KUTAI KARTANEGARA
PROGRAM : PENGADAAN, PENINGKATAN DAN PERBAIKAN SARANA DAN PRASARANA
PUSKESMAS PEMBATU DAN JARINGANNYA
KEGIATAN : PEMBANGUNAN PUSKESMAS PEMBANTU KEDANG IPIL
LOKASI : KEC. KOTA BANGUN
TAHUN : 2013
A. UPAH KERJA
1 Pekerja OH 70,000.0
2 Tukang Kayu OH 90,000.0
3 Kepala Tukang Kayu OH 100,000.0
4 Tukang Cat OH 90,000.0
5 Kepala Tukang Cat OH 100,000.0
6 Tukang Batu OH 90,000.0
7 Kepala Tukang Batu OH 100,000.0
8 Tukang Besi OH 90,000.0
9 Kepala Tukang Besi OH 100,000.0
10 Tukang Atap Baja Ringan OH 90,000.0
11 Kepala Tukang Atap Baja Ringan OH 100,000.0
12 Mandor OH 125,000.0
B. HARGA BAHAN
B1 Aggregat Kasar & Bahan Perkerasan
1 Batu Bata Bh 1,100.0
2 Batu Belah 15/20 m3 350,000.0
3 Batu Gunung m3 350,000.0
4 Batu Pecah Palu m3 550,000.0
5 Batu Koral Long iram m3 500,000.0
6 Koral Beton m3 525,000.0
7 Pasir Beton m3 150,000.0
8 Pasir Pasang m3 125,000.0
9 Pasir Urug m3 125,000.0
10 Semen Kg 1,500.0
11 Semen Warna Kg 6,000.0
12 Tanah Urug m3 50,000.0
B2 BAHAN FINISHING
1 Cat Antara Besi Kg 70,000.0
2 Cat Besi Kg 80,000.0
3 Cat Meni Kayu Kg 40,000.0
4 Cat Dasar Tembok Kg 30,000.0
5 Cat Penutup Tembok Kg 30,000.0
6 Cat penutup Kayu Kg 80,000.0
7 Dempul Ltr 15,000.0
8 Plamir Kg 15,000.0
9 Vernis Ltr 70,000.0
10 Residu atau Ter Ltr 20,000.0
11 Kuas Bh 15,000.0
No. URAIAN JENIS JASA / BARANG SATUAN HARGA SATUAN (Rp)
B3 BAHAN KAYU
1 Kayu Bengkirai (balok) m3 3,250,000.0
2 Kayu Bengkirai (papan) m3 3,500,000.0
3 Kayu Kapur ( Balok ) m3 5,000,000.0
4 Kayu Kapur ( Papan ) m3 5,500,000.0
5 Kayu Kapur ( Reng ) m3 4,500,000.0
6 Kayu Meranti ( Balok ) m3 2,750,000.0
7 Kayu Meranti ( Papan ) m' 3,000,000.0
8 Kayu Profil m1 20,000.0
9 List Gypsum Profil m1 25,000.0
10 Kayu Ulin ( Balok ) m3 3,500,000.0
11 Kayu Ulin ( Papan ) m3 3,750,000.0
12 Gypsum t. 9 mm Lbr 60,000.0
13 Plywood t. 6mm Lbr 65,000.0
14 Plywood tebal 9 mm Lbr 125,000.0
15 Dolken Kayu dia. 8-400 cm Btg 20,000.0
16 Kayu Kruing (Balok ) m3 2,800,000.0
17 Kayu Kruing ( Papan ) m3 3,100,000.0
18 Kayu Kruing ( Reng ) m3 2,500,000.0
19 Plywood t. 3,6 mm Lbr 45,000.0
20 Lem Kaayu ex Fox Kg 25,000.0
B5 Bahan Kaca
1 Kaca Polos 5 mm m2 175,000.0
2 Kaca Polos 8 mm m2 300,000.0
3 Kaca Polos Nako 5 mm m2 175,000.0
4 Kaca Rip Dark Blue Standard 5 mm m2 200,000.0
5 Kaca Rip Dark Blue Nako Standard 5 mm m2 200,000.0
6 Kaca Buram 5 mm m3 250,000.0
7 Stiker Sandblast m1 75,000.0
No. URAIAN JENIS JASA / BARANG SATUAN HARGA SATUAN (Rp)