PEMBAYARAN (Rp.)
NO. ITEM PEMBAYARAN MANDOR RENCANA BAYAR Rp. SISA KETERANGAN/TTD
I II III IV
Pekerjaan U DS 3
1 HAMZAH 103,573,000.00
(Bekisting Baja)
Pekerjaan U DS 3
2 HAMZAH 72,121,000.00
(Bekisting Baja)
3 Fc' 15 Rabat Bahu HAMZAH 20,566,000.00
4 Fc' 15 (Samping Uditch) HAMZAH 2,851,000.00 50,000,000.00 100,000,000.00 40,000,000.00 15,000,000.00 15,963,000.00
Timbunan(Samping
5 HAMZAH 3,192,000.00
Uditch)
Timbunan(Samping
6 HAMZAH 1,560,000.00
Uditch)
7 Pemasangan Guardrail HAMZAH 17,100,000.00
220,963,000.00
TOTAL : Rp. 15,963,000.00
TERBILANG : Lima Belas Juta Sembilan Ratus Enam Puluh Tiga Ribu Rupiah