JADWAL WAKTU PELAKSANAAN

RENOVASI RUANG KERJA KANTOR DITJEN KEBUDAYAAN ( 2 Lantai )

Waktu Pelaksanaan : 45 (Empat Puluh Lima) Hari Kalender


Minggu Ke :
No Jenis Pekerjaan Jumlah Bobot 1 2 3 4 5 6 7 Ket
Rp. % Hari Ke :
1 s/d 7 8 s/d 14 15 s/d 21 22 s/d 28 29 s/d 35 36 s/d 42 43 s/d 45
100,000
I PEKERJAAN PERSIAPAN & SMK3K 167,452,250.55 3.538 0.590 0.590 0.590 0.590 0.590 0.590

90,000
II PEKERJAAN BONGKARAN
II . A LANTAI 9 60,485,471.48 1.278 Chart
1.278 Title
II . B LANTAI 10 57,626,635.51 1.217 1.217 80,000
III PEKERJAAN ARSITEKTUR - INTERIOR
III . A LANTAI 9
70,000
III . A . 1 PEK. DINDING DAN PARTISI 308,961,398.96 6.527 3.264 3.264

P
III . A . 2 PEK. KUSEN PINTU DAN JENDELA 338,350,318.00 7.148 3.574 3.574

III . A . 3 PEK. PENUTUP LANTAI DAN DINDING 222,146,525.33 4.693 2.347 2.347 60,000
III . A . 4 PEK. PLAFOND DAN PENGGANTUNG 283,639,334.34 5.992 2.996 2.996

III . A . 5 PEK. PENGECATAN DAN FINISHING DINDING 168,905,635.39 3.568 1.784 1.784

H
III . A . 6 PEK. FURNITURE INTERIOR MELEKAT 188,427,561.05 3.981 1.990 1.990 50,000
III . A . 7 PEK. LAIN-LAIN 120,380,591.76 2.543 1.272 1.272

III . B LANTAI 10 -
40,000
III . B . 1 PEK. DINDING DAN PARTISI 419,187,987.55 8.856 4.428 4.428

O
III . B . 2 PEK. KUSEN PINTU DAN JENDELA 292,826,379.00 6.186 3.093 3.093

III . B . 3 PEK. PENUTUP LANTAI DAN DINDING 277,337,061.89 5.859 2.930 2.930 30,000
III . B . 4 PEK. PLAFOND DAN PENGGANTUNG 303,177,185.73 6.405 3.203 3.203

III . B . 5 PEK. PENGECATAN DAN FINISHING DINDING 212,697,785.07 4.494 2.247 2.247

III . B . 6 PEK. FURNITURE INTERIOR MELEKAT 225,559,179.65 4.765 2.383 2.383


20,000
III . B . 7 PEK. LAIN-LAIN 178,534,257.76 3.772 1.886 1.886

IV PEKERJAAN ELEKTRIKAL
10,000
IV . A LANTAI 9 484,313,970.00 10.232 5.116 5.116

IV . B LANTAI 10 423,356,379.00 8.944 4.472 4.472

0,000
JUMLAH 4,733,365,908.00 100.00
PROGRESS MINGGUAN % (%) 3.085 12.770 31.470 30.921 16.693 5.062 -
KOMULATIF MINGGUAN % (%) 3.085 15.855 47.325 78.245 94.938 100.000 100.000

Jakarta, 28 Oktober 2020


PT. PUBAGOT JAYA ABADI

TTD

PANIHA HUTAHAYAN
Direktur Utama
Formulir Rekapitulasi Perhitungan Tingkat Komponen Dalam Negeri
(TKDN)

Nilai Gabungan Barang/Jasa (Rp) TKDN


Uraian Pekerjaan TOTAL Barang/
DN LN Gabungan
Ribu Rp % KDN Jasa
(1) (2) (3) (4) (5) (7) (8)
Barang
I. Material Langsung (Bahan Baku) 3,408,023,453.76 - 3,408,023,453.76 100% 3,408,023,453.76 72.00%
II. Peralatan (Barang Jadi) - - - - - -
A. Sub-Total Barang 3,408,023,453.76 - 3,408,023,453.76 3,408,023,453.76 72.00%
Jasa
III. Manajemen Proyek dan 118,334,147.70 - 118,334,147.70 100% 118,334,147.70 2.50%
Perekayasaan
IV. Alat Kerja/Fasilitas Kerja 1,207,008,306.54 - 1,207,008,306.54 100% 1,207,008,306.54 25.50%
V. Konstruksi dan Fabrikasi - - - - - -
VI. Jasa Umum - - - - - -
B. Sub-Total Jasa 1,325,342,454.24 - 1,325,342,454.24 1,325,342,454.24 28.00%

C. TOTAL Biaya (A+B) 4,733,365,908.00 - 4,733,365,908.00 4,733,365,908.00 100.00%

Jakarta, 28 Oktober 2020


PT. PUBAGOT JAYA ABADI

TTD

PANIHA HUTAHAYAN
Direktur Utama
SPESIFIKASI TEKNIS

NO NAMA BAHAN/MATERIAL SAT MERK / TYPE


1 Pasir Pasang m3 Sesuai spesifikasi teknis yang disyaratkan
2 Bata Merah bh Sesuai spesifikasi teknis yang disyaratkan
3 Dolken kayu Ø 8-10 cm/400 cm btg Sesuai spesifikasi teknis yang disyaratkan
4 Kayu m3 Sesuai spesifikasi teknis yang disyaratkan
5 Paku biasa kg Sesuai spesifikasi teknis yang disyaratkan
6 Paku tripek kg Sesuai spesifikasi teknis yang disyaratkan
7 Semen Portland kg Sesuai spesifikasi teknis yang disyaratkan
8 Pasir beton m3 Sesuai spesifikasi teknis yang disyaratkan
9 Koral beton m3 Sesuai spesifikasi teknis yang disyaratkan
10 Batu Koral Putih krg Sesuai spesifikasi teknis yang disyaratkan
11 Seng gelombang lbr Sesuai spesifikasi teknis yang disyaratkan
12 Jendela nako bh Sesuai spesifikasi teknis yang disyaratkan
13 Triplek 4mm lbr Sesuai spesifikasi teknis yang disyaratkan
14 Gypsum Board 9 mm lbr Sesuai spesifikasi teknis yang disyaratkan
15 Gypsum Board 12 mm lbr Sesuai spesifikasi teknis yang disyaratkan
16 Rockwool, density 60 kg/m3 m2 Sesuai spesifikasi teknis yang disyaratkan
17 Kayu Klas III m3 Sesuai spesifikasi teknis yang disyaratkan
18 Kayu Kamper m3 Sesuai spesifikasi teknis yang disyaratkan
19 Kayu solid wood filler jati uk. 40x40 mm m3 Sesuai spesifikasi teknis yang disyaratkan
20 Bambu ampel 1/2 Ø 10 cm m1 Sesuai spesifikasi teknis yang disyaratkan
21 Bambu ampel 1/2 Ø 5 cm m1 Sesuai spesifikasi teknis yang disyaratkan
22 Besi polos kg Sesuai spesifikasi teknis yang disyaratkan
23 Besi plat strip kg Sesuai spesifikasi teknis yang disyaratkan
24 Pipa Besi 2" btg Sesuai spesifikasi teknis yang disyaratkan
25 Paku Ramset bh Sesuai spesifikasi teknis yang disyaratkan
26 Skrup Gypsum kg Sesuai spesifikasi teknis yang disyaratkan
27 Textile Gypsum roll Sesuai spesifikasi teknis yang disyaratkan
28 Compound Gypsum zak Sesuai spesifikasi teknis yang disyaratkan
29 Compound Gypsum kg Sesuai spesifikasi teknis yang disyaratkan
30 Shadowline btg Sesuai spesifikasi teknis yang disyaratkan
31 Shadowline m' Sesuai spesifikasi teknis yang disyaratkan
32 Solar ltr Sesuai spesifikasi teknis yang disyaratkan
33 Triplex 6 mm lbr Sesuai spesifikasi teknis yang disyaratkan
34 Multiplex 9 mm lbr Sesuai spesifikasi teknis yang disyaratkan
35 Multiplex 15 mm lbr Sesuai spesifikasi teknis yang disyaratkan
36 Multiplex 12 mm lbr Sesuai spesifikasi teknis yang disyaratkan
37 Multiplex 18 mm lbr Sesuai spesifikasi teknis yang disyaratkan
38 Multiplex 20 mm lbr Sesuai spesifikasi teknis yang disyaratkan
39 Solid surface tebal 2 cm, warna hitam m2 Sesuai spesifikasi teknis yang disyaratkan
40 Milaminto 3 mm lbr Sesuai spesifikasi teknis yang disyaratkan
41 Banner m2 Sesuai spesifikasi teknis yang disyaratkan
42 Stiker sandblast m2 Sesuai spesifikasi teknis yang disyaratkan
43 Rangka Hollow besi 40x40x1,7x6000mm btg Sesuai spesifikasi teknis yang disyaratkan
44 Metal stud uk. 34x76 mm tbl. 0,40 mm m1 Sesuai spesifikasi teknis yang disyaratkan
45 U runner uk. 25x76 mm tbl. 0,35 mm m1 Sesuai spesifikasi teknis yang disyaratkan
46 Aluminium "U" uk. 20x20x2 mm m1 Sesuai spesifikasi teknis yang disyaratkan
47 Hosplin AAE (Hospital Plint Aluminium Alloy Extrussion) m1 Sesuai spesifikasi teknis yang disyaratkan
48 Hollow galvalum, uk. 40/40 mm, t=0,3 mm m1 Sesuai spesifikasi teknis yang disyaratkan
49 Hollow galvalum, uk. 20/40 mm t=0,3 mm m1 Sesuai spesifikasi teknis yang disyaratkan
50 Rangka besi hollow 50x100 mm, tebal 1,8 mm m1 Sesuai spesifikasi teknis yang disyaratkan
51 Rangka dudukan ornamen besi hollow 20x40 mm, tebal 1,4 mm m1 Sesuai spesifikasi teknis yang disyaratkan
52 Base plate uk. 10x15 cm, tebal 5 mm + pengelasan m1 Sesuai spesifikasi teknis yang disyaratkan
53 Dynabolt M-8 m1 Sesuai spesifikasi teknis yang disyaratkan
54 Rangka besi hollow galvanis uk. 40x40 mm, tebal 1,4 mm m1 Sesuai spesifikasi teknis yang disyaratkan
55 Plat stainless steel hairline lebar 10 cm, tebal 1,5 mm lbr Sesuai spesifikasi teknis yang disyaratkan
56 MDF 15 mm m2 Sesuai spesifikasi teknis yang disyaratkan
NO NAMA BAHAN/MATERIAL SAT MERK / TYPE
57 MDF 20 mm m2 Sesuai spesifikasi teknis yang disyaratkan
58 Cutting Laer m2 Sesuai spesifikasi teknis yang disyaratkan
59 Wallpaper, goodrich m2 Sesuai spesifikasi teknis yang disyaratkan
60 Glass stone tebal 8 mm, warna putih susu m2 Sesuai spesifikasi teknis yang disyaratkan
61 Kawat Las kg Sesuai spesifikasi teknis yang disyaratkan
62 Skrup kg Sesuai spesifikasi teknis yang disyaratkan
63 Meni besi kg Sesuai spesifikasi teknis yang disyaratkan
64 Amplas m' Sesuai spesifikasi teknis yang disyaratkan
65 Lantai vinyl TACO uk. 304,8 x 609,6 x 3 mm grey slate m2 Sesuai spesifikasi teknis yang disyaratkan
66 Lantai vinyl TACO uk. 152,4 x 914,4 x 3 mm washed oak m2 Sesuai spesifikasi teknis yang disyaratkan
67 Lem kg Sesuai spesifikasi teknis yang disyaratkan
68 GRC cetak bulat m2 Sesuai spesifikasi teknis yang disyaratkan
69 Lem beton kg Sesuai spesifikasi teknis yang disyaratkan
70 Wood filler kg Sesuai spesifikasi teknis yang disyaratkan
71 Politur kg Sesuai spesifikasi teknis yang disyaratkan
72 Thinner kg Sesuai spesifikasi teknis yang disyaratkan
73 HPL m2 Sesuai spesifikasi teknis yang disyaratkan
74 Lem kuning kg Sesuai spesifikasi teknis yang disyaratkan
75 Cat Besi Duco kg Sesuai spesifikasi teknis yang disyaratkan
76 Dempul Duco kg Sesuai spesifikasi teknis yang disyaratkan
77 List Plywood 9 mm finish melamic m Sesuai spesifikasi teknis yang disyaratkan
78 Kayu kamper solid uk. 20x30 mm m3 Sesuai spesifikasi teknis yang disyaratkan
79 Cat Dasar kg Sesuai spesifikasi teknis yang disyaratkan
80 Cat Penutup Ex. Jotun kg Sesuai spesifikasi teknis yang disyaratkan
81 Roll cat bh Sesuai spesifikasi teknis yang disyaratkan
82 Kwas 3" bh Sesuai spesifikasi teknis yang disyaratkan
83 Plamur/compound kg Sesuai spesifikasi teknis yang disyaratkan
84 Profil aluminium 4" powder coating m1 Sesuai spesifikasi teknis yang disyaratkan
85 Aluminium 3" Powder coating btg Sesuai spesifikasi teknis yang disyaratkan
86 Profil frame daun pintu aluminium powder coating m1 Sesuai spesifikasi teknis yang disyaratkan
87 Sealent btl Sesuai spesifikasi teknis yang disyaratkan
88 Kunci tanam bh Sesuai spesifikasi teknis yang disyaratkan
89 Pull handle SS-304 38x630x600 mm TPH 981 bh Sesuai spesifikasi teknis yang disyaratkan
90 Pull Handle SS 32x300 mm PH 801 bh Sesuai spesifikasi teknis yang disyaratkan
91 Pull handle SS-304 38x1200 mm PH 802 bh Sesuai spesifikasi teknis yang disyaratkan
92 Floor hinge FH 80 SSS bh Sesuai spesifikasi teknis yang disyaratkan
93 Top patch PT 20 bh Sesuai spesifikasi teknis yang disyaratkan
94 Patch fitting PT 40 bh Sesuai spesifikasi teknis yang disyaratkan
95 Bottom patch PT 10 bh Sesuai spesifikasi teknis yang disyaratkan
96 Corner lock/Patch lock US 10 bh Sesuai spesifikasi teknis yang disyaratkan
97 Mortise lock set Sesuai spesifikasi teknis yang disyaratkan
98 Escutcheon bh Sesuai spesifikasi teknis yang disyaratkan
99 Cylinder + kunci set Sesuai spesifikasi teknis yang disyaratkan
100 Sealant kaca m1 Sesuai spesifikasi teknis yang disyaratkan
101 Door closer Dekkson 40 kg bh Sesuai spesifikasi teknis yang disyaratkan
102 Lever handle dekkson LHTR 39 psg Sesuai spesifikasi teknis yang disyaratkan
103 Engsel pintu stainless 4" dekson set Sesuai spesifikasi teknis yang disyaratkan
104 Rell laci panjang 40 cm bh Sesuai spesifikasi teknis yang disyaratkan
105 Engsel sendok lemari bh Sesuai spesifikasi teknis yang disyaratkan
106 Handle lemari + laci bh Sesuai spesifikasi teknis yang disyaratkan
107 Magnet Door Stoper Stainless Steel bh Sesuai spesifikasi teknis yang disyaratkan
108 Panel sliding aluminium uk. 210x91 cm + kaca tb. 8 mm bh Sesuai spesifikasi teknis yang disyaratkan
109 Panel sliding aluminium uk. 260x80 cm + kaca tb. 8 mm bh Sesuai spesifikasi teknis yang disyaratkan
110 Panel sliding uk. 104x260 cm bh Sesuai spesifikasi teknis yang disyaratkan
111 Pintu box 3 daun set Sesuai spesifikasi teknis yang disyaratkan
112 Sound barrier m1 Sesuai spesifikasi teknis yang disyaratkan
113 Box penyimpanan, aksessoris tambahan ls Sesuai spesifikasi teknis yang disyaratkan
114 Track runner set Sesuai spesifikasi teknis yang disyaratkan
NO NAMA BAHAN/MATERIAL SAT MERK / TYPE
115 Finishing powder coating super white gloss 160 m1 Sesuai spesifikasi teknis yang disyaratkan
116 Kaca bening 5mm m2 Sesuai spesifikasi teknis yang disyaratkan
117 Kaca polos 6 mm m2 Sesuai spesifikasi teknis yang disyaratkan
118 Kaca polos, tebal 8 mm m2 Sesuai spesifikasi teknis yang disyaratkan
119 Kaca painted glass stone, tebal 8 mm warna putih m2 Sesuai spesifikasi teknis yang disyaratkan
120 Kaca polos 3 mm m2 Sesuai spesifikasi teknis yang disyaratkan
121 Kaca tempered, tebal 12 mm m2 Sesuai spesifikasi teknis yang disyaratkan
122 Karpet Tile 50x50 merk. SMJ tipe Natural Evolution #13 m2 Sesuai spesifikasi teknis yang disyaratkan
123 Roll Blinds m Sesuai spesifikasi teknis yang disyaratkan
124 Plywood 12 mm + rangka finish melamic m2 Sesuai spesifikasi teknis yang disyaratkan
125 Kusen kayu solid oven 5x10cm finish melamic m Sesuai spesifikasi teknis yang disyaratkan
126 Insulasi pipa armaflex uk. 3/8" m2 Sesuai spesifikasi teknis yang disyaratkan
127 Klem kabel bh Sesuai spesifikasi teknis yang disyaratkan
128 CD copy soft file foto image bh Sesuai spesifikasi teknis yang disyaratkan
129 Cetak foto lbr Sesuai spesifikasi teknis yang disyaratkan
130 Album foto ls Sesuai spesifikasi teknis yang disyaratkan
131 Kamera DSLR Sewa/Hr Sesuai spesifikasi teknis yang disyaratkan
132 Pipa Conduit d 20 mm ex Clipsal m1 Sesuai spesifikasi teknis yang disyaratkan
133 Saklar Tunggal Schneider bh Sesuai spesifikasi teknis yang disyaratkan
134 Saklar Ganda Schneider bh Sesuai spesifikasi teknis yang disyaratkan
135 Stop Kontak ex. Broco bh Sesuai spesifikasi teknis yang disyaratkan
136 Lampu hidend lamp T5 8 watt P=60 cm,lengkap dengan instalasi unit Sesuai spesifikasi teknis yang disyaratkan
137 Lampu downlight dia. 6" cover kaca, LED 13 W Philips bh Sesuai spesifikasi teknis yang disyaratkan
138 Lampu downlight dia. 6" cover kaca, LED 10 W Philips bh Sesuai spesifikasi teknis yang disyaratkan
139 Pilot Lamp + Fuse (R/S/T) TELE (3 set) set Sesuai spesifikasi teknis yang disyaratkan
140 Amper Meter 0 ~ 100 A (3 bh) bh Sesuai spesifikasi teknis yang disyaratkan
141 Volt Meter 0 ~ 500 V (1 bh) bh Sesuai spesifikasi teknis yang disyaratkan
142 Volt Selector Switch/VSS (1 bh) bh Sesuai spesifikasi teknis yang disyaratkan
143 Trafo Arus CT 100/5A, GAE (3 bh) bh Sesuai spesifikasi teknis yang disyaratkan
144 MCCB 3P 100~250A 36KA/NSX-250F, Schneider (1 bh) bh Sesuai spesifikasi teknis yang disyaratkan
145 MCCB 3P 50~100A 25KA/NSX-100F, Schneider (2 bh) bh Sesuai spesifikasi teknis yang disyaratkan
146 Magnetik Kontaktror (MC) 80 A, Schneider (2 bh) bh Sesuai spesifikasi teknis yang disyaratkan
147 MCB 1P 10 A 5KA, Schneider (18 bh) bh Sesuai spesifikasi teknis yang disyaratkan
148 MCB 1P 16 A 7.5KA, Schneider (24 bh) bh Sesuai spesifikasi teknis yang disyaratkan
149 CU Busbar set Sesuai spesifikasi teknis yang disyaratkan
150 Box Panel 140 x 120 x 40 cm, Free standing bh Sesuai spesifikasi teknis yang disyaratkan
151 Kabel NYY 4 x 70 mm2 m1 Sesuai spesifikasi teknis yang disyaratkan
152 Kabel NYM 3 x 2,5 mm m1 Sesuai spesifikasi teknis yang disyaratkan
153 Kabel NYMHY 3 x 1,5 mm m1 Sesuai spesifikasi teknis yang disyaratkan
154 Tray Kabel uk. 400 x 100 x 3000 x 1,2 mm ( Galvanized ) m1 Sesuai spesifikasi teknis yang disyaratkan
155 Tray Kabel uk. 300 x 100 x 3000 x 1,2 mm ( Galvanized ) m1 Sesuai spesifikasi teknis yang disyaratkan
156 Equal Cross Tray U 400 x 100 mm bh Sesuai spesifikasi teknis yang disyaratkan
157 Tee Tray U 400 x 100 mm bh Sesuai spesifikasi teknis yang disyaratkan
158 Cover Tray U 400 x 100 mm m1 Sesuai spesifikasi teknis yang disyaratkan
159 Equal Cross Tray U 300 x 100 mm bh Sesuai spesifikasi teknis yang disyaratkan
160 Tee Tray U 300 x 100 mm bh Sesuai spesifikasi teknis yang disyaratkan
161 Cover Tray U 300 x 100 mm m1 Sesuai spesifikasi teknis yang disyaratkan
162 Pesawat Telepon Panasonic KX TS880 bh Sesuai spesifikasi teknis yang disyaratkan
163 Telepon Outlet bh Sesuai spesifikasi teknis yang disyaratkan
164 Ceiling Acces Point bh Sesuai spesifikasi teknis yang disyaratkan
165 Lan/data Outlet - Inbow bh Sesuai spesifikasi teknis yang disyaratkan
166 Rack Server Wallmount 8 U singledoor bh Sesuai spesifikasi teknis yang disyaratkan
167 Kabel ITC 1 x ( 2 x 0,6 mm2 ) m1 Sesuai spesifikasi teknis yang disyaratkan
168 Kabel STP cat 6E m1 Sesuai spesifikasi teknis yang disyaratkan
169 Kabel Coax RG6 m1 Sesuai spesifikasi teknis yang disyaratkan
170 Kabel Coax RG59 + Power m1 Sesuai spesifikasi teknis yang disyaratkan
171 Kabel Grounding BC 25 mm m1 Sesuai spesifikasi teknis yang disyaratkan
172 Saddle/Klem bh Sesuai spesifikasi teknis yang disyaratkan
NO NAMA BAHAN/MATERIAL SAT MERK / TYPE
173 Fresher dan Scrup bh Sesuai spesifikasi teknis yang disyaratkan
174 Flexible Conduit PVC 20 mm m1 Sesuai spesifikasi teknis yang disyaratkan
175 Tee Dos bh Sesuai spesifikasi teknis yang disyaratkan
176 Head sprinkler bh Sesuai spesifikasi teknis yang disyaratkan
177 Flexible round duct 8" bh Sesuai spesifikasi teknis yang disyaratkan
178 Diffuser bh Sesuai spesifikasi teknis yang disyaratkan
179 Return Air Grill (RAG) bh Sesuai spesifikasi teknis yang disyaratkan
180 Linear diffuser 1200x200 mm bh Sesuai spesifikasi teknis yang disyaratkan
181 Exhaust Air Grill (EAG) bh Sesuai spesifikasi teknis yang disyaratkan
182 Amplifier Mixer Power 120 W, Toa ZA 2120 bh Sesuai spesifikasi teknis yang disyaratkan
183 Multimedia Player Background Music Player, Toa Z CD 2011R bh Sesuai spesifikasi teknis yang disyaratkan
184 Speaker Selector 10 Channel 2 Input, Daya Input max. 1.000 watt bh Sesuai spesifikasi teknis yang disyaratkan
185 Mic Car Call / Pagging, Toa ZM 100EC Golden + Cadangan bh Sesuai spesifikasi teknis yang disyaratkan
186 Rack Audio System Toa 12 U Roda bh Sesuai spesifikasi teknis yang disyaratkan
187 Terminal Box SS -1 unit Sesuai spesifikasi teknis yang disyaratkan
188 Ceiling speaker bh Sesuai spesifikasi teknis yang disyaratkan
189 Attenuator / Volume kontrol, Toa ZV 303 bh Sesuai spesifikasi teknis yang disyaratkan
190 Outlet MATV bh Sesuai spesifikasi teknis yang disyaratkan
191 Splitter MATV 4 Way bh Sesuai spesifikasi teknis yang disyaratkan
192 Smart TV Led 43 " + Bracket, Samsung unit Sesuai spesifikasi teknis yang disyaratkan
193 Outlet Stop-Kontak 1 phasa 220V/16A 1 gang ( 1 Power ) bh Sesuai spesifikasi teknis yang disyaratkan
194 Power Supply Central Unit, Layar Monitor set Sesuai spesifikasi teknis yang disyaratkan
195 Kamera indoor ( eksisting ) bh Sesuai spesifikasi teknis yang disyaratkan
196 Saklar Grid Switch 9 Gang merk. Schneider tipe Neo bh Sesuai spesifikasi teknis yang disyaratkan
197 Saklar Grid Switch 6 Gang merk. Schneider tipe Neo bh Sesuai spesifikasi teknis yang disyaratkan
198 Stop kontak 1 gang Normal merk. Schneider tipe Neo Bh Sesuai spesifikasi teknis yang disyaratkan
199 Stop Kontak Lantai/Universal ( 3 Lubang ) Power, merk. Panasonic Bh Sesuai spesifikasi teknis yang disyaratkan
200 Stop Kontak Lantai ( 2 Lubang ) Power, & Power Bh Sesuai spesifikasi teknis yang disyaratkan

Jakarta, 28 Oktober 2020


PT. PUBAGOT JAYA ABADI

TTD

PANIHA HUTAHAYAN
Direktur Utama
REKAPITULASI
BILL of QUANTITY

KEGIATAN : REDESAIN TATA LETAK RUANG KERJA KANTOR DIREKTORAT JENDERAL

KEBUDAYAAN GEDUNG E LANTAI 9 DAN 10 JAKARTA

LOKASI : JL. JENDERAL SUDIRMAN SENAYAN, KOTAK POS 4104 JAKARTA 10270

TAHUN ANGGARAN : 2020

TOTAL JUMLAH
NO URAIAN KEGIATAN
( Rp )

I PEKERJAAN PERSIAPAN & SMK3K 167,452,250.55

II PEKERJAAN BONGKARAN 118,112,106.99

III PEKERJAAN ARSITEKTUR - INTERIOR 3,540,131,201.46

IV PEKERJAAN ELEKTRIKAL 907,670,349.00

Lim
a JUMLAH 4,733,365,908.00
Mily
PPN 10% 473,336,590.80
ar
Dua JUMLAH TOTAL 5,206,702,498.80
Rat
us DIBULATKAN 5,206,702,000.00
Ena
m
Jut
Terbilang : alima milyar dua ratus enam juta tujuh ratus dua ribu rupiah
Tuj
uh
Rat
us
Dua Jakarta, 28 Oktober 2020
Rib
u KONTRAKTOR PELAKSANA
Rup PT. PUBAGOT JAYA ABADI
iah

TTD

PANIHA HUTAHAYAN

Direktur Utama

REKAPITULASI
BILL of QUANTITY
8
SUB REKAP
BILL of QUANTITY ( PERSIAPAN & SMK3K )

KEGIATAN : REDESAIN TATA LETAK RUANG KERJA KANTOR DIREKTORAT JENDERAL

KEBUDAYAAN GEDUNG E LANTAI 9 DAN 10 JAKARTA

LOKASI : JL. JENDERAL SUDIRMAN SENAYAN, KOTAK POS 4104 JAKARTA 10270

TAHUN ANGGARAN : 2020

TOTAL JUMLAH
NO URAIAN KEGIATAN
( Rp )

I PEKERJAAN PERSIAPAN & SMK3K 167,452,250.55

JUMLAH I 167,452,250.55

SUB REKAP
PERSIAPAN DAN SMK3K
9
BILL of QUANTITY ( PERSIAPAN & SMK3K )

KEGIATAN : REDESAIN TATA LETAK RUANG KERJA KANTOR DIREKTORAT JENDERAL

KEBUDAYAAN GEDUNG E LANTAI 9 DAN 10 JAKARTA

LOKASI : JL. JENDERAL SUDIRMAN SENAYAN, KOTAK POS 4104 JAKARTA 10270

TAHUN ANGGARAN : 2020

HARGA SATUAN JUMLAH HARGA


NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

I PEKERJAAN PERSIAPAN & SMK3K

1 Papan Nama Proyek Uk. 120 x 240 cm 1.00 unit 376,528.00 376,528.00

2 Administrasi, Dokumentasi dan Pelaporan 1.00 ls 4,077,937.68 4,077,937.68

(Pekerjaan administrasi, dokumentasi dan pelaporan meliputi :

foto proyek 5 phase (0%, 25%, 50%, 75%, 100%) color uk. 3R,

shop drawing dan as built drawing)

3 Pembuatan Pagar Pengaman Banner Proteksi 17.82 m1 355,400.00 6,333,228.00

(Banner proteksi diletakkan pada akses pintu masuk lantai dibawahnya

menuju lantai ruangan kerja yang mengalami renovasi)

4 Penyediaan Kantor Direksi Keet (space ruangan sudah disediakan) 1.00 ls 4,000,000.00 4,000,000.00

5 Pembuatan Gudang Material 12.00 m2 1,180,241.00 14,162,892.00

6 Pembuatan Bedeng Pekerja 12.00 m2 1,180,241.00 14,162,892.00

7 Pembersihan Site Area Pekerjaan 2,923.58 m2 15,675.00 45,827,056.94

8 Listrik Kerja 1.50 bln 2,500,000.00 3,750,000.00

9 Air Kerja 1.50 bln 2,000,000.00 3,000,000.00

10 Mobilisasi Pemindahan Meubel/Furniture Dalam Area Pekerjaan 1.00 ls 10,500,000.00 10,500,000.00

11 Sistem Manajemen Keselamatan dan Kesehatan Kerja (SMK3) Konstruksi 1.00 ls 61,261,715.94 61,261,715.94

JUMLAH I 167,452,250.55

BILL of QUANTITY
PERSIAPAN SMK3K
10
SISTEM MANAJEMEN KESELAMATAN DAN KESEHATAN KERJA (SMK3) KONSTRUKSI

KEGIATAN : REDESAIN TATA LETAK RUANG KERJA KANTOR DIREKTORAT JENDERAL

KEBUDAYAAN GEDUNG E LANTAI 9 DAN 10 JAKARTA

LOKASI : JL. JENDERAL SUDIRMAN SENAYAN, KOTAK POS 4104 JAKARTA 10270

TAHUN ANGGARAN : 2020

PAGU ANGGARAN : Rp 10,750,000,000.00

NO URAIAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

1 Penyiapan RK3K, terdiri atas :

a. Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja dan Formulir 1.00 set 500,000.00 500,000.00

b. Pembuatan Kartu Identitas Pekerja (KIP) 50.00 org 5,000.00 250,000.00

2 Sosialisasi dan Promosi K3, terdiri atas :

a. Induksi K3 (Safety Induction) ; khusus untuk pekerja baru 50.00 org 7,500.00 375,000.00

b. Pelatihan K3 :

o Bekerja di Ketinggian 5.00 org TIDAK ADA

o K3 Peralatan Konstruksi & Penggunaan Bahan Kimia (MSDS) 5.00 org TIDAK ADA

o Analisis Keselamatan Pekerjaan 5.00 org 7,500.00 37,500.00

o Perilaku Berbasis Komputer (Budaya K3) 50.00 org 7,500.00 375,000.00

o P3K 1.00 org 500,000.00 500,000.00

c. Simulasi K3 50.00 org 7,500.00 375,000.00

d. Spanduk (banner) 2.00 lb 150,000.00 300,000.00

e. Poster 2.00 lb 50,000.00 100,000.00

f. Papan Informasi K3 1.00 bh 500,000.00 500,000.00

3 Alat Pelindung Kerja, terdiri atas :

a. Jaring Pengaman (Safety Net) 1.00 ls TIDAK ADA

b. Tali Keselamatan (Life Line) 1.00 ls TIDAK ADA

c. Penahan Jatuh (Safety Deck) 1.00 ls TIDAK ADA

d. Pagar Pengaman (Guard Railling) 1.00 ls TIDAK ADA

e. Pembatas Area (Restricted Area) 1.00 ls 5,000,000.00 5,000,000.00

4 Alat Pelindung Diri, terdiri atas :

a. Topi Pelindung (Safety Helmet) 50.00 bh 75,000.00 3,750,000.00

b. Pelindung Pernapasan dan Mulut (Masker) 50.00 bh 25,000.00 1,250,000.00

c. Sarung Tangan (Safety Gloves) 50.00 psg 5,000.00 250,000.00

d. Sepatu Keselamatan (Safety Shoes); untuk Staf 5.00 psg 250,000.00 1,250,000.00

e. Sepatu Keselamatan (Rubber Safety Shoes and Toe Cap) 55.00 psg 125,000.00 6,875,000.00

f. Penunjang Seluruh Tubuh (Full Body Harness) 5.00 bh TIDAK ADA

g. Rompi Keselamatan ( Safety vest) 50.00 bh 25,000.00 1,250,000.00


h. Thermometer infrared 1.00 bh Rp 750,000.00 750,000.00
i. Pengukur tekanan darah 1.00 bh Rp 475,000.00 475,000.00
j. Handsanitizer 3.00 liter Rp 125,000.00 375,000.00
k. Washtafel 1.00 bh Rp 775,000.00 775,000.00

5 Asuransi dan Perijinan, terdiri atas :

a. BPJS Ketenagakerjaan dan Kesehatan Kerja ; (BERDASARKAN KEPMENAKER 1.00 ls 7,159,215.94 7,159,215.94

NOMOR : KEP-196/MEN/1999, untuk Tenaga Harian Proyek)

SMK3K
11
NO URAIAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

6 Personil K3, terdiri atas :

a. Ahli K3 1.00 ob 6,500,000.00 6,500,000.00

b. Petugas K3 1.00 ob 4,500,000.00 4,500,000.00

c. Ass. Petugas K3/Safety Man/Pengatur Lalu Lintas (Flagman) 1.00 ob 4,500,000.00 4,500,000.00

7 Fasilitas Sarana Kesehatan, terdiri atas :

a. Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban, dll) 1.00 ls 4,500,000.00 4,500,000.00

b. Ruang P3K (Tempat Tidur Pasien, Stetoskop, Timbangan Berat Badan, 1.00 ls 4,000,000.00 4,000,000.00

Tensimeter, dll)

8 Rambu-rambu, terdiri atas :

a. Rambu Petunjuk 4.00 bh 75,000.00 300,000.00

b. Rambu Larangan 4.00 bh 75,000.00 300,000.00

c. Rambu Peringatan 4.00 bh 75,000.00 300,000.00

d. Rambu Kewajiban 4.00 bh 75,000.00 300,000.00

e. Rambu Informasi 4.00 bh 75,000.00 300,000.00

9 Lain-lain Terkait Pengendalian Resiko K3, terdiri atas :

a. Alat Pemadam Api Ringan (APAR) ; 10 kg 2.00 bh 620,000.00 1,240,000.00

b. Bendera K3 1.00 bh 50,000.00 50,000.00

c. Program Inspeksi dan Audit Internal 1.00 org 1,500,000.00 1,500,000.00

d. Pelaporan dan Penyelidikan Insiden 1.00 ls 500,000.00 500,000.00

JUMLAH SMK3K 61,261,715.94

SMK3K
12
SUB REKAP
BILL of QUANTITY ( BONGKARAN )

KEGIATAN : REDESAIN TATA LETAK RUANG KERJA KANTOR DIREKTORAT JENDERAL

KEBUDAYAAN GEDUNG E LANTAI 9 DAN 10 JAKARTA

LOKASI : JL. JENDERAL SUDIRMAN SENAYAN, KOTAK POS 4104 JAKARTA 10270

TAHUN ANGGARAN : 2020

TOTAL JUMLAH
NO URAIAN KEGIATAN
( Rp )

II PEKERJAAN BONGKARAN

II . A LANTAI 9 60,485,471.48

II . B LANTAI 10 57,626,635.51

JUMLAH II 118,112,106.99

SUB REKAP
BONGKARAN
13
BILL of QUANTITY ( BONGKARAN )

KEGIATAN : REDESAIN TATA LETAK RUANG KERJA KANTOR DIREKTORAT JENDERAL

KEBUDAYAAN GEDUNG E LANTAI 9 DAN 10 JAKARTA

LOKASI : JL. JENDERAL SUDIRMAN SENAYAN, KOTAK POS 4104 JAKARTA 10270

TAHUN ANGGARAN : 2020

HARGA SATUAN JUMLAH HARGA


NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

II PEKERJAAN BONGKARAN

II . A LANTAI 9

1 Bongkaran Dinding Partisi serta Kusen dan Daun Pintu/Jendela Melekat Eksisting 932.62 m2 38,252.00 35,674,580.24

2 Bongkaran Penutup Plafond Linear Termasuk Rangka Penggantung Eksisting 66.89 m2 20,075.00 1,342,832.81

3 Bongkaran Penutup Plafond Gypsum Termasuk Rangka Penggantung Eksisting 1,169.02 m2 20,075.00 23,468,058.43

JUMLAH II . A 60,485,471.48

II . B LANTAI 10

1 Bongkaran Dinding Partisi serta Kusen dan Daun Pintu/Jendela Melekat Eksisting 871.81 m2 38,252.00 33,348,323.11

2 Bongkaran Dinding Bata serta Kusen dan Daun Pintu Melekat Eksisting 5.20 m2 26,537.00 137,992.40

3 Bongkaran Penutup Plafond Linear Termasuk Rangka Penggantung Eksisting 96.18 m2 20,075.00 1,930,737.22

4 Bongkaran Penutup Plafond Gypsum Termasuk Rangka Penggantung Eksisting 1,106.33 m2 20,075.00 22,209,582.78

JUMLAH II . B 57,626,635.51

JUMLAH II 118,112,106.99

BILL of QUANTITY
BONGKARAN
14
SUB REKAP
BILL of QUANTITY ( ARSITEKTUR - INTERIOR )

KEGIATAN : REDESAIN TATA LETAK RUANG KERJA KANTOR DIREKTORAT JENDERAL

KEBUDAYAAN GEDUNG E LANTAI 9 DAN 10 JAKARTA

LOKASI : JL. JENDERAL SUDIRMAN SENAYAN, KOTAK POS 4104 JAKARTA 10270

TAHUN ANGGARAN : 2020

TOTAL JUMLAH
NO URAIAN KEGIATAN
( Rp )

III PEKERJAAN ARSITEKTUR - INTERIOR

III . A LANTAI 9

III . A . 1 PEK. DINDING DAN PARTISI 308,961,398.96

III . A . 2 PEK. KUSEN PINTU DAN JENDELA 338,350,318.00

III . A . 3 PEK. PENUTUP LANTAI DAN DINDING 222,146,525.33

III . A . 4 PEK. PLAFOND DAN PENGGANTUNG 283,639,334.34

III . A . 5 PEK. PENGECATAN DAN FINISHING DINDING 168,905,635.39

III . A . 6 PEK. FURNITURE INTERIOR MELEKAT 188,427,561.05

III . A . 7 PEK. LAIN-LAIN 120,380,591.76

III . B LANTAI 10

III . B . 1 PEK. DINDING DAN PARTISI 419,187,987.55

III . B . 2 PEK. KUSEN PINTU DAN JENDELA 292,826,379.00

III . B . 3 PEK. PENUTUP LANTAI DAN DINDING 277,337,061.89

III . B . 4 PEK. PLAFOND DAN PENGGANTUNG 303,177,185.73

III . B . 5 PEK. PENGECATAN DAN FINISHING DINDING 212,697,785.07

III . B . 6 PEK. FURNITURE INTERIOR MELEKAT 225,559,179.65

III . B . 7 PEK. LAIN-LAIN 178,534,257.76

JUMLAH III 3,540,131,201.46

SUB REKAP
ARSITEKTUR - INTERIOR
15
RENCANA ANGGARAN BIAYA

KEGIATAN : REDESAIN TATA LETAK RUANG KERJA KANTOR DIREKTORAT JENDERAL

KEBUDAYAAN GEDUNG E LANTAI 9 DAN 10 JAKARTA

LOKASI : JL. JENDERAL SUDIRMAN SENAYAN, KOTAK POS 4104 JAKARTA 10270

TAHUN ANGGARAN : 2020

HARGA SATUAN JUMLAH HARGA


NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

III PEKERJAAN ARSITEKTUR - INTERIOR

III . A LANTAI 9

III . A . 1 PEK. DINDING DAN PARTISI

1 Pasangan Dinding Partisi Gypsum

a. Pasangan Dinding Partisi Gypsum T=260 cm, Type 1

o Pasangan rangka metal stud uk. 34x76 mm tbl. 0,40 mm dan 294.85 m2 150,072.00 44,248,053.88

U runner uk. 25x76 mm tbl. 0,35 mm

o Pasangan penutup dinding partisi gypsum tbl. 12 mm (2 muka) 602.61 m2 147,582.00 88,934,167.65

b. Pasangan Dinding Partisi Gypsum T=260 cm, Type 2

o Pasangan rangka metal stud uk. 34x76 mm tbl. 0,40 mm dan 23.50 m2 150,072.00 3,527,292.29

U runner uk. 25x76 mm tbl. 0,35 mm

o Pasangan rockwool 2 lapis, tb. 5 cm dencity 60 kg/m3 47.01 m2 90,238.00 4,241,907.90

o Pasangan penutup dinding partisi gypsum tbl. 12 mm (2 muka) 47.53 m2 147,582.00 7,014,277.30

c. Pasangan Dinding Partisi Gypsum T=260 cm, Type 3

o Pasangan rangka metal stud uk. 34x76 mm tbl. 0,40 mm dan 70.06 m2 150,072.00 10,514,044.32

U runner uk. 25x76 mm tbl. 0,35 mm

o Pasangan rockwool 2 lapis, tb. 5 cm dencity 60 kg/m3 140.12 m2 90,238.00 12,644,148.56

o Pasangan penutup dinding partisi gypsum tbl. 12 mm (2 muka) 143.54 m2 147,582.00 21,183,920.28

2 Pasangan Dinding Partisi Kaca

a. Partisi Kaca Folding, Type PK-1 (Fabrikasi) 1.00 unit 20,530,300.00 20,530,300.00

o Frame : Aluminium powder coating (super white)

o Pengunci : Slot dan cylinder key

o Penggerak : Rell dan roda

o Glass : 8 mm polos

o System : Foldside

o Kontruksi penggantung CNP 100X50X2,3 mm + besi siku 30x30x3 mm

b. Dinding Partisi Kaca, Type PK-4 & PK-5 (R. Ekspresi Seni Pegawai)

o Kusen aluminium 4", powder coating (white) 17.58 m1 140,745.00 2,474,297.10

o Kaca tempered 12 mm 12.07 m2 1,102,070.00 13,302,535.94

o Sealant 90.91 m1 22,500.00 2,045,484.00

c. Dinding Partisi Kaca, Type PK-6 (R. Tamu)

o Pasangan aluminium - "U" Uk. 20x20x2,0 mm 14.93 m1 140,745.00 2,100,619.13

o Kaca tempered 12 mm 11.86 m2 1,102,070.00 13,073,305.38

o Pasangan stiker sandblast kaca 6.13 m2 78,106.00 478,399.25

o Sealant 51.65 m1 22,500.00 1,162,125.00

3 Pasangan Dinding Partisi Movable Wall Type MW-1 (Fabrikasi) 3.00 unit 20,495,507.00 61,486,521.00

Pembatas Antara Ruang Rapat 1 - Ruang Rapat 2 - Ruang Rapat 3 dan

Pembatas Antara Ruang Rapat 4

Spesifikasi movable wall :

o Tipe : WP-65

o Tebal panel : 65 mm

o Pengunci : Jack mecanic

o Penggerak : Rell dan roda

o Frame : Aluminium powder coating (super white)

o Insulation : Rockwool density 60 kg/m3

BILL of QUANTITY
ARSITEKTUR - INTERIOR
16
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

o System : Centre 1 roda

o Konstruksi angle bar 30x30x3 mm, rod stell hanger dia. 10 mm

o Sound barrier gypsum 12 mm rangka metal stud

o Box penyimpanan

Sub Jumlah III . A . 1 308,961,398.96

III . A . 2 PEK. KUSEN PINTU DAN JENDELA

1 Daun Pintu Kaca, Type P-1 19.00 unit 9,254,403.00 175,833,657.00

Spesifikasi Daun PintuKaca, Type P-1 :

a. Kaca tempered 12 mm

b. Pasangan stiker sandblast kaca

c. Pull handle SS-304 38x630x600 mm TPH 981

d. Floor hinge FH 80 SSS

e. Top patch PT 20

f. Bottom patch PT 10

g. Corner lock/Patch lock US 10

2 Daun Pintu Kaca, Type P-2 2.00 unit 9,379,803.00 18,759,606.00

Spesifikasi Daun PintuKaca, Type P-2 :

a. Kaca tempered 12 mm

b. Pasangan stiker sandblast kaca

c. Pull handle SS-304 38x630x600 mm TPH 981

d. Floor hinge FH 80 SSS

e. Top patch PT 20

g. Bottom patch PT 10

h. Corner lock/Patch lock US 10

3 Daun Pintu Kaca, Type P-3 2.00 unit 18,024,066.00 36,048,132.00

Spesifikasi Daun PintuKaca, Type P-3 :

a. Kaca tempered 12 mm

b. Pasangan stiker sandblast kaca

c. Pull handle SS-304 38x1200 mm PH 802

d. Floor hinge FH 80 SSS

e. Top patch PT 20

f. Bottom patch PT 10

g. Corner lock/Patch lock US 10

4 Daun Pintu Kaca, Type P-3A 4.00 unit 20,119,991.00 80,479,964.00

Spesifikasi Daun PintuKaca, Type P-3A :

a. Kaca tempered 12 mm

b. Pasangan stiker sandblast kaca

c. Pull handle SS-304 38x1200 mm PH 802

d. Floor hinge FH 80 SSS

e. Top patch PT 20

f. Bottom patch PT 10

g. Corner lock/Patch lock US 10

h. Architrave multiplek 100x15 mm

i. Pasangan HPL, warna/tekstur disesuaikan dengan gambar

5 Kusen Pintu dan Daun Pintu, Type P-5 3.00 unit 4,433,403.00 13,300,209.00

Spesifikasi Kusen Pintu dan Daun Pintu, Type P-5 :

a. Kusen aluminium 4", powder coating (white)

b. Daun pintu multiplek 9 mm + rangka kayu

c. Finishing daun pintu HPL serat kayu

d. Engsel pintu

e. Lever handle

f. Mortise lock

g. Escutcheon

BILL of QUANTITY
ARSITEKTUR - INTERIOR
17
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

h. Door closer

i. Cylinder + kunci

j. Sealant

6 Kusen Pintu dan Daun Pintu, Type PJ-1 2.00 unit 5,807,269.00 11,614,538.00

Spesifikasi Kusen Pintu dan Daun Pintu, Type PJ-1 :

a. Kusen aluminium 4", powder coating (white)

b. Daun pintu multiplek 9 mm + rangka kayu

c. Finishing daun pintu HPL serat kayu

e. Engsel pintu

f. Lever handle

g. Mortise lock

h. Escutcheon

i. Door closer

j. Cylinder + kunci

k. Sealant kusen + kaca

7 Kusen Pintu dan Daun Pintu Besi, Type PE-1 (eksisting) 2.00 unit 1,157,106.00 2,314,212.00

Pengecatan ulang pintu eksisting dengan cat besi

Sub Jumlah III . A . 2 338,350,318.00

III . A . 3 PEK. PENUTUP LANTAI DAN DINDING

1 Pasangan Lantai Vinyl uk. 304,8 x 609,6 x 3 mm Grey Slate (V-1 Type 1) 222.14 m2 296,648.00 65,898,187.67

2 Pasangan Hosplint Aluminium 702.88 m1 222,297.00 156,248,337.66

Spesifikasi Plin Dinding : Tinggi lengkung 12 cm, Radius Cekung atas 1,1 cm dan

Radius Cekung Bawah 3 cm, Ketebalan 1.9 mm

Sub Jumlah III . A . 3 222,146,525.33

III . A . 4 PEK. PLAFOND DAN PENGGANTUNG

1 Pasangan Plafond Gypsum Tipe PG

a. Pasangan Rangka Plafond Hollow Galvalum 20x40 mm & 40x40 mm 1,453.20 m2 100,738.00 146,392,260.12

b. Pasangan Penutup Plafond Gypsum tebal 9 mm 1,453.20 m2 55,067.00 80,023,254.27

2 Pasangan Plafond Multiplek Tipe MH (Area Ruang Rapat)

a. Pasangan Rangka Plafond Hollow Galvalum 20x40 mm & 40x40 mm 6.40 m2 100,738.00 644,723.20

b. Pasangan Penutup Plafond Multiplek tebal 9 mm 6.40 m2 76,628.00 490,419.20

c. Pasangan HPL, warna/tekstur disesuaikan dengan gambar 6.40 m2 200,084.00 1,280,537.60

3 Pasangan Grid Ceiling 10x10 cm, Aluminium Warna Cokelat Termasuk Penggantung 38.99 m2 178,540.00 6,961,274.60

Wall angle, Rod drat, Angle clip, Gording clip, Main runner, Clip runner, dan Cross runner

4 Pasangan Up/Down Ceiling Plafond Gypsum 188.59 m1 94,567.00 17,834,012.26

5 Pasangan List Plafond Shadow Line Tebal 3 mm 784.71 m1 38,247.00 30,012,853.09

Sub Jumlah III . A . 4 283,639,334.34

III . A . 5 PEK. PENGECATAN DAN FINISHING DINDING

1 Pengecatan Partisi Gypsum, Cat Interior 650.14 m2 40,759.00 26,498,913.60

2 Pengecatan Dinding, Partisi Gypsum dan Kolom Eksisting, Cat Interior 699.00 m2 40,759.00 28,490,376.33

3 Pengecatan Plafond Gypsum, Up/Down Ceiling, Cat Interior 1,528.63 m2 40,759.00 62,305,527.99

4 Finishing Wallpaper, Dinding, kolom dan Partisi Gypsum 184.96 m2 279,037.00 51,610,817.46

Sub Jumlah III . A . 5 168,905,635.39

III . A . 6 PEK. FURNITURE INTERIOR MELEKAT

Area direktorat pengembangan & pemanfaatan budaya

1 Wall Art Tipe - W1 1.00 unit 4,888,485.00 4,888,485.00

Spesifikasi wall art tipe - W1 :

o Rangka metal stud uk. 34x76 mm tbl. 0,40 mm dan

U runner uk. 25x76 mm tbl. 0,35 mm

o Gypsum 12 mm

BILL of QUANTITY
ARSITEKTUR - INTERIOR
18
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

o Backing multiplek 9 mm

o Multiplek 15 mm

o Teakwood 3 mm

o Finishing cat interior (area gypsum)

o Finishing cat politur (area multiplek + teakwood)

o Finishing HPL, warna disesuaikan dengan gambar (area nat)

2 Wall Covering Tipe - WC1 1.00 unit 12,581,064.00 12,581,064.00

Spesifikasi wall covering tipe - WC1 :

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm

o Multiplek 6 mm

o Multiplek 15 mm

o Finishing HPL, warna/tekstur disesuaikan dengan gambar

o Finishing cat duco warna hitam pada nat

3 Covering Kolom Tipe - CK2 3.00 unit 6,035,131.00 18,105,393.00

Spesifikasi covering kolom tipe - CK2 :

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm

o Multiplek 9 mm

o Finishing HPL, warna/tekstur disesuaikan dengan gambar

4 Covering Kolom Tipe - CK3 1.00 unit 4,221,831.00 4,221,831.00

Spesifikasi covering kolom tipe - CK3 :

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm

o Multiplek 9 mm

o Finishing HPL, warna/tekstur disesuaikan dengan gambar

5 Covering Kolom Tipe - CK4 1.00 unit 2,713,048.00 2,713,048.00

Spesifikasi covering kolom tipe - CK4 :

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm

o Multiplek 9 mm

o Finishing HPL, warna/tekstur disesuaikan dengan gambar

6 Covering Kolom Tipe - CK5 1.00 unit 5,730,614.00 5,730,614.00

Spesifikasi covering kolom tipe - CK5 :

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm

o Multiplek 9 mm

o Finishing HPL, warna/tekstur disesuaikan dengan gambar

7 Covering Kolom Tipe - CK6 1.00 unit 3,702,745.00 3,702,745.00

Spesifikasi covering kolom tipe - CK6 :

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm

o Multiplek 9 mm

o Finishing HPL, warna/tekstur disesuaikan dengan gambar

Area lobby dan ruang rapat

1 Ornamen Kolom Tipe - CK1 2.00 unit 4,400,309.00 8,800,618.00

Spesifikasi ornamen kolom tipe - CK:

o Kayu solid jati uk. 40x40 mm

o Finishing HPL, warna/motif disesuaikan dengan gambar

o Finishing wallpaper, warna/motif disesuaikan dengan gambar

2 Backdrop Tipe - B1 2.00 unit 18,704,251.00 37,408,502.00

Spesifikasi backdrop tipe - B1 :

o Rangka metal stud uk. 34x76 mm tbl. 0,40 mm dan

U runner uk. 25x76 mm tbl. 0,35 mm

o Gypsum 12 mm

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm

o Multiplek 9 mm

o Sirip kayu solid 40x40 mm, wood filler jati

o Rangka pigura kayu solid 25x50 mm, wood filler jati

o Frame pigura kayu solid 20x30 mm, wood filler jati

o Finishing cat interior (area gypsum)

BILL of QUANTITY
ARSITEKTUR - INTERIOR
19
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

o Finishing HPL, warna/motif disesuaikan dengan gambar

o Finishing cat politur

o Name sign stainless steel * DIREKTORAT KEPERCAYAAN TERHADAP TUHAN YME

DAN MASYARAKAT ADAT *, tinggi huruf 7 cm

o Logo timbul stainless steel lapis stiker, uk. 50x51 cm tebal 4 cm

3 Backdrop Tipe - B2 2.00 unit 7,151,812.00 14,303,624.00

Spesifikasi backdrop tipe - B2 :

o Rangka metal stud uk. 34x76 mm tbl. 0,40 mm dan

U runner uk. 25x76 mm tbl. 0,35 mm

o Gypsum 12 mm (sisi dalam)

o Multiplek 9 mm (sisi luar)

o Finishing HPL, warna/motif disesuaikan dengan gambar (sisi luar)

4 Meja Resepsionis 2.00 unit 6,584,945.00 13,169,890.00

Spesifikasi meja resepsionis :

o Rangka kayu solid uk. 20x30 mm

o Multiplek 15 mm

o Melaminto 3 mm (area lemari & laci sisi dalam)

o Ornamen MDF 15 mm cutting laser + HPL (chrome)

o Finishing HPL, warna/tekstur disesuaikan dengan gambar

o Rell laci panjang 40 cm

o Engsel sendok lemari

o Handle lemari + laci

o Plat stainless steel hairline tebal 1,5 mm

5 Covering Dinding Granit Eksisting (lobby)

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm 30.37 m2 245,041.00 7,441,405.09

o Multiplek 6 mm 30.63 m2 67,388.00 2,063,959.66

o Finishing wallpaper, warna/motif disesuaikan dengan gambar 30.63 m2 279,037.00 8,546,345.24

o Pasangan Hosplint Aluminium (warna putih) 11.78 m1 222,297.00 2,618,658.66

Area direktorat pembinaan tenaga & lembaga kebudayaan

1 Wall Covering Tipe - WC2

Spesifikasi wall covering tipe - WC2 :

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm 65.07 m2 245,041.00 15,944,572.83

o Multiplek 6 mm 65.07 m2 67,388.00 4,384,869.77

o Finishing HPL, warna/tekstur disesuaikan dengan gambar 65.07 m2 200,084.00 13,019,265.80

2 Wall Art Tipe - W9 1.00 unit 8,782,670.00 8,782,670.00

Spesifikasi wall art tipe - W9 :

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm

o Multiplek 6 mm

o Multiplek 20 mm

o Finishing HPL, warna/tekstur disesuaikan dengan gambar

Sub Jumlah III . A . 6 188,427,561.05

III . A . 7 PEK. LAIN-LAIN

1 Pasangan Penutup Jendela Roller Blind Fabric Sun Screen Seri 1803 Type 1 175.19 m2 595,000.00 104,236,860.00

Lengkap dengan tail bracket, tail plug, aluminium tube, head bracket, clutch, chain,

Fabric sun screen, bottom raill dan end cap

2 Pasangan Penutup Jendela Roller Blind Fabric Black Out Seri 4306 Type 2 26.36 m2 612,340.00 16,143,731.76

Lengkap dengan tail bracket, tail plug, aluminium tube, head bracket, clutch, chain,

Fabric black out, bottom raill dan end cap

Sub Jumlah III . A . 7 120,380,591.76

JUMLAH III . A 1,630,811,364.82

BILL of QUANTITY
ARSITEKTUR - INTERIOR
20
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

III . B LANTAI 10

III . B . 1 PEK. DINDING DAN PARTISI

1 Pasangan Dinding Partisi Gypsum

a. Pasangan Dinding Partisi Gypsum T=260 cm, Type 1

o Pasangan rangka metal stud uk. 34x76 mm tbl. 0,40 mm dan 191.20 m2 150,072.00 28,694,366.69

U runner uk. 25x76 mm tbl. 0,35 mm

o Pasangan penutup dinding partisi gypsum tbl. 12 mm (2 muka) 388.89 m2 147,582.00 57,392,868.82

b. Pasangan Dinding Partisi Gypsum T=260 cm, Type 2

o Pasangan rangka metal stud uk. 34x76 mm tbl. 0,40 mm dan 12.48 m2 150,072.00 1,872,898.56

U runner uk. 25x76 mm tbl. 0,35 mm

o Pasangan rockwool 2 lapis, tb. 5 cm dencity 60 kg/m3 24.96 m2 90,238.00 2,252,340.48

o Pasangan penutup dinding partisi gypsum tbl. 12 mm (2 muka) 26.00 m2 147,582.00 3,837,132.00

c. Pasangan Dinding Partisi Gypsum T=260 cm, Type 3

o Pasangan rangka metal stud uk. 34x76 mm tbl. 0,40 mm dan 110.90 m2 150,072.00 16,642,534.58

U runner uk. 25x76 mm tbl. 0,35 mm

o Pasangan rockwool 2 lapis, tb. 5 cm dencity 60 kg/m3 221.79 m2 90,238.00 20,014,246.97

o Pasangan penutup dinding partisi gypsum tbl. 12 mm (2 muka) 225.25 m2 147,582.00 33,242,697.92

2 Pasangan Dinding Partisi Kaca

a. Partisi Kaca Folding, Type PK-1 (Fabrikasi) 3.00 unit 20,530,300.00 61,590,900.00

Spesifikasi Type Full Frame : uk. 455 x 210 cm

o Frame : Aluminium powder coating (super white)

o Pengunci : Slot dan cylinder key

o Penggerak : Rell dan roda

o Glass : 8 mm polos

o System : Foldside

o Kontruksi penggantung CNP 100X50X2,3 mm + besi siku 30x30x3 mm

b. Partisi Kaca Folding, Type PK-2 (Fabrikasi) 1.00 unit 13,562,400.00 13,562,400.00

Spesifikasi Type Full Frame : uk. 270 x 210 cm

o Frame : Aluminium powder coating (super white)

o Pengunci : Slot dan cylinder key

o Penggerak : Rell dan roda

o Glass : 8 mm polos

o System : Foldside

o Kontruksi penggantung CNP 100X50X2,3 mm + besi siku 30x30x3 mm

c. Partisi Kaca Folding, Type PK-3 (Fabrikasi) 2.00 unit 12,549,100.00 25,098,200.00

Spesifikasi Type Full Frame : uk. 262 x 210 cm

o Frame : Aluminium powder coating (super white)

o Pengunci : Slot dan cylinder key

o Penggerak : Rell dan roda

o Glass : 8 mm polos

o System : Foldside

o Kontruksi penggantung CNP 100X50X2,3 mm + besi siku 30x30x3 mm

d. Partisi Kaca Folding, Type PK-4 (Fabrikasi) 1.00 unit 31,265,600.00 31,265,600.00

Spesifikasi Type Full Frame : uk. 260 x 562 cm

o Frame : Aluminium powder coating (super white)

o Pengunci : Slot dan cylinder key

o Penggerak : Rell dan roda

o Glass : 8 mm polos

o System : Foldside

o Kontruksi penggantung CNP 100X50X2,3 mm + besi siku 30x30x3 mm

e. Dinding Partisi Kaca, Type PK-8 & PK-9 (R. Rapat)

o Pasangan aluminium - "U" Uk. 20x20x2,0 mm 27.44 m1 140,745.00 3,862,042.80

o Kaca tempered 12 mm (partisi) 7.09 m2 1,102,070.00 7,808,165.95

o Pasangan stiker sandblast kaca 1.64 m2 78,106.00 127,937.63

o Sealant 56.88 m1 22,500.00 1,279,800.00

BILL of QUANTITY
ARSITEKTUR - INTERIOR
21
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

f. Dinding Partisi Kaca, Type PK-10

o Kusen aluminium 4", powder coating (white) 20.88 m1 140,745.00 2,938,755.60

o Kaca polos 8 mm (partisi) 13.00 m2 361,550.00 4,701,306.96

o Sealant kaca + kusen 82.88 m1 22,500.00 1,864,800.00

g. Dinding Partisi Kaca, Type PK-11

o Kusen aluminium 4", powder coating (white) 14.45 m1 140,745.00 2,033,765.25

o Kaca polos 8 mm (partisi) 3.59 m2 361,550.00 1,296,807.54

o Sealant kaca + kusen 48.12 m1 22,500.00 1,082,700.00

h. Dinding Partisi Kaca, Type PK-12

o Kusen aluminium 4", powder coating (white) 23.60 m1 140,745.00 3,321,582.00

o Kaca polos 8 mm (partisi) 11.32 m2 361,550.00 4,093,902.96

o Sealant kaca + kusen 83.36 m1 22,500.00 1,875,600.00

i. Dinding Partisi Kaca, Type PK-13

o Kusen aluminium 4", powder coating (white) 20.26 m1 140,745.00 2,851,493.70

o Kaca polos 8 mm (partisi) 4.68 m2 361,550.00 1,691,620.14

o Sealant kaca + kusen 75.28 m1 22,500.00 1,693,800.00

3 Pasangan Dinding Partisi Movable Wall Type MW-1 (Fabrikasi) 3.00 unit 20,495,507.00 61,486,521.00

Pembatas Antara Ruang Rapat 1 - Ruang Rapat 2 - Ruang Rapat 3 dan

Pembatas Antara Ruang Tamu, Ruang Kerja

Spesifikasi movable wall :

o Tipe : WP-65

o Tebal panel : 65 mm

o Pengunci : Jack mecanic

o Penggerak : Rell dan roda

o Frame : Aluminium powder coating (super white)

o Insulation : Rockwool density 60 kg/m3

o System : Centre 1 roda

o Konstruksi angle bar 30x30x3 mm, rod stell hanger dia. 10 mm

o Sound barrier gypsum 12 mm rangka metal stud

o Box penyimpanan

4 Pasangan Dinding Partisi Movable Wall Type MW-2 (Fabrikasi) 2.00 unit 9,855,600.00 19,711,200.00

Pembatas Antara Ruang Rapat 1 - Ruang Rapat 2 - Ruang Rapat 3 Pada As-10 & As-11

Spesifikasi movable wall :

o Tipe : WP-65

o Tebal panel : 65 mm

o Pengunci : Jack mecanic

o Penggerak : Rell dan roda

o Frame : Aluminium powder coating (super white)

o Insulation : Rockwool density 60 kg/m3

o System : Induction stacking 2 roda

o Konstruksi angle bar 30x30x3 mm, rod stell hanger dia. 10 mm

Sub Jumlah III . B . 1 419,187,987.55

III . B . 2 PEK. KUSEN PINTU DAN JENDELA

1 Daun Pintu Kaca, Type P-1 9.00 unit 9,254,403.00 83,289,627.00

Spesifikasi Daun Pintu Kaca, Type P-1 :

a. Kaca tempered 12 mm

b. Pasangan stiker sandblast kaca

c. Pull handle SS-304 38x630x600 mm TPH 981

d. Floor hinge FH 80 SSS

e. Top patch PT 20

f. Bottom patch PT 10

g. Corner lock/Patch lock US 10

BILL of QUANTITY
ARSITEKTUR - INTERIOR
22
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

2 Daun Pintu Kaca, Type P-2 2.00 unit 9,379,803.00 18,759,606.00

Spesifikasi Daun Pintu Kaca, Type P-2 :

a. Kaca tempered 12 mm

b. Pasangan stiker sandblast kaca

c. Pull handle SS-304 38x630x600 mm TPH 981

d. Floor hinge FH 80 SSS

e. Top patch PT 20

f. Patch fitting PT 40

g. Bottom patch PT 10

h. Corner lock/Patch lock US 10

3 Daun Pintu Kaca, Type P-3 3.00 unit 18,024,066.00 54,072,198.00

Spesifikasi Daun Pintu Kaca, Type P-3 :

a. Kaca tempered 12 mm

b. Pasangan stiker sandblast kaca

c. Pull handle SS-304 38x1200 mm PH 802

d. Floor hinge FH 80 SSS

e. Top patch PT 20

f. Bottom patch PT 10

g. Corner lock/Patch lock US 10

4 Daun Pintu Kaca, Type P-3A 4.00 unit 20,119,991.00 80,479,964.00

Spesifikasi Daun Pintu Kaca, Type P-3A :

a. Kaca tempered 12 mm

b. Pasangan stiker sandblast kaca

c. Pull handle SS-304 38x1200 mm PH 802

d. Floor hinge FH 80 SSS

e. Top patch PT 20

f. Bottom patch PT 10

g. Corner lock/Patch lock US 10

h. Architrave multiplek 100x15 mm

i. Pasangan HPL, warna/tekstur disesuaikan dengan gambar

5 Daun Pintu Kaca Frame Aluminium, Type P-4 4.00 unit 8,357,357.00 33,429,428.00

Spesifikasi Daun Pintu Frame Aluminium, Type P-4 :

a. Frame aluminium 4", powder coating (white)

b. Kaca polos 8 mm

c. Engsel pintu

d. Pull handle SS-304 32x300 mm PH 801

e. Floor hinge FH 80 SSS

f. Top patch PT 20

g. Bottom patch PT 10

h. Mortise lock

i. Escutcheon

j. Cylinder + kunci

k. Sealant kaca

6 Kusen Pintu dan Daun Pintu, Type P-5 2.00 unit 4,433,403.00 8,866,806.00

Spesifikasi Kusen Pintu dan Daun Pintu, Type P-5 :

a. Kusen aluminium 4", powder coating (white)

b. Daun pintu multiplek 9 mm + rangka kayu

c. Finishing daun pintu HPL serat kayu

d. Engsel pintu

e. Lever handle

f. Mortise lock

g. Escutcheon

h. Door closer

i. Cylinder + kunci

j. Sealant

BILL of QUANTITY
ARSITEKTUR - INTERIOR
23
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

7 Kusen Pintu dan Daun Pintu, Type PJ-1 2.00 unit 5,807,269.00 11,614,538.00

Spesifikasi Kusen Pintu dan Daun Pintu, Type PJ-1 :

a. Kusen aluminium 4", powder coating (white)

b. Daun pintu multiplek 9 mm + rangka kayu

c. Finishing daun pintu HPL serat kayu

d. Kaca polos 6 mm

e. Engsel pintu

f. Lever handle

g. Mortise lock

h. Escutcheon

i. Door closer

j. Cylinder + kunci

k. Sealant kusen + kaca

8 Kusen Pintu dan Daun Pintu Besi, Type PE-1 (eksisting) 2.00 unit 1,157,106.00 2,314,212.00

Pengecatan ulang pintu eksisting dengan cat besi

Sub Jumlah III . B . 2 292,826,379.00

III . B . 3 PEK. PENUTUP LANTAI DAN DINDING

1 Pasangan Lantai Vinyl uk. 304,8 x 609,6 x 3 mm Grey Slate (V-1 Type 1) 370.46 m2 296,648.00 109,895,921.43

2 Pasangan Lantai Vinyl uk. 152,4 x 914,4 x 3 mm Washed Oak (V-2 Type 2) 63.18 m2 313,808.00 19,827,173.96

3 Pasangan Hosplint Aluminium 664.04 m1 222,297.00 147,613,966.50

Spesifikasi Plin Dinding : Tinggi lengkung 12 cm, Radius Cekung atas 1,1 cm dan

Radius Cekung Bawah 3 cm, Ketebalan 1.9 mm

Sub Jumlah III . B . 3 277,337,061.89

III . B . 4 PEK. PLAFOND DAN PENGGANTUNG

1 Pasangan Plafond Gypsum Tipe PG

a. Pasangan Rangka Plafond Hollow Galvalum 20x40 mm & 40x40 mm 1,483.72 m2 100,738.00 149,466,960.18

b. Pasangan Penutup Plafond Gypsum tebal 9 mm 1,483.72 m2 55,067.00 81,703,995.47

2 Pasangan Plafond Multiplek Tipe MH (Area Lounge & Tempat Diskusi)

a. Pasangan rangka penggantung hollow galvanis uk. 40x40 mm, tebal 1,4 mm 14.22 m1 245,041.00 3,484,483.02

b. Base plate uk. 10x10 cm, tebal 5 mm + pengelasan 0.08 m2 855,600.00 68,448.00

c. Dynabolt M-8 32.00 bh 3,500.00 112,000.00

d. Pasangan rangka plafond hollow galvanis uk. 40x40 mm, tebal 1,4 mm 23.38 m2 245,041.00 5,728,078.42

e. Pasangan Penutup Plafond Multiplek tebal 9 mm 26.28 m2 76,628.00 2,013,553.96

f. Pasangan HPL, warna/tekstur disesuaikan dengan gambar 26.28 m2 200,084.00 5,257,607.27

g. Pengecatan rangka penggantung, cat besi 1.02 m2 39,798.00 40,753.15

3 Pasangan Plafond Multiplek Tipe MH (Area Ruang Rapat)

a. Pasangan Rangka Plafond Hollow Galvalum 20x40 mm & 40x40 mm 6.40 m2 100,738.00 644,723.20

b. Pasangan Penutup Plafond Multiplek tebal 9 mm 6.40 m2 76,628.00 490,419.20

c. Pasangan HPL, warna/tekstur disesuaikan dengan gambar 6.40 m2 200,084.00 1,280,537.60

4 Pasangan Grid Ceiling 10x10 cm, Aluminium Warna Cokelat Termasuk Penggantung 34.93 m2 178,540.00 6,236,402.20

Wall angle, Rod drat, Angle clip, Gording clip, Main runner, Clip runner, dan Cross runner

5 Pasangan Up/Down Ceiling Plafond Gypsum 207.07 m1 94,567.00 19,581,657.71

6 Pasangan List Plafond Shadow Line Tebal 3 mm 707.70 m1 38,247.00 27,067,566.36

Sub Jumlah III . B . 4 303,177,185.73

III . B . 5 PEK. PENGECATAN DAN FINISHING DINDING

1 Pengecatan Partisi Gypsum, Cat Interior 414.89 m2 40,759.00 16,910,419.99

2 Pengecatan Dinding, Partisi Gypsum dan Kolom Eksisting, Cat Interior 717.48 m2 40,759.00 29,243,715.15

3 Pengecatan Plafond Gypsum, Up/Down Ceiling, Cat Interior 1,566.55 m2 40,759.00 63,850,862.68

4 Finishing Wallpaper, Dinding, kolom dan Partisi Gypsum 368.03 m2 279,037.00 102,692,787.25

Sub Jumlah III . B . 5 212,697,785.07

BILL of QUANTITY
ARSITEKTUR - INTERIOR
24
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

III . B . 6 PEK. FURNITURE INTERIOR MELEKAT

Area Direktorat Kepercayaan Terhadap Tuhan YME dan Masyarakat Adat

1 Wall Art Tipe - W1 1.00 unit 4,888,485.00 4,888,485.00

Spesifikasi wall art tipe - W1 :

o Rangka metal stud uk. 34x76 mm tbl. 0,40 mm dan

U runner uk. 25x76 mm tbl. 0,35 mm

o Gypsum 12 mm

o Backing multiplek 9 mm

o Multiplek 15 mm

o Teakwood 3 mm

o Finishing cat interior (area gypsum)

o Finishing cat politur (area multiplek + teakwood)

o Finishing HPL, warna disesuaikan dengan gambar (area nat)

2 Wall Art Tipe - W2 1.00 unit 7,854,231.00 7,854,231.00

Spesifikasi wall art :

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm

o Backing multiplek 9 mm

o Multiplek 15 mm

o Teakwood 3 mm

o Finishing cat politur (area multiplek + teakwood)

o Finishing HPL, warna disesuaikan dengan gambar (area nat)

o Ornamen gunungan MDF 15 mm cutting laser + HPL (warna tembaga)

Area Lobby dan Ruang Rapat

1 Ornamen Kolom Tipe - CK1 2.00 unit 4,400,309.00 8,800,618.00

Spesifikasi ornamen kolom tipe - CK:

o Kayu solid jati uk. 40x40 mm

o Finishing HPL, warna/motif disesuaikan dengan gambar

o Finishing wallpaper, warna/motif disesuaikan dengan gambar

2 Backdrop Tipe - B1 2.00 unit 18,704,251.00 37,408,502.00

Spesifikasi backdrop tipe - 1 :

o Rangka metal stud uk. 34x76 mm tbl. 0,40 mm dan

U runner uk. 25x76 mm tbl. 0,35 mm

o Gypsum 12 mm

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm

o Multiplek 9 mm

o Sirip kayu solid 40x40 mm, wood filler jati

o Rangka pigura kayu solid 25x50 mm, wood filler jati

o Frame pigura kayu solid 20x30 mm, wood filler jati

o Finishing cat interior (area gypsum)

o Finishing HPL, warna/motif disesuaikan dengan gambar

o Finishing cat politur

o Name sign stainless steel * DIREKTORAT KEPERCAYAAN TERHADAP TUHAN YME

DAN MASYARAKAT ADAT *, tinggi huruf 7 cm

o Logo timbul stainless steel lapis stiker, uk. 50x51 cm tebal 4 cm

3 Backdrop Tipe - B2 2.00 unit 7,151,812.00 14,303,624.00

Spesifikasi backdrop tipe - 2 :

o Rangka metal stud uk. 34x76 mm tbl. 0,40 mm dan

U runner uk. 25x76 mm tbl. 0,35 mm

o Gypsum 12 mm (sisi dalam)

o Multiplek 9 mm (sisi luar)

o Finishing HPL, warna/motif disesuaikan dengan gambar (sisi luar)

4 Meja Resepsionis 2.00 unit 6,584,945.00 13,169,890.00

Spesifikasi meja resepsionis :

o Rangka kayu solid uk. 20x30 mm

o Multiplek 15 mm

o Melaminto 3 mm (area lemari & laci sisi dalam)

BILL of QUANTITY
ARSITEKTUR - INTERIOR
25
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

o Ornamen MDF 15 mm cutting laser + HPL (chrome)

o Finishing HPL, warna/motif disesuaikan dengan gambar

o Rell laci panjang 40 cm

o Engsel sendok lemari

o Handle lemari + laci

o Plat stainless steel hairline tebal 1,5 mm

5 Wall Art Tipe - W3 (R. Tamu Pamong) 1.00 unit 11,351,555.00 11,351,555.00

Spesifikasi wall art :

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm

o Multiplek 9 mm

o Kaca polos 8 mm

o Finishing HPL, warna/motif disesuaikan dengan gambar

o Ornamen gunungan MDF 15 mm cutting laser + HPL (cooper brush)

6 Covering Dinding Granit Eksisting (lobby)

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm 30.37 m2 245,041.00 7,441,405.09

o Multiplek 6 mm 30.63 m2 67,388.00 2,063,959.66

o Finishing wallpaper, warna/motif disesuaikan dengan gambar 30.63 m2 279,037.00 8,546,345.24

o Pasangan Hosplint Aluminium (warna putih) 11.78 m1 222,297.00 2,618,658.66

Area Direktorat Jenderal

1 Wall Art Tipe - W4 1.00 unit 14,907,106.00 14,907,106.00

Spesifikasi wall art :

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm

o Multiplek 6 mm

o Bambu ampel 1/2 Ø 10 cm

o Bambu ampel 1/2 Ø 5 cm

o Finishing wallpaper, warna/motif disesuaikan dengan gambar

o Finishing HPL, warna/motif disesuaikan dengan gambar

o Finishing cat politur

2 Wall Art Tipe - W5 1.00 unit 4,814,760.00 4,814,760.00

Spesifikasi wall art :

o Bambu ampel 1/2 Ø 10 cm

o Bambu ampel 1/2 Ø 5 cm

o Finishing wallpaper, warna/motif disesuaikan dengan gambar

o Finishing cat politur

3 Wall Art Tipe - W6 1.00 unit 20,982,576.00 20,982,576.00

Spesifikasi wall art :

o Rangka besi hollow 50x100 mm, tebal 1,8 mm

o Rangka dudukan ornamen besi hollow 20x40 mm, tebal 1,4 mm

o Base plate uk. 10x15 cm, tebal 5 mm + pengelasan

o Dynabolt M-8

o Backing multiplek 6 mm

o Ornamen MDF 20 mm cutting laser + HPL (cooper brush)

o Finishing HPL, warna/motif disesuaikan dengan gambar

o Finishing cat duco, warna tembaga

4 Wall Art Tipe - W7 (Ruang Gamelan) 1.00 unit 25,025,460.00 25,025,460.00

Spesifikasi wall art :

o Rangka box besi hollow 20x40 mm, tebal 1,4 mm

o Multiplek 6 mm

o Finishing HPL, warna/motif disesuaikan dengan gambar

o Batu koral putih

o Ornamen MDF 20 mm cutting laser + HPL (cooper brush)

5 Wall Art Tipe - W8 (Ruang Gamelan) 1.00 unit 23,475,184.00 23,475,184.00

Spesifikasi wall art :

o Rangka box besi hollow 20x40 mm, tebal 1,4 mm

o Multiplek 6 mm

BILL of QUANTITY
ARSITEKTUR - INTERIOR
26
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

o Finishing HPL, warna/motif disesuaikan dengan gambar

o Batu koral putih

o Ornamen MDF 20 mm cutting laser + HPL (cooper brush)

6 Backdrop Tipe - B3 1.00 unit 4,959,542.00 4,959,542.00

Spesifikasi backdrop :

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm

o Multiplek 9 mm

o Finishing HPL, warna/motif disesuaikan dengan gambar

7 Backdrop Tipe - B4 2.00 unit 1,936,914.00 3,873,828.00

Spesifikasi backdrop :

o Multiplek 12 mm

o Finishing HPL, warna/motif disesuaikan dengan gambar

8 Backdrop Tipe - B5 1.00 unit 9,073,450.00 9,073,450.00

Spesifikasi backdrop :

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm

o Base plate uk. 10x10 cm, tebal 5 mm + pengelasan

o Dynabolt M-8

o Multiplek 9 mm

o Finishing HPL, warna/motif disesuaikan dengan gambar

o Finishing cat duco, warna hitam

Sub Jumlah III . B . 6 225,559,179.65

III . B . 7 PEK. LAIN-LAIN

1 Pasangan Penutup Jendela Roller Blind Fabric Sun Screen Seri 1803 Type 1 172.19 m2 595,000.00 102,450,075.00

Lengkap dengan tail bracket, tail plug, aluminium tube, head bracket, clutch, chain,

Fabric sun screen, bottom raill dan end cap

2 Pasangan Penutup Jendela Roller Blind Fabric Black Out Seri 4306 Type 2 26.36 m2 612,340.00 16,143,731.76

Lengkap dengan tail bracket, tail plug, aluminium tube, head bracket, clutch, chain,

Fabric black out, bottom raill dan end cap

3 Pengadaan Furniture Area Lounge

a. Soffa Lounge (Custom) 2.00 unit 10,250,000.00 20,500,000.00

Spesifikasi :

o Dimensi : W.135,7-57 cm x Ø 82 cm x H.74 cm

o Solid wood frame and covered with foam Finishing fabric

b. Round Coffe Table (Custom) 2.00 unit 1,975,600.00 3,951,200.00

Spesifikasi :

o Dimensi : Diameter 600 cm x 450 mm

o Top table plywood finish HPL, tebal 25 mm edging PVC 2 mm

o Bagian bawah top table melaminto putih

o Leg frame Solid beech, Stain, Clear acrylic lacquer

c. Single Seat (Custom) 4.00 unit 755,000.00 3,020,000.00

Spesifikasi :

o Width : 630 mm

o Depth : 740 mm

o Height : 710 mm

o Lapisan tempat duduk dan sandaran fabric

o Kaki stainless steel

d. Meja Bar (Custom) 1.00 unit 2,650,000.00 2,650,000.00

Spesifikasi :

o Dimensi : 240 x 120 x 120 cm

o Top table multipleks 18 mm lapis HPL edging PVC 2 mm

o Kaki rangka besi hollow 60 x 60 mm, finishing cat duco

BILL of QUANTITY
ARSITEKTUR - INTERIOR
27
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

e. Planter Box / Pot Tanaman (Custom) 3.00 unit 355,000.00 1,065,000.00

Spesifikasi :

o Dimensi : Tinggi 90 cm Panjang 70 cm lebar 35 cm

o Material rangka besi kotak finish cat duco

f. Kursi Bar Stool (Pabrikan) 6.00 unit 1,154,000.00 6,924,000.00

Spesifikasi :

o Dimensi : 380 x 380 x 720-940 mm

o Dudukan dan sandaran lapis busa hydolic

o Kaki chrome

g. Snack & Baverage (Custom) 1.00 unit 21,830,251.00 21,830,251.00

Spesifikasi :

o Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm

o Multiplek 18 mm

o Melaminto 3 mm (area sisi dalam almari)

o Finishing HPL, warna disesuaikan dengan gambar

o Top table solid surface tebal 2 cm, Black

o Kaca polos tebal 6 mm

o Glass stone tebal 8 mm, warna putih susu

o List plat stainless steel hairline tebal 1,5 mm

o Engsel sendok

o Magnet Door Stoper Stainless Steel

o Lampu hidend lamp T5 8 watt P=60 cm,lengkap dengan instalasi

Sub Jumlah III . B . 7 178,534,257.76

JUMLAH III . B 1,909,319,836.65

JUMLAH III 3,540,131,201.46

BILL of QUANTITY
ARSITEKTUR - INTERIOR
28
SUB REKAP
BILL of QUANTITY ( ELEKTRIKAL )

KEGIATAN : REDESAIN TATA LETAK RUANG KERJA KANTOR DIREKTORAT JENDERAL

KEBUDAYAAN GEDUNG E LANTAI 9 DAN 10 JAKARTA

LOKASI : JL. JENDERAL SUDIRMAN SENAYAN, KOTAK POS 4104 JAKARTA 10270

TAHUN ANGGARAN : 2020

TOTAL JUMLAH
NO URAIAN KEGIATAN
( Rp )

IV PEKERJAAN ELEKTRIKAL

IV . A LANTAI 9

IV . A . 1 PEK. PANEL LISTRIK 25,175,185.00

IV . A . 2 PEK. INSTALASI KABEL DAYA 1,891,641.00

IV . A . 3 PEK. INSTALASI PENERANGAN DAN STOP KONTAK 231,891,210.00

IV . A . 4 PEK. INSTALASI TATA UDARA / AC 37,091,156.00

IV . A . 5 PEK. INSTALASI FIRE ALARM 3,838,388.00

IV . A . 6 PEK. TRAY KABEL 78,808,250.00

IV . A . 7 PEK. TELEPON / PABX 4,389,912.00

IV . A . 8 PEK. DATA LAN 31,365,272.00

IV . A . 9 PEK. SOUND SYSTEM 28,829,332.00

IV . A . 10 PEK. MATV 33,019,000.00

IV . A . 11 PEK. CCTV 8,014,624.00

IV . B LANTAI 10

IV . B . 1 PEK. PANEL LISTRIK 25,175,185.00

IV . B . 2 PEK. INSTALASI KABEL DAYA 1,891,641.00

IV . B . 3 PEK. INSTALASI PENERANGAN DAN STOP KONTAK 193,628,685.00

IV . B . 4 PEK. INSTALASI TATA UDARA / AC 17,691,736.00

IV . B . 5 PEK. INSTALASI FIRE ALARM 2,993,188.00

IV . B . 6 PEK. TRAY KABEL 79,319,050.00

IV . B . 7 PEK. TELEPON / PABX 4,389,912.00

IV . B . 8 PEK. DATA LAN 26,340,536.00

IV . B . 9 PEK. SOUND SYSTEM 30,344,416.00

IV . B . 10 PEK. MATV 33,019,000.00

IV . B . 11 PEK. CCTV 8,563,030.00

JUMLAH IV 907,670,349.00

SUB REKAP
ELEKTRIKAL
29
RENCANA ANGGARAN BIAYA

KEGIATAN : REDESAIN TATA LETAK RUANG KERJA KANTOR DIREKTORAT JENDERAL

KEBUDAYAAN GEDUNG E LANTAI 9 DAN 10 JAKARTA

LOKASI : JL. JENDERAL SUDIRMAN SENAYAN, KOTAK POS 4104 JAKARTA 10270

TAHUN ANGGARAN : 2020

HARGA SATUAN JUMLAH HARGA


NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

IV PEKERJAAN ELEKTRIKAL

Pengadaan dan instalasi dari peralatan elektrikal harus melibatkan semua

pekerjaan yang menjadi konsekuensi dari terlaksananya pemasangan dengan baik

instalasi beserta support, insulasi, kabel dan armatur lampu termasuk aksesoris

segala pekerjaan sipil serta perapihannya, sehinggga dapat berfungsi baik dan rapi

IV . A LANTAI 9

IV . A . 1 PEK. PANEL LISTRIK

1 Penyesuaian Panel Penerangan Dan Daya ( pada Panel eksisting ke Panel baru ) 1.00 unit 1,575,750.00 1,575,750.00

di Lantai 9 serta berfungsi normal kembali, yang terdiri dari :

o Pembongkaran Panel Eksisting

o Instalasi/konekting dan perapihan kembali pada Panel Baru

2 Pengadaan dan Pemasangan Panel LP/PP-9 di Lantai 9 terdiri dari : 1.00 unit 21,599,435.00 21,599,435.00

o Pilot Lamp + Fuse (R/S/T) TELE (3 set)

o Amper Meter 0 ~ 100 A (3 bh)

o Volt Meter 0 ~ 500 V (1 bh)

o Volt Selector Switch/VSS (1 bh)

o Trafo Arus CT 100/5A, GAE (3 bh)

o MCCB 3P 100~250A 36KA/NSX-250F, Schneider (1 bh)

o MCCB 3P 50~100A 25KA/NSX-100F, Schneider (2 bh)

o Magnetik Kontaktror (MC) 80 A, Schneider (2 bh)

o MCB 1P 10 A 5KA, Schneider (18 bh)

o MCB 1P 16 A 7.5KA, Schneider (24 bh)

o CU Busbar

o Wiring dan Accessories ( 10% Bahan )

o Grounding sistem

o Box Panel 140 x 120 x 40 cm, Free standing

o Biaya Pemasangan

3 Testing Commisioning 1.00 ls 2,000,000.00 2,000,000.00

Sub Jumlah IV . A . 1 25,175,185.00

IV . A . 2 PEK. INSTALASI KABEL DAYA

Pekerjaan Pengadaan dan Pemasangan Kabel Daya berikut Koneksi Instalasi

dan Aksesoris, sehingga dapat berfungsi dengan baik, antara lain :

1 Kabel NYY 4 x 70 mm2, dari Panel SDP Lt. 9 Eksisting ke Panel Baru + Grounding 3.00 m1 630,547.00 1,891,641.00

Sub Jumlah IV . A . 2 1,891,641.00

IV . A . 3 PEK. INSTALASI PENERANGAN DAN STOP KONTAK

1 Instalasi Titik Nyala Lampu dengan Kabel NYM 3 x 2,5 mm2 339.00 ttk 276,870.00 93,858,930.00

dalam Pipa Conduit Lengkap dengan Aksesoris

2 Instalasi Stop Kontak Daya dengan Kabel NYM 3 x 2,5 mm2 44.00 ttk 321,090.00 14,127,960.00

dalam Pipa Conduit Lengkap dengan Aksesoris

3 Instalasi Stop Kontak Daya Lantai dengan Kabel NYM 3 x 2,5 mm2 73.00 ttk 321,090.00 23,439,570.00

dalam Pipa Conduit + Typing dan perapihan kembali Lengkap dengan Aksesoris

BILL of QUANTITY
ELEKTRIKAL
30
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

4 Pengadaan dan Pemasangan Armatur Lampu termasuk Aksesoris terdiri dari :

a. Downlight Outbow dia. 6", LED 15 W 61.00 bh 203,120.00 12,390,320.00

b. LED Strip with Aluminium Profile 18 Watt 12 Volt/meter + Adaptor 183.00 m1 87,500.00 16,012,500.00

c. Downlight dia. 6" Cover Kaca, LED 13 W Philips 27.00 bh 193,050.00 5,212,350.00

d. Lampu LED Spotlight, 7 W 35.00 bh 167,540.00 5,863,900.00

e. Downlight dia. 6" Cover Kaca, LED 10 W Philips 182.00 bh 185,185.00 33,703,670.00

f. Lampu Outbow TL LED Cover 1 x 18 W 6.00 bh 221,400.00 1,328,400.00

g. Lampu Exit LED 5 W c/w Battery 4.00 bh 156,400.00 625,600.00

h. Stop Kontak Dinding 44.00 bh 67,265.00 2,959,660.00

i. Stop Kontak Lantai 2 hole , Panasonic 73.00 bh 225,400.00 16,454,200.00

j. Saklar Tunggal 11.00 bh 72,710.00 799,810.00

k. Saklar Seri 63.00 bh 81,180.00 5,114,340.00

Sub Jumlah IV . A . 3 231,891,210.00

IV . A . 4 PEK. INSTALASI TATA UDARA / AC

1 Pekerjaan Perbaikan, Pengadaan dan Pemasangan Instalasi Tata Udara

Perbaikan dan Pemasangan Instalasi Ducting, Flexible Round Duct,

Supply Diffuser, Return Grill Berikut Support dan Aksesoris lain :

a. Perbaikan dan pemasangan instalasi ducting, flexible round duct 8" 14.00 ttk 588,802.00 8,243,228.00

b. Perbaikan dan pemasangan supply air diffuser 7.00 ttk 369,352.00 2,585,464.00

c. Perbaikan dan pemasangan return air grill 4.00 ttk 407,302.00 1,629,208.00

d. Penggantian dan pemasangan Exhaust air grill 200x200 8.00 ttk 357,082.00 2,856,656.00

e. Pengadaan dan pemasangan linear diffuser 1200X200 (ruang rapat) 12.00 bh 523,050.00 6,276,600.00

2 Testing Commisioning 1.00 ls 1,500,000.00 1,500,000.00

3 Pekerjaan pengadaan Purifier sirkulasi udara, dengan spesifikasi : ( Samsung ) 8.00 unit 1,750,000.00 14,000,000.00

Dimensi : 350 × 540 × 350 mm

Kapasitas : 34 m2, Daya : 30 Watt, instalasi lengkap

Sub Jumlah IV . A . 4 37,091,156.00

IV . A . 5 PEK. INSTALASI FIRE ALARM

1 Pekerjaan Perbaikan, Pengadaan dan Pemasangan Instalasi Pemadam Kebakaran

Berikut Support dan Aksesoris lain :

a. Perbaikan dan pemasangan instalasi pipa sprinkler 12.00 ttk 211,300.00 2,535,600.00

b. Pengadaan dan pemasangan head sprinkler type Pendant 6.00 bh 133,798.00 802,788.00

2 Testing Commisioning 1.00 ls 500,000.00 500,000.00

Sub Jumlah IV . A . 5 3,838,388.00

IV . A . 6 PEK. TRAY KABEL

Pengadaan dan Pemasangan Tray Kabel, Bahan Galvanized, tebal 1,2 mm

Lengkap Aksesoris berikut Support Penggantung

sesuai Gambar Perencanaan dan Spesifikasi, yaitu :

1 Tray Kabel Elektrik / Arus Kuat

a. Kabel Tray U 400 x 100 mm 145.00 m1 283,162.00 41,058,490.00

b. Equal Cross Tray U 400 x 100 mm 2.00 bh 305,000.00 610,000.00

c. Tee Tray U 400 x 100 mm 8.00 bh 277,600.00 2,220,800.00

d. Cover Tray U 400 x 100 mm 12.00 m1 115,000.00 1,380,000.00

2 Tray Kabel Eletronik / Arus Lemah

a. Kabel Tray U 300 x 100 mm 120.00 m1 256,498.00 30,779,760.00

b. Equal Cross Tray U 300 x 100 mm 2.00 bh 193,400.00 386,800.00

c. Tee Tray U 300 x 100 mm 6.00 bh 255,400.00 1,532,400.00

d. Cover Tray U 300 x 100 mm 8.00 m1 105,000.00 840,000.00

Sub Jumlah IV . A . 6 78,808,250.00

BILL of QUANTITY
ELEKTRIKAL
31
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

IV . A . 7 PEK. TELEPON / PABX

1 Pengadaan dan Pemasangan Instalasi Telepon dengan Kabel ITC 2x2x0,60 mm2 4.00 ttk 172,078.00 688,312.00

Conduit HI 20 Lengkap dan Sesuai Gambar Perencanaan dan Persyaratan

2 Pesawat Telepon Panasonic KX TS880 4.00 bh 675,400.00 2,701,600.00

3 Telepon Outlet 4.00 bh 125,000.00 500,000.00

4 Testing Commisioning 1.00 ls 500,000.00 500,000.00

Sub Jumlah IV . A . 7 4,389,912.00

IV . A . 8 PEK. DATA LAN

1 Pengadaan dan Pemasasangan Instalasi LAN dengan Kabel UTP Belden USA 49.00 ttk 233,128.00 11,423,272.00

Cat 6e + Konektor, Conduit PVC dia. 5/8 " Lengkap dan Sesuai

Gambar Perencanaan dan Persyaratan

2 Ceiling Acces Point 4.00 bh 1,255,000.00 5,020,000.00

3 Lan/data Outlet - Inbow 45.00 bh 185,600.00 8,352,000.00

4 Rack Server Wallmount 8 U singledoor 2.00 bh 2,785,000.00 5,570,000.00

5 Testing Commisioning 1.00 ls 1,000,000.00 1,000,000.00

Sub Jumlah IV . A . 8 31,365,272.00

IV . A . 9 PEK. SOUND SYSTEM

1 Pengadaan dan Pemasangan Instalasi Kabel NYMHY 2 x 1,5 mm Ceiling Speaker 19.00 ttk 249,628.00 4,742,932.00

dan Attenuator dengan Conduit PVC dia. 5/8 " Lengkap dan Sesuai

Gambar Perencanaan dan Persyaratan

a. Amplifier Mixer Power 120 W, Toa ZA 2120 1.00 bh 2,675,000.00 2,675,000.00

b. Multimedia Player Background Music Player, Toa Z CD 2011R 1.00 bh 4,650,000.00 4,650,000.00

c. Speaker Selector 10 Channel 2 Input, Daya Input max. 1.000 watt 1.00 bh 1,675,400.00 1,675,400.00

d. Mic Car Call / Pagging, Toa ZM 100EC Golden + Cadangan 2.00 bh 2,876,500.00 5,753,000.00

e. Rack Audio System Toa 12 U Roda 1.00 bh 3,075,400.00 3,075,400.00

f. Terminal Box SS -1 1.00 unit 1,155,000.00 1,155,000.00

g. Ceiling speaker 14.00 bh 255,400.00 3,575,600.00

h. Attenuator / Volume kontrol, Toa ZV 303 5.00 bh 205,400.00 1,027,000.00

2 Testing Commisioning 1.00 ls 500,000.00 500,000.00

Sub Jumlah IV . A . 9 28,829,332.00

IV . A . 10 PEK. MATV

1 Pekerjaan dan Pemasangan Reposisi Instalasi MATV Berikut Lengkap Konektor

dan Berfungsi Sesuai Persyaratan dan Gambar Perencanaan

a. Instalasi kabel Coaxial RG6 MATV 4.00 ttk 127,858.00 511,432.00

b. Reposisi Instalasi kabel Coaxial RG6 MATV 4.00 ttk 74,002.00 296,008.00

c. Instalasi Power MATV NYM 3 x 2,5 mm2 8.00 ttk 276,870.00 2,214,960.00

d. Outlet MATV 8.00 bh 87,500.00 700,000.00

e. Splitter MATV 4 Way 2.00 bh 110,500.00 221,000.00

f. Smart TV Led 43 " + Bracket, Samsung 4.00 unit 6,877,500.00 27,510,000.00

g. Outlet Stop-Kontak 1 phasa 220V/16A 1 gang ( 1 Power ) 8.00 bh 133,200.00 1,065,600.00

2 Testing Commisioning 1.00 ls 500,000.00 500,000.00

Sub Jumlah IV . A . 10 33,019,000.00

IV . A . 11 PEK. CCTV

1 Pekerjaan dan Pemasangan Reposisi Instalasi CCTV Lengkap Berikut Konektor 4.00 ttk 93,406.00 373,624.00

dan Berfungsi Sesuai Persyaratan dan Gambar Perencanaan

a. Power Supply Central Unit, Layar Monitor 1.00 set 5,321,000.00 5,321,000.00

b. Kamera indoor ( eksisting ) 4.00 bh 455,000.00 1,820,000.00

2 Testing Commisioning 1.00 ls 500,000.00 500,000.00

Sub Jumlah IV . A . 11 8,014,624.00

JUMLAH IV . A 484,313,970.00

BILL of QUANTITY
ELEKTRIKAL
32
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

IV . B LANTAI 10

IV . B . 1 PEK. PANEL LISTRIK

1 Penyesuaian Panel Penerangan Dan Daya ( pada Panel eksisting ke Panel baru ) 1.00 unit 1,575,750.00 1,575,750.00

di Lantai 10 serta berfungsi normal kembali, yang terdiri dari :

o Pembongkaran Panel Eksisting

o Instalasi/konekting dan perapihan kembali pada Panel Baru

2 Pengadaan dan Pemasangan Panel LP/PP-10 di Lantai 10 terdiri dari : 1.00 unit 21,599,435.00 21,599,435.00

o Pilot Lamp + Fuse (R/S/T) TELE (3 set)

o Amper Meter 0 ~ 100 A (3 bh)

o Volt Meter 0 ~ 500 V (1 bh)

o Volt Selector Switch/VSS (1 bh)

o Trafo Arus CT 100/5A, GAE (3 bh)

o MCCB 3P 100~250A 36KA/NSX-250F, Schneider (1 bh)

o MCCB 3P 50~100A 25KA/NSX-100F, Schneider (2 bh)

o Magnetik Kontaktror (MC) 80 A, Schneider (2 bh)

o MCB 1P 10 A 5KA, Schneider (18 bh)

o MCB 1P 16 A 7.5KA, Schneider (24 bh)

o CU Busbar

o Wiring dan Accessories ( 10% Bahan )

o Grounding sistem

o Box Panel 140 x 120 x 40 cm, Free standing

o Biaya Pemasangan

3 Testing Commisioning 1.00 ls 2,000,000.00 2,000,000.00

Sub Jumlah IV . B . 1 25,175,185.00

IV . B . 2 PEK. INSTALASI KABEL DAYA

Pekerjaan Pengadaan dan Pemasangan Kabel Daya berikut Koneksi Instalasi

dan Aksesoris, sehingga dapat berfungsi dengan baik, antara lain :

1 Kabel NYY 4 x 70 mm2, dari Panel SDP Lt. 10 Eksisting ke Panel Baru + Grounding 3.00 m1 630,547.00 1,891,641.00

Sub Jumlah IV . B . 2 1,891,641.00

IV . B . 3 PEK. INSTALASI PENERANGAN DAN STOP KONTAK

1 Instalasi Titik Nyala Lampu dengan Kabel NYM 3 x 2,5 mm2 306.00 ttk 276,870.00 84,722,220.00

dalam Pipa Conduit Lengkap dengan Aksesoris

2 Instalasi Stop Kontak Daya dengan Kabel NYM 3 x 2,5 mm2 51.00 ttk 321,090.00 16,375,590.00

dalam Pipa Conduit Lengkap dengan Aksesoris

3 Instalasi Stop Kontak Daya Lantai dengan Kabel NYM 3 x 2,5 mm2 38.00 ttk 321,090.00 12,201,420.00

dalam Pipa Conduit + Typing dan perapihan kembali Lengkap dengan Aksesoris

4 Pengadaan dan Pemasangan Armatur Lampu termasuk Aksesoris terdiri dari :

a. Down Light Outbow dia. 6", LED 15 W 29.00 bh 203,120.00 5,890,480.00

b. LED Strip with Aluminium Profile 18 Watt 12 Volt/meter + Adaptor 60.00 m1 87,500.00 5,250,000.00

c. Downlight dia. 6" Cover Kaca, LED 13 W Philips 32.00 bh 193,050.00 6,177,600.00

d. Lampu LED Spotlight, 7 W 17.00 bh 167,540.00 2,848,180.00

e. Downlight dia. 6" Cover Kaca, LED 10 W Philips 182.00 bh 185,185.00 33,703,670.00

f. Lampu Outbow TL LED Cover 1 x 18 W 6.00 bh 221,400.00 1,328,400.00

g. LED Linear Housing type LED SMD 2835, Size 180 cm 60 Watt + asscesories 27.00 bh 255,400.00 6,895,800.00

h. Kap Lampu Gantung + LED 12 W 3.00 bh 267,500.00 802,500.00

i. Lampu Exit LED 5 W c/w Battery 4.00 bh 156,400.00 625,600.00

j. Stop Kontak Dinding 51.00 bh 67,265.00 3,430,515.00

k. Stop Kontak Lantai 2 hole , Panasonic 38.00 bh 225,400.00 8,565,200.00

l. Saklar Tunggal 7.00 bh 72,710.00 508,970.00

m. Saklar Seri 53.00 bh 81,180.00 4,302,540.00

Sub Jumlah IV . B . 3 193,628,685.00

BILL of QUANTITY
ELEKTRIKAL
33
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

IV . B . 4 PEK. INSTALASI TATA UDARA / AC

1 Pekerjaan Perbaikan, Pengadaan dan Pemasangan Instalasi Tata Udara

Perbaikan dan Pemasangan Instalasi Ducting, Flexible Round Duct,

Supply Diffuser, Return Grill Berikut Support dan Aksesoris lain :

a. Perbaikan dan pemasangan instalasi ducting, flexible round duct 8" 12.00 ttk 588,802.00 7,065,624.00

b. Perbaikan dan pemasangan supply air diffuser 6.00 ttk 369,352.00 2,216,112.00

c. Perbaikan dan pemasangan return air grill 4.00 ttk 407,302.00 1,629,208.00

d. Penggantian dan pemasangan Exhaust air grill 200x200 6.00 ttk 357,082.00 2,142,492.00

e. Pengadaan dan pemasangan linear diffuser 1200X200 (ruang rapat) 6.00 bh 523,050.00 3,138,300.00

2 Testing Commisioning 1.00 ls 1,500,000.00 1,500,000.00

Sub Jumlah IV . B . 4 17,691,736.00

IV . B . 5 PEK. INSTALASI FIRE ALARM

1 Pekerjaan Perbaikan, Pengadaan dan Pemasangan Instalasi Pemadam Kebakaran

Berikut Support dan Aksesoris lain :

a. Perbaikan dan pemasangan instalasi pipa sprinkler 8.00 ttk 211,300.00 1,690,400.00

b. Pengadaan dan pemasangan head sprinkler type Pendant 6.00 bh 133,798.00 802,788.00

2 Testing Commisioning 1.00 ls 500,000.00 500,000.00

Sub Jumlah IV . B . 5 2,993,188.00

IV . B . 6 PEK. TRAY KABEL

Pengadaan dan Pemasangan Tray Kabel, Bahan Galvanized, tebal 1,2 mm

Lengkap Aksesoris berikut Support Penggantung

sesuai Gambar Perencanaan dan Spesifikasi, yaitu :

1 Tray Kabel Elektrik / Arus Kuat

a. Kabel Tray U 400 x 100 mm 145.00 m1 283,162.00 41,058,490.00

b. Equal Cross Tray U 400 x 100 mm 2.00 bh 305,000.00 610,000.00

c. Tee Tray U 400 x 100 mm 8.00 bh 277,600.00 2,220,800.00

d. Cover Tray U 400 x 100 mm 12.00 m1 115,000.00 1,380,000.00

2 Tray Kabel Eletronik / Arus Lemah

a. Kabel Tray U 300 x 100 mm 120.00 m1 256,498.00 30,779,760.00

b. Equal Cross Tray U 300 x 100 mm 2.00 bh 193,400.00 386,800.00

c. Tee Tray U 300 x 100 mm 8.00 bh 255,400.00 2,043,200.00

d. Cover Tray U 300 x 100 mm 8.00 m1 105,000.00 840,000.00

Sub Jumlah IV . B . 6 79,319,050.00

IV . B . 7 PEK. TELEPON / PABX

1 Pengadaan dan Pemasangan Instalasi Telepon dengan Kabel ITC 2x2x0,60 mm2 4.00 ttk 172,078.00 688,312.00

Conduit HI 20 Lengkap dan Sesuai Gambar Perencanaan dan Persyaratan

2 Pesawat Telepon Panasonic KX TS880 4.00 bh 675,400.00 2,701,600.00

3 Telepon Outlet 4.00 bh 125,000.00 500,000.00

4 Testing Commisioning 1.00 ls 500,000.00 500,000.00

Sub Jumlah IV . B . 7 4,389,912.00

IV . B . 8 PEK. DATA LAN

1 Pengadaan dan Pemasasangan Instalasi LAN dengan Kabel UTP Belden USA 37.00 ttk 233,128.00 8,625,736.00

Cat 6e + Konektor, Conduit PVC dia. 5/8 " Lengkap dan Sesuai

Gambar Perencanaan dan Persyaratan

2 Ceiling Acces Point 4.00 bh 1,255,000.00 5,020,000.00

3 Lan/data Outlet - Inbow 33.00 bh 185,600.00 6,124,800.00

4 Rack Server Wallmount 8 U singledoor 2.00 bh 2,785,000.00 5,570,000.00

5 Testing Commisioning 1.00 ls 1,000,000.00 1,000,000.00

Sub Jumlah IV . B . 8 26,340,536.00

BILL of QUANTITY
ELEKTRIKAL
34
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN VOL SAT
( Rp ) ( Rp )

IV . B . 9 PEK. SOUND SYSTEM

1 Pengadaan dan Pemasangan Instalasi Kabel NYMHY 2 x 1,5 mm Ceiling Speaker 22.00 ttk 249,628.00 5,491,816.00

dan Attenuator dengan Conduit PVC dia. 5/8 " Lengkap dan Sesuai

Gambar Perencanaan dan Persyaratan

a. Amplifier Mixer Power 120 W, Toa ZA 2120 1.00 bh 2,675,000.00 2,675,000.00

b. Multimedia Player Background Music Player, Toa Z CD 2011R 1.00 bh 4,650,000.00 4,650,000.00

c. Speaker Selector 10 Channel 2 Input, Daya Input max. 1.000 watt 1.00 bh 1,675,400.00 1,675,400.00

d. Mic Car Call / Pagging, Toa ZM 100EC Golden + Cadangan 2.00 bh 2,876,500.00 5,753,000.00

e. Rack Audio System Toa 12 U Roda 1.00 bh 3,075,400.00 3,075,400.00

f. Terminal Box SS -1 1.00 unit 1,155,000.00 1,155,000.00

g. Ceiling speaker 17.00 bh 255,400.00 4,341,800.00

h. Attenuator / Volume kontrol, Toa ZV 303 5.00 bh 205,400.00 1,027,000.00

2 Testing Commisioning 1.00 ls 500,000.00 500,000.00

Sub Jumlah IV . B . 9 30,344,416.00

IV . B . 10 PEK. MATV

1 Pekerjaan dan Pemasangan Reposisi Instalasi MATV Berikut Lengkap Konektor

dan Berfungsi Sesuai Persyaratan dan Gambar Perencanaan

a. Instalasi kabel Coaxial RG6 MATV 4.00 ttk 127,858.00 511,432.00

b. Reposisi Instalasi kabel Coaxial RG6 MATV 4.00 ttk 74,002.00 296,008.00

c. Instalasi Power MATV NYM 3 x 2,5 mm2 8.00 ttk 276,870.00 2,214,960.00

d. Outlet MATV 8.00 bh 87,500.00 700,000.00

e. Splitter MATV 4 Way 2.00 bh 110,500.00 221,000.00

f. Smart TV Led 43 " + Bracket, Samsung 4.00 unit 6,877,500.00 27,510,000.00

g. Outlet Stop-Kontak 1 phasa 220V/16A 1 gang ( 1 Power ) 8.00 bh 133,200.00 1,065,600.00

2 Testing Commisioning 1.00 ls 500,000.00 500,000.00

Sub Jumlah IV . B . 10 33,019,000.00

IV . B . 11 PEK. CCTV

1 Pekerjaan dan Pemasangan Reposisi Instalasi CCTV Lengkap Berikut Konektor 5.00 ttk 93,406.00 467,030.00

dan Berfungsi Sesuai Persyaratan dan Gambar Perencanaan

a. Power Supply Central Unit, Layar Monitor 1.00 set 5,321,000.00 5,321,000.00

b. Kamera indoor ( eksisting ) 5.00 bh 455,000.00 2,275,000.00

2 Testing Commisioning 1.00 ls 500,000.00 500,000.00

Sub Jumlah IV . B . 11 8,563,030.00

JUMLAH IV . B 423,356,379.00

JUMLAH IV 907,670,349.00

BILL of QUANTITY
ELEKTRIKAL
35
HARGA SATUAN PEKERJAAN

KEGIATAN : REDESAIN TATA LETAK RUANG KERJA KANTOR DIREKTORAT JENDERAL

KEBUDAYAAN GEDUNG E LANTAI 9 DAN 10 JAKARTA

LOKASI : JL. JENDERAL SUDIRMAN SENAYAN, KOTAK POS 4104 JAKARTA 10270

TAHUN ANGGARAN : 2020

KODE URAIAN PEKERJAAN JUMLAH HARGA

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PERSIAPAN

1 1 unit Papan nama proyek spanduk banner uk. 100 x 200 cm 376,528.00

2 1 set Foto dokumentasi menggunakan kamera digital tanpa film 704,000.00

(jika menggunakan kamera digital, untuk dokumentasinya dg CD dan album foto)

3 1 m2 Pembuatan kantor direksi keet sementara dengan lantai plesteran 1,547,536.00

4 1 m2 Pembuatan gudang material dan bedeng buruh pekerja 1,180,241.00

5 1 m2 Pembersihan lokasi proyek 15,675.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN BONGKARAN

1 1 m2 Bongkaran dinding bata + kusen melekat 26,537.00

2 1 m2 Bongkaran dinding partisi kaca/partisi gypsum termasuk rangka + kusen 38,252.00

& daun pintu/jendela melekat

3 1 m2 Bongkaran rangka + penutup plafond 20,075.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN DINDING PARTISI

1 1 m2 Pasangan rangka dinding partisi, metal stud + u runner 150,072.00

2 1 m1 Pasangan aluminium "U" uk. 20x20x2 mm 46,528.00

3 1 m2 Pasangan penutup dinding partisi gypsum tbl. 12 mm 73,791.00

4 1 m2 Pasangan lapisan peredam suara rockwool density 60 kg/m3 90,238.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PINTU DAN JENDELA ALUMINIUM

1 1 m1 Pasangan kusen aluminium 4" powder coating 140,745.00

2 1 m1 Pasangan frame daun pintu aluminium powder coating 237,545.00

3 1 m2 Pasangan daun pintu double multiplek 9 mm, rangka kayu kamper 698,489.00

4 1 m2 Pasangan kaca polos, tebal 6 mm 227,966.00

5 1 m2 Pasangan kaca polos, tebal 8 mm 361,550.00

6 1 m2 Pasangan kaca painted glass stone, tebal 8 mm warna putih 347,756.00

7 1 m2 Pasangan kaca tempered, tebal 12 mm 1,102,070.00

8 1 m2 Pasangan finishing HPL 191,449.00

HARGA SATUAN PEKERJAAN/HSP


36
KODE URAIAN PEKERJAAN JUMLAH HARGA

9 1 m2 Pasangan stiker sandblast kaca 78,106.00

10 1 unit Daun Pintu Kaca, Type P-1 9,254,403.00

11 1 unit Daun Pintu Kaca, Type P-2 9,379,803.00

12 1 unit Daun Pintu Kaca, Type P-3 18,024,066.00

13 1 unit Daun Pintu Kaca, Type P-3A 20,119,991.00

14 1 unit Daun Pintu Kaca Frame Aluminium, Type P-4 8,357,357.00

15 1 unit Kusen Pintu dan Daun Pintu, Type P-5 4,433,403.00

16 1 unit Kusen Pintu dan Daun Pintu, Type PJ1 5,807,269.00

17 1 unit Pengecatan Kusen dan Daun Pintu Besi, Type PE-1 (eksisting) 1,157,106.00

18 1 unit Partisi Kaca Folding, Type PK-1 (Fabrikasi) 20,530,300.00

19 1 unit Partisi Kaca Folding, Type PK-2 (Fabrikasi) 13,562,400.00

20 1 unit Partisi Kaca Folding, Type PK-3 (Fabrikasi) 12,549,100.00

21 1 unit Partisi Kaca Folding, Type PK-4 (Fabrikasi) 31,265,600.00

22 1 unit Partisi Movable Wall Type MW-1 (Fabrikasi) 20,495,507.00

23 1 unit Partisi Movable Wall Type MW-2 (Fabrikasi) 9,855,600.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENGGANTUNG DAN KUNCI

1 1 set Pasangan engsel pintu 121,446.00

2 1 bh Pasangan floor hinges FH 80 SSS 5,312,896.00

3 1 bh Pasangan bottom pivot patch PT 10/PSS 208,346.00

4 1 bh Pasangan top pivot patch PT 20 143,446.00

5 1 bh Pasangan patch fitting PT 40 165,886.00

6 1 bh Pasangan patch lock US 10/PSS + Cylinder PC 91/61 mm 308,456.00

7 1 set Pasangan pull handle stainless steel, panjang 60 cm 918,156.00

8 1 set Pasangan pull handle stainless steel tinggi 30 cm 456,156.00

9 1 set Pasangan pull handle stainless steel, panjang 120 cm 1,693,656.00

10 1 bh Pasangan door closer 398,406.00

11 1 psg Pasangan lever handle pintu 387,406.00

12 1 bh Pasangan escutcheon 66,456.00

13 1 set Pasangan mortise lock 242,896.00

14 1 set Pasangan cylinder DC + kunci 165,456.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN DINDING

1 1 m2 Pasangan lantai vinyl uk. 304,8 x 609,6 x 3 mm grey slate (V-1 Type 1) 296,648.00

2 1 m2 Pasangan lantai vinyl uk. 152,4 x 914,4 x 3 mm washed oak (V-2 Type 2) 313,808.00

3 1 m1 Pasangan plin dinding lengkung (hosplin aluminium 12 cm) 222,297.00

4 1 m2 Pasangan wallpaper 279,037.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PLAFOND

1 1 m2 Pasangan rangka plafond besi hollow 40/40 & 20/40 mm galvalum 100,738.00

2 1 m2 Pasangan penutup plafond gypsum tbl. 9 mm 55,067.00

HARGA SATUAN PEKERJAAN/HSP


37
KODE URAIAN PEKERJAAN JUMLAH HARGA

3 1 m1 Pasangan up/down ceiling plafond 94,567.00

4 1 m1 Pasangan list plafond shadow line tebal 3 mm 38,247.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENGECATAN

1 1 m2 Pengecatan dinding, partisi dan plafond 1 lapis cat dasar, 2 lapis cat penutup (interior) 40,759.00

2 1 m2 Pengecatan politur dengan semprot 113,333.00

3 1 m2 Pengecatan zinchromate baja/besi 39,798.00

4 1 m2 Pengecatan duco dengan cara semprot 255,997.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN INTERIOR MELEKAT

1 1 m3 Pasangan rangka kayu solid jati uk. 40x40 mm 10,556,975.00

2 1 m2 Pasangan multiplek tebal 9 mm 76,628.00

3 1 m2 Pasangan multiplek tebal 6 mm 67,388.00

4 1 m2 Pasangan multiplek tebal 15 mm 111,278.00

5 1 m2 Pasangan multiplek tebal 20 mm 155,622.00

6 1 m2 Pasangan multiplek tebal 12 mm 100,306.00

7 1 m2 Pasangan multiplek tebal 18 mm 137,060.00

8 1 m2 Pasangan melaminto tebal 3 mm 52,085.00

9 1 m2 Pasangan solid surface tebal 2 cm, warna hitam 1,785,236.00

10 1 m1 Pasangan list plat stainless steel hairline tebal 1,5 mm 151,984.00

11 1 m2 Pasangan Rangka kayu kamper solid uk. 20x30 mm 82,265.00

12 1 m2 Pasangan finishing HPL 200,084.00

13 1 m2 Pasangan rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm 245,041.00

14 1 m2 Pasangan ornamen MDF 15 mm, cutting laser + HPL 1,155,935.00

15 1 m2 Pasangan ornamen MDF 20 mm, cutting laser + HPL 1,180,135.00

16 1 unit Wall Art Tipe - W1 4,888,485.00

17 1 unit Wall Art Tipe - W2 7,854,231.00

18 1 unit Wall Art Tipe - W3 11,351,555.00

19 1 unit Wall Art Tipe - W4 14,907,106.00

20 1 unit Wall Art Tipe - W5 4,814,760.00

21 1 unit Wall Art Tipe - W6 20,982,576.00

22 1 unit Wall Art Tipe - W7 25,025,460.00

23 1 unit Wall Art Tipe - W8 23,475,184.00

24 1 unit Ornamen Kolom Tipe - CK1 4,400,309.00

25 1 unit Backdrop Tipe - B1 18,704,251.00

26 1 unit Backdrop Tipe - B2 7,151,812.00

27 1 unit Backdrop Tipe - B3 4,959,542.00

28 1 unit Backdrop Tipe - B4 1,936,914.00

29 1 unit Backdrop Tipe - B5 9,073,450.00

30 1 unit Meja Resepsionis 6,584,945.00

31 1 unit Wall Covering Tipe - WC1 12,581,064.00

HARGA SATUAN PEKERJAAN/HSP


38
KODE URAIAN PEKERJAAN JUMLAH HARGA

32 1 unit Covering Kolom Tipe - CK2 6,035,131.00

33 1 unit Covering Kolom Tipe - CK3 4,221,831.00

34 1 unit Covering Kolom Tipe - CK4 2,713,048.00

35 1 unit Covering Kolom Tipe - CK5 5,730,614.00

36 1 unit Covering Kolom Tipe - CK6 3,702,745.00

37 1 unit Wall Art Tipe - W9 8,782,670.00

38 1 unit Snack & Baverage 21,830,251.00

HARGA SATUAN PEKERJAAN/HSP


39
HARGA SATUAN PEKERJAAN

KEGIATAN : REDESAIN TATA LETAK RUANG KERJA KANTOR DIREKTORAT JENDERAL

KEBUDAYAAN GEDUNG E LANTAI 9 DAN 10 JAKARTA

LOKASI : JL. JENDERAL SUDIRMAN SENAYAN, KOTAK POS 4104 JAKARTA 10270

TAHUN ANGGARAN : 2020

KODE URAIAN PEKERJAAN JUMLAH HARGA

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN ELEKTRIKAL

1 1 unit Penyesuaian dan pembongkaran panel eksisting 1,575,750.00

2 1 unit Panel penerangan dan daya ( P.LP/PP-9 ) Lantai 9, Penyesuaian 21,599,435.00

3 1 unit Panel penerangan dan daya ( P.LP/PP-10 ) Lantai 10, Penyesuaian 21,599,435.00

4 1 m1 Pasangan kabel daya NYY 4 x 70 mm2 630,547.00

5 1 titik Instalasi titik nyala lampu dengan kabel NYM 3 x 2,5 mm2 276,870.00

6 1 titik Instalasi stop kontak daya dengan kabel NYM 3 x 2,5 mm2 321,090.00

7 1 bh Pasangan lampu downlight dia 6" cover kaca, LED 13 W Philips 193,050.00

8 1 bh Pasangan lampu downlight dia 6" cover kaca, LED 10 W Philips 185,185.00

9 1 bh Pasangan stop kontak 67,265.00

10 1 bh Pasangan saklar tunggal 72,710.00

11 1 bh Pasangan saklar ganda 81,180.00

12 1 m1 Pasangan tray kabel uk. 400 x 100 x 3000 mm 283,162.00

13 1 m1 Pasangan tray kabel uk. 300 x 100 x 3000 mm 256,498.00

14 1 titik Instalasi telepon 172,078.00

15 1 titik Instalasi LAN 233,128.00

16 1 titik Instalasi sound sistem dengan kabel NYMHY 3 x 1,5 mm2 249,628.00

17 1 titik Instalasi MATV 127,858.00

18 1 titik Reposisi instalasi MATV 74,002.00

19 1 titik Reposisi instalasi CCTV 93,406.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN AC DUCTING

1 1 bh Pasangan head sprinkler 133,798.00

2 1 titik Perbaikan ducting, pasangan flexible round duct 8" 588,802.00

3 1 bh Perbaikan & pasangan supply air diffuser 369,352.00

4 1 bh Perbaikan & pasangan Return Air Grill (RAG) 407,302.00

5 1 bh Pasangan linear diffuser 1200x200 mm 523,050.00

6 1 bh Pasangan exhaust air grill (EAG) 357,082.00

HARGA SATUAN PEKERJAAN/HSP


40
ANALISA HARGA SATUAN

KEGIATAN : REDESAIN TATA LETAK RUANG KERJA KANTOR DIREKTORAT JENDERAL

KEBUDAYAAN GEDUNG E LANTAI 9 DAN 10 JAKARTA

LOKASI : JL. JENDERAL SUDIRMAN SENAYAN, KOTAK POS 4104 JAKARTA 10270

TAHUN ANGGARAN : 2020

HARGA SATUAN JUMLAH HARGA


NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PERSIAPAN

1 1 unit Papan nama proyek spanduk banner uk. 100 x 200 cm

Banner spanduk uk. 100 x 200 cm m2 2.0000 125,000.00 250,000.00


Bahan
Multiplek 9 mm lbr 0.7000 98,000.00 68,600.00

Pekerja oh 0.1500 125,000.00 18,750.00

Tukang kayu oh 0.0150 140,000.00 2,100.00


Tenaga
Kepala tukang oh 0.0160 160,000.00 2,560.00

Mandor oh 0.0017 175,000.00 288.75

Jumlah 342,298.75

Keuntungan Mak. 10% 34,229.88

Jumlah + Keuntungan 376,528.63

Dibulatkan 376,528.00

1 set Foto dokumentasi menggunakan kamera digital tanpa film


2
(jika menggunakan kamera digital, untuk dokumentasinya dg CD dan album foto)

CD copy soft file foto image bh 2.0000 5,000.00 10,000.00

Bahan Cetak foto lbr 80.0000 3,000.00 240,000.00

Album foto ls 1.0000 75,000.00 75,000.00

Tenaga Tukang foto oh 1.0000 140,000.00 140,000.00

Peralatan Kamera DSLR Sewa/hari 1.0000 175,000.00 175,000.00

Jumlah 640,000.00

Keuntungan Mak. 10% 64,000.00

Jumlah + Keuntungan 704,000.00

Dibulatkan 704,000.00

3 1 m2 Pembuatan kantor direksi keet sementara dengan lantai plesteran

Kayu kelas III m3 0.1800 2,455,000.00 441,900.00

Paku biasa kg 0.0800 22,500.00 1,800.00

Besi strip kg 1.1000 11,500.00 12,650.00

Semen portland kg 35.0000 1,200.00 42,000.00

Pasir pasang m3 0.1500 230,000.00 34,500.00

Pasir beton m3 0.1000 232,400.00 23,240.00

Bahan Koral beton m3 0.1500 236,500.00 35,475.00

Bata merah bh 30.0000 650.00 19,500.00

Seng gelombang lbr 0.2500 49,000.00 12,250.00

Jendela nako bh 0.2000 110,500.00 22,100.00

Kaca polos 3 mm m2 0.0800 105,000.00 8,400.00

Kunci tanam bh 0.1500 145,000.00 21,750.00

Triplek 6 mm lbr 0.0600 75,600.00 4,536.00

Pekerja oh 2.0000 125,000.00 250,000.00

Tukang kayu oh 2.0000 140,000.00 280,000.00

Tenaga Tukang batu oh 1.0000 140,000.00 140,000.00

Kepala tukang oh 0.3000 160,000.00 48,000.00

Mandor oh 0.0500 175,000.00 8,750.00

Jumlah 1,406,851.00

Keuntungan Mak. 10% 140,685.10

Jumlah + Keuntungan 1,547,536.10

Dibulatkan 1,547,536.00

ANALISA HARGA SATUAN


41
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

4 1 m2 Pembuatan gudang material dan bedeng buruh pekerja

Kayu kelas III m3 0.2100 2,455,000.00 515,550.00

Paku biasa kg 0.3000 22,500.00 6,750.00

Semen portland kg 10.5000 1,200.00 12,600.00


Bahan
Pasir beton m3 0.0300 232,400.00 6,972.00

Koral beton m3 0.0500 236,500.00 11,825.00

Seng gelombang bjls 28 lbr 1.5000 49,000.00 73,500.00

Pekerja oh 1.0000 125,000.00 125,000.00

Tukang kayu oh 2.0000 140,000.00 280,000.00


Tenaga
Kepala tukang oh 0.2000 160,000.00 32,000.00

Mandor oh 0.0500 175,000.00 8,750.00

Jumlah 1,072,947.00

Keuntungan Mak. 10% 107,294.70

Jumlah + Keuntungan 1,180,241.70

Dibulatkan 1,180,241.00

5 1 m2 Pembersihan lokasi proyek

Pekerja oh 0.1000 125,000.00 12,500.00


Tenaga
Mandor oh 0.0100 175,000.00 1,750.00

Jumlah 14,250.00

Keuntungan Mak. 10% 1,425.00

Jumlah + Keuntungan 15,675.00

Dibulatkan 15,675.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN BONGKARAN

1 1 m2 Bongkaran dinding bata + kusen melekat

Pekerja oh 0.1300 125,000.00 16,250.00


Tenaga
Mandor oh 0.0450 175,000.00 7,875.00

Jumlah 24,125.00

Keuntungan Mak. 10% 2,412.50

Jumlah + Keuntungan 26,537.50

Dibulatkan 26,537.00

2 1 m2 Bongkaran dinding partisi kaca/partisi gypsum termasuk rangka + kusen

& daun pintu/jendela melekat

Pekerja oh 0.1900 125,000.00 23,750.00


Tenaga
Mandor oh 0.0630 175,000.00 11,025.00

Jumlah 34,775.00

Keuntungan Mak. 10% 3,477.50

Jumlah + Keuntungan 38,252.50

Dibulatkan 38,252.00

3 1 m2 Bongkaran rangka + penutup plafond

Pekerja oh 0.1250 125,000.00 15,625.00


Tenaga
Mandor oh 0.0150 175,000.00 2,625.00

Jumlah 18,250.00

Keuntungan Mak. 10% 1,825.00

Jumlah + Keuntungan 20,075.00

Dibulatkan 20,075.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN DINDING PARTISI

1 1 m2 Pasangan rangka dinding partisi, metal stud + u runner

Metal stud uk. 34x76 mm tbl. 0,40 mm m1 1.1000 26,500.00 29,150.00

Bahan U runner uk. 25x76 mm tbl. 0,35 mm m1 1.1000 12,400.00 13,640.00

Alat bantu termasuk sekrup, dll ls 1.0000 2,139.50 2,139.50

ANALISA HARGA SATUAN


42
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

Pekerja oh 0.1500 125,000.00 18,750.00

Tukang kayu oh 0.4500 140,000.00 63,000.00


Tenaga
Kepala tukang oh 0.0500 160,000.00 8,000.00

Mandor oh 0.0100 175,000.00 1,750.00

Jumlah 136,429.50

Keuntungan Mak. 10% 13,642.95

Jumlah + Keuntungan 150,072.45

Dibulatkan 150,072.00

2 1 m1 Pasangan aluminium "U" uk. 20x20x2 mm

Aluminium "U" uk. 20x20x2 mm m1 1.1000 28,700.00 31,570.00


Bahan
Alat bantu termasuk sekrup, dll ls 1.0000 1,578.50 1,578.50

Pekerja oh 0.0150 125,000.00 1,875.00

Tukang kayu oh 0.0450 140,000.00 6,300.00


Tenaga
Kepala tukang oh 0.0050 160,000.00 800.00

Mandor oh 0.0010 175,000.00 175.00

Jumlah 42,298.50

Keuntungan Mak. 10% 4,229.85

Jumlah + Keuntungan 46,528.35

Dibulatkan 46,528.00

3 1 m2 Pasangan penutup dinding partisi gypsum tbl. 12 mm

Gypsum board tbl. 12 mm lbr 0.3470 144,700.00 50,210.90

Bahan Gypsum tape rol 0.0533 30,000.00 1,600.00

Paku sekrup kg 0.0100 34,000.00 340.00

Pekerja oh 0.0300 125,000.00 3,750.00

Tukang kayu oh 0.0700 140,000.00 9,800.00


Tenaga
Kepala tukang oh 0.0070 160,000.00 1,120.00

Mandor oh 0.0015 175,000.00 262.50

Jumlah 67,083.40

Keuntungan Mak. 10% 6,708.34

Jumlah + Keuntungan 73,791.74

Dibulatkan 73,791.00

4 1 m2 Pasangan lapisan peredam suara rockwool density 60 kg/m3

Bahan Rockwool, density 60 kg/m3 m2 1.0500 49,700.00 52,185.00

Pekerja oh 0.1000 125,000.00 12,500.00

Tukang kayu oh 0.1000 140,000.00 14,000.00


Tenaga
Kepala tukang oh 0.0100 160,000.00 1,600.00

Mandor oh 0.0100 175,000.00 1,750.00

Jumlah 82,035.00

Keuntungan Mak. 10% 8,203.50

Jumlah + Keuntungan 90,238.50

Dibulatkan 90,238.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PINTU DAN JENDELA ALUMINIUM

1 1 m1 Pasangan kusen aluminium 4" powder coating

Bahan Profil aluminium 4" powder coating m1 1.1000 105,000.00 115,500.00

Pekerja oh 0.0430 125,000.00 5,375.00

Tukang besi oh 0.0430 140,000.00 6,020.00


Tenaga
Kepala tukang oh 0.0043 160,000.00 688.00

Mandor oh 0.0021 175,000.00 367.50

Jumlah 127,950.50

Keuntungan Mak. 10% 12,795.05

Jumlah + Keuntungan 140,745.55

Dibulatkan 140,745.00

ANALISA HARGA SATUAN


43
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

2 1 m1 Pasangan frame daun pintu aluminium powder coating

Bahan Profil frame daun pintu aluminium powder coating m1 1.1000 185,000.00 203,500.00

Pekerja oh 0.0430 125,000.00 5,375.00

Tukang besi oh 0.0430 140,000.00 6,020.00


Tenaga
Kepala tukang oh 0.0043 160,000.00 688.00

Mandor oh 0.0021 175,000.00 367.50

Jumlah 215,950.50

Keuntungan Mak. 10% 21,595.05

Jumlah + Keuntungan 237,545.55

Dibulatkan 237,545.00

3 1 m2 Pasangan daun pintu double multiplek 9 mm, rangka kayu kamper

Rangka kayu kamper m3 0.0160 3,897,500.00 62,360.00

Multiplek 9 mm m2 2.0000 98,000.00 196,000.00


Bahan
Lem kayu kg 0.4000 55,000.00 22,000.00

Paku kg 0.0400 34,500.00 1,380.00

Pekerja oh 0.5000 125,000.00 62,500.00

Tukang kayu oh 1.0000 140,000.00 140,000.00


Tenaga
Kepala tukang oh 0.4500 160,000.00 72,000.00

Mandor oh 0.4500 175,000.00 78,750.00

Jumlah 634,990.00

Keuntungan Mak. 10% 63,499.00

Jumlah + Keuntungan 698,489.00

Dibulatkan 698,489.00

4 1 m2 Pasangan kaca polos, tebal 6 mm

Bahan Kaca polos, tebal 6 mm m2 1.1000 163,000.00 179,300.00

Pekerja oh 0.0165 125,000.00 2,062.50

Tukang kayu oh 0.1650 140,000.00 23,100.00


Tenaga
Kepala tukang oh 0.0165 160,000.00 2,640.00

Mandor oh 0.0008 175,000.00 140.00

Jumlah 207,242.50

Keuntungan Mak. 10% 20,724.25

Jumlah + Keuntungan 227,966.75

Dibulatkan 227,966.00

5 1 m2 Pasangan kaca polos, tebal 8 mm

Bahan Kaca polos, tebal 8 mm m2 1.1000 273,400.00 300,740.00

Pekerja oh 0.0165 125,000.00 2,062.50

Tukang kayu oh 0.1650 140,000.00 23,100.00


Tenaga
Kepala tukang oh 0.0165 160,000.00 2,640.00

Mandor oh 0.0008 175,000.00 140.00

Jumlah 328,682.50

Keuntungan Mak. 10% 32,868.25

Jumlah + Keuntungan 361,550.75

Dibulatkan 361,550.00

6 1 m2 Pasangan kaca painted glass stone, tebal 8 mm warna putih

Bahan kaca painted glass stone, tebal 8 mm warna putih m2 1.1000 262,000.00 288,200.00

Pekerja oh 0.0165 125,000.00 2,062.50

Tukang kayu oh 0.1650 140,000.00 23,100.00


Tenaga
Kepala tukang oh 0.0165 160,000.00 2,640.00

Mandor oh 0.0008 175,000.00 140.00

Jumlah 316,142.50

Keuntungan Mak. 10% 31,614.25

Jumlah + Keuntungan 347,756.75

Dibulatkan 347,756.00

ANALISA HARGA SATUAN


44
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

7 1 m2 Pasangan kaca tempered, tebal 12 mm

Bahan Kaca tempered, tebal 12 mm m2 1.1000 885,400.00 973,940.00

Pekerja oh 0.0165 125,000.00 2,062.50

Tukang kayu oh 0.1650 140,000.00 23,100.00


Tenaga
Kepala tukang oh 0.0165 160,000.00 2,640.00

Mandor oh 0.0008 175,000.00 140.00

Jumlah 1,001,882.50

Keuntungan Mak. 10% 100,188.25

Jumlah + Keuntungan 1,102,070.75

Dibulatkan 1,102,070.00

8 1 m2 Pasangan finishing HPL

HPL taco m2 1.1000 78,500.00 86,350.00


Bahan
Lem kuning kg 0.2500 55,000.00 13,750.00

Pekerja oh 0.1750 125,000.00 21,875.00

Tukang kayu oh 0.3500 140,000.00 49,000.00


Tenaga
Kepala tukang oh 0.0170 160,000.00 2,720.00

Mandor oh 0.0020 175,000.00 350.00

Jumlah 174,045.00

Keuntungan Mak. 10% 17,404.50

Jumlah + Keuntungan 191,449.50

Dibulatkan 191,449.00

9 1 m2 Pasangan stiker sandblast kaca

Bahan Stiker sandblast m2 1.0000 45,600.00 45,600.00

Pekerja oh 0.0150 125,000.00 1,875.00

Tukang kayu oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.0150 160,000.00 2,400.00

Mandor oh 0.0008 175,000.00 131.25

Jumlah 71,006.25

Keuntungan Mak. 10% 7,100.63

Jumlah + Keuntungan 78,106.88

Dibulatkan 78,106.00

10 1 unit Daun Pintu Kaca, Type P-1

Kaca tempered 12 mm m2 2.0475 1,102,070.00 2,256,488.33

Pasangan stiker sandblast kaca m2 1.3650 78,106.00 106,614.69

Pull handle SS-304 38x630x600 mm TPH 981 psg 1.0000 918,156.00 918,156.00
Bahan &
Floor hinge FH 80 SSS bh 1.0000 5,312,896.00 5,312,896.00
Tenaga
Top patch PT 20 bh 1.0000 143,446.00 143,446.00

Bottom patch PT 10 bh 1.0000 208,346.00 208,346.00

Corner lock/Patch lock US 10 bh 1.0000 308,456.00 308,456.00

Jumlah 9,254,403.02

Dibulatkan 9,254,403.00

11 1 unit Daun Pintu Kaca, Type P-2

Kaca tempered 12 mm m2 2.0475 1,102,070.00 2,256,488.33

Pasangan stiker sandblast kaca m2 1.3650 78,106.00 106,614.69

Pull handle SS-304 38x630x600 mm TPH 981 psg 1.0000 918,156.00 918,156.00

Bahan & Floor hinge FH 80 SSS bh 1.0000 5,312,896.00 5,312,896.00


Tenaga Top patch PT 20 bh 1.0000 143,446.00 143,446.00

Patch fitting PT 40 bh 1.0000 125,400.00 125,400.00

Bottom patch PT 10 bh 1.0000 208,346.00 208,346.00

Corner lock/Patch lock US 10 bh 1.0000 308,456.00 308,456.00

Jumlah 9,379,803.02

Dibulatkan 9,379,803.00

ANALISA HARGA SATUAN


45
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

12 1 unit Daun Pintu Kaca, Type P-3

Kaca tempered 12 mm m2 3.6750 1,102,070.00 4,050,107.25

Pasangan stiker sandblast kaca m2 2.4500 78,106.00 191,359.70

Pull handle SS-304 38x1200 mm PH 802 psg 2.0000 918,156.00 1,836,312.00


Bahan &
Floor hinge FH 80 SSS bh 2.0000 5,312,896.00 10,625,792.00
Tenaga
Top patch PT 20 bh 2.0000 143,446.00 286,892.00

Bottom patch PT 10 bh 2.0000 208,346.00 416,692.00

Corner lock/Patch lock US 10 bh 2.0000 308,456.00 616,912.00

Jumlah 18,024,066.95

Dibulatkan 18,024,066.00

13 1 unit Daun Pintu Kaca, Type P-3A

Kaca tempered 12 mm m2 3.6750 1,102,070.00 4,050,107.25

Pasangan stiker sandblast kaca m2 2.4500 78,106.00 191,359.70

Pull handle SS-304 38x1200 mm PH 802 psg 2.0000 1,693,656.00 3,387,312.00

Floor hinge FH 80 SSS bh 2.0000 5,312,896.00 10,625,792.00


Bahan &
Top patch PT 20 bh 2.0000 143,446.00 286,892.00
Tenaga
Bottom patch PT 10 bh 2.0000 208,346.00 416,692.00

Corner lock/Patch lock US 10 bh 2.0000 308,456.00 616,912.00

Architrave multiplek 100x15 mm m2 1.2700 182,000.00 231,140.00

Pasangan HPL, warna/tekstur disesuaikan dengan gambar m2 1.6390 191,449.00 313,784.91

Jumlah 20,119,991.86

Dibulatkan 20,119,991.00

14 1 unit Daun Pintu Kaca Frame Aluminium, Type P-4

Frame aluminium 4", powder coating (white) m1 5.0000 140,745.00 703,725.00

Kaca polos 8 mm m2 1.2738 361,550.00 460,542.39

Engsel pintu set 3.0000 121,446.00 364,338.00

Pull handle SS-304 32x300 mm PH 801 psg 1.0000 456,156.00 456,156.00

Floor hinge FH 80 SSS bh 1.0000 5,312,896.00 5,312,896.00


Bahan &
Top patch PT 20 bh 1.0000 143,446.00 143,446.00
Tenaga
Bottom patch PT 10 bh 1.0000 208,346.00 208,346.00

Mortise lock set 1.0000 242,896.00 242,896.00

Escutcheon bh 1.0000 66,456.00 66,456.00

Cylinder + kunci set 1.0000 165,456.00 165,456.00

Sealant kaca m1 10.3600 22,500.00 233,100.00

Jumlah 8,357,357.39

Dibulatkan 8,357,357.00

15 1 unit Kusen Pintu dan Daun Pintu, Type P-5

Kusen aluminium 4", powder coating (white) m1 5.1000 140,745.00 717,799.50

Daun pintu multiplek 9 mm + rangka kayu m2 1.6800 698,489.00 1,173,461.52

Finishing daun pintu HPL serat kayu m2 3.5920 191,449.00 687,684.81

Engsel pintu set 3.0000 121,446.00 364,338.00

Bahan & Lever handle psg 1.0000 387,406.00 387,406.00


Tenaga Mortise lock set 1.0000 242,896.00 242,896.00

Escutcheon bh 1.0000 66,456.00 66,456.00

Door closer bh 1.0000 398,406.00 398,406.00

Cylinder + kunci set 1.0000 165,456.00 165,456.00

Sealant m1 10.2000 22,500.00 229,500.00

Jumlah 4,433,403.83

Dibulatkan 4,433,403.00

16 1 unit Kusen Pintu dan Daun Pintu, Type PJ1

Kusen aluminium 4", powder coating (white) m1 9.9400 140,745.00 1,399,005.30

Daun pintu multiplek 9 mm + rangka kayu m2 1.6800 698,489.00 1,173,461.52

Finishing daun pintu HPL serat kayu m2 3.5920 191,449.00 687,684.81

Kaca polos 6 mm m2 1.2250 227,966.00 279,258.35

Bahan &
Tenaga

ANALISA HARGA SATUAN


46
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

Engsel pintu set 3.0000 121,446.00 364,338.00


Bahan &
Lever handle psg 1.0000 387,406.00 387,406.00
Tenaga
Mortise lock set 1.0000 242,896.00 242,896.00

Escutcheon bh 1.0000 66,456.00 66,456.00

Door closer bh 1.0000 398,406.00 398,406.00

Cylinder + kunci set 1.0000 165,456.00 165,456.00

Sealant kusen + kaca m1 28.5734 22,500.00 642,901.50

Jumlah 5,807,269.48

Dibulatkan 5,807,269.00

17 1 unit Pengecatan Kusen dan Daun Pintu Besi, Type PE-1 (eksisting)

Bahan & kusen m2 1.0400 255,997.00 266,236.88


Tenaga daun pintu m2 3.4800 255,997.00 890,869.56

Jumlah 1,157,106.44

Dibulatkan 1,157,106.00

18 1 unit Partisi Kaca Folding, Type PK-1 (Fabrikasi)

Panel sliding aluminium uk. 210x91 cm + kaca tb. 8 mm bh 5.0000 2,975,400.00 14,877,000.00

Track runner set 2.0000 495,400.00 990,800.00

Bahan & Finishing powder coating super white gloss 160 m1 30.1000 125,000.00 3,762,500.00
Tenaga Aksessoris Slot dan cylinder key, Rell dan roda ls 1.0000 550,000.00 550,000.00

Kontruksi penggantung CNP 100X50X2,3 mm ls 1.0000 350,000.00 350,000.00

dan besi siku 30x30x3 mm

Jumlah 20,530,300.00

Dibulatkan 20,530,300.00

19 1 unit Partisi Kaca Folding, Type PK-2 (Fabrikasi)

Panel sliding aluminium uk. 210x90 cm + kaca tb. 8 mm bh 3.0000 2,975,400.00 8,926,200.00

Track runner set 3.0000 495,400.00 1,486,200.00

Bahan & Finishing powder coating super white gloss 160 m1 18.0000 125,000.00 2,250,000.00
Tenaga Aksessoris Slot dan cylinder key, Rell dan roda ls 1.0000 550,000.00 550,000.00

Kontruksi penggantung CNP 100X50X2,3 mm ls 1.0000 350,000.00 350,000.00

dan besi siku 30x30x3 mm

Jumlah 13,562,400.00

Dibulatkan 13,562,400.00

20 1 unit Partisi Kaca Folding, Type PK-3 (Fabrikasi)

Panel sliding aluminium uk. 210x87 cm + kaca tb. 8 mm bh 3.0000 2,975,400.00 8,926,200.00

Track runner set 1.0000 495,400.00 495,400.00

Bahan & Finishing powder coating super white gloss 160 m1 17.8200 125,000.00 2,227,500.00
Tenaga Aksessoris Slot dan cylinder key, Rell dan roda ls 1.0000 550,000.00 550,000.00

Kontruksi penggantung CNP 100X50X2,3 mm ls 1.0000 350,000.00 350,000.00

dan besi siku 30x30x3 mm

Jumlah 12,549,100.00

Dibulatkan 12,549,100.00

21 1 unit Partisi Kaca Folding, Type PK-4 (Fabrikasi)

Panel sliding aluminium uk. 260x80 cm + kaca tb. 8 mm bh 7.0000 3,212,000.00 22,484,000.00

Track runner set 4.0000 495,400.00 1,981,600.00

Bahan & Finishing powder coating super white gloss 160 m1 47.6000 125,000.00 5,950,000.00
Tenaga Aksessoris Slot dan cylinder key, Rell dan roda ls 1.0000 550,000.00 550,000.00

Kontruksi penggantung CNP 100X50X2,3 mm ls 1.0000 300,000.00 300,000.00

dan besi siku 30x30x3 mm

Jumlah 31,265,600.00

Dibulatkan 31,265,600.00

ANALISA HARGA SATUAN


47
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

22 1 unit Partisi Movable Wall Type MW-1 (Fabrikasi)

Panel sliding uk. 104x260 cm bh 6.0000 950,400.00 5,702,400.00

Pintu box 3 daun set 1.0000 7,500,000.00 7,500,000.00


Bahan &
Track runner set 6.0000 495,400.00 2,972,400.00
Tenaga
Sound barrier m1 7.1900 545,300.00 3,920,707.00

Box penyimpanan, aksessoris tambahan ls 1.0000 400,000.00 400,000.00

Jumlah 20,495,507.00

Dibulatkan 20,495,507.00

23 1 unit Partisi Movable Wall Type MW-2 (Fabrikasi)

Panel sliding uk. 102x260 cm bh 6.0000 950,400.00 5,702,400.00

Bahan & Telescopic set 1.0000 755,400.00 755,400.00


Tenaga Track runner set 6.0000 495,400.00 2,972,400.00

Rail staking manuver set 1.0000 225,400.00 225,400.00

Aksessoris konstruksi ls 1.0000 200,000.00 200,000.00

Jumlah 9,855,600.00

Dibulatkan 9,855,600.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENGGANTUNG DAN KUNCI

1 1 set Pasangan engsel pintu

Bahan Engsel pintu stainless 4" dekson set 1.0000 85,000.00 85,000.00

Pekerja oh 0.0150 125,000.00 1,875.00

Tukang kayu oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.0150 160,000.00 2,400.00

Mandor oh 0.0008 175,000.00 131.25

Jumlah 110,406.25

Keuntungan Mak. 10% 11,040.63

Jumlah + Keuntungan 121,446.88

Dibulatkan 121,446.00

2 1 bh Pasangan floor hinges FH 80 SSS

Bahan Floor hinge FH 80 SSS, Dekson bh 1.0000 4,804,500.00 4,804,500.00

Pekerja oh 0.0150 125,000.00 1,875.00

Tukang kayu oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.0150 160,000.00 2,400.00

Mandor oh 0.0008 175,000.00 131.25

Jumlah 4,829,906.25

Keuntungan Mak. 10% 482,990.63

Jumlah + Keuntungan 5,312,896.88

Dibulatkan 5,312,896.00

3 1 bh Pasangan bottom pivot patch PT 10/PSS

Bahan Bottom pivot patch PT 10/PSS, Dekson bh 1.0000 164,000.00 164,000.00

Pekerja oh 0.0150 125,000.00 1,875.00

Tukang kayu oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.0150 160,000.00 2,400.00

Mandor oh 0.0008 175,000.00 131.25

Jumlah 189,406.25

Keuntungan Mak. 10% 18,940.63

Jumlah + Keuntungan 208,346.88

Dibulatkan 208,346.00

4 1 bh Pasangan top pivot patch PT 20

Bahan Top pivot patch PT 20/PSS, Dekson bh 1.0000 105,000.00 105,000.00

Pekerja oh 0.0150 125,000.00 1,875.00

Tukang kayu oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.0150 160,000.00 2,400.00

Mandor oh 0.0008 175,000.00 131.25

ANALISA HARGA SATUAN


48
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

Jumlah 130,406.25

Keuntungan Mak. 10% 13,040.63

Jumlah + Keuntungan 143,446.88

Dibulatkan 143,446.00

5 1 bh Pasangan patch fitting PT 40

Bahan Patch fitting PT 40, Dekson bh 1.0000 125,400.00 125,400.00

Pekerja oh 0.0150 125,000.00 1,875.00

Tukang kayu oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.0150 160,000.00 2,400.00

Mandor oh 0.0008 175,000.00 131.25

Jumlah 150,806.25

Keuntungan Mak. 10% 15,080.63

Jumlah + Keuntungan 165,886.88

Dibulatkan 165,886.00

6 1 bh Pasangan patch lock US 10/PSS + Cylinder PC 91/61 mm

Bahan Patch lock US 10/PSS + Cylinder, Dekson bh 1.0000 255,000.00 255,000.00

Pekerja oh 0.0150 125,000.00 1,875.00

Tukang kayu oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.0150 160,000.00 2,400.00

Mandor oh 0.0008 175,000.00 140.00

Jumlah 280,415.00

Keuntungan Mak. 10% 28,041.50

Jumlah + Keuntungan 308,456.50

Dibulatkan 308,456.00

7 1 set Pasangan pull handle stainless steel, panjang 60 cm

Bahan Pull handle SS-304 38x630x600 mm TPH 981 psg 1.0000 750,000.00 750,000.00

Pekerja oh 0.0500 125,000.00 6,250.00

Tukang kayu oh 0.5000 140,000.00 70,000.00


Tenaga
Kepala tukang oh 0.0500 160,000.00 8,000.00

Mandor oh 0.0025 175,000.00 437.50

Jumlah 834,687.50

Keuntungan Mak. 10% 83,468.75

Jumlah + Keuntungan 918,156.25

Dibulatkan 918,156.00

8 1 set Pasangan pull handle stainless steel tinggi 30 cm

Bahan Pull Handle SS 32x300 mm PH 801 psg 1.0000 330,000.00 330,000.00

Pekerja oh 0.0500 125,000.00 6,250.00

Tukang kayu oh 0.5000 140,000.00 70,000.00


Tenaga
Kepala tukang oh 0.0500 160,000.00 8,000.00

Mandor oh 0.0025 175,000.00 437.50

Jumlah 414,687.50

Keuntungan Mak. 10% 41,468.75

Jumlah + Keuntungan 456,156.25

Dibulatkan 456,156.00

9 1 set Pasangan pull handle stainless steel, panjang 120 cm

Bahan Pull handle SS-304 38x1200 mm PH 802 psg 1.0000 1,455,000.00 1,455,000.00

Pekerja oh 0.0500 125,000.00 6,250.00

Tukang kayu oh 0.5000 140,000.00 70,000.00


Tenaga
Kepala tukang oh 0.0500 160,000.00 8,000.00

Mandor oh 0.0025 175,000.00 437.50

Jumlah 1,539,687.50

Keuntungan Mak. 10% 153,968.75

Jumlah + Keuntungan 1,693,656.25

Dibulatkan 1,693,656.00

ANALISA HARGA SATUAN


49
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

10 1 bh Pasangan door closer

Bahan Door closer Dekkson 40 kg bh 1.0000 277,500.00 277,500.00

Pekerja oh 0.0500 125,000.00 6,250.00

Tukang kayu oh 0.5000 140,000.00 70,000.00


Tenaga
Kepala tukang oh 0.0500 160,000.00 8,000.00

Mandor oh 0.0025 175,000.00 437.50

Jumlah 362,187.50

Keuntungan Mak. 10% 36,218.75

Jumlah + Keuntungan 398,406.25

Dibulatkan 398,406.00

11 1 psg Pasangan lever handle pintu

Bahan Lever handle dekkson LHTR 39 psg 1.0000 267,500.00 267,500.00

Pekerja oh 0.0500 125,000.00 6,250.00

Tukang kayu oh 0.5000 140,000.00 70,000.00


Tenaga
Kepala tukang oh 0.0500 160,000.00 8,000.00

Mandor oh 0.0025 175,000.00 437.50

Jumlah 352,187.50

Keuntungan Mak. 10% 35,218.75

Jumlah + Keuntungan 387,406.25

Dibulatkan 387,406.00

12 1 bh Pasangan escutcheon

Bahan Escutcheon, Dekson set 1.0000 35,000.00 35,000.00

Pekerja oh 0.0150 125,000.00 1,875.00

Tukang kayu oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.0150 160,000.00 2,400.00

Mandor oh 0.0008 175,000.00 140.00

Jumlah 60,415.00

Keuntungan Mak. 10% 6,041.50

Jumlah + Keuntungan 66,456.50

Dibulatkan 66,456.00

13 1 set Pasangan mortise lock

Bahan Mortise lock, Dekson MTS IL 8485 SSS set 1.0000 195,400.00 195,400.00

Pekerja oh 0.0150 125,000.00 1,875.00

Tukang kayu oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.0150 160,000.00 2,400.00

Mandor oh 0.0008 175,000.00 140.00

Jumlah 220,815.00

Keuntungan Mak. 10% 22,081.50

Jumlah + Keuntungan 242,896.50

Dibulatkan 242,896.00

14 1 set Pasangan cylinder DC + kunci

Bahan Cylinder DC DL 60 mm + kunci set 1.0000 125,000.00 125,000.00

Pekerja oh 0.0150 125,000.00 1,875.00

Tukang kayu oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.0150 160,000.00 2,400.00

Mandor oh 0.0008 175,000.00 140.00

Jumlah 150,415.00

Keuntungan Mak. 10% 15,041.50

Jumlah + Keuntungan 165,456.50

Dibulatkan 165,456.00

ANALISA HARGA SATUAN


50
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN DINDING

1 1 m2 Pasangan lantai vinyl uk. 304,8 x 609,6 x 3 mm grey slate (V-1 Type 1)

Lantai vinyl TACO uk. 304,8 x 609,6 x 3 mm grey slate m2 1.2000 172,400.00 206,880.00
Bahan
Lem vinyl kg 0.3500 55,000.00 19,250.00

Pekerja oh 0.1500 125,000.00 18,750.00

Tukang batu oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.0150 160,000.00 2,400.00

Mandor oh 0.0080 175,000.00 1,400.00

Jumlah 269,680.00

Keuntungan Mak. 10% 26,968.00

Jumlah + Keuntungan 296,648.00

Dibulatkan 296,648.00

2 1 m2 Pasangan lantai vinyl uk. 152,4 x 914,4 x 3 mm washed oak (V-2 Type 2)

Lantai vinyl TACO uk. 152,4 x 914,4 x 3 mm washed oak m2 1.2000 185,400.00 222,480.00

Lem vinyl kg 0.3500 55,000.00 19,250.00

Pekerja oh 0.1500 125,000.00 18,750.00

Tukang batu oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.0150 160,000.00 2,400.00

Mandor oh 0.0080 175,000.00 1,400.00

Jumlah 285,280.00

Keuntungan Mak. 10% 28,528.00

Jumlah + Keuntungan 313,808.00

Dibulatkan 313,808.00

3 1 m1 Pasangan plin dinding lengkung (hosplin aluminium 12 cm)

Hosplin AAE (Hospital Plint Aluminium Alloy Extrussion) m1 1.0500 155,000.00 162,750.00

Tinggi lengkung 12 cm, Radius Cekung atas 1,1 cm dan


Bahan
Radius Cekung Bawah 3 cm, Ketebalan 1.9 mm

Peralatan bantu + aksessoris lem ls 0.1000 8,137.50 813.75

Pekerja oh 0.1000 125,000.00 12,500.00

Tukang kayu oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.0150 160,000.00 2,400.00

Mandor oh 0.0150 175,000.00 2,625.00

Jumlah 202,088.75

Keuntungan Mak. 10% 20,208.88

Jumlah + Keuntungan 222,297.63

Dibulatkan 222,297.00

4 1 m2 Pasangan wallpaper

Wallpaper, goodrich (warna/motif di sesuaikan dengan gambar) m2 1.2000 140,500.00 168,600.00


Bahan
Lem kuning kg 0.2500 55,000.00 13,750.00

Pekerja oh 0.3500 125,000.00 43,750.00

Tukang oh 0.1750 140,000.00 24,500.00


Tenaga
Kepala tukang oh 0.0170 160,000.00 2,720.00

Mandor oh 0.0020 175,000.00 350.00

Jumlah 253,670.00

Keuntungan Mak. 10% 25,367.00

Jumlah + Keuntungan 279,037.00

Dibulatkan 279,037.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PLAFOND

1 1 m2 Pasangan rangka plafond besi hollow 40/40 & 20/40 mm galvalum

Hollow galvalum, uk. 40/40 mm, t=0,3 mm m1 1.2000 11,500.00 13,800.00

Bahan Hollow galvalum, uk. 20/40 mm t=0,3 mm m1 1.2000 9,500.00 11,400.00

Alat bantu (10% total bahan) ls 0.0500 25,200.00 1,260.00

ANALISA HARGA SATUAN


51
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

Pekerja oh 0.2000 125,000.00 25,000.00

Tukang kayu oh 0.2100 140,000.00 29,400.00


Tenaga
Kepala tukang oh 0.0320 160,000.00 5,120.00

Mandor oh 0.0320 175,000.00 5,600.00

Jumlah 91,580.00

Keuntungan Mak. 10% 9,158.00

Jumlah + Keuntungan 100,738.00

Dibulatkan 100,738.00

2 1 m2 Pasangan penutup plafond gypsum tbl. 9 mm

Gypsum board tbl. 9 mm lbr 0.3640 74,000.00 26,936.00

Bahan Gypsum tape rol 0.0533 30,000.00 1,600.00

Paku sekrup gypsum kg 0.0100 35,000.00 350.00

Pekerja oh 0.1000 125,000.00 12,500.00

Tukang kayu oh 0.0500 140,000.00 7,000.00


Tenaga
Kepala tukang oh 0.0050 160,000.00 800.00

Mandor oh 0.0050 175,000.00 875.00

Jumlah 50,061.00

Keuntungan Mak. 10% 5,006.10

Jumlah + Keuntungan 55,067.10

Dibulatkan 55,067.00

3 1 m1 Pasangan up/down ceiling plafond

Hollow galvanis, uk. 40/40 mm, t=0,3 mm m1 2.0000 11,500.00 23,000.00

Hollow galvanis, uk. 20/40 mm t=0,3 mm m1 0.8000 9,500.00 7,600.00

Bahan Gypsum board tbl. 9 mm lbr 0.5000 74,000.00 37,000.00

Gypsum tape rol 0.0533 30,000.00 1,600.00

Paku sekrup kg 0.0400 35,000.00 1,400.00

Pekerja oh 0.0300 125,000.00 3,750.00

Tukang kayu oh 0.0700 140,000.00 9,800.00


Tenaga
Kepala tukang oh 0.0070 160,000.00 1,120.00

Mandor oh 0.0040 175,000.00 700.00

Jumlah 85,970.00

Keuntungan Mak. 10% 8,597.00

Jumlah + Keuntungan 94,567.00

Dibulatkan 94,567.00

4 1 m1 Pasangan list plafond shadow line tebal 3 mm

List Shadow line tebal 3 mm m1 1.0500 18,900.00 19,845.00


Bahan
Paku sekrup kg 0.0100 35,000.00 350.00

Pekerja oh 0.0500 125,000.00 6,250.00

Tukang kayu oh 0.0500 140,000.00 7,000.00


Tenaga
Kepala tukang oh 0.0050 160,000.00 800.00

Mandor oh 0.0030 175,000.00 525.00

Jumlah 34,770.00

Keuntungan Mak. 10% 3,477.00

Jumlah + Keuntungan 38,247.00

Dibulatkan 38,247.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENGECATAN

1 1 m2 Pengecatan dinding, partisi dan plafond 1 lapis cat dasar, 2 lapis cat penutup (interior)

Cat dasar kg 0.1250 30,500.00 3,812.50

Cat penutup 2x Jotun, interior kg 0.2600 35,600.00 9,256.00


Bahan
Ampelas lbr 0.2500 6,000.00 1,500.00

Rol cat bh 0.0200 45,000.00 900.00

Pekerja oh 0.0200 125,000.00 2,500.00

Tukang cat oh 0.1260 140,000.00 17,640.00


Tenaga

ANALISA HARGA SATUAN


52
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )
Tenaga
Kepala tukang oh 0.0063 160,000.00 1,008.00

Mandor oh 0.0025 175,000.00 437.50

Jumlah 37,054.00

Keuntungan Mak. 10% 3,705.40

Jumlah + Keuntungan 40,759.40

Dibulatkan 40,759.00

2 1 m2 Pengecatan politur dengan semprot

Politur kg 0.0300 82,000.00 2,460.00

Thiner ltr 0.1000 35,000.00 3,500.00

Bahan Amplas kayu / besi lbr 0.2000 6,000.00 1,200.00

Wood filer kg 0.2000 30,100.00 6,020.00

Alat bantu semprot ls 1.0000 2,500.00 2,500.00

Pekerja oh 0.2500 125,000.00 31,250.00

Tukang cat oh 0.3050 140,000.00 42,700.00


Tenaga
Kepala tukang oh 0.0400 160,000.00 6,400.00

Mandor oh 0.0400 175,000.00 7,000.00

Jumlah 103,030.00

Keuntungan Mak. 10% 10,303.00

Jumlah + Keuntungan 113,333.00

Dibulatkan 113,333.00

3 1 m2 Pengecatan zinchromate baja/besi

Meni Besi kg 0.4000 38,000.00 15,200.00


Bahan
Kwas 3" bh 0.0400 12,000.00 480.00

Pekerja oh 0.0400 125,000.00 5,000.00

Tukang cat oh 0.0400 140,000.00 5,600.00


Tenaga
Kepala tukang oh 0.0400 160,000.00 6,400.00

Mandor oh 0.0200 175,000.00 3,500.00

Jumlah 36,180.00

Keuntungan Mak. 10% 3,618.00

Jumlah + Keuntungan 39,798.00

Dibulatkan 39,798.00

4 1 m2 Pengecatan duco dengan cara semprot

Cat menie besi/kayu kg 0.2000 38,000.00 7,600.00

Dempul duco kg 0.1500 40,500.00 6,075.00


Bahan
Cat besi/kayu kg 0.3500 83,000.00 29,050.00

Alat bantu spray ls 1.0000 3,000.00 3,000.00

Pekerja oh 0.4000 125,000.00 50,000.00

Tukang cat oh 0.5000 140,000.00 70,000.00


Tenaga
Kepala tukang oh 0.2000 160,000.00 32,000.00

Mandor oh 0.2000 175,000.00 35,000.00

Jumlah 232,725.00

Keuntungan Mak. 10% 23,272.50

Jumlah + Keuntungan 255,997.50

Dibulatkan 255,997.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN INTERIOR MELEKAT

1 1 m3 Pasangan rangka kayu solid jati uk. 40x40 mm

Kayu solid wood filler jati uk. 40x40 mm m3 1.0000 9,350,000.00 9,350,000.00
Bahan
Paku 5-7 cm kg 0.5000 22,500.00 11,250.00

Pekerja oh 0.5000 125,000.00 62,500.00

Tukang kayu oh 1.0000 140,000.00 140,000.00


Tenaga
Kepala tukang oh 0.1000 160,000.00 16,000.00

Mandor oh 0.1000 175,000.00 17,500.00

ANALISA HARGA SATUAN


53
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

Jumlah 9,597,250.00

Keuntungan Mak. 10% 959,725.00

Jumlah + Keuntungan 10,556,975.00

Dibulatkan 10,556,975.00

2 1 m2 Pasangan multiplek tebal 9 mm

Multiplek 9 mm lbr 0.3750 98,000.00 36,750.00

Bahan Lem kayu kg 0.0300 55,000.00 1,650.00

Paku 2 - 3 cm kg 0.2800 22,500.00 6,300.00

Pekerja oh 0.0700 125,000.00 8,750.00

Tukang kayu oh 0.1000 140,000.00 14,000.00


Tenaga
Kepala tukang oh 0.0100 160,000.00 1,600.00

Mandor oh 0.0035 175,000.00 612.50

Jumlah 69,662.50

Keuntungan Mak. 10% 6,966.25

Jumlah + Keuntungan 76,628.75

Dibulatkan 76,628.00

3 1 m2 Pasangan multiplek tebal 6 mm

Multiplek 6 mm lbr 0.3750 75,600.00 28,350.00

Bahan Lem kayu kg 0.0300 55,000.00 1,650.00

Paku 2 - 3 cm kg 0.2800 22,500.00 6,300.00

Pekerja oh 0.0700 125,000.00 8,750.00

Tukang kayu oh 0.1000 140,000.00 14,000.00


Tenaga
Kepala tukang oh 0.0100 160,000.00 1,600.00

Mandor oh 0.0035 175,000.00 612.50

Jumlah 61,262.50

Keuntungan Mak. 10% 6,126.25

Jumlah + Keuntungan 67,388.75

Dibulatkan 67,388.00

4 1 m2 Pasangan multiplek tebal 15 mm

Multiplek 15 mm lbr 0.3750 182,000.00 68,250.00

Bahan Lem kayu kg 0.0300 55,000.00 1,650.00

Paku 2 - 3 cm kg 0.2800 22,500.00 6,300.00

Pekerja oh 0.0700 125,000.00 8,750.00

Tukang kayu oh 0.1000 140,000.00 14,000.00


Tenaga
Kepala tukang oh 0.0100 160,000.00 1,600.00

Mandor oh 0.0035 175,000.00 612.50

Jumlah 101,162.50

Keuntungan Mak. 10% 10,116.25

Jumlah + Keuntungan 111,278.75

Dibulatkan 111,278.00

5 1 m2 Pasangan multiplek tebal 20 mm

Multiplek 20 mm lbr 0.3750 289,500.00 108,562.50

Bahan Lem kayu kg 0.0300 55,000.00 1,650.00

Paku 2 - 3 cm kg 0.2800 22,500.00 6,300.00

Pekerja oh 0.0700 125,000.00 8,750.00

Tukang kayu oh 0.1000 140,000.00 14,000.00


Tenaga
Kepala tukang oh 0.0100 160,000.00 1,600.00

Mandor oh 0.0035 175,000.00 612.50

Jumlah 141,475.00

Keuntungan Mak. 10% 14,147.50

Jumlah + Keuntungan 155,622.50

Dibulatkan 155,622.00

ANALISA HARGA SATUAN


54
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

6 1 m2 Pasangan multiplek tebal 12 mm

Multiplek 12 mm lbr 0.3750 155,400.00 58,275.00

Bahan Lem kayu kg 0.0300 55,000.00 1,650.00

Paku 2 - 3 cm kg 0.2800 22,500.00 6,300.00

Pekerja oh 0.0700 125,000.00 8,750.00

Tukang kayu oh 0.1000 140,000.00 14,000.00


Tenaga
Kepala tukang oh 0.0100 160,000.00 1,600.00

Mandor oh 0.0035 175,000.00 612.50

Jumlah 91,187.50

Keuntungan Mak. 10% 9,118.75

Jumlah + Keuntungan 100,306.25

Dibulatkan 100,306.00

7 1 m2 Pasangan multiplek tebal 18 mm

Multiplek 18 mm lbr 0.3750 244,500.00 91,687.50

Bahan Lem kayu kg 0.0300 55,000.00 1,650.00

Paku 2 - 3 cm kg 0.2800 22,500.00 6,300.00

Pekerja oh 0.0700 125,000.00 8,750.00

Tukang kayu oh 0.1000 140,000.00 14,000.00


Tenaga
Kepala tukang oh 0.0100 160,000.00 1,600.00

Mandor oh 0.0035 175,000.00 612.50

Jumlah 124,600.00

Keuntungan Mak. 10% 12,460.00

Jumlah + Keuntungan 137,060.00

Dibulatkan 137,060.00

8 1 m2 Pasangan melaminto tebal 3 mm

Melaminto tebal 3 mm lbr 0.3750 55,300.00 20,737.50


Bahan
Lem kayu kg 0.0300 55,000.00 1,650.00

Pekerja oh 0.0700 125,000.00 8,750.00

Tukang kayu oh 0.1000 140,000.00 14,000.00


Tenaga
Kepala tukang oh 0.0100 160,000.00 1,600.00

Mandor oh 0.0035 175,000.00 612.50

Jumlah 47,350.00

Keuntungan Mak. 10% 4,735.00

Jumlah + Keuntungan 52,085.00

Dibulatkan 52,085.00

9 1 m2 Pasangan solid surface tebal 2 cm, warna hitam

Bahan Solid surface tebal 2 cm, warna hitam m2 1.1000 1,450,000.00 1,595,000.00

Pekerja oh 0.0165 125,000.00 2,062.50

Tukang kayu oh 0.1650 140,000.00 23,100.00


Tenaga
Kepala tukang oh 0.0165 160,000.00 2,640.00

Mandor oh 0.0008 175,000.00 140.00

Jumlah 1,622,942.50

Keuntungan Mak. 10% 162,294.25

Jumlah + Keuntungan 1,785,236.75

Dibulatkan 1,785,236.00

10 1 m1 Pasangan list plat stainless steel hairline tebal 1,5 mm

Plat stainless steel hairline lebar 10 cm, tebal 1,5 mm lbr 0.0370 2,250,000.00 83,142.97
Bahan
Lem aibon kg 0.3000 55,000.00 16,500.00

Pekerja oh 0.1000 125,000.00 12,500.00

Tukang kayu oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.0150 160,000.00 2,400.00

Mandor oh 0.0150 175,000.00 2,625.00

Jumlah 138,167.97

Keuntungan Mak. 10% 13,816.80

Jumlah + Keuntungan 151,984.77

Dibulatkan 151,984.00

ANALISA HARGA SATUAN


55
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

11 1 m2 Pasangan Rangka kayu kamper solid uk. 20x30 mm

kayu kamper solid uk. 20x30 mm m3 0.0024 10,556,975.00 25,336.74


Bahan
Paku 3-5 cm kg 0.1000 22,500.00 2,250.00

Pekerja oh 0.1000 125,000.00 12,500.00

Tukang kayu oh 0.2000 140,000.00 28,000.00


Tenaga
Kepala tukang oh 0.0200 160,000.00 3,200.00

Mandor oh 0.0200 175,000.00 3,500.00

Jumlah 74,786.74

Keuntungan Mak. 10% 7,478.67

Jumlah + Keuntungan 82,265.41

Dibulatkan 82,265.00

12 1 m2 Pasangan finishing HPL

HPL Taco, warna/motif di sesuaikan dengan gambar m2 1.2000 78,500.00 94,200.00


Bahan
Lem kuning kg 0.2500 55,000.00 13,750.00

Pekerja oh 0.1750 125,000.00 21,875.00

Tukang kayu oh 0.3500 140,000.00 49,000.00


Tenaga
Kepala tukang oh 0.0170 160,000.00 2,720.00

Mandor oh 0.0020 175,000.00 350.00

Jumlah 181,895.00

Keuntungan Mak. 10% 18,189.50

Jumlah + Keuntungan 200,084.50

Dibulatkan 200,084.00

13 1 m2 Pasangan rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm

Rangka besi hollow galvanis uk. 40x40 mm, tebal 1,4 mm m1 4.0000 25,600.00 102,400.00
Bahan
Alat bantu/aksesoris ls 0.1000 102,400.00 10,240.00

Pekerja oh 0.2500 125,000.00 31,250.00

Tukang besi oh 0.5000 140,000.00 70,000.00


Tenaga
Kepala tukang oh 0.0500 160,000.00 8,000.00

Mandor oh 0.0050 175,000.00 875.00

Jumlah 222,765.00

Keuntungan Mak. 10% 22,276.50

Jumlah + Keuntungan 245,041.50

Dibulatkan 245,041.00

14 1 m2 Pasangan ornamen MDF 15 mm, cutting laser + HPL

MDF 15 mm m2 1.0000 76,500.00 76,500.00

Bahan HPL taco, motif/warna di sesuaikan dengan gambar m2 1.0000 78,500.00 78,500.00

Cutting laser m2 1.0000 675,600.00 675,600.00

Pekerja oh 0.5000 125,000.00 62,500.00

Tukang kayu oh 1.0000 140,000.00 140,000.00


Tenaga
Kepala tukang oh 0.1000 160,000.00 16,000.00

Mandor oh 0.0100 175,000.00 1,750.00

Jumlah 1,050,850.00

Keuntungan Mak. 10% 105,085.00

Jumlah + Keuntungan 1,155,935.00

Dibulatkan 1,155,935.00

15 1 m2 Pasangan ornamen MDF 20 mm, cutting laser + HPL

MDF 20 mm m2 1.0000 98,500.00 98,500.00

Bahan HPL taco, motif/warna di sesuaikan dengan gambar m2 1.0000 78,500.00 78,500.00

Cutting laser m2 1.0000 675,600.00 675,600.00

Pekerja oh 0.5000 125,000.00 62,500.00

Tukang kayu oh 1.0000 140,000.00 140,000.00


Tenaga
Kepala tukang oh 0.1000 160,000.00 16,000.00

Mandor oh 0.0100 175,000.00 1,750.00

ANALISA HARGA SATUAN


56
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

Jumlah 1,072,850.00

Keuntungan Mak. 10% 107,285.00

Jumlah + Keuntungan 1,180,135.00

Dibulatkan 1,180,135.00

16 1 unit Wall Art Tipe - W1

Rangka metal stud uk. 34x76 mm tbl. 0,40 mm dan m2 6.7600 150,072.00 1,014,486.72

U runner uk. 25x76 mm tbl. 0,35 mm

Gypsum 12 mm m2 7.2800 55,067.00 400,887.76

Backing multiplek 9 mm m2 6.7600 76,628.00 518,005.28

Bahan + Upah Multiplek 15 mm m2 6.7600 111,278.00 752,239.28

Teakwood 3 mm m2 6.7600 52,085.00 352,094.60

Finishing cat interior (area gypsum) m2 7.2800 40,759.00 296,725.52

Finishing cat politur (area multiplek + teakwood) m2 6.7600 113,333.00 766,131.08

Finishing HPL, warna disesuaikan dengan gambar (area nat) m2 3.9379 200,084.00 787,914.79

Jumlah 4,888,485.03

Dibulatkan 4,888,485.00

17 1 unit Wall Art Tipe - W2

Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm m2 6.7600 245,041.00 1,656,477.16

Backing multiplek 9 mm m2 6.9680 76,628.00 533,943.90

Multiplek 15 mm m2 6.7600 111,278.00 752,239.28

Bahan + Upah Teakwood 3 mm m2 6.7600 52,085.00 352,094.60

Finishing cat politur (area multiplek + teakwood) m2 6.7600 113,333.00 766,131.08

Finishing HPL, warna disesuaikan dengan gambar (area nat) m2 3.9379 200,084.00 787,914.79

Ornamen gunungan MDF 15 mm cutting laser + HPL (warna tembaga) m2 2.6000 1,155,935.00 3,005,431.00

Jumlah 7,854,231.81

Dibulatkan 7,854,231.00

18 1 unit Wall Art Tipe - W3

Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm m2 16.0800 245,041.00 3,940,259.28

Multiplek 9 mm m2 12.4728 76,628.00 955,765.72

Bahan + Upah Kaca polos 8 mm m2 2.6400 361,550.00 954,492.00

Finishing HPL, warna/motif disesuaikan dengan gambar m2 12.4728 200,084.00 2,495,607.72

Ornamen gunungan MDF 15 mm cutting laser + HPL (cooper brush) m2 2.6000 1,155,935.00 3,005,431.00

Jumlah 11,351,555.71

Dibulatkan 11,351,555.00

19 1 unit Wall Art Tipe - W4

Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm m2 25.3760 245,041.00 6,218,160.42

Multiplek 6 mm m2 23.2000 67,388.00 1,563,401.60

Bambu ampel 1/2 Ø 10 cm m1 45.0800 5,500.00 247,940.00

Bahan + Upah Bambu ampel 1/2 Ø 5 cm m1 30.3200 3,500.00 106,120.00

Finishing wallpaper, warna/motif disesuaikan dengan gambar m2 19.1360 279,037.00 5,339,652.03

Finishing HPL, warna/motif disesuaikan dengan gambar m2 3.7440 200,084.00 749,114.50

Finishing cat politur m2 6.0240 113,333.00 682,717.99

Jumlah 14,907,106.54

Dibulatkan 14,907,106.00

20 1 unit Wall Art Tipe - W5

Bambu ampel 1/2 Ø 10 cm m1 37.1000 5,500.00 204,050.00

Bambu ampel 1/2 Ø 5 cm m1 21.8200 3,500.00 76,370.00


Bahan + Upah
Finishing wallpaper, warna/motif disesuaikan dengan gambar m2 14.3000 279,037.00 3,990,229.10

Finishing cat politur m2 4.8010 113,333.00 544,111.73

Jumlah 4,814,760.83

Dibulatkan 4,814,760.00

ANALISA HARGA SATUAN


57
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

21 1 unit Wall Art Tipe - W6

Rangka besi hollow 50x100 mm, tebal 1,8 mm m1 16.4400 42,300.00 695,412.00

Rangka dudukan ornamen besi hollow 20x40 mm, tebal 1,4 mm m1 22.5000 22,500.00 506,250.00

Base plate uk. 10x15 cm, tebal 5 mm + pengelasan m2 0.0300 855,600.00 25,668.00

Dynabolt M-8 bh 8.0000 3,500.00 28,000.00


Bahan + Upah
Backing multiplek 6 mm m2 12.7500 67,388.00 859,197.00

Ornamen MDF 20 mm cutting laser + HPL (cooper brush) m2 12.7500 1,180,135.00 15,046,721.25

Finishing HPL, warna/motif disesuaikan dengan gambar m2 12.7500 200,084.00 2,551,071.00

Finishing cat duco, warna tembaga m2 4.9620 255,997.00 1,270,257.11

Jumlah 20,982,576.36

Dibulatkan 20,982,576.00

22 1 unit Wall Art Tipe - W7

Rangka box besi hollow 20x40 mm, tebal 1,4 mm m2 11.6840 198,750.00 2,322,195.00

Multiplek 6 mm m2 7.6200 67,388.00 513,496.56

Bahan + Upah Finishing HPL, warna/motif disesuaikan dengan gambar m2 7.6200 200,084.00 1,524,640.08

Batu koral putih krg 26.2467 45,000.00 1,181,100.00

Ornamen MDF 20 mm cutting laser + HPL (cooper brush) m2 16.5100 1,180,135.00 19,484,028.85

Jumlah 25,025,460.49

Dibulatkan 25,025,460.00

23 1 unit Wall Art Tipe - W8

Rangka box besi hollow 20x40 mm, tebal 1,4 mm m2 8.4709 198,750.00 1,683,591.38

Multiplek 6 mm m2 6.0135 67,388.00 405,234.37

Bahan + Upah Finishing HPL, warna/motif disesuaikan dengan gambar m2 6.0135 200,084.00 1,203,195.13

Batu koral putih krg 15.5363 45,000.00 699,135.00

Ornamen MDF 20 mm cutting laser + HPL (cooper brush) m2 16.5100 1,180,135.00 19,484,028.85

Jumlah 23,475,184.72

Dibulatkan 23,475,184.00

24 1 unit Ornamen Kolom Tipe - CK1

Kayu solid jati uk. 40x40 mm m3 0.0832 10,556,975.00 878,340.32

Bahan + Upah Finishing HPL, warna/motif disesuaikan dengan gambar m2 8.3200 200,084.00 1,664,698.88

Finishing wallpaper, warna/motif disesuaikan dengan gambar m2 6.6560 279,037.00 1,857,270.27

Jumlah 4,400,309.47

Dibulatkan 4,400,309.00

25 1 unit Backdrop Tipe - B1

Rangka metal stud uk. 34x76 mm tbl. 0,40 mm dan m2 4.5240 150,072.00 678,925.73

U runner uk. 25x76 mm tbl. 0,35 mm

Gypsum 12 mm m2 4.7840 73,791.00 353,016.14

Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm m2 14.8460 245,041.00 3,637,878.69

Multiplek 9 mm m2 7.4360 76,628.00 569,805.81

Sirip kayu solid 40x40 mm, wood filler jati m3 0.0328 10,556,975.00 346,268.78

Rangka pigura kayu solid 25x50 mm, wood filler jati m3 0.0140 10,556,975.00 147,797.65
Bahan + Upah
Frame pigura kayu solid 20x30 mm, wood filler jati m3 0.0084 10,556,975.00 88,678.59

Finishing cat interior (area gypsum) m2 4.7840 40,759.00 194,991.06

Finishing HPL, warna/motif disesuaikan dengan gambar m2 7.4360 200,084.00 1,487,824.62

Finishing cat politur m2 5.5400 113,333.00 627,864.82

Name sign stainless steel * DIREKTORAT KEPERCAYAAN TERHADAP TUHAN YME cm 378.0000 15,400.00 5,821,200.00

DAN MASYARAKAT ADAT *, tinggi huruf 7 cm

Logo timbul stainless steel lapis stiker, uk. 50x51 cm tebal 4 cm unit 1.0000 4,750,000.00 4,750,000.00

Jumlah 18,704,251.89

Dibulatkan 18,704,251.00

26 1 unit Backdrop Tipe - B2

Rangka metal stud uk. 34x76 mm tbl. 0,40 mm dan m2 14.8980 150,072.00 2,235,772.66

U runner uk. 25x76 mm tbl. 0,35 mm

Bahan + Upah

ANALISA HARGA SATUAN


58
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

Bahan + Upah Gypsum 12 mm (sisi dalam) m2 10.1920 73,791.00 752,077.87

Multiplek 9 mm (sisi luar) m2 15.0480 76,628.00 1,153,098.14

Finishing HPL, warna/motif disesuaikan dengan gambar (sisi luar) m2 15.0480 200,084.00 3,010,864.03

Jumlah 7,151,812.70

Dibulatkan 7,151,812.00

27 1 unit Backdrop Tipe - B3

Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm m2 11.9600 245,041.00 2,930,690.36

Bahan + Upah Multiplek 9 mm m2 7.3320 76,628.00 561,836.50

Finishing HPL, warna/motif disesuaikan dengan gambar m2 7.3320 200,084.00 1,467,015.89

Jumlah 4,959,542.74

Dibulatkan 4,959,542.00

28 1 unit Backdrop Tipe - B4

Multiplek 12 mm m2 6.4480 100,306.00 646,773.09


Bahan + Upah
Finishing HPL, warna/motif disesuaikan dengan gambar m2 6.4480 200,084.00 1,290,141.63

Jumlah 1,936,914.72

Dibulatkan 1,936,914.00

29 1 unit Backdrop Tipe - B5

Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm m2 16.6000 245,041.00 4,067,680.60

Base plate uk. 10x10 cm, tebal 5 mm + pengelasan m2 0.0400 855,600.00 34,224.00

Dynabolt M-8 bh 16.0000 3,500.00 56,000.00


Bahan + Upah
Multiplek 9 mm m2 17.2120 76,628.00 1,318,921.14

Finishing HPL, warna/motif disesuaikan dengan gambar m2 17.2120 200,084.00 3,443,845.81

Finishing cat duco, warna hitam m2 0.5968 255,997.00 152,779.01

Jumlah 9,073,450.55

Dibulatkan 9,073,450.00

30 1 unit Meja Resepsionis

Rangka kayu solid uk. 20x30 mm m2 10.8550 82,265.00 892,986.58

Multiplek 15 mm m2 12.7575 111,278.00 1,419,629.09

Melaminto 3 mm (area lemari & laci sisi dalam) m2 2.6285 52,085.00 136,905.42

Ornamen MDF 15 mm cutting laser + HPL (chrome) m2 1.6000 1,155,935.00 1,849,496.00

Bahan + Upah Finishing HPL, warna/motif disesuaikan dengan gambar m2 8.9250 200,084.00 1,785,749.70

Rell laci panjang 40 cm bh 2.0000 77,500.00 155,000.00

Engsel sendok lemari bh 2.0000 23,500.00 47,000.00

Handle lemari + laci bh 2.0000 46,500.00 93,000.00

Plat stainless steel hairline tebal 1,5 mm m1 1.3500 151,984.00 205,178.40

Jumlah 6,584,945.18

Dibulatkan 6,584,945.00

31 1 unit Wall Covering Tipe - WC1

Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm m2 19.2350 245,041.00 4,713,363.64

Multiplek 6 mm m2 19.2350 67,388.00 1,296,208.18

Bahan + Upah Multiplek 15 mm m2 19.2350 111,278.00 2,140,432.33

Finishing HPL, warna/tekstur disesuaikan dengan gambar m2 19.2350 200,084.00 3,848,615.74

Finishing cat duco warna hitam pada nat m2 2.2752 255,997.00 582,444.37

Jumlah 12,581,064.26

Dibulatkan 12,581,064.00

32 1 unit Covering Kolom Tipe - CK2

Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm m2 10.9200 245,041.00 2,675,847.72

Bahan + Upah Multiplek 9 mm m2 12.1400 76,628.00 930,263.92

Finishing HPL, warna/tekstur disesuaikan dengan gambar m2 12.1400 200,084.00 2,429,019.76

Jumlah 6,035,131.40

Dibulatkan 6,035,131.00

ANALISA HARGA SATUAN


59
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

33 1 unit Covering Kolom Tipe - CK3

Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm m2 7.6700 245,041.00 1,879,464.47

Bahan + Upah Multiplek 9 mm m2 8.4650 76,628.00 648,656.02

Finishing HPL, warna/tekstur disesuaikan dengan gambar m2 8.4650 200,084.00 1,693,711.06

Jumlah 4,221,831.55

Dibulatkan 4,221,831.00

34 1 unit Covering Kolom Tipe - CK4

Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm m2 4.9400 245,041.00 1,210,502.54

Bahan + Upah Multiplek 9 mm m2 5.4300 76,628.00 416,090.04

Finishing HPL, warna/tekstur disesuaikan dengan gambar m2 5.4300 200,084.00 1,086,456.12

Jumlah 2,713,048.70

Dibulatkan 2,713,048.00

35 1 unit Covering Kolom Tipe - CK5

Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm m2 10.4000 245,041.00 2,548,426.40

Bahan + Upah Multiplek 9 mm m2 11.5000 76,628.00 881,222.00

Finishing HPL, warna/tekstur disesuaikan dengan gambar m2 11.5000 200,084.00 2,300,966.00

Jumlah 5,730,614.40

Dibulatkan 5,730,614.00

36 1 unit Covering Kolom Tipe - CK6

Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm m2 6.6950 245,041.00 1,640,549.50

Bahan + Upah Multiplek 9 mm m2 7.4525 76,628.00 571,070.17

Finishing HPL, warna/tekstur disesuaikan dengan gambar m2 7.4525 200,084.00 1,491,126.01

Jumlah 3,702,745.68

Dibulatkan 3,702,745.00

37 1 unit Wall Art Tipe - W9

Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm m2 12.4800 245,041.00 3,058,111.68

Multiplek 6 mm m2 13.1040 67,388.00 883,052.35


Bahan + Upah
Multiplek 20 mm m2 6.2400 155,622.00 971,081.28

Finishing HPL, warna/tekstur disesuaikan dengan gambar m2 19.3440 200,084.00 3,870,424.90

Jumlah 8,782,670.21

Dibulatkan 8,782,670.00

38 1 unit Snack & Baverage

Rangka hollow galvanis uk. 40x40 mm, tebal 1,4 mm m2 23.6910 245,041.00 5,805,266.33

Multiplek 18 mm m2 31.8050 137,060.00 4,359,193.30

Melaminto 3 mm (area sisi dalam almari) m2 6.7470 52,085.00 351,417.50

Finishing HPL, warna disesuaikan dengan gambar m2 28.6445 200,084.00 5,731,306.14

Top table solid surface tebal 2 cm, Black m2 1.0140 1,785,236.00 1,810,229.30

Bahan + Upah Kaca polos tebal 6 mm m2 0.0600 227,966.00 13,677.96

Glass stone tebal 8 mm, warna putih susu m2 1.9200 987,500.00 1,896,000.00

List plat stainless steel hairline tebal 1,5 mm m1 2.4500 151,984.00 372,360.80

Engsel sendok bh 10.0000 23,500.00 235,000.00

Magnet Door Stoper Stainless Steel bh 5.0000 145,000.00 725,000.00

Lampu hidend lamp T5 8 watt P=60 cm,lengkap dengan instalasi unit 2.0000 265,400.00 530,800.00

Jumlah 21,830,251.33

Dibulatkan 21,830,251.00

ANALISA HARGA SATUAN


60
ANALISA HARGA SATUAN

KEGIATAN : REDESAIN TATA LETAK RUANG KERJA KANTOR DIREKTORAT JENDERAL

KEBUDAYAAN GEDUNG E LANTAI 9 DAN 10 JAKARTA

LOKASI : JL. JENDERAL SUDIRMAN SENAYAN, KOTAK POS 4104 JAKARTA 10270

TAHUN ANGGARAN : 2020

HARGA SATUAN JUMLAH HARGA


NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN ELEKTRIKAL

1 1 unit Penyesuaian dan pembongkaran panel eksisting

Bongkar panel ls 1.0000 300,000.00 300,000.00

Bahan Perapihan ls 1.0000 200,000.00 200,000.00

Biaya Pemasangan/Konekting ls 1.0000 500,000.00 500,000.00

Pekerja oh 1.0000 125,000.00 125,000.00

Tukang listrik oh 1.0000 140,000.00 140,000.00


Tenaga
Kepala tukang oh 0.5000 160,000.00 80,000.00

Mandor oh 0.5000 175,000.00 87,500.00

Jumlah 1,432,500.00

Keuntungan Mak. 10% 143,250.00

Jumlah + Keuntungan 1,575,750.00

Dibulatkan 1,575,750.00

2 1 unit Panel penerangan dan daya ( P.LP/PP-9 ) Lantai 9, Penyesuaian

Pilot Lamp + Fuse (R/S/T) TELE (3 set) set 3.0000 15,400.00 46,200.00

Amper Meter 0 ~ 100 A (3 bh) bh 3.0000 128,000.00 384,000.00

Volt Meter 0 ~ 500 V (1 bh) bh 1.0000 87,500.00 87,500.00

Volt Selector Switch/VSS (1 bh) bh 1.0000 95,000.00 95,000.00

Trafo Arus CT 100/5A, GAE (3 bh) bh 3.0000 321,000.00 963,000.00

MCCB 3P 100~250A 36KA/NSX-250F, Schneider (1 bh) bh 1.0000 1,850,000.00 1,850,000.00

MCCB 3P 50~100A 25KA/NSX-100F, Schneider (2 bh) bh 2.0000 775,000.00 1,550,000.00

Bahan Magnetik Kontaktror (MC) 80 A, Schneider (2 bh) bh 2.0000 1,655,400.00 3,310,800.00

MCB 1P 10 A 5KA, Schneider (18 bh) bh 18.0000 86,500.00 1,557,000.00

MCB 1P 16 A 7.5KA, Schneider (24 bh) bh 24.0000 105,000.00 2,520,000.00

CU Busbar set 1.0000 110,000.00 110,000.00

Wiring dan Accessories ( 10% Bahan ) ls 1.0000 1,247,350.00 1,247,350.00

Grounding sistem ls 1.0000 1,500,000.00 1,500,000.00

Box Panel 140 x 120 x 40 cm, Free standing bh 1.0000 3,550,000.00 3,550,000.00

Biaya Pemasangan set 1.0000 600,000.00 600,000.00

Pekerja oh 1.0000 125,000.00 125,000.00

Tukang listrik oh 1.0000 140,000.00 140,000.00


Tenaga
Kepala tukang oh -

Mandor oh -

Jumlah 19,635,850.00

Keuntungan Mak. 10% 1,963,585.00

Jumlah + Keuntungan 21,599,435.00

Dibulatkan 21,599,435.00

3 1 unit Panel penerangan dan daya ( P.LP/PP-10 ) Lantai 10, Penyesuaian

Pilot Lamp + Fuse (R/S/T) TELE (3 set) set 3.0000 15,400.00 46,200.00

Amper Meter 0 ~ 100 A (3 bh) bh 3.0000 128,000.00 384,000.00

Volt Meter 0 ~ 500 V (1 bh) bh 1.0000 87,500.00 87,500.00

Volt Selector Switch/VSS (1 bh) bh 1.0000 95,000.00 95,000.00

Trafo Arus CT 100/5A, GAE (3 bh) bh 3.0000 321,000.00 963,000.00

MCCB 3P 100~250A 36KA/NSX-250F, Schneider (1 bh) bh 1.0000 1,850,000.00 1,850,000.00

MCCB 3P 50~100A 25KA/NSX-100F, Schneider (2 bh) bh 2.0000 775,000.00 1,550,000.00

Bahan Magnetik Kontaktror (MC) 80 A, Schneider (2 bh) bh 2.0000 1,655,400.00 3,310,800.00

MCB 1P 10 A 5KA, Schneider (18 bh) bh 18.0000 86,500.00 1,557,000.00

MCB 1P 16 A 7.5KA, Schneider (24 bh) bh 24.0000 105,000.00 2,520,000.00


ANALISA HARGA SATUAN
61
Bahan

HARGA SATUAN JUMLAH HARGA


NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

CU Busbar set 1.0000 110,000.00 110,000.00

Wiring dan Accessories ( 10% Bahan ) ls 1.0000 1,247,350.00 1,247,350.00

Grounding sistem ls 1.0000 1,500,000.00 1,500,000.00

Box Panel 140 x 120 x 40 cm, Free standing bh 1.0000 3,550,000.00 3,550,000.00

Biaya Pemasangan set 1.0000 600,000.00 600,000.00

Pekerja oh 1.0000 125,000.00 125,000.00

Tukang listrik oh 1.0000 140,000.00 140,000.00


Tenaga
Kepala tukang oh -

Mandor oh -

Jumlah 19,635,850.00

Keuntungan Mak. 10% 1,963,585.00

Jumlah + Keuntungan 21,599,435.00

Dibulatkan 21,599,435.00

4 1 m1 Pasangan kabel daya NYY 4 x 70 mm2

Kabel NYY 4 x 70 mm2 m1 1.0000 405,000.00 405,000.00

Bahan Kabel Grounding BC 25 mm m1 1.0000 26,500.00 26,500.00

Perlengkapan dan peralatan bantu (15% Dari Bahan) ls 1.0000 64,725.00 64,725.00

Pekerja oh 0.3000 125,000.00 37,500.00

Tukang listrik oh 0.2000 140,000.00 28,000.00


Tenaga
Kepala tukang oh 0.0500 160,000.00 8,000.00

Mandor oh 0.0200 175,000.00 3,500.00

Jumlah 573,225.00

Keuntungan Mak. 10% 57,322.50

Jumlah + Keuntungan 630,547.50

Dibulatkan 630,547.00

5 1 titik Instalasi titik nyala lampu dengan kabel NYM 3 x 2,5 mm2

Kabel NYM 3 x 2,5 mm m1 10.0000 12,300.00 123,000.00

Pipa Conduit PVC 20 mm m1 8.0000 3,600.00 28,800.00

Saddle/Klem bh 6.0000 3,000.00 18,000.00


Bahan
Fresher dan Scrup bh 12.0000 600.00 7,200.00

Flexible Conduit PVC 20 mm m1 1.0000 13,000.00 13,000.00

Tee Dos bh 1.0000 4,500.00 4,500.00

Pekerja oh 0.2500 125,000.00 31,250.00

Tukang listrik oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.0200 160,000.00 3,200.00

Mandor oh 0.0100 175,000.00 1,750.00

Jumlah 251,700.00

Keuntungan Mak. 10% 25,170.00

Jumlah + Keuntungan 276,870.00

Dibulatkan 276,870.00

6 1 titik Instalasi stop kontak daya dengan kabel NYM 3 x 2,5 mm2

Kabel NYM 3 x 2,5 mm m1 12.0000 12,300.00 147,600.00

Pipa Conduit PVC 20 mm m1 10.0000 3,600.00 36,000.00

Saddle/Klem bh 8.0000 3,000.00 24,000.00


Bahan
Fresher dan Scrup bh 16.0000 600.00 9,600.00

Flexible Conduit PVC 20 mm m1 1.0000 13,000.00 13,000.00

Tee Dos bh 1.0000 4,500.00 4,500.00

Pekerja oh 0.2500 125,000.00 31,250.00

Tukang listrik oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.0200 160,000.00 3,200.00

Mandor oh 0.0100 175,000.00 1,750.00

Jumlah 291,900.00

Keuntungan Mak. 10% 29,190.00

Jumlah + Keuntungan 321,090.00

Dibulatkan 321,090.00

ANALISA HARGA SATUAN


62
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

7 1 bh Pasangan lampu downlight dia 6" cover kaca, LED 13 W Philips

Lampu downlight dia. 6" cover kaca, LED 13 W Philips bh 1.0000 105,000.00 105,000.00
Bahan
Perlengkapan dan peralatan bantu (10% Dari Bahan) lot 1.0000 10,500.00 10,500.00

Pekerja oh 0.1000 125,000.00 12,500.00

Tukang listrik oh 0.1000 140,000.00 14,000.00


Tenaga
Kepala tukang oh 0.1000 160,000.00 16,000.00

Mandor oh 0.1000 175,000.00 17,500.00

Jumlah 175,500.00

Keuntungan Mak. 10% 17,550.00

Jumlah + Keuntungan 193,050.00

Dibulatkan 193,050.00

8 1 bh Pasangan lampu downlight dia 6" cover kaca, LED 10 W Philips

Lampu downlight dia. 6" cover kaca, LED 10 W Philips bh 1.0000 98,500.00 98,500.00
Bahan
Perlengkapan dan peralatan bantu (10% Dari Bahan) lot 1.0000 9,850.00 9,850.00

Pekerja oh 0.1000 125,000.00 12,500.00

Tukang listrik oh 0.1000 140,000.00 14,000.00


Tenaga
Kepala tukang oh 0.1000 160,000.00 16,000.00

Mandor oh 0.1000 175,000.00 17,500.00

Jumlah 168,350.00

Keuntungan Mak. 10% 16,835.00

Jumlah + Keuntungan 185,185.00

Dibulatkan 185,185.00

9 1 bh Pasangan stop kontak

Stop Kontak Broco bh 1.0000 40,500.00 40,500.00


Bahan
Alat Bantu ( 10% Harga Bahan) lot 1.0000 4,050.00 4,050.00

Pekerja oh 0.0500 125,000.00 6,250.00

Tukang listrik oh 0.0500 140,000.00 7,000.00


Tenaga
Kepala tukang oh 0.0100 160,000.00 1,600.00

Mandor oh 0.0100 175,000.00 1,750.00

Jumlah 61,150.00

Keuntungan Mak. 10% 6,115.00

Jumlah + Keuntungan 67,265.00

Dibulatkan 67,265.00

10 1 bh Pasangan saklar tunggal

Saklar Tunggal Schneider bh 1.0000 45,000.00 45,000.00


Bahan
Alat Bantu ( 10% Harga Bahan) lot 1.0000 4,500.00 4,500.00

Pekerja oh 0.0500 125,000.00 6,250.00

Tukang listrik oh 0.0500 140,000.00 7,000.00


Tenaga
Kepala tukang oh 0.0100 160,000.00 1,600.00

Mandor oh 0.0100 175,000.00 1,750.00

Jumlah 66,100.00

Keuntungan Mak. 10% 6,610.00

Jumlah + Keuntungan 72,710.00

Dibulatkan 72,710.00

11 1 bh Pasangan saklar ganda

Saklar Ganda Schneider bh 1.0000 52,000.00 52,000.00


Bahan
Alat Bantu ( 10% Harga Bahan) lot 1.0000 5,200.00 5,200.00

Pekerja oh 0.0500 125,000.00 6,250.00

Tukang listrik oh 0.0500 140,000.00 7,000.00


Tenaga
Kepala tukang oh 0.0100 160,000.00 1,600.00

Mandor oh 0.0100 175,000.00 1,750.00

Jumlah 73,800.00

Keuntungan Mak. 10% 7,380.00

Jumlah + Keuntungan 81,180.00

Dibulatkan 81,180.00

ANALISA HARGA SATUAN


63
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

12 1 m1 Pasangan tray kabel uk. 400 x 100 x 3000 mm

Tray Kabel uk. 400 x 100 x 3000 x 1,2 mm ( Galvanized ) bh 1.0000 145,600.00 145,600.00
Bahan
Alat Bantu + Asessories ( 20% Harga Bahan ) lot 1.0000 29,120.00 29,120.00

Pekerja oh 0.2000 125,000.00 25,000.00

Tukang listrik oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.1200 160,000.00 19,200.00

Mandor oh 0.1000 175,000.00 17,500.00

Jumlah 257,420.00

Keuntungan Mak. 10% 25,742.00

Jumlah + Keuntungan 283,162.00

Dibulatkan 283,162.00

13 1 m1 Pasangan tray kabel uk. 300 x 100 x 3000 mm

Tray Kabel uk. 300 x 100 x 3000 x 1,2 mm ( Galvanized ) bh 1.0000 125,400.00 125,400.00
Bahan
Alat Bantu + Asessories ( 20% Harga Bahan ) lot 1.0000 25,080.00 25,080.00

Pekerja oh 0.2000 125,000.00 25,000.00

Tukang listrik oh 0.1500 140,000.00 21,000.00


Tenaga
Kepala tukang oh 0.1200 160,000.00 19,200.00

Mandor oh 0.1000 175,000.00 17,500.00

Jumlah 233,180.00

Keuntungan Mak. 10% 23,318.00

Jumlah + Keuntungan 256,498.00

Dibulatkan 256,498.00

14 1 titik Instalasi telepon

Kabel ITC 1 x ( 2 x 0,6 mm2 ) m1 20.0000 5,500.00 110,000.00


Bahan
Perlengkapan ( 20% harga kabel ) lot 1.0000 22,000.00 22,000.00

Pekerja oh 0.0200 125,000.00 2,500.00

Tukang listrik oh 0.1350 140,000.00 18,900.00


Tenaga
Kepala tukang oh 0.0135 160,000.00 2,160.00

Mandor oh 0.0050 175,000.00 875.00

Jumlah 156,435.00

Keuntungan Mak. 10% 15,643.50

Jumlah + Keuntungan 172,078.50

Dibulatkan 172,078.00

15 1 titik Instalasi LAN

Kabel STP cat 6E m1 20.0000 7,500.00 150,000.00


Bahan
Perlengkapan ( 25% harga kabel ) lot 1.0000 37,500.00 37,500.00

Pekerja oh 0.0200 125,000.00 2,500.00

Tukang listrik oh 0.1350 140,000.00 18,900.00


Tenaga
Kepala tukang oh 0.0135 160,000.00 2,160.00

Mandor oh 0.0050 175,000.00 875.00

Jumlah 211,935.00

Keuntungan Mak. 10% 21,193.50

Jumlah + Keuntungan 233,128.50

Dibulatkan 233,128.00

16 1 titik Instalasi sound sistem dengan kabel NYMHY 3 x 1,5 mm2

Kabel NYMHY 3 x 1,5 mm m1 15.0000 11,250.00 168,750.00


Bahan
Perlengkapan ( 20% harga kabel ) lot 1.0000 33,750.00 33,750.00

Pekerja oh 0.0200 125,000.00 2,500.00

Tukang listrik oh 0.1350 140,000.00 18,900.00


Tenaga
Kepala tukang oh 0.0135 160,000.00 2,160.00

Mandor oh 0.0050 175,000.00 875.00

Jumlah 226,935.00

Keuntungan Mak. 10% 22,693.50

Jumlah + Keuntungan 249,628.50

Dibulatkan 249,628.00

ANALISA HARGA SATUAN


64
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

17 1 titik Instalasi MATV

Kabel Coax RG6 m1 15.0000 5,100.00 76,500.00


Bahan
Perlengkapan ( 20% harga kabel ) lot 1.0000 15,300.00 15,300.00

Pekerja oh 0.0200 125,000.00 2,500.00

Tukang listrik oh 0.1350 140,000.00 18,900.00


Tenaga
Kepala tukang oh 0.0135 160,000.00 2,160.00

Mandor oh 0.0050 175,000.00 875.00

Jumlah 116,235.00

Keuntungan Mak. 10% 11,623.50

Jumlah + Keuntungan 127,858.50

Dibulatkan 127,858.00

18 1 titik Reposisi instalasi MATV

Kabel Coax RG6 m1 7.0000 5,100.00 35,700.00


Bahan
Perlengkapan ( 20% harga kabel ) lot 1.0000 7,140.00 7,140.00

Pekerja oh 0.0200 125,000.00 2,500.00

Tukang listrik oh 0.1350 140,000.00 18,900.00


Tenaga
Kepala tukang oh 0.0135 160,000.00 2,160.00

Mandor oh 0.0050 175,000.00 875.00

Jumlah 67,275.00

Keuntungan Mak. 10% 6,727.50

Jumlah + Keuntungan 74,002.50

Dibulatkan 74,002.00

19 1 titik Reposisi instalasi CCTV

Kabel Coax RG59 + Power m1 7.0000 7,200.00 50,400.00


Bahan
Perlengkapan ( 20% harga kabel ) lot 1.0000 10,080.00 10,080.00

Pekerja oh 0.0200 125,000.00 2,500.00

Tukang listrik oh 0.1350 140,000.00 18,900.00


Tenaga
Kepala tukang oh 0.0135 160,000.00 2,160.00

Mandor oh 0.0050 175,000.00 875.00

Jumlah 84,915.00

Keuntungan Mak. 10% 8,491.50

Jumlah + Keuntungan 93,406.50

Dibulatkan 93,406.00

PENETAPAN INDEKS HARGA SATUAN PEKERJAAN AC DUCTING

1 1 bh Pasangan head sprinkler

Head sprinkler bh 1.0000 58,600.00 58,600.00


Bahan
Perlengkapan & Penyambungan ( 35 % dari harga bahan ) lot 1.0000 20,510.00 20,510.00

Pekerja oh 0.1080 125,000.00 13,500.00

Tukang pipa oh 0.1800 140,000.00 25,200.00


Tenaga
Kepala tukang oh 0.0180 160,000.00 2,880.00

Mandor oh 0.0054 175,000.00 945.00

Jumlah 121,635.00

Keuntungan Mak. 10% 12,163.50

Jumlah + Keuntungan 133,798.50

Dibulatkan 133,798.00

2 1 titik Perbaikan ducting, pasangan flexible round duct 8"

Flexible round duct 8" bh 1.0000 365,000.00 365,000.00


Bahan
Perlengkapan & Penyambungan ( 35 % dari harga bahan ) lot 1.0000 127,750.00 127,750.00

Pekerja oh 0.1080 125,000.00 13,500.00

Tukang pipa oh 0.1800 140,000.00 25,200.00


Tenaga
Kepala tukang oh 0.0180 160,000.00 2,880.00

Mandor oh 0.0054 175,000.00 945.00

Jumlah 535,275.00

Keuntungan Mak. 10% 53,527.50

Jumlah + Keuntungan 588,802.50

Dibulatkan 588,802.00

ANALISA HARGA SATUAN


65
HARGA SATUAN JUMLAH HARGA
NO JENIS PEKERJAAN BANGUNAN SAT INDEKS
( Rp ) ( Rp )

3 1 bh Perbaikan & pasangan supply air diffuser

Diffuser bh 1.0000 255,000.00 255,000.00


Bahan
Perlengkapan & Penyambungan ( 15 % dari harga bahan ) lot 1.0000 38,250.00 38,250.00

Pekerja oh 0.1080 125,000.00 13,500.00

Tukang pipa oh 0.1800 140,000.00 25,200.00


Tenaga
Kepala tukang oh 0.0180 160,000.00 2,880.00

Mandor oh 0.0054 175,000.00 945.00

Jumlah 335,775.00

Keuntungan Mak. 10% 33,577.50

Jumlah + Keuntungan 369,352.50

Dibulatkan 369,352.00

4 1 bh Perbaikan & pasangan Return Air Grill (RAG)

Return Air Grill (RAG) bh 1.0000 285,000.00 285,000.00


Bahan
Perlengkapan & Penyambungan ( 15 % dari harga bahan ) lot 1.0000 42,750.00 42,750.00

Pekerja oh 0.1080 125,000.00 13,500.00

Tukang pipa oh 0.1800 140,000.00 25,200.00


Tenaga
Kepala tukang oh 0.0180 160,000.00 2,880.00

Mandor oh 0.0054 175,000.00 945.00

Jumlah 370,275.00

Keuntungan Mak. 10% 37,027.50

Jumlah + Keuntungan 407,302.50

Dibulatkan 407,302.00

5 1 bh Pasangan linear diffuser 1200x200 mm

Linear diffuser 1200x200 mm bh 1.0000 376,500.00 376,500.00


Bahan
Perlengkapan & Penyambungan ( 15 % dari harga bahan ) lot 1.0000 56,475.00 56,475.00

Pekerja oh 0.1080 125,000.00 13,500.00

Tukang pipa oh 0.1800 140,000.00 25,200.00


Tenaga
Kepala tukang oh 0.0180 160,000.00 2,880.00

Mandor oh 0.0054 175,000.00 945.00

Jumlah 475,500.00

Keuntungan Mak. 10% 47,550.00

Jumlah + Keuntungan 523,050.00

Dibulatkan 523,050.00

6 1 bh Pasangan exhaust air grill (EAG)

Exhaust Air Grill (EAG) bh 1.0000 245,300.00 245,300.00


Bahan
Perlengkapan & Penyambungan ( 15 % dari harga bahan ) lot 1.0000 36,795.00 36,795.00

Pekerja oh 0.1080 125,000.00 13,500.00

Tukang pipa oh 0.1800 140,000.00 25,200.00


Tenaga
Kepala tukang oh 0.0180 160,000.00 2,880.00

Mandor oh 0.0054 175,000.00 945.00

Jumlah 324,620.00

Keuntungan Mak. 10% 32,462.00

Jumlah + Keuntungan 357,082.00

Dibulatkan 357,082.00

ANALISA HARGA SATUAN


66
HARGA SATUAN BAHAN

NO NAMA BARANG SAT HARGA


1 Pasir Pasang m3 Rp 230,000.00
2 Bata Merah bh Rp 650.00
3 Dolken kayu Ø 8-10 cm/400 cm btg Rp 18,000.00
4 Kayu m3 Rp 2,050,000.00
5 Paku biasa kg Rp 22,500.00
6 Paku tripek kg Rp 34,500.00
7 Semen Portland kg Rp 1,200.00
8 Pasir beton m3 Rp 232,400.00
9 Koral beton m3 Rp 236,500.00
10 Batu Koral Putih krg Rp 45,000.00
11 Seng gelombang lbr Rp 49,000.00
12 Jendela nako bh Rp 110,500.00
13 Triplek 4mm lbr Rp 53,000.00
14 Gypsum Board 9 mm lbr Rp 74,000.00
15 Gypsum Board 12 mm lbr Rp 144,700.00
16 Rockwool, density 60 kg/m3 m2 Rp 49,700.00
17 Kayu Klas III m3 Rp 2,455,000.00
18 Kayu Kamper m3 Rp 3,897,500.00
19 Kayu solid wood filler jati uk. 40x40 mm m3 Rp 9,350,000.00
20 Bambu ampel 1/2 Ø 10 cm m1 Rp 5,500.00
21 Bambu ampel 1/2 Ø 5 cm m1 Rp 3,500.00
22 Besi polos kg Rp 10,500.00
23 Besi plat strip kg Rp 11,500.00
24 Pipa Besi 2" btg Rp 490,000.00
25 Paku Ramset bh Rp 1,200.00
26 Skrup Gypsum kg Rp 34,000.00
27 Textile Gypsum roll Rp 30,000.00
28 Compound Gypsum zak Rp 85,000.00
29 Compound Gypsum kg Rp 4,250.00
30 Shadowline btg Rp 75,600.00
31 Shadowline m' Rp 18,900.00
32 Solar ltr Rp 11,500.00
33 Triplex 6 mm lbr Rp 75,600.00
34 Multiplex 9 mm lbr Rp 98,000.00
35 Multiplex 15 mm lbr Rp 182,000.00
36 Multiplex 12 mm lbr Rp 155,400.00
37 Multiplex 18 mm lbr Rp 244,500.00
38 Multiplex 20 mm lbr Rp 289,500.00
39 Solid surface tebal 2 cm, warna hitam m2 Rp 1,450,000.00
40 Milaminto 3 mm lbr Rp 55,300.00
41 Banner m2 Rp 125,000.00
42 Stiker sandblast m2 Rp 45,600.00
43 Rangka Hollow besi 40x40x1,7x6000mm btg Rp 108,000.00
44 Metal stud uk. 34x76 mm tbl. 0,40 mm m1 Rp 26,500.00
45 U runner uk. 25x76 mm tbl. 0,35 mm m1 Rp 12,400.00
46 Aluminium "U" uk. 20x20x2 mm m1 Rp 28,700.00
47 Hosplin AAE (Hospital Plint Aluminium Alloy Extrussion) m1 Rp 155,000.00
48 Hollow galvalum, uk. 40/40 mm, t=0,3 mm m1 Rp 11,500.00
49 Hollow galvalum, uk. 20/40 mm t=0,3 mm m1 Rp 9,500.00
50 Rangka besi hollow 50x100 mm, tebal 1,8 mm m1 Rp 42,300.00
51 Rangka dudukan ornamen besi hollow 20x40 mm, tebal 1,4 mm m1 Rp 22,500.00
52 Base plate uk. 10x15 cm, tebal 5 mm + pengelasan m1 Rp 855,600.00
53 Dynabolt M-8 m1 Rp 3,500.00
54 Rangka besi hollow galvanis uk. 40x40 mm, tebal 1,4 mm m1 Rp 25,600.00
55 Plat stainless steel hairline lebar 10 cm, tebal 1,5 mm lbr Rp 2,250,000.00
56 MDF 15 mm m2 Rp 76,500.00
57 MDF 20 mm m2 Rp 98,500.00
58 Cutting Laer m2 Rp 675,600.00
59 Wallpaper, goodrich m2 Rp 140,500.00
60 Glass stone tebal 8 mm, warna putih susu m2 Rp 987,500.00
61 Kawat Las kg Rp 28,000.00
62 Skrup kg Rp 35,000.00
63 Meni besi kg Rp 38,000.00
64 Amplas m' Rp 6,000.00
65 Lantai vinyl TACO uk. 304,8 x 609,6 x 3 mm grey slate m2 Rp 172,400.00
66 Lantai vinyl TACO uk. 152,4 x 914,4 x 3 mm washed oak m2 Rp 185,400.00
67 Lem kg Rp 55,000.00
68 GRC cetak bulat m2 Rp 55,000.00
69 Lem beton kg Rp 64,300.00
70 Wood filler kg Rp 30,100.00
71 Politur kg Rp 82,000.00
72 Thinner kg Rp 35,000.00
73 HPL m2 Rp 78,500.00
74 Lem kuning kg Rp 55,000.00
75 Cat Besi Duco kg Rp 83,000.00
76 Dempul Duco kg Rp 40,500.00
77 List Plywood 9 mm finish melamic m Rp 41,000.00
78 Kayu kamper solid uk. 20x30 mm m3 Rp 5,375,000.00
79 Cat Dasar kg Rp 30,500.00
80 Cat Penutup Ex. Jotun kg Rp 35,600.00
81 Roll cat bh Rp 45,000.00
82 Kwas 3" bh Rp 12,000.00
83 Plamur/compound kg Rp 22,000.00
84 Profil aluminium 4" powder coating m1 Rp 105,000.00
85 Aluminium 3" Powder coating btg Rp 443,000.00
86 Profil frame daun pintu aluminium powder coating m1 Rp 185,000.00
87 Sealent btl Rp 45,000.00
88 Kunci tanam bh Rp 145,000.00
89 Pull handle SS-304 38x630x600 mm TPH 981 bh Rp 750,000.00
90 Pull Handle SS 32x300 mm PH 801 bh Rp 330,000.00
91 Pull handle SS-304 38x1200 mm PH 802 bh Rp 1,455,000.00
92 Floor hinge FH 80 SSS bh Rp 4,804,500.00
93 Top patch PT 20 bh Rp 105,000.00
94 Patch fitting PT 40 bh Rp 125,400.00
95 Bottom patch PT 10 bh Rp 164,000.00
96 Corner lock/Patch lock US 10 bh Rp 255,000.00
97 Mortise lock set Rp 195,400.00
98 Escutcheon bh Rp 35,000.00
99 Cylinder + kunci set Rp 125,000.00
100 Sealant kaca m1 Rp 22,500.00
101 Door closer Dekkson 40 kg bh Rp 277,500.00
102 Lever handle dekkson LHTR 39 psg Rp 267,500.00
103 Engsel pintu stainless 4" dekson set Rp 85,000.00
104 Rell laci panjang 40 cm bh Rp 77,500.00
105 Engsel sendok lemari bh Rp 23,500.00
106 Handle lemari + laci bh Rp 46,500.00
107 Magnet Door Stoper Stainless Steel bh Rp 145,000.00
108 Panel sliding aluminium uk. 210x91 cm + kaca tb. 8 mm bh Rp 2,975,400.00
109 Panel sliding aluminium uk. 260x80 cm + kaca tb. 8 mm bh Rp 3,212,000.00
110 Panel sliding uk. 104x260 cm bh Rp 950,400.00
111 Pintu box 3 daun set Rp 7,500,000.00
112 Sound barrier m1 Rp 545,300.00
113 Box penyimpanan, aksessoris tambahan ls Rp 400,000.00
114 Track runner set Rp 495,400.00
115 Finishing powder coating super white gloss 160 m1 Rp 125,000.00
116 Kaca bening 5mm m2 Rp 125,000.00
117 Kaca polos 6 mm m2 Rp 163,000.00
118 Kaca polos, tebal 8 mm m2 Rp 273,400.00
119 Kaca painted glass stone, tebal 8 mm warna putih m2 Rp 262,000.00
120 Kaca polos 3 mm m2 Rp 105,000.00
121 Kaca tempered, tebal 12 mm m2 Rp 885,400.00
122 Karpet Tile 50x50 merk. SMJ tipe Natural Evolution #13 m2 Rp 85,000.00
123 Roll Blinds m Rp 215,400.00
124 Plywood 12 mm + rangka finish melamic m2 Rp 550,000.00
125 Kusen kayu solid oven 5x10cm finish melamic m Rp 144,500.00
126 Insulasi pipa armaflex uk. 3/8" m2 Rp 42,000.00
127 Klem kabel bh Rp 300.00
128 CD copy soft file foto image bh Rp 5,000.00
129 Cetak foto lbr Rp 3,000.00
130 Album foto ls Rp 75,000.00
131 Kamera DSLR Sewa/Hr Rp 175,000.00
132 Pipa Conduit d 20 mm ex Clipsal m1 Rp 3,600.00
133 Saklar Tunggal Schneider bh Rp 45,000.00
134 Saklar Ganda Schneider bh Rp 52,000.00
135 Stop Kontak ex. Broco bh Rp 40,500.00
136 Lampu hidend lamp T5 8 watt P=60 cm,lengkap dengan instalasi unit Rp 265,400.00
137 Lampu downlight dia. 6" cover kaca, LED 13 W Philips bh Rp 105,000.00
138 Lampu downlight dia. 6" cover kaca, LED 10 W Philips bh Rp 98,500.00
139 Pilot Lamp + Fuse (R/S/T) TELE (3 set) set Rp 15,400.00
140 Amper Meter 0 ~ 100 A (3 bh) bh Rp 128,000.00
141 Volt Meter 0 ~ 500 V (1 bh) bh Rp 87,500.00
142 Volt Selector Switch/VSS (1 bh) bh Rp 95,000.00
143 Trafo Arus CT 100/5A, GAE (3 bh) bh Rp 321,000.00
144 MCCB 3P 100~250A 36KA/NSX-250F, Schneider (1 bh) bh Rp 1,850,000.00
145 MCCB 3P 50~100A 25KA/NSX-100F, Schneider (2 bh) bh Rp 775,000.00
146 Magnetik Kontaktror (MC) 80 A, Schneider (2 bh) bh Rp 1,655,400.00
147 MCB 1P 10 A 5KA, Schneider (18 bh) bh Rp 86,500.00
148 MCB 1P 16 A 7.5KA, Schneider (24 bh) bh Rp 105,000.00
149 CU Busbar set Rp 110,000.00
150 Box Panel 140 x 120 x 40 cm, Free standing bh Rp 3,550,000.00
151 Kabel NYY 4 x 70 mm2 m1 Rp 405,000.00
152 Kabel NYM 3 x 2,5 mm m1 Rp 12,300.00
153 Kabel NYMHY 3 x 1,5 mm m1 Rp 11,250.00
154 Tray Kabel uk. 400 x 100 x 3000 x 1,2 mm ( Galvanized ) m1 Rp 145,600.00
155 Tray Kabel uk. 300 x 100 x 3000 x 1,2 mm ( Galvanized ) m1 Rp 125,400.00
156 Equal Cross Tray U 400 x 100 mm bh Rp 305,000.00
157 Tee Tray U 400 x 100 mm bh Rp 277,600.00
158 Cover Tray U 400 x 100 mm m1 Rp 115,000.00
159 Equal Cross Tray U 300 x 100 mm bh Rp 193,400.00
160 Tee Tray U 300 x 100 mm bh Rp 255,400.00
161 Cover Tray U 300 x 100 mm m1 Rp 105,000.00
162 Pesawat Telepon Panasonic KX TS880 bh Rp 675,400.00
163 Telepon Outlet bh Rp 125,000.00
164 Ceiling Acces Point bh Rp 1,255,000.00
165 Lan/data Outlet - Inbow bh Rp 185,600.00
166 Rack Server Wallmount 8 U singledoor bh Rp 2,785,000.00
167 Kabel ITC 1 x ( 2 x 0,6 mm2 ) m1 Rp 5,500.00
168 Kabel STP cat 6E m1 Rp 7,500.00
169 Kabel Coax RG6 m1 Rp 5,100.00
170 Kabel Coax RG59 + Power m1 Rp 7,200.00
171 Kabel Grounding BC 25 mm m1 Rp 26,500.00
172 Saddle/Klem bh Rp 3,000.00
173 Fresher dan Scrup bh Rp 600.00
174 Flexible Conduit PVC 20 mm m1 Rp 13,000.00
175 Tee Dos bh Rp 4,500.00
176 Head sprinkler bh Rp 58,600.00
177 Flexible round duct 8" bh Rp 365,000.00
178 Diffuser bh Rp 255,000.00
179 Return Air Grill (RAG) bh Rp 285,000.00
180 Linear diffuser 1200x200 mm bh Rp 376,500.00
181 Exhaust Air Grill (EAG) bh Rp 245,300.00
182 Amplifier Mixer Power 120 W, Toa ZA 2120 bh Rp 2,675,000.00
183 Multimedia Player Background Music Player, Toa Z CD 2011R bh Rp 4,650,000.00
184 Speaker Selector 10 Channel 2 Input, Daya Input max. 1.000 watt bh Rp 1,675,400.00
185 Mic Car Call / Pagging, Toa ZM 100EC Golden + Cadangan bh Rp 2,876,500.00
186 Rack Audio System Toa 12 U Roda bh Rp 3,075,400.00
187 Terminal Box SS -1 unit Rp 1,155,000.00
188 Ceiling speaker bh Rp 255,400.00
189 Attenuator / Volume kontrol, Toa ZV 303 bh Rp 205,400.00
190 Outlet MATV bh Rp 87,500.00
191 Splitter MATV 4 Way bh Rp 110,500.00
192 Smart TV Led 43 " + Bracket, Samsung unit Rp 6,877,500.00
193 Outlet Stop-Kontak 1 phasa 220V/16A 1 gang ( 1 Power ) bh Rp 133,200.00
194 Power Supply Central Unit, Layar Monitor set Rp 5,321,000.00
195 Kamera indoor ( eksisting ) bh Rp 455,000.00
196 Saklar Grid Switch 9 Gang merk. Schneider tipe Neo bh Rp 524,300.00
197 Saklar Grid Switch 6 Gang merk. Schneider tipe Neo bh Rp 421,400.00
198 Stop kontak 1 gang Normal merk. Schneider tipe Neo Bh Rp 67,500.00
199 Stop Kontak Lantai/Universal ( 3 Lubang ) Power, merk. Panasonic Bh Rp 617,400.00
200 Stop Kontak Lantai ( 2 Lubang ) Power, & Power Bh Rp 512,300.00
HARGA SATUAN UPAH
NO JABATAN SAT HARGA
1 Pekerja Orang/Hari Rp 125,000.00
2 Tukang gali Orang/Hari Rp 125,000.00
3 Tukang batu Orang/Hari Rp 140,000.00
4 Kepala tukang batu Orang/Hari Rp 160,000.00
5 Tukang kayu Orang/Hari Rp 140,000.00
6 Kepala tukang kayu Orang/Hari Rp 160,000.00
7 Tukang Gypsum Orang/Hari Rp 140,000.00
8 Kepala tukang Gypsum Orang/Hari Rp 160,000.00
9 Tukang Aluminium Orang/Hari Rp 140,000.00
10 Kepala tukang Aluminium Orang/Hari Rp 160,000.00
11 Tukang Cat Orang/Hari Rp 140,000.00
12 Kepala tukang Cat Orang/Hari Rp 160,000.00
13 Tukang Pipa Orang/Hari Rp 125,000.00
14 Kepala tukang Pipa Orang/Hari Rp 140,000.00
15 Tukang Las Orang/Hari Rp 140,000.00
16 Kepala Tukang Las Orang/Hari Rp 160,000.00
17 Tukang Listrik Orang/Hari Rp 140,000.00
18 Kepala Tukang Listrik Orang/Hari Rp 160,000.00
19 Pembantu instalator Orang/Hari Rp 140,000.00
20 Instalator Orang/Hari Rp 175,000.00
21 Mandor Orang/Hari Rp 175,000.00