DAFTAR HARGA SATUAN UPAH

SATUAN KERJA : 0

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU

LOKASI : KABUPATEN BONE BOLANGO

THN. ANGGARAN : 2016

HARGA
NO. URAIAN SAT
(Rp)

I UPAH

1 Mandor OH 90,000.00

2 Kepala Tukang OH 125,000.00

3 Tukang Batu OH 110,000.00

4 Tukang Besi OH 110,000.00

5 Tukang Kayu OH 110,000.00


6 Tukang Las OH 110,000.00

7 Tukang Listrik OH 110,000.00

8 Tukang Cat OH 110,000.00

9 Pekerja OH 80,000.00

10 Kameraman OH 110,000.00

11 Pimpinan Teknik OB 1,250,000.00

B. ALAT

1 Tangki Air Hari 50,000.00

2 Pompa Air Jam 15,000.00

3 Dump Truk Hari 700,000.00


4 Mesin Las Jam 125,000.00

Gorontalo, Juni 2015

Dibuat Oleh :

0
0

0
Direktur
DAFTAR HARGA SATUAN BAHAN

SATUAN KERJA : 0

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU

LOKASI : KABUPATEN BONE BOLANGO

THN. ANGGARAN 2016

HARGA
NO. URAIAN SAT
(Rp)

A. BAHAN LOKAL

1 Batu Bata (Standart) Bh 750.00

2 Batu Kali Belah (15/20 cm) M3 175,000.00

3 Batu Kerikil M3 175,000.00

4 Batu Karang M3 90,000.00

5 Ijuk M2 50,000.00

6 Kayu Kls I (Balok) M2 5,000,000.00

7 Kayu Kls I (Papan) M3 5,000,000.00

8 Kayu Kls II (Balok) M3 2,800,000.00

9 Kayu Kls II (Papan) M3 2,800,000.00

10 Kayu Kls III (Balok) M3 2,000,000.00

11 Kayu Kls III (Papan) M3 2,000,000.00


12 Dolken Kayu / Bambu Dia. 10-15 Cm Pjg 4 M Btg 17,500.00

13 Pasir Pasang M3 175,000.00

14 Pasir Urug M3 100,000.00

15 Pasir Domato M3 85,000.00

B. BAHAN NON LOKAL

I SEMEN

1 Semen @50 Kg Tonasa Zak 75,000.00

2 Semen Putih @ 40 Kg Zak 100,000.00


3 Drymix Floor Hardener @ 25 Kg Zak 85,000.00

4 Semen Warna Kg 12,500.00


HARGA
NO. URAIAN SAT
(Rp)

II ATAP

1 Genteng Metal Lbr 37,500.00

2 Bubungan Genteng Metal Lbr 28,200.00

3 Seng Gelombang BJLS 20 Lbr 39,000.00

4 Atap Onduline (Uk. 90x2,00 M) Lbr 167,500.00

5 Bubungan Onduline Lbr 95,000.00

6 Listplank GRC M1 55,000.00

7 Bubungan Seng M1 13,500.00

8 Talang Karet M1 10,000.00

III BESI

1 Besi Beton Kg 10,400.00

2 Besi Strip T = 5 mm Kg 17,500.00

3 Kawat Beton Kg 25,000.00

4 Pipa Galvanis 2,5 Inch M1 118,333.33

5 Pipa Galvanis 3/4 Inch M1 30,000.00

IV ALUMINIUM

1 Tripleks Lapis Alumunium Lbr 80,000.00

2 Kuda-kuda Baja Ringan setara taso M2 176,700.00

3 Rangka Plafond Baja Ringan M1 11,500.00

4 Silmar Aluminium 5x10 M1 85,000.00

5 Silmar Aluminium 3x10 M1 80,000.00

6 Baut Fisher 8 mm Bh 400.00

7 Engsel Aluminium Bh 7,500.00

8 Handel Stainlesteel Set 370,000.00

9 Handel Pintu Set 325,000.00

10 Karet Aluminium Bh 3,750.00


HARGA
NO. URAIAN SAT
(Rp)

11 Treck moor Bh 45,000.00

12 Kunci Pintu Aluminium Bh 220,000.00

13 Handel Pintu Psg 250,000.00

14 Door Closer Bh 225,000.00

15 Besi Strip M1 22,500.00

16 Pintu Aluminium Bh 425,000.00

17 Lem Sealant Tube 30,000.00

18 Rangka Hollow 4.2 M 15,000.00

19 Pintu Harmonika M2 750,000.00

V CAT

1 Cat Kayu Kg 52,000.00

2 Cat Meni Kayu Kg 21,200.00

3 Cat Tembok Dasar Kg 22,000.00

4 Cat Tembok Penutup Kg 22,000.00

5 Cat Vernis Kg 36,700.00

6 Dempul Kg 37,500.00

7 Kertas Ampelas Lbr 10,000.00

8 Plamur Kg 7,340.00

9 Waterprofing Kg 45,000.00
10 Membran 3 mm M2 85,700.00

VI KERAMIK

1 Keramik Lantai 40x40 cm Setara Kw1 Bh 11,387.63

2 Anti Slip Tangga Bh 40,000.00

3 Keramik 25x25 Cm Anti Slip Setara Kw1 Bh 4,843.75

4 Keramik Dinding 25x40 Cm Setara Kw1 Bh 7,500.00

VII INSTALASI LISTRIK


1 Kabel Listrik NYM 3 x 1 1/2 mm M' 10,930.00

2 Lampu SL 18 Watt (Philips) Bh 45,000.00

3 Lampu SL 11 Watt (Philips) BH 40,000.00

4 Lampu SL 8 Watt (Philips) BH 37,500.00

5 Peteng Lampu Down Light BH 45,000.00

6 Lampu Armateru 2x18 Watt Bh 475,000.00

7 Saklar Ganda BH 29,000.00

8 Saklar Tripel BH 35,000.00

9 Saklar Tunggal BH 25,000.00


HARGA
NO. URAIAN SAT
(Rp)

10 Seal Tape BH 5,000.00


HARGA
NO. URAIAN SAT
(Rp)

11 Pipa Instalasi 5/8 Inchi Ujg 7,000.00

12 Peteng Lampu BH 7,500.00

13 Isolatip Bh 3,000.00

14 Stop Kontak BH 25,000.00

15 T. Dos PVC 1/2 inch Bh 1,500.00

16 Bok PVC 1/2" Bh 4,900.00

17 MCB Bh 55,000.00

18 Panel Box Bh 850,000.00

19 Klem PVC 1/2 inch Lot 4,900.00

20 Kabel LAN M1 15,000.00

21 Kabel Sound M1 32,500.00

22 Stop kontak AC M1 85,000.00

23 Socket TV M1 67,500.00

24 PABX PANASONIC Type TA 616 M1 15,000,000.00

25 Socket Telepon M1 75,000.00

26 Ceilling Speaker 6 W M1 200,000.00

27 Horn Speaker M1 350,000.00

28 Attenuator M1 175,000.00

29 Exhaust Fan BH 550,000.00


30 Lampu Sorot Hologen 10 watt Bh 475,000.00

31 Elektroda Kg 75,000.00

VIII KACA

1 Kaca Bening 3 mm M2 95,000.00

2 Kaca Bening 5 mm M2 120,000.00

3 Kaca Reyband 5 mm (Degree) M2 130,000.00

4 Kaca Tempered 10 MM M2 765,000.00

IX BAHAN KUNCI DAN GANTUNGAN

3 Engsel Pintu 4" Bh 22,500.00

4 Engsel Jendela 3" Bh 17,500.00

5 Hak Angin Kuningan Bh 15,000.00

6 Grendel Bh 12,500.00

7 Expanyolet Bh 45,000.00
8 Tarikan Jendela Bh 12,500.00

9 Kunci Pintu 2 Slaag Bh 135,000.00

10 Kunci Pintu 3 Slaag Bh 150,000.00


HARGA
NO. URAIAN SAT
(Rp)

X. PAKU, MUR & BAUT


1 Paku Kg 16,500.00
2 Paku Genteng Kg 25,000.00
3 Paku Seng Kg 25,000.00
4 Paku Triplex Kg 25,000.00

5 Paku Skrup Kuda2 Baja ringan Bh 650.00

6 Paku skrup Genteng Metal + karet Bh 500.00

7 Mur Baut Kg 29,000.00

8 Paku River Kg 500.00

9 Lem Kayu Kg 19,000.00


10 Paku Gyfsum Kg 30,000.00

11 Baut Sekrup Baja Bh 200.00

XI PELUMAS

1 Pelumas Bekisting Ltr 25,000.00

2 Solar Ltr 11,450.00

3 Minyak Pelumas Ltr 30,000.00

XII BAHAN INSTALASI AIR


1 Pipa Galv Æ ¾ inch M1 40,000.00

2 Pipa PE Æ 1/2 inch M1 7,000.00

3 Pipa PVC AW Æ 2 inch M1 9,125.00

4 Pipa PVC AW Æ 4 inch M1 23,250.00

5 Pintu PVC Pabrikasi Bh 300,000.00


6 Bak Air Fiber Bh 450,000.00

7 Kloset Duduk / Monoblok BH 1,750,000.00

8 Kloset Jongkok BH 240,000.00

9 Mata Kran BH 40,000.00

10 Floor Drain Besi BH 33,000.00

11 Wastafel Bh 300,000.00

12 Mata Kran BH 40,000.00

13 Roof Drain BH 42,500.00


HARGA
NO. URAIAN SAT
(Rp)

XIII BAHAN PALFOND

1 Tripleks 3 MM Lbr 55,000.00

2 Plywood 9 mm Lbr 155,000.00

3 Gyfsum Board 9 mm Lbr 75,700.00

4 GRC 4 mm Lbr 75,700.00

5 Profil Gyfsum M1 25,000.00

6 Tepung Gypsum Kg 18,000.00

7 Profil Sp. 3 M1 2,750.00

8 Profil Sp. 4 M1 3,125.00

9 Multipleks 12 MM Lbr 225,000.00

10 HPL Lbr 250,000.00


11 Perekat Kg 35,000.00

12 ACP (Seven) M2 225,000.00

XIV KERTAS

1 Kertas A3 Rim 65,000.00

2 Kertas A4 Rim 40,000.00

3 Tinta Printer Dos 37,500.00

XV HURUF & Logo

1 Huruf Rim 325,000.00

2 Logo Rim 4,500,000.00

Gorontalo, Juni 2015


Dibuat Oleh :
0
0

0
Direktur
ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pengecetan Dinding
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Plamir Kg 0.1000 7,340.00 734.00
2 Cat Dasar Kg 0.1000 22,000.00 2,200.00
3 Cat Penutup (Jotun) Kg 0.2600 22,000.00 5,720.00

Sub Total A 8,654.00

B. UPAH
1 Mandor OH 0.0030 90,000.00 270.00
2 Kepala Tukang OH 0.0060 125,000.00 750.00
3 Tukang Cat OH 0.0630 110,000.00 6,930.00
4 Pekerja OH 0.2000 80,000.00 16,000.00

Sub Total B 23,950.00

C. Jumlah Harga Satuan ( A + B ) 32,604.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pengecetan Plafond
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
2 Cat Dasar Kg 0.1500 22,000.00 3,300.00
3 Cat Penutup Kg 0.1800 22,000.00 3,960.00

Sub Total A 7,260.00

B. UPAH
1 Mandor OH 0.0030 90,000.00 270.00
2 Kepala Tukang OH 0.0060 125,000.00 750.00
3 Tukang Cat OH 0.0630 110,000.00 6,930.00
4 Pekerja OH 0.2000 80,000.00 16,000.00

Sub Total B 23,950.00


C. Jumlah Harga Satuan ( A + B ) 31,210.00
ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pengecetan Kayu (Mengkilap)
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
4 Cat Meni Kg 0.2000 21,200.00 4,240.00
2 Plamir Kg 0.1500 7,340.00 1,101.00
3 Cat Dasar Kg 0.1700 52,000.00 8,840.00
1 Cat Penutup 3x lapis Kg 0.2600 52,000.00 13,520.00

Sub Total A 27,701.00

B. UPAH
1 Mandor OH 0.0025 90,000.00 225.00
2 Kepala Tukang OH 0.0060 125,000.00 750.00
3 Tukang Cat OH 0.0090 110,000.00 990.00
4 Pekerja OH 0.0700 80,000.00 5,600.00

Sub Total B 7,565.00

C. Jumlah Harga Satuan ( A + B ) 35,266.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pengecetan Waterproof
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Waterproof Kg 2.9000 45,000.00 130,500.00
2 Membran 3 mm M2 1.1000 85,700.00 94,270.00

Sub Total A 224,770.00

B. UPAH
1 Mandor OH 0.0150 90,000.00 1,350.00
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Cat OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.3000 80,000.00 24,000.00

Sub Total B 37,600.00


C. Jumlah Harga Satuan ( A + B ) 262,370.00
ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : MCB 3 Phase
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 MCB 3 Phase Bh 1.0000 55,000.00 55,000.00
2 Panel Box Bh 1.0000 850,000.00 850,000.00

Sub Total A 905,000.00

B. UPAH
1 Mandor OH - 90,000.00 -
2 Kepala Tukang OH 0.0375 125,000.00 4,687.50
3 Tukang Listrik OH 0.3750 110,000.00 41,250.00
4 Pekerja OH 0.2500 80,000.00 20,000.00

Sub Total B 65,937.50

C. Jumlah Harga Satuan ( A + B ) 970,937.50

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Instalasi Titik Lampu
SATUAN : TTk

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kabel NYM 3x1 1/2 Mm M1 3.0000 10,930.00 32,790.00
2 Pipa PVC 5/8" M1 1.3000 7,000.00 9,100.00
3 Klem PVC 1/2" Lot 0.4500 4,900.00 2,205.00
4 T. Dos PVC 1/2" Bh 3.0000 1,500.00 4,500.00
5 Bok PVC 1/2" Bh 3.0000 4,900.00 14,700.00
6 Isolatip Bh 1.0000 3,000.00 3,000.00

Sub Total A 66,295.00

B. UPAH
1 Mandor OH - 90,000.00 -
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Listrik OH 0.5350 110,000.00 58,850.00
4 Pekerja OH 0.0500 80,000.00 4,000.00

Sub Total B 64,100.00

C. Jumlah Harga Satuan ( A + B ) 130,395.00


ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Saklar Ganda
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Saklar Ganda Bh 1.0000 29,000.00 29,000.00

Sub Total A 29,000.00

B. UPAH
1 Mandor OH - 90,000.00 -
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Listrik OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.0500 80,000.00 4,000.00

Sub Total B 16,250.00

C. Jumlah Harga Satuan ( A + B ) 45,250.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Saklar Tunggal
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Saklar Tunggal Bh 1.0000 25,000.00 25,000.00

Sub Total A 25,000.00

B. UPAH
1 Mandor OH - 90,000.00 -
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Listrik OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.0500 80,000.00 4,000.00

Sub Total B 16,250.00

C. Jumlah Harga Satuan ( A + B ) 41,250.00


ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Stop Kontak
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Stop Kontak Bh 1.0000 25,000.00 25,000.00

Sub Total A 25,000.00

B. UPAH
1 Mandor OH - 90,000.00 -
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Listrik OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.0500 80,000.00 4,000.00

Sub Total B 16,250.00

C. Jumlah Harga Satuan ( A + B ) 41,250.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pas. Lampu Armateure RMI 2 x 18 W
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Armateure 2x18 W Bh 1.0000 475,000.00 475,000.00

Sub Total A 475,000.00

B. UPAH
1 Mandor OH - 90,000.00 -
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Listrik OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.0500 80,000.00 4,000.00

Sub Total B 16,250.00

C. Jumlah Harga Satuan ( A + B ) 491,250.00


ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Pas. Lampu SL 8 Watt
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Lampu SL 8 Watt Bh 1.0000 37,500.00 37,500.00
2 Peteng Lampu Bh 1.0000 - -

Sub Total A 37,500.00

B. UPAH
1 Mandor OH - 90,000.00 -
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Listrik OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.0500 80,000.00 4,000.00

Sub Total B 16,250.00


C. Jumlah Harga Satuan ( A + B ) 53,750.00
ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pasang Pipa PVC AW Æ 4 inci
SATUAN : M1

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Pipa PVC AW Æ 4 inci M' 1.2000 23,250.00 27,900.00
2 Perlengkapan (35% harga pipa) Ls 1.0000 8,137.50 8,137.50

Sub Total A 36,037.50

B. UPAH
1 Mandor OH 0.0041 90,000.00 369.00
2 Kepala Tukang OH 0.0135 125,000.00 1,687.50
3 Tukang Batu OH 0.1350 110,000.00 14,850.00
4 Pekerja OH 0.0810 80,000.00 6,480.00

Sub Total B 23,386.50

C. Jumlah Harga Satuan ( A + B ) 59,424.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pasang Pipa PVC AW Æ 2 inci
SATUAN : M1

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Pipa PVC AW Æ 2 inci M' 1.2000 9,125.00 10,950.00
2 Perlengkapan (35% harga pipa) Ls 1.0000 3,193.75 3,193.75

Sub Total A 14,143.75

B. UPAH
1 Mandor OH 0.0027 90,000.00 243.00
2 Kepala Tukang OH 0.0090 125,000.00 1,125.00
3 Tukang Batu OH 0.0900 110,000.00 9,900.00
4 Pekerja OH 0.0540 80,000.00 4,320.00

Sub Total B 15,588.00

C. Jumlah Harga Satuan ( A + B ) 29,731.75


ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pasang Pipa PE Æ 1/2 inci
SATUAN : M1

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Pipa PE Æ 1/2 inci M' 1.2000 7,000.00 8,400.00
2 Perlengkapan (35% harga pipa) Ls 1.0000 2,450.00 2,450.00

Sub Total A 10,850.00

B. UPAH
1 Mandor OH 0.0018 90,000.00 162.00
2 Kepala Tukang OH 0.0060 125,000.00 750.00
3 Tukang Batu OH 0.0600 110,000.00 6,600.00
4 Pekerja OH 0.0360 80,000.00 2,880.00

Sub Total B 10,392.00

C. Jumlah Harga Satuan ( A + B ) 21,242.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pasang Pipa Galv Æ 3/4 inci
SATUAN : M1

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Pipa Galv Æ 3/4 inci M' 1.2000 40,000.00 48,000.00
2 Perlengkapan (35% harga pipa) Ls 1.0000 14,000.00 14,000.00

Sub Total A 62,000.00

B. UPAH
1 Mandor OH 0.0270 90,000.00 2,430.00
2 Kepala Tukang OH 0.0090 125,000.00 1,125.00
3 Tukang Batu OH 0.0900 110,000.00 9,900.00
4 Pekerja OH 0.0540 80,000.00 4,320.00

Sub Total B 17,775.00

C. Jumlah Harga Satuan ( A + B ) 79,775.00


ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pasang Mata Kran Æ 1/2 inci
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Mata Kran Æ 4 inci Bh 1.0000 40,000.00 40,000.00
2 Seal Tape Bh 0.0250 5,000.00 125.00

Sub Total A 40,125.00

B. UPAH
1 Mandor OH 0.0050 90,000.00 450.00
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Batu OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.0100 80,000.00 800.00

Sub Total B 13,500.00

C. Jumlah Harga Satuan ( A + B ) 53,625.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pasang Floor Drain
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Floor Drain Bh 1.0000 33,000.00 33,000.00

Sub Total A 33,000.00

B. UPAH
1 Mandor OH 0.0050 90,000.00 450.00
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Batu OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.0100 80,000.00 800.00

Sub Total B 13,500.00

C. Jumlah Harga Satuan ( A + B ) 46,500.00


ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pasang Kloset Duduk
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kloset Duduk / Monoblok Bh 1.0000 1,750,000.00 1,750,000.00
2 Perlengkapan (6 % Harga) Ls 1.0000 105,000.00 105,000.00

Sub Total A 1,855,000.00

B. UPAH
1 Mandor OH 0.1600 90,000.00 14,400.00
2 Kepala Tukang OH 0.1500 125,000.00 18,750.00
3 Tukang Batu OH 1.5000 110,000.00 165,000.00
4 Pekerja OH 1.0000 80,000.00 80,000.00

Sub Total B 278,150.00

C. Jumlah Harga Satuan ( A + B ) 2,133,150.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pasang Kloset Jongkok
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kloset Jongkok Bh 1.0000 240,000.00 240,000.00
2 Semen @50 Kg Zak 0.1200 75,000.00 9,000.00
3 Pasir Pasang M3 0.0100 175,000.00 1,750.00

Sub Total A 250,750.00

B. UPAH
1 Mandor OH 0.1600 90,000.00 14,400.00
2 Kepala Tukang OH 0.1500 125,000.00 18,750.00
3 Tukang Batu OH 1.5000 110,000.00 165,000.00
4 Pekerja OH 1.0000 80,000.00 80,000.00

Sub Total B 278,150.00

C. Jumlah Harga Satuan ( A + B ) 528,900.00


ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pasang Wastafel
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Wastafel Bh 1.0000 300,000.00 300,000.00
2 Perlengkapan (12 % Harga) Ls 1.0000 36,000.00 36,000.00
3 Semen @50 Kg Zak 0.1200 75,000.00 9,000.00
4 Pasir Pasang M3 0.0100 175,000.00 1,750.00

Sub Total A 346,750.00

B. UPAH
1 Mandor OH 0.1600 90,000.00 14,400.00
2 Kepala Tukang OH 0.1500 125,000.00 18,750.00
3 Tukang Batu OH 1.5000 110,000.00 165,000.00
4 Pekerja OH 1.0000 80,000.00 80,000.00

Sub Total B 278,150.00

C. Jumlah Harga Satuan ( A + B ) 624,900.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Septicktank Lengkap
SATUAN : Unit

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Galian Tanah M3 8.5000 62,250.00 529,125.00
2 Urugan Pasir M3 0.6500 144,900.00 94,185.00
3 Pas. Batu Bata Sp 1:3 M3 12.3000 118,655.00 1,459,456.50
4 Plesteran Sp 1:3 M2 23.0000 59,414.00 1,366,522.00
5 Cor Beton Tumbuk Sp. 1:3:5 M3 0.4200 740,075.00 310,831.50
6 Batu Gunung M3 0.8000 727,825.00 582,260.00
7 Ijuk M2 5.5000 50,000.00 275,000.00
8 Pipa PVC Dia. 4" M1 6.0000 59,424.00 356,544.00
9 Pipa Galv. Dia. 2" M1 2.1500 29,731.75 63,923.26

B Jumlah Harga Satuan 5,037,847.26


ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Pasang Pipa PVC AW Æ 2,5 inci
SATUAN : M1

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Pipa PVC AW Æ 2 inci M' 1.2000 9,125.00 10,950.00
2 Perlengkapan (35% harga pipa) Ls 1.0000 3,193.75 3,193.75

Sub Total A 14,143.75

B. UPAH
1 Mandor OH 0.0027 90,000.00 243.00
2 Kepala Tukang OH 0.0090 125,000.00 1,125.00
3 Tukang Batu OH 0.0900 110,000.00 9,900.00
4 Pekerja OH 0.0540 80,000.00 4,320.00

Sub Total B 15,588.00


C. Jumlah Harga Satuan ( A + B ) 29,731.75

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pasang roof Drain
SATUAN : bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Roof Drain M' 1.0000 42,500.00 42,500.00

Sub Total A 42,500.00

B. UPAH
1 Mandor OH 0.0027 90,000.00 243.00
2 Kepala Tukang OH 0.0090 125,000.00 1,125.00
3 Tukang Batu OH 0.0900 110,000.00 9,900.00
4 Pekerja OH 0.0540 80,000.00 4,320.00

Sub Total B 15,588.00


C. Jumlah Harga Satuan ( A + B ) 58,088.00
ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Beton tumbuk 1:3:5
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Semen @50 Kg Zak 4.3600 75,000.00 327,000.00
2 Pasir Pasang M3 0.5200 175,000.00 91,000.00
3 Batu Kerikil M3 0.8700 175,000.00 152,250.00

Sub Total A 570,250.00

B. UPAH
1 Mandor OH 0.0800 90,000.00 7,200.00
2 Kepala Tukang OH 0.0250 125,000.00 3,125.00
3 Tukang Batu OH 0.2500 110,000.00 27,500.00
4 Pekerja OH 1.6500 80,000.00 132,000.00

Sub Total B 169,825.00

C. Jumlah Harga Satuan ( A + B ) 740,075.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Lantai Keramik Anti Slip 25 x 25
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Keramik 25 x 25 cm (Anti slip) Bh 16.0000 4,843.75 77,500.00
2 Semen @50 Kg Zak 0.2080 75,000.00 15,600.00
3 Pasir Pasang M3 0.0450 175,000.00 7,875.00
4 Semen Warna (grout) Zak 0.0405 100,000.00 4,050.00

Sub Total A 105,025.00

B. UPAH
1 Mandor OH 0.0140 90,000.00 1,260.00
2 Kepala Tukang OH 0.0140 125,000.00 1,750.00
3 Tukang Batu OH 0.1350 110,000.00 14,850.00
4 Pekerja OH 0.2700 80,000.00 21,600.00

Sub Total B 39,460.00


C. Jumlah Harga Satuan ( A + B ) 144,485.00
ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Dinding Keramik 25 x 40 Cm
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Keramik 25x40 cm Bh 10.0000 7,500.00 75,000.00
2 Semen @50 Kg Zak 0.2080 75,000.00 15,600.00
3 Pasir Pasang M3 0.0450 175,000.00 7,875.00
4 Semen Warna (grout) Zak 0.0405 100,000.00 4,050.00

Sub Total A 102,525.00

B. UPAH
1 Mandor OH 0.0140 90,000.00 1,260.00
2 Kepala Tukang OH 0.0140 125,000.00 1,750.00
3 Tukang Batu OH 0.1350 110,000.00 14,850.00
4 Pekerja OH 0.2700 80,000.00 21,600.00

Sub Total B 39,460.00


C. Jumlah Harga Satuan ( A + B ) 141,985.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Lantai Keramik 40 x 40 Setara Kw1
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Keramik 40x40 Cm Setara Kw1 BH 6.6300 11,387.63 75,500.00
2 Semen @50 Kg Zak 0.1960 75,000.00 14,700.00
3 Pasir Pasang M3 0.0450 175,000.00 7,875.00
4 Semen Warna (grout) Zak 0.0325 100,000.00 3,250.00

Sub Total A 101,325.00

B. UPAH
1 Mandor OH 0.0130 90,000.00 1,170.00
2 Kepala Tukang OH 0.0130 125,000.00 1,625.00
3 Tukang Batu OH 0.1250 110,000.00 13,750.00
4 Pekerja OH 0.2500 80,000.00 20,000.00

Sub Total B 36,545.00


C. Jumlah Harga Satuan ( A + B ) 137,870.00
ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Plint Lantai Keramik 10 x 40 Setara Kw1
SATUAN : M1

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Keramik 10x40 Cm Setara Kw1 Bh 2.6500 11,387.63 30,177.22
2 Semen @50 Kg Zak 0.0228 75,000.00 1,710.00
3 Pasir Pasang M3 0.0030 175,000.00 525.00
0.0025
Sub Total A 32,412.22

B. UPAH
1 Mandor OH 0.0045 90,000.00 405.00
2 Kepala Tukang OH 0.0090 125,000.00 1,125.00
3 Tukang Batu OH 0.0900 110,000.00 9,900.00
4 Pekerja OH 0.0900 80,000.00 7,200.00

Sub Total B 18,630.00


C. Jumlah Harga Satuan ( A + B ) 51,042.22
ANALISA HARGA SATUAN

PEKERJAAN : PEMBANGUNAN GEDUNG RKB (1 RKB)


JENIS PEKERJAAN : Rangka Plafond Kayu Kls.II
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Kls II M3 0.0120 2,800,000.00 33,600.00
2 Paku Kg 0.1000 20,500.00 2,050.00

Sub Total A 35,650.00

B. UPAH
1 Mandor OH 0.0750 90,000.00 6,750.00
2 Kepala Tukang OH 0.0250 125,000.00 3,125.00
3 Tukang Kayu OH 0.2500 110,000.00 27,500.00
4 Pekerja OH 0.1500 80,000.00 12,000.00

Sub Total B 49,375.00


C. Jumlah Harga Satuan ( A + B ) 85,025.00

PEKERJAAN : PEMBANGUNAN GEDUNG RKB (1 RKB)


JENIS PEKERJAAN : Plafond Tripleks 3 mm
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Tripleks 3 mm Lbr 0.3750 47,000.00 17,625.00
2 Paku Tripleks Kg 0.0300 25,000.00 750.00

Sub Total A 18,375.00

B. UPAH
1 Mandor OH 0.0050 90,000.00 450.00
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Kayu OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.1000 80,000.00 8,000.00

Sub Total B 20,700.00


C. Jumlah Harga Satuan ( A + B ) 39,075.00

PEKERJAAN : PEMBANGUNAN GEDUNG RKB (1 RKB)


JENIS PEKERJAAN : List Plafon Profil SP4
SATUAN : M1

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Profil SP4 M' 1.0500 2,750.00 2,887.50
2 Paku Kg 0.0100 20,500.00 205.00

Sub Total A 3,092.50

B. UPAH
1 Mandor OH 0.0030 90,000.00 270.00
2 Kepala Tukang OH 0.0050 125,000.00 625.00
3 Tukang Kayu OH 0.0500 110,000.00 5,500.00
4 Pekerja OH 0.0500 80,000.00 4,000.00

Sub Total B 10,395.00


C. Jumlah Harga Satuan ( A + B ) 13,487.50
ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Plafond Gyfsum Board 9 mm
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Gyfsum Board 9 mm Lbr 0.3640 75,700.00 27,554.80
2 Paku Sekrup Gyfsum Kg 0.1100 30,000.00 3,300.00

Sub Total A 30,854.80

B. UPAH
1 Mandor OH 0.0050 90,000.00 450.00
2 Kepala Tukang OH 0.0050 125,000.00 625.00
3 Tukang Kayu OH 0.0500 110,000.00 5,500.00
4 Pekerja OH 0.1000 80,000.00 8,000.00

Sub Total B 14,575.00


C. Jumlah Harga Satuan ( A + B ) 45,429.80

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : List Plafon Gyfsum 14 Cm
SATUAN : M1

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 profil Gyfsum 14 Cm M' 1.0500 25,000.00 26,250.00
2 Tepung Gypsum Kg 0.1500 18,000.00 2,700.00

Sub Total A 28,950.00

B. UPAH
1 Mandor OH 0.0030 90,000.00 270.00
2 Kepala Tukang OH 0.0060 125,000.00 750.00
3 Tukang Kayu OH 0.0600 110,000.00 6,600.00
4 Pekerja OH 0.0600 80,000.00 4,800.00

Sub Total B 12,420.00


C. Jumlah Harga Satuan ( A + B ) 41,370.00
ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Pek. Rangka Plafond Hollow Aluminium
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Hollow Aluminium M1 3.6000 11,500.00 41,400.00
2 Mur Baut Kg 0.2000 29,000.00 5,800.00
3 Alat Bantu Ls 1.0000 5,000.00 5,000.00
Sub Total A 52,200.00

B. UPAH
1 Mandor OH 0.0750 60,000.00 4,500.00
2 Kepala Tukang OH 0.0250 75,000.00 1,875.00
3 Tukang Kayu OH 0.2500 70,000.00 17,500.00
4 Pekerja OH 0.1500 50,000.00 7,500.00

Sub Total B 31,375.00


C. Jumlah Harga Satuan ( A + B ) 83,575.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Partisi Gyfsum Board 9 mm
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Rangka Hollow M1 3.6000 11,500.00 41,400.00
2 Mur Baut Kg 0.2000 29,000.00 5,800.00
3 Alat Bantu Ls 1.0000 5,000.00 5,000.00
4 Gyfsum Board 9 mm Lbr 0.7280 75,700.00 55,109.60
5 Paku Sekrup Gyfsum Kg 0.2200 30,000.00 6,600.00

Sub Total A 113,909.60

B. UPAH
1 Mandor OH 0.0050 90,000.00 450.00
2 Kepala Tukang OH 0.0050 125,000.00 625.00
3 Tukang Kayu OH 0.0500 110,000.00 5,500.00
4 Pekerja OH 0.1000 80,000.00 8,000.00

Sub Total B 14,575.00


C. Jumlah Harga Satuan ( A + B ) 128,484.60
ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pek. Kuda - Kuda Baja Ringan dan Atap Metal
SATUAN : M2

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN
1 Rangka Atap Baja Ringan M2 1.000 176,700.00 176,700.00
2 Atap Genteng Metal Lbr 1.560 37,500.00 58,500.00
3 Paku skrup Genteng Metal + karet Bh 14.000 500.00 7,000.00

Sub Total A 242,200.00

B. UPAH
1 Mandor OH 0.022 90,000.00 2,000.00
2 Kepala Tukang OH 0.022 125,000.00 2,777.78
3 Tukang OH 0.222 110,000.00 24,444.44
4 Pekerja OH 0.444 80,000.00 35,555.56

Sub Total B 64,777.78


C. Jumlah Harga Satuan ( A + B ) 306,977.78

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Jurai Dalam
SATUAN : M1

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Talang Karet M 1.1000 10,000.00 11,000.00
2 Paku Bh 6.0000 500.00 3,000.00

Sub Total A 14,000.00

B. UPAH
1 Mandor OH 0.0130 90,000.00 1,170.00
2 Kepala Tukang OH 0.0120 125,000.00 1,500.00
3 Tukang Kayu OH 0.1500 110,000.00 16,500.00
4 Pekerja OH 0.2500 80,000.00 20,000.00

Sub Total B 39,170.00


C. Jumlah Harga Satuan ( A + B ) 53,170.00
ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Bubungan Genteng Metal
SATUAN : M1

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Bubungan Genteng Metal bh 1.1000 28,200.00 31,020.00
2 Paku skrup Genteng Metal + karet bh 6.0000 500.00 3,000.00

Sub Total A 34,020.00

B. UPAH
1 Mandor OH 0.0130 90,000.00 1,170.00
2 Kepala Tukang OH 0.0120 125,000.00 1,500.00
3 Tukang Kayu OH 0.1500 110,000.00 16,500.00
4 Pekerja OH 0.2500 80,000.00 20,000.00

Sub Total B 39,170.00


C. Jumlah Harga Satuan ( A + B ) 73,190.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Listplank GRC
SATUAN : M1

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 GRC M1 1.1000 55,000.00 60,500.00
2 Paku Sekrup Bh 6.0000 500.00 3,000.00

Sub Total A 63,500.00

B. UPAH
1 Mandor OH 0.0010 90,000.00 90.00
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Kayu OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.0100 80,000.00 800.00

Sub Total B 13,140.00


C. Jumlah Harga Satuan ( A + B ) 76,640.00
ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Ventilasi Atap Grc
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Rangka Hollow M1 1.1000 11,500.00 12,650.00
2 Paku Sekrup Kg 6.0000 500.00 3,000.00
3 GRC Board 4 mm Lbr 0.3640 75,700.00 27,554.80
4 Paku Sekrup Gyfsum Kg 0.1100 30,000.00 3,300.00

Sub Total A 46,504.80

B. UPAH
1 Mandor OH 0.0050 90,000.00 450.00
2 Kepala Tukang OH 0.0050 125,000.00 625.00
3 Tukang Kayu OH 0.0500 110,000.00 5,500.00
4 Pekerja OH 0.1000 80,000.00 8,000.00

Sub Total B 14,575.00


C. Jumlah Harga Satuan ( A + B ) 61,079.80
ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Kosen Pintu / Jendela / Ventilasi Kayu Kls I
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Kls I M3 1.2000 5,000,000.00 6,000,000.00
2 Paku Kg 0.2000 20,000.00 4,000.00

Sub Total A 6,004,000.00

B. UPAH
1 Mandor OH 0.3000 90,000.00 27,000.00
2 Kepala Tukang OH 2.0000 125,000.00 250,000.00
3 Tukang Kayu OH 18.0000 110,000.00 1,980,000.00
4 Pekerja OH 6.0000 80,000.00 480,000.00

Sub Total B 2,737,000.00

C. Jumlah Harga Satuan ( A + B ) 8,741,000.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Daun Pintu Panel Kayu Kls II
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Kls II M3 0.0400 2,800,000.00 112,000.00
2 Paku Kg 0.1000 20,000.00 2,000.00

Sub Total A 114,000.00

B. UPAH
1 Mandor OH 0.0500 90,000.00 4,500.00
2 Kepala Tukang OH 0.2500 125,000.00 31,250.00
3 Tukang Kayu OH 2.5000 110,000.00 275,000.00
4 Pekerja OH 1.0000 80,000.00 80,000.00

Sub Total B 390,750.00

C. Jumlah Harga Satuan ( A + B ) 504,750.00


PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Daun Pintu Panel Lapis Alumunium Kayu Kls II
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Kls II M3 0.0400 2,800,000.00 112,000.00
2 Paku Kg 0.1000 20,000.00 2,000.00
3 Tripleks Aluminium Lbr 0.4098 105,000.00 43,032.79

Sub Total A 157,032.79

B. UPAH
1 Mandor OH 0.0500 90,000.00 4,500.00
2 Kepala Tukang OH 0.2500 125,000.00 31,250.00
3 Tukang Kayu OH 2.5000 110,000.00 275,000.00
4 Pekerja OH 1.0000 80,000.00 80,000.00

Sub Total B 390,750.00


C. Jumlah Harga Satuan ( A + B ) 547,782.79

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Daun Pintu / Jendela / Ventilasi Kaca 4,5 mm Kayu Kls II
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Kls II M3 0.0350 2,800,000.00 98,000.00
2 Kaca Bening 4,5 mm M2 0.6000 93,000.00 55,800.00

Sub Total A 153,800.00

B. UPAH
1 Mandor OH 0.0400 90,000.00 3,600.00
2 Kepala Tukang OH 0.2000 125,000.00 25,000.00
3 Tukang Kayu OH 2.0000 110,000.00 220,000.00
4 Pekerja OH 0.8000 80,000.00 64,000.00

Sub Total B 312,600.00


C. Jumlah Harga Satuan ( A + B ) 466,400.00
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Engsel Pintu 4 Inci
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Engsel Pintu 4 " Bh 1.0000 27,000.00 27,000.00

Sub Total A 27,000.00

B. UPAH
1 Mandor OH 0.0008 90,000.00 67.50
2 Kepala Tukang OH 0.0150 125,000.00 1,875.00
3 Tukang Kayu OH 0.1500 110,000.00 16,500.00
4 Pekerja OH 0.0150 80,000.00 1,200.00

Sub Total B 19,642.50

C. Jumlah Harga Satuan ( A + B ) 46,642.50

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Engsel Jendela 3 Inci
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Engsel Jendela 3" Bh 1.0000 13,000.00 13,000.00

Sub Total A 13,000.00

B. UPAH
1 Mandor OH 0.0008 90,000.00 67.50
2 Kepala Tukang OH 0.0150 125,000.00 1,875.00
3 Tukang Kayu OH 0.1500 110,000.00 16,500.00
4 Pekerja OH 0.0150 80,000.00 1,200.00

Sub Total B 19,642.50

C. Jumlah Harga Satuan ( A + B ) 32,642.50


PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Kunci Tanam 2 Slaag
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kunci 2 Slaag Bh 1.0000 115,000.00 115,000.00

Sub Total A 115,000.00

B. UPAH
1 Mandor OH 0.0003 90,000.00 22.50
2 Kepala Tukang OH 0.0050 125,000.00 625.00
3 Tukang Kayu OH 0.5000 110,000.00 55,000.00
4 Pekerja OH 0.0050 80,000.00 400.00

Sub Total B 56,047.50

C. Jumlah Harga Satuan ( A + B ) 171,047.50

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Grendel
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Grendel Bh 1.0000 5,000.00 5,000.00

Sub Total A 5,000.00

B. UPAH
1 Mandor OH 0.0008 90,000.00 67.50
2 Kepala Tukang OH 0.0150 125,000.00 1,875.00
3 Tukang Kayu OH 0.1500 110,000.00 16,500.00
4 Pekerja OH 0.0150 80,000.00 1,200.00

Sub Total B 19,642.50

C. Jumlah Harga Satuan ( A + B ) 24,642.50


PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Kait Angin
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kait Angin Bh 1.0000 7,000.00 7,000.00

Sub Total A 7,000.00

B. UPAH
1 Mandor OH 0.0008 90,000.00 67.50
2 Kepala Tukang OH 0.0150 125,000.00 1,875.00
3 Tukang Kayu OH 0.1500 110,000.00 16,500.00
4 Pekerja OH 0.0150 80,000.00 1,200.00

Sub Total B 19,642.50

C. Jumlah Harga Satuan ( A + B ) 26,642.50

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Tarikan Jendela
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Tarikan Bh 1.0000 7,000.00 7,000.00

Sub Total A 7,000.00

B. UPAH
1 Mandor OH 0.0008 90,000.00 67.50
2 Kepala Tukang OH 0.0150 125,000.00 1,875.00
3 Tukang Kayu OH 0.1500 110,000.00 16,500.00
4 Pekerja OH 0.0150 80,000.00 1,200.00

Sub Total B 19,642.50

C. Jumlah Harga Satuan ( A + B ) 26,642.50


PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Expanyolet Tanam
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Expanyolet Tanam Bh 1.0000 40,500.00 40,500.00

Sub Total A 40,500.00

B. UPAH
1 Mandor OH 0.0008 90,000.00 67.50
2 Kepala Tukang OH 0.0150 125,000.00 1,875.00
3 Tukang Kayu OH 0.1500 110,000.00 16,500.00
4 Pekerja OH 0.0150 80,000.00 1,200.00

Sub Total B 19,642.50

C. Jumlah Harga Satuan ( A + B ) 60,142.50

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Jalusi Papan Kayu Kls II
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Papan Kayu Kls I M3 0.0252 2,800,000.00 70,560.00
2 Paku Kg 0.0600 20,000.00 1,200.00
3 Pengecatan M2 2.52 35,266.00 88,870.32

Sub Total A 160,630.32

B. UPAH
1 Mandor OH 0.0500 90,000.00 4,500.00
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Kayu OH 0.7200 110,000.00 79,200.00
4 Pekerja OH 0.1000 80,000.00 8,000.00

Sub Total B 92,950.00


C. Jumlah Harga Satuan ( A + B ) 253,580.32
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Pas. Pintu Harmonika
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Pintu Harmonika M2 1.0000 750,000.00 750,000.00

Sub Total A 750,000.00

B. UPAH
1 Mandor OH 0.0320 90,000.00 2,880.00
2 Kepala Tukang OH 0.0650 125,000.00 8,125.00
3 Tukang Batu OH 0.6500 110,000.00 71,500.00
4 Pekerja OH 0.2000 80,000.00 16,000.00

Sub Total B 98,505.00


C. Jumlah Harga Satuan ( A + B ) 848,505.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Ventilasi Besi
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Besi Dia. 19 mm Kg 11.8500 10,400.00 123,240.00

Sub Total A 123,240.00

B. UPAH

Sub Total B -
C. Jumlah Harga Satuan ( A + B ) 123,240.00
ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Membuat 1 M1 Kusen Pintu / Jendela Aluminium
SATUAN : M1

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN
1 Silmar Aluminium 5x10 M' 1.100 85,000.00 93,500.00
2 Baut Fisher 8mm Bh 2.000 400.00 800.00

Sub Total A 94,300.00

B. UPAH
1 Mandor OH 0.002 90,000.00 189.00
2 Kepala Tukang OH 0.004 125,000.00 537.50
3 Tukang Aluminium OH 0.043 110,000.00 4,730.00
4 Pekerja OH 0.043 80,000.00 3,440.00

Sub Total B 8,896.50


C. Jumlah Harga Satuan ( A + B ) 103,196.50

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Membuat 1 M2 Pasang Pintu Aluminium
SATUAN : M2

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN
Silmar Aluminium 3x10 M' 1.100 80,000.00 88,000.00
Baut Fisher Bh 2.000 400.00 800.00

Sub Total A 88,800.00

B. UPAH
1 Mandor OH 0.002 90,000.00 189.00
2 Kepala Tukang OH 0.004 125,000.00 537.50
3 Tukang Aluminium OH 0.043 110,000.00 4,730.00
4 Pekerja OH 0.043 80,000.00 3,440.00

Sub Total B 8,896.50


C. Jumlah Harga Satuan ( A + B ) 97,696.50
ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Memasang 1 M Karet Kosen
SATUAN : M2

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN
Karet Kosen M' 1.100 3,750.00 4,125.00

Sub Total A 4,125.00

B. UPAH
1 Mandor OH 0.002 90,000.00 189.00
2 Kepala Tukang OH 0.004 125,000.00 537.50
3 Tukang Aluminium OH 0.043 110,000.00 4,730.00
4 Pekerja OH 0.043 80,000.00 3,440.00

Sub Total B 8,896.50


C. Jumlah Harga Satuan ( A + B ) 13,021.50

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Memasang 1 Set Handel Stenlees
SATUAN : Set

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN
1 Handel Stenless Bh 1.000 370,000.00 370,000.00

Sub Total A 370,000.00

B. UPAH
1 Mandor OH 0.003 90,000.00 270.00
2 Kepala Tukang OH 0.050 125,000.00 6,250.00
3 Tukang Aluminium OH 0.500 110,000.00 55,000.00
4 Pekerja OH 0.050 80,000.00 4,000.00

Sub Total B 65,520.00


C. Jumlah Harga Satuan ( A + B ) 435,520.00
ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Memasang 1 Set Handel Pintu
SATUAN : Set

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN
Handle Pintu Bh 1.000 325,000.00 325,000.00

Sub Total A 325,000.00

B. UPAH
1 Mandor OH 0.003 90,000.00 270.00
2 Kepala Tukang OH 0.050 125,000.00 6,250.00
3 Tukang Aluminium OH 0.500 110,000.00 55,000.00
4 Pekerja OH 0.050 80,000.00 4,000.00

Sub Total B 65,520.00


C. Jumlah Harga Satuan ( A + B ) 390,520.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pasangan 1 Bh Engsel Pintu
SATUAN : Bh

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN
Engsel Pintu 4 " Bh 1.000 22,500.00 22,500.00

Sub Total A 22,500.00

B. UPAH
1 Mandor OH 0.008 90,000.00 720.00
2 Kepala Tukang OH 0.015 125,000.00 1,875.00
3 Tukang Aluminium OH 0.150 110,000.00 16,500.00
4 Pekerja OH 0.015 80,000.00 1,200.00

Sub Total B 20,295.00


C. Jumlah Harga Satuan ( A + B ) 42,795.00
ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Pasangan 1 Bh Engsel Jendela
SATUAN : Bh

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN
Engsel Pintu 3 " Bh 1.000 17,500.00 17,500.00

Sub Total A 17,500.00

B. UPAH
1 Mandor OH 0.008 90,000.00 720.00
2 Kepala Tukang OH 0.015 125,000.00 1,875.00
3 Tukang Aluminium OH 0.150 110,000.00 16,500.00
4 Pekerja OH 0.015 80,000.00 1,200.00

Sub Total B 20,295.00


C. Jumlah Harga Satuan ( A + B ) 37,795.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pasangan 1 Bh Hak Angin
SATUAN : Bh

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN
Hak Angin Bh 1.000 15,000.00 15,000.00

Sub Total A 15,000.00

B. UPAH
1 Mandor OH 0.008 90,000.00 720.00
2 Kepala Tukang OH 0.015 125,000.00 1,875.00
3 Tukang Aluminium OH 0.150 110,000.00 16,500.00
4 Pekerja OH 0.015 80,000.00 1,200.00

Sub Total B 20,295.00


C. Jumlah Harga Satuan ( A + B ) 35,295.00
ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Pasangan 1 Bh Grendel
SATUAN : Bh

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN
Grendel Bh 1.000 12,500.00 12,500.00

Sub Total A 12,500.00

B. UPAH
1 Mandor OH 0.008 90,000.00 720.00
2 Kepala Tukang OH 0.015 125,000.00 1,875.00
3 Tukang Aluminium OH 0.150 110,000.00 16,500.00
4 Pekerja OH 0.015 80,000.00 1,200.00

Sub Total B 20,295.00


C. Jumlah Harga Satuan ( A + B ) 32,795.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pasangan 1 Bh Kunci Tanam
SATUAN : Bh

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN
Kunci Tanam Bh 1.000 135,000.00 135,000.00

Sub Total A 135,000.00

B. UPAH
1 Mandor OH 0.008 90,000.00 720.00
2 Kepala Tukang OH 0.015 125,000.00 1,875.00
3 Tukang Aluminium OH 0.150 110,000.00 16,500.00
4 Pekerja OH 0.015 80,000.00 1,200.00

Sub Total B 20,295.00


C. Jumlah Harga Satuan ( A + B ) 155,295.00
ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Pas. Kaca Bening 5 mm
SATUAN : M2

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN

1 Kaca Bening 5 mm M2 1.100 120,000.00 132,000.00


2 Karet Kaca M 4.000 3,750.00 15,000.00

Sub Total A 147,000.00

B. UPAH
1 Mandor OH 0.001 90,000.00 90.00
2 Kepala Tukang OH 0.015 125,000.00 1,875.00
3 Tukang Aluminium OH 0.150 110,000.00 16,500.00
4 Pekerja OH 0.015 80,000.00 1,200.00

Sub Total B 19,665.00


C. Jumlah Harga Satuan ( A + B ) 166,665.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pas. Kaca Bening 10 mm
SATUAN : M2

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN

1 Kaca Bening 10 mm M2 1.100 765,000.00 841,500.00


2 Karet Kaca M 4.000 3,750.00 15,000.00
3 Perlengkapan 15% x Harga Bahan Ls 1.000 115,312.50 115,312.50

Sub Total A 971,812.50

B. UPAH
1 Mandor OH 0.001 90,000.00 90.00
2 Kepala Tukang OH 0.015 125,000.00 1,875.00
3 Tukang Aluminium OH 0.150 110,000.00 16,500.00
4 Pekerja OH 0.015 80,000.00 1,200.00

Sub Total B 19,665.00


C. Jumlah Harga Satuan ( A + B ) 991,477.50
ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Memasang 1 Bh Door Closer
SATUAN : Bh

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN

1 Door Closer Bh 1.000 225,000.00 225,000.00

Sub Total A 225,000.00

B. UPAH
1 Mandor OH 0.001 90,000.00 90.00
2 Kepala Tukang OH 0.015 125,000.00 1,875.00
3 Tukang Aluminium OH 0.150 110,000.00 16,500.00
4 Pekerja OH 0.001 80,000.00 80.00

Sub Total B 18,545.00


C. Jumlah Harga Satuan ( A + B ) 243,545.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pasang Pintu Double P1
SATUAN : 1 Unit

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN

1 Silmar Aluminium 3x10 M1 10.960 97,696.50 1,070,753.64


2 Kaca Bening T=5 mm M2 2.470 166,665.00 411,729.22
3 Karet Kusen Aluminium M1 20.560 13,021.50 267,722.04
4 Handel Pintu Bh 1.000 390,520.00 390,520.00
5 Door Closer Bh 1.000 243,545.00 243,545.00
6 Engsel Pintu Bh 4.000 42,795.00 171,180.00

C. Jumlah Harga Satuan Pekerjaan 2,555,449.90


ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Pasang Pintu Single
SATUAN : Unit

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN

1 Silmar Aluminium 3x10 M1 5.500 97,696.50 537,330.75


2 Kaca Panassa Blue T=5 mm M2 2.280 166,665.00 379,996.20
3 Karet Kusen Aluminium M1 10.000 13,021.50 130,215.00
4 Handel Pintu Bh 1.000 390,520.00 390,520.00
5 Door Closer Bh 1.000 243,545.00 243,545.00
6 Engsel Pintu Bh 2.000 42,795.00 85,590.00

C. Jumlah Harga Satuan Pekerjaan 1,767,196.95

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pasang Daun Jendela
SATUAN : Unit

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN

1 Silmar Aluminium 3x10 M1 4.000 97,696.50 390,786.00


2 Kaca Panassa Blue T=5 mm M2 0.560 166,665.00 93,332.40
3 Karet Kusen Aluminium M1 3.600 13,021.50 46,877.40
4 Grendel Bh 1.000 32,795.00 32,795.00
5 Hak Angin Bh 2.000 35,295.00 70,590.00
6 Engsel Jendela Bh 2.000 37,795.00 75,590.00

C. Jumlah Harga Satuan Pekerjaan 709,970.80


ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Pasang Ventilasi
SATUAN : Unit

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN

1 Silmar Aluminium 3x10 M1 2.040 97,696.50 199,300.86


2 Kaca Panassa Blue T=5 mm M2 0.200 166,665.00 33,333.00
3 Karet Kusen Aluminium M1 3.600 13,021.50 46,877.40
4 Grendel Bh 1.000 1,875.00 1,875.00
5 Hak Angin Bh 2.000 1,875.00 3,750.00
6 Engsel Jendela Bh 2.000 1,875.00 3,750.00

C. Jumlah Harga Satuan Pekerjaan 288,886.26

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pintu KM/Wc Aluminium
SATUAN : Bh

Harga Satuan Jumlah Harga


No. Uraian Sat Volume
(Rp.) (Rp.)

A. BAHAN
1 Pintu Aluminium Set 1.000 425,000.00 425,000.00

Sub Total A 425,000.00

B. UPAH
1 Mandor OH 0.050 90,000.00 4,500.00
2 Kepala Tukang OH 0.100 125,000.00 12,500.00
3 Tukang Aluminium OH 1.000 110,000.00 110,000.00
4 Pekerja OH 1.000 80,000.00 80,000.00

Sub Total B 207,000.00


C. Jumlah Harga Satuan ( A + B ) 632,000.00
ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Dinding Batu ½ Bata sp. 1 : 3
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Batu Bata Bh 70.0000 750.00 52,500.00
2 Semen @50 Kg Zak 0.2874 75,000.00 21,555.00
3 Pasir Pasang M3 0.0400 175,000.00 7,000.00

Sub Total A 81,055.00

B. UPAH
1 Mandor OH 0.0150 90,000.00 1,350.00
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Batu OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.3000 80,000.00 24,000.00

Sub Total B 37,600.00

C. Jumlah Harga Satuan ( A + B ) 118,655.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Dinding Batu ½ Bata sp. 1 : 5
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Batu Bata Bh 70.0000 750.00 52,500.00
2 Semen @50 Kg Zak 0.1936 75,000.00 14,520.00
3 Pasir Pasang M3 0.0450 175,000.00 7,875.00

Sub Total A 74,895.00

B. UPAH
1 Mandor OH 0.0150 90,000.00 1,350.00
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Batu OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.3000 80,000.00 24,000.00

Sub Total B 37,600.00

C. Jumlah Harga Satuan ( A + B ) 112,495.00


ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Plesteran Dinding Trasraam,Beton + Pondasi sp.1 : 3 Tbl = 15 MM
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Semen @50 Kg Zak 0.1555 75,000.00 11,664.00
2 Pasir Pasang M3 0.0230 175,000.00 4,025.00

Sub Total A 15,689.00

B. UPAH
1 Mandor OH 0.0150 90,000.00 1,350.00
2 Kepala Tukang OH 0.0150 125,000.00 1,875.00
3 Tukang Batu OH 0.1500 110,000.00 16,500.00
4 Pekerja OH 0.3000 80,000.00 24,000.00

Sub Total B 43,725.00

C. Jumlah Harga Satuan ( A + B ) 59,414.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Plesteran Dinding sp. 1 : 5 Tbl = 15 MM
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Semen @50 Kg Zak 0.1037 75,000.00 7,776.00
2 Pasir Pasang M3 0.0260 175,000.00 4,550.00

Sub Total A 12,326.00

B. UPAH
1 Mandor OH 0.0150 90,000.00 1,350.00
2 Kepala Tukang OH 0.0150 125,000.00 1,875.00
3 Tukang Batu OH 0.1500 110,000.00 16,500.00
4 Pekerja OH 0.3000 80,000.00 24,000.00

Sub Total B 43,725.00

C. Jumlah Harga Satuan ( A + B ) 56,051.00


ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Acian Dinding
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Semen @50 Kg Zak 0.0650 75,000.00 4,875.00

Sub Total A 4,875.00

B. UPAH
1 Mandor OH 0.0100 90,000.00 900.00
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Batu OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.2000 80,000.00 16,000.00

Sub Total B 29,150.00

C. Jumlah Harga Satuan ( A + B ) 34,025.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Plesteran Ciprat sp 1 : 2
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Semen @50 Kg Zak 0.0864 75,000.00 6,480.00
2 Pasir Pasang M3 0.0060 175,000.00 1,050.00

Sub Total A 7,530.00

B. UPAH
1 Mandor OH 0.0150 90,000.00 1,350.00
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Batu OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.3000 80,000.00 24,000.00

Sub Total B 37,600.00

C. Jumlah Harga Satuan ( A + B ) 45,130.00


ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : List Tali Air Dinding
SATUAN : M1

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN

Sub Total A -

B. UPAH
1 Mandor OH 0.0020 90,000.00 180.00
2 Kepala Tukang OH 0.0020 125,000.00 250.00
3 Tukang Batu OH 0.0200 110,000.00 2,200.00
4 Pekerja OH 0.1360 80,000.00 10,880.00

Sub Total B 13,510.00

C. Jumlah Harga Satuan ( A + B ) 13,510.00


ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Beton K250
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Semen @50 Kg Zak 7.6800 75,000.00 576,000.00
2 Pasir Beton M3 0.5930 175,000.00 103,775.00
3 Split M3 0.7700 175,000.00 134,750.00
4 Air Ltr 215.0000 25.00 5,375.00

Sub Total A 819,900.00

B. UPAH
1 Mandor OH 0.0830 90,000.00 7,470.00
2 Kepala Tukang OH 0.0280 125,000.00 3,500.00
3 Tukang Batu OH 0.2750 110,000.00 30,250.00
4 Pekerja OH 1.6500 80,000.00 132,000.00

Sub Total B 173,220.00

C. Jumlah Harga Satuan ( A + B ) 993,120.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pekerjaan Pembesian
SATUAN : Kg

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Besi Beton Kg 1.1000 10,400.00 11,440.00
2 Kawat Beton Kg 0.0150 25,000.00 375.00

Sub Total A 11,815.00

B. UPAH
1 Mandor OH 0.0003 90,000.00 27.00
2 Kepala Tukang OH 0.0007 125,000.00 87.50
3 Tukang Besi OH 0.0070 110,000.00 770.00
4 Pekerja OH 0.0070 80,000.00 560.00

Sub Total B 1,444.50

C. Jumlah Harga Satuan ( A + B ) 13,259.50


ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Memasang Bekisting Untuk Pondasi
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Kls III M3 0.0400 2,000,000.00 80,000.00
2 Paku Kg 0.3000 16,500.00 4,950.00
3 Minyak Bekisting Lt 0.1000 25,000.00 2,500.00

Sub Total A 87,450.00

B. UPAH
1 Mandor OH 0.0260 90,000.00 2,340.00
2 Kepala Tukang OH 0.0260 125,000.00 3,250.00
3 Tukang Kayu OH 0.2600 110,000.00 28,600.00
4 Pekerja OH 0.5200 80,000.00 41,600.00

Sub Total B 75,790.00


C. Jumlah Harga Satuan ( A + B ) 163,240.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Memasang Bekisting Untuk Sloef
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Kls III M3 0.0450 2,000,000.00 90,000.00
2 Paku Kg 0.3000 16,500.00 4,950.00
3 Minyak Bekisting Lt 0.1000 25,000.00 2,500.00

Sub Total A 97,450.00

B. UPAH
1 Mandor OH 0.0260 90,000.00 2,340.00
2 Kepala Tukang OH 0.0260 125,000.00 3,250.00
3 Tukang Kayu OH 0.2600 110,000.00 28,600.00
4 Pekerja OH 0.5200 80,000.00 41,600.00

Sub Total B 75,790.00


C. Jumlah Harga Satuan ( A + B ) 173,240.00
ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Memasang Bekisting Untuk Kolom
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Terentang Kls III M3 0.0400 2,000,000.00 80,000.00
2 Kayu Balok Kls III M4 0.0150 2,000,000.00 30,000.00
3 Paku Kg 0.4000 16,500.00 6,600.00
4 Minyak Bekisting Lt 0.2000 25,000.00 5,000.00
5 Plywood T = 9 mm Lbr 0.3500 155,000.00 54,250.00
6 Dolken Kayu Dia. 10-15 Cm Pjg 4 M Btg 2.0000 17,500.00 35,000.00

Sub Total A 210,850.00

B. UPAH
1 Mandor OH 0.0330 90,000.00 2,970.00
2 Kepala Tukang OH 0.0330 125,000.00 4,125.00
3 Tukang Kayu OH 0.3300 110,000.00 36,300.00
4 Pekerja OH 0.6600 80,000.00 52,800.00

Sub Total B 96,195.00


C. Jumlah Harga Satuan ( A + B ) 307,045.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Memasang Bekisting Untuk Balok
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Terentang Kls III M3 0.0400 2,000,000.00 80,000.00
2 Kayu Balok Kls III M4 0.0180 2,000,000.00 36,000.00
3 Paku Kg 0.4000 16,500.00 6,600.00
4 Minyak Bekisting Lt 0.2000 25,000.00 5,000.00
5 Plywood T = 9 mm Lbr 0.3500 155,000.00 54,250.00
6 Dolken Kayu Dia. 10-15 Cm Pjg 4 M Btg 2.0000 17,500.00 35,000.00

Sub Total A 216,850.00

B. UPAH
1 Mandor OH 0.0330 90,000.00 2,970.00
2 Kepala Tukang OH 0.0330 125,000.00 4,125.00
3 Tukang Kayu OH 0.3300 110,000.00 36,300.00
4 Pekerja OH 0.6600 80,000.00 52,800.00

Sub Total B 96,195.00


C. Jumlah Harga Satuan ( A + B ) 313,045.00
ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Memasang Bekisting Untuk Plat Lantai
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Terentang Kls III M3 0.0400 2,000,000.00 80,000.00
2 Kayu Balok Kls III M4 0.0150 2,000,000.00 30,000.00
3 Paku Kg 0.4000 16,500.00 6,600.00
4 Minyak Bekisting Lt 0.2000 25,000.00 5,000.00
5 Plywood T = 9 mm Lbr 0.3500 155,000.00 54,250.00
6 Dolken Kayu Dia. 10-15 Cm Pjg 4 M Btg 6.0000 17,500.00 105,000.00

Sub Total A 280,850.00

B. UPAH
1 Mandor OH 0.0330 90,000.00 2,970.00
2 Kepala Tukang OH 0.0330 125,000.00 4,125.00
3 Tukang Kayu OH 0.3300 110,000.00 36,300.00
4 Pekerja OH 0.6600 80,000.00 52,800.00

Sub Total B 96,195.00


C. Jumlah Harga Satuan ( A + B ) 377,045.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Membongkar Cetakan dan Menyiram Beton
SATUAN : Ls

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN

Sub Total A -

B. UPAH
1 Pekerja OH 4.0000 80,000.00 320,000.00

Sub Total B 320,000.00

C. Jumlah Harga Satuan ( A + B ) 320,000.00


ANALISA HARGA SATUAN
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Membuat Beton Bertulang K 250
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. Pek. Beton M3 1.0000 993,120.00 993,120.00


B. Pek. Pembesian Kg 1.0000 13,259.50 13,259.50
C. Memasang Bekisting Untuk Pondasi M2 1.0000 163,240.00 163,240.00
D. Memasang Bekisting Untuk Sloef M2 1.0000 173,240.00 173,240.00
E. Memasang Bekisting Untuk Kolom M2 1.0000 307,045.00 307,045.00
F. Memasang Bekisting Untuk Balok M2 1.0000 313,045.00 313,045.00
G. Memasang Bekisting Untuk Plat Lantai M2 1.0000 377,045.00 377,045.00
H. Membongkar & Menyiram Beton Ls 1.0000 320,000.00 320,000.00

C. Jumlah Harga Beton / M3 1,313,120.00


Dengan Dengan Jumlah
No. Uraian Sat Memasang Memakai Besi Harga
Bekisting (M2) (Kg)
(Rp.)

1 Beton Pondasi Telapak M³ 0.3000 110.00 2,820,637.00

2 Beton Sloof (15X20) M³ 3.3333 174.00 4,197,739.67

3 Beton Sloof (20X25) M³ 3.3333 215.00 4,741,379.17

4 Beton Kolom (30x30) Cm M³ 4.0000 141.00 3,875,669.50


5 Beton Kolom (20x20) Cm M³ 6.1667 254.00 5,749,346.33

5 Beton Balok (15x30) Cm M³ 9.5556 167.00 5,182,860.94

6 Beton Balok (20x40) Cm M³ 4.6250 115.00 3,639,197.50

7 Beton Kolom Praktis (12x12) M³ 5.5556 248.00 6,307,281.56

8 Beton Balok Latei (12x12) M³ 5.5556 248.00 6,340,614.89

9 Beton Ring Balok (15x25) M³ 4.4444 146.00 4,640,318.11

10 Beton Ring Balok (15x20) M³ 4.4444 174.00 5,011,584.11

11 Beton Plat Lantai M³ 100.00 2,639,070.00


ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Aanstamping Batu Kali / Belah
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Batu Kali Belah (15/20 cm) M3 1.2000 175,000.00 210,000.00

Sub Total A 210,000.00

B. UPAH
1 Mandor OH 0.0390 90,000.00 3,510.00
2 Kepala Tukang OH 0.0390 125,000.00 4,875.00
3 Tukang Batu OH 0.3900 110,000.00 42,900.00
4 Pekerja OH 0.7800 80,000.00 62,400.00

Sub Total B 113,685.00

C. Jumlah Harga Satuan ( A + B ) 323,685.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pasangan Batu kali 1 : 5
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Semen @50 Kg Zak 2.7200 75,000.00 204,000.00
2 Pasir Pasang M3 0.5440 175,000.00 95,200.00
3 Batu Kali Belah (15/20 cm) M3 1.2000 175,000.00 210,000.00

Sub Total A 509,200.00

B. UPAH
1 Mandor OH 0.0750 90,000.00 6,750.00
2 Kepala Tukang OH 0.0750 125,000.00 9,375.00
3 Tukang Batu OH 0.7500 110,000.00 82,500.00
4 Pekerja OH 1.5000 80,000.00 120,000.00

Sub Total B 218,625.00

C. Jumlah Harga Satuan ( A + B ) 727,825.00


ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Galian Tanah Biasa
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN

Sub Total A -

B. UPAH
1 Mandor OH 0.0250 90,000.00 2,250.00
2 Pekerja OH 0.7500 80,000.00 60,000.00

Sub Total B 62,250.00

C. Jumlah Harga ( A + B ) 62,250.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Galian Tanah Telapak
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN

Sub Total A -

B. UPAH
1 Mandor OH 0.0450 90,000.00 4,050.00
2 Pekerja OH 0.9000 80,000.00 72,000.00

Sub Total B 76,050.00


C. Jumlah Harga ( A + B ) 76,050.00
ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Urugan Tanah Kembali
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN

Sub Total A -

B. UPAH
1 Mandor OH 0.0190 90,000.00 1,710.00
2 Pekerja OH 0.1920 80,000.00 15,360.00

Sub Total B 17,070.00

C. Jumlah Harga ( A + B ) 17,070.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Urugan Domato Bawah Lantai
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Domato M3 1.2000 85,000.00 102,000.00

Sub Total A 102,000.00

B. UPAH
1 Mandor OH 0.0250 90,000.00 2,250.00
2 Pekerja OH 0.2500 80,000.00 20,000.00

C. PEMADATAN (Per 20 Cm)


1 Mandor OH 0.0500 90,000.00 4,500.00
2 Pekerja OH 0.5000 80,000.00 40,000.00

Sub Total B 66,750.00

C. Jumlah Harga Satuan ( A + B ) 168,750.00


ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Urugan Pasir Dibawah Lantai & Pondasi
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Pasir Urug M3 1.2000 100,000.00 120,000.00

Sub Total A 120,000.00

B. UPAH
1 Mandor OH 0.0100 90,000.00 900.00
2 Pekerja OH 0.3000 80,000.00 24,000.00

Sub Total B 24,900.00

C. Jumlah Harga Satuan ( A + B ) 144,900.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pas. Cerucut Dolken Kayu/Bambu Dia. 10-15 Cm
SATUAN : Bh

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Dolken Kayu / Bambu 10-15 Cm M1 2.0000 4,375.00 8,750.00

Sub Total A 8,750.00

B. UPAH
1 Mandor OH 0.0100 90,000.00 900.00
2 Pekerja OH 0.1000 80,000.00 8,000.00

Sub Total B 8,900.00


C. Jumlah Harga Satuan ( A + B ) 17,650.00
ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Bongkaran Dinding
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN

Sub Total A -

B. UPAH
1 Mandor OH 0.0150 90,000.00 1,350.00
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Batu OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.2000 80,000.00 16,000.00

Sub Total B 29,600.00

C. Jumlah Harga Satuan ( A + B ) 29,600.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Bongkaran Atap
SATUAN : #REF!

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN

Sub Total A -

B. UPAH
1 Mandor OH 0.0010 90,000.00 90.00
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Batu OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.1600 80,000.00 12,800.00
ANALISA HARGA SATUAN
Sub Total B 25,140.00

C. Jumlah Harga Satuan ( A + B ) 25,140.00


ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Bongkaran Kosen
SATUAN : #REF!

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN

Sub Total A -

B. UPAH
1 Mandor OH 0.0010 90,000.00 90.00
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Batu OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.2500 80,000.00 20,000.00

Sub Total B 32,340.00

C. Jumlah Harga Satuan ( A + B ) 32,340.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Bongkaran Pondasi
SATUAN : #REF!

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN

Sub Total A -

B. UPAH
1 Mandor OH 0.0750 90,000.00 6,750.00
2 Kepala Tukang OH 0.0600 125,000.00 7,500.00
3 Tukang Batu OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.0500 80,000.00 4,000.00

Sub Total B 29,250.00


ANALISA HARGA SATUAN
C. Jumlah Harga Satuan ( A + B ) 29,250.00
ANALISA HARGA SATUAN

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Bongkaran Bangunan Lama
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN

Sub Total A -

B. UPAH
1 Mandor OH 0.0150 90,000.00 1,350.00
2 Kepala Tukang OH 0.0100 125,000.00 1,250.00
3 Tukang Batu OH 0.1000 110,000.00 11,000.00
4 Pekerja OH 0.4000 80,000.00 32,000.00

Sub Total B 45,600.00

C. Jumlah Harga Satuan ( A + B ) 45,600.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Asbuild Drawing
SATUAN : Ls

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kertas A3 Rim 3.0000 65,000.00 195,000.00
2 Tinta Printer Dos 2.0000 37,500.00 75,000.00
3 foto Copy Dokumen Lbr 35.0000 1,500.00 52,500.00

Sub Total A 322,500.00

B. UPAH
1 Operator Komputer Hari 12.0000 80,000.00 960,000.00

C ALAT
1 Komputer Hari 12.0000 45,000.00 540,000.00

Sub Total B 1,500,000.00


D. Jumlah Harga Satuan ( A + B ) 1,822,500.00
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Pembersihan lapangan
SATUAN : Ls

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN

Sub Total A -

B. UPAH
1 Pekerja OH 1.1500 80,000.00 92,000.00
2 Mandor OH 15.0000 90,000.00 1,350,000.00

Sub Total B 1,442,000.00


D. Jumlah Harga Satuan ( A + B ) 1,442,000.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pengukuran & Pasang Bowplank
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Papan Bouwplank Kayu Kls III M3 0.3200 2,000,000.00 640,000.00
2 Balok Bouwplank Kayu Kls III M3 0.2500 2,000,000.00 500,000.00
3 Paku Kg 0.9000 16,500.00 14,850.00

Sub Total A 1,154,850.00

B. UPAH
1 Mandor OH 0.1000 90,000.00 9,000.00
2 Kepala Tukang OH 125,000.00 -
3 Tukang Batu OH 1.0000 110,000.00 110,000.00
4 Pekerja OH 1.0000 80,000.00 80,000.00

Sub Total B 199,000.00


C. Jumlah Harga Satuan ( A + B ) 1,353,850.00
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Alat Bantu / Steling / Perancah
SATUAN : Ls

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu bulat Kayu Kls III M3 0.6700 2,000,000.00 1,340,000.00
2 Papan alas Kayu Kls III M3 0.5500 2,000,000.00 1,100,000.00
3 Paku Kg 0.5000 16,500.00 8,250.00

Sub Total A 2,448,250.00

B. UPAH
1 Mandor OH 0.1000 90,000.00 9,000.00
2 Kepala Tukang OH 0.0500 125,000.00 6,250.00
3 Tukang Batu OH 0.5000 110,000.00 55,000.00
4 Pekerja OH 2.0000 80,000.00 160,000.00

Sub Total B 230,250.00


C. Jumlah Harga Satuan ( A + B ) 2,678,500.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Air Kerja
SATUAN : Ls

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Tangki Air Hari 40.0000 50,000.00 2,000,000.00
2 pompa Air Jam 30.0000 15,000.00 450,000.00

Sub Total A 2,450,000.00

B. UPAH
4 Pekerja OH 15.1400 80,000.00 1,211,200.00

Sub Total B 1,211,200.00


C. Jumlah Harga Satuan ( A + B ) 3,661,200.00
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : pembersihan Sisa-sia Material
SATUAN : Ls

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Dump Truk Hari 3.0000 700,000.00 2,100,000.00

Sub Total A 2,100,000.00

B. UPAH
4 Pekerja OH 2.0000 80,000.00 160,000.00

Sub Total B 160,000.00


C. Jumlah Harga Satuan ( A + B ) 2,260,000.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Administrasi & Dokumentasi
SATUAN : Ls

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kertas A4 Rim 3.0000 40,000.00 120,000.00
2 Kertas A3 Rim 1.0000 65,000.00 65,000.00
3 Tinta Printer Dos 2.0000 37,500.00 75,000.00
4 Foto Dokumentasi Lbr 35.0000 1,500.00 52,500.00
5 Foto Copy Laporan Lbr 666.0000 250.00 166,500.00

Sub Total A 479,000.00

B. UPAH
1 Kameraman OH 1.0000 110,000.00 110,000.00
2 Pimpinan Teknik OB 1.0000 1,250,000.00 1,250,000.00

Sub Total B 1,360,000.00


C. Jumlah Harga Satuan ( A + B ) 1,839,000.00
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Pas. Huruf Stenlees
SATUAN : Ls

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Huruf Stenlees Bh 1.0000 325,000.00 325,000.00

Sub Total A 325,000.00

B. UPAH
1 Upah Pemasangan 15% dr Harga Ls 1.0000 - 48,750.00

Sub Total B 48,750.00


C. Jumlah Harga Satuan ( A + B ) 373,750.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Pas. Logo
SATUAN : Ls

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Logo Bh 1.0000 4,500,000.00 4,500,000.00

Sub Total A 4,500,000.00

B. UPAH
1 Upah Pemasangan 15% dr Harga Ls 1.0000 - 675,000.00

Sub Total B 675,000.00


C. Jumlah Harga Satuan ( A + B ) 5,175,000.00
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
JENIS PEKERJAAN : Direksi Keet

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Klas III M3 0.0900 2,000,000.00 180,000.00
2 Seng Gelombang Lbr 1.0000 39,000.00 39,000.00
3 Paku Seng Kg 0.0400 25,000.00 1,000.00
4 Paku Kg 0.4000 16,500.00 6,600.00

B. UPAH
1 Mandor OH 0.0500 90,000.00 4,500.00
Kepala Tukang OH 0.0800 125,000.00 10,000.00
Tukang OH 0.4500 110,000.00 49,500.00
2 Pekerja OH 0.7500 80,000.00 60,000.00

C. Jumlah Harga ( A + B ) 350,600.00

PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU


JENIS PEKERJAAN : Papan Nama Proyek

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 MultiPleks Lbr 0.2500 300,000.00 75,000.00
2 Kayu Klas II M3 0.0568 2,800,000.00 159,040.00
3 Cat Minyak Kg 0.3400 52,000.00 17,680.00
4 Paku Kg 0.4920 16,500.00 8,118.00

B. UPAH
1 Mandor OH 0.1500 90,000.00 13,500.00
2 Pekerja OH 1.0000 80,000.00 80,000.00

C. Jumlah Harga ( A + B ) 353,338.00


DAFTAR HARGA SATUAN JADI

SATUAN KERJA : 0
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
LOKASI : KABUPATEN BONE BOLANGO
TAHUN ANGGARAN : 2016

HARGA SATUAN
NO URAIAN PEKERJAAN SAT
(Rp)

1. Pek. Galian Tanah Pondasi Jalur M³ 62,250.00


2. Pek. Galian Tanah Pondasi Telapak M³ 76,050.00
3. Pek. Urugan Tanah Kembali M³ 17,070.00
4. Pek. Pasir Alas Bwh Lantai & Pondasi teras M³ 144,900.00
5. Pek. Urugan Pasir Domato Bawah Lantai & Pemadatan M³ 168,750.00
6. Pas. Aanstamping Batu Kali M³ 323,685.00
7. Pek. Pondasi Batu Kali Sp. 1:5 M³ 727,825.00
8. Pek. Lantai Kerja Pondasi Telapak M³ 740,075.00
9. Pek. Cor Beton Bertulang Telapak M³ 2,820,637.00
10. Pek. Cor Beton Bertulang Sloef (15/20) Cm M³ 4,197,739.67
11. Pek. Cor Beton Bertulang Sloef (20/25) Cm M³ 4,741,379.17
12. Pek. Cor Beton Bertulang kolom (30x30) Cm M³ 3,875,669.50
13. Pek. Cor Beton Bertulang kolom (20x20) Cm M³ 5,749,346.33
14. Pek. Cor Beton Bertulang Kolom Praktis (12x12) Cm M³ 6,307,281.56
15. Pek. Cor Beton Bertulang Balok Latey (12x12) M³ 6,340,614.89
16. Pek. Cor Beton Bertulang Balok (20x40) Cm M³ 3,639,197.50
17. Pek. Cor Beton Bertulang Balok (15x25) Cm M³ 4,640,318.11
18. Pek. Cor Beton Bertulang Balok (15x20) Cm M³ 5,011,584.11
19. Pas. Dinding Batu ½ Bata sp. 1 : 3 M² 118,655.00
20. Pas. Dinding Batu ½ Bata sp. 1 : 5 M² 112,495.00
21. Pek. Plesteran Dinding,Beton, dan Pondasi sp. 1 : 3 M² 59,414.00
22. Pek. Plesteran Dinding sp. 1 : 5 M² 56,051.00
23. Pek. Acian Semen M² 34,025.00
24. Pek. Kosen Kayu Kls I M³ 103,196.50
25. Pek. Daun PintuPanel Kayu Kls II M² 504,750.00
26. Pek. Daun Pintu Panel Kayu Kls II Belakang lapis Tripleks Aluminium M² 547,782.79
27. Pek. Daun Ventilasi Kaca 5 mm Panel Kayu Kls II M² 466,400.00
28. Pek. Teralis Pengaman Ventilasi M² 123,240.00
29. Pas. Pintu Harmonika M² 848,505.00
30. Pas. Engsel Pintu 4" Bh 46,642.50
31. Pas. Engse Jendela 3" Bh 32,642.50
32. Pas. Kunci Pintu 2 Slaag Bh 171,047.50
33. Pas. Tarikan Jendela Bh 26,642.50
34. Pas. Grendel Jendela Bh 24,642.50
35. Pas, Hak Angin Jendela Bh 26,642.50
36. Pas. Expanyolet Bh 60,142.50
HARGA SATUAN
NO URAIAN PEKERJAAN SAT
(Rp)

37. Pek. Rangka Plafond Hollow Aluminium M² 83,575.00


38. Pas. Plafond Gypsum Board 9 mm M² 45,429.80
39. Pek. Cor Beton Tumbuk Lantai Sp 1:3:5 M³ 740,075.00
40. Pas. Lantai keramik 40x40 Cm Setara Kw1 M² 137,870.00
41. Pas. Plint Lantai Keramik 10x40 Cm Setara Kw1 M¹ 51,042.22
42. Pas. Lantai Keramik Anti Slip 25x25 Cm Setara Kw1 M² 144,485.00
43. Pas. Dinding Keramik 25x40 Cm Setara Kw1 M² 141,985.00
44. Pas. Pipa PVC (AW). Dia 4" + Accessories (Air kotor) M¹ 59,424.00
45. Pas. Pipa PVC (AW). Dia 2" + Accessories (Air kotor) M¹ 29,731.75
46. Pas. Pipa PE Dia 1/2" + Accessories (Air bersih) M¹ 21,242.00
47. Pas. Mata Kran Air 1/2" Bh 53,625.00
48. Pas. Floor Drain Bh 46,500.00
49. Pas. Kloset Jongkok Setara Toto Bh 528,900.00
50. Pek. Septick Tank Bh 5,037,847.26
51. Pek. Rangka Atap Baja Ringan setara taso & Genteng Metal M² 306,977.78
52. Pek. Bubungan Genteng Metal M¹ 73,190.00
53. Pek. Listplank GRC M¹ 76,640.00
54. Pas. Jurai Dalam M¹ 53,170.00
55. Pas. MCB 3 Phase + Panel Box Bh 970,937.50
56. Pas. Instalasi Listrik (Lengkap Acc. + Kabel Listrik) Ttk 130,395.00
57. Pas. Saklar Ganda Bh 45,250.00
58. Pas. Stop Kontak Bh 41,250.00
59. Pas.Lampu Armateure RMI 2 x18 W Bh 491,250.00
60. Pas. Lampu SL 8 Watt Bh 53,750.00
61. Pek. Pengecatan Dinding & Beton M² 32,604.00
62. Pek. Pengecatan Plafond M² 31,210.00
63. Pek. Pengecatan Kosen, Daun Pintu & Ventilasi M² 35,266.00

Gorontalo, Juni 2015


Dibuat Oleh :
-
-

-
Direktur
ENGINEERING ESTIMATE
(EE)
SATUAN KERJA : 0
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
LOKASI : KABUPATEN BONE BOLANGO
T. A : 2016

HARGA JUMLAH HARGA


NO URAIAN PEKERJAAN SAT VOL SATUAN
(Rp) (Rp)
A. PEKERJAAN PERSIAPAN 4,450,000.00
1. Pengukuran & Pasang Bowplank Ls 1.00 500,000.00 500,000.00
2. Papan Nama Proyek Bh 1.00 250,000.00 250,000.00
3. Alat Bantu / Steling / Perancah Ls 1.00 850,000.00 850,000.00
4. Direksi Keet Ls 1.00 2,000,000.00 2,000,000.00
5. Penggunaan Air Kerja dan listrik kerja Ls 1.00 850,000.00 850,000.00

B. PEKERJAAN GEDUNG WAREHOUSE

I. Pekerjaan Tanah 29,387,848.31


1. Pek. Galian Tanah Pondasi Jalur M³ 91.53 62,250.00 5,698,022.63
2. Pek. Galian Tanah Pondasi Telapak M³ 9.22 76,050.00 700,876.80
3. Pek. Urugan Tanah Kembali M³ 25.19 17,070.00 429,952.76
4. Pek. Pasir Alas Bwh Lantai & Pondasi teras M³ 20.91 144,900.00 3,030,402.38
5. Pek. Urugan Pasir Domato Bawah Lantai & Pemadatan M³ 115.73 168,750.00 19,528,593.75
II. Pekerjaan Pondasi 57,752,272.43
1. Pas. Aanstamping Batu Kali M³ 20.74 323,685.00 6,714,117.03
2. Pek. Pondasi Batu Kali Sp. 1:5 M³ 69.73 727,825.00 50,753,966.59
3. Pek. Lantai Kerja Pondasi Telapak M³ 0.38 740,075.00 284,188.80
III. Pekerjaan Beton 121,122,532.29
1. Pek. Cor Beton Bertulang Telapak M³ 1.92 2,820,637.00 5,415,623.04
2. Pek. Cor Beton Bertulang Sloef (15/20) Cm M³ 0.62 4,197,739.67 2,613,092.94
3. Pek. Cor Beton Bertulang Sloef (20/25) Cm M³ 5.40 4,741,379.17 25,579,740.60
4. Pek. Cor Beton Bertulang kolom (30x30) Cm M³ 9.94 3,875,669.50 38,508,652.15
5. Pek. Cor Beton Bertulang kolom (20x20) Cm M³ 1.74 5,749,346.33 10,003,862.62
6. Pek. Cor Beton Bertulang Kolom Praktis (12x12) Cm M³ 0.86 6,307,281.56 5,418,585.58
7. Pek. Cor Beton Bertulang Balok Latey (12x12) M³ 0.84 6,340,614.89 5,302,985.94
8. Pek. Cor Beton Bertulang Balok (20x40) Cm M³ 0.91 3,639,197.50 3,318,948.12
9. Pek. Cor Beton Bertulang Balok (15x30) Cm M³ 0.34 5,182,860.94 1,749,215.57
10. Pek. Cor Beton Bertulang Balok (15x25) Cm M³ 4.30 4,640,318.11 19,941,767.08
11. Pek. Cor Beton Bertulang Balok (15x20) Cm M³ 0.65 5,011,584.11 3,270,058.63
IV. Pekerjaan Dinding & Plesteran 131,165,035.70
1. Pas. Dinding Batu ½ Bata sp. 1 : 3 M² 28.53 118,655.00 3,385,227.15
2. Pas. Dinding Batu ½ Bata sp. 1 : 5 M² 355.86 112,495.00 40,032,695.69
3. Pek. Plesteran Dinding,Beton, dan Pondasi sp. 1 : 3 M² 252.98 59,414.00 15,030,339.83
4. Pek. Plesteran Dinding sp. 1 : 5 M² 711.72 56,051.00 39,892,841.92
5. Pek. Acian Semen M² 964.70 34,025.00 32,823,931.11

V. Pekerjaan Pintu / Jendela 34,646,484.79


1. Pek. Kosen Kayu Kls I M³ 0.60 103,196.50 62,124.29
2. Pek. Daun PintuPanel Kayu Kls II M² 10.71 504,750.00 5,405,872.50
3. Pek. Daun Pintu Panel Kayu Kls II Belakang lapis Tripleks Aluminium M² 1.47 547,782.79 805,240.70
4. Pek. Daun Ventilasi Kaca 5 mm Panel Kayu Kls II M² 1.80 466,400.00 839,520.00
5. Pek. Teralis Pengaman Ventilasi M² 6.72 123,240.00 828,172.80
6. Pas. Pintu Harmonika M² 27.90 848,505.00 23,673,289.50
7. Pas. Engsel Pintu 4" Bh 16.00 46,642.50 746,280.00
8. Pas. Engse Jendela 3" Bh 12.00 32,642.50 391,710.00
9. Pas. Kunci Pintu 2 Slaag Bh 6.00 171,047.50 1,026,285.00
10. Pas. Tarikan Jendela Bh 6.00 26,642.50 159,855.00
11. Pas. Grendel Jendela Bh 6.00 24,642.50 147,855.00
12. Pas, Hak Angin Jendela Bh 12.00 26,642.50 319,710.00
13. Pas. Expanyolet Bh 4.00 60,142.50 240,570.00
HARGA JUMLAH HARGA
NO URAIAN PEKERJAAN SAT VOL SATUAN
(Rp) (Rp)
VI. Pekerjaan Plafon 41,179,871.96
1. Pek. Rangka Plafond Hollow Aluminium M² 265.93 83,575.00 22,225,099.75
2. Pas. Plafond Gypsum Board 9 mm M² 265.93 45,429.80 12,081,146.71
3. Pas. Listprofil Gypsum 9 cm M¹ 166.15 41,370.00 6,873,625.50

VII. Pekerjaan Lantai & Keramik 71,886,152.32


1. Pek. Cor Beton Tumbuk Lantai Sp 1:3:5 M³ 10.62 740,075.00 7,857,820.32
2. Pek. Cor Beton Bertulang Ad. 1 : 2 : 3 T = 15 Cm M³ 18.80 2,639,070.00 49,609,237.86
3. Pas. Lantai keramik 40x40 Cm Setara Kw1 M² 69.23 137,870.00 9,544,740.10
4. Pas. Plint Lantai Keramik 10x40 Cm Setara Kw1 M¹ 67.80 51,042.22 3,460,662.84
5. Pas. Lantai Keramik Anti Slip 25x25 Cm Setara Kw1 M² 2.08 144,485.00 300,528.80
6. Pas. Dinding Keramik 25x40 Cm Setara Kw1 M² 7.84 141,985.00 1,113,162.40

VIII. Pekerjaan Jaringan Sanitasi Air Bersih / Kotor 6,230,595.95


1. Pas. Pipa PVC (AW). Dia 4" + Accessories (Air kotor) M¹ 4.00 59,424.00 237,696.00
2. Pas. Pipa PVC (AW). Dia 2" + Accessories (Air kotor) M¹ 5.25 29,731.75 156,091.69
3. Pas. Pipa PE Dia 1/2" + Accessories (Air bersih) M¹ 8.00 21,242.00 169,936.00
4. Pas. Mata Kran Air 1/2" Bh 1.00 53,625.00 53,625.00
5. Pas. Floor Drain Bh 1.00 46,500.00 46,500.00
6. Pas. Kloset Jongkok Setara Toto Bh 1.00 528,900.00 528,900.00
7. Pek. Septick Tank Bh 1.00 5,037,847.26 5,037,847.26

IX. Pekerjaan Atap & Penutup 163,797,605.75


1. Pek. Rangka Atap Baja Ringan setara taso & Genteng Metal M² 468.63 306,977.78 143,857,461.11
2. Pek. Bubungan Genteng Metal M¹ 85.85 73,190.00 6,283,361.50
3. Pek. Listplank GRC M¹ 154.50 76,640.00 11,840,880.00
4. Pas. Jurai Dalam M¹ 20.00 53,170.00 1,063,400.00
5. Pek. Grc Ventilasi Atap + Rangka M² 12.32 61,079.80 752,503.14

X. Pekerjaan Instalasi Listrik 23,842,542.50


1. Pas. MCB 3 Phase + Panel Box Bh 1.00 970,937.50 970,937.50
2. Pas. Instalasi Listrik (Lengkap Acc. + Kabel Listrik) Ttk 49.00 130,395.00 6,389,355.00
3. Pas. Saklar Ganda Bh 9.00 45,250.00 407,250.00
4. Pas. Stop Kontak Bh 6.00 41,250.00 247,500.00
5. Pas.Lampu Armateure RMI 2 x18 W Bh 32.00 491,250.00 15,720,000.00
6. Pas. Lampu SL 8 Watt Bh 2.00 53,750.00 107,500.00

XI. Pekerjaan Finishing 41,318,224.88


1. Pek. Pengecatan Dinding & Beton M² 964.70 32,604.00 31,453,091.84
2. Pek. Pengecatan Plafond M² 265.93 31,210.00 8,299,675.30
3. Pek. Pengecatan Kosen, Daun Pintu & Ventilasi M² 44.39 35,266.00 1,565,457.74

C. PEKERJAAN LAIN-LAIN 500,000.00

1. Administrasi / Dokumentasi Ls 1.00 500,000.00 500,000.00

Gorontalo, Juni 2015


Dibuat Oleh :
-
-

Ir. HELMI LATADA


Direktur
REKAPITULASI
ENGINEER ESTIMATE (EE)

SATUAN KERJA :
PEKERJAAN : JALAN RABAT BETON KECAMATAN PINOGU
LOKASI : KABUPATEN BONE BOLANGO
THN. ANGGARAN : 2016

NO KOMPONEN PEKERJAAN JUMLAH

A. PEKERJAAN PERSIAPAN Rp. 4,450,000.00

B. PEKERJAAN GEDUNG WAREHOUSE

I. Pekerjaan Tanah Rp. 29,387,848.31

II. Pekerjaan Pondasi Rp. 57,752,272.43

III. Pekerjaan Beton Rp. 121,122,532.29

IV. Pekerjaan Dinding & Plesteran Rp. 131,165,035.70

V. Pekerjaan Pintu / Jendela Rp. 34,646,484.79

VI. Pekerjaan Plafon Rp. 41,179,871.96

VII. Pekerjaan Lantai & Keramik Rp. 71,886,152.32

VIII. Pekerjaan Jaringan Sanitasi Air Bersih / Kotor Rp. 6,230,595.95

IX. Pekerjaan Atap & Penutup Rp. 163,797,605.75

X. Pekerjaan Instalasi Listrik Rp. 23,842,542.50

XI. Pekerjaan Finishing Rp. 41,318,224.88

C. PEKERJAAN LAIN-LAIN Rp. 500,000.00

JUMLAH Rp. 727,279,166.88

PAJAK PERTAMBAHAN NILAI (PPN) 10% Rp. 72,727,916.69

TOTAL Rp. 800,007,083.57

DIBULATKAN Rp. 800,000,000.00

Terbilang : Delapan Ratus Juta Rupiah

Gorontalo, Juni 2015


Mengetahui/Menyetujui : Dibuat Oleh :
PENGGUNA ANGGARAN

NIP. 196004051988037002 Direktur

`
Hitungan Volume gedung Kantor KSOP

NO URAIAN PEKERJAAN PJG LBR LBR RT2 TGGI JMLH VOLUME


Galian Tanah Biasa 121.15 0.90 0.70 76.32
26.00 0.90 0.65 15.21

Total 91.53
Galian Telapak 0.80 0.80 1.20 12.00 9.22
-
Total Galian 9.22

Cor. Lantai Kerja 0.80 0.80 0.05 12.00 0.38


-
Total Galian 0.38

Cor. Telapak 0.80 0.80 0.25 12.00 1.92


-
Total Galian 1.92

Urugan Tanah Kembali 22.88


Urugan Tanah Bwh Lantai 5.70 3.80 0.50 2.00 21.66
5.70 4.80 0.50 1.00 13.68
1.55 1.30 0.50 2.00 2.02
6.00 2.75 0.50 1.00 8.25
3.80 2.75 0.50 2.00 10.45
7.80 5.85 0.50 2.00 45.63
4.80 5.85 0.50 1.00 14.04

Total 115.73
Urugan Pasir Bwh Lantai & P 5.70 3.80 0.10 2.00 2.17
5.70 4.80 0.10 1.00 2.74
1.55 1.30 0.10 2.00 0.20
6.00 2.75 0.10 1.00 1.65
3.80 2.75 0.10 2.00 1.05
7.80 5.85 0.10 2.00 4.56
4.80 5.85 0.10 1.00 2.81

127.65 0.90 0.05 5.74


0.90 0.05 -
Total Uruga Pasir 20.91
Pas. Batu Kosong 127.65 0.90 0.15 17.23
26.00 0.90 0.15 3.51
0.90 -
Total Pas. Batu Kosong 20.74
Pek. Pondasi 127.65 0.50 0.95 1.00 60.63
26.00 0.50 0.70 1.00 9.10
-
Total Pas. Batu Pondasi 69.73
Pas. Rolag Bata -

Sloef 20/25 107.90 0.20 0.25 5.40


Sloef 15/20 20.75 0.15 0.20 0.62
- 0.15 -
Total cor Sloef
Kolom praktis 11x11 5.35 0.11 0.11 10.00 0.65
1.75 0.11 0.11 10.00 0.21
Total Klom Praktis 0.86
Kolom Utama 9.20 0.30 0.30 12.00 9.94
Kolom 20x20 7.25 0.20 0.20 6.00 1.74

Balok 20/40 11.40 0.20 0.40 0.91


Rb 15/25 114.60 0.15 0.25 4.30
Ring Balok 15/20 21.75 0.15 0.20 0.65
Balok 15/30 3.75 0.15 0.30 2.00 0.34

Balok Latey 11/11 69.12 0.11 0.11 0.84

Plat leufel 8.80 0.75 0.08 0.53


3.65 1.00 0.08 0.29

Pas. Batu Bata Trasram 47.55 0.60 28.53


0.60 -

Total Pas. Sp. 1:3 28.53


Total Pas. Dinding 1 Bata Sp 69.12 4.60 317.95
22.60 1.75 39.55
2.33 2.00 2.00 9.30
366.80

Kurang Luas Kusen 1.55 0.70 8.00 8.68


2.15 1.30 2.00 5.59
2.15 1.00 2.00 4.30
2.15 0.80 1.00 1.72

Total Luas Kosen 20.29


Pas. Batu Bata Sp. 1:5 366.80 20.29 355.86

Total Penebalan Sp.1:5 -


Pek. Plesteran Kolom 7.55 0.90 6.00 40.77
5.60 0.90 6.00 30.24
5.60 0.60 6.00 20.16
Plesteran Pondasi 74.00 0.46 1.00 34.04
Plesteran Sloef 74.00 0.25 1.00 18.50
Plesteran Balok Laty 69.12 0.22 1.00 15.21
Plesteran Balok 74.00 0.50 1.00 37.00

Total Plester Kolom dan Balok 195.92

Kosen Kayu 5.30 2.00 10.60


5.00 3.00 15.00
4.80 1.00 4.80
5.10 8.00 40.80
4.30 2.00 8.60
3.10 2.00 6.20

total Pjg Kosen 86.00

Volume Kosen 86.00 0.05 0.14 0.60

Daun Pintu Panel Kayu 2.10 1.20 2.00 5.04


2.10 0.90 3.00 5.67
10.71
Daun Pintu Km/Wc 2.10 0.70 1.00 1.47

Daun Ventilasi 0.50 0.50 2.00 2.00 1.00


0.50 0.80 1.00 2.00 0.80
1.80

Teralis 0.70 0.60 2.00 8.00 6.72

Pek. Rangka Plafond 5.70 3.80 2.00 1.00 43.32


5.70 4.80 1.00 1.00 27.36
1.55 1.30 2.00 1.00 4.03
6.00 2.75 1.00 1.00 16.50
3.80 2.75 2.00 1.00 20.90
7.80 5.85 2.00 1.00 91.26
4.80 5.85 1.00 1.00 28.08
43.10 0.80 1.00 1.00 34.48
Total 265.93
Cor Lantai Beton Tumbuk 5.70 3.80 0.07 2.00 3.03
5.70 4.80 0.07 -
1.55 1.30 0.07 2.00 0.28
6.00 2.75 0.07 1.00 1.16
3.80 2.75 0.07 2.00 1.46
7.80 5.85 0.07 -
4.80 5.85 0.07 1.00 1.97
21.00 1.85 0.07 1.00 2.72
Total Cor Lantai Beton tumbuk 10.62
Cor Tulangan 7.80 5.85 0.10 2.00 9.13
5.70 4.80 0.10 2.00 5.47
21.00 2.00 0.10 1.00 4.20
18.80

Floor Hardener 5.70 4.80 1.00 2.00 54.72


5.70 4.80 1.00 2.00 54.72
21.00 2.00 1.00 1.00 42.00
21.00 0.85 1.00 1.00 17.85
169.29

Pas. Keramik 60x60 3.85 5.65 1.00 2.00 43.51


6.10 2.75 1.00 - -
1.75 1.30 1.00 2.00 4.55
3.85 2.75 1.00 2.00 21.18

Total Keramik 69.23

Kurang Keramik Km/WC 1.60 1.30 1.00 2.08


Total 2.08

Keramik 20x25 1.6 1.6 2 1 5.12


1.3 1.6 2 1 4.16
Total 9.28
Kurang Luas Kusen 0.8 1.8 1 1.44
Total Keramik Dinding 7.84

Rangka Atap Baja Ringan 6.875 5.15 4 141.625


6.55 5 4 131
10.5 4 1 42
15.4 5 2 154

Total 468.625
List Plank 154.5
Talang 20
Bumbungan 85.85