PEKERJAAN PERSIAPAN 24 days
3
Mobilisasi 20 days
4
Pek. Pagar Seng Keliling Proyek 6 days
5
PEKERJAAN STRUKTUR BANGUNAN BAWAH 48 days
6
Pekerjaan Pondasi Sumuran 13 days
13
Pekerjaan Kepala Jembatan / Abutment (ABT) 22 days
21
Pek. Jalan Pendekatan (Plat Injak) 12 days
28
Pekerjaan Blok Angkur Kabel Utama 18 days
35
PEKERJAAN STRUKTUR BANGUNAN ATAS 99 days
36
Pekerjaan Menara / Pylar Jembatan Gantung (Baja 98 days
BJ - 37, f'y = 240 MPa)
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 1
ID Task Task Name Duration
Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Mode
April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
39 Pek. Pelana Pylar Jembatan, UNP. 300 x 90
8 days
x 9 mm
46
Pekerjaan Kabel Jembatan Gantung (Ungalvanized 51 days
Steel Wire Rope, f'y = 2000 MPa, 06 x 36 (WS) + 1
WRC)
Pek. Kabel Baja Utama / Sling 2 Ø 1.1/4" 15 days
47
Pek. Kabel Baja Ikatan Angin bawah / Sling,
4Ø 3/4"
48 days
54
Pekerjaan Gelagar Jembatan Gantung (Baja BJ - 61 days
37, f'y = 240 MPa)
55
Pek. Baja Struktur Gelagar memanjang, UNP. 80 x 45
15xdays
6 x 8 mm
56
Pek. Baja Struktur Gelagar melintang, UNP. 100 x 504 xdays
6 x 8,5 mm
57
Pek. Baja Struktur Diafragma, L 60 x 60 x 6 mm 5 days
58
Pek. Plat Buhul pada Diafragma, uk. 250 x 200 mm, 5t =days
8 mm
59
Pekerjaan Lantai Jembatan Gantung (Baja BJ - 37, 8 days
f'y = 240 MPa)
60
Pek. Plat Lantai, motif kembang, t = 3,2 mm 8 days
61
Pekerjaan Sadaran (Railing) Jembatan Gantung 15 days
(Steel Pipe Galvanized)
62
Pek. Tiang Sandaran / Railing, L 50 x 50 x 4 mm 2 days
63
Pek. Pengaku Tiang Sandaran / Railing, L 50 x 50 x 24 days
mm
64
Pek. Sandaran / Railing Atas, uk. 50 x 50 x 4 mm 3 days
65
Pek. Sandaran / Railing Tengah dan Bawah, L 40 x 40
4 days
x 4 mm
66
PEKERJAAN PENGECATAN 56 days
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 2