PROGRES PEKERJAAN FAÇADE PRECAST
Pekerjaan Dinding Precast
14/02/2020
HOIST BONGKAR :
10/02-14/02

TC BONGKAR :
13/02-20/02

TAMPAK TIMUR TAMPAK BARAT


PROYEK PEMBANGUNAN TERASKITA HOTEL - MAKASSAR
PROGRES PEKERJAAN FAÇADE PRECAST
Pekerjaan Dinding Precast
TAMPAK UTARA TAMPAK SELATAN

BRACING TC
(20/02/2020)

BRACING TC
(20/02/2020)

HOIST BONGKAR : TC BONGKAR :


10/02-14/02 13/02-20/02
PROYEK PEMBANGUNAN TERASKITA HOTEL - MAKASSAR
PROGRES PEKERJAAN FAÇADE

TAMPAK UTARA TAMPAK SELATAN

BELUM SELESAI
PEKERJAAN KUSEN JENDELA PRECAST
BELUM SELESAI
TERPASANG 99 %
KECUALI AREA BRACING TC PEKERJAAN KUSEN JENDELA PRECAST
SELESAI 10/2/2020 (Sealent Luar) SELESAI 10/02/2020 (Sealent Luar)

TC BONGKAR
(13/02 – 20/02)
Sealent Precast
22/02

TC BONGKAR
(13/02 – 20/02)
Sealent Precast
22/02

PEKERJAAN LIST ACP


SELESAI 31/01/2020
PEKERJAAN KUSEN WINDOW WALL SELESAI

PEKERJAAN SHOP FRONT


1. LOBBY GF (18/02/2020)
2. LOBBY LIFT LT. 4-5 (31/01/2020)
3. LOUNGE (24/02/2020)

PROYEK PEMBANGUNAN TERASKITA HOTEL - MAKASSAR


PROGRES PEKERJAAN FAÇADE
Pekerjaan Façade ACP & Kanopi Baja PASANG
PRECAST
14/02/2020

BELUM SELESAI
BELUM SELESAI
PEKERJAAN KUSEN JENDELA PRECAST
PEKERJAAN KUSEN JENDELA PRECAST SELESAI 10/2/2020 (Sealent Luar)
SELESAI 10/02/2020 (Sealent Luar)

PEKERJAAN KISI-KISI ALUMINIUM


SELESAI 27/02/2020
PEKERJAAN KUSEN WINDOW WALL
TERPASANG 95 % (PH Bongkar 10/02 – 14/02)
PEKERJAAN LIST ACP
SELESAI 17/02/2020
SELESAI 19/02/2020 (AREA PH)

PEKERJAAN ACP
SELESAI 31/01/2020

PEKERJAAN KANOPI BAJA


1. KACA TEMPERED LAMINATED SELESAI
21/02/2020

TAMPAK TIMUR
PROYEK PEMBANGUNAN TERASKITA HOTEL - MAKASSAR
PROGRES PEKERJAAN FAÇADE
TAMPAK TIMUR TAMPAK BARAT

RAILING OUTDOOR
BELUM SELESAI AC:
LT. 12 & 14 SELESAI
PEKERJAAN KUSEN JENDELA 21/02/2020
PRECAST
SELESAI 10/2/2020 (Sealent Luar)

RAILING OUTDOOR
RAILING STAINLESS STEEL: AC:
LT. 4 & 5 SELESAI 27/02/2020 LT. 5,6,8,10 SELESAI
18/02/2020

BELUM SELESAI
RAILING OUTDOOR
AC:
LT. MZ,2,3,4 SELESAI
14/02/2020

PROYEK PEMBANGUNAN TERASKITA HOTEL - MAKASSAR


PROGRES PEKERJAAN CAT DINDING LUAR

BELUM SELESAI, sisa


BELUM SELESAI, sisa cat parapet lt. atap
cat parapet lt. atap

04/02
14/02

25/01
18/02

21/02

TAMPAK UTARA TAMPAK SELATAN


PROYEK PEMBANGUNAN TERASKITA HOTEL - MAKASSAR
PROGRES PEKERJAAN CAT DINDING LUAR

BELUM SELESAI, sisa


cat bagian koridor
dan tali air
18/02

31/01

24/02

TAMPAK TIMUR TAMPAK BARAT

PROYEK PEMBANGUNAN TERASKITA HOTEL - MAKASSAR


SEQUEN PEKERJAAN GRC

4 3

5 2

6 1

C - BELAKANG C - DEPAN

PROYEK PEMBANGUNAN TERASKITA HOTEL - MAKASSAR


PROGRES PEKERJAAN GRC

BELUM SELESAI

PROYEK PEMBANGUNAN TERASKITA HOTEL - MAKASSAR


PROGRES PEKERJAAN GRC

PROYEK PEMBANGUNAN TERASKITA HOTEL - MAKASSAR


PROGRESS PEKERJAAN GAWANGAN GRC TAMPAK 2

TOTAL TERPASAN BELUM STOK


TAMPAK G (MERAH) PRODUKSI (HIJAU)
(KUNING)
INSTALL :
12/02-17/02
138 PCS 31 PCS 69 PCS 41 PCS
(22 %) (49 %) (30 %) INSTALL :
08-09/02
INSTALL :
Data Update 07 Februari 2020 11/02-13/02

BELUM SELESAI

BELUM SELESAI INSTALL :


06-07/02
INSTALL :
09/02-10/02

BELUM SELESAI
INSTALL :
04/02-05/02

PROYEK PEMBANGUNAN TERASKITA HOTEL - MAKASSAR


MONITORING CLOSING PODIUM

MAPPING LANTAI GF TC BONGKAR : BONGKAR PONDASI


13/02-20/02 TC : 21/02-23//02

RAMP 2 27/02

LOBBY 21/02
BASEMENT : 27/02
LANDSCAPE & PAGAR
29/02

RAMP 1 14/02
BELUM SELESAI
MONITORING CLOSING PODIUM

MAPPING LANTAI UG
BELUM SELESAI

KERAMIK : 14/02

BELUM SELESAI
KERAMIK LANTAI &
DINDING : 10/02 UNIT AC : 31/01
FEEDER : 08/02
PLAFOND : 12/02
CAT : 14/02
CAT BELUM SELESAI SANITAIR : 23/02

CAT OUTDOOR RESTO: 07/02


LANTAI FH :14/02 RAILING STAINLESS : 17/02
MONITORING CLOSING PODIUM

MAPPING LANTAI MZ

SANITAIR : 23/02 DINDING


LOBBY : 13/02
14/02 14/02
RAILING
STAINLESS
KORIDOR : 17/02 27/02

RAILING OUTDOR AC
14/02 21/02
BELUM 21/02 21/02 21/02
SELESAI
MONITORING CLOSING PODIUM

MAPPING LANTAI 2

SANITAIR: 23/02 DINDING


LOBBY :
21/02 10/02
21/02
27/02

RAILING OUTDOR AC KORIDOR : 17/02


14/02
BELUM
SELESAI

27/02 27/02 27/02 27/02


MONITORING CLOSING PODIUM

MAPPING LANTAI 3

SANITAIR : 23/02
DINDING
17/02 LOBBY: 10/02

RAILING OUTDOR AC KORIDOR : 17/02


14/02
BELUM
SELESAI

27/02
MONITORING CLOSING PODIUM

MAPPING LANTAI 4

DINDING
21/02 LOBBY :
25/02 14/02
24/02

RAILING OUTDOR AC KORIDOR : 25/02


14/02
BELUM
SELESAI

21/02 21/02 27/02 27/02


MONITORING CLOSING PODIUM

MAPPING LANTAI 5
HOLD AREA DINDING LOBBY :
16/02

29/02
27/02
BELUM RAILING
SELESAI STAINLESS
27/02
POOL DECK: 14/02
PLAFOND : 29/02

29/02
MOZAIK: 16/02
SANITAIR : 23/02
RAILING OUTDOR AC CAT DINDING LUAR POOL FINISH : 21/02
18/02
BELUM
SELESAI
MONITORING CLOSING UNIT

MAPPING CLOSING UNIT LANTAI 6

BELUM SELESAI

03/02 03/02
05/02
03/02 03/02

RAILING OUTDOR AC KORIDOR KARPET : 21/02/20


18/02

05/02 05/02 05/02 07/02 07/02 07/02 07/02 07/02


MONITORING CLOSING UNIT
MAPPING CLOSING UNIT LANTAI 7

AREA BRACING TC BELUM


SELESAI
05/02 19/02 19/02
07/02
05/02

KORIDOR KARPET : 21/02/20

07/02 07/02 07/02 09/02 09/02 09/02 09/02 09/02


BELUM SELESAI
MONITORING CLOSING UNIT
MAPPING CLOSING UNIT LANTAI 8

BELUM SELESAI BELUM SELESAI BELUM


SELESAI
07/02 07/02
09/02
07/02 07/02

RAILING OUTDOR AC KORIDOR KARPET : 21/02/20


18/02

09/02 09/02 09/02 11/02 11/02 11/02 11/02 11/02


BELUM SELESAI
MONITORING CLOSING UNIT
MAPPING CLOSING UNIT LANTAI 9

BELUM SELESAI BELUM SELESAI


14/02 14/02
16/02
14/02 14/02

KORIDOR KARPET : 26/02/20

16/02 16/02 16/02 18/02 18/02 18/02 18/02 18/02


MONITORING CLOSING UNIT
MAPPING CLOSING UNIT LANTAI 10

17/02 17/02
19/02
17/02 17/02

RAILING OUTDOR AC KORIDOR KARPET : 29/02/20


18/02

19/02 19/02 19/02 21/02 21/02 21/02 21/02 21/02


MONITORING CLOSING UNIT

MAPPING CLOSING UNIT LANTAI 11

19/02
19/02 19/02 19/02 21/02

KORIDOR KARPET : 29/02/20

21/02 21/02 21/02 23/02 23/02 23/02 23/02


MONITORING CLOSING UNIT

MAPPING CLOSING UNIT LANTAI 12

22/02
22/02 22/02 22/02 24/02

KORIDOR KARPET : 29/02/20


RAILING OUTDOR AC
21/02

24/02 24/02 24/02 26/02 26/02 26/02 26/02


MONITORING CLOSING UNIT

MAPPING CLOSING UNIT LANTAI 13

BELUM
BELUM SELESAI SELESAI
11/02
11/02 11/02 11/02 13/02
BELUM SELESAI

KORIDOR KARPET : 29/02/20


BELUM SELESAI

13/02 13/02 13/02 15/02 15/02 15/02 15/02


MONITORING CLOSING UNIT

MAPPING CLOSING UNIT LANTAI 14

BELUM
BELUM SELESAI BELUM SELESAI
SELESAI

11/02 11/02 11/02 11/02

RAILING OUTDOR AC
21/02
KORIDOR KARPET : 29/02/20
BELUM
SELESAI
13/02 13/02 13/02 13/02 15/02 15/02 15/02 15/02
MONITORING CLOSING UNIT

MAPPING CLOSING UNIT LANTAI 15

BELUM
BELUM SELESAI BELUM SELESAI
SELESAI

13/02 13/02 13/02 13/02

KORIDOR KARPET : 29/02/20

15/02 15/02 15/02 15/02 17/02 17/02 17/02 17/02


MONITORING CLOSING UNIT
MAPPING CLOSING UNIT LANTAI ATAP
(WATERPROOFING MEMBRAN)
TES RENDAM : 14/02-15/02
SCREED : 16/02

FINISH FINISH TES RENDAM :


10/02-11/02
SCREED : 12/02

TES RENDAM :
08/02-09/02
FINISH SCREED : 10/02

TES RENDAM : 12/02-13/02


SCREED : 14/02

TC BONGKAR : HOIST BONGKAR :


13/02-20/02 10/02-14/02