TIME SCHEDULE

PEKERJAAN : JASA PENGANGKUTAN BBMP (AVTUR) WILAYAH MOR VI KALIMANTAN

Bobot 2021
No. Uraian Pekerjaan PIC
(%) Jan Feb Mar Apr Mei Jun Jul Ags Sep Okt

1 Pembuatan Dokumen Pengadaan PPN 2.50 2.50

2 Comissioning pekerjaan PPN 2.50 2.50

Proses Pengisian BBP (Avtur) di Fuel/


3 PPN 25.00 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08
Integrated Terminal

4 Proses Pengiriman BBMP (Avtur) PPN 25.00 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08

5 Proses Pembongkaran BBMP (Avtur) di DPPU PPN 25.00 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08

6 Penagihan Biaya Pekerjaan PPN 20.00 1.67 1.67 1.67 1.67 1.67 1.67 1.67 1.67 1.67 1.67

JUMLAH BOBOT 100 10.42 10.42 7.92 7.92 7.92 7.92 7.92 7.92 7.92 7.92

BOBOT MINGGUAN KUMULATIF - 10.42 20.83 28.75 36.67 44.58 52.50 60.42 68.33 76.25 84.17
Ket
Nop Des

100%

2.08 2.08 50%

2.08 2.08

2.08 2.08

1.67 1.67

0%

7.92 7.92 100

92.08 100.00