A.

Opname Mandor Safingi (Sub Kon Gedung) :

1 Material dan Upah (100%)


Ukuran gedung : 12 m x 9 m @ 2,5jt 108 m2 x 2,500,000 = 270,000,000

2 Kontrak Sub Kon Safingi 80% x 270,000,000 = 216,000,000


Retensi 20% dr Kontrak Subkon 432,000,000

Retensi 20% x 216,000,000 = 43,200,000

Kontrak netto - rettensi = 172,800,000

3 Kas bon dan Opame pekerja :


Opname ke-1 dibayar 35% x 270,000,000 = 94,500,000
Kas bon dan Opame pekerja :
5-Sep Ke-1 4,000,000 = 125,565,000
13-Sep Ke-2 15,000,000
26-Sep Ke-3 9,044,000
26-Sep Ke-4 10,000,000
6-Oct Ke-5 15,000,000
9-Oct Ke-6 30,193,200
12-Oct Ke-7 15,000,000
3-Nov Ke-8 6,989,300
3-Nov Ke-9 20,338,500

Kas bon material :


5-Sep ke-1 24,992,500 = 41,263,556
17-Nov Ke-2 10,633,500
10-Nov ke-3 840,000
10-Nov ke-4 900,000
10-Nov ke-5 3,897,556
Total opn + kasbon material 166,828,556

Sisa opname = 5,971,444