PEMBANGUNAN JALAN KA JALUR KA TRANS SULAWESI SELATAN

LINTAS MAKASSAR - PAREPARE

MONITORING KEMAJUAN PEKERJAAN JEMBATAN


Bulan: 2020

Sub Struktur Super Struktur


Lokasi Span Site Clearing Stacking Out Bored Pile Galian Pile Cap Coble stone Lantai Kerja
Jenis
CT Sub Structure Pile Cap Body I Body II Top Head Girder Erection Slab Pasangan Batu
Struktur

Km m' Mulai Selesai Mulai Selesai Mulai Selesai Mulai Selesai Mulai Selesai Mulai Selesai Mulai Selesai Mulai Selesai Mulai Selesai Mulai Selesai Mulai Selesai Mulai Selesai Mulai Selesai

A1
402 16+990 20 I Girder
A2

A1
402 17+300 20 I Girder
A2

A1
402 17+581 30 I Girder
A2

A1

P1
403 19+250 20+40+40+40 I Girder
P2

A2

A1
404 24+800 40 I Girder
A2

A1

P1
405 29+075 30+30+30 I Girder
P2

A2

A1
406 31+747 30 I Girder
A2

A1
406 32+430 40 I Girder
A2

A1

407 P1 32+710 30+30 I Girder

A2

A1
407 34+149 40 I Girder
A2

A1
408 37+850 30 I Girder
A2

A1
409 42+000 40+40 I Girder
A2