6 Plasteran Dinding
221.4 2 442.8 m2
7 Plasteran trasram
36.9 2 34.9 34.9 m2
8 kolom Tinggi Jumlah Lebar pajang
kolom 3 19 0.2 0.2 2.28
83.36 m2
83.36 m2
PROYEK KANTOR ARSIP DAN PERPUSTAKAAN
KOLOM
Begel 0.006 0.22 0.150 167 25.000 110.220 24.474 10.00
1 0.200 0.200 0.012 0.89 25.000 - - 86.152
K 20/20
0.010 0.62 4 25.000 100.000 61.679
Sloof 0.006 0.22 0.150 134 20.000 101.840 22.613 5.00
2 0.200 0.250 0.012 0.89 0 20.000 - - 71.956
K 20/25
0.010 0.62 4 20.000 80.000 49.343
Begel 0.006 0.22 0.150 178 26.667 117.480 26.086 13.33
3 0.150 0.250 0.010 0.62 0 26.667 - - 91.876
K 15/25
0.010 0.62 4 26.667 106.667 65.790
BALOK
Begel 0.006 0.22 0.150 223 33.333 124.880 27.729 13.33
1 0.150 0.200 0.010 0.62 0 33.333 - - 109.967
balok Latai
0.010 0.62 4 33.333 133.333 82.238
0.63%
1.26%
0.79%
0.63%
0.84%
1.05%
1.28%
2.18%
0.98%
2.03%
0.96%
1.75%
tabel Besi
uk bsi vi r r pjng bd berat
Besi 06 3.14 0.003 0.003 12 7850 2.662092
Besi 8 3.14 0.004 0.004 12 7850 4.732608
Besi 10 3.14 0.005 0.005 12 7850 7.3947
Besi 12 3.14 0.006 0.006 12 7850 10.648368
contoh
Sloof 1.845
Besi 8 41.721 8.816 btg
Besi 10 91.038 12.311 btg
450.08
31.28
Perencanaan rumah tinggal 2 lantai || 2015
URAIAN VOLUME PEKERJAAN BETON
50
STROUS O 30 cm
Panjang = 14.1542817 m1
T.pokok = 52.381 kg
0.01 0.617
Begel = 19.74 kg
0.006 0.222
Total 1m3 = 72.1180952 kg 273.17
Terbilang : Tiga Ratus Enam Puluh Delapan Juta Enam Puluh Empat Ribu Rupiah
Drs. H. AH NASUTION
Direktur
433,636,171 1,424,922
236,538,171 54.5476108 %
RINCIAN SATUAN PEKERJAAN
I PEKERJAAN PERSIAPAN
1 Uetset, Pembersihan Lokasi, dan Pemasangan Bowplank 1.000 Ls Rp 500,000.00 Rp 500,000.00
2 Pasang Papan Nama Kegiatan 1.000 Ls Rp 350,000.00 Rp 350,000.00
Rp 850,000.00
II PEKERJAAN TANAH
1 Urugan Pasir bawah lantai 7.200 M3 Rp 211,400.00 Rp 1,522,080.00
2 Urugan Tanah Bawah Lantai 7.200 M3 Rp 127,400.00 Rp 917,280.00
Rp 2,439,360.00
III PEKERJAAN PASANGAN & PLESTERAN
1 Pasangan dinding trassram 1Pc : 3Ps 36.900 M2 Rp 187,190.00 Rp 6,907,311.00
2 Pasangan dinding bata merah 1Pc : 5Ps 221.400 M2 Rp 155,010.00 Rp 34,319,214.00
3 Plesteran dinding trassram 1Pc : 3PS 34.900 M2 Rp 110,972.00 Rp 3,872,922.80
4 Plesteran dinding bata merah 1Pc : 5PS 442.800 M2 Rp 93,218.00 Rp 41,276,930.40
5 Acian Dinding 477.700 M2 Rp 58,450.00 Rp 27,921,565.00
Rp 114,297,943.20
IV PEKERJAAN BETON
1 Sloof uk. 20x25 Cm 1.845 M3 Rp 2,723,307.62 Rp 5,024,502.56
2 Kolom 20x20 Cm 2.280 M3 Rp 2,723,307.62 Rp 6,209,141.37
3 Ring Balk 15x20 Cm 1.107 M3 Rp 2,723,307.62 Rp 3,014,701.53
Rp 14,248,345.46
V PEKERJAAN PEMBESIAN
1 Sloof uk. 20x25 Cm 132.758 Kg Rp 23,087.00 Rp 3,064,990.17
2 Kolom 20x20 Cm 196.427 Kg Rp 23,087.00 Rp 4,534,907.10
3 Ring Balk 15x20 Cm 121.733 Kg Rp 23,087.00 Rp 2,810,455.67
Rp 10,410,352.95
Rp 147,816,971.61
VI PEKERJAAN BEGESTING
1 Sloof uk. 20x25 Cm 18.450 M2 Rp 87,000.00 Rp 1,605,150.00
2 Kolom 20x20 Cm 30.400 M2 Rp 87,000.00 Rp 2,644,800.00
3 Ring Balk 15x20 Cm 14.760 M2 Rp 89,500.00 Rp 1,321,020.00
Rp -
Rp 5,570,970.00
XI PEKERJAAN PLAFOND Rp -
1 Rangka Hollow 83.360 M2 Rp 127,070.00 Rp 10,592,555.20
2 Pasangan calsiboard 83.360 M2 Rp 80,995.00 Rp 6,751,743.20
Rp 17,344,298.40
1m Bor Stouse
A TENAGA
Pekerja L.01 OH 0.250 Rp 100,000 Rp 25,000.00
Mandor L.04 0.125 Rp 140,000 Rp 17,500.00
JUMLAH TENAGA KERJA Rp 42,500.00
B BAHAN
JUMLAH BAHAN
C PERALATAN
Sewa Bor Strouse Hari 0.042 Rp 25,000 Rp 1,050.00
JUMLAH PERALATAN Rp 1,050.00
D Jumlah (A+B+C) 0% x D Rp 43,550.00
E OverHead & Profit )%
F Harga Satuan Pekerjaan (D+E) Rp 43,550.00
Pemasangan 1 M2 Dinding Bata Merah (5x11x22) cm tbl,1/2 Bata Campuran 1SP : 3PP
A TENAGA
Pekerja L.01 OH 0.300 Rp 100,000 Rp 30,000.00
Tukang Batu L.02 OH 0.100 Rp 130,000 Rp 13,000.00
Kepala Tukang Batu L.03 OH 0.010 Rp 130,000 Rp 1,300.00
Mandor L.04 OH 0.015 Rp 140,000 Rp 2,100.00
JUMLAH TENAGA KERJA Rp 46,400.00
B BAHAN
Bata Merah Bh 70.000 Rp 500 Rp 35,000.00
Sement Portland kg 14.370 Rp 7,000 Rp 100,590.00
Pasir Pasang m3 0.040 Rp 130,000 Rp 5,200.00
JUMLAH BAHAN Rp 140,790.00
C PERALATAN
JUMLAH PERALATAN
D Jumlah (A+B+C) 0% x D Rp 187,190.00
E OverHead & Profit )%
F Harga Satuan Pekerjaan (D+E) Rp 187,190.00
Pemasangan 1 M2 Dinding Bata Merah (5x11x22) cm tbl,1/2 Bata Campuran 1SP : 5PP
A TENAGA
Pekerja L.01 OH 0.300 Rp 100,000 Rp 30,000.00
Tukang Batu L.02 OH 0.100 Rp 130,000 Rp 13,000.00
Kepala Tukang Batu L.03 OH 0.010 Rp 130,000 Rp 1,300.00
Mandor L.04 OH 0.015 Rp 140,000 Rp 2,100.00
JUMLAH TENAGA KERJA Rp 46,400.00
B BAHAN
Bata Merah Bh 70.000 Rp 500 Rp 35,000.00
Sement Portland kg 9.680 Rp 7,000 Rp 67,760.00
Pasir Pasang m3 0.045 Rp 130,000 Rp 5,850.00
JUMLAH BAHAN Rp 108,610.00
C PERALATAN
JUMLAH PERALATAN
D Jumlah (A+B+C) 0% x D Rp 155,010.00
E OverHead & Profit )%
F Harga Satuan Pekerjaan (D+E) Rp 155,010.00
Pemasangan 1 M2 Dinding Bata Merah (5x11x22) cm tbl,1 Bata Campuran 1SP : 5PP
A TENAGA
Pekerja L.01 OH 0.600 Rp 100,000 Rp 60,000.00
Tukang Batu L.02 OH 0.200 Rp 130,000 Rp 26,000.00
Kepala Tukang Batu L.03 OH 0.020 Rp 130,000 Rp 2,600.00
Mandor L.04 OH 0.030 Rp 140,000 Rp 4,200.00
JUMLAH TENAGA KERJA Rp 92,800.00
B BAHAN
Bata Merah Bh 140.000 Rp 500 Rp 70,000.00
Sement Portland kg 22.200 Rp 7,000 Rp 155,400.00
Pasir Pasang m3 0.102 Rp 130,000 Rp 13,260.00
JUMLAH BAHAN Rp 238,660.00
C PERALATAN
JUMLAH PERALATAN
D Jumlah (A+B+C) 0% x D Rp 331,460.00
E OverHead & Profit )%
F Harga Satuan Pekerjaan (D+E) Rp 331,460.00
Pemasangan 1 M2 Acian
A TENAGA
Pekerja L.01 OH 0.200 Rp 100,000 Rp 20,000.00
Tukang Batu L.02 OH 0.100 Rp 130,000 Rp 13,000.00
Kepala Tukang Batu L.03 OH 0.010 Rp 130,000 Rp 1,300.00
Mandor L.04 OH 0.010 Rp 140,000 Rp 1,400.00
JUMLAH TENAGA KERJA Rp 35,700.00
B BAHAN
Sement Portland Kg 3.250 Rp 7,000 Rp 22,750.00
JUMLAH BAHAN Rp 22,750.00
C PERALATAN
JUMLAH PERALATAN
D Jumlah (A+B+C) 0% x D Rp 58,450.00
E OverHead & Profit )%
F Harga Satuan Pekerjaan (D+E) Rp 58,450.00
Pemasangan 1 M2 Calsiboard
A TENAGA
Pekerja L.01 OH 0.100 Rp 100,000 Rp 10,000.00
Tukang Batu L.02 OH 0.050 Rp 130,000 Rp 6,500.00
Kepala Tukang Batu L.03 OH 0.005 Rp 130,000 Rp 650.00
Mandor L.04 OH 0.005 Rp 140,000 Rp 700.00
JUMLAH TENAGA KERJA Rp 17,850.00
B BAHAN
Calsiboard tb. 4 mm Lbr 0.347 Rp 175,000 Rp 60,725.00
Paku skrup Kg 0.110 Rp 22,000 Rp 2,420.00
JUMLAH BAHAN Rp 63,145.00
C PERALATAN
JUMLAH PERALATAN
D Jumlah (A+B+C) 0% x D Rp 80,995.00
E OverHead & Profit )%
F Harga Satuan Pekerjaan (D+E) Rp 80,995.00
Pengecatan 1 m2 tembok baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup) Exterior
A TENAGA
Pekerja L.01 OH 0.020 Rp 100,000 Rp 2,000.00
Tukang Batu L.02 OH 0.063 Rp 130,000 Rp 8,190.00
Kepala Tukang Batu L.03 OH 0.0063 Rp 130,000 Rp 819.00
Mandor L.04 OH 0.003 Rp 140,000 Rp 420.00
JUMLAH TENAGA KERJA Rp 11,429.00
B BAHAN
Plamir Kg 0.100 Rp 20,000 Rp 2,000.00
Cat Dasar Kg 0.100 Rp 25,000 Rp 2,500.00
Cat Penutup Kg 0.260 Rp 25,000 Rp 6,500.00
JUMLAH BAHAN Rp 11,000.00
C PERALATAN
JUMLAH PERALATAN
D Jumlah (A+B+C) 0% x D Rp 22,429.00
E OverHead & Profit )%
F Harga Satuan Pekerjaan (D+E) Rp 22,429.00
1 Mandor OH Rp 140,000
2 Kepala Tukang Batu OH Rp 130,000
3 Kepala Tukang Besi OH Rp 130,000
4 Kepala Tukang Cat OH Rp 130,000
5 Kepala Tukang Kayu OH Rp 130,000
6 Kepala Tukang Listrik OH Rp 130,000
7 Tukang Batu OH Rp 130,000
8 Tukang Besi OH Rp 130,000
9 Tukang Cat OH Rp 130,000
10 Tukang Kayu OH Rp 130,000
11 Tukang Listrik OH Rp 130,000
12 Pekerja OH Rp 100,000
DAFTAR HARGA BAHAN
NO URAIAN SATUAN HARGA SATUAN KET
(Rp.)