang/Hari
Produksi per hari = 1.00 x 0.86 = 1 M3
Waktu dibutuhkan = 17.0 : 1 = 19.77 Hari = 3 Minggu
Jumlah Pemakaian Bahan =
1 Batu Belah 15 cm/20 cm = 1.20 M3
2 Semen Portland = 202.00 Kg
3 Pasir Pasang = 0.49 M3
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

6 Pondasi Bata Rolag 1 Pc : 2 PP (Trasraam) Teras


Volume pekerjaan = 23.40 M2
Tenaga kerja yang digunakan = Man Power
1 Pekerja 0.300 OH
2 Tukang Batu 0.100 OH
3 Kepala Tukang 0.010 OH
4 Mandor 0.015 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 2.00 M2/Orang/Hari
Produksi per hari = 2.00 x 2.00 = 4 M2
Waktu dibutuhkan = 23.4 : 4 = 5.85 Hari = 1 Minggu
Jumlah Pemakaian Bahan =
1 Pasir Pasang = 0.89 M3
2 Batu Bata = 1638.00 Buah
3 Semen Portland = 443.43 Kg
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

III. PEKERJAAN BETON BERTULANG


1 Sloof Beton uk. 20/25 cm
Volume pekerjaan = 2.50 M3
Tenaga kerja yang digunakan = Man Power
1 Pekerja 1.65 OH
2 Tukang Batu 0.275 OH
3 Kepala Tukang 0.028 OH
4 Mandor 0.083 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 0.06 M3/Orang/Hari
Produksi per hari = 2.00 x 0.06 = 0.12 M3
Waktu dibutuhkan = 2.5 : 0 = 20.83 Hari = 3 Minggu
Jumlah Pemakaian Bahan =
1 Semen Portland = 960.00 Kg
2 Pasir Beton = 1730.00 Kg
3 Kerikil = 2597.50 Kg
4 Air = 537.50 Liter
5 Besi Beton polos / ulir = 26.25 Kg
6 Kawat Beton = 0.38 Kg
7 Kayu Kelas III = 0.11 M3
8 Paku 2" - 5 " = 0.75 Kg
9 Minyak Bekisting = 0.25 Ltr
Jumlah Pemakaian Alat = Molen Beton Alat-alat Bantu (Cangkul, pacul, parang dll)

2 Plat Dack T=08 cm


Volume pekerjaan = 1.33 M3
Tenaga kerja yang digunakan = Man Power
1 Pekerja 1.65 OH
2 Tukang Batu 0.275 OH
3 Kepala Tukang 0.028 OH
4 Mandor 0.083 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 0.05 M3/Orang/Hari
Produksi per hari = 2.00 x 0.05 = 0.10 M3
Waktu dibutuhkan = 1.3 : 0 = 13.27 Hari = 2 Minggu
Jumlah Pemakaian Bahan =
1 Semen Portland = 509.64 Kg
2 Pasir Beton = 918.42 Kg
3 Kerikil = 1378.96 Kg
4 Air = 285.35 Liter
5 Besi Beton polos / ulir = 13.94 Kg
6 Kawat Beton = 0.20 Kg
7 Kayu Kelas III = 0.06 M3
8 Paku 2" - 5 " = 0.40 Kg
9 Minyak Bekisting = 0.13 Ltr
Jumlah Pemakaian Alat = Molen Beton Alat-alat Bantu (Cangkul, pacul, parang dll)

3 Kolom 20/20 cm
Volume pekerjaan = 3.60 M3
Tenaga kerja yang digunakan = Man Power
1 Pekerja 1.65 OH
2 Tukang Batu 0.275 OH
3 Kepala Tukang 0.028 OH
4 Mandor 0.083 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 0.06 M3/Orang/Hari
Produksi per hari = 2.00 x 0.06 = 0.12 M3
Waktu dibutuhkan = 3.6 : 0 = 30.00 Hari = 4 Minggu
Jumlah Pemakaian Bahan =
1 Semen Portland = 1382.40 Kg
2 Pasir Beton = 2491.20 Kg
3 Kerikil = 3740.40 Kg
4 Air = 774.00 Liter
5 Besi Beton polos / ulir = 37.80 Kg
6 Kawat Beton = 0.54 Kg
7 Kayu Kelas III = 0.16 M3
8 Paku 2" - 5 " = 1.08 Kg
9 Minyak Bekisting = 0.36 Ltr
Jumlah Pemakaian Alat = Molen Beton Alat-alat Bantu (Cangkul, pacul, parang dll)

4 Ring Balok & Balok uk. 15/18 cm


Volume pekerjaan = 1.62 M3
Tenaga kerja yang digunakan = Man Power
1 Pekerja 1.65 OH
2 Tukang Batu 0.275 OH
3 Kepala Tukang 0.028 OH
4 Mandor 0.083 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 0.05 M3/Orang/Hari
Produksi per hari = 2.00 x 0.05 = 0.09 M3
Waktu dibutuhkan = 1.6 : 0 = 18.00 Hari = 3 Minggu
Jumlah Pemakaian Bahan =
1 Semen Portland = 622.08 Kg
2 Pasir Beton = 1121.04 Kg
3 Kerikil = 1683.18 Kg
4 Air = 348.30 Liter
5 Besi Beton polos / ulir = 17.01 Kg
6 Kawat Beton = 0.24 Kg
7 Kayu Kelas III = 0.07 M3
8 Paku 2" - 5 " = 0.49 Kg
9 Minyak Bekisting = 0.16 Ltr
Jumlah Pemakaian Alat = Molen Beton Alat-alat Bantu (Cangkul, pacul, parang dll)

5 Kolom Fasade Jendela (Bingkai) uk. 13/13 cm


Volume pekerjaan = 1.01 M3
Tenaga kerja yang digunakan = Man Power
1 Pekerja 1.65 OH
2 Tukang Batu 0.275 OH
3 Kepala Tukang 0.028 OH
4 Mandor 0.083 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 0.03 M3/Orang/Hari
Produksi per hari = 2.00 x 0.03 = 0.06 M3
Waktu dibutuhkan = 1.0 : 0 = 16.90 Hari = 3 Minggu
Jumlah Pemakaian Bahan =
1 Semen Portland = 389.38 Kg
2 Pasir Beton = 701.69 Kg
3 Kerikil = 1053.55 Kg
4 Air = 218.01 Liter
5 Besi Beton polos / ulir = 10.65 Kg
6 Kawat Beton = 0.15 Kg
7 Kayu Kelas III = 0.05 M3
8 Paku 2" - 5 " = 0.30 Kg
9 Minyak Bekisting = 0.10 Ltr
Jumlah Pemakaian Alat = Molen Beton Alat-alat Bantu (Cangkul, pacul, parang dll)

IV. PEKERJAAN PASANGAN DAN PLESTERAN


1 Pasangan Trasraam Bata 1 PC : 2 PP
Volume pekerjaan = 19.00 M2
Tenaga kerja yang digunakan = Man Power
1 Pekerja 0.300 OH
2 Tukang Batu 0.100 OH
3 Kepala Tukang 0.010 OH
4 Mandor 0.015 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 4.00 M2/Orang/Hari
Produksi per hari = 2.00 x 4.00 = 8.00 M2
Waktu dibutuhkan = 19.0 : 8.00 = 2.38 Hari = 1 Minggu
Jumlah Pemakaian Bahan =
1 Pasir Pasang = 0.72 M3
2 Batu Bata = 1330.00 Buah
3 Semen Portland = 360.05 Kg
Jumlah Pemakaian Alat = Molen Beton Alat-alat Bantu (Cangkul, pacul, parang dll)

2 Plesteran trasraam Bata 1 PC : 2 PP


Volume pekerjaan = 38.00 M2
Tenaga kerja yang digunakan = Man Power
1 Pekerja 0.300 OH
2 Tukang Batu 0.150 OH
3 Kepala Tukang 0.015 OH
4 Mandor 0.015 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 4.00 M2/Orang/Hari
Produksi per hari = 2.00 x 4.00 = 8.00 M2
Waktu dibutuhkan = 38.0 : 8.00 = 4.75 Hari = 1 Minggu
Jumlah Pemakaian Bahan =
1 Pasir Pasang = 0.76 M3
2 Semen Portland = 388.51 Kg
Jumlah Pemakaian Alat = Molen Beton Alat-alat Bantu (Cangkul, pacul, parang dll)

3 Pasangan Dinding Bata 1 PC : 4 PP


Volume pekerjaan = 93.32 M2
Tenaga kerja yang digunakan = Man Power
1 Pekerja 0.300 OH
2 Tukang Batu 0.150 OH
3 Kepala Tukang 0.015 OH
4 Mandor 0.015 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 3.00 M2/Orang/Hari
Produksi per hari = 2.00 x 3.00 = 6.00 M2
Waktu dibutuhkan = 93.3 : 6.00 = 15.55 Hari = 3 Minggu
Jumlah Pemakaian Bahan =
1 Pasir Pasang = 4.01 M3
2 Batu Bata = 6532.40 Buah
3 Semen Portland = 1073.18 Kg
Jumlah Pemakaian Alat = Molen Beton Alat-alat Bantu (Cangkul, pacul, parang dll)

4 Plesteran Dinding Bata 1 PC : 4 PP


Volume pekerjaan = 239.30 M3
Tenaga kerja yang digunakan = Man Power
1 Pekerja 0.200 OH
2 Tukang Batu 0.150 OH
3 Kepala Tukang 0.015 OH
4 Mandor 0.015 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 9.00 M2/Orang/Hari
Produksi per hari = 2.00 x 9.00 = 18.00 M3
Waktu dibutuhkan = 239.3 : 18.00 = 13.29 Hari = 2 Minggu
Jumlah Pemakaian Bahan =
1 Pasir Pasang = 0.02 M3
2 Semen Portland = 6.24 Kg
Jumlah Pemakaian Alat = Molen Beton Alat-alat Bantu (Cangkul, pacul, parang dll)

V. PEKERJAAN LANTAI
1 Timbunan Tanah bawah Lantai
Volume pekerjaan = 27.50 M3
Tenaga kerja yang digunakan = Man Power
1 Pekerja 0.000 OH
2 Mandor 0.000 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 4.00 M3/Orang/Hari
Produksi per hari = 2.00 x 4.00 = 8.00 M3
Waktu dibutuhkan = 27.5 : 8.00 = 3.44 Hari = 1 Minggu
Jumlah Pemakaian Bahan =
1 Tanah Urug = 33.00 Oh
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

2 Urugan Pasir Bawah Lantai


Volume pekerjaan = 6.88 M3
Tenaga kerja yang digunakan = Man Power
1 Pekerja 0.300 OH
2 Mandor 0.010 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 3.00 M3/Orang/Hari
Produksi per hari = 2.00 x 3.00 = 6.00 M3
Waktu dibutuhkan = 6.9 : 6.00 = 1.15 Hari = 1 Minggu
Jumlah Pemakaian Bahan =
1 Pasir urug = 8.25 0
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

1 Rabat Beton dibawah Lantai Keramik


Volume pekerjaan = 3.44 M3
Tenaga kerja yang digunakan = Man Power
1 Pekerja 1.650 OH
2 Tukang Batu 0.275 OH
3 Kepala Tukang 0.028
4 Mandor 0.083
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 1.00 M3/Orang/Hari
Produksi per hari = 1.00 x 1.00 = 1.00 M3
Waktu dibutuhkan = 3.4 : 1.00 = 3.44 Hari = 1 Minggu
Jumlah Pemakaian Bahan =
1 Semen Portland = 948.75 Kg
2 Pasir Beton = 2846.25 Kg
3 Kerikil = 3478.75 Kg
4 Air = 739.06 Liter
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

2 Keramik Lantai 40 x 40 cm (Polished)


Volume pekerjaan = 77.38 M2
Tenaga kerja yang digunakan = Man Power
1 Pekerja 0.620 OH
2 Tukang Batu 0.350 OH
3 Kepala Tukang 0.035
4 Mandor 0.030
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 5.00 M2/Orang/Hari
Produksi per hari = 1.00 x 5.00 = 5.00 M2
Waktu dibutuhkan = 77.4 : 5.00 = 15.48 Hari = 3 Minggu
Jumlah Pemakaian Bahan =
1 Keramik 40 x 40 cm Polis = 483.59 Buah
2 Semen Portland = 773.75 Kg
3 Pasir Pasang = 3.48 M3
4 Semen Warna = 116.06 Kg
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

VI. PEKERJAAN ATAP DAN PLAFOND


1 Ranga Kuda-kuda Baja Ringan
Volume pekerjaan = 109.35 M2
Tenaga kerja yang digunakan = Man Power
1 Pekerja 0.140 OH
2 Tukang 0.100 OH
3 Kepala Tukang 0.040 OH
4 Mandor 0.070 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 2.00 M2/Orang/Hari
Produksi per hari = 2.00 x 2.00 = 4.00 M2
Waktu dibutuhkan = 109.4 : 4.00 = 27.34 Hari = 4 Minggu
Jumlah Pemakaian Bahan =
1 Profil C 75.75 Panjang 6 = 465.85 M1
2 Reng U 0.5 Panjang 6 M' = 539.11 M1
3 Baut Truss Ukuran 12 (14 = 1530.95 Buah
4 Baut Reng Ukuran 10 (16 x = 1202.89 Buah
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

2 Atap Seng Genteng Metal


Volume pekerjaan = 109.35 M2
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 3.00 M2/Orang/Hari
Produksi per hari = 2.00 x 3.00 = 6.00 M2
Waktu dibutuhkan = 109.4 : 6.00 = 18.23 Hari = 3 Minggu
Jumlah Pemakaian Bahan = Atap Seng Genteng
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

3 Kubah Steinlessteel Fabrikasi


Volume pekerjaan = 1.00 Unit
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 1.00 M2/Orang/Hari
Produksi per hari =
Taksir
Waktu dibutuhkan = = 2 Minggu
Jumlah Pemakaian Bahan = Atap Seng Genteng
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

4 Listplank Papan + Pengecatan


Volume pekerjaan = 47.90 M
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 8.00 M/Orang/Hari
Produksi per hari = 2.00 x 8.00 = 16.00 M
Waktu dibutuhkan = 47.9 : 16.00 = 2.99 Hari = 2 Minggu
Jumlah Pemakaian Bahan = Atap Seng Genteng
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

5 Plafond Gypsum
Volume pekerjaan = 107.81 M2
Tenaga kerja yang digunakan = Man Power
1 Pekerja 0.100 OH
2 Tukang 0.100 OH
3 Kepala Tukang 0.010 OH
4 Mandor 0.050 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 4.00 M2/Orang/Hari
Produksi per hari = 2.00 x 4.00 = 8.00 M2
Waktu dibutuhkan = 107.8 : 8.00 = 13.48 Hari = 2 Minggu
Jumlah Pemakaian Bahan =
1 GypsumBoard T.9 mm = 39.24 Oh
2 Paku Sekrup = 11.86 Oh
Jumlah Pemakaian Alat = Alat-alat Bantu

6 Rangka Plafond Puring


Volume pekerjaan = 107.81 M2
Tenaga kerja yang digunakan = Man Power
1 Pekerja 0.150 OH
2 Tukang Kayu 0.300 OH
3 Kepala Tukang 0.030 OH
4 Mandor 0.075 OH
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 4.00 M2/Orang/Hari
Produksi per hari = 2.00 x 4.00 = 8.00 M2
Waktu dibutuhkan = 107.8 : 8.00 = 13.48 Hari = 2 Minggu
Jumlah Pemakaian Bahan =
1 Rangka Furing 0,4 = 431.24 M'
2 Skrup = 12.40 Kg
Jumlah Pemakaian Alat = Alat-alat Bantu

7 Profil Gypsum
Volume pekerjaan = 108.50 M'
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 10.00 M2/Orang/Hari
Produksi per hari = 2.00 x 10.00 = 20.00 M'
Waktu dibutuhkan = 108.5 : 20.00 = 5.43 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Bahan Profil Gypsum
Jumlah Pemakaian Alat = Alat-alat Bantu

VII. PEKERJAAN PINTU,JENDELA DAN KUNCI


1 Pintu Type P1 (3 Unit)
Kosen Kayu Kelas II
Volume pekerjaan = 0.17 M3
Tenaga kerja yang digunakan = Man Power
1 Pekerja 6.000 OH
2 Tukang Kayu 18.00 OH
3 Kepala Tukang 1.800 OH
4 Mandor 0.300 OH
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 0.05 M3/Orang/Hari
Produksi per hari = 1.00 x 0.05 = 0.05 M3
Waktu dibutuhkan = 0.2 : 0.05 = 3.43 Hari = 1 Minggu
Jumlah Pemakaian Bahan =
1 Bahan Kayu Kelas - II = 0.21 M3
2 Lem kayu = 0.17 Kg
3 Paku Biasa 10 cm = 0.21 Kg
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

Daun Pintu Kayu P1 Uk.60x210 cm


Volume pekerjaan = 6.00 Lembar
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 2.00 M3/Orang/Hari
Produksi per hari = 1.00 x 2.00 = 2.00 Lembar
Waktu dibutuhkan = 6.0 : 2.00 = 3.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan =
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

Kunci Pintu Standar


Volume pekerjaan = 3.00 Set
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 2.00 Set/Orang/Hari
Produksi per hari = 1.00 x 2.00 = 2.00 Set
Waktu dibutuhkan = 3.0 : 2.00 = 1.50 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Kunci Pintu Standar
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

Engsel Pintu
Volume pekerjaan = 18.00 Buah
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 5.00 Buah/Orang/Hari
Produksi per hari = 1.00 x 5.00 = 5.00 Buah
Waktu dibutuhkan = 18.0 : 5.00 = 3.60 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Engsel Pintu
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

2 Jendela Type J1 (12 Unit)


Kosen Kayu Kelas II
Volume pekerjaan = 0.55 M3
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 5.00 M3/Orang/Hari
Produksi per hari = 0.03 x 5.00 = 0.15 M3
Waktu dibutuhkan = 0.6 : 0.15 = 3.69 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Kosen Kayu Kelas II
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

Daun Jendela Uk. 60x180 cm


Volume pekerjaan = 12.00 Lembar
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 5.00 Lembar/Orang/Hari
Produksi per hari = 2.00 x 5 = 10.00 Lembar
Waktu dibutuhkan = 12.0 : 10.00 = 1.20 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Daun Jendela Uk. 60x180 cm
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

Engsel Jendela
Volume pekerjaan = 24.00 Buah
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 5.00 Buah/Orang/Hari
Produksi per hari = 5.00 x 5.00 = 25.00 Buah
Waktu dibutuhkan = 24.0 : 25.00 = 0.96 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Engsel Jendela
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

Hak Penahan Angin Jendela


Volume pekerjaan = 12.00 Buah
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 5.00 Buah/Orang/Hari
Produksi per hari = 4.00 x 5.00 = 20.00 Buah
Waktu dibutuhkan = 12.0 : 20.00 = 0.60 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Hak Penahan Angin Jendela
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

Tarikan Jendela
Volume pekerjaan = 12.00 Buah
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 5.00 Buah/Orang/Hari
Produksi per hari = 6.00 x 5.00 = 30.00 Buah
Waktu dibutuhkan = 12.0 : 30.00 = 0.40 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Tarikan Jendela
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

3 Jendela Type V1 (2 Unit)


Kosen Kayu Kelas II
Volume pekerjaan = 0.03 M3
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 5.00 M3/Orang/Hari
Produksi per hari = 0.03 x 5.00 = 0.15 M3
Waktu dibutuhkan = 0.03 : 0.15 = 0.19 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Kosen Kayu Kelas II
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

Daun Jendela Uk. 60x180 cm


Volume pekerjaan = 2.00 Lembar
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 1.00 M3/Orang/Hari
Produksi per hari = 1.00 x 1.00 = 1.00 Lembar
Waktu dibutuhkan = 2.00 : 1.00 = 2.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Daun Jendela Uk. 60x180 cm
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)
Engsel Jendela Ventilasi
Volume pekerjaan = 4.00 Buah
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 1.00 Buah/Orang/Hari
Produksi per hari = 1.00 x 1.00 = 1.00 Buah
Waktu dibutuhkan = 4.00 : 1.00 = 4.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Engsel Jendela Ventilasi
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

Grendel Jendela Ventilasi


Volume pekerjaan = 2.00 Buah
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 1.00 Buah/Orang/Hari
Produksi per hari = 1.00 x 1.00 = 1.00 Buah
Waktu dibutuhkan = 2.00 : 1.00 = 2.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Grendel Jendela Ventilasi
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

Hak Penahan Angin Jendela/Ventilasi


Volume pekerjaan = 2.00 Buah
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 1.00 Buah/Orang/Hari
Produksi per hari = 1.00 x 1.00 = 1.00 Buah
Waktu dibutuhkan = 2.00 : 1.00 = 2.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Hak Penahan Angin Jendela/Ventilasi
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

Tarikan Jendela/Ventilasi
Volume pekerjaan = 2.00 Buah
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 1.00 OH
Kapasitas produksi per hari = 1.00 Buah/Orang/Hari
Produksi per hari = 1.00 x 1.00 = 1.00 Buah
Waktu dibutuhkan = 2.00 : 1.00 = 2.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Tarikan Jendela/Ventilasi
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

VIII. PEKERJAAN PENGECATAN


1 Cat Tembok 3 x (L/D)
Volume pekerjaan = 277.30 M2
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 1.00 M2/Orang/Hari
Produksi per hari = 20.00 x 1.00 = 20.00 M2
Waktu dibutuhkan = 277.30 : 20.00 = 13.87 Hari = 2 Minggu
Jumlah Pemakaian Bahan = Cat Tembok 3 x (L/D)
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

2 Cat Plafond
Volume pekerjaan = 107.81 M2
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 1.00 M2/Orang/Hari
Produksi per hari = 20.00 x 1.00 = 20.00 M2
Waktu dibutuhkan = 107.81 : 20.00 = 5.39 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Cat Plafond
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

3 Cat Mengkilat kosen dan Daun Pintu/Jendela


Volume pekerjaan = 77.26 M2
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 1.00 M2/Orang/Hari
Produksi per hari = 20.00 x 1.00 = 20.00 M2
Waktu dibutuhkan = 77.26 : 20.00 = 3.86 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Cat Mengkilat kosen dan Daun Pintu/Jendela
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

IX. PEKERJAAN INSTALASI LISTRIK


1 Pemasukan Listrik 6 Ampere + Grounding
Volume pekerjaan = 1.00 Ls
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 1.00 M2/Orang/Hari
Produksi per hari = 1.00 x 1.00 = 1.00 Ls
Waktu dibutuhkan = 1.00 : 1.00 = 1.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Pemasukan Listrik 6 Ampere + Grounding
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

2 Zekering Kast Lokal 2 Group


Volume pekerjaan = 1.00 Buah
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 1.00 M2/Orang/Hari
Produksi per hari = 1.00 x 1.00 = 1.00 Buah
Waktu dibutuhkan = 1.00 : 1.00 = 1.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Zekering Kast Lokal 2 Group
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

3 Lampu HE 18 Watt
Volume pekerjaan = 4.00 Buah
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 4.00 Buah/Orang/Hari
Produksi per hari = 1.00 x 4.00 = 4.00 Buah
Waktu dibutuhkan = 4.00 : 4.00 = 1.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Lampu HE 18 Watt
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

3 Lampu TL 2x20 Watt


Volume pekerjaan = 4.00 Buah
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 4.00 Buah/Orang/Hari
Produksi per hari = 1.00 x 4.00 = 4.00 Buah
Waktu dibutuhkan = 4.00 : 4.00 = 1.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Lampu TL 2x20 Watt
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

4 Saklar lampu Merk Panasonik


Volume pekerjaan = 6.00 Buah
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 6.00 Buah/Orang/Hari
Produksi per hari = 1.00 x 6.00 = 6.00 Buah
Waktu dibutuhkan = 6.00 : 6.00 = 1.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Saklar lampu Merk Panasonik
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

5 Instalasi Titik Penerangan, Instalasi termasuk Kabel NYA 2,5


Volume pekerjaan = 8.00 Buah
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 8.00 Buah/Orang/Hari
Produksi per hari = 1.00 x 8.00 = 8.00 Buah
Waktu dibutuhkan = 8.00 : 8.00 = 1.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Instalasi Titik Penerangan, Instalasi termasuk Kabel NYA 2,5
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)
6 Stop Kontak + Instalasi Titik Stop Kontak, Termasuk Kabel
Volume pekerjaan = 6.00 Buah
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 6.00 Buah/Orang/Hari
Produksi per hari = 1.00 x 6.00 = 6.00 Buah
Waktu dibutuhkan = 6.00 : 6.00 = 1.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Stop Kontak + Instalasi Titik Stop Kontak, Termasuk Kabel
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)

XI. PEKERJAAN LAIN-LAIN


1 Pembersihan Akhir
Volume pekerjaan = 1.00 Ls
Tenaga kerja yang digunakan = Man Power
Jumlah tenaga dipekerjakan = 2.00 OH
Kapasitas produksi per hari = 1.00 M2/Orang/Hari
Produksi per hari = 1.00 x 1.00 = 1.00 Ls
Waktu dibutuhkan = 1.00 : 1.00 = 1.00 Hari = 1 Minggu
Jumlah Pemakaian Bahan = Pembersihan Akhir
Jumlah Pemakaian Alat = Alat-alat Bantu (Cangkul, pacul, parang dll)
II. Berdasarkan Pemeriksaan dan Penelitian tersebut bahwa :

KEMAJUAN KEMAJUAN
TOTAL HARGA NILAI BOBOT PERSENTASE
NO URAIAN PEKERJAAN TOTAL HARGA TERHADAP SUB TERHADAP ITEM KET.
REALISASI TERHADAP TOTAL (%) REALISASI (%)
PEKERJAAN (%) PEKERJAAN (%)

1 2 7 8 9 10 11 12
I. PEKERJAAN PERSIAPAN
1 Persiapan & Pembersihan Lapangan 500,000.00 500,000.00 0.22 100.00 100.00 0.22
2 Pengukuran dan pemasangan bowplank 500,000.00 500,000.00 0.22 100.00 100.00 0.22
3 Papan Nama Proyek 300,000.00 300,000.00 0.13 100.00 100.00 0.13
4 Administrasi dan Dokumentasi 850,000.00 510,000.00 0.37 60.00 60.00 0.22
Sub Jumlah 2,150,000.00 1,810,000.00 0.94 0.79
II. PEKERJAAN TANAH DAN PONDASI
1 Galian Tanah Pondasi 1,634,000.00 1,634,000.00 0.71 100.00 100.00 0.71
2 Urugan Kembali Bekas Galian 240,666.67 240,666.67 0.11 100.00 100.00 0.11
3 Urugan Pasir Alas Pondasi 298,400.00 298,400.00 0.13 100.00 100.00 0.13
4 Pasangan Batu Kosong / Aanstamping 1,108,800.00 1,108,800.00 0.48 100.00 100.00 0.48
5 Pasangan Pondasi Batu Gunung 10,511,100.00 10,511,100.00 4.59 100.00 100.00 4.59
6 Pondasi Bata Rolag 1 Pc : 2 PP (Trasraam) Teras 2,267,460.00 2,267,460.00 0.99 100.00 100.00 0.99
Sub Jumlah 16,060,426.67 16,060,426.67 7.01 7.01
III. PEKERJAAN BETON BERTULANG
1 Sloof Beton uk. 20/25 cm 13,158,750.00 13,158,750.00 5.74 100.00 100.00 5.74
2 Plat Dack T=08 cm 8,641,930.08 8,641,930.08 3.77 100.00 100.00 3.77
3 Kolom 20/20 cm 31,550,400.00 31,550,400.00 13.77 100.00 100.00 13.77
4 Ring Balok & Balok uk. 15/18 cm 11,254,626.00 11,254,626.00 4.91 100.00 100.00 4.91
5 Kolom Fasade Jendela (Bingkai) uk. 13/13 cm 7,044,562.20 - 3.08 - - -
Sub Jumlah 71,650,268.28 64,605,706.08 31.28 28.20
IV. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasangan Trasraam Bata 1 PC : 2 PP 1,841,100.00 1,841,100.00 0.80 100.00 100.00 0.80
2 Plesteran trasraam Bata 1 PC : 2 PP 1,888,600.00 1,888,600.00 0.82 100.00 100.00 0.82
3 Pasangan Dinding Bata 1 PC : 4 PP 8,221,492.00 8,221,492.00 3.59 100.00 100.00 3.59
4 Plesteran Dinding Bata 1 PC : 4 PP 9,332,700.00 9,332,700.00 4.07 100.00 100.00 4.07
Sub Jumlah 21,283,892.00 21,283,892.00 9.29 9.29
V. PEKERJAAN LANTAI
Pekerjaan Timbunan dan Urugan
1 Timbunan Tanah bawah Lantai 2,354,000.00 2,354,000.00 1.03 100.00 100.00 1.03
2 Urugan Pasir Bawah Lantai 1,025,750.00 - 0.45 - - -
Pekerjaan Keramik
1 Rabat Beton dibawah Lantai Keramik 2,380,812.50 - 1.04 - - -
2 Keramik Lantai 40 x 40 cm (Polished) 14,716,725.00 - 6.42 - - -
Sub Jumlah 20,477,287.50 2,354,000.00 8.94 1.03
VI. PEKERJAAN ATAP DAN PLAFOND
1 Ranga Kuda-kuda Baja Ringan 24,112,413.39 9,644,965.36 10.53 40.00 40.00 4.21
2 Atap Seng Genteng Metal 13,122,401.85 3,280,600.46 5.73 25.00 25.00 1.43
3 Kubah Steinlessteel Fabrikasi 5,000,000.00 1,250,000.00 2.18 25.00 25.00 0.55
4 Listplank Papan + Pengecatan 1,916,000.00 - 0.84 - - -
5 Plafond Gypsum 5,606,120.00 - 2.45 - - -
6 Rangka Plafond Puring 10,198,826.00 - 4.45 - - -
7 Profil Gypsum 1,627,500.00 - 0.71 - - -
Sub Jumlah 61,583,261.24 14,175,565.82 26.88 6.19
VII. PEKERJAAN PINTU,JENDELA DAN KUNCI
1 Pintu Type P1 (3 Unit)
- Kosen Kayu Kelas II 1,193,254.92 1,193,254.92 0.52 100.00 100.00 0.52
- Daun Pintu Kayu P1 Uk.60x210 cm 4,800,000.00 - 2.10 - - -
- Kunci Pintu Standar 253,500.00 - 0.11 - - -
- Engsel Pintu 671,400.00 - 0.29 - - -
2 Jendela Type J1 (12 Unit)
- Kosen Kayu Kelas II 3,850,959.06 3,850,959.06 1.68 100.00 100.00 1.68
- Daun Jendela Uk. 60x180 cm 3,000,000.00 - 1.31 - - -
- Engsel Jendela 484,800.00 - 0.21 - - -
- Grendel Jendela 388,800.00 - 0.17 - - -
- Hak Penahan Angin Jendela 327,600.00 - 0.14 - - -
- Tarikan Jendela 327,600.00 - 0.14 - - -
KEMAJUAN KEMAJUAN
TOTAL HARGA NILAI BOBOT PERSENTASE
NO URAIAN PEKERJAAN TOTAL HARGA TERHADAP SUB TERHADAP ITEM KET.
REALISASI TERHADAP TOTAL (%) REALISASI (%)
PEKERJAAN (%) PEKERJAAN (%)

1 2 7 8 9 10 11 12
3 Jendela Type V1 (2 Unit)
- Kosen Kayu Kelas II 198,875.82 198,875.82 0.09 100.00 100.00 0.09
- Daun Jendela Uk. 60x180 cm 400,000.00 - 0.17 - - -
- Engsel Jendela Ventilasi 80,800.00 - 0.04 - - -
- Grendel Jendela Ventilasi 64,800.00 - 0.03 - - -
- Hak Penahan Angin Jendela/Ventilasi 54,600.00 - 0.02 - - -
- Tarikan Jendela/Ventilasi 54,600.00 - 0.02 - - -
Sub Jumlah 16,151,589.80 5,243,089.80 7.05 2.29
VIII. PEKERJAAN PENGECATAN
1 Cat Tembok 3 x (L/D) 6,793,850.00 - 2.97 - - -
2 Cat Plafond 4,312,400.00 - 1.88 - - -
3 Cat Mengkilat kosen dan Daun Pintu/Jendela 3,090,240.00 - 1.35 - - -
Sub Jumlah 14,196,490.00 - 6.20 -
IX. PEKERJAAN INSTALASI LISTRIK
1 Pemasukan Listrik 6 Ampere + Grounding 2,500,000.00 - 1.09 - - -
2 Zekering Kast Lokal 2 Group 250,000.00 - 0.11 - - -
3 Armatur
Lampu HE 18 Watt 168,000.00 - 0.07 - - -
Lampu TL 2x20 Watt 200,000.00 - 0.09 - - -
4 Saklar lampu Merk Panasonik
Saklar 1 Seri + Instalasi 90,000.00 - 0.04 - - -
5 Instalasi Titik Penerangan, Instalasi termasuk Kabel NYA 2,5 880,000.00 264,000.00 0.38 30.00 30.00 0.12
mm Dalam Pipa PVC Fitting Lampu dan Kelengkapan
Instalasi (terpasang)
6 Stop Kontak + Instalasi Titik Stop Kontak, Termasuk Kabel 750,000.00 225,000.00 0.33 30.00 30.00 0.10
NYA 2,5 mm Dalam Pipa PVC, Kotak Kontak dan Kelengkapan
Instalasi (terpasang)
Sub Jumlah 4,838,000.00 489,000.00 2.11 0.21
XI. PEKERJAAN LAIN-LAIN
1 Pembersihan Akhir 700,000.00 - 0.31 - - -
Sub Jumlah 700,000.00 - 0.31 -
JUMLAH 229,091,215.49 126,021,680.37 100.00 55.01
PPn 10 % 22,909,121.55 12,602,168.04
JUMLAH TOTAL 252,000,337.04 138,623,848.40
PEMBULATAN 252,000,000.00 138,600,000.00

Banda Aceh, Oktober 2014


Konsultan Pengawas Kontraktor Pelaksana
CV. PATI UTAMA KONSULTAN CV. RIVIA

M. WINARDI, A. Md JIKO JASMI


Direktur Direktur
Menyetujui
PEJABAT PELAKSANA TEKNIS KEGIATAN

Drs. IKHWANUDDIN, M.Si


Nip : 19661216 199503 1 001
II. Berdasarkan Pemeriksaan dan Penelitian tersebut bahwa :

KEMAJUAN KEMAJUAN
NILAI BOBOT PERSENTASE
NO URAIAN PEKERJAAN TOTAL HARGA TERHADAP SUB TERHADAP ITEM KET.
TERHADAP TOTAL (%) REALISASI (%)
PEKERJAAN (%) PEKERJAAN (%)

1 2 7 8 9 10 11 12
I. PEKERJAAN PERSIAPAN
1 Persiapan & Pembersihan Lapangan 500,000.00 0.22 100.00 100.00 0.22
2 Pengukuran dan pemasangan bowplank 500,000.00 0.22 100.00 100.00 0.22
3 Papan Nama Proyek 300,000.00 0.13 100.00 100.00 0.13
4 Administrasi dan Dokumentasi 850,000.00 0.37 60.00 60.00 0.22
Sub Jumlah 2,150,000.00 0.94 0.79
II. PEKERJAAN TANAH DAN PONDASI
1 Galian Tanah Pondasi 1,634,000.00 0.71 100.00 100.00 0.71
2 Urugan Kembali Bekas Galian 240,666.67 0.11 100.00 100.00 0.11
3 Urugan Pasir Alas Pondasi 298,400.00 0.13 100.00 100.00 0.13
4 Pasangan Batu Kosong / Aanstamping 1,108,800.00 0.48 100.00 100.00 0.48
5 Pasangan Pondasi Batu Gunung 10,511,100.00 4.59 100.00 100.00 4.59
6 Pondasi Bata Rolag 1 Pc : 2 PP (Trasraam) Teras 2,267,460.00 0.99 100.00 100.00 0.99
Sub Jumlah 16,060,426.67 7.01 7.01
III. PEKERJAAN BETON BERTULANG
1 Sloof Beton uk. 20/25 cm 13,158,750.00 5.74 100.00 100.00 5.74
2 Plat Dack T=08 cm 8,641,930.08 3.77 100.00 100.00 3.77
3 Kolom 20/20 cm 31,550,400.00 13.77 100.00 100.00 13.77
4 Ring Balok & Balok uk. 15/18 cm 11,254,626.00 4.91 100.00 100.00 4.91
5 Kolom Fasade Jendela (Bingkai) uk. 13/13 cm 7,044,562.20 3.08 - - -
Sub Jumlah 71,650,268.28 31.28 28.20
IV. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasangan Trasraam Bata 1 PC : 2 PP 1,841,100.00 0.80 100.00 100.00 0.80
2 Plesteran trasraam Bata 1 PC : 2 PP 1,888,600.00 0.82 100.00 100.00 0.82
3 Pasangan Dinding Bata 1 PC : 4 PP 8,221,492.00 3.59 100.00 100.00 3.59
4 Plesteran Dinding Bata 1 PC : 4 PP 9,332,700.00 4.07 100.00 100.00 4.07
Sub Jumlah 21,283,892.00 9.29 9.29
V. PEKERJAAN LANTAI
Pekerjaan Timbunan dan Urugan
1 Timbunan Tanah bawah Lantai 2,354,000.00 1.03 100.00 100.00 1.03
2 Urugan Pasir Bawah Lantai 1,025,750.00 0.45 - - -
Pekerjaan Keramik
1 Rabat Beton dibawah Lantai Keramik 2,380,812.50 1.04 - - -
2 Keramik Lantai 40 x 40 cm (Polished) 14,716,725.00 6.42 - - -
Sub Jumlah 20,477,287.50 8.94 1.03
VI. PEKERJAAN ATAP DAN PLAFOND
1 Ranga Kuda-kuda Baja Ringan 24,112,413.39 10.53 40.00 40.00 4.21
2 Atap Seng Genteng Metal 13,122,401.85 5.73 25.00 25.00 1.43
3 Kubah Steinlessteel Fabrikasi 5,000,000.00 2.18 25.00 25.00 0.55
4 Listplank Papan + Pengecatan 1,916,000.00 0.84 - - -
5 Plafond Gypsum 5,606,120.00 2.45 - - -
6 Rangka Plafond Puring 10,198,826.00 4.45 - - -
7 Profil Gypsum 1,627,500.00 0.71 - - -
Sub Jumlah 61,583,261.24 26.88 6.19
VII. PEKERJAAN PINTU,JENDELA DAN KUNCI
1 Pintu Type P1 (3 Unit)
- Kosen Kayu Kelas II 1,193,254.92 0.52 100.00 100.00 0.52
- Daun Pintu Kayu P1 Uk.60x210 cm 4,800,000.00 2.10 - - -
- Kunci Pintu Standar 253,500.00 0.11 - - -
- Engsel Pintu 671,400.00 0.29 - - -
2 Jendela Type J1 (12 Unit)
- Kosen Kayu Kelas II 3,850,959.06 1.68 100.00 100.00 1.68
- Daun Jendela Uk. 60x180 cm 3,000,000.00 1.31 - - -
- Engsel Jendela 484,800.00 0.21 - - -
- Grendel Jendela 388,800.00 0.17 - - -
- Hak Penahan Angin Jendela 327,600.00 0.14 - - -
- Tarikan Jendela 327,600.00 0.14 - - -
KEMAJUAN KEMAJUAN
NILAI BOBOT PERSENTASE
NO URAIAN PEKERJAAN TOTAL HARGA TERHADAP SUB TERHADAP ITEM KET.
TERHADAP TOTAL (%) REALISASI (%)
PEKERJAAN (%) PEKERJAAN (%)

1 2 7 8 9 10 11 12
3 Jendela Type V1 (2 Unit)
- Kosen Kayu Kelas II 198,875.82 0.09 100.00 100.00 0.09
- Daun Jendela Uk. 60x180 cm 400,000.00 0.17 - - -
- Engsel Jendela Ventilasi 80,800.00 0.04 - - -
- Grendel Jendela Ventilasi 64,800.00 0.03 - - -
- Hak Penahan Angin Jendela/Ventilasi 54,600.00 0.02 - - -
- Tarikan Jendela/Ventilasi 54,600.00 0.02 - - -
Sub Jumlah 16,151,589.80 7.05 2.29
VIII. PEKERJAAN PENGECATAN
1 Cat Tembok 3 x (L/D) 6,793,850.00 2.97 - - -
2 Cat Plafond 4,312,400.00 1.88 - - -
3 Cat Mengkilat kosen dan Daun Pintu/Jendela 3,090,240.00 1.35 - - -
Sub Jumlah 14,196,490.00 6.20 -
IX. PEKERJAAN INSTALASI LISTRIK
1 Pemasukan Listrik 6 Ampere + Grounding 2,500,000.00 1.09 - - -
2 Zekering Kast Lokal 2 Group 250,000.00 0.11 - - -
3 Armatur
Lampu HE 18 Watt 168,000.00 0.07 - - -
Lampu TL 2x20 Watt 200,000.00 0.09 - - -
4 Saklar lampu Merk Panasonik
Saklar 1 Seri + Instalasi 90,000.00 0.04 - - -
5 Instalasi Titik Penerangan, Instalasi termasuk Kabel NYA 2,5 880,000.00 0.38 30.00 30.00 0.12
mm Dalam Pipa PVC Fitting Lampu dan Kelengkapan
Instalasi (terpasang)
6 Stop Kontak + Instalasi Titik Stop Kontak, Termasuk Kabel 750,000.00 0.33 30.00 30.00 0.10
NYA 2,5 mm Dalam Pipa PVC, Kotak Kontak dan Kelengkapan
Instalasi (terpasang)
Sub Jumlah 4,838,000.00 2.11 0.21
XI. PEKERJAAN LAIN-LAIN
1 Pembersihan Akhir 700,000.00 0.31 - - -
Sub Jumlah 700,000.00 0.31 -
JUMLAH 229,091,215.49 100.00 55.01
PPn 10 % 22,909,121.55
JUMLAH TOTAL 252,000,337.04

NILAI KONTRAK 252,000,000.00

NILAI PEKERJAAN BAP INI 138,600,000.00

NILAI PEKERJAAN BAP YANG LALU -


NILAI PEKERJAAN S/D BAP INI 138,600,000.00
POTONGAN-POTONGAN
I. JAMINAN PEMELIHARAAN (5%) -
II. PENGEMBALIAN UANG MUKA -
III. DENDA -
IV. JUMLAH POTONGAN -

PEMBAYARAN BAP INI (TERMASUK PPn/ BRUTO/ GROSS) 138,600,000.00

TERBILANG Seratus tiga puluh delapan juta enam ratus ribu rupiah

Banda Aceh, Oktober 2014


Konsultan Pengawas Kontraktor Pelaksana
CV. PATI UTAMA KONSULTAN CV. RIVIA

M. WINARDI, A. Md JIKO JASMI


Direktur Direktur
Menyetujui
PEJABAT PELAKSANA TEKNIS KEGIATAN
KEMAJUAN KEMAJUAN
NILAI BOBOT PERSENTASE
NO URAIAN PEKERJAAN TOTAL HARGA TERHADAP SUB TERHADAP ITEM KET.
TERHADAP TOTAL (%) REALISASI (%)
PEKERJAAN (%) PEKERJAAN (%)

1 2 7 8 9 10 11 12

Drs. IKHWANUDDIN, M.Si


Nip : 19661216 199503 1 001
PEMERINTAH ACEH REKAPITULASI
DINAS PENDIDIKAN KEMAJUAN PEKERJAAN
Jln. Tgk. H. Mohd. Daud Beureueh No. 22 Tlp. 21011, 22121 Fax (0651) 31991-32386 BULAN KE - II

PEKERJAAN : PEMBANGUNAN RUANG IBADAH SD MUHAMMADIYAH SINABANG, KAB. SIMEULUE KONSULTAN PENGAWAS : CV. PATI UTAMA KONSULTAN
LOKASI : SIMEULUE KONTRAKTOR PELAKSANA : CV. RIVIA
NO. KONTRAK : 306/C.3/KONT-FSK/16,11/VIII/2014 BULAN : SEPTEMBER S.D OKTOBER 2014
TGL. KONTRAK : 25 AGUSTUS 2014 PERIODE : 26 SEPTEMBER S.D 10 OKTOBER 2014
TAHUN ANGGARAN : 2014 PROGRESS S.D SAAT INI 55.01 %

KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI


NO URAIAN PEKERJAAN JUMLAH HARGA BOBOT JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT
(Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%)

I PEKERJAAN PERSIAPAN 2,150,000.00 0.94 1,640,000.00 - 170,000.00 0.07 1,810,000.00 0.79


II PEKERJAAN TANAH DAN PONDASI 16,060,426.67 7.01 14,102,058.67 - 1,958,368.00 0.85 16,060,426.67 7.01

III PEKERJAAAN BETON BERTULANG 71,650,268.28 31.28 5,263,500.00 - 59,342,206.08 25.90 64,605,706.08 28.20

IV PEKERJAAN PASANGAN DAN PLESTERAN 21,283,892.00 9.29 - - 21,283,892.00 9.29 21,283,892.00 9.29
V PEKERJAAN LANTAI 20,477,287.50 8.94 - - 2,354,000.00 1.03 2,354,000.00 1.03

VI PEKERJAAN ATAP DAN PLAFOND 61,583,261.24 26.88 - - 14,175,565.82 6.19 14,175,565.82 6.19
VII PEKERJAAN PINTU, JENDELA DAN KUNCI 16,151,589.80 7.05 - - 5,243,089.80 2.29 5,243,089.80 2.29

VIII PEKERJAAN PENGECATAN 14,196,490.00 6.20 - - - - - -

IX PEKERJAAN INSTALASI LISTRIK 4,838,000.00 2.11 - - 489,000.00 0.21 489,000.00 0.21


X PEKERJAAN LAIN-LAIN 700,000.00 0.31 - - - - - -

JUMLAH 229,091,215.49 100.00 21,005,558.67 - 105,016,121.70 45.84 126,021,680.37 55.01


PPN 10% 22,909,121.55 2,100,555.87 10,501,612.17 12,602,168.04

TOTAL 252,000,337.04 23,106,114.53 115,517,733.87 138,623,848.40


DIBULATKAN 252,000,000.00 23,100,000.00 115,510,000.00 138,600,000.00

Diperiksa Oleh, Dibuat Oleh,


Konsultan Pengawas Kontraktor Pelaksana
CV. PATI UTAMA KONSULTAN CV. RIVIA

M. WINARDI, A. Md JIKO JASMI


Direktur Direktur

Mengetahui / Disetujui Oleh,


PEJABAT PELAKSANA TEKNIS KEGIATAN (PPTK)
DINAS PENDIDIKAN ACEH

Drs. IKHWANUDDIN, M. Si
Nip. 19661216 199503 1 001
PEMERINTAH ACEH

DINAS PENDIDIKAN LAPORAN KEAMAJUAN PEKERJAAN


Jln. Tgk. H. Mohd. Daud Beureueh No. 22 Tlp. 21011, 22121 Fax (0651) 31991-32386 BULAN KE - II

PEKERJAAN : PEMBANGUNAN RUANG IBADAH SD MUHAMMADIYAH SINABANG, KAB. SIMEULUE KONSULTAN PENGAWAS : CV. PATI UTAMA KONSULTAN
LOKASI : SIMEULUE KONTRAKTOR PELAKSANA : CV. RIVIA
NO. KONTRAK : 306/C.3/KONT-FSK/16,11/VIII/2014 BULAN : SEPTEMBER S.D OKTOBER 2014
TGL. KONTRAK : 25 AGUSTUS 2014 PERIODE : 26 SEPTEMBER S.D 10 OKTOBER 2014
TAHUN ANGGARAN : 2014 PROGRESS S.D SAAT INI 55.01 %

KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
TERHADAP
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT
VOLUME VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN

1 Persiapan & Pembersihan Lapangan 1.00 Paket 500,000.00 500,000.00 0.22 1.00 500,000.00 100.00 - - - 1.00 500,000.00 100.00 0.22
2 Pengukuran dan pemasangan bowplank 1.00 Paket 500,000.00 500,000.00 0.22 1.00 500,000.00 100.00 - - - 1.00 500,000.00 100.00 0.22

3 Papan Nama Proyek 1.00 Paket 300,000.00 300,000.00 0.13 1.00 300,000.00 100.00 - - - 1.00 300,000.00 100.00 0.13

4 Administrasi dan Dokumentasi 1.00 Paket 850,000.00 850,000.00 0.37 0.40 340,000.00 40.00 0.20 170,000.00 20.00 0.60 510,000.00 60.00 0.22
Sub Jumlah 2,150,000.00 0.94 1,640,000.00 170,000.00 1,810,000.00 0.79

II. PEKERJAAN TANAH DAN PONDASI

1 Galian Tanah Pondasi 38.00 M3 43,000.00 1,634,000.00 0.71 38.00 1,634,000.00 100.00 - - - 38.00 1,634,000.00 100.00 0.71
2 Urugan Kembali Bekas Galian 12.67 M3 19,000.00 240,666.67 0.11 5.07 96,266.67 40.00 7.60 144,400.00 60.00 12.67 240,666.67 100.00 0.11

3 Urugan Pasir Alas Pondasi 2.00 M3 149,200.00 298,400.00 0.13 2.00 298,400.00 100.00 - - - 2.00 298,400.00 100.00 0.13
4 Pasangan Batu Kosong / Aanstamping 4.00 M3 277,200.00 1,108,800.00 0.48 4.00 1,108,800.00 100.00 - - - 4.00 1,108,800.00 100.00 0.48

5 Pasangan Pondasi Batu Gunung 17.00 M3 618,300.00 10,511,100.00 4.59 17.00 10,511,100.00 100.00 - - - 17.00 10,511,100.00 100.00 4.59

6 Pondasi Bata Rolag 1 Pc : 2 PP (Trasraam) Teras 23.40 M2 96,900.00 2,267,460.00 0.99 4.68 453,492.00 20.00 18.72 1,813,968.00 80.00 23.40 2,267,460.00 100.00 0.99
Sub Jumlah 16,060,426.67 7.01 14,102,058.67 1,958,368.00 16,060,426.67 7.01

III. PEKERJAAN BETON BERTULANG

1 Sloof Beton uk. 20/25 cm 2.50 M3 5,263,500.00 13,158,750.00 5.74 1.00 5,263,500.00 40.00 1.50 7,895,250.00 60.00 2.50 13,158,750.00 100.00 5.74
2 Plat Dack T=08 cm 1.33 M3 6,511,400.00 8,641,930.08 3.77 - - - 1.33 8,641,930.08 100.00 1.33 8,641,930.08 100.00 3.77

3 Kolom 20/20 cm 3.60 M3 8,764,000.00 31,550,400.00 13.77 - - - 3.60 31,550,400.00 100.00 3.60 31,550,400.00 100.00 13.77
4 Ring Balok & Balok uk. 15/18 cm 1.62 M3 6,947,300.00 11,254,626.00 4.91 - - - 1.62 11,254,626.00 100.00 1.62 11,254,626.00 100.00 4.91

5 Kolom Fasade Jendela (Bingkai) uk. 13/13 cm 1.01 M3 6,947,300.00 7,044,562.20 3.08 - - - - - - - - - -

Sub Jumlah 71,650,268.28 31.28 5,263,500.00 59,342,206.08 64,605,706.08 28.20


IV. PEKERJAAN PASANGAN DAN PLESTERAN

1 Pasangan Trasraam Bata 1 PC : 2 PP 19.00 M2 96,900.00 1,841,100.00 0.80 - - - 19.00 1,841,100.00 100.00 19.00 1,841,100.00 100.00 0.80

2 Plesteran trasraam Bata 1 PC : 2 PP 38.00 M2 49,700.00 1,888,600.00 0.82 - - - 38.00 1,888,600.00 100.00 38.00 1,888,600.00 100.00 0.82
3 Pasangan Dinding Bata 1 PC : 4 PP 93.32 M2 88,100.00 8,221,492.00 3.59 - - - 93.32 8,221,492.00 100.00 93.32 8,221,492.00 100.00 3.59

4 Plesteran Dinding Bata 1 PC : 4 PP 239.30 M2 39,000.00 9,332,700.00 4.07 - - - 239.30 9,332,700.00 100.00 239.30 9,332,700.00 100.00 4.07
Sub Jumlah 21,283,892.00 9.29 - 21,283,892.00 21,283,892.00 9.29
KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
TERHADAP
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT
VOLUME VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
V. PEKERJAAN LANTAI

Pekerjaan Timbunan dan Urugan

1 Timbunan Tanah bawah Lantai 27.50 M3 85,600.00 2,354,000.00 1.03 - - - 27.50 2,354,000.00 100.00 27.50 2,354,000.00 100.00 1.03

2 Urugan Pasir Bawah Lantai 6.88 M3 149,200.00 1,025,750.00 0.45 - - - - - - - - - -

Pekerjaan Keramik

1 Rabat Beton dibawah Lantai Keramik 3.44 M3 692,600.00 2,380,812.50 1.04 - - - - - - - - - -

2 Keramik Lantai 40 x 40 cm (Polished) 77.38 M2 190,200.00 14,716,725.00 6.42 - - - - - - - - - -

Sub Jumlah 20,477,287.50 8.94 - 2,354,000.00 2,354,000.00 1.03


VI. PEKERJAAN ATAP DAN PLAFOND

1 Ranga Kuda-kuda Baja Ringan 109.35 M2 220,500.00 24,112,413.39 10.53 - - - 43.74 9,644,965.36 40.00 43.74 9,644,965.36 40.00 4.21

2 Atap Seng Genteng Metal 109.35 M2 120,000.00 13,122,401.85 5.73 - - - 27.34 3,280,600.46 25.00 27.34 3,280,600.46 25.00 1.43
3 Kubah Steinlessteel Fabrikasi 1.00 Unit 5,000,000.00 5,000,000.00 2.18 - - - 0.25 1,250,000.00 25.00 0.25 1,250,000.00 25.00 0.55

4 Listplank Papan + Pengecatan 47.90 M 40,000.00 1,916,000.00 0.84 - - - - - - - - - -

5 Plafond Gypsum 107.81 M2 52,000.00 5,606,120.00 2.45 - - - - - - - - - -


6 Rangka Plafond Puring 107.81 M2 94,600.00 10,198,826.00 4.45 - - - - - - - - - -

7 Profil Gypsum 108.50 M' 15,000.00 1,627,500.00 0.71 - - - - - - - - - -


Sub Jumlah 61,583,261.24 26.88 - 14,175,565.82 14,175,565.82 6.19

VII. PEKERJAAN PINTU,JENDELA DAN KUNCI

1 Pintu Type P1 (3 Unit)


- Kosen Kayu Kelas II 0.17 M3 6,953,700.00 1,193,254.92 0.52 - - - 0.17 1,193,254.92 100.00 0.17 1,193,254.92 100.00 0.52

- Daun Pintu Kayu P1 Uk.60x210 cm 6.00 Lembar 800,000.00 4,800,000.00 2.10 - - - - - - - - - -

- Kunci Pintu Standar 3.00 Set 84,500.00 253,500.00 0.11 - - - - - - - - - -


- Engsel Pintu 18.00 Buah 37,300.00 671,400.00 0.29 - - - - - - - - - -

2 Jendela Type J1 (12 Unit)


- Kosen Kayu Kelas II 0.55 M3 6,953,700.00 3,850,959.06 1.68 - - - 0.55 3,850,959.06 100.00 0.55 3,850,959.06 100.00 1.68

- Daun Jendela Uk. 60x180 cm 12.00 Lembar 250,000.00 3,000,000.00 1.31 - - - - - - - - - -

- Engsel Jendela 24.00 Buah 20,200.00 484,800.00 0.21 - - - - - - - - - -

- Grendel Jendela 12.00 Buah 32,400.00 388,800.00 0.17 - - - - - - - - - -

- Hak Penahan Angin Jendela 12.00 Buah 27,300.00 327,600.00 0.14 - - - - - - - - - -

- Tarikan Jendela 12.000 Buah 27,300.00 327,600.00 0.14 - - - - - - - - - -


3 Jendela Type V1 (2 Unit)

- Kosen Kayu Kelas II 0.03 M3 6,953,700.00 198,875.82 0.09 - - - 0.03 198,875.82 100.00 0.03 198,875.82 100.00 0.09
- Daun Jendela Uk. 60x180 cm 2.00 Lembar 200,000.00 400,000.00 0.17 - - - - - - - - - -

- Engsel Jendela Ventilasi 4.00 Buah 20,200.00 80,800.00 0.04 - - - - - - - - - -

- Grendel Jendela Ventilasi 2.00 Buah 32,400.00 64,800.00 0.03 - - - - - - - - - -


- Hak Penahan Angin Jendela/Ventilasi 2.00 Buah 27,300.00 54,600.00 0.02 - - - - - - - - - -

- Tarikan Jendela/Ventilasi 2.000 Buah 27,300.00 54,600.00 0.02 - - - - - - - - - -

Sub Jumlah 16,151,589.80 7.05 - 5,243,089.80 5,243,089.80 2.29


KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
TERHADAP
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT
VOLUME VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
VIII. PEKERJAAN PENGECATAN

1 Cat Tembok 3 x (L/D) 277.30 M2 24,500.00 6,793,850.00 2.97 - - - - - - - - - -

2 Cat Plafond 107.81 M2 40,000.00 4,312,400.00 1.88 - - - - - - - - - -


KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
TERHADAP
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT
VOLUME VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
3 Cat Mengkilat kosen dan Daun Pintu/Jendela 77.26 M2 40,000.00 3,090,240.00 1.35 - - - - - - - - - -

Sub Jumlah 14,196,490.00 6.20 - - - -

IX. PEKERJAAN INSTALASI LISTRIK

1 Pemasukan Listrik 6 Ampere + Grounding 1.00 Ls 2,500,000.00 2,500,000.00 1.09 - - - - - - - - - -

2 Zekering Kast Lokal 2 Group 1.00 Buah 250,000.00 250,000.00 0.11 - - - - - - - - - -

3 Armatur

Lampu HE 18 Watt 4.00 Buah 42,000.00 168,000.00 0.07 - - - - - - - - - -

Lampu TL 2x20 Watt 4.00 Buah 50,000.00 200,000.00 0.09 - - - - - - - - - -


4 Saklar lampu Merk Panasonik

Saklar 1 Seri + Instalasi 6.00 Buah 15,000.00 90,000.00 0.04 - - - - - - - - - -

5 Instalasi Titik Penerangan, Instalasi termasuk Kabel NYA 2, 8.00 Buah 110,000.00 880,000.00 0.38 - - - 2.40 264,000.00 30.00 2.40 264,000.00 30.00 0.12
mm Dalam Pipa PVC Fitting Lampu dan Kelengkapan

Instalasi (terpasang)

6 Stop Kontak + Instalasi Titik Stop Kontak, Termasuk Kabel 6.00 Buah 125,000.00 750,000.00 0.33 - - - 1.80 225,000.00 30.00 1.80 225,000.00 30.00 0.10
NYA 2,5 mm Dalam Pipa PVC, Kotak Kontak dan Kelengkapan

Instalasi (terpasang)
Sub Jumlah 4,838,000.00 2.11 - 489,000.00 489,000.00 0.21

XI. PEKERJAAN LAIN-LAIN

1 Pembersihan Akhir 1.00 Ls 700,000.00 700,000.00 0.31 - - - - - - - - - -


Sub Jumlah 700,000.00 0.31 - - - - - - - - - -

JUMLAH HARGA DAN BOBOT 229,091,215.49 100.00 21,005,558.67 105,016,121.70 126,021,680.37 55.01
PPN 10% 22,909,121.55

JUMLAH TOTAL 252,000,337.04

DIBULATKAN 252,000,000.00

Diperiksa Oleh, Dibuat Oleh,


Konsultan Pengawas Kontraktor Pelaksana
CV. PATI UTAMA KONSULTAN CV. RIVIA

FACHRURRAZI, ST HANIF, ST
Pengawas Lapangan Site Manager
PEMERINTAH ACEH

DINAS PENDIDIKAN LAPORAN KEAMAJUAN PEKERJAAN


Jln. Tgk. H. Mohd. Daud Beureueh No. 22 Tlp. 21011, 22121 Fax (0651) 31991-32386 BULAN KE - I

PEKERJAAN : PEMBANGUNAN RUANG IBADAH SD MUHAMMADIYAH SINABANG, KAB. SIMEULUE KONSULTAN PENGAWAS : CV. PATI UTAMA KONSULTAN
LOKASI : SIMEULUE KONTRAKTOR PELAKSANA : CV. RIVIA
NO. KONTRAK : 306/C.3/KONT-FSK/16,11/VIII/2014 BULAN : AGUSTUS S.D SEPTEMBER 2014
TGL. KONTRAK : 25 AGUSTUS 2014 PERIODE : 25 AGUSTUS S.D 25 SEPTEMBER 2014
TAHUN ANGGARAN : 2014 PROGRESS S.D SAAT INI 9.17 %

KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
TERHADAP
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT
VOLUME VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN

1 Persiapan & Pembersihan Lapangan 1.00 Paket 500,000.00 500,000.00 0.22 - - - 1.00 500,000.00 100.00 1.00 500,000.00 100.00 0.22
2 Pengukuran dan pemasangan bowplank 1.00 Paket 500,000.00 500,000.00 0.22 - - - 1.00 500,000.00 100.00 1.00 500,000.00 100.00 0.22

3 Papan Nama Proyek 1.00 Paket 300,000.00 300,000.00 0.13 - - - 1.00 300,000.00 100.00 1.00 300,000.00 100.00 0.13

4 Administrasi dan Dokumentasi 1.00 Paket 850,000.00 850,000.00 0.37 - - - 0.40 340,000.00 40.00 0.40 340,000.00 40.00 0.15
Sub Jumlah 2,150,000.00 0.94 - 1,640,000.00 1,640,000.00 0.72

II. PEKERJAAN TANAH DAN PONDASI

1 Galian Tanah Pondasi 38.00 M3 43,000.00 1,634,000.00 0.71 - - - 38.00 1,634,000.00 100.00 38.00 1,634,000.00 100.00 0.71
2 Urugan Kembali Bekas Galian 12.67 M3 19,000.00 240,666.67 0.11 - - - 5.07 96,266.67 40.00 5.07 96,266.67 40.00 0.04

3 Urugan Pasir Alas Pondasi 2.00 M3 149,200.00 298,400.00 0.13 - - - 2.00 298,400.00 100.00 2.00 298,400.00 100.00 0.13
4 Pasangan Batu Kosong / Aanstamping 4.00 M3 277,200.00 1,108,800.00 0.48 - - - 4.00 1,108,800.00 100.00 4.00 1,108,800.00 100.00 0.48

5 Pasangan Pondasi Batu Gunung 17.00 M3 618,300.00 10,511,100.00 4.59 - - - 17.00 10,511,100.00 100.00 17.00 10,511,100.00 100.00 4.59

6 Pondasi Bata Rolag 1 Pc : 2 PP (Trasraam) Teras 23.40 M2 96,900.00 2,267,460.00 0.99 - - - 4.68 453,492.00 20.00 4.68 453,492.00 20.00 0.20
Sub Jumlah 16,060,426.67 7.01 - 14,102,058.67 14,102,058.67 6.16

III. PEKERJAAN BETON BERTULANG

1 Sloof Beton uk. 20/25 cm 2.50 M3 5,263,500.00 13,158,750.00 5.74 - - - 1.00 5,263,500.00 40.00 1.00 5,263,500.00 40.00 2.30
2 Plat Dack T=08 cm 1.33 M3 6,511,400.00 8,641,930.08 3.77 - - - - - - - - - -

3 Kolom 20/20 cm 3.60 M3 8,764,000.00 31,550,400.00 13.77 - - - - - - - - - -


4 Ring Balok & Balok uk. 15/18 cm 1.62 M3 6,947,300.00 11,254,626.00 4.91 - - - - - - - - - -

5 Kolom Fasade Jendela (Bingkai) uk. 13/13 cm 1.01 M3 6,947,300.00 7,044,562.20 3.08 - - - - - - - - - -

Sub Jumlah 71,650,268.28 31.28 - 5,263,500.00 5,263,500.00 2.30


IV. PEKERJAAN PASANGAN DAN PLESTERAN

1 Pasangan Trasraam Bata 1 PC : 2 PP 19.00 M2 96,900.00 1,841,100.00 0.80 - - - - - - - - - -

2 Plesteran trasraam Bata 1 PC : 2 PP 38.00 M2 49,700.00 1,888,600.00 0.82 - - - - - - - - - -


3 Pasangan Dinding Bata 1 PC : 4 PP 93.32 M2 88,100.00 8,221,492.00 3.59 - - - - - - - - - -

4 Plesteran Dinding Bata 1 PC : 4 PP 239.30 M2 39,000.00 9,332,700.00 4.07 - - - - - - - - - -


Sub Jumlah 21,283,892.00 9.29 - - - -
KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
TERHADAP
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT
VOLUME VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
V. PEKERJAAN LANTAI

Pekerjaan Timbunan dan Urugan

1 Timbunan Tanah bawah Lantai 27.50 M3 85,600.00 2,354,000.00 1.03 - - - - - - - - - -

2 Urugan Pasir Bawah Lantai 6.88 M3 149,200.00 1,025,750.00 0.45 - - - - - - - - - -

Pekerjaan Keramik

1 Rabat Beton dibawah Lantai Keramik 3.44 M3 692,600.00 2,380,812.50 1.04 - - - - - - - - - -

2 Keramik Lantai 40 x 40 cm (Polished) 77.38 M2 190,200.00 14,716,725.00 6.42 - - - - - - - - - -

Sub Jumlah 20,477,287.50 8.94 - - - -


VI. PEKERJAAN ATAP DAN PLAFOND

1 Ranga Kuda-kuda Baja Ringan 109.35 M2 220,500.00 24,112,413.39 10.53 - - - - - - - - - -

2 Atap Seng Genteng Metal 109.35 M2 120,000.00 13,122,401.85 5.73 - - - - - - - - - -


3 Kubah Steinlessteel Fabrikasi 1.00 Unit 5,000,000.00 5,000,000.00 2.18 - - - - - - - - - -

4 Listplank Papan + Pengecatan 47.90 M 40,000.00 1,916,000.00 0.84 - - - - - - - - - -

5 Plafond Gypsum 107.81 M2 52,000.00 5,606,120.00 2.45 - - - - - - - - - -


6 Rangka Plafond Puring 107.81 M2 94,600.00 10,198,826.00 4.45 - - - - - - - - - -

7 Profil Gypsum 108.50 M' 15,000.00 1,627,500.00 0.71 - - - - - - - - - -


Sub Jumlah 61,583,261.24 26.88 - - - -

VII. PEKERJAAN PINTU,JENDELA DAN KUNCI

1 Pintu Type P1 (3 Unit)


- Kosen Kayu Kelas II 0.17 M3 6,953,700.00 1,193,254.92 0.52 - - - - - - - - - -

- Daun Pintu Kayu P1 Uk.60x210 cm 6.00 Lembar 800,000.00 4,800,000.00 2.10 - - - - - - - - - -

- Kunci Pintu Standar 3.00 Set 84,500.00 253,500.00 0.11 - - - - - - - - - -


- Engsel Pintu 18.00 Buah 37,300.00 671,400.00 0.29 - - - - - - - - - -

2 Jendela Type J1 (12 Unit)


- Kosen Kayu Kelas II 0.55 M3 6,953,700.00 3,850,959.06 1.68 - - - - - - - - - -

- Daun Jendela Uk. 60x180 cm 12.00 Lembar 250,000.00 3,000,000.00 1.31 - - - - - - - - - -

- Engsel Jendela 24.00 Buah 20,200.00 484,800.00 0.21 - - - - - - - - - -

- Grendel Jendela 12.00 Buah 32,400.00 388,800.00 0.17 - - - - - - - - - -

- Hak Penahan Angin Jendela 12.00 Buah 27,300.00 327,600.00 0.14 - - - - - - - - - -

- Tarikan Jendela 12.000 Buah 27,300.00 327,600.00 0.14 - - - - - - - - - -


3 Jendela Type V1 (2 Unit)

- Kosen Kayu Kelas II 0.03 M3 6,953,700.00 198,875.82 0.09 - - - - - - - - - -


- Daun Jendela Uk. 60x180 cm 2.00 Lembar 200,000.00 400,000.00 0.17 - - - - - - - - - -

- Engsel Jendela Ventilasi 4.00 Buah 20,200.00 80,800.00 0.04 - - - - - - - - - -

- Grendel Jendela Ventilasi 2.00 Buah 32,400.00 64,800.00 0.03 - - - - - - - - - -


- Hak Penahan Angin Jendela/Ventilasi 2.00 Buah 27,300.00 54,600.00 0.02 - - - - - - - - - -

- Tarikan Jendela/Ventilasi 2.000 Buah 27,300.00 54,600.00 0.02 - - - - - - - - - -

Sub Jumlah 16,151,589.80 7.05 - - - -


KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
TERHADAP
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT
VOLUME VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
VIII. PEKERJAAN PENGECATAN

1 Cat Tembok 3 x (L/D) 277.30 M2 24,500.00 6,793,850.00 2.97 - - - - - - - - - -

2 Cat Plafond 107.81 M2 40,000.00 4,312,400.00 1.88 - - - - - - - - - -


KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
TERHADAP
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT
VOLUME VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
3 Cat Mengkilat kosen dan Daun Pintu/Jendela 77.26 M2 40,000.00 3,090,240.00 1.35 - - - - - - - - - -

Sub Jumlah 14,196,490.00 6.20 - - - -

IX. PEKERJAAN INSTALASI LISTRIK

1 Pemasukan Listrik 6 Ampere + Grounding 1.00 Ls 2,500,000.00 2,500,000.00 1.09 - - - - - - - - - -

2 Zekering Kast Lokal 2 Group 1.00 Buah 250,000.00 250,000.00 0.11 - - - - - - - - - -

3 Armatur

Lampu HE 18 Watt 4.00 Buah 42,000.00 168,000.00 0.07 - - - - - - - - - -

Lampu TL 2x20 Watt 4.00 Buah 50,000.00 200,000.00 0.09 - - - - - - - - - -


4 Saklar lampu Merk Panasonik

Saklar 1 Seri + Instalasi 6.00 Buah 15,000.00 90,000.00 0.04 - - - - - - - - - -

5 Instalasi Titik Penerangan, Instalasi termasuk Kabel NYA 2, 8.00 Buah 110,000.00 880,000.00 0.38 - - - - - - - - - -
mm Dalam Pipa PVC Fitting Lampu dan Kelengkapan

Instalasi (terpasang)

6 Stop Kontak + Instalasi Titik Stop Kontak, Termasuk Kabel 6.00 Buah 125,000.00 750,000.00 0.33 - - - - - - - - - -
NYA 2,5 mm Dalam Pipa PVC, Kotak Kontak dan Kelengkapan

Instalasi (terpasang)
Sub Jumlah 4,838,000.00 2.11 - - - -

XI. PEKERJAAN LAIN-LAIN

1 Pembersihan Akhir 1.00 Ls 700,000.00 700,000.00 0.31 - - - - - - - - - -


Sub Jumlah 700,000.00 0.31 - - - - -

JUMLAH HARGA DAN BOBOT 229,091,215.49 100.00 - 21,005,558.67 21,005,558.67 9.17


PPN 10% 22,909,121.55

JUMLAH TOTAL 252,000,337.04

DIBULATKAN 252,000,000.00

Diperiksa Oleh, Dibuat Oleh,


Konsultan Pengawas Kontraktor Pelaksana
CV. PATI UTAMA KONSULTAN CV. RIVIA

FACHRURRAZI, ST HANIF, ST
Pengawas Lapangan Site Manager
PEMERINTAH ACEH REKAPITULASI
DINAS PENDIDIKAN KEMAJUAN PEKERJAAN
Jln. Tgk. H. Mohd. Daud Beureueh No. 22 Tlp. 21011, 22121 Fax (0651) 31991-32386 BULAN KE - I

PEKERJAAN : PEMBANGUNAN RUANG IBADAH SD MUHAMMADIYAH SINABANG, KAB. SIMEULUE KONSULTAN PENGAWAS : CV. PATI UTAMA KONSULTAN
LOKASI : SIMEULUE KONTRAKTOR PELAKSANA : CV. RIVIA
NO. KONTRAK : 306/C.3/KONT-FSK/16,11/VIII/2014 BULAN : AGUSTUS S.D SEPTEMBER 2014
TGL. KONTRAK : 25 AGUSTUS 2014 PERIODE : 25 AGUSTUS S.D 25 SEPTEMBER 2014
TAHUN ANGGARAN : 2014 PROGRESS S.D SAAT INI 9.17 %

KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI


NO URAIAN PEKERJAAN JUMLAH HARGA BOBOT JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT
(Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%)

I PEKERJAAN PERSIAPAN 2,150,000.00 0.94 - - 1,640,000.00 0.72 1,640,000.00 0.72


II PEKERJAAN TANAH DAN PONDASI 16,060,426.67 7.01 - - 14,102,058.67 6.16 14,102,058.67 6.16

III PEKERJAAAN BETON BERTULANG 71,650,268.28 31.28 - - 5,263,500.00 2.30 5,263,500.00 2.30

IV PEKERJAAN PASANGAN DAN PLESTERAN 21,283,892.00 9.29 - - - - - -


V PEKERJAAN LANTAI 20,477,287.50 8.94 - - - - - -

VI PEKERJAAN ATAP DAN PLAFOND 61,583,261.24 26.88 - - - - - -


VII PEKERJAAN PINTU, JENDELA DAN KUNCI 16,151,589.80 7.05 - - - - - -

VIII PEKERJAAN PENGECATAN 14,196,490.00 6.20 - - - - - -

IX PEKERJAAN INSTALASI LISTRIK 4,838,000.00 2.11 - - - - - -


X PEKERJAAN LAIN-LAIN 700,000.00 0.31 - - - - - -

JUMLAH 229,091,215.49 100.00 - - 21,005,558.67 9.17 21,005,558.67 9.17


PPN 10% 22,909,121.55 - 2,100,555.87 2,100,555.87

TOTAL 252,000,337.04 - 23,106,114.53 23,106,114.53


DIBULATKAN 252,000,000.00 - 23,100,000.00 23,100,000.00

Diperiksa Oleh, Dibuat Oleh,


Konsultan Pengawas Kontraktor Pelaksana
CV. PATI UTAMA KONSULTAN CV. RIVIA

M. WINARDI, A. Md JIKO JASMI


Direktur Direktur

Mengetahui / Disetujui Oleh,


PEJABAT PELAKSANA TEKNIS KEGIATAN (PPTK)
DINAS PENDIDIKAN ACEH

Drs. IKHWANUDDIN, M. Si
Nip. 19661216 199503 1 001
PEMERINTAH KABUPATEN PIDIE

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN LAPORAN KEMAJUAN PEKERJAAN


Jl. Prof. A. Majid Ibrahim Tijue - Sigli (0653) 21209 BULAN KE - IV

PEKERJAAN : PEMBANGUNAN PANGGUNG UTAMA PADA ARENA UTAMA MTQ KE XXXIV PROV. ACEH TAHUN 2019
LOKASI : KAB. PIDIE KONTRAKTOR PELAKSANA : CV. GUNTOMARA
NO. KONTRAK : 640/015/DAU/PRKP/2019 BULAN : IV
TGL. KONTRAK : 29 APRIL 2019 PERIODE : 22 JULI S.D 26 AGUSTUS 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI #REF! %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT
KONTRAK VOLUME VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN

1 Pengukuran / Setting Out 1.00 Ls 5,000,000.00 5,000,000.00 0.46 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!

2 Biaya Penyelenggaraan Keamanan dan Keselamatan Ker 1.00 Ls 5,000,000.00 5,000,000.00 0.46 - - #REF! 0.20 1,000,000.00 20.00 0.20 1,000,000.00 #REF! #REF!

3 Papan Nama Proyek 1.00 Ls 800,000.00 800,000.00 0.07 - - #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

4 Administrasi Dan Dokumentasi 1.00 Ls 5,000,000.00 5,000,000.00 0.46 #REF! #REF! #REF! 0.20 1,000,000.00 20.00 #REF! #REF! #REF! #REF!

Sub Jumlah 15,800,000.00 1.45 #REF! #REF! #REF! #REF!


II. PEKERJAAN PANGGUNG UTAMA

A. PEMBUATAN PANGGUNG

1 Rangka Panggung Utama + Lantai Tripleks T = 18 mm 1.00 Unit 80,000,000.00 80,000,000.00 7.33 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!

2 Karpet Lantai 1.00 Unit 15,000,000.00 15,000,000.00 1.37 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!

3 ORNAMEN PVC CUTTING CNC 1.00 Unit 20,000,000.00 20,000,000.00 1.83 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!
Sub Jumlah 115,000,000.00 10.54 #REF! - #REF! #REF!

B. PEKERJAAN BACKDROP
1 ORNAMEN PVC 18 T = 18 MM CUTTING CNC + RANG 17.78 M2 1,300,000.00 23,114,000.00 2.12 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!

2 ORNAMEN TEMBAGA 1.00 LS 5,000,000.00 5,000,000.00 0.46 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!

3 ORNNAMEN PVC 18 MM 50.44 M2 1,000,000.00 50,440,000.00 4.62 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!
4 PRINTING ORNAMANEN VINYL 59.16 M2 250,000.00 14,790,000.00 1.36 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!

5 ORNAMEN GRC 8.68 M2 1,180,000.00 10,242,400.00 0.94 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!
Sub Jumlah 103,586,400.00 9.49 #REF! - #REF! #REF!

C. PEKERJAAN DEKORASI TAMAN DAN SCLUPTURE

1 LANSEKAP DAN TAMAN 1.00 Ls 80,000,000.00 80,000,000.00 7.33 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!
2 SCLUPTURE AKRILIK 1.00 Ls 30,000,000.00 30,000,000.00 2.75 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!

Sub Jumlah 110,000,000.00 10.08 #REF! - #REF! #REF!


III. PEMBUATAN MIMBAR TILAWAH

1 Rangka Mimbar Tilawah + Dinding Tripleks T = 8 mm 23.36 M2 120,000.00 2,803,200.00 0.26 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!
2 Cat Dinding Mimbar Tilawah 23.36 M2 80,000.00 1,868,800.00 0.17 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!

3 PVC CUTTING CNC 12 MM 7.60 M2 730,000.00 5,548,000.00 0.51 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!

4 AIR CONDITIONER AC 1 PK 1.00 Ls 4,000,000.00 4,000,000.00 0.37 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!
5 KACA AKRILIK 5MM 13.04 M2 900,000.00 11,736,000.00 1.08 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!

6 ATAP RESINE FIBER 26.08 M2 1,200,000.00 31,296,000.00 2.87 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!
NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT
KONTRAK VOLUME VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Sub Jumlah 57,252,000.00 5.25 #REF! - #REF! #REF!

IV. PEMBUATAN BILIK DEWAN HAKIM

1 ORNAMEN PVC 18 MM 40.88 M2 1,300,000.00 53,144,000.00 4.87 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!

2 Rangka Bilik + Dinding Tripleks T = 8 mm 178.28 M2 120,000.00 21,393,600.00 1.96 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF!

3 CAT DINDING BILIK 178.28 M2 80,000.00 14,262,400.00 1.31 #REF! #REF! #REF! 35.66 2,852,480.00 20.00 #REF! #REF! #REF! #REF!
4 KACA AKRILIK 5MM 17.78 M2 800,000.00 14,224,000.00 1.30 #REF! #REF! #REF! 3.56 2,844,800.00 20.00 #REF! #REF! #REF! #REF!

5 AIR CONDITIONER (AC) 2 PK 2.00 Ls 6,500,000.00 13,000,000.00 1.19 #REF! #REF! #REF! 0.40 2,600,000.00 20.00 #REF! #REF! #REF! #REF!

6 MEJA DEWAN HAKIM 14.00 BUAH 500,000.00 7,000,000.00 0.64 #REF! #REF! #REF! 8.40 4,200,000.00 60.00 #REF! #REF! #REF! #REF!

7 KURSI DEWAN HAKIM 14.00 BUAH 250,000.00 3,500,000.00 0.32 #REF! #REF! #REF! 8.40 2,100,000.00 60.00 #REF! #REF! #REF! #REF!

Sub Jumlah 126,524,000.00 11.60 #REF! 14,597,280.00 #REF! #REF!

V. PEKERJAAN LAIN-LAIN

1 SEWA KURSI PESERTA (75 ORANG X 23 KAB/KOTA 1725.00 BH 87,900.00 151,627,500.00 13.90 #REF! #REF! #REF! 517.50 45,488,250.00 30.00 #REF! #REF! #REF! #REF!

2 SEWA KURSI PADUAN SUARA 45.00 BH 100,000.00 4,500,000.00 0.41 #REF! #REF! #REF! 13.50 1,350,000.00 30.00 #REF! #REF! #REF! #REF!
3 SEWA KURSI TAMU UNDANGAN NON VIP 50.00 BH 100,000.00 5,000,000.00 0.46 #REF! #REF! #REF! 15.00 1,500,000.00 30.00 #REF! #REF! #REF! #REF!

4 SEWA KURSI TAMU UNDANGAN TAMU VIP 100.00 Ls 100,000.00 10,000,000.00 0.92 #REF! #REF! #REF! 30.00 3,000,000.00 30.00 #REF! #REF! #REF! #REF!
5 SEWA MEJA TAMU UNDANGAN TAMU VIP 20.00 Ls 100,000.00 2,000,000.00 0.18 #REF! #REF! #REF! 6.00 600,000.00 30.00 #REF! #REF! #REF! #REF!

6 SEWA TENDA TERATAK UK.5X5 M UNTUK KAFILAH 23 69.00 UNIT 300,000.00 20,700,000.00 1.90 #REF! #REF! #REF! 20.70 6,210,000.00 30.00 #REF! #REF! #REF! #REF!

7 SEWA TENDA TERATAK UK.5X5 M UNTUK TAMU UND 4.00 UNIT 300,000.00 1,200,000.00 0.11 #REF! #REF! #REF! 1.20 360,000.00 30.00 #REF! #REF! #REF! #REF!
8 SEWA TENDA TERATAK UK.5X5 M UNTUK PADUAN SU 2.00 UNIT 300,000.00 600,000.00 0.05 #REF! #REF! #REF! 0.60 180,000.00 30.00 #REF! #REF! #REF! #REF!

9 SEWA TENDA TERATAK UK.5X5 M UNTUK CADANGAN 4.00 UNIT 300,000.00 1,200,000.00 0.11 #REF! #REF! #REF! 1.20 360,000.00 30.00 #REF! #REF! #REF! #REF!

10 SEWA SOUND SYTEM 60.000 WATT 1.00 LS 150,000,000.00 150,000,000.00 13.75 #REF! #REF! #REF! 0.30 45,000,000.00 30.00 #REF! #REF! #REF! #REF!

11 LIGHTING + GENSET 1.00 LS 135,000,000.00 135,000,000.00 12.37 #REF! #REF! #REF! 0.30 40,500,000.00 30.00 #REF! #REF! #REF! #REF!

12 PRINTING TEMA 1.00 LS 6,000,000.00 6,000,000.00 0.55 #REF! #REF! #REF! 0.30 1,800,000.00 30.00 #REF! #REF! #REF! #REF!
Sub Jumlah 487,827,500.00 44.71 #REF! 146,348,250.00 #REF! #REF!

VI. PEMBUATAN MENARA

1 ORNAMEN PVC CUTTING CNC 1.00 Ls 40,000,000.00 40,000,000.00 3.67 #REF! #REF! #REF! 0.70 28,000,000.00 70.00 #REF! #REF! #REF! #REF!

2 Rangka Menara dari Besi Hollow 40 x 40 mm 1.00 Ls 30,000,000.00 30,000,000.00 2.75 #REF! #REF! #REF! 0.70 21,000,000.00 70.00 #REF! #REF! #REF! #REF!

3 Lighting 1.00 Ls 5,000,000.00 5,000,000.00 0.46 #REF! #REF! #REF! 0.90 4,500,000.00 90.00 #REF! #REF! #REF! #REF!
Sub Jumlah 75,000,000.00 6.87 #REF! 53,500,000.00 #REF! #REF!

JUMLAH HARGA DAN BOBOT 1,090,989,900.00 100.00 #REF! #REF! #REF! #REF!

PPN 10% 109,098,990.00 #REF! #REF! #REF!

TOTAL KESELURUHAN 1,200,088,890.00 #REF! #REF! #REF!


DIBULATKAN 1,200,088,000.00 #REF! #REF! #REF!

Pidie, 26 Agustus 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. GUNTOMARA
NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT
KONTRAK VOLUME VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
T. EPI ISWARI, ST YUSWADI, ST SAID HUSAIN
Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur
PEMERINTAH KABUPATEN PIDIE

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN PROGRESS REPORT


Jl. Prof. A. Majid Ibrahim Tijue - Sigli (0653) 21209 100%

PEKERJAAN : PEMBANGUNAN PANGGUNG UTAMA PADA ARENA UTAMA MTQ KE XXXIV PROV. ACEH TAHUN 2019
LOKASI : KAB. PIDIE KONTRAKTOR PELAKSANA : CV. GUNTOMARA
NO. KONTRAK : 640/015/DAU/PRKP/2019 BULAN : IV
TGL. KONTRAK : 29 APRIL 2019 PERIODE : 22 JULI S.D 26 AGUSTUS 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI - %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH BOBOT JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN
1 Pengukuran 1.00 Ls 2,000,000.00 2,000,000.00 1.49 - - - - - - - -

2 SMK3 1.00 Ls 1,125,000.00 1,125,000.00 0.84 - - - - - - - -


Sub Jumlah 3,125,000.00 2.33 - - - -

II. PEKERJAAN INTERIOR RUANG KEPALA DINAS

1 Drop Ceiling HPL 16.00 M2 800,000.00 12,800,000.00 9.56 - - - - - - - - -

2 Perbaikan dan pemasangan plafond gypsum bertingkat + cat - - - - - - - - -


1. Bongkar Plafond Lama 102.00 M2 10,000.00 1,020,000.00 0.76 -
2. Pasang Rangka furing 60x120 cm 102.00 M2 140,000.00 14,280,000.00 10.66 -
3. Pemasangan Panel gypsum 102.00 M2 91,861.00 9,369,822.00 7.00 -
4. Pengecatan 102.00 M2 23,552.58 2,402,363.16 1.79 -
3 Pantry + Kabinet Ekstensi Lemari Existing 1.00 Unit 12,500,000.00 12,500,000.00 9.33 -

4 Coffe Maker 1.00 Unit 13,000,000.00 13,000,000.00 9.71 -


5 Wallpaper ex. Zinniz/setara 80.00 M2 148,995.00 11,919,600.00 8.90 -

6 lighting + instalasi 1.00 Ls 10,000,000.00 10,000,000.00 7.47 -


7 Lapis dinding Plywood+HPL area box panel (foyer tangga) 10.00 M2 800,000.00 8,000,000.00 5.97 -

Pemasangan Shading plywood + HPL di jendela tangga (sesuai


8 1.00 M2 4,000,000.00 4,000,000.00 2.99 -
gambar)

9 Logo PANCACITA dari PVC + acrilic 80x80 cm 1.00 Unit 4,000,000.00 4,000,000.00 2.99 -

Cat Ulang pintu-pintu, kusen, plafond ruang sekretaris,


10 perbaikan furnitur dan pemasangan stiker sandblast kaca 1.00 Ls 6,000,000.00 6,000,000.00 4.48 -
jendela

11 Pajangan Lambang Garuda Pancasila 1.00 Unit 2,000,000.00 2,000,000.00 1.49 -


12 TV Cabinet + TV Backdrop ukiran 1.00 Unit 4,000,000.00 4,000,000.00 2.99 -

13 Blinds/gorden 32.50 M2 200,000.00 6,500,000.00 4.85 -


14 Tempat Tidur + lemari bedhead 1.00 Unit 8,000,000.00 8,000,000.00 5.97 -

Sub Jumlah 129,791,785.16 96.92 - - - -


III. FINISHING

1 Pembersihan akhir 1.00 Taksir 1,000,000.00 1,000,000.00 0.75 - - - 1.00 1,000,000.00 100.00 1.00 1,000,000.00 100.00 0.75

Sub Jumlah 1,000,000.00 0.75 - 1,000,000.00 1,000,000.00 0.75

JUMLAH HARGA DAN BOBOT 133,916,785.16 100.00 #VALUE! #VALUE! #VALUE! #VALUE!
PPN 10% 13,391,678.52 #VALUE! #VALUE! #VALUE!
TOTAL KESELURUHAN 147,308,463.68 #VALUE! #VALUE! #VALUE!

DIBULATKAN 147,308,000.00 #VALUE! #VALUE! #VALUE!

Pidie, 26 Agustus 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. GUNTOMARA

T. EPI ISWARI, ST YUSWADI, ST SAID HUSAIN


Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur
PEMERINTAH ACEH

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN LAPORAN


Jl. Pemancar No.5 Simpang Tiga Telp. (0651) 42882 Fax. (0651) 41130 B. Aceh PELAKSANAAN PEKERJAAN BULANAN

PEKERJAAN : REHABILITASI RUANG KERJA KEPALA DINAS


LOKASI : BANDA ACEH KONTRAKTOR PELAKSANA : CV. DITOZ
NO. KONTRAK : 602.I/001/SEK-PL.02/PERKIM/APBA/2019 BULAN : III
TGL. KONTRAK : 24 SEPTEMBER 2019 PERIODE : 23 NOPEMBER S.D 22 DESEMBER 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI 100.00 %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN

1 Pengukuran 1.00 Ls 2,000,000.00 2,000,000.00 1.49 1.00 2,000,000.00 100.00 - - - 1.00 2,000,000.00 100.00 1.49

2 SMK3 1.00 Ls 1,125,000.00 1,125,000.00 0.84 - - 20.00 - 80.00 - - 100.00 0.84

Sub Jumlah 3,125,000.00 2.33 2,000,000.00 - 2,000,000.00 2.33

II. PEKERJAAN INTERIOR RUANG KEPALA DINAS

1 Drop Ceiling HPL 16.00 M2 800,000.00 12,800,000.00 9.56 6.40 5,120,000.00 40.00 9.60 7,680,000.00 60.00 16.00 12,800,000.00 100.00 9.56

2 Perbaikan dan pemasangan plafond gypsum bertingkat + cat

1. Bongkar Plafond Lama 102.00 M2 10,000.00 1,020,000.00 0.76 40.80 408,000.00 40.00 61.20 612,000.00 60.00 102.00 1,020,000.00 100.00 0.76

2. Pasang Rangka furing 60x120 cm 102.00 M2 140,000.00 14,280,000.00 10.66 40.80 5,712,000.00 40.00 61.20 8,568,000.00 60.00 102.00 14,280,000.00 100.00 10.66

3. Pemasangan Panel gypsum 102.00 M2 91,861.00 9,369,822.00 7.00 40.80 3,747,928.80 40.00 61.20 5,621,893.20 60.00 102.00 9,369,822.00 100.00 7.00

4. Pengecatan 102.00 M2 23,552.58 2,402,363.16 1.79 20.40 480,472.63 20.00 81.60 1,921,890.53 80.00 102.00 2,402,363.16 100.00 1.79

3 Pantry + Kabinet Ekstensi Lemari Existing 1.00 Unit 12,500,000.00 12,500,000.00 9.33 0.20 2,500,000.00 20.00 0.80 10,000,000.00 80.00 1.00 12,500,000.00 100.00 9.33

4 Coffe Maker 1.00 Unit 13,000,000.00 13,000,000.00 9.71 0.20 2,600,000.00 20.00 0.80 10,400,000.00 80.00 1.00 13,000,000.00 100.00 9.71

5 Wallpaper ex. Zinniz/setara 80.00 M2 148,995.00 11,919,600.00 8.90 16.00 2,383,920.00 20.00 64.00 9,535,680.00 80.00 80.00 11,919,600.00 100.00 8.90

6 lighting + instalasi 1.00 Ls 10,000,000.00 10,000,000.00 7.47 0.10 1,000,000.00 10.00 0.90 9,000,000.00 90.00 1.00 10,000,000.00 100.00 7.47

7 Lapis dinding Plywood+HPL area box panel (foyer tangga) 10.00 M2 800,000.00 8,000,000.00 5.97 1.00 800,000.00 10.00 9.00 7,200,000.00 90.00 10.00 8,000,000.00 100.00 5.97

Pemasangan Shading plywood + HPL di jendela tangga (sesuai


8 1.00 M2 4,000,000.00 4,000,000.00 2.99 0.10 400,000.00 10.00 0.90 3,600,000.00 90.00 1.00 4,000,000.00 100.00 2.99
gambar)

9 Logo PANCACITA dari PVC + acrilic 80x80 cm 1.00 Unit 4,000,000.00 4,000,000.00 2.99 0.10 400,000.00 10.00 0.90 3,600,000.00 90.00 1.00 4,000,000.00 100.00 2.99

Cat Ulang pintu-pintu, kusen, plafond ruang sekretaris, perbaikan


10 1.00 Ls 6,000,000.00 6,000,000.00 4.48 0.10 600,000.00 10.00 0.90 5,400,000.00 90.00 1.00 6,000,000.00 100.00 4.48
furnitur dan pemasangan stiker sandblast kaca jendela

11 Pajangan Lambang Garuda Pancasila 1.00 Unit 2,000,000.00 2,000,000.00 1.49 - - - 1.00 2,000,000.00 100.00 1.00 2,000,000.00 100.00 1.49
NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

12 TV Cabinet + TV Backdrop ukiran 1.00 Unit 4,000,000.00 4,000,000.00 2.99 - - - 1.00 4,000,000.00 100.00 1.00 4,000,000.00 100.00 2.99

13 Blinds/gorden 32.50 M2 200,000.00 6,500,000.00 4.85 - - - 32.50 6,500,000.00 100.00 32.50 6,500,000.00 100.00 4.85

14 Tempat Tidur + lemari bedhead 1.00 Unit 8,000,000.00 8,000,000.00 5.97 - - - 1.00 8,000,000.00 100.00 1.00 8,000,000.00 100.00 5.97

Sub Jumlah 129,791,785.16 96.92 26,152,321.43 103,639,463.73 129,791,785.16 96.92

III. FINISHING

1 Pembersihan akhir 1.00 Taksir 1,000,000.00 1,000,000.00 0.75 - - - 1.00 1,000,000.00 100.00 1.00 1,000,000.00 100.00 0.75

Sub Jumlah 1,000,000.00 0.75 - 1,000,000.00 1,000,000.00 0.75

JUMLAH HARGA DAN BOBOT 133,916,785.16 100.00 28,152,321.43 104,639,463.73 132,791,785.16 100.00

PPN 10% 13,391,678.52 2,815,232.14 10,463,946.37 13,279,178.52

TOTAL KESELURUHAN 147,308,463.68 30,967,553.58 115,103,410.10 146,070,963.68

DIBULATKAN 147,308,000.00 30,967,000.00 115,103,000.00 146,070,000.00

Banda Aceh, 10 Desember 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. DITOZ

T. EPI ISWARI, ST YUSWADI, ST HARDIANTO ZAINAL


Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur
PEMERINTAH ACEH

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN LAPORAN


Jl. Pemancar No.5 Simpang Tiga Telp. (0651) 42882 Fax. (0651) 41130 B. Aceh PELAKSANAAN PEKERJAAN MINGGUAN

PEKERJAAN : REHABILITASI RUANG KERJA KEPALA DINAS


LOKASI : BANDA ACEH KONTRAKTOR PELAKSANA : CV. DITOZ
NO. KONTRAK : 602.I/001/SEK-PL.02/PERKIM/APBA/2019 MINGGU : 12
TGL. KONTRAK : 24 SEPTEMBER 2019 PERIODE : 16 S.D 22 DESEMBER 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI 100.00 %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN

1 Pengukuran 1.00 Ls 2,000,000.00 2,000,000.00 1.49 1.00 2,000,000.00 100.00 - - - 1.00 2,000,000.00 100.00 1.49

2 SMK3 1.00 Ls 1,125,000.00 1,125,000.00 0.84 - - 95.00 - 5.00 - - 100.00 0.84

Sub Jumlah 3,125,000.00 2.33 2,000,000.00 - 2,000,000.00 2.33

II. PEKERJAAN INTERIOR RUANG KEPALA DINAS

1 Drop Ceiling HPL 16.00 M2 800,000.00 12,800,000.00 9.56 16.00 12,800,000.00 100.00 - - - 16.00 12,800,000.00 100.00 9.56

2 Perbaikan dan pemasangan plafond gypsum bertingkat + cat

1. Bongkar Plafond Lama 102.00 M2 10,000.00 1,020,000.00 0.76 102.00 1,020,000.00 100.00 - - - 102.00 1,020,000.00 100.00 0.76

2. Pasang Rangka furing 60x120 cm 102.00 M2 140,000.00 14,280,000.00 10.66 102.00 14,280,000.00 100.00 - - - 102.00 14,280,000.00 100.00 10.66

3. Pemasangan Panel gypsum 102.00 M2 91,861.00 9,369,822.00 7.00 102.00 9,369,822.00 100.00 - - - 102.00 9,369,822.00 100.00 7.00

4. Pengecatan 102.00 M2 23,552.58 2,402,363.16 1.79 102.00 2,402,363.16 100.00 - - - 102.00 2,402,363.16 100.00 1.79

3 Pantry + Kabinet Ekstensi Lemari Existing 1.00 Unit 12,500,000.00 12,500,000.00 9.33 1.00 12,500,000.00 100.00 - - - 1.00 12,500,000.00 100.00 9.33

4 Coffe Maker 1.00 Unit 13,000,000.00 13,000,000.00 9.71 1.00 13,000,000.00 100.00 - - - 1.00 13,000,000.00 100.00 9.71

5 Wallpaper ex. Zinniz/setara 80.00 M2 148,995.00 11,919,600.00 8.90 80.00 11,919,600.00 100.00 - - - 80.00 11,919,600.00 100.00 8.90

6 lighting + instalasi 1.00 Ls 10,000,000.00 10,000,000.00 7.47 1.00 10,000,000.00 100.00 - - - 1.00 10,000,000.00 100.00 7.47

7 Lapis dinding Plywood+HPL area box panel (foyer tangga) 10.00 M2 800,000.00 8,000,000.00 5.97 10.00 8,000,000.00 100.00 - - - 10.00 8,000,000.00 100.00 5.97

Pemasangan Shading plywood + HPL di jendela tangga (sesuai


8 1.00 M2 4,000,000.00 4,000,000.00 2.99 1.00 4,000,000.00 100.00 - - - 1.00 4,000,000.00 100.00 2.99
gambar)

9 Logo PANCACITA dari PVC + acrilic 80x80 cm 1.00 Unit 4,000,000.00 4,000,000.00 2.99 1.00 4,000,000.00 100.00 - - - 1.00 4,000,000.00 100.00 2.99

Cat Ulang pintu-pintu, kusen, plafond ruang sekretaris, perbaikan


10 1.00 Ls 6,000,000.00 6,000,000.00 4.48 1.00 6,000,000.00 100.00 - - - 1.00 6,000,000.00 100.00 4.48
furnitur dan pemasangan stiker sandblast kaca jendela

11 Pajangan Lambang Garuda Pancasila 1.00 Unit 2,000,000.00 2,000,000.00 1.49 0.80 1,600,000.00 80.00 0.20 400,000.00 20.00 1.00 2,000,000.00 100.00 1.49
NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

12 TV Cabinet + TV Backdrop ukiran 1.00 Unit 4,000,000.00 4,000,000.00 2.99 0.80 3,200,000.00 80.00 0.20 800,000.00 20.00 1.00 4,000,000.00 100.00 2.99

13 Blinds/gorden 32.50 M2 200,000.00 6,500,000.00 4.85 26.00 5,200,000.00 80.00 6.50 1,300,000.00 20.00 32.50 6,500,000.00 100.00 4.85

14 Tempat Tidur + lemari bedhead 1.00 Unit 8,000,000.00 8,000,000.00 5.97 0.80 6,400,000.00 80.00 0.20 1,600,000.00 20.00 1.00 8,000,000.00 100.00 5.97

Sub Jumlah 129,791,785.16 96.92 125,691,785.16 4,100,000.00 129,791,785.16 96.92

III. FINISHING

1 Pembersihan akhir 1.00 Taksir 1,000,000.00 1,000,000.00 0.75 - - - 1.00 1,000,000.00 100.00 1.00 1,000,000.00 100.00 0.75

Sub Jumlah 1,000,000.00 0.75 - 1,000,000.00 1,000,000.00 0.75

JUMLAH HARGA DAN BOBOT 133,916,785.16 100.00 127,691,785.16 5,100,000.00 132,791,785.16 100.00

PPN 10% 13,391,678.52 12,769,178.52 510,000.00 13,279,178.52

TOTAL KESELURUHAN 147,308,463.68 140,460,963.68 5,610,000.00 146,070,963.68

DIBULATKAN 147,308,000.00 140,460,000.00 5,610,000.00 146,070,000.00

Banda Aceh, 10 Desember 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. DITOZ

T. EPI ISWARI, ST YUSWADI, ST HARDIANTO ZAINAL


Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur
PEMERINTAH ACEH

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN LAPORAN


Jl. Pemancar No.5 Simpang Tiga Telp. (0651) 42882 Fax. (0651) 41130 B. Aceh PELAKSANAAN PEKERJAAN MINGGUAN

PEKERJAAN : REHABILITASI RUANG KERJA KEPALA DINAS


LOKASI : BANDA ACEH KONTRAKTOR PELAKSANA : CV. DITOZ
NO. KONTRAK : 602.I/001/SEK-PL.02/PERKIM/APBA/2019 MINGGU : 11
TGL. KONTRAK : 24 SEPTEMBER 2019 PERIODE : 08 S.D 15 DESEMBER 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI 99.21 %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN

1 Pengukuran 1.00 Ls 2,000,000.00 2,000,000.00 1.49 1.00 2,000,000.00 100.00 - - - 1.00 2,000,000.00 100.00 1.49

2 SMK3 1.00 Ls 1,125,000.00 1,125,000.00 0.84 - - 95.00 - - - - 95.00 0.80

Sub Jumlah 3,125,000.00 2.33 2,000,000.00 - 2,000,000.00 2.29

II. PEKERJAAN INTERIOR RUANG KEPALA DINAS

1 Drop Ceiling HPL 16.00 M2 800,000.00 12,800,000.00 9.56 16.00 12,800,000.00 100.00 - - - 16.00 12,800,000.00 100.00 9.56

2 Perbaikan dan pemasangan plafond gypsum bertingkat + cat

1. Bongkar Plafond Lama 102.00 M2 10,000.00 1,020,000.00 0.76 102.00 1,020,000.00 100.00 - - - 102.00 1,020,000.00 100.00 0.76

2. Pasang Rangka furing 60x120 cm 102.00 M2 140,000.00 14,280,000.00 10.66 102.00 14,280,000.00 100.00 - - - 102.00 14,280,000.00 100.00 10.66

3. Pemasangan Panel gypsum 102.00 M2 91,861.00 9,369,822.00 7.00 102.00 9,369,822.00 100.00 - - - 102.00 9,369,822.00 100.00 7.00

4. Pengecatan 102.00 M2 23,552.58 2,402,363.16 1.79 102.00 2,402,363.16 100.00 - - - 102.00 2,402,363.16 100.00 1.79

3 Pantry + Kabinet Ekstensi Lemari Existing 1.00 Unit 12,500,000.00 12,500,000.00 9.33 1.00 12,500,000.00 100.00 - - - 1.00 12,500,000.00 100.00 9.33

4 Coffe Maker 1.00 Unit 13,000,000.00 13,000,000.00 9.71 1.00 13,000,000.00 100.00 - - - 1.00 13,000,000.00 100.00 9.71

5 Wallpaper ex. Zinniz/setara 80.00 M2 148,995.00 11,919,600.00 8.90 80.00 11,919,600.00 100.00 - - - 80.00 11,919,600.00 100.00 8.90

6 lighting + instalasi 1.00 Ls 10,000,000.00 10,000,000.00 7.47 1.00 10,000,000.00 100.00 - - - 1.00 10,000,000.00 100.00 7.47

7 Lapis dinding Plywood+HPL area box panel (foyer tangga) 10.00 M2 800,000.00 8,000,000.00 5.97 10.00 8,000,000.00 100.00 - - - 10.00 8,000,000.00 100.00 5.97

Pemasangan Shading plywood + HPL di jendela tangga (sesuai


8 1.00 M2 4,000,000.00 4,000,000.00 2.99 1.00 4,000,000.00 100.00 - - - 1.00 4,000,000.00 100.00 2.99
gambar)

9 Logo PANCACITA dari PVC + acrilic 80x80 cm 1.00 Unit 4,000,000.00 4,000,000.00 2.99 1.00 4,000,000.00 100.00 - - - 1.00 4,000,000.00 100.00 2.99

Cat Ulang pintu-pintu, kusen, plafond ruang sekretaris, perbaikan


10 1.00 Ls 6,000,000.00 6,000,000.00 4.48 1.00 6,000,000.00 100.00 - - - 1.00 6,000,000.00 100.00 4.48
furnitur dan pemasangan stiker sandblast kaca jendela

11 Pajangan Lambang Garuda Pancasila 1.00 Unit 2,000,000.00 2,000,000.00 1.49 0.80 1,600,000.00 80.00 0.20 400,000.00 20.00 1.00 2,000,000.00 100.00 1.49
NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

12 TV Cabinet + TV Backdrop ukiran 1.00 Unit 4,000,000.00 4,000,000.00 2.99 0.80 3,200,000.00 80.00 0.20 800,000.00 20.00 1.00 4,000,000.00 100.00 2.99

13 Blinds/gorden 32.50 M2 200,000.00 6,500,000.00 4.85 26.00 5,200,000.00 80.00 6.50 1,300,000.00 20.00 32.50 6,500,000.00 100.00 4.85

14 Tempat Tidur + lemari bedhead 1.00 Unit 8,000,000.00 8,000,000.00 5.97 0.80 6,400,000.00 80.00 0.20 1,600,000.00 20.00 1.00 8,000,000.00 100.00 5.97

Sub Jumlah 129,791,785.16 96.92 125,691,785.16 4,100,000.00 129,791,785.16 96.92

III. FINISHING

1 Pembersihan akhir 1.00 Taksir 1,000,000.00 1,000,000.00 0.75 - - - - - - - - - -

Sub Jumlah 1,000,000.00 0.75 - - - -

JUMLAH HARGA DAN BOBOT 133,916,785.16 100.00 127,691,785.16 4,100,000.00 131,791,785.16 99.21

PPN 10% 13,391,678.52 12,769,178.52 410,000.00 13,179,178.52

TOTAL KESELURUHAN 147,308,463.68 140,460,963.68 4,510,000.00 144,970,963.68

DIBULATKAN 147,308,000.00 140,460,000.00 4,510,000.00 144,970,000.00

Banda Aceh, 15 Desember 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. DITOZ

T. EPI ISWARI, ST YUSWADI, ST HARDIANTO ZAINAL


Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur
PEMERINTAH ACEH

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN LAPORAN


Jl. Pemancar No.5 Simpang Tiga Telp. (0651) 42882 Fax. (0651) 41130 B. Aceh PELAKSANAAN PEKERJAAN MINGGUAN

PEKERJAAN : REHABILITASI RUANG KERJA KEPALA DINAS


LOKASI : BANDA ACEH KONTRAKTOR PELAKSANA : CV. DITOZ
NO. KONTRAK : 602.I/001/SEK-PL.02/PERKIM/APBA/2019 MINGGU : 10
TGL. KONTRAK : 24 SEPTEMBER 2019 PERIODE : 30 NOPEMBER S.D 07 DESEMBER 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI 96.15 %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN

1 Pengukuran 1.00 Ls 2,000,000.00 2,000,000.00 1.49 1.00 2,000,000.00 100.00 - - - 1.00 2,000,000.00 100.00 1.49

2 SMK3 1.00 Ls 1,125,000.00 1,125,000.00 0.84 - - 75.00 - 20.00 - - 95.00 0.80

Sub Jumlah 3,125,000.00 2.33 2,000,000.00 - 2,000,000.00 2.29

II. PEKERJAAN INTERIOR RUANG KEPALA DINAS

1 Drop Ceiling HPL 16.00 M2 800,000.00 12,800,000.00 9.56 16.00 12,800,000.00 100.00 - - - 16.00 12,800,000.00 100.00 9.56

2 Perbaikan dan pemasangan plafond gypsum bertingkat + cat

1. Bongkar Plafond Lama 102.00 M2 10,000.00 1,020,000.00 0.76 102.00 1,020,000.00 100.00 - - - 102.00 1,020,000.00 100.00 0.76

2. Pasang Rangka furing 60x120 cm 102.00 M2 140,000.00 14,280,000.00 10.66 102.00 14,280,000.00 100.00 - - - 102.00 14,280,000.00 100.00 10.66

3. Pemasangan Panel gypsum 102.00 M2 91,861.00 9,369,822.00 7.00 102.00 9,369,822.00 100.00 - - - 102.00 9,369,822.00 100.00 7.00

4. Pengecatan 102.00 M2 23,552.58 2,402,363.16 1.79 102.00 2,402,363.16 100.00 - - - 102.00 2,402,363.16 100.00 1.79

3 Pantry + Kabinet Ekstensi Lemari Existing 1.00 Unit 12,500,000.00 12,500,000.00 9.33 1.00 12,500,000.00 100.00 - - - 1.00 12,500,000.00 100.00 9.33

4 Coffe Maker 1.00 Unit 13,000,000.00 13,000,000.00 9.71 1.00 13,000,000.00 100.00 - - - 1.00 13,000,000.00 100.00 9.71

5 Wallpaper ex. Zinniz/setara 80.00 M2 148,995.00 11,919,600.00 8.90 80.00 11,919,600.00 100.00 - - - 80.00 11,919,600.00 100.00 8.90

6 lighting + instalasi 1.00 Ls 10,000,000.00 10,000,000.00 7.47 0.70 7,000,000.00 70.00 0.30 3,000,000.00 30.00 1.00 10,000,000.00 100.00 7.47

7 Lapis dinding Plywood+HPL area box panel (foyer tangga) 10.00 M2 800,000.00 8,000,000.00 5.97 7.00 5,600,000.00 70.00 3.00 2,400,000.00 30.00 10.00 8,000,000.00 100.00 5.97

Pemasangan Shading plywood + HPL di jendela tangga (sesuai


8 1.00 M2 4,000,000.00 4,000,000.00 2.99 0.70 2,800,000.00 70.00 0.30 1,200,000.00 30.00 1.00 4,000,000.00 100.00 2.99
gambar)

9 Logo PANCACITA dari PVC + acrilic 80x80 cm 1.00 Unit 4,000,000.00 4,000,000.00 2.99 0.70 2,800,000.00 70.00 0.30 1,200,000.00 30.00 1.00 4,000,000.00 100.00 2.99

Cat Ulang pintu-pintu, kusen, plafond ruang sekretaris, perbaikan


10 1.00 Ls 6,000,000.00 6,000,000.00 4.48 0.70 4,200,000.00 70.00 0.30 1,800,000.00 30.00 1.00 6,000,000.00 100.00 4.48
furnitur dan pemasangan stiker sandblast kaca jendela

11 Pajangan Lambang Garuda Pancasila 1.00 Unit 2,000,000.00 2,000,000.00 1.49 0.60 1,200,000.00 60.00 0.20 400,000.00 20.00 0.80 1,600,000.00 80.00 1.19
NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

12 TV Cabinet + TV Backdrop ukiran 1.00 Unit 4,000,000.00 4,000,000.00 2.99 0.60 2,400,000.00 60.00 0.20 800,000.00 20.00 0.80 3,200,000.00 80.00 2.39

13 Blinds/gorden 32.50 M2 200,000.00 6,500,000.00 4.85 19.50 3,900,000.00 60.00 6.50 1,300,000.00 20.00 26.00 5,200,000.00 80.00 3.88

14 Tempat Tidur + lemari bedhead 1.00 Unit 8,000,000.00 8,000,000.00 5.97 0.60 4,800,000.00 60.00 0.20 1,600,000.00 20.00 0.80 6,400,000.00 80.00 4.78

Sub Jumlah 129,791,785.16 96.92 111,991,785.16 13,700,000.00 125,691,785.16 93.86

III. FINISHING

1 Pembersihan akhir 1.00 Taksir 1,000,000.00 1,000,000.00 0.75 - - - - - - - - - -

Sub Jumlah 1,000,000.00 0.75 - - - -

JUMLAH HARGA DAN BOBOT 133,916,785.16 100.00 113,991,785.16 13,700,000.00 127,691,785.16 96.15

PPN 10% 13,391,678.52 11,399,178.52 1,370,000.00 12,769,178.52

TOTAL KESELURUHAN 147,308,463.68 125,390,963.68 15,070,000.00 140,460,963.68

DIBULATKAN 147,308,000.00 125,390,000.00 15,070,000.00 140,460,000.00

Banda Aceh, 07 Desember 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. DITOZ

T. EPI ISWARI, ST YUSWADI, ST HARDIANTO ZAINAL


Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur
PEMERINTAH ACEH

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN LAPORAN


Jl. Pemancar No.5 Simpang Tiga Telp. (0651) 42882 Fax. (0651) 41130 B. Aceh PELAKSANAAN PEKERJAAN MINGGUAN

PEKERJAAN : REHABILITASI RUANG KERJA KEPALA DINAS


LOKASI : BANDA ACEH KONTRAKTOR PELAKSANA : CV. DITOZ
NO. KONTRAK : 602.I/001/SEK-PL.02/PERKIM/APBA/2019 MINGGU :9
TGL. KONTRAK : 24 SEPTEMBER 2019 PERIODE : 23 S.D 29 NOPEMBER 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI 85.75 %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN

1 Pengukuran 1.00 Ls 2,000,000.00 2,000,000.00 1.49 1.00 2,000,000.00 100.00 - - - 1.00 2,000,000.00 100.00 1.49

2 SMK3 1.00 Ls 1,125,000.00 1,125,000.00 0.84 - - 70.00 - 5.00 - - 75.00 0.63

Sub Jumlah 3,125,000.00 2.33 2,000,000.00 - 2,000,000.00 2.12

II. PEKERJAAN INTERIOR RUANG KEPALA DINAS

1 Drop Ceiling HPL 16.00 M2 800,000.00 12,800,000.00 9.56 16.00 12,800,000.00 100.00 - - - 16.00 12,800,000.00 100.00 9.56

2 Perbaikan dan pemasangan plafond gypsum bertingkat + cat

1. Bongkar Plafond Lama 102.00 M2 10,000.00 1,020,000.00 0.76 102.00 1,020,000.00 100.00 - - - 102.00 1,020,000.00 100.00 0.76

2. Pasang Rangka furing 60x120 cm 102.00 M2 140,000.00 14,280,000.00 10.66 102.00 14,280,000.00 100.00 - - - 102.00 14,280,000.00 100.00 10.66

3. Pemasangan Panel gypsum 102.00 M2 91,861.00 9,369,822.00 7.00 102.00 9,369,822.00 100.00 - - - 102.00 9,369,822.00 100.00 7.00

4. Pengecatan 102.00 M2 23,552.58 2,402,363.16 1.79 81.60 1,921,890.53 80.00 20.40 480,472.63 20.00 102.00 2,402,363.16 100.00 1.79

3 Pantry + Kabinet Ekstensi Lemari Existing 1.00 Unit 12,500,000.00 12,500,000.00 9.33 0.80 10,000,000.00 80.00 0.20 2,500,000.00 20.00 1.00 12,500,000.00 100.00 9.33

4 Coffe Maker 1.00 Unit 13,000,000.00 13,000,000.00 9.71 0.80 10,400,000.00 80.00 0.20 2,600,000.00 20.00 1.00 13,000,000.00 100.00 9.71

5 Wallpaper ex. Zinniz/setara 80.00 M2 148,995.00 11,919,600.00 8.90 64.00 9,535,680.00 80.00 16.00 2,383,920.00 20.00 80.00 11,919,600.00 100.00 8.90

6 lighting + instalasi 1.00 Ls 10,000,000.00 10,000,000.00 7.47 0.70 7,000,000.00 70.00 - - - 0.70 7,000,000.00 70.00 5.23

7 Lapis dinding Plywood+HPL area box panel (foyer tangga) 10.00 M2 800,000.00 8,000,000.00 5.97 7.00 5,600,000.00 70.00 - - - 7.00 5,600,000.00 70.00 4.18

Pemasangan Shading plywood + HPL di jendela tangga (sesuai


8 1.00 M2 4,000,000.00 4,000,000.00 2.99 0.70 2,800,000.00 70.00 - - - 0.70 2,800,000.00 70.00 2.09
gambar)

9 Logo PANCACITA dari PVC + acrilic 80x80 cm 1.00 Unit 4,000,000.00 4,000,000.00 2.99 0.70 2,800,000.00 70.00 - - - 0.70 2,800,000.00 70.00 2.09

Cat Ulang pintu-pintu, kusen, plafond ruang sekretaris, perbaikan


10 1.00 Ls 6,000,000.00 6,000,000.00 4.48 0.70 4,200,000.00 70.00 - - - 0.70 4,200,000.00 70.00 3.14
furnitur dan pemasangan stiker sandblast kaca jendela

11 Pajangan Lambang Garuda Pancasila 1.00 Unit 2,000,000.00 2,000,000.00 1.49 0.60 1,200,000.00 60.00 - - - 0.60 1,200,000.00 60.00 0.90
NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

12 TV Cabinet + TV Backdrop ukiran 1.00 Unit 4,000,000.00 4,000,000.00 2.99 0.60 2,400,000.00 60.00 - - - 0.60 2,400,000.00 60.00 1.79

13 Blinds/gorden 32.50 M2 200,000.00 6,500,000.00 4.85 19.50 3,900,000.00 60.00 - - - 19.50 3,900,000.00 60.00 2.91

14 Tempat Tidur + lemari bedhead 1.00 Unit 8,000,000.00 8,000,000.00 5.97 0.60 4,800,000.00 60.00 - - - 0.60 4,800,000.00 60.00 3.58

Sub Jumlah 129,791,785.16 96.92 104,027,392.53 7,964,392.63 111,991,785.16 83.63

III. FINISHING

1 Pembersihan akhir 1.00 Taksir 1,000,000.00 1,000,000.00 0.75 - - - - - - - - - -

Sub Jumlah 1,000,000.00 0.75 - - - -

JUMLAH HARGA DAN BOBOT 133,916,785.16 100.00 106,027,392.53 7,964,392.63 113,991,785.16 85.75

PPN 10% 13,391,678.52 10,602,739.25 796,439.26 11,399,178.52

TOTAL KESELURUHAN 147,308,463.68 116,630,131.78 8,760,831.90 125,390,963.68

DIBULATKAN 147,308,000.00 116,630,000.00 8,760,000.00 125,390,000.00

Banda Aceh, 29 Nopember 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. DITOZ

T. EPI ISWARI, ST YUSWADI, ST HARDIANTO ZAINAL


Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur
PEMERINTAH ACEH

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN LAPORAN


Jl. Pemancar No.5 Simpang Tiga Telp. (0651) 42882 Fax. (0651) 41130 B. Aceh PELAKSANAAN PEKERJAAN BULANAN

PEKERJAAN : REHABILITASI RUANG KERJA KEPALA DINAS


LOKASI : BANDA ACEH KONTRAKTOR PELAKSANA : CV. DITOZ
NO. KONTRAK : 602.I/001/SEK-PL.02/PERKIM/APBA/2019 BULAN : II
TGL. KONTRAK : 24 SEPTEMBER 2019 PERIODE : 22 OKTOBER S.D 22 NOPEMBER 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI 79.76 %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN
1 Pengukuran 1.00 Ls 2,000,000.00 2,000,000.00 1.49 1.00 2,000,000.00 100.00 - - - 1.00 2,000,000.00 100.00 1.49

2 SMK3 1.00 Ls 1,125,000.00 1,125,000.00 0.84 - - 20.00 - 50.00 - - 70.00 0.59


Sub Jumlah 3,125,000.00 2.33 2,000,000.00 - 2,000,000.00 2.08

II. PEKERJAAN INTERIOR RUANG KEPALA DINAS

1 Drop Ceiling HPL 16.00 M2 800,000.00 12,800,000.00 9.56 6.40 5,120,000.00 40.00 9.60 7,680,000.00 60.00 16.00 12,800,000.00 100.00 9.56

2 Perbaikan dan pemasangan plafond gypsum bertingkat + cat


1. Bongkar Plafond Lama 102.00 M2 10,000.00 1,020,000.00 0.76 40.80 408,000.00 40.00 61.20 612,000.00 60.00 102.00 1,020,000.00 100.00 0.76
2. Pasang Rangka furing 60x120 cm 102.00 M2 140,000.00 14,280,000.00 10.66 40.80 5,712,000.00 40.00 61.20 8,568,000.00 60.00 102.00 14,280,000.00 100.00 10.66
3. Pemasangan Panel gypsum 102.00 M2 91,861.00 9,369,822.00 7.00 40.80 3,747,928.80 40.00 61.20 5,621,893.20 60.00 102.00 9,369,822.00 100.00 7.00
4. Pengecatan 102.00 M2 23,552.58 2,402,363.16 1.79 20.40 480,472.63 20.00 61.20 1,441,417.90 60.00 81.60 1,921,890.53 80.00 1.44
3 Pantry + Kabinet Ekstensi Lemari Existing 1.00 Unit 12,500,000.00 12,500,000.00 9.33 0.20 2,500,000.00 20.00 0.60 7,500,000.00 60.00 0.80 10,000,000.00 80.00 7.47

4 Coffe Maker 1.00 Unit 13,000,000.00 13,000,000.00 9.71 0.20 2,600,000.00 20.00 0.60 7,800,000.00 60.00 0.80 10,400,000.00 80.00 7.77
5 Wallpaper ex. Zinniz/setara 80.00 M2 148,995.00 11,919,600.00 8.90 16.00 2,383,920.00 20.00 48.00 7,151,760.00 60.00 64.00 9,535,680.00 80.00 7.12

6 lighting + instalasi 1.00 Ls 10,000,000.00 10,000,000.00 7.47 0.10 1,000,000.00 10.00 0.60 6,000,000.00 60.00 0.70 7,000,000.00 70.00 5.23
7 Lapis dinding Plywood+HPL area box panel (foyer tangga) 10.00 M2 800,000.00 8,000,000.00 5.97 1.00 800,000.00 10.00 6.00 4,800,000.00 60.00 7.00 5,600,000.00 70.00 4.18

Pemasangan Shading plywood + HPL di jendela tangga (sesuai


8 1.00 M2 4,000,000.00 4,000,000.00 2.99 0.10 400,000.00 10.00 0.60 2,400,000.00 60.00 0.70 2,800,000.00 70.00 2.09
gambar)

9 Logo PANCACITA dari PVC + acrilic 80x80 cm 1.00 Unit 4,000,000.00 4,000,000.00 2.99 0.10 400,000.00 10.00 0.60 2,400,000.00 60.00 0.70 2,800,000.00 70.00 2.09

Cat Ulang pintu-pintu, kusen, plafond ruang sekretaris, perbaikan


10 1.00 Ls 6,000,000.00 6,000,000.00 4.48 0.10 600,000.00 10.00 0.60 3,600,000.00 60.00 0.70 4,200,000.00 70.00 3.14
furnitur dan pemasangan stiker sandblast kaca jendela

11 Pajangan Lambang Garuda Pancasila 1.00 Unit 2,000,000.00 2,000,000.00 1.49 - - - 0.60 1,200,000.00 60.00 0.60 1,200,000.00 60.00 0.90
12 TV Cabinet + TV Backdrop ukiran 1.00 Unit 4,000,000.00 4,000,000.00 2.99 - - - 0.60 2,400,000.00 60.00 0.60 2,400,000.00 60.00 1.79

13 Blinds/gorden 32.50 M2 200,000.00 6,500,000.00 4.85 - - - 19.50 3,900,000.00 60.00 19.50 3,900,000.00 60.00 2.91
14 Tempat Tidur + lemari bedhead 1.00 Unit 8,000,000.00 8,000,000.00 5.97 - - - 0.60 4,800,000.00 60.00 0.60 4,800,000.00 60.00 3.58

Sub Jumlah 129,791,785.16 96.92 26,152,321.43 77,875,071.10 104,027,392.53 77.68


III. FINISHING

1 Pembersihan akhir 1.00 Taksir 1,000,000.00 1,000,000.00 0.75 - - - - - - - - - -

Sub Jumlah 1,000,000.00 0.75 - - - -

JUMLAH HARGA DAN BOBOT 133,916,785.16 100.00 28,152,321.43 77,875,071.10 106,027,392.53 79.76
PPN 10% 13,391,678.52 2,815,232.14 7,787,507.11 10,602,739.25
TOTAL KESELURUHAN 147,308,463.68 30,967,553.58 85,662,578.21 116,630,131.78

DIBULATKAN 147,308,000.00 30,967,000.00 85,662,000.00 116,630,000.00

Banda Aceh, 22 Nopember 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. DITOZ

T. EPI ISWARI, ST YUSWADI, ST HARDIANTO ZAINAL


Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur
PEMERINTAH ACEH

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN LAPORAN


Jl. Pemancar No.5 Simpang Tiga Telp. (0651) 42882 Fax. (0651) 41130 B. Aceh PELAKSANAAN PEKERJAAN MINGGUAN

PEKERJAAN : REHABILITASI RUANG KERJA KEPALA DINAS


LOKASI : BANDA ACEH KONTRAKTOR PELAKSANA : CV. DITOZ
NO. KONTRAK : 602.I/001/SEK-PL.02/PERKIM/APBA/2019 MINGGU :8
TGL. KONTRAK : 24 SEPTEMBER 2019 PERIODE : 12 S.D 22 NOPEMBER 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI 79.76 %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN

1 Pengukuran 1.00 Ls 2,000,000.00 2,000,000.00 1.49 1.00 2,000,000.00 100.00 - - - 1.00 2,000,000.00 100.00 1.49

2 SMK3 1.00 Ls 1,125,000.00 1,125,000.00 0.84 - - 60.00 - 10.00 - - 70.00 0.59

Sub Jumlah 3,125,000.00 2.33 2,000,000.00 - 2,000,000.00 2.08

II. PEKERJAAN INTERIOR RUANG KEPALA DINAS

1 Drop Ceiling HPL 16.00 M2 800,000.00 12,800,000.00 9.56 12.80 10,240,000.00 80.00 3.20 2,560,000.00 20.00 16.00 12,800,000.00 100.00 9.56

2 Perbaikan dan pemasangan plafond gypsum bertingkat + cat -

1. Bongkar Plafond Lama 102.00 M2 10,000.00 1,020,000.00 0.76 81.60 816,000.00 80.00 20.40 204,000.00 20.00 102.00 1,020,000.00 100.00 0.76

2. Pasang Rangka furing 60x120 cm 102.00 M2 140,000.00 14,280,000.00 10.66 81.60 11,424,000.00 80.00 20.40 2,856,000.00 20.00 102.00 14,280,000.00 100.00 10.66

3. Pemasangan Panel gypsum 102.00 M2 91,861.00 9,369,822.00 7.00 81.60 7,495,857.60 80.00 20.40 1,873,964.40 20.00 102.00 9,369,822.00 100.00 7.00

4. Pengecatan 102.00 M2 23,552.58 2,402,363.16 1.79 61.20 1,441,417.90 60.00 20.40 480,472.63 20.00 81.60 1,921,890.53 80.00 1.44

3 Pantry + Kabinet Ekstensi Lemari Existing 1.00 Unit 12,500,000.00 12,500,000.00 9.33 0.60 7,500,000.00 60.00 0.20 2,500,000.00 20.00 0.80 10,000,000.00 80.00 7.47

4 Coffe Maker 1.00 Unit 13,000,000.00 13,000,000.00 9.71 0.60 7,800,000.00 60.00 0.20 2,600,000.00 20.00 0.80 10,400,000.00 80.00 7.77

5 Wallpaper ex. Zinniz/setara 80.00 M2 148,995.00 11,919,600.00 8.90 48.00 7,151,760.00 60.00 16.00 2,383,920.00 20.00 64.00 9,535,680.00 80.00 7.12

6 lighting + instalasi 1.00 Ls 10,000,000.00 10,000,000.00 7.47 0.50 5,000,000.00 50.00 0.20 2,000,000.00 20.00 0.70 7,000,000.00 70.00 5.23

7 Lapis dinding Plywood+HPL area box panel (foyer tangga) 10.00 M2 800,000.00 8,000,000.00 5.97 5.00 4,000,000.00 50.00 2.00 1,600,000.00 20.00 7.00 5,600,000.00 70.00 4.18

Pemasangan Shading plywood + HPL di jendela tangga (sesuai


8 1.00 M2 4,000,000.00 4,000,000.00 2.99 0.50 2,000,000.00 50.00 0.20 800,000.00 20.00 0.70 2,800,000.00 70.00 2.09
gambar)

9 Logo PANCACITA dari PVC + acrilic 80x80 cm 1.00 Unit 4,000,000.00 4,000,000.00 2.99 0.50 2,000,000.00 50.00 0.20 800,000.00 20.00 0.70 2,800,000.00 70.00 2.09

Cat Ulang pintu-pintu, kusen, plafond ruang sekretaris, perbaikan


10 1.00 Ls 6,000,000.00 6,000,000.00 4.48 0.50 3,000,000.00 50.00 0.20 1,200,000.00 20.00 0.70 4,200,000.00 70.00 3.14
furnitur dan pemasangan stiker sandblast kaca jendela

11 Pajangan Lambang Garuda Pancasila 1.00 Unit 2,000,000.00 2,000,000.00 1.49 0.40 800,000.00 40.00 0.20 400,000.00 20.00 0.60 1,200,000.00 60.00 0.90
NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

12 TV Cabinet + TV Backdrop ukiran 1.00 Unit 4,000,000.00 4,000,000.00 2.99 0.40 1,600,000.00 40.00 0.20 800,000.00 20.00 0.60 2,400,000.00 60.00 1.79

13 Blinds/gorden 32.50 M2 200,000.00 6,500,000.00 4.85 13.00 2,600,000.00 40.00 6.50 1,300,000.00 20.00 19.50 3,900,000.00 60.00 2.91

14 Tempat Tidur + lemari bedhead 1.00 Unit 8,000,000.00 8,000,000.00 5.97 0.40 3,200,000.00 40.00 0.20 1,600,000.00 20.00 0.60 4,800,000.00 60.00 3.58

Sub Jumlah 129,791,785.16 96.92 78,069,035.50 25,958,357.03 104,027,392.53 77.68

III. FINISHING

1 Pembersihan akhir 1.00 Taksir 1,000,000.00 1,000,000.00 0.75 - - - - - - - - - -

Sub Jumlah 1,000,000.00 0.75 - - - -

JUMLAH HARGA DAN BOBOT 133,916,785.16 100.00 80,069,035.50 25,958,357.03 106,027,392.53 79.76

PPN 10% 13,391,678.52 8,006,903.55 2,595,835.70 10,602,739.25

TOTAL KESELURUHAN 147,308,463.68 88,075,939.05 28,554,192.74 116,630,131.78

DIBULATKAN 147,308,000.00 88,075,000.00 28,554,000.00 116,630,000.00

Banda Aceh, 22 Nopember 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. DITOZ

T. EPI ISWARI, ST YUSWADI, ST HARDIANTO ZAINAL


Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur
PEMERINTAH ACEH

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN LAPORAN


Jl. Pemancar No.5 Simpang Tiga Telp. (0651) 42882 Fax. (0651) 41130 B. Aceh PELAKSANAAN PEKERJAAN MINGGUAN

PEKERJAAN : REHABILITASI RUANG KERJA KEPALA DINAS


LOKASI : BANDA ACEH KONTRAKTOR PELAKSANA : CV. DITOZ
NO. KONTRAK : 602.I/001/SEK-PL.02/PERKIM/APBA/2019 MINGGU :7
TGL. KONTRAK : 24 SEPTEMBER 2019 PERIODE : 05 S.D 11 NOPEMBER 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI 60.29 %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN

1 Pengukuran 1.00 Ls 2,000,000.00 2,000,000.00 1.49 1.00 2,000,000.00 100.00 - - - 1.00 2,000,000.00 100.00 1.49

2 SMK3 1.00 Ls 1,125,000.00 1,125,000.00 0.84 - - 40.00 - 20.00 - - 60.00 0.50

Sub Jumlah 3,125,000.00 2.33 2,000,000.00 - 2,000,000.00 2.00

II. PEKERJAAN INTERIOR RUANG KEPALA DINAS

1 Drop Ceiling HPL 16.00 M2 800,000.00 12,800,000.00 9.56 11.20 8,960,000.00 70.00 1.60 1,280,000.00 10.00 12.80 10,240,000.00 80.00 7.65

2 Perbaikan dan pemasangan plafond gypsum bertingkat + cat

1. Bongkar Plafond Lama 102.00 M2 10,000.00 1,020,000.00 0.76 71.40 714,000.00 70.00 10.20 102,000.00 10.00 81.60 816,000.00 80.00 0.61

2. Pasang Rangka furing 60x120 cm 102.00 M2 140,000.00 14,280,000.00 10.66 71.40 9,996,000.00 70.00 10.20 1,428,000.00 10.00 81.60 11,424,000.00 80.00 8.53

3. Pemasangan Panel gypsum 102.00 M2 91,861.00 9,369,822.00 7.00 71.40 6,558,875.40 70.00 10.20 936,982.20 10.00 81.60 7,495,857.60 80.00 5.60

4. Pengecatan 102.00 M2 23,552.58 2,402,363.16 1.79 51.00 1,201,181.58 50.00 10.20 240,236.32 10.00 61.20 1,441,417.90 60.00 1.08

3 Pantry + Kabinet Ekstensi Lemari Existing 1.00 Unit 12,500,000.00 12,500,000.00 9.33 0.50 6,250,000.00 50.00 0.10 1,250,000.00 10.00 0.60 7,500,000.00 60.00 5.60

4 Coffe Maker 1.00 Unit 13,000,000.00 13,000,000.00 9.71 0.50 6,500,000.00 50.00 0.10 1,300,000.00 10.00 0.60 7,800,000.00 60.00 5.82

5 Wallpaper ex. Zinniz/setara 80.00 M2 148,995.00 11,919,600.00 8.90 40.00 5,959,800.00 50.00 8.00 1,191,960.00 10.00 48.00 7,151,760.00 60.00 5.34

6 lighting + instalasi 1.00 Ls 10,000,000.00 10,000,000.00 7.47 0.40 4,000,000.00 40.00 0.10 1,000,000.00 10.00 0.50 5,000,000.00 50.00 3.73

7 Lapis dinding Plywood+HPL area box panel (foyer tangga) 10.00 M2 800,000.00 8,000,000.00 5.97 4.00 3,200,000.00 40.00 1.00 800,000.00 10.00 5.00 4,000,000.00 50.00 2.99

Pemasangan Shading plywood + HPL di jendela tangga (sesuai


8 1.00 M2 4,000,000.00 4,000,000.00 2.99 0.40 1,600,000.00 40.00 0.10 400,000.00 10.00 0.50 2,000,000.00 50.00 1.49
gambar)

9 Logo PANCACITA dari PVC + acrilic 80x80 cm 1.00 Unit 4,000,000.00 4,000,000.00 2.99 0.40 1,600,000.00 40.00 0.10 400,000.00 10.00 0.50 2,000,000.00 50.00 1.49

Cat Ulang pintu-pintu, kusen, plafond ruang sekretaris, perbaikan


10 1.00 Ls 6,000,000.00 6,000,000.00 4.48 0.40 2,400,000.00 40.00 0.10 600,000.00 10.00 0.50 3,000,000.00 50.00 2.24
furnitur dan pemasangan stiker sandblast kaca jendela

11 Pajangan Lambang Garuda Pancasila 1.00 Unit 2,000,000.00 2,000,000.00 1.49 0.30 600,000.00 30.00 0.10 200,000.00 10.00 0.40 800,000.00 40.00 0.60
NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

12 TV Cabinet + TV Backdrop ukiran 1.00 Unit 4,000,000.00 4,000,000.00 2.99 0.30 1,200,000.00 30.00 0.10 400,000.00 10.00 0.40 1,600,000.00 40.00 1.19

13 Blinds/gorden 32.50 M2 200,000.00 6,500,000.00 4.85 9.75 1,950,000.00 30.00 3.25 650,000.00 10.00 13.00 2,600,000.00 40.00 1.94

14 Tempat Tidur + lemari bedhead 1.00 Unit 8,000,000.00 8,000,000.00 5.97 0.30 2,400,000.00 30.00 0.10 800,000.00 10.00 0.40 3,200,000.00 40.00 2.39

Sub Jumlah 129,791,785.16 96.92 65,089,856.98 12,979,178.52 78,069,035.50 58.30

III. FINISHING

1 Pembersihan akhir 1.00 Taksir 1,000,000.00 1,000,000.00 0.75 - - - - - - - - - -

Sub Jumlah 1,000,000.00 0.75 - - - -

JUMLAH HARGA DAN BOBOT 133,916,785.16 100.00 67,089,856.98 12,979,178.52 80,069,035.50 60.29

PPN 10% 13,391,678.52 6,708,985.70 1,297,917.85 8,006,903.55

TOTAL KESELURUHAN 147,308,463.68 73,798,842.68 14,277,096.37 88,075,939.05

DIBULATKAN 147,308,000.00 73,798,000.00 14,277,000.00 88,075,000.00

Banda Aceh, 11 Nopember 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. DITOZ

T. EPI ISWARI, ST YUSWADI, ST HARDIANTO ZAINAL


Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur
PEMERINTAH ACEH

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN LAPORAN


Jl. Pemancar No.5 Simpang Tiga Telp. (0651) 42882 Fax. (0651) 41130 B. Aceh PELAKSANAAN PEKERJAAN MINGGUAN

PEKERJAAN : REHABILITASI RUANG KERJA KEPALA DINAS


LOKASI : BANDA ACEH KONTRAKTOR PELAKSANA : CV. DITOZ
NO. KONTRAK : 602.I/001/SEK-PL.02/PERKIM/APBA/2019 MINGGU :6
TGL. KONTRAK : 24 SEPTEMBER 2019 PERIODE : 29 OKT S.D 04 NOPEMBER 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI 50.43 %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN

1 Pengukuran 1.00 Ls 2,000,000.00 2,000,000.00 1.49 1.00 2,000,000.00 100.00 - - - 1.00 2,000,000.00 100.00 1.49

2 SMK3 1.00 Ls 1,125,000.00 1,125,000.00 0.84 - - 30.00 - 10.00 - - 40.00 0.34

Sub Jumlah 3,125,000.00 2.33 2,000,000.00 - 2,000,000.00 1.83

II. PEKERJAAN INTERIOR RUANG KEPALA DINAS

1 Drop Ceiling HPL 16.00 M2 800,000.00 12,800,000.00 9.56 8.00 6,400,000.00 50.00 3.20 2,560,000.00 20.00 11.20 8,960,000.00 70.00 6.69

2 Perbaikan dan pemasangan plafond gypsum bertingkat + cat

1. Bongkar Plafond Lama 102.00 M2 10,000.00 1,020,000.00 0.76 51.00 510,000.00 50.00 20.40 204,000.00 20.00 71.40 714,000.00 70.00 0.53

2. Pasang Rangka furing 60x120 cm 102.00 M2 140,000.00 14,280,000.00 10.66 51.00 7,140,000.00 50.00 20.40 2,856,000.00 20.00 71.40 9,996,000.00 70.00 7.46

3. Pemasangan Panel gypsum 102.00 M2 91,861.00 9,369,822.00 7.00 51.00 4,684,911.00 50.00 20.40 1,873,964.40 20.00 71.40 6,558,875.40 70.00 4.90

4. Pengecatan 102.00 M2 23,552.58 2,402,363.16 1.79 30.60 720,708.95 30.00 20.40 480,472.63 20.00 51.00 1,201,181.58 50.00 0.90

3 Pantry + Kabinet Ekstensi Lemari Existing 1.00 Unit 12,500,000.00 12,500,000.00 9.33 0.30 3,750,000.00 30.00 0.20 2,500,000.00 20.00 0.50 6,250,000.00 50.00 4.67

4 Coffe Maker 1.00 Unit 13,000,000.00 13,000,000.00 9.71 0.30 3,900,000.00 30.00 0.20 2,600,000.00 20.00 0.50 6,500,000.00 50.00 4.85

5 Wallpaper ex. Zinniz/setara 80.00 M2 148,995.00 11,919,600.00 8.90 24.00 3,575,880.00 30.00 16.00 2,383,920.00 20.00 40.00 5,959,800.00 50.00 4.45

6 lighting + instalasi 1.00 Ls 10,000,000.00 10,000,000.00 7.47 0.20 2,000,000.00 20.00 0.20 2,000,000.00 20.00 0.40 4,000,000.00 40.00 2.99

7 Lapis dinding Plywood+HPL area box panel (foyer tangga) 10.00 M2 800,000.00 8,000,000.00 5.97 2.00 1,600,000.00 20.00 2.00 1,600,000.00 20.00 4.00 3,200,000.00 40.00 2.39

Pemasangan Shading plywood + HPL di jendela tangga (sesuai


8 1.00 M2 4,000,000.00 4,000,000.00 2.99 0.20 800,000.00 20.00 0.20 800,000.00 20.00 0.40 1,600,000.00 40.00 1.19
gambar)

9 Logo PANCACITA dari PVC + acrilic 80x80 cm 1.00 Unit 4,000,000.00 4,000,000.00 2.99 0.20 800,000.00 20.00 0.20 800,000.00 20.00 0.40 1,600,000.00 40.00 1.19

Cat Ulang pintu-pintu, kusen, plafond ruang sekretaris, perbaikan


10 1.00 Ls 6,000,000.00 6,000,000.00 4.48 0.20 1,200,000.00 20.00 0.20 1,200,000.00 20.00 0.40 2,400,000.00 40.00 1.79
furnitur dan pemasangan stiker sandblast kaca jendela

11 Pajangan Lambang Garuda Pancasila 1.00 Unit 2,000,000.00 2,000,000.00 1.49 0.10 200,000.00 10.00 0.20 400,000.00 20.00 0.30 600,000.00 30.00 0.45
NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

12 TV Cabinet + TV Backdrop ukiran 1.00 Unit 4,000,000.00 4,000,000.00 2.99 0.10 400,000.00 10.00 0.20 800,000.00 20.00 0.30 1,200,000.00 30.00 0.90

13 Blinds/gorden 32.50 M2 200,000.00 6,500,000.00 4.85 3.25 650,000.00 10.00 6.50 1,300,000.00 20.00 9.75 1,950,000.00 30.00 1.46

14 Tempat Tidur + lemari bedhead 1.00 Unit 8,000,000.00 8,000,000.00 5.97 0.10 800,000.00 10.00 0.20 1,600,000.00 20.00 0.30 2,400,000.00 30.00 1.79

Sub Jumlah 129,791,785.16 96.92 39,131,499.95 25,958,357.03 65,089,856.98 48.60

III. FINISHING

1 Pembersihan akhir 1.00 Taksir 1,000,000.00 1,000,000.00 0.75 - - - - - - - - - -

Sub Jumlah 1,000,000.00 0.75 - - - -

JUMLAH HARGA DAN BOBOT 133,916,785.16 100.00 41,131,499.95 25,958,357.03 67,089,856.98 50.43

PPN 10% 13,391,678.52 4,113,149.99 2,595,835.70 6,708,985.70

TOTAL KESELURUHAN 147,308,463.68 45,244,649.94 28,554,192.74 73,798,842.68

DIBULATKAN 147,308,000.00 45,244,000.00 28,554,000.00 73,798,000.00

Banda Aceh, 04 Nopember 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. DITOZ

T. EPI ISWARI, ST YUSWADI, ST HARDIANTO ZAINAL


Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur
PEMERINTAH ACEH

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN LAPORAN


Jl. Pemancar No.5 Simpang Tiga Telp. (0651) 42882 Fax. (0651) 41130 B. Aceh PELAKSANAAN PEKERJAAN MINGGUAN

PEKERJAAN : REHABILITASI RUANG KERJA KEPALA DINAS


LOKASI : BANDA ACEH KONTRAKTOR PELAKSANA : CV. DITOZ
NO. KONTRAK : 602.I/001/SEK-PL.02/PERKIM/APBA/2019 MINGGU :5
TGL. KONTRAK : 24 SEPTEMBER 2019 PERIODE : 22 S.D 28 OKTOBER 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI 30.97 %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN

1 Pengukuran 1.00 Ls 2,000,000.00 2,000,000.00 1.49 1.00 2,000,000.00 100.00 - - - 1.00 2,000,000.00 100.00 1.49

2 SMK3 1.00 Ls 1,125,000.00 1,125,000.00 0.84 - - 20.00 - 10.00 - - 30.00 0.25

Sub Jumlah 3,125,000.00 2.33 2,000,000.00 - 2,000,000.00 1.75

II. PEKERJAAN INTERIOR RUANG KEPALA DINAS

1 Drop Ceiling HPL 16.00 M2 800,000.00 12,800,000.00 9.56 6.40 5,120,000.00 40.00 1.60 1,280,000.00 10.00 8.00 6,400,000.00 50.00 4.78

2 Perbaikan dan pemasangan plafond gypsum bertingkat + cat

1. Bongkar Plafond Lama 102.00 M2 10,000.00 1,020,000.00 0.76 40.80 408,000.00 40.00 10.20 102,000.00 10.00 51.00 510,000.00 50.00 0.38

2. Pasang Rangka furing 60x120 cm 102.00 M2 140,000.00 14,280,000.00 10.66 40.80 5,712,000.00 40.00 10.20 1,428,000.00 10.00 51.00 7,140,000.00 50.00 5.33

3. Pemasangan Panel gypsum 102.00 M2 91,861.00 9,369,822.00 7.00 40.80 3,747,928.80 40.00 10.20 936,982.20 10.00 51.00 4,684,911.00 50.00 3.50

4. Pengecatan 102.00 M2 23,552.58 2,402,363.16 1.79 20.40 480,472.63 20.00 10.20 240,236.32 10.00 30.60 720,708.95 30.00 0.54

3 Pantry + Kabinet Ekstensi Lemari Existing 1.00 Unit 12,500,000.00 12,500,000.00 9.33 0.20 2,500,000.00 20.00 0.10 1,250,000.00 10.00 0.30 3,750,000.00 30.00 2.80

4 Coffe Maker 1.00 Unit 13,000,000.00 13,000,000.00 9.71 0.20 2,600,000.00 20.00 0.10 1,300,000.00 10.00 0.30 3,900,000.00 30.00 2.91

5 Wallpaper ex. Zinniz/setara 80.00 M2 148,995.00 11,919,600.00 8.90 16.00 2,383,920.00 20.00 8.00 1,191,960.00 10.00 24.00 3,575,880.00 30.00 2.67

6 lighting + instalasi 1.00 Ls 10,000,000.00 10,000,000.00 7.47 0.10 1,000,000.00 10.00 0.10 1,000,000.00 10.00 0.20 2,000,000.00 20.00 1.49

7 Lapis dinding Plywood+HPL area box panel (foyer tangga) 10.00 M2 800,000.00 8,000,000.00 5.97 1.00 800,000.00 10.00 1.00 800,000.00 10.00 2.00 1,600,000.00 20.00 1.19

Pemasangan Shading plywood + HPL di jendela tangga (sesuai


8 1.00 M2 4,000,000.00 4,000,000.00 2.99 0.10 400,000.00 10.00 0.10 400,000.00 10.00 0.20 800,000.00 20.00 0.60
gambar)

9 Logo PANCACITA dari PVC + acrilic 80x80 cm 1.00 Unit 4,000,000.00 4,000,000.00 2.99 0.10 400,000.00 10.00 0.10 400,000.00 10.00 0.20 800,000.00 20.00 0.60

Cat Ulang pintu-pintu, kusen, plafond ruang sekretaris, perbaikan


10 1.00 Ls 6,000,000.00 6,000,000.00 4.48 0.10 600,000.00 10.00 0.10 600,000.00 10.00 0.20 1,200,000.00 20.00 0.90
furnitur dan pemasangan stiker sandblast kaca jendela

11 Pajangan Lambang Garuda Pancasila 1.00 Unit 2,000,000.00 2,000,000.00 1.49 - - - 0.10 200,000.00 10.00 0.10 200,000.00 10.00 0.15
NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

12 TV Cabinet + TV Backdrop ukiran 1.00 Unit 4,000,000.00 4,000,000.00 2.99 - - - 0.10 400,000.00 10.00 0.10 400,000.00 10.00 0.30

13 Blinds/gorden 32.50 M2 200,000.00 6,500,000.00 4.85 - - - 3.25 650,000.00 10.00 3.25 650,000.00 10.00 0.49

14 Tempat Tidur + lemari bedhead 1.00 Unit 8,000,000.00 8,000,000.00 5.97 - - - 0.10 800,000.00 10.00 0.10 800,000.00 10.00 0.60

Sub Jumlah 129,791,785.16 96.92 26,152,321.43 12,979,178.52 39,131,499.95 29.22

III. FINISHING

1 Pembersihan akhir 1.00 Taksir 1,000,000.00 1,000,000.00 0.75 - - - - - - - - - -

Sub Jumlah 1,000,000.00 0.75 - - - -

JUMLAH HARGA DAN BOBOT 133,916,785.16 100.00 28,152,321.43 12,979,178.52 41,131,499.95 30.97

PPN 10% 13,391,678.52 2,815,232.14 1,297,917.85 4,113,149.99

TOTAL KESELURUHAN 147,308,463.68 30,967,553.58 14,277,096.37 45,244,649.94

DIBULATKAN 147,308,000.00 30,967,000.00 14,277,000.00 45,244,000.00

Banda Aceh, 28 Oktober 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. DITOZ

T. EPI ISWARI, ST YUSWADI, ST HARDIANTO ZAINAL


Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur
PEMERINTAH ACEH

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN LAPORAN


Jl. Pemancar No.5 Simpang Tiga Telp. (0651) 42882 Fax. (0651) 41130 B. Aceh PELAKSANAAN PEKERJAAN BULANAN

PEKERJAAN : REHABILITASI RUANG KERJA KEPALA DINAS


LOKASI : BANDA ACEH KONTRAKTOR PELAKSANA : CV. DITOZ
NO. KONTRAK : 602.I/001/SEK-PL.02/PERKIM/APBA/2019 BULAN :I
TGL. KONTRAK : 24 SEPTEMBER 2019 PERIODE : 24 SEPTEMBER S.D 21 OKTOBER 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI 21.19 %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN
1 Pengukuran 1.00 Ls 2,000,000.00 2,000,000.00 1.49 - - - 1.00 2,000,000.00 100.00 1.00 2,000,000.00 100.00 1.49

2 SMK3 1.00 Ls 1,125,000.00 1,125,000.00 0.84 - - - - 20.00 - - 20.00 0.17


Sub Jumlah 3,125,000.00 2.33 - 2,000,000.00 2,000,000.00 1.66

II. PEKERJAAN INTERIOR RUANG KEPALA DINAS

1 Drop Ceiling HPL 16.00 M2 800,000.00 12,800,000.00 9.56 - - - 6.40 5,120,000.00 40.00 6.40 5,120,000.00 40.00 3.82

2 Perbaikan dan pemasangan plafond gypsum bertingkat + cat


1. Bongkar Plafond Lama 102.00 M2 10,000.00 1,020,000.00 0.76 - - - 40.80 408,000.00 40.00 40.80 408,000.00 40.00 0.30
2. Pasang Rangka furing 60x120 cm 102.00 M2 140,000.00 14,280,000.00 10.66 - - - 40.80 5,712,000.00 40.00 40.80 5,712,000.00 40.00 4.27
3. Pemasangan Panel gypsum 102.00 M2 91,861.00 9,369,822.00 7.00 - - - 40.80 3,747,928.80 40.00 40.80 3,747,928.80 40.00 2.80
4. Pengecatan 102.00 M2 23,552.58 2,402,363.16 1.79 - - - 20.40 480,472.63 20.00 20.40 480,472.63 20.00 0.36
3 Pantry + Kabinet Ekstensi Lemari Existing 1.00 Unit 12,500,000.00 12,500,000.00 9.33 - - - 0.20 2,500,000.00 20.00 0.20 2,500,000.00 20.00 1.87

4 Coffe Maker 1.00 Unit 13,000,000.00 13,000,000.00 9.71 - - - 0.20 2,600,000.00 20.00 0.20 2,600,000.00 20.00 1.94
5 Wallpaper ex. Zinniz/setara 80.00 M2 148,995.00 11,919,600.00 8.90 - - - 16.00 2,383,920.00 20.00 16.00 2,383,920.00 20.00 1.78

6 lighting + instalasi 1.00 Ls 10,000,000.00 10,000,000.00 7.47 - - - 0.10 1,000,000.00 10.00 0.10 1,000,000.00 10.00 0.75
7 Lapis dinding Plywood+HPL area box panel (foyer tangga) 10.00 M2 800,000.00 8,000,000.00 5.97 - - - 1.00 800,000.00 10.00 1.00 800,000.00 10.00 0.60

Pemasangan Shading plywood + HPL di jendela tangga (sesuai


8 1.00 M2 4,000,000.00 4,000,000.00 2.99 - - - 0.10 400,000.00 10.00 0.10 400,000.00 10.00 0.30
gambar)

9 Logo PANCACITA dari PVC + acrilic 80x80 cm 1.00 Unit 4,000,000.00 4,000,000.00 2.99 - - - 0.10 400,000.00 10.00 0.10 400,000.00 10.00 0.30

Cat Ulang pintu-pintu, kusen, plafond ruang sekretaris, perbaikan


10 1.00 Ls 6,000,000.00 6,000,000.00 4.48 - - - 0.10 600,000.00 10.00 0.10 600,000.00 10.00 0.45
furnitur dan pemasangan stiker sandblast kaca jendela

11 Pajangan Lambang Garuda Pancasila 1.00 Unit 2,000,000.00 2,000,000.00 1.49 - - - - - - - - - -


12 TV Cabinet + TV Backdrop ukiran 1.00 Unit 4,000,000.00 4,000,000.00 2.99 - - - - - - - - - -

13 Blinds/gorden 32.50 M2 200,000.00 6,500,000.00 4.85 - - - - - - - - - -


14 Tempat Tidur + lemari bedhead 1.00 Unit 8,000,000.00 8,000,000.00 5.97 - - - - - - - - - -

Sub Jumlah 129,791,785.16 96.92 - 26,152,321.43 26,152,321.43 19.53


III. FINISHING

1 Pembersihan akhir 1.00 Taksir 1,000,000.00 1,000,000.00 0.75 - - - - - - - - - -

Sub Jumlah 1,000,000.00 0.75 - - - -

JUMLAH HARGA DAN BOBOT 133,916,785.16 100.00 - 28,152,321.43 28,152,321.43 21.19


PPN 10% 13,391,678.52 - 2,815,232.14 2,815,232.14
TOTAL KESELURUHAN 147,308,463.68 - 30,967,553.58 30,967,553.58

DIBULATKAN 147,308,000.00 - 30,967,000.00 30,967,000.00

Banda Aceh, 21 Oktober 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. DITOZ

T. EPI ISWARI, ST YUSWADI, ST HARDIANTO ZAINAL


Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur
PEMERINTAH ACEH

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN LAPORAN


Jl. Pemancar No.5 Simpang Tiga Telp. (0651) 42882 Fax. (0651) 41130 B. Aceh PELAKSANAAN PEKERJAAN MINGGUAN

PEKERJAAN : REHABILITASI RUANG KERJA KEPALA DINAS


LOKASI : BANDA ACEH KONTRAKTOR PELAKSANA : CV. DITOZ
NO. KONTRAK : 602.I/001/SEK-PL.02/PERKIM/APBA/2019 MINGGU :4
TGL. KONTRAK : 24 SEPTEMBER 2019 PERIODE : 15 S.D 21 OKTOBER 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI 21.19 %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN

1 Pengukuran 1.00 Ls 2,000,000.00 2,000,000.00 1.49 1.00 2,000,000.00 100.00 - - - 1.00 2,000,000.00 100.00 1.49

2 SMK3 1.00 Ls 1,125,000.00 1,125,000.00 0.84 - - 15.00 - 5.00 - - 20.00 0.17

Sub Jumlah 3,125,000.00 2.33 2,000,000.00 - 2,000,000.00 1.66

II. PEKERJAAN INTERIOR RUANG KEPALA DINAS

1 Drop Ceiling HPL 16.00 M2 800,000.00 12,800,000.00 9.56 4.80 3,840,000.00 30.00 1.60 1,280,000.00 10.00 6.40 5,120,000.00 40.00 3.82

2 Perbaikan dan pemasangan plafond gypsum bertingkat + cat

1. Bongkar Plafond Lama 102.00 M2 10,000.00 1,020,000.00 0.76 30.60 306,000.00 30.00 10.20 102,000.00 10.00 40.80 408,000.00 40.00 0.30

2. Pasang Rangka furing 60x120 cm 102.00 M2 140,000.00 14,280,000.00 10.66 30.60 4,284,000.00 30.00 10.20 1,428,000.00 10.00 40.80 5,712,000.00 40.00 4.27

3. Pemasangan Panel gypsum 102.00 M2 91,861.00 9,369,822.00 7.00 30.60 2,810,946.60 30.00 10.20 936,982.20 10.00 40.80 3,747,928.80 40.00 2.80

4. Pengecatan 102.00 M2 23,552.58 2,402,363.16 1.79 10.20 240,236.32 10.00 10.20 240,236.32 10.00 20.40 480,472.63 20.00 0.36

3 Pantry + Kabinet Ekstensi Lemari Existing 1.00 Unit 12,500,000.00 12,500,000.00 9.33 0.10 1,250,000.00 10.00 0.10 1,250,000.00 10.00 0.20 2,500,000.00 20.00 1.87

4 Coffe Maker 1.00 Unit 13,000,000.00 13,000,000.00 9.71 0.10 1,300,000.00 10.00 0.10 1,300,000.00 10.00 0.20 2,600,000.00 20.00 1.94

5 Wallpaper ex. Zinniz/setara 80.00 M2 148,995.00 11,919,600.00 8.90 8.00 1,191,960.00 10.00 8.00 1,191,960.00 10.00 16.00 2,383,920.00 20.00 1.78

6 lighting + instalasi 1.00 Ls 10,000,000.00 10,000,000.00 7.47 - - - 0.10 1,000,000.00 10.00 0.10 1,000,000.00 10.00 0.75

7 Lapis dinding Plywood+HPL area box panel (foyer tangga) 10.00 M2 800,000.00 8,000,000.00 5.97 - - - 1.00 800,000.00 10.00 1.00 800,000.00 10.00 0.60

Pemasangan Shading plywood + HPL di jendela tangga (sesuai


8 1.00 M2 4,000,000.00 4,000,000.00 2.99 - - - 0.10 400,000.00 10.00 0.10 400,000.00 10.00 0.30
gambar)

9 Logo PANCACITA dari PVC + acrilic 80x80 cm 1.00 Unit 4,000,000.00 4,000,000.00 2.99 - - - 0.10 400,000.00 10.00 0.10 400,000.00 10.00 0.30

Cat Ulang pintu-pintu, kusen, plafond ruang sekretaris, perbaikan


10 1.00 Ls 6,000,000.00 6,000,000.00 4.48 - - - 0.10 600,000.00 10.00 0.10 600,000.00 10.00 0.45
furnitur dan pemasangan stiker sandblast kaca jendela

11 Pajangan Lambang Garuda Pancasila 1.00 Unit 2,000,000.00 2,000,000.00 1.49 - - - - - - - - - -


NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

12 TV Cabinet + TV Backdrop ukiran 1.00 Unit 4,000,000.00 4,000,000.00 2.99 - - - - - - - - - -

13 Blinds/gorden 32.50 M2 200,000.00 6,500,000.00 4.85 - - - - - - - - - -

14 Tempat Tidur + lemari bedhead 1.00 Unit 8,000,000.00 8,000,000.00 5.97 - - - - - - - - - -

Sub Jumlah 129,791,785.16 96.92 15,223,142.92 10,929,178.52 26,152,321.43 19.53

III. FINISHING

1 Pembersihan akhir 1.00 Taksir 1,000,000.00 1,000,000.00 0.75 - - - - - - - - - -

Sub Jumlah 1,000,000.00 0.75 - - - -

JUMLAH HARGA DAN BOBOT 133,916,785.16 100.00 17,223,142.92 10,929,178.52 28,152,321.43 21.19

PPN 10% 13,391,678.52 1,722,314.29 1,092,917.85 2,815,232.14

TOTAL KESELURUHAN 147,308,463.68 18,945,457.21 12,022,096.37 30,967,553.58

DIBULATKAN 147,308,000.00 18,945,000.00 12,022,000.00 30,967,000.00

Banda Aceh, 21 Oktober 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. DITOZ

T. EPI ISWARI, ST YUSWADI, ST HARDIANTO ZAINAL


Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur
PEMERINTAH ACEH

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN LAPORAN


Jl. Pemancar No.5 Simpang Tiga Telp. (0651) 42882 Fax. (0651) 41130 B. Aceh PELAKSANAAN PEKERJAAN MINGGUAN

PEKERJAAN : REHABILITASI RUANG KERJA KEPALA DINAS


LOKASI : BANDA ACEH KONTRAKTOR PELAKSANA : CV. DITOZ
NO. KONTRAK : 602.I/001/SEK-PL.02/PERKIM/APBA/2019 MINGGU :3
TGL. KONTRAK : 24 SEPTEMBER 2019 PERIODE : 08 S.D 14 OKTOBER 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI 12.99 %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN

1 Pengukuran 1.00 Ls 2,000,000.00 2,000,000.00 1.49 1.00 2,000,000.00 100.00 - - - 1.00 2,000,000.00 100.00 1.49

2 SMK3 1.00 Ls 1,125,000.00 1,125,000.00 0.84 - - 10.00 - 5.00 - - 15.00 0.13

Sub Jumlah 3,125,000.00 2.33 2,000,000.00 - 2,000,000.00 1.62

II. PEKERJAAN INTERIOR RUANG KEPALA DINAS

1 Drop Ceiling HPL 16.00 M2 800,000.00 12,800,000.00 9.56 1.60 1,280,000.00 10.00 3.20 2,560,000.00 20.00 4.80 3,840,000.00 30.00 2.87

2 Perbaikan dan pemasangan plafond gypsum bertingkat + cat

1. Bongkar Plafond Lama 102.00 M2 10,000.00 1,020,000.00 0.76 10.20 102,000.00 10.00 20.40 204,000.00 20.00 30.60 306,000.00 30.00 0.23

2. Pasang Rangka furing 60x120 cm 102.00 M2 140,000.00 14,280,000.00 10.66 10.20 1,428,000.00 10.00 20.40 2,856,000.00 20.00 30.60 4,284,000.00 30.00 3.20

3. Pemasangan Panel gypsum 102.00 M2 91,861.00 9,369,822.00 7.00 10.20 936,982.20 10.00 20.40 1,873,964.40 20.00 30.60 2,810,946.60 30.00 2.10

4. Pengecatan 102.00 M2 23,552.58 2,402,363.16 1.79 - - - 10.20 240,236.32 10.00 10.20 240,236.32 10.00 0.18

3 Pantry + Kabinet Ekstensi Lemari Existing 1.00 Unit 12,500,000.00 12,500,000.00 9.33 - - - 0.10 1,250,000.00 10.00 0.10 1,250,000.00 10.00 0.93

4 Coffe Maker 1.00 Unit 13,000,000.00 13,000,000.00 9.71 - - - 0.10 1,300,000.00 10.00 0.10 1,300,000.00 10.00 0.97

5 Wallpaper ex. Zinniz/setara 80.00 M2 148,995.00 11,919,600.00 8.90 - - - 8.00 1,191,960.00 10.00 8.00 1,191,960.00 10.00 0.89

6 lighting + instalasi 1.00 Ls 10,000,000.00 10,000,000.00 7.47 - - - - - - - - - -

7 Lapis dinding Plywood+HPL area box panel (foyer tangga) 10.00 M2 800,000.00 8,000,000.00 5.97 - - - - - - - - - -

Pemasangan Shading plywood + HPL di jendela tangga (sesuai


8 1.00 M2 4,000,000.00 4,000,000.00 2.99 - - - - - - - - - -
gambar)

9 Logo PANCACITA dari PVC + acrilic 80x80 cm 1.00 Unit 4,000,000.00 4,000,000.00 2.99 - - - - - - - - - -

Cat Ulang pintu-pintu, kusen, plafond ruang sekretaris, perbaikan


10 1.00 Ls 6,000,000.00 6,000,000.00 4.48 - - - - - - - - - -
furnitur dan pemasangan stiker sandblast kaca jendela

11 Pajangan Lambang Garuda Pancasila 1.00 Unit 2,000,000.00 2,000,000.00 1.49 - - - - - - - - - -


NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

12 TV Cabinet + TV Backdrop ukiran 1.00 Unit 4,000,000.00 4,000,000.00 2.99 - - - - - - - - - -

13 Blinds/gorden 32.50 M2 200,000.00 6,500,000.00 4.85 - - - - - - - - - -

14 Tempat Tidur + lemari bedhead 1.00 Unit 8,000,000.00 8,000,000.00 5.97 - - - - - - - - - -

Sub Jumlah 129,791,785.16 96.92 3,746,982.20 11,476,160.72 15,223,142.92 11.37

III. FINISHING

1 Pembersihan akhir 1.00 Taksir 1,000,000.00 1,000,000.00 0.75 - - - - - - - - - -

Sub Jumlah 1,000,000.00 0.75 - - - -

JUMLAH HARGA DAN BOBOT 133,916,785.16 100.00 5,746,982.20 11,476,160.72 17,223,142.92 12.99

PPN 10% 13,391,678.52 574,698.22 1,147,616.07 1,722,314.29

TOTAL KESELURUHAN 147,308,463.68 6,321,680.42 12,623,776.79 18,945,457.21

DIBULATKAN 147,308,000.00 6,321,000.00 12,623,000.00 18,945,000.00

Banda Aceh, 14 Oktober 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. DITOZ

T. EPI ISWARI, ST YUSWADI, ST HARDIANTO ZAINAL


Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur
PEMERINTAH ACEH

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN LAPORAN


Jl. Pemancar No.5 Simpang Tiga Telp. (0651) 42882 Fax. (0651) 41130 B. Aceh PELAKSANAAN PEKERJAAN MINGGUAN

PEKERJAAN : REHABILITASI RUANG KERJA KEPALA DINAS


LOKASI : BANDA ACEH KONTRAKTOR PELAKSANA : CV. DITOZ
NO. KONTRAK : 602.I/001/SEK-PL.02/PERKIM/APBA/2019 MINGGU :2
TGL. KONTRAK : 24 SEPTEMBER 2019 PERIODE : 01 S.D 07 OKTOBER 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI 4.38 %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN

1 Pengukuran 1.00 Ls 2,000,000.00 2,000,000.00 1.49 1.00 2,000,000.00 100.00 - - - 1.00 2,000,000.00 100.00 1.49

2 SMK3 1.00 Ls 1,125,000.00 1,125,000.00 0.84 - - 5.00 - 5.00 - - 10.00 0.08

Sub Jumlah 3,125,000.00 2.33 2,000,000.00 - 2,000,000.00 1.58

II. PEKERJAAN INTERIOR RUANG KEPALA DINAS

1 Drop Ceiling HPL 16.00 M2 800,000.00 12,800,000.00 9.56 - - - 1.60 1,280,000.00 10.00 1.60 1,280,000.00 10.00 0.96

2 Perbaikan dan pemasangan plafond gypsum bertingkat + cat

1. Bongkar Plafond Lama 102.00 M2 10,000.00 1,020,000.00 0.76 - - - 10.20 102,000.00 10.00 10.20 102,000.00 10.00 0.08

2. Pasang Rangka furing 60x120 cm 102.00 M2 140,000.00 14,280,000.00 10.66 - - - 10.20 1,428,000.00 10.00 10.20 1,428,000.00 10.00 1.07

3. Pemasangan Panel gypsum 102.00 M2 91,861.00 9,369,822.00 7.00 - - - 10.20 936,982.20 10.00 10.20 936,982.20 10.00 0.70

4. Pengecatan 102.00 M2 23,552.58 2,402,363.16 1.79 - - - - - - - - - -

3 Pantry + Kabinet Ekstensi Lemari Existing 1.00 Unit 12,500,000.00 12,500,000.00 9.33 - - - - - - - - - -

4 Coffe Maker 1.00 Unit 13,000,000.00 13,000,000.00 9.71 - - - - - - - - - -

5 Wallpaper ex. Zinniz/setara 80.00 M2 148,995.00 11,919,600.00 8.90 - - - - - - - - - -

6 lighting + instalasi 1.00 Ls 10,000,000.00 10,000,000.00 7.47 - - - - - - - - - -

7 Lapis dinding Plywood+HPL area box panel (foyer tangga) 10.00 M2 800,000.00 8,000,000.00 5.97 - - - - - - - - - -

Pemasangan Shading plywood + HPL di jendela tangga (sesuai


8 1.00 M2 4,000,000.00 4,000,000.00 2.99 - - - - - - - - - -
gambar)

9 Logo PANCACITA dari PVC + acrilic 80x80 cm 1.00 Unit 4,000,000.00 4,000,000.00 2.99 - - - - - - - - - -

Cat Ulang pintu-pintu, kusen, plafond ruang sekretaris, perbaikan


10 1.00 Ls 6,000,000.00 6,000,000.00 4.48 - - - - - - - - - -
furnitur dan pemasangan stiker sandblast kaca jendela

11 Pajangan Lambang Garuda Pancasila 1.00 Unit 2,000,000.00 2,000,000.00 1.49 - - - - - - - - - -


NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

12 TV Cabinet + TV Backdrop ukiran 1.00 Unit 4,000,000.00 4,000,000.00 2.99 - - - - - - - - - -

13 Blinds/gorden 32.50 M2 200,000.00 6,500,000.00 4.85 - - - - - - - - - -

14 Tempat Tidur + lemari bedhead 1.00 Unit 8,000,000.00 8,000,000.00 5.97 - - - - - - - - - -

Sub Jumlah 129,791,785.16 96.92 - 3,746,982.20 3,746,982.20 2.80

III. FINISHING

1 Pembersihan akhir 1.00 Taksir 1,000,000.00 1,000,000.00 0.75 - - - - - - - - - -

Sub Jumlah 1,000,000.00 0.75 - - - -

JUMLAH HARGA DAN BOBOT 133,916,785.16 100.00 2,000,000.00 3,746,982.20 5,746,982.20 4.38

PPN 10% 13,391,678.52 200,000.00 374,698.22 574,698.22

TOTAL KESELURUHAN 147,308,463.68 2,200,000.00 4,121,680.42 6,321,680.42

DIBULATKAN 147,308,000.00 2,200,000.00 4,121,000.00 6,321,000.00

Banda Aceh, 07 Oktober 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. DITOZ

T. EPI ISWARI, ST YUSWADI, ST HARDIANTO ZAINAL


Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur
PEMERINTAH ACEH

DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN LAPORAN


Jl. Pemancar No.5 Simpang Tiga Telp. (0651) 42882 Fax. (0651) 41130 B. Aceh PELAKSANAAN PEKERJAAN MINGGUAN

PEKERJAAN : REHABILITASI RUANG KERJA KEPALA DINAS


LOKASI : BANDA ACEH KONTRAKTOR PELAKSANA : CV. DITOZ
NO. KONTRAK : 602.I/001/SEK-PL.02/PERKIM/APBA/2019 MINGGU :I
TGL. KONTRAK : 24 SEPTEMBER 2019 PERIODE : 24 SEP S.D 30 SEP 2019
TAHUN ANGGARAN : 2019 PROGRESS S.D SAAT INI 1.54 %

NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

I. PEKERJAAN PERSIAPAN

1 Pengukuran 1.00 Ls 2,000,000.00 2,000,000.00 1.49 - - - 1.00 2,000,000.00 100.00 1.00 2,000,000.00 100.00 1.49

2 SMK3 1.00 Ls 1,125,000.00 1,125,000.00 0.84 - - - - 5.00 - - 5.00 0.04

Sub Jumlah 3,125,000.00 2.33 - 2,000,000.00 2,000,000.00 1.54

II. PEKERJAAN INTERIOR RUANG KEPALA DINAS

1 Drop Ceiling HPL 16.00 M2 800,000.00 12,800,000.00 9.56 - - - - - - - - - -

2 Perbaikan dan pemasangan plafond gypsum bertingkat + cat

1. Bongkar Plafond Lama 102.00 M2 10,000.00 1,020,000.00 0.76 - - - - - - - - - -

2. Pasang Rangka furing 60x120 cm 102.00 M2 140,000.00 14,280,000.00 10.66 - - - - - - - - - -

3. Pemasangan Panel gypsum 102.00 M2 91,861.00 9,369,822.00 7.00 - - - - - - - - - -

4. Pengecatan 102.00 M2 23,552.58 2,402,363.16 1.79 - - - - - - - - - -

3 Pantry + Kabinet Ekstensi Lemari Existing 1.00 Unit 12,500,000.00 12,500,000.00 9.33 - - - - - - - - - -

4 Coffe Maker 1.00 Unit 13,000,000.00 13,000,000.00 9.71 - - - - - - - - - -

5 Wallpaper ex. Zinniz/setara 80.00 M2 148,995.00 11,919,600.00 8.90 - - - - - - - - - -

6 lighting + instalasi 1.00 Ls 10,000,000.00 10,000,000.00 7.47 - - - - - - - - - -

7 Lapis dinding Plywood+HPL area box panel (foyer tangga) 10.00 M2 800,000.00 8,000,000.00 5.97 - - - - - - - - - -

Pemasangan Shading plywood + HPL di jendela tangga (sesuai


8 1.00 M2 4,000,000.00 4,000,000.00 2.99 - - - - - - - - - -
gambar)

9 Logo PANCACITA dari PVC + acrilic 80x80 cm 1.00 Unit 4,000,000.00 4,000,000.00 2.99 - - - - - - - - - -

Cat Ulang pintu-pintu, kusen, plafond ruang sekretaris, perbaikan


10 1.00 Ls 6,000,000.00 6,000,000.00 4.48 - - - - - - - - - -
furnitur dan pemasangan stiker sandblast kaca jendela

11 Pajangan Lambang Garuda Pancasila 1.00 Unit 2,000,000.00 2,000,000.00 1.49 - - - - - - - - - -


NILAI KONTRAK S.D BULAN LALU BULAN INI S.D BULAN INI BOBOT
VOLUME TERHADAP
NO URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH JUMLAH JUMLAH BOBOT JUMLAH BOBOT
KONTRAK BOBOT (%) VOLUME BOBOT (%) VOLUME VOLUME KESELURUHAN
(Rp) HARGA (Rp) HARGA (Rp) HARGA (Rp) (%) HARGA (Rp) (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

12 TV Cabinet + TV Backdrop ukiran 1.00 Unit 4,000,000.00 4,000,000.00 2.99 - - - - - - - - - -

13 Blinds/gorden 32.50 M2 200,000.00 6,500,000.00 4.85 - - - - - - - - - -

14 Tempat Tidur + lemari bedhead 1.00 Unit 8,000,000.00 8,000,000.00 5.97 - - - - - - - - - -

Sub Jumlah 129,791,785.16 96.92 - - - -

III. FINISHING

1 Pembersihan akhir 1.00 Taksir 1,000,000.00 1,000,000.00 0.75 - - - - - - - - - -

Sub Jumlah 1,000,000.00 0.75 - - - -

JUMLAH HARGA DAN BOBOT 133,916,785.16 100.00 - 2,000,000.00 2,000,000.00 1.54

PPN 10% 13,391,678.52 - 200,000.00 200,000.00

TOTAL KESELURUHAN 147,308,463.68 - 2,200,000.00 2,200,000.00

DIBULATKAN 147,308,000.00 - 2,200,000.00 2,200,000.00

Banda Aceh, 30 September 2019


Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,
PEJABAT PELAKSANA TEKNIS KEGIATAN Pengawas Lapangan Kontraktor Pelaksana
DINAS PERUMAHAN RAKYAT DAN KAWASAN PERMUKIMAN KAB. PIDIE CV. DITOZ

T. EPI ISWARI, ST YUSWADI, ST HARDIANTO ZAINAL


Penata / Nip. 19750712 200604 1 030 Nip. 19760521 200904 1 004 Direktur