Anda di halaman 1dari 1

TIME SCHEDULE (KONTRAK) TIME SCHEDULE (ADDENDUM)

KEGIATAN :
PEKERJAAN : PEMBANGUNAN LAPANGAN PARKIR LAPANGAN SPORT CENTER DAN RUMAH SUSUN MIMIKA
TAHUN ANGGARAN : 2019-2020
LOKASI : KABUPATEN MIMIKA
WAKTU PELAKSANAAN
KONTRAK AWAL
JANUARI FEBRUARI MARET KONTRAK BOBOT (%) APRIL MEI JUNI JULI KETERAN
NO JENIS PEKERJAAN Mg 1 Mg 2 Mg 3 Mg 4 Mg 5 Mg 6 Mg 7 Mg 8 Mg 9 Mg 10 Mg 11 Mg 12 Mg 13 ADDENDUM/CCO PRESTASI Mg 14 Mg 15 Mg 16 Mg 17 Mg 18 Mg 19 Mg 20 Mg 21 Mg 22 Mg 23 Mg 24 Mg 25 Mg 26 Mg 27 Mg 28 Mg 29 Mg 30 Mg 31 GAN
VOLUME BOBOT 30-Des 06-Jan 13-Jan 20-Jan 27-Jan 03-Feb 10-Feb 17-Feb 24-Feb 02-Mar 09-Mar 16-Mar 23-Mar
VOLUME
30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-Mei 11-Mei 18-Mei 25-Mei 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul
BOBOT (%) REALISASI SISA
05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 01-Mar 08-Mar 15-Mar 22-Mar 29-Mar 05-Apr 12-Apr 19-Apr 26-Apr 03-Mei 10-Mei 17-Mei 24-Mei 31-Mei 07-Jun 14-Jun 21-Jun 28-Jun 05-Jul 12-Jul 19-Jul 26-Jul 31-Jul
(0,00)
A. PEKERJAAN PENDAHULUAN/PERSIAPAN 1,01% 0,000 0,001 0,001 0,001 0,000 0,000 0,000 0,000 0,000 - 0,000 0,001 1,006% 0,631% 0,376% 0,021% 0,021% 0,021% 0,021% 0,021% 0,021% 0,021% 0,021% 0,021% 0,021% 0,021% 0,021% 0,021% 0,021% 0,021% 0,021% 0,021% 0,021%

1 Pembersihan Lokasi 1,00 Ls 0,137% 1,00 Ls 0,137% 0,137% 0,000% 0,00% 0,00% 100,00%
2 Bangsal Kerja 1,00 Ls 0,068% 1,00 Ls 0,068% 0,068% -
3 Pengukuran/Pasangan Bouplan 1,00 Ls 0,046% 1,00 Ls 0,046% 0,046% -
96,71%

4 Pembuatan Papan Nama Proyek 1,00 Ls 0,005% 1,00 Ls 0,005% 0,005% -


5 Managemen Keselamatan dan Kesehatan Kerja 1,00 Ls 0,728% 1,00 Ls 0,728% 0,364% 0,364% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02%

6 Administrasi/Dan Dokumentasi 1,00 Ls 0,023% 1,00 Ls 0,023% 0,011% 0,011% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%

B. PEKERJAAN TANAH DAN PASIR - 60,79% 0,00% 0,00% 0,00% 0,80% 1,98% 3,17% 4,27% 5,36% 6,44% 7,64% 7,34% 6,27% 5,20% 67,107% 48,818% 18,356% 0,445% 0,886% 1,326% 1,779% 2,220% 2,654% 2,521% 2,081% 1,667% 1,247% 0,806% 0,366% 0,213% 0,060% 0,040% 0,020% 0,000% 0,000%

1 Galian Tanah 331,20 M3 0,44% 0,000% 86,22%


2 Urugan Tanah Kembali 82,80 M3 0,01% 0,000%
1 2 3 4 5 6 5 4 3 2 1
3 Timbunan Biasa 14.286,30 M3 36,73% 16.352,07 M3 42,046% 31,719% 10,327% 0,29% 0,57% 0,86% 1,15% 1,43% 1,72% 1,43% 1,15% 0,86% 0,57% 0,29%

1 2 3 4 5 6 7 6 5 4 3 2 1

4 Pemadatan Tanah 14.286,30 M3 18,97% 16.352,07 M3 21,709% 15,173% 6,536% 0,13% 0,27% 0,40% 0,53% 0,67% 0,80% 0,93% 0,80% 0,67% 0,53% 0,40% 0,27% 0,13%

5 Urugan Pasir Bawah Pondasi 33,12 M3 0,09%

- Saluran 24,82 M3 0,066% 0,053% 0,013% 0,00% 0,00% 0,00% 0,00% 0,00%

- Talud 25,55 M3 0,068% 0,068% 0,01% 0,01% 0,01% 0,01% 0,01%

- Pondasi Pagar Depan 9,80 M3 0,026% 0,000% 0,026%


1 2 3 4 5 6 7 6 7 7 6 5 4 3 2 1
6 Urugan Pasir Bawah Lantai (Paving Blok) 1.710,00 M3 4,55% 1.200,00 M3 3,193% 1,820% 1,373% 0,02% 0,04% 0,06% 0,08% 0,10% 0,12% 0,14% 0,12% 0,14% 0,14% 0,12% 0,10% 0,08% 0,06% 0,04% 0,02%

C. PEKERJAAN PAS. BATU DAN PLESTERAN - 3,40% 0,00% 0,00% 0,00% 0,00% 0,00% 0,05% 0,11% 0,16% 0,22% 0,27% 0,33% 0,38% 0,38% 3,495% 1,751% 1,744% 0,159% 0,159% 0,239% 0,257% 0,257% 0,257% 0,222% 0,143% 0,051% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000%

1 Pasangan Batu Kali 1:5 371,00 M3 3,08%


61,95%
- Pekerjaan Saluran - 162,25 M3 1,347% 1,140% 0,207% 0,03% 0,03% 0,03% 0,03% 0,03% 0,03%

- Pekerajaan Talud - 48,00 M3 0,398% 0,398% 0,08% 0,08% 0,08% 0,08% 0,08%

- Pondasi Pagar Depan - 70,00 M3 0,581% 0,581% 0,000%


54,65%
- Plesteran Saluran 1:3 - 695,75 M2 0,618% 0,030% 0,588%
52,37% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07%

- Plesteran Talud 1:4 (sisi Luar) - 100,80 M2 0,090% 0,090% 0,02% 0,02% 0,02% 0,02% 0,02%
52,39%
2 Pasangan Batu Plesteran 1:4 113,15 M2 0,32%

- Pasangan Batu Tela +Plestera (diatas saluran) 161,55 M2 0,461% 0,461% 0,05% 0,05% 0,05% 0,05% 0,05% 0,05% 0,05% 0,05% 0,05%

D. PEKERJAAN PLESTERAN 1:2 DAN PENGECATAN 0,15% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 1,463% 0,000% 1,463% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,044% 0,089% 0,133% 0,178% 0,251% 0,236% 0,221% 0,177% 0,103% 0,029%

1 Plesteran Balok Kansten 1:2 113,16 M2 0,12%


- Plesteran Kansteen 1:2 1.081,47 M2 1,111% 1,111% 0,00% 0,00% 0,00% 0,00% 0,04% 0,09% 0,13% 0,18% 0,22% 0,18% 0,13% 0,09% 0,04%

2 Pengecatan Balok Cansten 113,16 M2 0,04% 28,67%


- Pengecatan Kanstern 1.081,47 M2 0,352% 0,352% 0,03% 0,06% 0,09% 0,09% 0,06% 0,03%

E. PEKERJAAN PASANGAN PAVING BLOCK 30,40% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,54% 1,09% 1,63% 21,333% 1,520% 19,813% 0,275% 0,550% 0,826% 1,101% 1,376% 1,651% 1,926% 2,201% 2,201% 1,926% 1,651% 1,376% 1,101% 0,826% 0,550% 0,275% 0,000% 0,000%
1,00 2,00 3,00 4,00 5,00 6,00 7,00 8,00 8,00 7,00 6,00 5,00 4,00 3,00 2,00 1,00
1 Pek.Pasangan Paving Block untuk Parkir 17.100,00 M2 30,40% 12.000,00 M2 21,333% 1,520% 19,813% 0,28% 0,55% 0,83% 1,10% 1,38% 1,65% 1,93% 2,20% 2,20% 1,93% 1,65% 1,38% 1,10% 0,83% 0,55% 0,28%

F. PEKERJAAN PLAT BETON 3,72% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 23,15%
0,00% 0,00% 0,00% 0,00% 0,00% 5,077% 0,000% 5,077% 0,000% 0,000% 0,081% 0,328% 0,328% 0,247% 0,354% 0,214% 0,320% 0,427% 0,534% 0,641% 0,534% 0,427% 0,320% 0,214% 0,107% 0,000%

1 Pek.Pengecoran Beton Bertulang 1:2:3 76,00 M3 3,72%


Pengecoran Plat beton Bertulang (ramp/Jalan
- 20,19 M3 0,987% 0,987% 0,25% 0,25% 0,25% 0,25%
Masuk)
- Pengecoran Slof Bertulang Pagar depan 9,94% 5,00 M3 0,244% 0,244% 0,08% 0,08% 0,08%

- Pemasangan Kansten Beton 1:2:3 1.966,30 M' 3,845% 3,845% 0,001068159 0,002136319 0,003204478 0,004272638 0,005340797 0,006408957 0,005340797 0,004272638 0,003204478 0,002136319 0,001068159

G. PEK. PASANGAN PIPA PEMBUANGAN 0,49% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,02% 0,05% 0,07% 0,09% 0,09% 0,07% 0,05% 0,473% 0,237% 0,237% 0,030% 0,030% 0,030% 0,030% 0,030% 0,030% 0,030% 0,030% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000%

1 Pasangan Pipa PVC 2 Inc-2,5 Inc 560,00 m' 0,47% 560,00 m' 0,473% 0,237% 0,237% 0,03% 0,03% 0,03% 0,03% 0,03% 0,03% 0,03% 0,03%
3,10%
2 Pasangan Pipa L 2 inc-2,5 Inc 4,00 Bh 0,00% 4,00 Bh
0,00%
3 Pasangan Bak Kontrol 10,00 Bh 0,02%
H. PEKERJAAN AKHIR 0,05% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,046% 0,000% 0,046% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,023% 0,023%

1 Pembersihan Akhir 1,00 Ls 0,05% 1,00 Ls 0,046% 0,046% 0,02% 0,02%

TOTAL 100,00%

MINGGUAN/BULANAN 0,00% 0,0% 0,1% 0,1% 0,9% 2,0% 3,3% 4,4% 5,6% 6,8% 8,0% 8,3% 7,9% 7,3% 100,000% 52,956% 47,044% 0,9% 1,6% 2,5% 3,5% 4,2% 4,9% 5,1% 4,7% 4,3% 3,7% 3,1% 2,6% 2,1% 1,6% 1,2% 0,71% 0,25% 0,07%
PROGRESS RENCANA
KOMULATIF MINGGUAN/BULANAN 0,00% 0,02% 0,11% 0,22% 1,08% 3,10% 6,35% 10,78% 16,38% 23,15% 31,17% 39,48% 47,34% 54,65% CATATAN : 52,956% 53,89% 55,53% 58,05% 61,57% 65,80% 70,66% 75,73% 80,42% 84,73% 88,44% 91,58% 94,16% 96,28% 97,85% 99,01% 99,71% 99,97% 100,0%
:
MINGGUAN/BULANAN 0,00% 0,33% 0,66% 1,98% 2,64% 3,29% 3,95% 4,61% 5,27% 5,93% 6,59% 5,93% 5,27% 5,93% Rencana
REALISASI
KOMULATIF MINGGUAN/BULANAN 0,00% 0,33% 0,99% 2,97% 5,60% 8,90% 12,85% 17,46% 22,73% 28,67% 35,26% 41,19% 46,46% 52,39%

DEVIASI 0,00% 0,31% 0,88% 2,74% 4,52% 5,80% 6,50% 6,68% 6,36% 5,51% 4,09% 1,71% -0,88% -2,27%

Timika, 25 Maret 2020


DIKETAHUI/DISETUJUI OLEH DKETAHUI OLEH DKETAHUI OLEH DIPERIKSA OLEH Dibuat Oleh
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN RUANG (PUPR)
KEPALA BIDANG CIPTA KARYA PEJABAT PELAKSANA TEKNIS KEGIATAN (PPTK) Konsultan Pengawas Kontraktor Pelaksana
PROVINSI PAPUA
Selaku Pejabat Pembuat Komitmen (PPK) PT.INDOPAPUA

GORIUS ONE YOMAN ,S.Pd, M,Si RISLIANA PANGGOA, ST., MT ARDILES GERDEN, ST ………………………………………… BUDY SULTAN,ST
Nip. 19760314 301112 1 007 NIP. 19751010 200212 2 010 Nip. 19880608 201104 1 002 ………………………………. Direktur

Anda mungkin juga menyukai