SKEDJUL MINGGUAN

RUKO TARUMA CITY

NO DESCRIPTION START FINISH DURATION S S R K J S M S S R K J S M


16 17 18 19 20 21 22 23 24 25 26 27 28 29
PEKERJAAN LANTAI DASAR RUKO (UNIT PRIORITAS)
i GALIAN 16-Dec-19 21-Dec-19 6 days

ii LANTAI KERJA (PC+TB) 17-Dec-19 22-Dec-19 6 days

iii BEKISTING (PC+TB) 18-Dec-19 22-Dec-19 5 days

iv LANTAI KERJA (PLAT) 23-Dec-19 23-Dec-19 1 days

v PASANG PIPA PLUMBING 20-Dec-19 23-Dec-19 4 days

CHECK LIST
vi PEMBESIAN

PILE CAP & TIE BEAM 20-Dec-19 24-Dec-19 5 days

PLAT 22-Dec-19 25-Dec-19 4 days

COR 27-Dec-19 27-Dec-19 1 days

vii KOLOM

PEMBESIAN 28-Dec-19 29-Dec-19 4 days

BEKISTING 28-Dec-19 29-Dec-19 2 days

Jakarta, 16 Desember 2019


Dibuat Oleh,