"S - CURVE" JADWAL PELAKSANAAN PEKERJAAN

PROGRAM : PENGEMBANGAN KINERJA PENGELOLAAN AIR MINUM DAN AIR LIMBAH


KEGIATAN : REHABILITASI/PEMILIHARAAN SALURAN DRAINASE
SUB KEGIATAN : REHABILITASI DRAINASE PERMUKIMAN RAPAK MAHANG KELURAHAN TIMBAU
LOKASI : KECAMATAN TENGGARONG
TAHUN ANGGARAN : 2020
SUMBER DANA : APBD KABUPATEN KUTAI KARTANEGARA

MASA PELAKSANAAN 90 (SEMBILAN PULUH) HARI KALENDER MASA PEMELIHARAAN


BULAN KE - 1 BULAN KE - 2 BULAN KE - 3 ( 180 HARI KALENDER )

BULAN KE 1

BULAN KE 2

BULAN KE 3

BULAN KE 4

BULAN KE 5

BULAN KE 6
BOBOT
No URAIAN PEKERJAAN JUMLAH HARGA MINGGU KE MINGGU KE MINGGU KE Skala (%)
(%)

Mgg - 1 Mgg - 2 Mgg - 3 Mgg- 4 Mgg - 5 Mgg - 6 Mgg - 7 Mgg - 8 Mgg - 9 Mgg - 10 Mgg - 11 Mgg - 12
1-7 8 - 14 15-21 22-28 29-35 36-42 43-50 51-58 59-66 67-74 75-82 83-90

A PEKERJAAN PERSIAPAN 1.146.000,00 0,24 0,24 100%

B PEKERJAAN PARIT PASANGAN BATU GUNUNG 27.310.560,38 5,76 1,92 1,92 1,92 50%

C PEKERJAAN PLAT BETON PENUTUP PARIT 446.030.087,73 94,00 13,43 13,43 13,43 13,43 13,43 13,43 13,43 0%
V PHO

474.486.648,11 100,00
0,24 0,00 13,43 13,43 13,43 13,43 13,43 13,43 15,35 1,92 1,92
Rencana
0,24 0,24 13,67 27,10 40,53 53,96 67,39 80,82 96,16 98,08 100,00 100,00
PROGRES (%)
Realisasi

Tenggarong, 15 Juli 2020


CV. INDOKUTAI MANDIRI UTAMA

MUHAMMAD FAHRIZAL ANSHORI


Direktur