RENCANA ANGGARAN BIAYA PEMBANGUNAN PONDOK PES

"NUR AULA"
Total Penerimaan Dana (I) 2020 : 126,050,000 RAB :
Pembelian BB (II) : 151,213,000 Dana yang Masih Dibutuhkan :
Upah Tukang (III) : 22,500,000.00 Realisasi RAB :
Total Pengeluaran (II) + (III) : 173,713,000.00 Total Penerimaan Dana 2019 :
Total Dana Tersisa : -47,663,000.00 Rasio Upah Tukang / Beli Bahan :

No. Penerimaan Dana Jumlah (Rp) No.


1 Hamba Allah 10,000,000 1
2 Bpk Ivan 5,000,000
3 Ibu Ita 7,000,000
4 Hamba Allah 15,000,000
5 Hamba Allah 6,000,000 2
6 Bpk Farhan 4,000,000
7 Ibu Imel 3,000,000
8 Sdr Diki 2,000,000
9 Ibu Tania 10,000,000
10 Bpk Dwi 9,000,000 3
11 Ibu Tika 8,000,000
12 Hamba Allah 6,000,000
13 Sdr Diko 5,000,000
14 Ibu Putri 10,000,000
15 Bpk Ari 2,500,000
16 Hamba Allah 7,000,000
17 Ibu Erika 3,000,000 4
18 Sdri Adinda 7,500,000
19 Sdri Linda 500,000
20 Bpk Gusti 2,400,000
21 Bpk Deny 750,000
22 Ibu Dea 1,200,000
23 Hamba Allah 1,200,000

6
7
ANGGARAN BIAYA PEMBANGUNAN PONDOK PESANTREN
"NUR AULA"
RAB : 500,000,000
Dana yang Masih Dibutuhkan : 78,950,000
Realisasi RAB : 84%
Total Penerimaan Dana 2019 : 295,000,000
Rasio Upah Tukang / Beli Bahan : 15%

Pengeluaran Satuan Vol Harga Satuan (Rp) Jumlah(Rp)


PEKERJAAN PERSIAPAN
Pasang Bowplank M1 84 100,000 8,400,000
Pengadaan Air Kerja LS 1 500,000 500,000
Upah Tukang 1,800,000.00
PEKERJAAN TANAH
Galian Tanah Pondasi M3 84 50,000 4.200.000
Urugan Pasir Di Bawah Tanah M3 84 150,000 12.600.000
Urugan Tanah Kembali M3 84 150,000 12.600.000
Upah Tukang 3,500,000
PEKERJAAN PASANGAN
Pondasi Batu Kali 1:5 M3 84 85,000 7.140.000
Dinding Bata 1:5 M2 108 40,000 4.320.000
Plesteran Biasa 1:5 M2 108 40,000 4.320.000
Lantai Keramik 30/30 M2 84 150,000 12.600.000
Rabat Beton M3 15 100,000 1.500.000
Upah Tukang 4,000,000
PEKERJAAN BETON
BERTULANG
Beton Sloof 15/20 M3 84 52,000 4.368.000
Kolom Beton 20/20 (utama) M3 84 42,000 3.528.000
Kolom Beton 15/20 (selasar) M3 84 40,000 3.360.000
Kolom Praktis 15/15 M3 84 42,000 3.528.000
Balok Beton 10/25 (selasar) M3 84 71,000 5.964.000
Ring Balok Beton 15/20 M3 84 49,000 4.116.000
Upah Tukang 4,200,000
PEKERJAAN KAYU
Kusen Pintu M3 3 400,000 1.200.000
Kusen Jendela M3 7 300,000 2.100.000
Kaso / Reng Kayu Borneo M2 100 30,000 3.000.000
Daun Pintu Panel Kamper M2 3 800,000 2.400.000
Daun Pintu Jendela Kayu Kamper M2 7 200,000 1.400.000
Singkil
Rangka Pelapon M2 84 22,000 1.848.000
Penutup Pelapon Jabesmen 1 x M2 84 50,000 4.200.000
1m
Lis Profil Plapon Kayu Kamper M1 84 20,000 1.680.000
Kusen + Jalusi Papan Pada Atap M3 84 60,000 5.040.000
Genteng Press Setara JTW M2 1000 3,000 3.000.000
Upah Tukang 3,700,000
PEKERJAAN LISTRIK
Instalasi Titik Lampu + Saklar 2 x Ttk 20 150,000 3.000.000
1.5 mm eterna
Instalasi Stop Kontak 3 x 1.5 mm Ttk 10 150,000 1.500.000
eterna
Lampu TL 20 Watt Ttk 20 85,000 1.700.000
Upah Tukang 1,800,000
PEKERJAAN LAIN-LAIN
Pengecetan Dinding M2 108 120,000 12,960,000
Pengecetan Plapon M2 108 100,000 10.800.000
Pasang Kaca Polos 5 mm BH 7 125,000 875,000
Pasang Kunci (pintu panel) BH 9 75,000 675,000
Kwalitas Baik Tanam Setara Merk
Pasang Kunci BH 9 55,000 495,000
Union
Pasang Engsel Pintu BH 3 45,000 135,000
Pasang Engsel Jendela BH 7 23,000 161,000
Upah Tukang 3,500,000