BILL OF QUANTIT

Project ID : 212401
PEKERJAAN : T-06 Repair
LOKASI : TERMINAL AKR Stagen

N0 URAIAN PEKERJAAN VOL

A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Tenaga Kerja, Alat dan Material 1.00
2 Alat Pelindung Diri (APD) sesuai Contractor Safety Management System 1.00
3 Listrik dan Air Kerja 1.00
4 Direksi keet, gudang kontraktor, dan alat bantu kerja 1.00
5 Biaya Kebersihan, Ijin Kerja dan Koordinasi 1.00
6 Dokumentasi, shop drawing, as built drawing, reporting 1.00
7 Rapid Test 1.00
8 MCU 1.00
SUB TOTAL A

B BOTTOM PLATE PATCHING


1 Patching dengan pelat 10 mm 34.00
2 NDE Test (Visual, Penetrant, Vacuum) 1.00
SUB TOTAL B

C BOTTOM PLATE & TANKSUMP REPLACEMENT


1 Bongkar & ganti pelat Tank Sump (tebal 14mm) 1.00
Include surface preparation & coating coal tar epoxy
2 Bongkar & ganti pelat (tebal 12 mm) 13.00
Include surface preparation & coating coal tar epoxy
3 Replace aspal 1.00
4 Pembuatan akses (roof/doorsheet) 1.00
5 NDE Test (Visual, Penetrant, MPI, Radiografi & Vacuum)
a. Bottom Plate (Visual, Penetrant 100%, Vacuum 100%) 1.00
b. Tank Sump (Visual, MPI, Vacuum 100%) 1.00
c. Roof opening (Visual, Penetrant 100%, Vacuum 100%) 1.00
SUB TOTAL C

D DRAIN PIPE REPAIR & MODIF


1 Penambahan pipa product drain 4" (30cm) 1.00
2 Penggantian seluruh pipe support untuk Product-drain & water-drain 1.00
SUB TOTAL D

E PEKERJAAN MODIFIKASI PIPA FOAM CHAMBER


1 Modifikasi pipa foam chamber 1.00
2 NDE Test 1.00
(Visual, Penetrant, Radiography) & Commissioning
SUB TOTAL F

F PEKERJAAN PENGECATAN EKSTERNAL


Surface preparation : Sa 2 1/2
Jotun : Resist 78 - 75 μm, Penguard Midcoat - 200 μm, Hardtop XP - 50 μm
Garansi product & pekerjaan: 7 tahun

1 Surface preparation (Material: Garnett) 1.00


2 Re-painting 1.00
- Projection plate, handrail, pipa foam & hydrant, tangga, nozzle
- Identifikasi tangka
- 3 Logo (2 dinding & 1 atap)
- Diameter logo: dinding (1/4 tinggi tangki), atap (1/3 diameter atap)
- Lapisan tahan bahan kimia / anti selip untuk tangga, keliling atap
tangki sisi handrail (lebar 1 meter), dan disekitar roof manhole
SUB TOTAL G

G PEKERJAAN INTERNAL COATING


Surface preparation : Sa 2 1/2
Jotun : Tankguard SF 2x500 micron
1 Surface preparation 1.00
2 Re-painting 1.00
SUB TOTAL H

H GENERAL WORKS
1 Pembuatan Pembatas kaki Stilling well pada bottom Plate Tangki 1.00
2 Modifikasi support menjadi adjustable pipe support 1.00
SUB TOTAL J

Sub Total
Jumlah Material + Jasa
PEMBULATAN
PPN 10%
GRAND TOTAL

Catatan :
1. Validity penawaran harga belaku hingga 14 hari kalender dari tanggal pembuatan penawaran,

2. Lama Pekerjaan Total 60 hari Setelah KOM

2. Cara pembayaran
- Monthly Progress
- Retensi 5 % Dibayar 12 Bulan Setelah BAST 1
BILL OF QUANTITY

rev-00

SAT Breakdown SAT HARGA SATUAN HARGA TOTAL


Volume MATERIAL JASA MATERIAL

ls 14,450,000 -
ls 18,390,000 -
ls 8,500,000 -
ls 4,560,000 -
ls 7,560,000 -
ls 7,560,000 -
ls 33,750,000 -
ls 11,900,000 -
-

ttk by AKR 9,209,302 -


ls 17,000,000 -
-

ls by AKR 32,187,500 by AKR

ls 81.765 m2 by AKR 13,000,000 by AKR

ls 81.765 m2 21,576,025 18,364,000 21,576,025


ls 101,858,790 -

ls 25,600,000 -
ls 22,000,000 -
ls 9,000,000 -
21,576,025

ls 1,000,000 -
ls 2,450,000 1,000,000 2,450,000
2,450,000

ls 16,787,600 15,220,000 16,787,600


ls 13,899,249 -
16,787,600

ls 1451.415 m2 116,523 100,500 169,122,586


ls 1451.415 m2 152,334 100,500 221,099,946

390,222,533

ls 496.591 m2 116,523 100,500 57,864,052


ls 496.591 m2 670,734 100,500 333,080,364
390,944,416

ls 1,133,000 1,421,400 1,133,000


ls 2,500,000 10,500,000 2,500,000
3,633,000

825,613,574
mlah Material + Jasa
MBULATAN

AND TOTAL
12-Jan-21

HARGA TOTAL
JASA

14,450,000 1.16%
18,390,000 1.47%
8,500,000 0.68%
4,560,000 0.36%
7,560,000 0.61%
7,560,000 0.61%
33,750,000 2.70%
11,900,000 0.95%
106,670,000 8.54%

313,116,279 25.06%
17,000,000 1.36%
330,116,279 26.42%

32,187,500 2.58%

169,000,000 13.53%

18,364,000 1.47%
101,858,790 8.15%

25,600,000 2.05%
22,000,000 1.76%
9,000,000 0.72%
378,010,290 30.26%

1,000,000 0.08%
1,000,000 0.08%
2,000,000 0.16%

15,220,000 1.22%
13,899,249 1.11%
29,119,249 2.33%

145,867,209 11.68%
145,867,209 11.68% 1.13

291,734,417 23.35%

49,907,396 3.99%
49,907,396 3.99%
99,814,791 7.99%

1,421,400 0.11%
10,500,000 0.84%
11,921,400 0.95%

1,249,386,426 100.00%
2,075,000,000
2,075,000,000
207,500,000
2,282,500,000
TIMELINE
Project ID : 212401
PEKERJAAN : T-06 Repair 15-Feb-21 1-May-21 75 days
LOKASI : TERMINAL AKR Stagen 15-Feb-21 30-Apr-21 74 days

NO URAIAN PEKERJAAN VOL SAT Breakdown SAT BOBOT (%) START DATE END DATE REMARKS MONTH Feb-21 Mar-21 Apr-21 May-21
Volume WEEK 1 2 3 4 5 6 7 8 9 10 11 12
2/15/2021 2/18/2021 2/25/2021 3/4/2021 3/11/2021 3/18/2021 3/25/2021 4/1/2021 4/8/2021 4/15/2021 4/22/2021 4/29/2021
DATE
2/17/2021 2/24/2021 3/3/2021 3/10/2021 3/17/2021 3/24/2021 3/31/2021 4/7/2021 4/14/2021 4/21/2021 4/28/2021 5/5/2021
A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Tenaga Kerja, Alat dan Material 1.00 ls 1.16% 15-Feb-21 27-Feb-21 12 days 0.39% 0.39% 0.39%
2 Alat Pelindung Diri (APD) sesuai Contractor Safety Management System 1.00 ls 1.47% 15-Feb-21 27-Feb-21 12 days 0.49% 0.49% 0.49%
3 Listrik dan Air Kerja 1.00 ls 0.68% 15-Feb-21 27-Feb-21 12 days 0.23% 0.23% 0.23%
4 Direksi keet, gudang kontraktor, dan alat bantu kerja 1.00 ls 0.36% 15-Feb-21 25-Feb-21 10 days 0.12% 0.12% 0.12%
5 Biaya Kebersihan, Ijin Kerja dan Koordinasi 1.00 ls 0.61% 15-Feb-21 25-Feb-21 10 days 0.20% 0.20% 0.20%
6 Dokumentasi, shop drawing, as built drawing, reporting 1.00 ls 0.61% 15-Feb-21 27-Feb-21 12 days 0.20% 0.20% 0.20%
7 Rapid Test 1.00 ls 2.70% 15-Feb-21 25-Feb-21 10 days 0.90% 0.90% 0.90%
8 MCU 1.00 ls 0.95% 15-Feb-21 25-Feb-21 10 days 0.32% 0.32% 0.32%
SUB TOTAL A 8.54%

B BOTTOM PLATE PATCHING


1 Patching dengan pelat 10 mm 34.00 ttk 25.06% 21-Feb-21 10-Mar-21 17 days 12.53% 12.53%
a Fit-up 22-Feb-21 4-Mar-21 10 days
b Welding 23-Feb-21 6-Mar-21 11 days
2 NDE Test (Visual, Penetrant, Vacuum) 1.00 ls 1.36% 7-Mar-21 21-Mar-21 14 days 0.68% 0.68%
SUB TOTAL B 26.42%

C BOTTOM PLATE & TANKSUMP REPLACEMENT


1 Bongkar & ganti pelat Tank Sump (tebal 14mm) 1.00 ls 2.58% 23-Feb-21 12-Mar-21 17 days 0.86% 0.86% 0.86%
Include surface preparation & coating coal tar epoxy
2 Bongkar & ganti pelat (tebal 12 mm) 13.00 ls 81.765 m2 13.53% 23-Feb-21 13-Mar-21 18 days 4.51% 4.51% 4.51%
Include surface preparation & coating coal tar epoxy
3 Replace aspal 1.00 ls 81.765 m2 1.47% 25-Feb-21 12-Mar-21 15 days 0.49% 0.49% 0.49%
4 Pembuatan akses (roof/doorsheet) 1.00 ls 8.15% 25-Feb-21 14-Mar-21 17 days 2.72% 2.72% 2.72%
- Scaffolding 25-Feb-21 4-Mar-21 7 days
- Fit-up 1-Mar-21 6-Mar-21 5 days
- Welding 13-Mar-21 15-Mar-21 2 days
5 NDE Test (Visual, Penetrant, MPI, Radiografi & Vacuum) 12-Mar-21 17-Mar-21 5 days
a. Bottom Plate (Visual, Penetrant 100%, Vacuum 100%) 1.00 ls 2.05% 15-Mar-21 18-Mar-21 3 days 2.05%
b. Tank Sump (Visual, MPI, Vacuum 100%) 1.00 ls 1.76% 11-Mar-21 14-Mar-21 3 days 1.76%
c. Roof opening (Visual, Penetrant 100%, Vacuum 100%) 1.00 ls 0.72% 15-Mar-21 18-Mar-21 3 days 0.72%
SUB TOTAL C 30.26%
0.08%
D DRAIN PIPE REPAIR & MODIF 0.08%
1 Penambahan pipa product drain 4" (30cm) 1.00 ls 0.08% 25-Feb-21 3-Mar-21 6 days
2 Penggantian seluruh pipe support untuk Product-drain & water-drain 1.00 ls 0.08% 25-Feb-21 3-Mar-21 6 days
SUB TOTAL D 0.16%
0.61%
E PEKERJAAN MODIFIKASI PIPA FOAM CHAMBER 1.11%
1 Modifikasi pipa foam chamber 1.00 ls 1.22% 18-Feb-21 25-Feb-21 7 days 0.61%
2 NDE Test 1.00 ls 1.11% 23-Feb-21 27-Feb-21 4 days
(Visual, Penetrant, UT) & Commissioning
SUB TOTAL F 2.33%

F PEKERJAAN PENGECATAN EKSTERNAL


Surface preparation : Sa 2 1/2
Jotun : Resist 78 - 75 μm, Penguard Midcoat - 200 μm, Hardtop XP - 50 μm
Garansi product & pekerjaan: 7 tahun

1 Surface preparation (Material: Garnett) 1.00 ls 1451.415 m2 11.68% 5-Mar-21 4-Apr-21 30 days 2.92% 2.92% 2.92% 2.92%
2 Re-painting 1.00 ls 1451.415 m2 11.68% 7-Mar-21 21-Apr-21 45 days 1.95% 1.95% 1.95% 1.95% 1.95% 1.95%
- Projection plate, handrail, pipa foam & hydrant, tangga, nozzle
- Identifikasi tangka
- 3 Logo (2 dinding & 1 atap)
- Diameter logo: dinding (1/4 tinggi tangki), atap (1/3 diameter atap)
- Lapisan tahan bahan kimia / anti selip untuk tangga, keliling atap
tangki sisi handrail (lebar 1 meter), dan disekitar roof manhole
SUB TOTAL G 23.35%

G PEKERJAAN INTERNAL COATING


Surface preparation : Sa 2 1/2
Jotun : Tankguard SF 2x500 micron
1 Surface preparation 1.00 ls 496.591 m2 3.99% 14-Mar-21 8-Apr-21 25 days 1.00% 1.00% 1.00% 1.00%
2 Re-painting 1.00 ls 496.591 m2 3.99% 26-Mar-21 30-Apr-21 35 days 0.80% 0.80% 0.80% 0.80% 0.80%
SUB TOTAL H 7.99%

H GENERAL WORKS
1 Pembuatan Pembatas kaki Stilling well pada bottom Plate Tangki 1.00 ls 0.11% 24-Feb-21 26-Feb-21 2 days 0.11%
2 Modifikasi support menjadi adjustable pipe support 1.00 ls 0.84% 1-Mar-21 11-Mar-21 10 days 0.42% 0.42%
SUB TOTAL J 0.95%

100.00% RENCANA PROGRESS 2.85% 3.46% 25.95% 21.53% 16.30% 9.31% 5.86% 6.66% 3.74% 2.74% 0.80% 0.80%
RENCANA KUMULA 0% 2.85% 6.30% 32.25% 53.77% 70.08% 79.39% 85.25% 91.91% 95.66% 98.40% 99.20% 100.00%
AKTUAL PROGRESS
AKTUAL KUMULATI 0%

Page 8 of 10
TIMELINE

Project ID : 212401
PEKERJAAN : T-06 Repair 15-Feb-21 1-May-21 75 days
LOKASI : TERMINAL AKR Stagen 15-Feb-21 30-Apr-21 74 days

NO URAIAN PEKERJAAN VOL SAT Breakdown SAT BOBOT (%) START DATE END DATE REMARKS MONTH Feb-21 Mar-21 Apr-21 May-21
Volume WEEK 1 2 3 4 5 6 7 8 9 10 11 12
2/15/2021 2/18/2021 2/25/2021 3/4/2021 3/11/2021 3/18/2021 3/25/2021 4/1/2021 4/8/2021 4/15/2021 4/22/2021 4/29/2021
DATE
2/17/2021 2/24/2021 3/3/2021 3/10/2021 3/17/2021 3/24/2021 3/31/2021 4/7/2021 4/14/2021 4/21/2021 4/28/2021 5/5/2021
A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Tenaga Kerja, Alat dan Material 1.00 ls 1.16% 15-Feb-21 27-Feb-21 12 days 0.39% 0.39% 0.39%
2 Alat Pelindung Diri (APD) sesuai Contractor Safety Management System 1.00 ls 1.47% 15-Feb-21 27-Feb-21 12 days 0.49% 0.49% 0.49%
3 Listrik dan Air Kerja 1.00 ls 0.68% 15-Feb-21 27-Feb-21 12 days 0.23% 0.23% 0.23%
4 Direksi keet, gudang kontraktor, dan alat bantu kerja 1.00 ls 0.36% 15-Feb-21 25-Feb-21 10 days 0.12% 0.12% 0.12%
5 Biaya Kebersihan, Ijin Kerja dan Koordinasi 1.00 ls 0.61% 15-Feb-21 25-Feb-21 10 days 0.20% 0.20% 0.20%
6 Dokumentasi, shop drawing, as built drawing, reporting 1.00 ls 0.61% 15-Feb-21 27-Feb-21 12 days 0.20% 0.20% 0.20%
7 Rapid Test 1.00 ls 2.70% 15-Feb-21 25-Feb-21 10 days 0.90% 0.90% 0.90%
8 MCU 1.00 ls 0.95% 15-Feb-21 25-Feb-21 10 days 0.32% 0.32% 0.32%
SUB TOTAL A 8.54%

B BOTTOM PLATE PATCHING


1 Patching dengan pelat 10 mm 34.00 ttk 25.06% 21-Feb-21 10-Mar-21 17 days 12.53% 12.53%
a Fit-up 22-Feb-21 4-Mar-21 10 days
b Welding 23-Feb-21 6-Mar-21 11 days
2 NDE Test (Visual, Penetrant, Vacuum) 1.00 ls 1.36% 7-Mar-21 21-Mar-21 14 days 0.68% 0.68%
SUB TOTAL B 26.42%

C BOTTOM PLATE & TANKSUMP REPLACEMENT


1 Bongkar & ganti pelat Tank Sump (tebal 14mm) 1.00 ls 2.58% 23-Feb-21 12-Mar-21 17 days 0.52% 0.52% 0.52% 0.52% 0.52%
Include surface preparation & coating coal tar epoxy
2 Bongkar & ganti pelat (tebal 12 mm) 13.00 ls 81.765 m2 13.53% 23-Feb-21 13-Mar-21 18 days 2.71% 2.71% 2.71% 2.71% 2.71%
Include surface preparation & coating coal tar epoxy
3 Replace aspal 1.00 ls 81.765 m2 1.47% 25-Feb-21 12-Mar-21 15 days 0.29% 0.29% 0.29% 0.29% 0.29%
4 Pembuatan akses (roof/doorsheet) 1.00 ls 8.15% 25-Feb-21 14-Mar-21 17 days 2.72% 2.72% 2.72%
- Scaffolding 25-Feb-21 4-Mar-21 7 days
- Fit-up 1-Mar-21 6-Mar-21 5 days
- Welding 13-Mar-21 15-Mar-21 2 days
5 NDE Test (Visual, Penetrant, MPI, Radiografi & Vacuum) 12-Mar-21 17-Mar-21 5 days
a. Bottom Plate (Visual, Penetrant 100%, Vacuum 100%) 1.00 ls 2.05% 15-Mar-21 18-Mar-21 3 days 2.05%
b. Tank Sump (Visual, MPI, Vacuum 100%) 1.00 ls 1.76% 11-Mar-21 14-Mar-21 3 days 1.76%
c. Roof opening (Visual, Penetrant 100%, Vacuum 100%) 1.00 ls 0.72% 15-Mar-21 18-Mar-21 3 days 0.72%
SUB TOTAL C 30.26%

D DRAIN PIPE REPAIR & MODIF


1 Penambahan pipa product drain 4" (30cm) 1.00 ls 0.08% 25-Feb-21 3-Mar-21 6 days 0.08%
2 Penggantian seluruh pipe support untuk Product-drain & water-drain 1.00 ls 0.08% 25-Feb-21 3-Mar-21 6 days 0.08%
SUB TOTAL D 0.16%

E PEKERJAAN MODIFIKASI PIPA FOAM CHAMBER


1 Modifikasi pipa foam chamber 1.00 ls 1.22% 18-Feb-21 25-Feb-21 7 days 0.61% 0.61%
2 NDE Test 1.00 ls 1.11% 23-Feb-21 27-Feb-21 4 days 1.11%
(Visual, Penetrant, UT) & Commissioning
SUB TOTAL F 2.33%

F PEKERJAAN PENGECATAN EKSTERNAL


Surface preparation : Sa 2 1/2
Jotun : Resist 78 - 75 μm, Penguard Midcoat - 200 μm, Hardtop XP - 50 μm
Garansi product & pekerjaan: 7 tahun

1 Surface preparation (Material: Garnett) 1.00 ls 1451.415 m2 11.68% 5-Mar-21 4-Apr-21 30 days 2.92% 2.92% 2.92% 2.92%
2 Re-painting 1.00 ls 1451.415 m2 11.68% 7-Mar-21 21-Apr-21 45 days 1.95% 1.95% 1.95% 1.95% 1.95% 1.95%
- Projection plate, handrail, pipa foam & hydrant, tangga, nozzle
- Identifikasi tangka
- 3 Logo (2 dinding & 1 atap)
- Diameter logo: dinding (1/4 tinggi tangki), atap (1/3 diameter atap)
- Lapisan tahan bahan kimia / anti selip untuk tangga, keliling atap
tangki sisi handrail (lebar 1 meter), dan disekitar roof manhole
SUB TOTAL G 23.35%

G PEKERJAAN INTERNAL COATING


Surface preparation : Sa 2 1/2
Jotun : Tankguard SF 2x500 micron
1 Surface preparation 1.00 ls 496.591 m2 3.99% 14-Mar-21 8-Apr-21 25 days 1.00% 1.00% 1.00% 1.00%
2 Re-painting 1.00 ls 496.591 m2 3.99% 26-Mar-21 30-Apr-21 35 days 1.00% 1.00% 1.00% 1.00%
SUB TOTAL H 7.99%

H GENERAL WORKS
1 Pembuatan Pembatas kaki Stilling well pada bottom Plate Tangki 1.00 ls 0.11% 24-Feb-21 26-Feb-21 2 days 0.11%
2 Modifikasi support menjadi adjustable pipe support 1.00 ls 0.84% 1-Mar-21 11-Mar-21 10 days 0.42% 0.42%
SUB TOTAL J 0.95%

100.00% RENCANA PROGRESS 2.85% 2.85% 18.61% 15.76% 11.10% 9.06% 9.06% 9.63% 9.20% 8.89% 2.00% 1.00%
RENCANA KUMULA 0% 2.85% 5.69% 24.30% 40.07% 51.16% 60.22% 69.28% 78.91% 88.11% 97.00% 99.00% 100.00%
AKTUAL PROGRESS
AKTUAL KUMULATI 0%

Page 9 of 10
TIMELINE
Project ID : 212401
PEKERJAAN : T-06 Repair 15-Feb-21 1-May-21 75 days
LOKASI : TERMINAL AKR Stagen 15-Feb-21 30-Apr-21 74 days

NO URAIAN PEKERJAAN VOL SAT Breakdown SAT BOBOT START DATE END DATE REMARKS DURATION MINGGU LALU MINGGU INI KUMULATIF MIGGUAN
Volume (%)

A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Tenaga Kerja, Alat dan Material 1.00 ls 1.16% 15-Feb-21 27-Feb-21 12 days
2 Alat Pelindung Diri (APD) sesuai Contractor Safety Management System 1.00 ls 1.47% 15-Feb-21 27-Feb-21 12 days
3 Listrik dan Air Kerja 1.00 ls 0.68% 15-Feb-21 27-Feb-21 12 days
4 Direksi keet, gudang kontraktor, dan alat bantu kerja 1.00 ls 0.36% 15-Feb-21 25-Feb-21 10 days
5 Biaya Kebersihan, Ijin Kerja dan Koordinasi 1.00 ls 0.61% 15-Feb-21 25-Feb-21 10 days
6 Dokumentasi, shop drawing, as built drawing, reporting 1.00 ls 0.61% 15-Feb-21 27-Feb-21 12 days
7 Rapid Test 1.00 ls 2.70% 15-Feb-21 25-Feb-21 10 days
8 MCU 1.00 ls 0.95% 15-Feb-21 25-Feb-21 10 days
SUB TOTAL A 8.54%

B BOTTOM PLATE PATCHING


1 Patching dengan pelat 10 mm 34.00 ttk 25.06% 21-Feb-21 10-Mar-21 17 days
a Fit-up 22-Feb-21 4-Mar-21 10 days
b Welding 23-Feb-21 6-Mar-21 11 days
2 NDE Test (Visual, Penetrant, Vacuum) 1.00 ls 1.36% 7-Mar-21 21-Mar-21 14 days
SUB TOTAL B 26.42%

C BOTTOM PLATE & TANKSUMP REPLACEMENT


1 Bongkar & ganti pelat Tank Sump (tebal 14mm) 1.00 ls 2.58% 23-Feb-21 12-Mar-21 17 days
Include surface preparation & coating coal tar epoxy
2 Bongkar & ganti pelat (tebal 12 mm) 13.00 ls 81.765 m2 13.53% 23-Feb-21 13-Mar-21 18 days
Include surface preparation & coating coal tar epoxy
3 Replace aspal 1.00 ls 81.765 m2 1.47% 25-Feb-21 12-Mar-21 15 days
4 Pembuatan akses (roof/doorsheet) 1.00 ls 8.15% 25-Feb-21 14-Mar-21 17 days
- Scaffolding 25-Feb-21 4-Mar-21 7 days
- Fit-up 1-Mar-21 6-Mar-21 5 days
- Welding 13-Mar-21 15-Mar-21 2 days
5 NDE Test (Visual, Penetrant, MPI, Radiografi & Vacuum) 12-Mar-21 17-Mar-21 5 days
a. Bottom Plate (Visual, Penetrant 100%, Vacuum 100%) 1.00 ls 2.05% 15-Mar-21 18-Mar-21 3 days
b. Tank Sump (Visual, MPI, Vacuum 100%) 1.00 ls 1.76% 11-Mar-21 14-Mar-21 3 days
c. Roof opening (Visual, Penetrant 100%, Vacuum 100%) 1.00 ls 0.72% 15-Mar-21 18-Mar-21 3 days
SUB TOTAL C 30.26%

D DRAIN PIPE REPAIR & MODIF


1 Penambahan pipa product drain 4" (30cm) 1.00 ls 0.08% 25-Feb-21 3-Mar-21 6 days
2 Penggantian seluruh pipe support untuk Product-drain & water-drain 1.00 ls 0.08% 25-Feb-21 3-Mar-21 6 days
SUB TOTAL D 0.16%

E PEKERJAAN MODIFIKASI PIPA FOAM CHAMBER


1 Modifikasi pipa foam chamber 1.00 ls 1.22% 18-Feb-21 25-Feb-21 7 days
2 NDE Test 1.00 ls 1.11% 23-Feb-21 27-Feb-21 4 days
(Visual, Penetrant, Radiography) & Commissioning
SUB TOTAL F 2.33%

F PEKERJAAN PENGECATAN EKSTERNAL


Surface preparation : Sa 2 1/2
Jotun : Resist 78 - 75 μm, Penguard Midcoat - 200 μm, Hardtop XP - 50 μm
Garansi product & pekerjaan: 7 tahun

1 Surface preparation (Material: Garnett) 1.00 ls 1451.415 m2 11.68% 5-Mar-21 4-Apr-21 30 days
2 Re-painting 1.00 ls 1451.415 m2 11.68% 7-Mar-21 21-Apr-21 45 days
- Projection plate, handrail, pipa foam & hydrant, tangga, nozzle
- Identifikasi tangka
- 3 Logo (2 dinding & 1 atap)
- Diameter logo: dinding (1/4 tinggi tangki), atap (1/3 diameter atap)
- Lapisan tahan bahan kimia / anti selip untuk tangga, keliling atap
tangki sisi handrail (lebar 1 meter), dan disekitar roof manhole
SUB TOTAL G 23.35%

G PEKERJAAN INTERNAL COATING


Surface preparation : Sa 2 1/2
Jotun : Tankguard SF 2x500 micron
1 Surface preparation 1.00 ls 496.591 m2 3.99% 14-Mar-21 8-Apr-21 25 days
2 Re-painting 1.00 ls 496.591 m2 3.99% 26-Mar-21 30-Apr-21 35 days
SUB TOTAL H 7.99%

H GENERAL WORKS
1 Pembuatan Pembatas kaki Stilling well pada bottom Plate Tangki 1.00 ls 0.11% 24-Feb-21 26-Feb-21 2 days
2 Modifikasi support menjadi adjustable pipe support 1.00 ls 0.84% 1-Mar-21 11-Mar-21 10 days
SUB TOTAL J 0.95%

100.00% TOTAL 0% 0% 0%