Anda di halaman 1dari 6

RENCANA ANGGARAN BIAYA

BANGUNAN RUMAH NIRWANA


TAHAP 2

NO URAIAN PEKERJAAN KETERANGAN SPESIFIKASI

I PEKERJAAN PONDASI
1 Pasir Urug t = 5 cm Pondasi Pasir Cor
2 Pasir Urug t = 5 cm Sloof Pasir Cor
3 Lantai Kerja t = 5 cm Pondasi Adukan semen pasir 1 PC : 3 Psr
4 Lantai Kerja t = 5 cm Sloof Adukan semen pasir 1 PC : 3 Psr
5 Beton Pondasi P1
a Beton ( 80 X 80 ) X 20 K.300 Ready Mix
b Bekisting Papan / Multiplex + Kayu
c Pembesian Mutu Baja U-32 + Kawat Ikat, dia 12 - 15
6 Stump 25x25 ( K2 ) t = 40 cm
a Pembesian Mutu Baja U-32 + Kawat Ikat, dia 12
b Pembesian Mutu Baja U-32 + Kawat Ikat, dia 8 - 15
c Bekisting Papan / Multiplex + Kayu
d Beton K.300 Ready Mix

II PEKERJAAN STRUKTUR
A STRUKTUR LANTAI I + 0.00
1 SLOOF
Beton Tulang Sloof S1 ( 20/40 )
a Beton K.300 Ready Mix
b Bekisting Papan / Multiplex + Kayu
c Pembesian Mutu Baja U-32 + Kawat Ikat, dia 12
d Pembesian Mutu Baja U-32 + Kawat Ikat, dia 8 - 15
Beton Tulang Sloof S2 ( 20/30 )
a Beton K.300 Ready Mix
b Bekisting Papan / Multiplex + Kayu
c Pembesian Mutu Baja U-32 + Kawat Ikat, dia 12
d Pembesian Mutu Baja U-32 + Kawat Ikat, dia 8 - 15

3 KOLOM ( Lantai + 0.00 )


Beton Tulang Kolom K1 ( 11 x 40 )
a Beton K.300 Ready Mix
b Bekisting Papan / Multiplex + Kayu
c Pembesian Mutu Baja U-32 + Kawat Ikat, dia 12
d Pembesian Mutu Baja U-32 + Kawat Ikat, dia 8 - 15
Beton Tulang Kolom K2 ( 25 x 25 )
a Beton K.300 Ready Mix
b Bekisting Papan / Multiplex + Kayu
c Pembesian Mutu Baja U-32 + Kawat Ikat, dia 12
d Pembesian Mutu Baja U-32 + Kawat Ikat, dia 8 - 15
Beton Tulang Kolom KP ( 11 X 11 )
a Beton K.300 Ready Mix
b Bekisting Papan / Multiplex + Kayu
c Pembesian Mutu Baja U-32 + Kawat Ikat, dia 10
d Pembesian Mutu Baja U-32 + Kawat Ikat, dia 6 - 15

B STRUKTUR LANTAI II + 3.600


1 BALOK
Beton Tulang Balok + 3.600 B1 ( 20/40 )
a Beton K.300 Ready Mix
b Bekisting Papan / Multiplex + Kayu
c Pembesian Mutu Baja U-32 + Kawat Ikat, dia 12
d Pembesian Mutu Baja U-32 + Kawat Ikat, dia 8 - 15
Beton Tulang Balok + 3.600 B2 ( 15/25 )
a Beton K.300 Ready Mix
b Bekisting Papan / Multiplex + Kayu
c Pembesian Mutu Baja U-32 + Kawat Ikat, dia 12
d Pembesian Mutu Baja U-32 + Kawat Ikat, dia 8 - 15

2 LANTAI II + 3.600
Beton Tulang Plat lantai +3.600 T.12
a Beton K.300 Ready Mix
b Bekisting Bondex
c Pembesian Besi wiremesh A8

III PEKERJAAN ARSITEKTUR


A ARSITEKTUR LANTAI 1
1 Pasangan Bata
2 Plaster Aci Luar & Dalam
3 Pemasangan Keramik Lantai
4 Pembongkaran dinding

IV PEKERJAAN ME
3 Instalasi Pipa Air Kotor Lantai 1
a Pipa 4" & 6" AW w/ accessories
4 Instalasi Pipa Air Bekas Lt. 1
a Pipa 4" & 6" AW w/ accessories
5 Instalasi Pipa Air Bersih
a Pipa PPR PN-10 D 1/2" w/ accessories
b Kloset Jongkok
8 Instalasi Listrik Kamar
Stop kontak 13A
Stop kontak 15A
Saklar 1 Geng
Saklar 2 Geng
Saklar 3 Geng
Box MCB 4 Way

VI PEKERJAAN LAIN-LAIN
1 Pembersihan Lokasi Lokasi

JUML
D

KONTRAKTOR

POLLY
ARAN BIAYA
AH NIRWANA
2

VOLUME SAT HARGA UPAH TOTAL

4.48 m
2 Rp 50,000.00 Rp 224,000.00
9.44 m
2 Rp 50,000.00 Rp 471,900.00
4.48 m
2 Rp 50,000.00 Rp 224,000.00
9.44 m
2 Rp 50,000.00 Rp 471,900.00

0.90 m
3 Rp 240,000.00 Rp 215,040.00
4.48 m
2 Rp 28,000.00 Rp 125,440.00
67.76 kg Rp 2,000.00 Rp 135,520.00

59.14 kg Rp 2,000.00 Rp 118,272.00


11.06 kg Rp 2,000.00 Rp 22,120.00
29.96 m
2 Rp 28,000.00 Rp 838,880.00
1.87 m
3 Rp 240,000.00 Rp 449,400.00
JUMLAH I Rp 3,296,472.00

3.50 m
3 Rp 240,000.00 Rp 840,960.00
35.04 m
2 Rp 28,000.00 Rp 981,120.00
231.26 kg Rp 2,000.00 Rp 462,528.00
115.34 kg Rp 2,000.00 Rp 230,680.00

0.27 m
3 Rp 240,000.00 Rp 64,800.00
0.54 m
2 Rp 28,000.00 Rp 15,120.00
233.37 kg Rp 2,000.00 Rp 466,732.80
12.80 kg Rp 2,000.00 Rp 25,596.00

1.11 m
3 Rp 365,000.00 Rp 404,712.00
25.70 m
2 Rp 32,000.00 Rp 822,528.00
134.27 kg Rp 2,000.00 Rp 268,531.20
134.40 kg Rp 2,000.00 Rp 268,800.00

0.90 3
m Rp 365,000.00 Rp 328,500.00
12.80 2
m Rp 32,000.00 Rp 409,600.00
45.47 kg Rp 2,000.00 Rp 90,931.20
26.97 kg Rp 2,000.00 Rp 53,930.67

0.44 3
m Rp 365,000.00 Rp 158,994.00
7.92 2
m Rp 32,000.00 Rp 253,440.00
88.85 kg Rp 2,000.00 Rp 177,696.00
21.31 kg Rp 2,000.00 Rp 42,624.00
JUMLAH II Rp 6,367,823.87

3.51 3
m Rp 240,000.00 Rp 842,250.24
37.54 2
m Rp 28,000.00 Rp 1,051,232.00
390.01 kg Rp 2,000.00 Rp 780,019.20
207.52 kg Rp 2,000.00 Rp 415,044.00

0.72 3
m Rp 240,000.00 Rp 172,800.00
8.64 2
m Rp 28,000.00 Rp 241,920.00
68.20 kg Rp 2,000.00 Rp 136,396.80
21.24 kg Rp 2,000.00 Rp 42,470.40

8.70 3
m Rp 240,000.00 Rp 2,088,288.00
72.51 2
m Rp 35,000.00 Rp 2,537,850.00
72.51 m2 Rp 8,000.00 Rp 580,080.00
` Rp 8,888,350.64

62.28 m² Rp 20,000.00 Rp 1,245,600.00


55.44 m² Rp 75,000.00 Rp 4,158,000.00
56.70 m² Rp 45,000.00 Rp 2,551,500.00
1.00 ls Rp 1,000,000.00 Rp 1,000,000.00
JUMLAH IV Rp 8,955,100.00
3.00 btg Rp 150,000.00 Rp 450,000.00

3.00 btg Rp 150,000.00 Rp 450,000.00

5.00 btg Rp 90,000.00 Rp 450,000.00


1.00 unit Rp 45,000.00 Rp 45,000.00

4.00 set Rp 75,000.00 Rp 300,000.00


2.00 set Rp 75,000.00 Rp 150,000.00
1.00 set Rp 75,000.00 Rp 75,000.00
2.00 set Rp 75,000.00 Rp 150,000.00
2.00 set Rp 75,000.00 Rp 150,000.00
1.00 set Rp 75,000.00 Rp 75,000.00
JUMLAH V Rp 2,295,000.00

1.00 LS Rp 250,000.00 Rp 250,000.00


JUMLAH VI Rp 250,000.00
JUMLAH KESELURUHAN Rp 30,052,746.51
DISKON / POTONGAN
TOTAL HARGA Rp 30,052,746.51

PEMILIK BANGUNAN

ARASMI LUBIS