I. UMUM
1 Mobilisasi LS 1.0 25,000,000 25,000,000.00 1.020% 1.00 - 25,000,000.00 - - 25,000,000.00 - 1.00 25,000,000.00 25,000,000.00 1.02%
Total 25,000,000.00 Total - Total - Total 25,000,000.00 1.02%
II. PEKERJAAN DRAINASE
1 Galian Untuk Selokan Drainase dan Saluran Air m3 1,444.60 30,556.81 44,142,366.56 1.800% 1,075.18 - 30,556.81 - 369.42 30,556.81 11,288,384.36 1,075.18 30,556.81 32,853,982.20 1.34%
2 Pasangan Batu dengan Mortar m3 608.52 848,000.82 516,025,457.26 21.045% 187.80 - 848,000.82 - 420.72 848,000.82 356,770,903.80 187.80 848,000.82 159,254,553.46 6.49%
Total 560,167,823.82 Total - Total 368,059,288.15 Total 192,108,535.66 7.83%
III. PEKERJAAN TANAH
1 Galian Biasa DISETUJUI m3 1,496.25 30,556.81 45,720,625.75 1.865%MENGETAHUI
6,925.83 5,429.58 30,556.81 165,910,609.50 - 30,556.81 - 6,925.83 30,556.81 211,631,235.25 8.63%
MENGETAHUI DIBUAT OLEH
2 Timbunan Pilihan Dari sumber GalianPPHP
(Sirtu Kali) m3 2,562 95,349.00 244,284,127.71 KONSULTAN
TIM PUSAT PENGENDALI TEKNIS DAERAH 9.962% 4,624.80
PENGAWAS2,062.80 95,349.00 196,685,908.92 - 95,349.00 - 4,624.80 95,349.00 440,970,036.63 17.98%
3 Timbunan Pilihan Dari (Sirtu Gunung) m3 3,000 95,349.00 286,046,987.95 11.666% 2,696.40 - 95,349.00 - 303.60 95,349.00 28,947,955.18 2,696.40 95,349.00 257,099,032.77 10.48%
4 Penyiapan Badan Jalan m2 37,080 2,449.67 90,833,721.87 3.704% 47,608.00 10,528.00 2,449.67 25,790,113.91 - 2,449.67 - 47,608.00 2,449.67 116,623,835.78 4.76%
Total 666,885,463.29 Total 388,386,632.33 Total 28,947,955.18 Total 1,026,324,140.44 41.86%
IV. PEKERJAAN STRUKTUR
1 Beton K-225 m3 204.20 1,667,963.80 340,598,207.09 13.890% 303.60 99.40 1,667,963.80 165,795,601.30 - 1,667,963.80 - 303.60 1,667,963.80 506,393,808.39 20.65%
2 Baja Tulangan 24 Polos kg 20,682.19 15,572.50 322,073,403.78 13.135% 20,009.84 - 15,572.50 - 672.35 15,572.50 10,470,220.21 20,009.84 15,572.50 311,603,183.57 12.71%
3 Pasangan Batu m3 555.72 966,926.46 537,340,373.16 21.914% 404.00 - 966,926.46 - 151.72 966,926.46 146,704,770.08 404.00 966,926.46 390,635,603.08 15.93%
Total 1,200,011,984.03 Total 165,795,601.30 Total 157,174,990.29 Total 1,208,632,595.04 49.29%
2,452,065,271.14 100.000% 554,182,233.62 554,182,233.62 2,452,065,271.14 100.00%
ALAMSYAH PERJUANGAN
Ir. ALIN YURIANTO G, M.Si BLASIUS BESI META YOSEBIUS ELU,STPROJECT MANAGER
196110011994031001 NIP 196612311990031038 TIM LEADER
DISETUJUI
PEJABAT PEMBUAT KOMITMEN
Lokasi
NIP 196612311990031038
Dirun dan Dilumil Kabupaten Belu
Kontrak 173.2/SPK/DPDTU/SATKER/PPK3-PDP/09/2017 Tanggal 25 September 2017
CV SHALOM KONSULTAN
Nilai Kontrak Rp 2,697,271,000
Consultant CV SHALOM KONSULTAN Kontraktor Konsultan
Tgl. Mulai Wednesday, September 20, 2017
Tgl. Selesai Saturday, December 09, 2017
Kontraktor NENCI CITRA PRATAMA PT.
ALAMSYAH PERJUANGAN YOSEBIUS ELU,ST
PROJECT MANAGER TIM LEADER
== 9,8*(0,3+0,4)/2*(1,9+1,85)/2 = 6.431 M3
= 15,5*(0,3+0,4)/2*(1,05+1,85)/2 = 7.866 M3
33.01 M3
c) Dinding Penahan Panjang * Luas Penampang (Panjang = 76,9 M') (Pasangan Batu STRUKTUR )
= 9*(0,3+0,4)/2*(0,45+1,95)/2 = 3.78 M3
= 8,2*(0,3+0,4)/2*(1,95+1,9)/2 = 5.52 M3
= 7,5*(0,3+0,4)/2*0,85 = 2.23 M3
= 7,5*(0,3+0,4)/2*(0,85+2,15)/2 = 3.94 M3
= 8,5*(0,3+0,4)/2*(2,15+1,25)/2 = 5.06 M3
= 12,7*(0,3+0,4)/2*(0,85+1,6)/2 = 5.45 M3
= 9,5*(0,3+0,4)/2*(1,6+1,25)/2 = 4.74 M3
= 5*(0,3+0,4)/2*(1,25+0,85)/2 = 1.84 M3
= 4*(0,2+0,3)/2*(0,85+1,3)/2 = 1.08 M3
34.41 M3
C Dinding Penahan Panjang * Luas Penampang (Panjang =27 M') (Pasangan Batu STRUKTUR )
STA 0+150 =
L=5,75M = 5,75*((0,4+0,7)/2*1,35+(0,4+0,7)/2*1,75)/2 = 4.90 M3
L=5,75M = 5,75*((0,4+0,7)/2*1,85+(0,4+0,7)/2*1,75)/2 = 5.69 M3
DINDING PENAHAN SISI KANAN Pondasi Pas Batu (Pasangan Batu Struktur ) 10.59
= 27*0,3*0,7 = 5.67 M3
D Dinding Penahan Panjang * Luas Penampang (Panjang =1,8M') (Pasangan Batu STRUKTUR )
STA 0+150 =
L=,9M = 0,9*((0,4+0,7)/2*0,8+(0,4+0,7)/2*0,5)/2 = 0.32 M3
L=,9M = 0,9*((0,4+0,7)/2*0,5+(0,4+0,7)/2*0,25)/2 = 0.19 M3
Pondasi Pas Batu (Pasangan Batu Struktur ) 0.51
= 1,8*,3*,7 = 0.378 M3
E Dinding Penahan Panjang * Luas Penampang (Panjang =2,4 M') (Pasangan Batu STRUKTUR )
STA 0+150 =
L=2,4 M = 2,4*((0,4+0,7)/2*,25+(0,4+0,7)/2*,7)/2 = 0.627 M3
F Dinding Penahan Panjang * Luas Penampang (Panjang =20 M') (Pasangan Batu STRUKTUR )
STA 0+260 =
L=10 M = 10*((0,4+0,7)/2*,5+(0,4+0,7)/2*1,2)/2 = 4.675 M3
L=10 M = 10*((0,4+0,7)/2*1,2+(0,4+0,7)/2*,9)/2 = 5.775 M3
Pondasi Pas Batu (Pasangan Batu Struktur ) 10.45
= 20*,3*,7 = 4.20 M3
STA 1+100 = (0,3+0,8)/2*2,5*47,75 = 65.66 M3
TOTAL PAS BATU STRUKTUR SISI KANAN = 176.48 M3
403.997
109.77
BACK UP DATA PERHITUNGAN VOLUME Tim Teknis
KEMENTERIAN PEMBANGUNAN DAERAH TERTINGGAL DAN
TRANSMIGRASI REPUBLIK INDONESIA DIREKTORAT JENDERAL
Paket Pekerjaan Pembangunan Jalan Sirip di Wilayah PENGEMBANGAN DAERAH TERTENTU
DIRUN = = 85.530 M3
DILUMIL = = M3
85.530 M3 = -102.270 M3 Kurang
-Rp86,725,043.57
III. PEKERJAAN TANAH
1 Galian Biasa ruas Dirun+Dilumil ( Hit. Software LDD) = 1181,91+5743,919 = 6,925.83 M3
2 Timbunan Pilihan Dari sumber Galian (Sirtu Kali) = 3854*6*0,2 = 4,624.80 M3 (Dilumil)
3 Timbunan Pilihan Dari (Sirtu Gunung) = 2247*6*0,2 = 2,696.40 M3 (Dirun)
4 Penyiapan Badan Jalan = (3854+2247)*8-(5*240) = 47,608.00 M2
Total 2,646.05 M3
Kontrak 2,696.40 M3
-50.35 M3 Kurang
-Rp4,801,273.71
PEKERJAAN TANAH
Galian Biasa
Timbunan Pilihan Dari sumber Galian (Sirtu Kali) Rp 440,970,036.63 Rp 440,970,036.63 636,963,365.32 Pekerjaan yg belum dikerjakan di Ruas Dilumil
Timbunan Pilihan Dari (Sirtu Gunung) Rp 85,635,894.02 Rp 4,801,273.71
Penyiapan Badan Jalan
PEKERJAAN STRUKTUR
Beton K-225 Rp 7,822,515.42 Rp - (Volume Lebih)
Baja Tulangan 24 Polos
Pasangan Batu Rp 106,136,830.75 Rp 109,268,285.12
TOTAL Rp 776,755,697.30 Rp 641,764,639.03
SELISIH Rp134,991,058