Proyek A Proyek B
Tahun
Lajur Kas Laju Kas
0 -100 -100
1 30 40
2 30 40
3 30 30
4 30 20
5 30 20
( 1+ 10 % )5−1
= -100 + 30 ( 5
)
10 % ( 1+10 % )
0.610
= -100 + 30 ( )
0.161
= 13.723
Proyek B
Diketahui:
Investasi = -100
MARR = 10%
Tahun CF (1 + i%)-n
1 40 0.909
2 40 0.826
3 30 0.751
4 20 0.683
5 20 0.620
NPV = Investasi + CF (P/A, i% n)
= Investasi + CF ( 1 + 10%)-n
= -100 + 40(0.909) + 40(0.826) + 30(0.751) + 20(0.683) + 20(0.620)
= 18.040
-IRR
Proyek A
Untuk MARR =10%
( 1+ 10 % )5−1
PW = -100 + 30 ( 5
)
10 % ( 1+10 % )
0.610
= -100 + 30 ( )
0.161
= 13.723
( 1+ 20 % )5−1
PW = -100 + 30 ( 5
)
20 % ( 1+20 % )
1.488
= -100 + 30 ( )
0.498
= -10.282
IRR = 10%
IRR PROYEK A
+ (20% - 10%)
15
10 13.723
5 {13.723+10.282 }
0 =
10% 11% 12% 13% 14% 15% 16% 17% 18% 19% 20%
-5
-10
-15
15.717%
Proyek B
Untuk MARR = 10%
Tahun CF (1 + i%)-n
1 40 0.909
2 40 0.826
3 30 0.751
4 20 0.683
5 20 0.620
Tahun CF (1 + i%)-n
1 40 0.833
2 40 0.694
3 30 0.579
4 20 0.482
5 20 0.402
PW = -100 + 40(0.833) + 40(0.694) + 30 (0.579) + 20(0.482) +20(0.402)
10
IRR = 10%
5
+ (20% - 10%)
0
10% 11% 12% 13% 14% 15% 16% 17% 18% 19% 20%
-5
18.040
-10 {18.040+3.845 }
= 18.243%
-B/C
Proyek A
( 1+ 10 % )5−1
PWB pada MARR 10% = 30 ( 5
)
10 % ( 1+10 % )
0.610
= 30 ( )
0.161
= 113.723
PWB 113.723
B/C = = = 1.1723
C 100
Proyek B
PWB pada MARR 10% = 40(0.909) + 40(0.826) + 30(0.751) + 20(0.683) + 20(0.62
= 118.040
PWB 118.040
B/C = = = 1.1804
C 100
-POT
Proyek A
Tahun Proyek A
Lajur Kas
0 -100
1 30
2 30
3 30
4 30
5 30
100
POT = = 3.3 Tahun
30
Proyek B
Tahun 1 2 3 4 5
Investasi 100
CF 40 40 30 20 20
CCF -60 -20 10 30 50
40
POT = 2 + = 3.3 Tahun
30
2. Berdasarkan dari NPV, IRR, dan B/C maka proyek B lebih menguntungkan dibandingkan
dengan proyek A karena nilainya lebih besar. Walaupun memiliki POT yang sama yaitu
3.3 tahun.