NOPEMBER 2019
NO SPAN TOWER PEKERJAAN SISA PEKERJAAN Group Pekerja
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
PONDASI Selesai 150/150 0
1 KONSTRUKSI
ERECTION Selesai 150/150 0 Lansir T.047 Erected T.047
STRINGING
(T.027 - T.064)
STRINGING (Finishing)
38 Tower 12 Span T.027 T.028 T.029 T.030 T.031 T.032
ACSR Line OPGW T.033 T.034 T.035 T.036 T.037 T.038
Sagging/Jumper ACSR T.039 T.040 T.041 T.042 T.043 T.044
Clamping ACSR T.045 T.046 T.047 T.048 T.049 T.050
2
Spacer dumper line T.051, T.052 T.051, T.053 T.051, T.054
T.055 T.056 T.057 T.058 T.059 T.060
ACSR Line GSW T.061 T.062 T.063 T.064
Sagging/Jumper ACSR
Clamping ACSR
Spacer dumper line
1 Group
OPGW 70 mm2
Sagging (Formed,Jumper OPGW)
Clamping/Jumper OPGW
GSW 55 mm2
Sagging (Jumper GSW)
Clamping/Jumper GSW
T.44 - T.87
PONDASI
T.164 - ~ (T.238)