Catatan Cuaca :
NO RENCANA KEGIATAN BESOK
22101112010214 CERAH
1 Pembersihan dan Penurunan Atap Lama
2 Pasang Flashing GDS 2
21 09 03 15 MENDUNG
08 04
20 070605 16 HUJAN
19 18 17
CATATAN: 1. Sementara tidak ada bongkar pasang sampai GDS memberi izin
( ) (RONALD P.)
SPV Pasang Site Manager Mandor Project Manager
MAPPING
GEDUNG D
Pembongkaran Atap
Tanggal ML M² MP Mandor
03/08/2020 7 165,41 12
05/08/2020 18 384,03 15
06/08/2020 6 128,01 7 Udin
07/08/2020 12 256,02 12
08/08/2020 12 256,02 14
11/08/2020 6 128,01 13
12/08/2020 12 256,02 14
Pemasangan Atap
QTY
Tanggal M² MP Mandor
(pcs)
04/08/2020 6 173,47 10
05/08/2020 16 417,66 15
06/08/2020 6 156,62 7
Udin
07/08/2020 11 287,14 12
08/08/2020 12 313,29 14
11/08/2020 6 156,62 13
12/08/2020 11 287,14 14
EVALUASI PRODUKTIVITAS PEMASANGAN
Total Terpasang
Total Terpasang Total MP Roof & Total Terpasang
Udin Total MP Flashing Total MP
No Tanggal Roof & Clading Clading Flashing
Roof Clading Flashing
(M²) MP (M²) MP (ML) MP (M²) MP (ML) MP MP
1 04/08/2020 173,47 10 173,47 10 10
2 05/08/2020 417,66 15 417,66 15 15
3 06/08/2020 156,62 7 156,62 7 7
4 07/08/2020 287,14 12 287,14 12 12
5 08/08/2020 313,29 14 313,29 14 14
6 11/08/2020 156,62 13 156,62 13 13
7 12/08/2020 287,14 14 287,14 14 14