No Uraian Bobot Mei'18 Juni'18 Juli'18 Agust'18 Sept'18 Okt'18 Nov'18 Des'18 Jan'19 Feb'19 Maret'19 April'19
I PEKERJAAN PERSIAPAN 0.6909 0.173 0.173 0.173 0.173
XI PEKERJAAN ARSITEKTUR LANTAI LG 3.1334 0.313 0.313 0.313 0.313 0.313 0.313 0.313 0.313 0.313 0.313
XII PEKERJAAN ARSITEKTUR LANTAI GF 9.7188 0.694 0.694 0.694 0.694 0.694 0.694 0.694 0.694 0.694 0.694 0.694 0.694 0.694 0.694
XIII PEKERJAAN ARSITEKTUR LANTAI 1 5.9309 0.741 0.741 0.741 0.741 0.741 0.741 0.741 0.741
XIV PEKERJAAN ARSITEKTUR LANTAI 2 4.5878 0.573 0.573 0.573 0.573 0.573 0.573 0.573 0.573
XV PEKERJAAN ARSITEKTUR LANTAI 3 4.94 0.706 0.706 0.706 0.706 0.706 0.706 0.706
XVI PEKERJAAN EXTERIOR 7.875 0.875 0.875 0.875 0.875 0.875 0.875 0.875 0.875 0.875
XVII PEKERJAAN PLUMBING 6.8845 0.765 0.765 0.765 0.765 0.765 0.765 0.765 0.765 0.765
XVIII PEKERJAAN PEMADAM KEBAKARAN 1.8626 0.31 0.31 0.31 0.31 0.31 0.31
XIX PEKERJAAN ELEKTRIKAL 9.6642 1.208 1.208 1.208 1.208 1.208 1.208 1.208 1.208
XX PEKERJAAN TATA UDARA 6.5129 0.93 0.93 0.93 0.93 0.93 0.93 0.93
XXI PEKERJAAN ELEKTRONIK 2.1123 0.192 0.192 0.192 0.192 0.192 0.192 0.192 0.192 0.192 0.192 0.192
XXIII PEKERJAAN GAS MEDIS 2.0391 0.408 0.408 0.408 0.408 0.408
XXIV COMISIONING 0.5975 0.085 0.085 0.085 0.085 0.085 0.085 0.085
100.000
BOBOT PER 2 MINGGU 1.835 1.835 2.131 2.131 3.428 4.193 5.843 2.415 6.061 4.724 5.916 4.483 6.534 5.342 4.597 4.597 4.798 4.798 5.566 5.566 4.825 4.825 3.557
BOBOT KOMULATIF 1.835 3.669 5.8 7.931 11.36 15.55 21.4 23.81 29.87 34.59 40.51 44.99 51.53 56.87 61.47 66.07 70.86 75.66 81.23 86.79 91.62 96.44 100