FORMULIR
Tanggal Terbit : 29 Juni 2020
PT PLN (PERSERO) Revisi : 00
UNIT PELAKSANA PROYEK RISALAH RAPAT
JAWA BAGIAN TENGAH 3 Halaman : 1

Hari/ Tanggal : Jumat / 04 Juni 2021


Waktu : 15.00 WIB s.d. Selesai
Tempat : Zoom Meeting
Agenda : Rapat Koordinasi Pekerjaan SUTET 500 kV TX (Mandirancan) – PLTU Indramayu

NO PEMBAHASAN PIC TARGET KET

1. Progress s.d 2 Juni 2021 KSO MSJ 31-Jul-21 OPEN


Plan Kurva S : 100,000%
Aktual : 93,283% (94,272%)
Deviasi : - 6,712% (5,726%)

A. Pekerjaan Stringing
• Tarikan 1 (T.205-187: 18 span) KSO MSJ 4-Jul-21 OPEN
Stringing (T.194-204) : 100%
Sagging (T.194-204) : 100%
Clamping (T.194-204) : 100%
Spacer (T.194-204) : 100%
Jumper (T.202, 203) : 100%

Remaining:
Stringing (T.204-205L) : 0%
Sagging (T.187-194, 204-205L) : 0%
Clamping (T.187-194, 205L) : 0%
Spacer (T.187-194, 204-205) : 0%
Jumper (T.194, 204, 205) : 0%

• Tarikan 2 (T.080-059: 22 span) KSO MSJ 4-Jul-21 OPEN


Stringing : 100%
Sagging (T.058-072) : 100%
Clamping (T.058-072) : 100%
Spacer (T.058-072) : 100%

Remaining:
Sagging (T.072-080) : 0%
Clamping (T.072-080) : 0%
Spacer (T.072-080) : 0%
Jumper (T.058, 072) : 0%

Note:
1. Pekerjaan Remaining Sagging, Clamping dan Spacer pada section
tarikan 1 dan 2 menunggu Stringing pada section tarikan 3 (T.080 –
T.111) dan 7 (T.161 – T.187) selesai
2. On going pekerjaan
Langsir:
a. T.205L (Erection Basis 20%, Progres Erection 5%, MP: 15 org)
No. Dokumen : F-UIPJBT2-A-06-03
FORMULIR
Tanggal Terbit : 29 Juni 2020
PT PLN (PERSERO) Revisi : 00
UNIT PELAKSANA PROYEK RISALAH RAPAT
JAWA BAGIAN TENGAH 3 Halaman : 2

• Tarikan 3 (T.80-T.111: 31 span)

ROW Finish : 31/31 span (100%)


Pondasi Finish : 31/31 tower (100%) KSO MSJ 31-Jul-21 OPEN
Erection Finish : 31/31 tower (100%)
Pemasangan Insulator Finish : 31/31 tower (100%)
Finish : 0/31 span
Bush Clearing
On Going :-
Finish : 6/6 titik (Line GSW), 6/6 (Line OPGW) 100%
Steger
On Going :-
Finish : 24/31 tower (T.081, 082, 083, 084, 086,
087, 088, 089, 090, 091, 092, 093, 094, 095, 096, 097, 101,
Revisi Tower 103, 106, 107, 108, 109, 110, 111)
On Going : T.085 (idle), 098, 099, 100 (idle), 102 (idle)
Remaining : T.104, 105
Finish : 18/31 tower
On Going : -
Final Check
Remaining : T.096, 097, 098, 099, 100, 101, 102, 103,
104, 105, 106, 110
Montage Roll Finish : 31/31 tower (100%)
Mobilisasi Konduktor Finish : 28/180 haspel
OPGW =-
GSW = 100%
Line OPGW
Line GSW
Top = 100%
Stringing Konduktor Top = 100%
Middle = Pilot Rope
Middle =-
Ø22mm (T.111-082)
Bottom =-
Bottom =-
GSW =- OPGW =-
Line GSW Line OPGW
Sagging & Clamping Top =- Top =-
Middle =- Middle =-
Bottom =- Bottom =-
Line GSW Line OPGW
Top =- Top =-
Spacer & Damper
Middle =- Middle =-
Bottom =- Bottom =-

Note:
1. KSO MSJ menyediakan 4 tim revisi tower khusus tarikan 3 pada tanggal
21 Mei 2021. (T.85, 101,102,100)
2. Status pekerjaan Stringing on going menggunakan mesin 1
(Zeck Sumbagsel)
3. Material OPGW dipinjam UPP JBT 4 Semarang 2 Haspel @4000 m (LS
Cable), rencana pengembalian paling lambat tanggal 12 Juni 2021 ke
gudang Arjawinangun.
4. Tim Stringing datang tanggal 19 Mei 2021 (MP: 57 orang) (T.88 S/D
R.GSW 83-84)
5. Pemasangan stegger span 102-103 perlu segera direvisi
No. Dokumen : F-UIPJBT2-A-06-03
FORMULIR
Tanggal Terbit : 29 Juni 2020
PT PLN (PERSERO) Revisi : 00
UNIT PELAKSANA PROYEK RISALAH RAPAT
JAWA BAGIAN TENGAH 3 Halaman : 3

KSO MSJ 27-Jun-21 OPEN


• Tarikan 4 (T.051 - T.058: 8 span)

ROW Finish : 8/8 span


Pondasi Finish : 8/8 tower
Erection Finish : 8/8 tower
Pemasangan Insulator Finish : 8/8 tower
Finish : 0/8 span
Bush Clearing
Remaining : -
Steger Finish : 0/4 titik
Finish : 2/8 tower (T.057, 058)
Revisi Tower On Going : T.051, 052, 053, 054, 055, 056
Remaining : -
Finish : 2/8 tower (T.057, 058)
Final Check On Going :-
Remaining : T.051, 052, 053, 054, 055, 056
Finish : 6/8 tower (T.052, 052, 054, 055, 057, 058)
Montage Roll On Going :-
Remaining : T.053, 056
Pemasangan Vangnet 0/1 Set (T.056 – T.057)
Mobilisasi Konduktor Finish : 0/40 haspel
GSW =- OPGW =-
Line GSW Line OPGW
Stringing Konduktor Top =- Top =-
Middle =- Middle =-
Bottom =- Bottom =-
GSW =- OPGW =-
Line GSW Line OPGW
Sagging & Clamping Top =- Top =-
Middle =- Middle =-
Bottom =- Bottom =-
Line GSW Line OPGW
Top =- Top =-
Spacer & Damper
Middle =- Middle =-
Bottom =- Bottom =-

Note:
1. Diperlukan percepatan revisi tower dan Final Check yang harus sudah
selesai pada 14 Juni 2021
2. Rencana Stringing menggunakan mesin 3 (Tim Pak Sahlan) dengan
jadwal mobilisasi alat ke lapangan pada 15 Juni 2021
3. Tim Stringing tiba di lapangan pada 25 Mei 2021 (MP: 40 orang)
4. KSO MSJ akan segera menyampaikan metode kerja pemasangan
vangnet kepada PLN UPP JBT 3 pada tanggal 5 Juni 2021.
5. Dijadwalkan untuk pekerjaan instalasi Vangnet di span T.056-057
dimulai pada tanggal 8 Juni 2021.
6. Pemasangan montage roll di T.053 & 056 dimulai pada tanggal 6 Juni
2021
7. Jadwal start Stringing pada 15 Juni 2021.
No. Dokumen : F-UIPJBT2-A-06-03
FORMULIR
Tanggal Terbit : 29 Juni 2020
PT PLN (PERSERO) Revisi : 00
UNIT PELAKSANA PROYEK RISALAH RAPAT
JAWA BAGIAN TENGAH 3 Halaman : 4

KSO MSJ 20-Jun-21 OPEN


• Tarikan 5 (T.019 - T.036: 17 span)

ROW Finish : 17/17 span (100%)


Pondasi Finish : 17/17 tower (100%)
Erection Finish : 17/17 tower (100%)
Finish : 16/17 tower
Pemasangan Insulator
On going : T.020 (3/6)
Finish : 3/17 span (T.033-034, 034-035, 035-036)
Bush Clearing
Remaining :-
Steger Finish : 5/5 titik (100%)
Revisi Tower Finish : 17/17 tower (100%)
Final Check Finish : 17/17 tower (100%)
Montage Roll Finish : 17/17 tower (100%)
Mobilisasi Konduktor Finish : 32/92 haspel
GSW = 100% OPGW = 100%
Line GSW Line OPGW
Top = 100% Top = 100%
Stringing Konduktor
Middle = 100% Middle = 100%
Bottom = Pilot rope Bottom = ACSR (T.036-
T.019-030 024)
GSW = (7/17) 029, OPGW = (11/17) 021,
030, 031, 032, 033, 034, 022, 023, 024, 028, 030,
035. 031, 032, 033, 034, 035.
Sagging & Clamping Line GSW Line OPGW
Top = 5 / 17 tower Top = 6 / 17 tower
Middle =- Middle = 3 / 17 tower
Bottom =- Bottom =-
Line GSW Line OPGW
Top =- Top =-
Instal Spacer
Middle =- Middle =-
Bottom =- Bottom =-

Note:
1. Status pekerjaan Stringing on going menggunakan mesin 2 (Tim Pak
Sahlan)
2. Kontraktor akan segera memasang insulator (3/6) di T.020, Target
selesai tanggal 8 Juni 2021.
3. Kontraktor akan melakukan bush clearing pada span T.033-034 &
T.034-035 mulai 3 Juni 2021
No. Dokumen : F-UIPJBT2-A-06-03
FORMULIR
Tanggal Terbit : 29 Juni 2020
PT PLN (PERSERO) Revisi : 00
UNIT PELAKSANA PROYEK RISALAH RAPAT
JAWA BAGIAN TENGAH 3 Halaman : 5

KSO MSJ 27-Jul-21 OPEN


• Tarikan 6 (T.161 - T.142A : 20 span)

Finish : 19/20 span


ROW
Remaining : 145-146
Pondasi Finish : 20/20 tower (100%)
Finish : 20/20 tower (T.143, 144, 145, 146, 147, 148,
Erection 149, 150, 151, 152, 152A, 153, 154, 155, 156, 157, 158, 159,
160, 161)
Finish : 19/20 tower (T.144, 145, 146, 147, 148, 149,
150, 151, 152, 152A, 153, 154, 155, 156, 157, 158, 159, 160,
Pemasangan Insulator 161)
On going :-
Remaining : 143
Finish : 0/20 span
Bush Clearing
Remaining : -
Finish : 0/5 titik
On going : T.160 – 161
Steger
Remaining : T.159 – 160, 152A – 153, 149 – 150, 144 –
145
Finish : 9/20 tower (T.144, 145, 148, 149, 150, 152,
155, 158, 160)
Revisi Tower On going : T.146, 147 (idle), 151, 153 (idle), 154 (idle),
156 (idle), 157 (idle), 159, 161 (idle)
Remaining : T.143, 152A
Finish : 10/20 tower (T.143, 144, 145, 148, 149, 150,
152, 155, 158, 160)
Final Check
Remaining : T.146, 147, 152, 152A, 153, 154, 156, 157,
159, 161
Finish : 19/20 tower (T.144, 145, 146, 147, 148, 149,
150, 151, 152, 152A, 153, 154, 155, 156, 157, 158, 159, 160,
Montage Roll 161)
On Going :-
Remaining : T.143
Mobilisasi Konduktor Finish : 0/104 haspel
GSW = Pilot rope
OPGW =-
T.144-151 & 152A-161
Line OPGW
Line GSW
Stringing Konduktor Top =-
Top =-
Middle =-
Middle =-
Bottom =-
Bottom =-
GSW =- OPGW =-
Line GSW Line OPGW
Sagging & Clamping Top =- Top =-
Middle =- Middle =-
Bottom =- Bottom =-
Line GSW Line OPGW
Top =- Top =-
Spacer & Damper
Middle =- Middle =-
Bottom =- Bottom =-

Note:
1. On going pekerjaan:
- Persiapan pasang montage roll T.143 dan pasang eret-eret T.161
No. Dokumen : F-UIPJBT2-A-06-03
FORMULIR
Tanggal Terbit : 29 Juni 2020
PT PLN (PERSERO) Revisi : 00
UNIT PELAKSANA PROYEK RISALAH RAPAT
JAWA BAGIAN TENGAH 3 Halaman : 6

2. Diperlukan percepatan revisi tower dan Final Check yang harus sudah
selesai pada 7 Juni 2021
3. KSO MSJ akan menyediakan tim revisi tower sebanyak 6 group (MP: 24
orang)
4. Jadwal start Stringing pada 12 Juni 2021
5. Rencana Stringing menggunakan mesin 4 (Mesin Zeck Ex Gudang
Randugarut). Mesin tensioner sudah dimobilisasi ke lapangan pada
tanggal 2 Juni 2021. Mesin puller akan segera dimobilisasi ke lapangan
setelah persiapan akses masuk selesai.
6. Penyampaian buku tabungan akan dilakukan pada M2 Juni 2021 untuk
ROW span 145-146
No. Dokumen : F-UIPJBT2-A-06-03
FORMULIR
Tanggal Terbit : 29 Juni 2020
PT PLN (PERSERO) Revisi : 00
UNIT PELAKSANA PROYEK RISALAH RAPAT
JAWA BAGIAN TENGAH 3 Halaman : 7

• Tarikan 7 (T.161 - T.187 : 25 span) KSO MSJ 31-Jul-21 OPEN

Finish : 24/25 span


ROW
Remaining : 181-182 (konsinyasi)
Finish : 24/25 tower
Pondasi
Remaining : T.181
Finish : 17/25 (T.165, 166, 167, 169A, 170, 171, 172,
174, 175, 176, 177, 178, 179, 180, 182, 183, 185, 186)
Erection
On going : T.163, 173, 184
Remaining : T.162, 164, 168N, 181
Finish : 14/25 tower (T.165, 166, 167, 172, 174, 175,
176, 178, 179, 180, 182, 183, 185, 186)
Pemasangan insulator
Remaining : T.162, 163, 164, 168N, 169A, 170, 171, 173,
177, 181, 184
Finish : 0/25 span
Bush Clearing
Remaining : -
Finish : 0/5 titik
Steger Remaining : 168N – 169A, 169A – 170, 174 – 175, 180 –
181, 182 – 183
Finish : 4/25 tower (T.176, 178, 185, 186)
Remaining : T.162, 163, 164, 165, 166, 167, 168N, 169A,
Revisi Tower
170, 171, 172, 173, 174, 175, 177, 179, 180, 181, 182, 183,
184
Finish : 4/25 (T.176, 178, 185, 186)
Remaining : T.162, 163, 164, 165, 166, 167, 168N, 169A,
Final Check
170, 171, 172, 173, 174, 175, 177, 179, 180, 181, 182, 183,
184
Finish : 0/25
Montage Roll
Remaining : -
Mobilisasi Konduktor Finish : 0/140 haspel
GSW =- OPGW =-
Line GSW Line OPGW
Stringing Konduktor Top =- Top =-
Middle =- Middle =-
Bottom =- Bottom =-
GSW =- OPGW =-
Line GSW Line OPGW
Sagging & Clamping Top =- Top =-
Middle =- Middle =-
Bottom =- Bottom =-
Line GSW Line OPGW
Top =- Top =-
Spacer & Damper
Middle =- Middle =-
Bottom =- Bottom =-

Note:
1. Ongoing Pekerjaan
Langsir:
a. T.162 (Droping Material tower 50%, Material Onsite 15%,
Progres Erection 0%, MP: 8 org)
b. T.168N (Langsir Material Tower 80%, Progres Erection 0%, MP:
8 org
Erection:
No. Dokumen : F-UIPJBT2-A-06-03
FORMULIR
Tanggal Terbit : 29 Juni 2020
PT PLN (PERSERO) Revisi : 00
UNIT PELAKSANA PROYEK RISALAH RAPAT
JAWA BAGIAN TENGAH 3 Halaman : 8

a. T.163 (Erection Body Ext 95%, Progres Erection 28%, MP: 12


org)
b. T.173 (Sortir Material, Ginpole sudah terinstal, Progres
Erection 0%, MP: 14 org)
c. T.184 (Erection Common Body II 25%, Progres Erection 68%,
MP: 12 org)
2. Pekerjaan langsir T.162 dan T.164 akan diusahakan dilangsir secara
paralel.
3. Tim erection akan mulai bekerja di T.168N tanggal 5 Juni 2021
4. T.181 dijadwalkan mulai dropping & langsir material tower 5 Juni 2021,
mulai Erection pada 8 Juni 2021
5. Semua tower telah selesai Erection pada 17 Juni 2021
6. Diperlukan percepatan revisi tower dan Final Check yang harus sudah
selesai pada 22 Juni 2021
7. KSO MSJ akan menyediakan tim revisi sebanyak 6 group (MP: 24 orang)
8. Tim revisi tower on site 2 tim pada tanggal 1 Juni 2021. Tim revisi
diperbantukan pada tarikan 6 dan tarikan 9.
9. Mobilisasi set alat Stringing ke lapangan dijadwalkan pada 16 Juni 2021
10. Jadwal start Stringing pada 23 Juni 2021
11. Dijadwalkan melakukan uji beton T.181 pada 8 Juni 2021.
12. Status ROW span T.181-182 sudah terbit penetapan konsinyasi dari PN
Indramayu
No. Dokumen : F-UIPJBT2-A-06-03
FORMULIR
Tanggal Terbit : 29 Juni 2020
PT PLN (PERSERO) Revisi : 00
UNIT PELAKSANA PROYEK RISALAH RAPAT
JAWA BAGIAN TENGAH 3 Halaman : 9

• Tarikan 8 (T.036 - T.051 : 15 span) KSO MSJ 31-Jul-21 OPEN

Finish : 13/15 span


ROW
Remaining : T.048 – 049, 049-050 (Konsinyasi)
Pondasi Finish : 15/15 tower (100%)
Finish : 14/15
Erection
Remaining : T.049
Finish : 7/15 tower (T.037, 038, 039, 040, 041, 047,
Pemasangan Insulator 050)
Remaining : T.042, 043, 044, 044A, 045, 046, 048, 049
Finish : 0/15 span
Bush Clearing
Remaining : -
Finish : 0/7 titik
Steger Remaining : T.036 – 037, 038 – 039, 042 – 043, 043 – 044,
044A – 045, 048 – 049, 049 - 050
Finish : 1/15 tower (T.037)
On going : T.038 (idle), 039 (idle), 040 (idle), 041 (idle),
Revisi Tower
043, 044 (idle), 044A (idle), 047 (idle), 048 (idle)
Remaining : T.042, 045, 046, 049, 050
Finish : 1/15 tower (T.037)
Final Check Remaining : T.038, 039, 040, 041, 042, 043, 044, 044A,
045, 046, 047, 048, 049, 050
Finish : 6/15 tower (T.037, 038, 039, 040, 041, 042)
Montage Roll Remaining : T.043, 044, 044A, 045, 046, 047, 048, 049,
050
Pemasangan Vangnet 0/1 set (T.044A-T.045)
Mobilisasi Konduktor Finish : 0/84 haspel
GSW =- OPGW =-
Line GSW Line OPGW
Stringing Konduktor Top =- Top =-
Middle =- Middle =-
Bottom =- Bottom =-
GSW =- OPGW =-
Line GSW Line OPGW
Sagging & Clamping Top =- Top =-
Middle =- Middle =-
Bottom =- Bottom =-
Line GSW Line OPGW
Top =- Top =-
Spacer & Damper
Middle =- Middle =-
Bottom =- Bottom =-

Note:
1. Diperlukan percepatan revisi tower dan Final Check yang harus sudah
selesai pada 14 Juni 2021
2. Tim revisi dan final check direncanakan menggunakan tim pindahan
dari T.80 sampai T.111
3. Rencana Stringing menggunakan mesin 3 (Tim Pak Sahlan – Pindahan
tarikan 4) dengan jadwal mobilisasi alat ke lapangan pada 9 Juli 2021
4. Diperlukan set peralatan tower emergency untuk pemasangan
Vangnet Crossing SUTT 70 kV span T.044A-T.045. Dijadwalkan untuk
pekerjaan instalasi Vangnet pada 25 Juni 2021.
No. Dokumen : F-UIPJBT2-A-06-03
FORMULIR
Tanggal Terbit : 29 Juni 2020
PT PLN (PERSERO) Revisi : 00
UNIT PELAKSANA PROYEK RISALAH RAPAT
JAWA BAGIAN TENGAH 3 Halaman : 10

5. Perlu koordinasi dengan PPK 4.3 PUPR untuk crossing Jalan Nasional
(T.038-T.039)
6. Diperlukan pekerjaan pemasangan vangnet permanen dengan pondasi
untuk Crossing jalan tol span T.042-T.043. Dijadwalkan untuk
pekerjaan tersebut dimulai pada 1 Juni 2021. Tanggal 3 Juni 2021 PLN
akan memastikan WP sudah diapprove oleh LMS
7. KSO MSJ perlu submit design pondasi + struktur vangnet ke Ren Sipil,
dijadwalkan tanggal 2 Juni 2021 akan dilakukan sonding design ke PT
LMS dan Bidang Ren Sipil
8. PLN dan Kontraktor akan menyampaikan metode kerja, syarat teknis,
dan Pengaturan lalu lintas ke LMS pada tanggal 2 Juni 2021
9. UPP JBT 3 bersama KSO MSJ perlu mempersiapkan metode kerja,
syarat teknis untuk disampaikan kepada PT LMS dan PUPR sebagai
syarat izin mendahului dalam rangka status SUTET Mandra sebagai
PSN, paralel pengurusan izin melintas aset BUMN, akan dipastikan
pada rapat pembahasan dengan PUPR, BPJT, & PT LMS Pusat
10. Jadwal start Stringing pada 15 Juni 2021
11. ROW span T.048 – T.050 ditargetkan bebas pada M4 Juni 2021
No. Dokumen : F-UIPJBT2-A-06-03
FORMULIR
Tanggal Terbit : 29 Juni 2020
PT PLN (PERSERO) Revisi : 00
UNIT PELAKSANA PROYEK RISALAH RAPAT
JAWA BAGIAN TENGAH 3 Halaman : 11

• Tarikan 9 (T.001R - T.019 : 20 span) KSO MSJ 31-Jul-21 OPEN

Finish : 18/20 span


ROW
Remaining : T.003-004, 005 - 006
Pondasi Finish : 20/20 tower (100%)
Finish : 15/20 (T.002, 003, 004, 005, 008, 009, 010,
Erection 011, 012, 013, 014, 015, 016, 018N, 019)
Remaining : T.001R, 006, 007, 017, 017A
Finish : 10/20 tower (T.003, 004, 005, 009, 010, 011,
012, 014, 015, 016)
Pemasangan Insulator
Remaining : T.001R, 002, 006, 007, 008, 013, 017, 017A,
018N, 019
Finish : 0/20 span
Bush Clearing
Remaining : -
Finish : 0/9 titik
Steger Remaining : T.001R – 002, 002 – 003, 004 – 005, 005 –
006, 006 – 007, 007 – 008, 008 – 009, 012 – 013, 019 - 020
Finish : 0/20 tower
On going : 019 (idle)
Revisi Tower
Remaining : T.001R, 002, 003, 004, 005, 006, 007, 008,
009, 010, 011, 012, 013, 014, 015, 016, 017, 017A, 018
Finish : 0/20
Final Check Remaining : T.001R, 002, 003, 004, 005, 006, 007, 008,
009, 010, 011, 012, 013, 014, 015, 016, 017, 017A, 018, 019
Finish : 0/20
Montage Roll Remaining : T.001R, 002, 003, 004, 005, 006, 007, 008,
009, 010, 011, 012, 013, 014, 015, 016, 017, 017A, 018, 019
Mobilisasi Konduktor Finish : 0/96 haspel
GSW =- OPGW =-
Line GSW Line OPGW
Stringing Konduktor Top =- Top =-
Middle =- Middle =-
Bottom =- Bottom =-
GSW =- OPGW =-
Line GSW Line OPGW
Sagging & Clamping Top =- Top =-
Middle =- Middle =-
Bottom =- Bottom =-
Line GSW Line OPGW
Top =- Top =-
Spacer & Damper
Middle =- Middle =-
Bottom =- Bottom =-

Note:
1. On Going Pekerjaan
Langsir:
a. T.001R (Persiapan Setting Ginpole (Repair Ginpole), Progres
Erection 0%, MP: 18 org)
b. T.006 (Droping Material Tower 50%, Material Onsite 10%,
Progres Erection 0%, MP: 16 org)
c. T.017 (Droping Alat Kerja Erection, Material Onsite 35%,
Progres Erection 0%, MP: 14 org)
Erection:
No. Dokumen : F-UIPJBT2-A-06-03
FORMULIR
Tanggal Terbit : 29 Juni 2020
PT PLN (PERSERO) Revisi : 00
UNIT PELAKSANA PROYEK RISALAH RAPAT
JAWA BAGIAN TENGAH 3 Halaman : 12

a. T.007 (Erection Basis 80%, Common Body X 50%, Progres


Erection 17%, MP: 14 org)
2. KSO MSJ akan merencanakan menggunakan 3 tim Erection pada 27 Mei
2021 dan 1 tim langsir sudah on site di T.17 pada 23 Mei 2021
3. Diperlukan percepatan revisi tower dan Final Check yang harus sudah
selesai pada 26 Juni 2021
4. Rencana pekerjaan langsir material T.017A dimulai pada tanggal
tanggal 5 Juni 2021.
5. KSO MSJ akan segera menyediakan 3 group revisi tower dan rencana
ditambah tim revisi dari tarikan 3 (T.080-T.111)
6. Rencana Stringing menggunakan mesin 2 (Tim Pak Sahlan – Pindahan
tarikan 5) dengan jadwal mobilisasi alat ke lapangan pada 20 Juni 2021
7. Terkait crossing dengan SUTT 150 kV Mandirancan – Cikijing, KSO MSJ
akan segera menyampaikan metode kerja untuk pelepasan dan
pemasangan ulang konduktor setelah dilakukan survei bersama pada 9
Juni 2021
8. Jadwal start Stringing pada 27 Juni 2021
9. Penyampaian buku tabungan untuk ROW Span T.003 – T.004 & 005 -
006 direncanakan pada M2 Juni 2021
No. Dokumen : F-UIPJBT2-A-06-03
FORMULIR
Tanggal Terbit : 29 Juni 2020
PT PLN (PERSERO) Revisi : 00
UNIT PELAKSANA PROYEK RISALAH RAPAT
JAWA BAGIAN TENGAH 3 Halaman : 13

• Tarikan 10 (T.111 - T.142A : 33 span) KSO MSJ 31-Jul-21 OPEN

ROW Finish : 33/33 span (100%)


Pondasi Finish : 33/33 tower (100%)
Erection Finish : 28/33 tower (T.112, 113, 114, 115, 116, 117,
118, 119, 120, 121, 121A, 122, 123, 126, 127, 128, 129, 130,
131, 132, 133, 134, 135, 136, 137, 138, 139, 142A)
On going : 141B
Remaining : T.124, 125, 140, 141A
Pemasangan Insulator Finish : 17/33 tower (T.112, 114, 115, 116, 119, 120,
121A, 122, 129, 130, 132, 133, 134, 136, 138, 139)
Remaining : T.113, 117, 118, 121, 123, 124, 125, 126, 127,
128, 131, 135, 137, 140, 141A, 141B
Bush Clearing Finish : 0/33 span
Remaining : -
Steger Finish : 0/4 titik
Remaining : T.119 – 120, 121A – 122, 127 – 128, 130 – 131
Revisi Tower Finish : 1/33 tower (T.114)
On going : T.112 (idle), 115 (idle), 126, 127 (idle)
Remaining : T. 113, 115, 116, 117, 118, 119, 120, 121,
121A, 122, 123, 124, 125, 128, 129, 130, 131, 132, 133, 134,
135, 136, 137, 138, 139, 140, 141A, 141B, 142A
Final Check Finish : 1/33 (T.114)
Remaining : T.112, 113, 115, 116, 117, 118, 119, 120, 121,
121A, 122, 123, 124, 125, 126, 127, 128, 129, 130, 131, 132,
133, 134, 135, 136, 137, 138, 139, 140, 141A, 141B, 142A
Montage Roll Finish : 19/33 (T.112, 113, 114, 115, 116, 119, 120,
121, 122, 129, 130, 131, 132, 133, 134, 136, 138, 139, 142A)
On going :-
Remaining : T.117, 118, 121A, 123, 124, 125, 126, 127,
128, 135, 137, 140, 141A, 141B
Mobilisasi Konduktor Finish : 0/172 haspel
Stringing Konduktor GSW =- OPGW =-
Line GSW Line OPGW
Top =- Top =-
Middle =- Middle =-
Bottom =- Bottom =-
Sagging & Clamping GSW =- OPGW =-
Line GSW Line OPGW
Top =- Top =-
Middle =- Middle =-
Bottom =- Bottom =-
Spacer & Damper Line GSW Line OPGW
Top =- Top =-
Middle =- Middle =-
Bottom =- Bottom =-

Note:
1. On going Pekerjaan
2. Langsir:
a. T.125 (Droping Material Tower 85%, Material Onsite 18%,
Progres Erection 0%, MP: 15 org)
No. Dokumen : F-UIPJBT2-A-06-03
FORMULIR
Tanggal Terbit : 29 Juni 2020
PT PLN (PERSERO) Revisi : 00
UNIT PELAKSANA PROYEK RISALAH RAPAT
JAWA BAGIAN TENGAH 3 Halaman : 14

b. T.140 (Persiapan Langsir material onsite, Droping Material


Tower 95%, Progres Erection 0%, MP: 30 org)
c. T.141A (Droping Material Tower 12%, Progres Erection 0%,
MP: 14 org)
Erection:
a. T.141B (Droping Alat Kerja Erection (Material Onsite 95%),
Progres Erection 0%, MP: 0 org)
2. Direncanakan langsir material tower T.124 mulai pada tanggal 5 juni
2021
3. Direncanakan tim erection di T.141B akan menggunakan tim dari
T.143, mulai erection pada tanggal 6 Juni 2021
4. Diperlukan percepatan revisi tower dan Final Check yang harus sudah
selesai pada 21 Juni 2021
5. Diperlukan pekerjaan pemasangan vangnet permanen dengan pondasi
untuk Crossing Rel KAI span T.127-T.128. Dijadwalkan untuk pekerjaan
tersebut dimulai pada 1 Juni 2021.
6. UPP JBT 3 perlu koordinasi lebih lanjut terkait izin kerja di area lahan
PT KAI. Izin prinsip sudah tersedia namun masih dalam proses
perpanjangan waktu. Rencana akan tersedia di M1 Juni
7. Rencana Stringing menggunakan mesin 5 (Mesin Zeck Ex Gudang
Randugarut) dengan jadwal mobilisasi alat ke lapangan pada 15 Juni
2021
8. Pengembalian material Leg Besar T.124 akan dilaksanakan pada
tanggal M2 Juni 2021, dan kekurangannya akan dikoordinasikan
kembali ke KAP.
9. Perlu pemasangan vangnet untuk crossing SUTT 150 kV (T.121A-T.122)
dijadwalkan mulai pada 8 Juni 2021
10. Jadwal start Stringing pada 22 Juni 2021
No. Dokumen : F-UIPJBT2-A-06-03
FORMULIR
Tanggal Terbit : 29 Juni 2020
PT PLN (PERSERO) Revisi : 00
UNIT PELAKSANA PROYEK RISALAH RAPAT
JAWA BAGIAN TENGAH 3 Halaman : 15

B. Main Issue

1. Dengan jadwal yang sangat ketat, berdasarkan timeLine yang sudah


disusun bersama maka diperlukan tim / group pekerjaan sebagai
berikut (Include alat kerja untuk masing-masing group):
2. Erection : 20 Group
3. Stringing : 6 Group
4. Kebutuhan set alat Stringing adalah 5 set dengan breakdown sebagai
berikut:
No Mesin Asal Mesin Status Section
Mesin 1 PLN SUMBAGSEL (Zeck) On going T.080 – T.111
T.019 – T.036
Mesin 2 KSO MSJ (Pak Sahlan) On going
T.01R – T.019
T.051 – T.058
Mesin 3 KSO MSJ (Pak Sahlan) On site Gudang
T.036 – T.051
Mesin 4 PLN UIP JBT (Zeck) On site Gudang T.142A – T.161
Mesin 5 PLN UIP JBT (Zeck) On site Gudang T.111 – T.142A
Masih
digunakan di
Mesin 1 PLN SUMBAGSEL (Zeck) T.161 – T.187
tarikan T.080 –
T.111

5. Perlu ekskalasi terkait kesiapan crossing dengan SUTT, Jalan Nasional,


Jalan Tol dan Rel Kereta Api. Breakdown kesiapan crossing sebagai
berikut:
Crossing
Span Progress Perizinan Tindak Lanjut
Remark
PPK 4.3 mensyaratkan
T.038 – T.039 Jl. Nasional Surat pemberitahuan
izin onLine kepada BBPJN
UPP 3 akan
T.042 – T.043 Jl. Tol (BMN) Ekspose mengusahakan izin
mendahului
Penyampaian Penyampaian jadwal
T.043 – T.044 SUTT 150 kV
metode kerja pemasangan vangnet
Penyampaian Penyampaian jadwal
T.044A – T.045 SUTT 70 kV
metode kerja pemasangan vangnet
Penyampaian Penyampaian jadwal
T.056 – T.057 SUTT 70 kV
metode kerja pemasangan vangnet
Penyampaian metode
T.121A – T.122 SUTT 150 kV Survey Lokasi
kerja
UPP 3 akan
mengusahakan izin
T.127 – T.128 Rel KAI Izin prinsip + EOT mendahului (schedule
update 1 Juni 2021 akan
terbit ijin pemberitahuan)
6. Tindak lanjut proses amandemen tambah kurang ke 8 saat ini sedang
diproses di kantor Induk, UPP akan melakukan kordinasi dengan UIT
terkait proses amandemen tersebut.
No. Dokumen : F-UIPJBT2-A-06-03
FORMULIR
Tanggal Terbit : 29 Juni 2020
PT PLN (PERSERO) Revisi : 00
UNIT PELAKSANA PROYEK RISALAH RAPAT
JAWA BAGIAN TENGAH 3 Halaman : 16