PROSEDUR KERJA ARUNA MENGWI

1. MENGHUBUNGI PELANGGAN APAKAH BISA DILAKUKAN PEMASANGAN (5 MENIT)


KENDALA :
- TIDAK BISA DI HUBUNGI
- NOMER YANG DITUJU SALAH
2. SURVEY LOKASI PEMASANGAN (10 MENIT)
- MENGHITUNG PANJANG SALURAN RENDAH (SR) DARI TIANG KE RUMAH
PELANGGAN
- MENGECEK TARIKAN SR KE BERAPA
- MEMERLUKAN PERLUASAN ATAU TIDAK
3. PENYAMBUNGAN SR KE RUMAH ( 15 MENIT)
4. PEMASANGAN KWH METER ( 15 MENIT)
- MEMASTIKAN KWH METER SUDAH TERPASANG DENGAN BAIK
- MENGINPUT KCT PADA METER ( UNTUK PREPAID METER)
5. MENGINPUT BUKTI PEMASANGAN KE APLIKASI FSO (10 MENIT MENYESUAIKAN)
KENDALA :
- TIDAK SEMU WILAYAH SINYALNYA BAGUS UNTUK BISA MENGINPUT FSO
- TERKADANG DALAM MENGINPUT BUKTI PEMASANGAN APLIKASI FSO ERROR
6. MELAKUKAN TAGGING LOKASI VIA APLIKASI WHATSAPP ( 2 MENIT)
7. MENGGAMBAR SKETS LOKASI SESUAI PEMASANGAN ( 5 MENIT)
8. MENGISI BERITA ACARA PEMASANGAN ( 5 MENIT)
- MEMINTA TANDA TANGAN PELANGGAN
- MEMINTA NOMER KTP PELANGGAN

KENDALA :

- UNTUK KOSTAN BIASANYA PELANGGAN TIDAK ADA DIRUMAH JADI MENUNGGU


TUAN RUMAH PEMILIK KOST UNTUK MEMINTA NOMER KTP