RENCANA ANGGARAN BIAYA

KEGIATAN : PENGEMBANGAN TPQ


PEKERJAAN : REHABILITASI
LOKASI : Kp. Cirewed Rt 03 Rw 03
TAHUN ANGGARAN : 2019

HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME TOTAL HARGA
(RP)
I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pasang Bouwplank m1 2.0 1,500,000 3,000,000
SUBTOTAL (I) PEKERJAAN PESIAPAN 3,000,000
II PEKERJAAN TANAH DAN PASIR
1 Galian tanah pondasi m3 - 39,000 -
2 Mengurug kembali galian pondasi m3 - 13,000 -
3 Urugan pasir bawah pondasi m3 - 117,000 -
4 Urugan tanah peninggian lantai disiram m3 - 91,500 -
5 Pemadatan tanah m3 - 29,000 -
SUBTOTAL (II) PEKERJAAN TANAH DAN PASIR -
III PEKERJAAN PASANGAN
1 Pasangan batu kosong m3 - 298,000 -
2 Pasangan pondasi batu 1 pc : 5 ps m3 - 518,000 -
3 Pasangan dinding 1/2 bata 1 pc : 5 ps m2 20.0 87,000 1,740,000
4 Pasangan dinding 1/2 bata 1 pc : 3 ps m2 93,000 -
SUB TOTAL (III) PEKERJAAN PASANGAN 1,740,000
IV PEKEJAAN BETON
1 Sloop 13/20 m3 - 3,500,000 -
2 Kolom 13/20 m3 0.1 5,200,000 364,000
3 Balok 13/20 m3 0.5 4,468,000 2,234,000
4 Kolom praktis 10/10 m3 - 6,900,000 -
5 Kolom struktur 15/15 (selasar) m3 0.5 4,700,000 2,350,000
6 Balok ring, geuvel 10/15 m3 1.9 6,900,000 13,110,000
SUB TOTAL (IV) PEKERJAAN BETON 18,058,000
V PEKERJAAN PLESTERAN DAN LANTAI
1 Pek. Lantai keramik 40x40 (Lt.1+Lt.2) m2 140.0 144,000 20,160,000
2 Plesteran m2 35.0 42,000 1,470,000
3 Acian plesteran m2 35.0 23,000 805,000
SUB TOTAL (V) PEKERJAAN PLESTERAN DAN LANTAI 22,435,000
VI PEKERJAAN KAYU DAN ALUMINIUM
1 Listplank kayu klas II m' 26.0 61,700 1,604,200
2 Kusen kayu klas II m3 0.7 6,100,000 4,270,000
3 Daun jendela kaca m2 21.0 332,000 6,972,000
4 Daun pintu panil m2 3.2 466,000 1,491,200
5 Pek. Ventilasi krepyek m2 8.0 268,000 2,144,000
6 Kaca polos 3 mm m2 14.0 138,000 1,932,000
SUB TOTAL (VI) PEKERJAAN KAYU DAN ALUMINIUM 18,413,400
VII PEKERJAAN ATAP / PLAFOND
1 Pek. Rangka baja ringan m2 224.0 225,000 50,400,000
2 Atap genteng pejaten lokal m2 224.0 61,000 13,664,000
3 Bubungan genteng pejaten m' 17.0 37,000 629,000
4 Plafond calsiboard 3,5 mm rangka kayu m2 186.0 80,600 14,991,600
5 List gifsum C7 m' 156.0 25,000 3,900,000
SUB TOTAL (VII) PEKERJAAN ATAP / PLAFOND 83,584,600
VIII PEKERJAAN BESI
1 Kunci pintu 2 slang besar bh 2.0 161,000 322,000
2 Engsel pintu bh 6.0 39,000 234,000
3 Engsel jendela bh 44.0 23,200 1,020,800
4 Hak angin kecil bh 44.0 27,500 1,210,000
5 Grendel kecil bh 44.0 21,500 946,000
SUB TOTAL (VIII) PEKEJAAN BESI 3,732,800
IX PEKERJAAN INSTALASI LISTRIK
1 Titik lampu + instalasi bh 8.0 173,500 1,388,000
2 Lampu SL 18 watt bh 8.0 39,900 319,200
3 Saklar dobell bh 1.3 55,000 71,500
4 Saklar tunggal bh 2.0 55,000 110,000
5 Stop kontak bh 2.0 56,000 112,000
SUB TOTAL (IX) PEKERJAAN INSTALASI LISTRIK 2,000,700
X PEKERJAAN PENGECATAN
1 Cat tembok m2 174.0 20,000 3,480,000
2 Cat plapond m2 186.0 20,000 3,720,000
3 Cat kayu m2 77.0 27,000 2,079,000
SUB TOTAL (X) PEKERJAAN PENGECATAN 9,279,000
XI PEKERJAAN REHAB/PENGADAAN MEUBLELAIR
REHABILITASI
1 Meja belajar bh 13.0 250,000 3,250,000
2 Kursi siswa bh 16.0 100,000 1,600,000
3 Meja kerja 1/2 biro bh 0.6 350,000 210,000
4 kursi kerja bh 0.6 175,000 105,000
5 lemari kelas bh 1.3 400,000 520,000
PENGADAAN
6 Meja belajar bh 10.0 650,000 6,500,000
7 Kursi siswa bh 31.0 175,000 5,425,000
8 Meja kerja 1/2 biro bh 1.3 725,000 942,500
9 kursi kerja bh 1.3 250,000 325,000
10 lemari kelas bh 0.6 1,350,000 810,000
11 Tempat sampah bh - 100,000 -
12 Papan tulis (whiteboard) bh 2.0 350,000 700,000

SUB TOTAL (XI) PEKERJAAN PENGADAAN MEUBLAELAIR 20,387,500


TOTAL : I + II + III + IV + V + VI + VII + VIII + IX + X + XI 182,631,000
PEMBULATAN 182,631,000