SCHEDULE

RUKO TARUMA CITY

NO DESCRIPTION START FINISH DURATION Dec-19 Jan-19 Feb-19 Mar-19


29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
I PEKERJAAN STRUKTUR
A STURKTUR LANTAI 2
1 BEKISTING PLAT LANTAI 2 & BALOK LANTAI 1 29-Dec-19 6-Jan-20 9 days

2 PEMBESIAN 1-Jan-20 7-Jan-20 7 days

3 CHECKLIST 8-Jan-20 8-Jan-20 1 days

4 PENGECORAN BALOK LT 1 DAN PLAT LT 2 9-Jan-20 9-Jan-20 1 days

5 PEKERJAAN KOLOM LT 2 10-Jan-20 12-Jan-20 2 days

B STURKTUR LANTAI 3
1 BEKISTING PLAT LANTAI 3 & BALOK LANTAI 2 11-Jan-20 18-Jan-20 8 days

2 PEMBESIAN 13-Jan-20 19-Jan-20 7 days

3 CHECKLIST 20-Jan-20 20-Jan-20 1 days

4 PENGECORAN BALOK LT 2 DAN PLAT LT 3 21-Jan-20 21-Jan-20 1 days

5 PEKERJAAN KOLOM LT 3 22-Jan-20 24-Jan-20 2 days

C STURKTUR LANTAI ATAP


1 BEKISTING PLAT LANTAI ATAP & BALOK LANTAI 3 23-Jan-20 28-Jan-20 6 days

2 PEMBESIAN 25-Jan-20 29-Jan-20 5 days

3 CHECKLIST 30-Jan-20 30-Jan-20 1 days


4 PENGECORAN BALOK LT 3 DAN PLAT LT ATAP 31-Jan-20 31-Jan-20 1 days

II PEKERJAAN ARSITEKTUR

A ARSITEKTUR LANTAI I
1 PASANGAN DINDING BATA 20-Jan-20 1-Feb-20 13 days

2 PLESTERAN DINDING BATA 27-Jan-20 5-Feb-20 10 days

3 ACIAN 3-Feb-20 9-Feb-20 7 days


4 PEKERJAAN PLAFON 10-Feb-20 23-Feb-20 14 days

5 PEKERJAAN KERAMIK LANTAI 17-Feb-20 28-Feb-20 12 days

6 PEKERJAAN TOILET 3-Feb-20 22-Feb-20 20 days


7 PEKERJAAN PINTU DAN JENDELA 2-Mar-20 6-Mar-20 5 days

8 PEKERJAAN CAT 10-Mar-20 16-Mar-20 7 days

B ARSITEKTUR LANTAI II
1 PASANGAN DINDING BATA 3-Feb-20 16-Feb-20 14 days

2 PLESTERAN DINDING BATA 10-Feb-20 23-Feb-20 14 days

3 ACIAN 17-Feb-20 25-Feb-20 9 days

4 PEKERJAAN PLAFON 20-Feb-20 2-Mar-20 12 days

5 PEKERJAAN KERAMIK LANTAI 24-Feb-20 5-Mar-20 11 days

6 PEKERJAAN TOILET 10-Feb-20 23-Feb-20 14 days

7 PEKERJAAN PINTU DAN JENDELA 6-Mar-20 10-Mar-20 5 days

8 PEKERJAAN CAT 8-Mar-20 14-Mar-20 7 days

C ARSITEKTUR LANTAI III


1 PASANGAN DINDING BATA 17-Feb-20 2-Mar-20 15 days

2 PLESTERAN DINDING BATA 24-Feb-20 8-Mar-20 14 days

3 ACIAN 3-Mar-20 10-Mar-20 8 days

4 PEKERJAAN PLAFON 5-Mar-20 15-Mar-20 11 days

5 PEKERJAAN KERAMIK LANTAI 10-Mar-20 20-Mar-20 11 days

6 PEKERJAAN TOILET 5-Mar-20 19-Mar-20 15 days

7 PEKERJAAN PINTU DAN JENDELA 20-Mar-20 25-Mar-20 6 days

8 PEKERJAAN CAT 22-Mar-20 28-Mar-20 7 days

D ARSITEKTUR LANTAI ATAP


1 PASANGAN DINDING PARAVET 3-Mar-20 9-Mar-20 7 days

2 PEK. WATER PROOFING 10-Mar-20 16-Mar-20 7 days

3 PEK. SCREED LT. ATAP 14-Mar-20 20-Mar-20 7 days

E PEKERJAAN LAIN-LAIN
4 PEKERJAAN RAILING TANGGA 3-Feb-20 16-Feb-20 14 days

5 PEKERJAAN CANOPY DEPAN 17-Feb-20 15-Mar-20 43 days

6 PEKERJAAN KERAMIK TANGGA 15-Feb-20 15-Mar-20 30 days

Jakarta, 16 Desember 2019