DAFTAR UPAH
1 2 3 4 5
1 Pekerja OH 100,000.00
2 Tukang Batu OH 120,000.00
3 Tukang Kayu OH 120,000.00
4 Tukang Besi OH 120,000.00
5 Tukang Las OH 120,000.00
6 Tukang Cat OH 120,000.00
7 Tukang Pipa OH 120,000.00
8 Kepala Tukang OH 150,000.00
9 Mandor OH 150,000.00
10 Operator Alat Berat OH 94,500.00
11 Pembantu Operator Alat Berat OH 70,700.00
1 2 3 4 5
I BAHAN PASANGAN
1 Pasir Urug (PU) M3 145,000.00
2 Pasir Pasang (PP) M3 145,000.00
3 Pasir Beton (PB) M3 173,000.00
4 Pasir Kuarsa M3 173,000.00
5 Kerikil (KR) M3 191,300.00
6 Sirtu M3 200,000.00
7 Batu Belah (gunung) 15cm/20 cm M3 335,000.00
8 Batu sungai (mangga) M3 290,000.00
9 Portland Cement (PC) Kg 1,550.00
10 Semen Warna Kg 3,100.00
11 Cornite Compound Jayaboard Zak 103,000.00
12 Bata Merah (Ukuran Sedang ) Buah 600.00
13 Kerawang (Roster semen)20x20 cm Buah 25,100.00
14 Kerawang (Roster semen)40x40 cm Buah 50,100.00
15 Rumput Gajah Mini M2 46,500.00
16 Rumput Biasa M2 18,500.00
17 Tanah Hitam M3 175,000.00
19 Urugan Biasa M3 66,000.00
20 Conblock Segi 6 Tebal 8 CM Bh 2,100.00
21 Conblock Segi 4 Tebal 8 CM Bh 2,100.00
22 Paving Block Segi 6 Tebal 6 CM Bh 1,250.00
23 Paving Block Segi 4 Tebal 6 CM Bh 1,250.00
24 Glass Block T= 6 cm Bh 25,200.00
25 Buis Beton Dia 20cm P= 90 Cm (Lingkaran Dalam) Bh 162,000.00
26 Buis Beton Dia 40cm P = 90 Cm (Lingkaran Dalam) Bh 255,000.00
27 Buis Beton Dia 60cm P= 90 Cm (Lingkaran Dalam) Bh 335,000.00
28 Buis Beton Dia 80cm P= 90 Cm (Lingkaran Dalam) Bh 495,000.00
29 Buis Beton Dia 100cm P = 90 Cm (Lingkaran Dalam) Bh 700,000.00
30 Batu Split / Pecah M3 345,000.00
31 Bata Beton Ringan Uk. ( 10 x20 x 40 ) CM Buah 10,300.00
32 Batu Tempel Uk. 20 x 20 CM Buah 5,100.00
NO. JENIS BAHAN SATUAN HARGA SATUAN KET.
1 2 3 4 5
33 Batu Tempel Uk. 20 x 40 CM Buah 12,600.00
34 Kanstin Beton Ukuran Sedang (20x25x15) CM Unit 13,000.00
35 Conwood untuk Dinding Tebal 11 MM M2 452,000.00
36 Conwood untuk Lantai Tebal 25 MM M2 833,000.00
II BAHAN KAYU
1 Kayu Kelas I (Ex: Kayu Tembusu, Kayu Kulim) M3 5,585,000.00
2 Kayu Kelas II (Ex: Kayu Meranti) M3 2,695,000.00
3 Kayu Kelas III (Ex: Kayu Campuran) M3 2,050,000.00
4 Kayu List Profil siku2" M' 2,700.00
5 Kayu List Profil 0.8x3" M' 3,200.00
6 Papan 2 x 20 CM Kayu Kelas II M3 2,275,000.00
7 Kayu Cerocok dia. 10 - 15 cm Batang 40,250.00
8 Dolken Kayu Galam, Ø (8-10)Cm,Panjang 4 M Batang 7,000.00
9 Kayu Bakar ( Non Kelas ) M3 315,000.00
10 Papan Piri - piri (Siap Ketam 3 sisi) M3 2,900,000.00
11 Papan Lebah Bergayut M' 166,000.00
12 Singap Ukir kayu (Ex. Kayu Meranti) M2 913,000.00
13 Singap Ukir GRC M2 863,000.00
14 Selembayung GRC Lebar 30 cm Pasang 406,000.00
15 Selembayung kayu lebar 30 cm Pasang 256,000.00
16 Sayap layang-layang lebar 30 cm Pasang 256,000.00
17 Lisplank GRC Lebar 20 CM M1 70,000.00
IV BAHAN PAKU
1 Paku 1 Cm - 2,5 Cm Kg 28,550.00
2 Paku 5 Cm - 12 Cm Kg 28,550.00
3 Paku Skrup 1-5 CM Kg 40,200.00
4 Paku Skrup 5-10 Cm Kg 38,200.00
5 Paku Skrup 10-15 Cm Kg 35,200.00
6 Paku Asbes Kg 20,200.00
7 Paku Atap Genteng Metal Kg 24,200.00
8 Paku Atap Seng Gelombang Kg 20,200.00
9 Skrup Fixer Buah 300.00
10 Skrup / Paku Atap dan Genteng Bitumen Monolayer Buah 1,200.00
11 DynaBolt Rangka Baja Ringan Buah 1,100.00
V BAHAN ALLUMUNIUM
1 Profil Allumunium "T" M' 54,000.00
2 Kusen Alumunium 3'' M' 54,000.00
NO. JENIS BAHAN SATUAN HARGA SATUAN KET.
1 2 3 4 5
3 Rangka Jendela Almunium M' 54,000.00
4 Rangka Pintu Almunium M' 132,000.00
VI BAHAN LANTAI
1 Granit Ukuran ( 60 x 60 ) Cm Buah 61,000.00
2 Keramik (40x40) Cm Buah 13,300.00
4 Keramik (25x40) Cm Buah 8,200.00
5 Keramik (25x25) Cm Buah 5,100.00
6 Keramik (20x25) Cm Buah 4,000.00
7 Keramik (20x20) Cm Buah 3,400.00
8 Plint Keramik (10x20) Cm Buah 1,600.00
9 Plint Keramik (10x40) Cm Buah 3,300.00
10 Plint Granit (10x60) Cm Buah 10,200.00
11 Bon-bon Keramik M' 8,600.00
12 Floor hardener M2 20,200.00
13 Parquette M2 200,200.00
14 Karpet Standar M2 38,750.00
15 Granit Alam Setara Starwhite M2 985,000.00
16 Marmer Alam Setara Crystalwhite M2 2,595,000.00
1 2 3 4 5
IX BAHAN LANGIT-LANGIT
1 Teakwood Tebal 12 mm Lembar 175,750.00
2 Multiplek Tebal 12,0 MM Lembar 226,700.00
3 Multiplek Tebal 9,0 MM Lembar 136,400.00
4 Triplek Tebal 4,0 MM Lembar 86,100.00
5 Triplek Tebal 3,6 MM Lembar 65,850.00
6 Triplek Tebal 3,0 MM Lembar 55,700.00
7 Gypsum Board 9 mm Lembar 96,400.00
8 List Gypsum lbr 15-20cm M' 20,500.00
9 Kalsiboard Tebal 4 MM Lembar 66,500.00
10 Triplek melamin Lembar 121,500.00
1 2 3 4 5
XI BAHAN PINTU
1 Pintu Pelat Tebal 2 MM Rangka Besi (lengkap kunci dan aksesoris) M2 775,000.00
2 Pintu Fiber Warna dan Bermotif (lengkap Aksesoris) Lbr 512,500.00
3 Pintu Fiber KM/WC Standar (lengkap aksesoris) Lbr 362,500.00
4 Pintu Panel kelas I Uk. 90 x 210 CM (Ex. Kayu Tembusu) Lbr 3,520,000.00
5 Pintu Panel Kelas II Uk. 80 x 210 CM (Ex. Kayu Meranti) Lbr 820,000.00
6 Pintu Plywood (triplek depan blkg) Lbr 320,000.00
7 Pintu Teakwood (depan belakang) Lbr 700,000.00
8 Rolling Door M2 595,000.00
9 Folding Gate M2 755,000.00
1 2 3 4 5
17 Saklar Triple (setara broco) Buah 25,200.00
18 Zakering Khas (setara merlin gerlin) Buah 66,200.00
XV BAHAN CAT
1 Cat Tembok (Standar Dulux) Kg 75,300.00
NO. JENIS BAHAN SATUAN HARGA SATUAN KET.
1 2 3 4 5
2 Cat Tembok Biasa (Standar Catylac) Kg 22,800.00
3 Cat Tembok (Standar Jotun Jotaplast) Kg 85,300.00
4 Cat Kayu dan Besi (Setara Aviant) Kg 60,300.00
5 Cat Dasar / Kapur Kg 6,900.00
6 Cat Dasar Kayu / Menie Kayu Kg 30,300.00
7 Cat Vernish Ltr 30,300.00
8 Cat Impra Kg 45,300.00
9 Cat Residu Kg 40,300.00
10 Soda Api Kg 13,300.00
11 Plamir setara RJ Kg 30,300.00
12 Dempul Kayu Kg 43,300.00
13 Kertas Amplas Lbr 8,100.00
14 Kuas 3" Bh 17,400.00
15 Kuas Golong/rol Bh 30,100.00
16 Thinner / Pengencer Cat Kg 41,300.00
17 Flincote / Menie Besi Kg 16,800.00
1 2 3 4 5
37 Ember Plastik Hitam 3,5 Liter Unit 20,000.00
38 Ember Plastik 40 Liter Unit 55,000.00
39 Ember Plastik 60 Liter Unit 95,000.00
NO. JENIS BAHAN SATUAN HARGA SATUAN KET.
1 2 3 4 5
40 Container Plastik 70 Liter Unit 117,000.00
41 Container Plastik 100 Liter Unit 192,000.00
42 Tong Sampah Fiberglass 120 Liter (Pakai Roda) Unit 1,250,000.00
43 Tong Sampah Fiberglass 240 Liter (Pakai Roda) Unit 2,000,000.00
1 2 3 4 5
43 Pintu Terali Besi Polos Ø 12 MM (Lengkap Kunci dan Aksesoris) M2 990,000.00
44 Batu Coral Sikat + Coating (Terpasang) M2 137,500.00
45 Plastik Cor M2 5,500.00
46 Plafond PVC + Rangka Hollow (Motif Standar) M2 302,500.00
STANDAR BIAYA
DI LINGKUNGAN DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN KAMPAR
BIDANG CIPTA KARYA
TAHUN ANGGARAN 2021
DAERAH BAIK
DAFTAR UPAH
NO. JENIS UPAH SATUAN UPAH KETERANGAN
1 2 3 4 5
1 Pekerja OH 100,000.00
2 Tukang Batu OH 120,000.00
3 Tukang Kayu OH 120,000.00
4 Tukang Besi OH 120,000.00
5 Tukang Las OH 120,000.00
6 Tukang Cat OH 120,000.00
7 Tukang Pipa OH 120,000.00
8 Kepala Tukang OH 150,000.00
9 Mandor OH 150,000.00
10 Operator Alat Berat OH 94,500.00
11 Pembantu Operator Alat Berat OH 70,700.00
1 2 3 4 5 6 7 (4+5+6)
I BAHAN PASANGAN
1 Pasir Urug (PU) M3 100,000.00 20,000.00 25,000.00 145,000.00
2 Pasir Pasang (PP) M3 100,000.00 20,000.00 25,000.00 145,000.00
3 Pasir Beton (PB) M3 128,000.00 20,000.00 25,000.00 173,000.00
4 Pasir Kuarsa M3 128,000.00 20,000.00 25,000.00 173,000.00
5 Kerikil (KR) M3 146,300.00 20,000.00 25,000.00 191,300.00
6 Sirtu M3 155,000.00 20,000.00 25,000.00 200,000.00
7 Batu Belah (gunung) 15cm/20 cm M3 255,000.00 20,000.00 60,000.00 335,000.00
8 Batu sungai (mangga) M3 245,000.00 20,000.00 25,000.00 290,000.00
9 Portland Cement (PC) Kg 1,450.00 50.00 50.00 1,550.00
10 Semen Warna Kg 3,000.00 50.00 50.00 3,100.00
11 Cornite Compound Jayaboard Zak 100,000.00 2,500.00 500.00 103,000.00
HARGA TOKO / MUAT DAN
NO. JENIS BAHAN SATUAN TRANSPORT JUMLAH
QUARRY BONGKAR
1 2 3 4 5 6 7 (4+5+6)
12 Bata Merah (Ukuran Sedang ) Buah 550.00 30.00 20.00 600.00
13 Kerawang (Roster semen)20x20 cm Buah 25,000.00 20.00 80.00 25,100.00
14 Kerawang (Roster semen)40x40 cm Buah 50,000.00 20.00 80.00 50,100.00
15 Rumput Gajah Mini M2 45,000.00 500.00 1,000.00 46,500.00
16 Rumput Biasa M2 17,000.00 500.00 1,000.00 18,500.00
17 Tanah Hitam M3 130,000.00 20,000.00 25,000.00 175,000.00
18 Urugan Pilihan M3 26,000.00 20,000.00 25,000.00 71,000.00
19 Urugan Biasa M3 21,000.00 20,000.00 25,000.00 66,000.00
20 Conblock Segi 6 Tebal 8 CM Bh 2,000.00 50.00 50.00 2,100.00
21 Conblock Segi 4 Tebal 8 CM Bh 2,000.00 50.00 50.00 2,100.00
22 Paving Block Segi 6 Tebal 6 CM Bh 1,700.00 50.00 50.00 1,800.00
23 Paving Block Segi 4 Tebal 6 CM Bh 1,700.00 50.00 50.00 1,800.00
24 Glass Block T= 6 cm Bh 25,000.00 100.00 100.00 25,200.00
25 Buis Beton Dia 20cm P= 90 Cm (Lingkaran Dalam) Bh 150,000.00 7,000.00 5,000.00 162,000.00
26 Buis Beton Dia 40cm P = 90 Cm (Lingkaran Dalam) Bh 230,000.00 10,000.00 15,000.00 255,000.00
27 Buis Beton Dia 60cm P= 90 Cm (Lingkaran Dalam) Bh 300,000.00 20,000.00 15,000.00 335,000.00
28 Buis Beton Dia 80cm P= 90 Cm (Lingkaran Dalam) Bh 450,000.00 25,000.00 20,000.00 495,000.00
29 Buis Beton Dia 100cm P = 90 Cm (Lingkaran Dalam) Bh 650,000.00 30,000.00 20,000.00 700,000.00
30 Batu Split / Pecah M3 300,000.00 20,000.00 25,000.00 345,000.00
31 Bata Beton Ringan Uk. ( 10 x20 x 40 ) CM Buah 9,600.00 300.00 400.00 10,300.00
32 Batu Tempel Uk. 20 x 20 CM Buah 5,000.00 50.00 50.00 5,100.00
33 Batu Tempel Uk. 20 x 40 CM Buah 12,500.00 50.00 50.00 12,600.00
34 Kanstin Beton Ukuran Sedang (20x25x15) CM Unit 12,000.00 500.00 500.00 13,000.00
35 Conwood untuk Dinding Tebal 11 MM M2 382,000.00 35,000.00 35,000.00 452,000.00
36 Conwood untuk Lantai Tebal 25 MM M2 763,000.00 35,000.00 35,000.00 833,000.00
II BAHAN KAYU
1 Kayu Kelas I (Ex: Kayu Tembusu, Kayu Kulim) M3 5,500,000.00 50,000.00 35,000.00 5,585,000.00
2 Kayu Kelas II (Ex: Kayu Meranti) M3 2,625,000.00 40,000.00 30,000.00 2,695,000.00
3 Kayu Kelas III (Ex: Kayu Campuran) M3 1,995,000.00 30,000.00 25,000.00 2,050,000.00
4 Kayu List Profil siku2" M' 2,500.00 100.00 100.00 2,700.00
5 Kayu List Profil 0.8x3" M' 3,000.00 100.00 100.00 3,200.00
6 Papan 2 x 20 CM Kayu Kelas II M3 2,200,000.00 40,000.00 35,000.00 2,275,000.00
7 Kayu Cerocok dia. 10 - 15 cm Batang 36,750.00 500.00 3,000.00 40,250.00
8 Dolken Kayu Galam, Ø (8-10)Cm,Panjang 4 M Batang 6,000.00 500.00 500.00 7,000.00
HARGA TOKO / MUAT DAN
NO. JENIS BAHAN SATUAN TRANSPORT JUMLAH
QUARRY BONGKAR
1 2 3 4 5 6 7 (4+5+6)
9 Kayu Bakar ( Non Kelas ) M3 250,000.00 30,000.00 35,000.00 315,000.00
10 Papan Piri - piri (Siap Ketam 3 sisi) M3 2,825,000.00 40,000.00 35,000.00 2,900,000.00
11 Papan Lebah Bergayut M' 165,000.00 500.00 500.00 166,000.00
12 Singap Ukir kayu (Ex. Kayu Meranti) M2 900,000.00 3,000.00 10,000.00 913,000.00
13 Singap Ukir GRC M2 850,000.00 3,000.00 10,000.00 863,000.00
14 Selembayung GRC Lebar 30 cm Pasang 400,000.00 1,000.00 5,000.00 406,000.00
15 Selembayung kayu lebar 30 cm Pasang 250,000.00 1,000.00 5,000.00 256,000.00
16 Sayap layang-layang lebar 30 cm Pasang 250,000.00 1,000.00 5,000.00 256,000.00
17 Lisplank GRC Lebar 20 CM M1 69,000.00 500.00 500.00 70,000.00
18 Lisplank GRC Lebar 10 CM M1 55,000.00 500.00 500.00 56,000.00
IV BAHAN PAKU
1 Paku 1 Cm - 2,5 Cm Kg 28,350.00 100.00 100.00 28,550.00
2 Paku 5 Cm - 12 Cm Kg 28,350.00 100.00 100.00 28,550.00
3 Paku Skrup 1-5 CM Kg 40,000.00 100.00 100.00 40,200.00
4 Paku Skrup 5-10 Cm Kg 38,000.00 100.00 100.00 38,200.00
5 Paku Skrup 10-15 Cm Kg 35,000.00 100.00 100.00 35,200.00
HARGA TOKO / MUAT DAN
NO. JENIS BAHAN SATUAN TRANSPORT JUMLAH
QUARRY BONGKAR
1 2 3 4 5 6 7 (4+5+6)
6 Paku Asbes Kg 20,000.00 100.00 100.00 20,200.00
7 Paku Atap Genteng Metal Kg 24,000.00 100.00 100.00 24,200.00
8 Paku Atap Seng Gelombang Kg 20,000.00 100.00 100.00 20,200.00
9 Skrup Fixer Buah 200.00 50.00 50.00 300.00
10 Skrup / Paku Atap dan Genteng Bitumen Monolayer Buah 1,100.00 50.00 50.00 1,200.00
11 DynaBolt Rangka Baja Ringan Buah 1,000.00 50.00 50.00 1,100.00
V BAHAN ALLUMUNIUM
1 Profil Allumunium "T" M' 52,000.00 500.00 1,500.00 54,000.00
2 Kusen Alumunium 3'' M' 52,000.00 500.00 1,500.00 54,000.00
3 Rangka Jendela Almunium M' 52,000.00 500.00 1,500.00 54,000.00
4 Rangka Pintu Almunium M' 130,000.00 500.00 1,500.00 132,000.00
VI BAHAN LANTAI
1 Granit Ukuran ( 60 x 60 ) Cm Buah 60,000.00 500.00 500.00 61,000.00
2 Keramik (40x40) Cm Buah 12,500.00 400.00 400.00 13,300.00
3 Keramik (30x30) Cm Buah 5,900.00 350.00 350.00 6,600.00
4 Keramik (25x40) Cm Buah 7,500.00 350.00 350.00 8,200.00
5 Keramik (25x25) Cm Buah 4,500.00 300.00 300.00 5,100.00
6 Keramik (20x25) Cm Buah 3,500.00 250.00 250.00 4,000.00
7 Keramik (20x20) Cm Buah 3,000.00 200.00 200.00 3,400.00
8 Plint Keramik (10x20) Cm Buah 1,500.00 50.00 50.00 1,600.00
9 Plint Keramik (10x40) Cm Buah 3,150.00 75.00 75.00 3,300.00
10 Plint Granit (10x60) Cm Buah 10,000.00 100.00 100.00 10,200.00
11 Bon-bon Keramik M' 8,500.00 50.00 50.00 8,600.00
12 Floor hardener M2 20,000.00 100.00 100.00 20,200.00
13 Parquette M2 200,000.00 100.00 100.00 200,200.00
14 Karpet Standar M2 35,000.00 350.00 3,400.00 38,750.00
15 Granit Alam Setara Starwhite M2 900,000.00 35,000.00 50,000.00 985,000.00
16 Marmer Alam Setara Crystalwhite M2 2,500,000.00 40,000.00 55,000.00 2,595,000.00
1 2 3 4 5 6 7 (4+5+6)
4 Genteng Metal gelombang Tebal 0,25 MM Lbr 40,000.00 100.00 200.00 40,300.00
5 Genteng Metal alur lurus Tebal 0,25 MM Lbr 40,000.00 100.00 200.00 40,300.00
6 Perabung genteng metal (Panjang 0,90 Meter) Lbr 18,000.00 100.00 200.00 18,300.00
7 Atap Seng Gelombang 0,20 mm x 180 cm x 90 cm (Setara Crown swan) Lbr 50,000.00 200.00 300.00 50,500.00
8 Plat Alumunium Tebal 0,25 MM Uk. 1M x 2M Lbr 75,000.00 200.00 300.00 75,500.00
9 Seng Plat BJLS 20 Lbr 50,000.00 200.00 300.00 50,500.00
10 Bubungan beton warna BH 30,000.00 100.00 200.00 30,300.00
11 Allumunium Foil / Sisalation M2 15,000.00 100.00 200.00 15,300.00
12 Formika M2 46,000.00 500.00 1,000.00 47,500.00
13 Spandek Tebal 0,30 MM M2 45,000.00 500.00 500.00 46,000.00
14 Spandek Tebal 0,25 MM M2 40,000.00 500.00 500.00 41,000.00
15 Genteng Keramik Bh 8,500.00 100.00 250.00 8,850.00
16 Genteng Keramik Glazur Bh 4,500.00 100.00 250.00 4,850.00
17 Nok Genteng Keramik Bh 30,000.00 100.00 250.00 30,350.00
18 Nok Genteng Keramik Glazur Bh 30,000.00 100.00 250.00 30,350.00
19 Nok Genteng Metal ( Panjang 90 CM ) Bh 18,000.00 500.00 700.00 19,200.00
20 Atap Bitumen Bergelombang Monolayer Uk. 200 x 95 x 0,3 CM Lbr 155,000.00 200.00 300.00 155,500.00
21 Genteng Bitumen Bergelombang Monolayer Uk. 106 x 40 x 0,3 CM Lbr 48,800.00 200.00 300.00 49,300.00
22 Genteng Bitumen Bergelombang Memanjang Monolayer Uk. 195 x 96 x 0,3 CM Lbr 145,000.00 200.00 300.00 145,500.00
23 Nok Bitumen Monolayer Bh 82,000.00 200.00 300.00 82,500.00
24 Terpal Khusus untuk Atap ( Lebar 50 CM ) M1 12,500.00 500.00 500.00 13,500.00
25 Listplank Conwood Tebal 8 MM M1 75,300.00 1,500.00 2,500.00 79,300.00
IX BAHAN LANGIT-LANGIT
1 Teakwood Tebal 12 mm Lembar 175,000.00 250.00 500.00 175,750.00
2 Multiplek Tebal 12,0 MM Lembar 225,000.00 500.00 1,200.00 226,700.00
3 Multiplek Tebal 9,0 MM Lembar 135,000.00 400.00 1,000.00 136,400.00
4 Triplek Tebal 4,0 MM Lembar 85,000.00 300.00 800.00 86,100.00
5 Triplek Tebal 3,6 MM Lembar 65,000.00 250.00 600.00 65,850.00
6 Triplek Tebal 3,0 MM Lembar 55,000.00 200.00 500.00 55,700.00
HARGA TOKO / MUAT DAN
NO. JENIS BAHAN SATUAN TRANSPORT JUMLAH
QUARRY BONGKAR
1 2 3 4 5 6 7 (4+5+6)
7 Gypsum Board 9 mm Lembar 95,000.00 400.00 1,000.00 96,400.00
8 List Gypsum lbr 15-20cm M' 20,000.00 250.00 250.00 20,500.00
9 Kalsiboard Tebal 4 MM Lembar 65,000.00 500.00 1,000.00 66,500.00
10 Triplek melamin Lembar 120,000.00 500.00 1,000.00 121,500.00
1 2 3 4 5 6 7 (4+5+6)
30 Tangki Plastik 500 Liter Unit 1,045,000.00 5,000.00 20,000.00 1,070,000.00
31 Tangki Plastik 1000 Liter Unit 1,800,000.00 7,500.00 25,000.00 1,832,500.00
32 Tangki Stainless 500 Liter + Kaki Unit 1,750,000.00 5,000.00 20,000.00 1,775,000.00
33 Tangki Stainless 1000 Liter + Kaki Unit 3,500,000.00 7,500.00 25,000.00 3,532,500.00
34 Pipa Baja Kg 20,000.00 250.00 250.00 20,500.00
35 Bioseptictank Kapasitas 1000 Liter (Bahan HDPE) Unit 3,600,000.00 75,000.00 150,000.00 3,825,000.00
36 Bioseptictank Kapasitas 1600 Liter (Bahan HDPE) Unit 4,700,000.00 80,000.00 165,000.00 4,945,000.00
37 Bioseptictank Kapasitas 2000 Liter (Bahan HDPE) Unit 5,900,000.00 95,000.00 180,000.00 6,175,000.00
38 Pipa PPR-PN 10 Diameter 1/2 Inch (Setara Rucika) M1 10,950.00 500.00 750.00 12,200.00
39 Pipa PPR-PN 10 Diameter 3/4 Inch (Setara Rucika) M1 14,400.00 850.00 1,000.00 16,250.00
40 Pipa PPR-PN 10 Diameter 1 Inch (Setara Rucika) M1 23,100.00 1,000.00 1,200.00 25,300.00
41 Pipa PPR-PN 10 Diameter 2 Inch (Setara Rucika) M1 89,700.00 1,500.00 2,000.00 93,200.00
42 Pipa PPR-PN 10 Diameter 3 Inch (Setara Rucika) M1 181,150.00 1,700.00 2,500.00 185,350.00
43 Pipa PPR-PN 10 Diameter 4 Inch (Setara Rucika) M1 269,000.00 1,900.00 2,700.00 273,600.00
44 Pipa PPR-PN 10 Diameter 5 Inch (Setara Rucika) M1 559,200.00 2,200.00 3,000.00 564,400.00
45 Pipa PPR-PN 10 Diameter 6 Inch (Setara Rucika) M1 916,700.00 2,500.00 3,250.00 922,450.00
XI BAHAN PINTU
1 Pintu Pelat Tebal 2 MM Rangka Besi (lengkap kunci dan aksesoris) M2 750,000.00 5,000.00 20,000.00 775,000.00
2 Pintu Fiber Warna dan Bermotif (lengkap Aksesoris) Lbr 500,000.00 2,500.00 10,000.00 512,500.00
3 Pintu Fiber KM/WC Standar (lengkap aksesoris) Lbr 350,000.00 2,500.00 10,000.00 362,500.00
4 Pintu Panel kelas I Uk. 90 x 210 CM (Ex. Kayu Tembusu) Lbr 3,500,000.00 5,000.00 15,000.00 3,520,000.00
5 Pintu Panel Kelas II Uk. 80 x 210 CM (Ex. Kayu Meranti) Lbr 800,000.00 5,000.00 15,000.00 820,000.00
6 Pintu Plywood (triplek depan blkg) Lbr 300,000.00 5,000.00 15,000.00 320,000.00
7 Pintu Teakwood (depan belakang) Lbr 680,000.00 5,000.00 15,000.00 700,000.00
8 Rolling Door M2 550,000.00 20,000.00 25,000.00 595,000.00
9 Folding Gate M2 700,000.00 25,000.00 30,000.00 755,000.00
1 2 3 4 5 6 7 (4+5+6)
7 Grendel pintu 6" (krom) Bh 22,000.00 50.00 100.00 22,150.00
8 Grendel Pintu 4"(krom) Bh 14,000.00 50.00 100.00 14,150.00
9 Grendel Jendela 2" (krom) Bh 10,000.00 50.00 100.00 10,150.00
10 Kait Angin / Hak Angin Bh 8,000.00 50.00 100.00 8,150.00
11 Tarikan Tangan ( Jendela / Ventilasi ) Bh 9,000.00 50.00 100.00 9,150.00
12 Door Closer Bh 430,000.00 100.00 150.00 430,250.00
13 Door Stoper Plastik Bh 22,000.00 100.00 100.00 22,200.00
14 Selinder Bh 8,000.00 50.00 100.00 8,150.00
15 Handle Jendela Bh 8,000.00 50.00 100.00 8,150.00
1 2 3 4 5 6 7 (4+5+6)
13 Lampu Baret Buah 210,000.00 100.00 100.00 210,200.00
14 Stop Kontak (setara broco) Buah 20,000.00 100.00 100.00 20,200.00
15 Saklar Tunggal (setara broco) Buah 15,000.00 100.00 100.00 15,200.00
16 Saklar Ganda (setara broco) Buah 20,000.00 100.00 100.00 20,200.00
17 Saklar Triple (setara broco) Buah 25,000.00 100.00 100.00 25,200.00
18 Zakering Khas (setara merlin gerlin) Buah 66,000.00 100.00 100.00 66,200.00
XV BAHAN CAT
1 Cat Tembok (Standar Dulux) Kg 75,000.00 100.00 200.00 75,300.00
2 Cat Tembok Biasa (Standar Catylac) Kg 22,500.00 100.00 200.00 22,800.00
3 Cat Tembok (Standar Jotun Jotaplast) Kg 85,000.00 100.00 200.00 85,300.00
4 Cat Kayu dan Besi (Setara Aviant) Kg 60,000.00 100.00 200.00 60,300.00
5 Cat Dasar / Kapur Kg 6,600.00 100.00 200.00 6,900.00
6 Cat Dasar Kayu / Menie Kayu Kg 30,000.00 100.00 200.00 30,300.00
7 Cat Vernish Ltr 30,000.00 100.00 200.00 30,300.00
8 Cat Impra Kg 45,000.00 100.00 200.00 45,300.00
9 Cat Residu Kg 40,000.00 100.00 200.00 40,300.00
10 Soda Api Kg 13,000.00 100.00 200.00 13,300.00
11 Plamir setara RJ Kg 30,000.00 100.00 200.00 30,300.00
12 Dempul Kayu Kg 43,000.00 100.00 200.00 43,300.00
13 Kertas Amplas Lbr 8,000.00 50.00 50.00 8,100.00
14 Kuas 3" Bh 17,300.00 50.00 50.00 17,400.00
15 Kuas Golong/rol Bh 30,000.00 50.00 50.00 30,100.00
16 Thinner / Pengencer Cat Kg 41,000.00 100.00 200.00 41,300.00
17 Flincote / Menie Besi Kg 16,500.00 100.00 200.00 16,800.00
1 2 3 4 5 6 7 (4+5+6)
10 Minyak Pelumas Liter 40,000.00 500.00 1,500.00 42,000.00
11 Minyak Bekisting Liter 5,000.00 500.00 1,500.00 7,000.00
12 Aspal Drum Kg 13,500.00 300.00 1,000.00 14,800.00
13 Tempat Masak Aspal BH 45,000.00 1,500.00 4,500.00 51,000.00
14 Ijuk M3 25,000.00 100.00 200.00 25,300.00
15 Water proofing Coating Kg 25,000.00 100.00 200.00 25,300.00
16 Water proofing Membran M2 90,000.00 500.00 1,000.00 91,500.00
17 Alat Pemadat ( Stamper ) Hari 150,000.00 500.00 1,000.00 151,500.00
18 Penjaga Jarak Bekisting / Spacer Buah 4,000.00 500.00 1,000.00 5,500.00
19 Pupuk Kandang Krg 25,000.00 100.00 100.00 25,200.00
20 Wallpaper Standar M2 45,000.00 500.00 500.00 46,000.00
21 Sunscreeen Alluminium M2 325,000.00 500.00 1,000.00 326,500.00
22 Beton Ready Mix K-175 ( Batu Koral) M3 750,000.00 50,000.00 50,000.00 850,000.00
23 Beton Ready Mix K-225 ( Batu Koral) M3 850,000.00 50,000.00 50,000.00 950,000.00
24 Beton Ready Mix K-250 ( Batu Split / Batu Pecah) M3 980,000.00 50,000.00 50,000.00 1,080,000.00
25 Beton Ready Mix K-300 ( Batu Split / Batu Pecah) M3 1,070,000.00 50,000.00 50,000.00 1,170,000.00
26 Beton Ready Mix K-350 ( Batu Split / Batu Pecah) M3 1,150,000.00 50,000.00 50,000.00 1,250,000.00
27 Minyak Tanah (Non Subsidi) Liter 11,220.00 130.00 200.00 11,550.00
28 U Ditch Uk. ( 30x30x120 ) CM Tebal 5 CM Beton K.250 M1 233,000.00 25,000.00 25,000.00 283,000.00
29 U Ditch Uk. ( 80x100x120 ) CM Tebal 10 CM Beton K.250 M1 812,000.00 35,000.00 30,000.00 877,000.00
30 U Ditch Uk. ( 80x120x100 ) CM Tebal 7 CM Beton K.250 M1 714,000.00 50,000.00 35,000.00 799,000.00
31 U Ditch Uk. ( 160x140x120 ) CM Tebal 13 CM Beton K.250 M1 3,342,000.00 150,000.00 40,000.00 3,532,000.00
32 Box Culvert Uk. (100x100x100) CM Tebal 23 CM Beton K.250 M1 4,210,000.00 25,000.00 25,000.00 4,260,000.00
33 Box Culvert Uk. (100x150x100) CM Tebal 20 CM Beton K.250 M1 5,506,000.00 35,000.00 30,000.00 5,571,000.00
34 Box Culvert Uk. (60x60x100) CM Tebal 14 CM Beton K.250 M1 1,167,000.00 50,000.00 35,000.00 1,252,000.00
35 Box Culvert Uk. (200x200x120) CM Tebal 25 CM Beton K.250 M1 15,094,000.00 150,000.00 40,000.00 15,284,000.00
36 Gayung Plastik Standar Unit 7,000.00 7,000.00
37 Ember Plastik Hitam 3,5 Liter Unit 20,000.00 20,000.00
38 Ember Plastik 40 Liter Unit 55,000.00 55,000.00
39 Ember Plastik 60 Liter Unit 95,000.00 95,000.00
40 Container Plastik 70 Liter Unit 117,000.00 117,000.00
41 Container Plastik 100 Liter Unit 192,000.00 192,000.00
42 Tong Sampah Fiberglass 120 Liter (Pakai Roda) Unit 1,250,000.00 1,250,000.00
43 Tong Sampah Fiberglass 240 Liter (Pakai Roda) Unit 2,000,000.00 2,000,000.00
HARGA TOKO / PROFIT DAN
NO. JENIS BAHAN SATUAN TRANSPORT JUMLAH
QUARRY OVERHEAD 10%
1 2 3 4 5 6=(4+5)*10% 7
XVII BAHAN TERPASANG
1 Aluminium Composite Panel (ACP PE 0,21 MM) Rangka Hollow M2 500,000.00 50,000.00 550,000.00
2 Aluminium Composite Panel (ACP PVDF 0,30 MM) Rangka Hollow M2 600,000.00 60,000.00 660,000.00
3 Atap Canopy (Polycarbonat + Rangka Hollow) M2 460,000.00 46,000.00 506,000.00
4 Atap Canopy ( Atap Longspan + Rangka Hollow ) M2 440,000.00 44,000.00 484,000.00
5 Partisi Kaca ( Tebal 8 MM ) Frameless M2 1,200,000.00 120,000.00 1,320,000.00
6 Partisi Kaca ( Tebal 12 MM ) Frameless M2 1,400,000.00 140,000.00 1,540,000.00
7 Pintu Kaca Tempered Frameless Uk. 80 x 200 CM (Tebal 12 MM) Lengkap dengan Unit 4,950,000.00 495,000.00 5,445,000.00
Handle, Kunci dan Engsel Pivot
8 Pintu Kaca Tempered Fitting Uk. 80 x 200 CM ( Tebal 12 MM ) Lengkap dengan Handle, Unit 6,500,000.00 650,000.00 7,150,000.00
Kunci dan Engsel Pivot
9 Pintu Kaca Polos Swing Uk. 80 x 200 CM ( Tebal 5 MM ) Lengkap dengan Handle, Kunci Unit 1,485,000.00 148,500.00 1,633,500.00
dan Engsel
10 Pintu Kaca Polos Sliding Uk. 80 x 200 CM ( Tebal 5 MM ) Lengkap dengan Handle, Kunci Unit 1,540,000.00 154,000.00 1,694,000.00
dan Rel
11 Pagar Hollow (standard minimalis) M2 375,000.00 37,500.00 412,500.00
12 Ventilasi Aluminium + Rangka Aluminium Lengkap Aksesoris M2 650,000.00 65,000.00 715,000.00
13 Jendela Kaca Tebal 5 MM Rangka Aluminium Lengkap dengan Kunci dan Aksesoris M2 650,000.00 65,000.00 715,000.00
Jendela Sliding Kaca Tebal 5 MM Rangka Aluminium Lengkap dengan Kunci dan 675,000.00
14 Aksesoris M2
67,500.00 742,500.00
15 Satu Buah Huruf Timbul Akrilik CM1 24,500.00 2,450.00 26,950.00
16 Terali Besi Polos Ø 12 MM / Nako 12 MM M2 350,000.00 35,000.00 385,000.00
17 Terali Besi Polos Ø 14 MM M2 420,000.00 42,000.00 462,000.00
18 Pagar Besi BRC Tinggi 1,20 Meter Diameter 6 MM M1 183,000.00 18,300.00 201,300.00
19 Pondasi Tiang Pancang Mini Pile Uk.20x20 CM K.450 (Menggunakan Drop Hammer) M1 219,000.00 21,900.00 240,900.00
20 Pondasi Tiang Pancang Mini Pile Uk.25x25 CM K.450 (Menggunakan Drop Hammer) M1 269,000.00 26,900.00 295,900.00
21 Pondasi Tiang Pancang Mini Pile Uk.20x20 CM K.450 Menggunakan System Hydraulic M1 267,000.00 26,700.00 293,700.00
Static Pile Driver (HSPD)
22 Pondasi Tiang Pancang Mini Pile Uk.25x25 CM K.450 Menggunakan System Hydraulic M1 312,000.00 31,200.00 343,200.00
Static Pile Driver (HSPD)
23 AC Standart 1/2 PK (Termasuk Aksesoris dan Pemasangan) M1 4,000,000.00 400,000.00 4,400,000.00
24 AC Standart 3/4 PK (Termasuk Aksesoris dan Pemasangan) M1 4,200,000.00 420,000.00 4,620,000.00
25 AC Standart 1 PK (Termasuk Aksesoris dan Pemasangan) M1 4,350,000.00 435,000.00 4,785,000.00
26 AC Standart 1,5 PK (Termasuk Aksesoris dan Pemasangan) M1 5,700,000.00 570,000.00 6,270,000.00
27 AC Standart 2 PK (Termasuk Aksesoris dan Pemasangan) M1 7,400,000.00 740,000.00 8,140,000.00
28 Kusen dan Daun Pintu Swing Rangka UPVC (Kaca Tebal 5 MM) M2 1,700,000.00 170,000.00 1,870,000.00
HARGA TOKO / PROFIT DAN
NO. JENIS BAHAN SATUAN TRANSPORT JUMLAH
QUARRY OVERHEAD 10%
1 2 3 4 5 6=(4+5)*10% 7
29 Jendela Swing / Jungkit Rangka UPVC (Kaca Tebal 5 MM) M2 1,500,000.00 150,000.00 1,650,000.00
30 Jendela Slading Rangka UPVC (Kaca Tebal 5 MM) M2 1,500,000.00 150,000.00 1,650,000.00
31 Kaca Mati Rangka UPVC (Kaca Tebal 5 MM) M2 1,300,000.00 130,000.00 1,430,000.00
32 Kisi - Kisi Rangka UPVC (Kaca Tebal 5 MM) M2 1,300,000.00 130,000.00 1,430,000.00
33 Atap Zincalume System Klip-Lok BMT 0,45 MM M2 282,000.00 28,200.00 310,200.00
34 Atap Zincalume System Klip-Lok BMT 0,40 MM M2 214,000.00 21,400.00 235,400.00
35 Polis Marmer (Termasuk Obat) M2 100,000.00 10,000.00 110,000.00
36 Polis Granit M2 125,000.00 12,500.00 137,500.00
37 Vertikal / Horizontal Blind M2 175,000.00 17,500.00 192,500.00
38 Rolling Door M2 550,000.00 55,000.00 605,000.00
39 Folding Gate M2 700,000.00 70,000.00 770,000.00
40 Pintu Kaca Tebal 5 MM Rangka Aluminium (Lengkap Aksesoris) Lembar 2,300,000.00 230,000.00 2,530,000.00
41 Pintu HPL Lengkap Kunci (Lengkap Aksesoris) Lembar 1,950,000.00 195,000.00 2,145,000.00
42 Pintu Terali Besi Polos Ø 14 MM (Lengkap Kunci dan Aksesoris) M2 1,100,000.00 110,000.00 1,210,000.00
43 Pintu Terali Besi Polos Ø 12 MM (Lengkap Kunci dan Aksesoris) M2 900,000.00 90,000.00 990,000.00
44 Batu Coral Sikat + Coating (Terpasang) M2 125,000.00 12,500.00 137,500.00
45 Plastik Cor M2 5,000.00 500.00 5,500.00
46 Plafond PVC + Rangka Hollow (Motif Standar) M2 275,000.00 27,500.00 302,500.00
REKAPITULASI ANALISA PEKERJAAN DAERAH BA
1 2 3
1 PEKERJAAN PERSIAPAN 1
2
3
4
5
1 2 3
10
11
12
13
14
15
16
17
18
2
3
REKAPITULASI ANALISA PEKERJAAN DAERAH BA
1 2 3
4
5
6
7
8
9
10
X. PEKERJAAN ATAP 1
2
3
4
5
6
1 2 3
7
8
9
1 2 3
XV. PEKERJAAN RANGKA ATAP BAJA RINGAN 1
2
3
3 4
3 4
Pemasangan 1 M2 jembatan Rangka Kayu untuk pengecoran beton Rp 107,470.00
Membuat 1 M' Kolom Praktis Beton Bertulang (11 x 11) CM Rp 105,462.72
Membuat 1 M' Ring Balok Beton Bertulang Uk. 10 x 15 CM Rp 134,075.15
Pekerjaan 1 M3 beton Ready Mix dan bahan aditif ( K 250 ) Rp 1,375,385.00
Membuat Beton Camp. 1 PC : 3 Psr : 5 Krk Rp 821,377.26
Membuat Beton Camp. 1 PC : 2 Psr : 3 Krk Rp 845,521.05
Membuat 1 M3 Beton Mutu F'c = 14,5 Mpa Atau Setara K 175, Slump ( 120±20 ) MM Rp 1,046,682.08
Membuat 1 M3 Beton Mutu F'c = 21,7 Mpa Atau Setara K 250 Rp 1,138,621.79
Membuat 1 M3 Beton Mutu F'c = 26,4 Mpa Atau Setara K 300 Rp 1,184,711.05
3 4
Pemasangan 1 m' plint keramik ukuran 10 x 20 cm Rp 36,373.70
Pemasangan 1 m' plint keramik ukuran 10 x 40 cm Rp 37,825.70
Pemasangan 1 m' plin Granit Uk. 10/60 Rp 49,219.87
Pemasangan 1 m2 dinding keramik warna 20x20 CM Rp 297,702.90
Pemasangan 1 M2 Lantai Karpet Rp 103,815.25
Pemasangan 1 M2 Lantai Parquet Rp 389,345.00
Pemasangan 1 M2 Dinding Batu Tempel Uk. 20 X 20 CM Rp 309,031.25
Pembuatan & Pemasangan 1 m3 Kusen Pintu dan Kusen Jendela, Kayu Kelas I Rp 10,772,396.25
Pembuatan & Pemasangan 1 M3 Kusen Pintu dan Kusen Jendela Kayu Kelas II Rp 7,008,196.25
Pembuatan & Pemasangan 1 M2 Daun Pintu Panel, Kayu Kelas II Rp 696,850.00
Pembuatan & Pemasangan 1 M2 Pintu/Jendela Kaca Kayu Kelas II Rp 630,740.00
Pembuatan & Pemasangan 1 M2 Jalusi Pintu/Jendela Kayu Kelas II Rp 767,998.00
Pemasangan 1M3 Kuda-kuda Konvensional Kayu Kelas II Rp 5,893,118.00
Pemasangan 1 M3 Konstruksi Gordeng, Kayu Kelas II Rp 7,333,590.00
Pemasangan 1 M2 Rangka Langit-langit Kayu Kelas II Rp 124,372.60
Pemasangan 1 M2 Rangka Dinding Pemisah Kayu Kelas II Rp 172,361.75
Pemasangan 1 M2 Dinding Pemisah Plywood Rangkap Rangka Kayu Kelas II Rp 298,179.75
Pemasangan 1 M' Listplank Ukuran ( 3x20 ) cm , Kayu Kelas II Rp 76,682.10
REKAPITULASI ANALISA PEKERJAAN DAERAH BAIK
3 4
3 4
1 M2 Pasang Kuda - Kuda Baja Ringan + Reng untuk Atap Genteng Metal biasa Rp 181,776.00
1 M2 Pasang Kuda - Kuda Baja Ringan + Reng untuk Atap Asbes / Spandek Rp 177,096.00
1 M2 Pasang Kuda - Kuda Baja Ringan + Reng untuk Atap Bitumen Rp 186,396.00
HARGA JUMLAH
No. URAIAN PEKERJAAN VOLUME SAT. SATUAN HARGA
( Rp. ) ( Rp. )
I PEKERJAAN PERSIAPAN
1 Pek. Pas. Bowplank , Pengukuran , dan Elevasi 16.000 M' 83,628.60 1,338,057.60
2 Pek. Pas. Kanstin Beton Pengunci Cor 1 : 2 : 3 Uk. 10 x 20 cm 1.320 M3 845,521.05 1,116,087.79
40 48 88 0.1 0.15
1.32
89,341,905.39
8,934,191
98,276,095.92
98,276,000.00 ###
###
RENCANA ANGGARAN BIAYA
ENGINEERING ESTIMATE
HARGA JUMLAH
No. URAIAN PEKERJAAN VOLUME SAT. SATUAN HARGA
A PEKERJAAN PAGAR DEPAN ( Rp. ) ( Rp. )
A PEKERJAAN GERBANG
I PEKERJAAN PERSIAPAN
1 Pek. Bobok Kepala Tiang Kolom Pagar Untuk Gerbang 1.000 Ls 1,500,000.00 1,500,000.00
II PEKERJAAN TANAH DAN PONDASI Sub Total 1,500,000.00
II PEKERJAAN STRUKTUR
3 Pek. Pas. Bata 1/2 Bata 1 : 4 Gerbang Pagar 1.665 M2 105,413.00 175,512.65
4 Pek. Plasteran 3.330 M2 52,852.80 175,999.82
Sub Total 1,861,202.60
III PEKERJAAN PLASTERAN DAN DINDING
1 Pek. Acian Tiang Kolom dan Balok Gerbang 8.200 M2 31,231.75 256,100.35
2 Pek. Relif Beton Tiang Gerbang 2.000 Bh 750,000.00 1,500,000.00
3 Pek. Pembuatan Nama Sekolah dari acliric 1.000 Unit 2,800,000.00 2,800,000.00
Sub Total 4,556,100.35
IV PEKERJAAN KUDA - KUDA DAN ATAP
V PEKERJAAN PLAFOND
VI PEKERJAAN PENGECATAN
1 Pek. Cat Air Kolom dan Dinding Plank Nama makam 8.200 M2 19,756.00 161,999.20
2 Pek. Cat Minyak Plafond Lambersering, Singap , Piri-piri 23.780 M2 43,233.91 1,028,102.26
Sub Total 1,190,101.46
JUMLAH 19,069,868.71
B PEKERJAAN PAGAR BETON
I PEKERJAAN PERSIAPAN
1 Pek. Pas. Bata 1/2 Bata Dinding Pagar 108.175 M2 122,991.00 13,304,576.02
Sub Total 13,304,576.02
V PEKERJAAN PLASTERAN
1 Pek. Plasteran Dinding Bata 1 : 4 216.350 M2 72,217.20 15,624,220.11
Sub Total 15,624,220.11
VI PEKERJAAN PENGECATAN
1 Pek. Cat Air Dinding dan Kolom Pagar 216.350 M2 24,412.30 5,281,610.87
I PEKERJAAN PERSIAPAN
1 Pek. Pengikisan Grid Beton Kolom Pagar Lama 1.000 Ls 2,500,000.00 2,500,000.00
Sub Total 2,500,000.00
II PEKERJAAN DINDING DAN PAGAR
1 Pek. Cat Air Dinding Kolom Pagar Depan, Samping, Dind 223.960 M2 24,412.30 5,467,378.71
2 Pek. Cat Minyak Rangka Hollow Pagar Lama 36.320 M2 48,286.70 1,753,772.94
4 1
1 2 4.1 1 8.2
1.9 6 11.4
0.7 2 1.4
18.72 0.3 5.62
95.9 1
90 1.2 108.1752
3 1.2
30 1.7 51 51
7 5.5 38.5 12.25 26.25
16 1.7 27.2 27.2
7.9 6.9 1 1 54.51
158.96
33.4 1 0.3 10.02
33.4 1 1 33.4
RENCANA ANGGARAN BIAYA
ENGINEERING ESTIMATE
HARGA JUMLAH
No. URAIAN PEKERJAAN VOLUME SAT. SATUAN HARGA
( Rp. ) ( Rp. )
I PEKERJAAN PERSIAPAN
1 Pek. Pas. Bowplank , Pengukuran , dan Elevasi 20.000 M' 83,628.60 1,672,572.00
2 Pek. Pembersihan Lokasi, , galian , perataan Tanah 238.648 M2 19,250.00 4,593,974.00
3 Papan Nama Kegiatan 1.000 Ls 250,000.00 250,000.00
HARGA JUMLAH
No. URAIAN PEKERJAAN VOLUME SAT. SATUAN HARGA
( Rp. ) ( Rp. )
A PEMBANGUNAN MUSHOLLAH
I PEKERJAAN PERSIAPAN
V PEKERJAAN PLASTERAN
1 Pek. Plasteran Dinding Bata 1 : 4 48.960 M2 72,217.20 3,535,754.11
X PEKERJAAN PENGECATAN
1 Pek. Cat Air Dinding 48.960 M2 24,412.30 1,195,226.21
2 Pek. Cat air Plafond 70.560 M2 24,412.30 1,722,531.89
3 Pek. Cat Lisplank, Singap 6.000 M2 48,286.70 289,720.20
I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi 20.000 M2 19,250.00 385,000.00
2 Pek. Pasang Bouwplank / Pengukuran 12.000 M' 83,628.60 1,003,543.20
Sub Total 1,388,543.20
II PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian Tanah Pondasi 2.412 M3 86,625.00 208,939.50
2 Pek. Urugan Kembali Bekas Galian 0.603 M3 28,875.00 17,411.63
3 Pek. Urugan Pasir Bawah Pondasi 0.151 M3 226,050.00 34,077.04
4 Pek. Cor Lantai Kerja 1 : 3 : 5 0.151 M3 0.00 0.00
Sub Total 260,428.16
III PEKERJAAN STRUKTUR
1 Pek. Pondasi Setempat Cor Beton Bertulang 1 : 2 : 3
Bekisting M2
Pembesian 26.640 Kg 20,134.40 536,380.42
V PEKERJAAN PLASTERAN
1 Pek. Plasteran Dinding Bata 1 : 4 75.138 M2 72,217.20 5,426,255.97
2 Pek. Pas. Dinding Keramik km/wc tinggi 1,25 m 25.750 M2 179,569.50 4,623,914.63
Sub Total 10,050,170.60
VI PEKERJAAN KUDA - KUDA DAN ATAP
1 Pek. Pas. Kuda-kuda Baja Ringan 33.600 M2 177,096.00 5,950,425.60
3 Pek. Pas. Atap Longspan 0,3 mm 33.600 M2 74,328.10 2,497,424.16
4 Pek. Pas. Perabung Atap 13.880 M' 45,806.20 635,790.06
5 Pek. Pas. Listplank Papan 2 x 2/20 21.400 M' 76,682.10 1,640,996.94
Sub Total 10,724,636.76
VII PEKERJAAN KOSEN PINTU DAN JENDELA
1 Pek. Pas. Pintu Fiber + Rangka PVC 2.000 Unit 700,000.00 1,400,000.00
2 Pek. Pas. Lubang Angin 1.000 Ls 600,000.00 600,000.00
Sub Total 2,000,000.00
VIII PEKERJAAN PLAFOND
1 Pek. Pas. Rangka Plafond Triplek 16.240 M2 124,372.60 2,019,811.02
2 Pek. Pas. Plafond Triplek tbl 4 mm 16.240 M2 63,133.40 1,025,286.42
3 Pek. Pas. List Profil 26.400 M' 16,852.55 444,907.32
IX PEKERJAAN LANTAI
1 Pek. Urugan Tanah Bawah Lantai 3.330 M3 118,745.00 395,420.85
2 Pek. Urugan Pasir Bawah Lantai 0.522 M3 226,050.00 117,998.10
3 Pek. Cor Lantai 1 : 3 : 5 0.522 M3 0.00 0.00
4 Pek. Pas. Lantai Keramik dalam 10.800 M2 171,219.40 1,849,169.52
10
10 4.8 0.616667 1 29.6
24 0.2 2 1 9.6
24 4 0.616667 1 59.2
160 0.82 0.221667 1 29.08267 88.28267
24 0.18 0.2 1 0.864
0.36 24 1 1 8.64
24 4 0.616667 1 59.2
160 0.48 0.221667 1 17.024 76.224
24 0.15 0.18 1 0.648
24 0.35 1 1 8.4
11.31 2 1 22.62
8 4 32
11.8 2 27.6
24 0.250 6.000
24 1 0.2 1 4.8
24 0.3 1 1 7.2
24 0.3 1 1 7.2
24 1 0.05 1 1.2
5 4 1 1 20
6
9 4.8 0.616667 1 26.64
20.6 1 1 20.6
13.88
21.4
14.8 1 14.8
2.9 4 11.6 26.4
17.4
3.6 3 1 1 10.8
17.54 0.8 0.05 0.7016
17.54 0.2 0.8 2.8064
17.54 0.2 1 3.508
JUMLAH
No. URAIAN PEKERJAAN HARGA
(Rp.)
1 2 3
A PEMBANGUNAN MUSHOLLAH
1 PEKERJAAN PERSIAPAN 3,004,057.60
2 PEKERJAAN TANAH DAN PONDASI 521,652.54
3 PEKERJAAN STRUKTUR 15,882,790.06
4 PEKERJAAN DINDING DAN PINTU 5,602,819.68
5 PEKERJAAN PLASTERAN 3,535,754.11
6 PEKERJAAN KUDA - KUDA DAN ATAP 24,376,871.22
8 PEKERJAAN PLAFOND 13,695,553.74
9 PEKERJAAN LANTAI 9,023,248.50
11 PEKERJAAN INSTALASI LISTRIK 1,026,800.00
12 PEKERJAAN PENGECATAN 3,207,478.30
13 PEKERJAAN SELASAR BANGUNAN 3,114,840.30
JUMLAH 155,817,630.49
JUMLAH 171,399,393.54
DIBULATKAN 171,399,000.00
Dibuat Oleh
KONSULTAN PERENCANA
CV. CIPTA REKAYASA ARSITEKTUR
ANTONY, ST
DIREKTUR
2 Pengukuran dan pemasangan 1 M' bouwplank
Permen PUPERA No. 28 /PRT/M/2016 Hal. 572
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.100 Rp 100,000.00 Rp 10,000.00
Tukang Kayu L.02 OH 0.100 Rp 120,000.00 Rp 12,000.00
Kepala Tukang L.03 OH 0.010 Rp 150,000.00 Rp 1,500.00
Mandor L.04 OH 0.005 Rp 150,000.00 Rp 750.00
JUMLAH TENAGA KERJA Rp 24,250.00
B BAHAN
Kayu Balok Uk. 5/7 CM Kelas II M3 0.012 Rp 2,695,000.00 Rp 32,340.00
Paku 2" - 3" Kg 0.020 Rp 28,550.00 Rp 571.00
Kayu Papan Uk. 3/20 CM Kelas II M3 0.007 Rp 2,695,000.00 Rp 18,865.00
JUMLAH HARGA BAHAN Rp 51,776.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 76,026.00
E Overhead & Profit ( 10 % ) 10% x D Rp 7,602.60
F Harga Satuan Pekerjaan (D+E) Rp 83,628.60
A TENAGA
Pekerja L.01 OH 0.250 Rp 100,000.00 Rp 25,000.00
Mandor L.04 OH 0.025 Rp 150,000.00 Rp 3,750.00
JUMLAH TENAGA KERJA Rp 28,750.00
B BAHAN
Tanah Urug M3 1.200 66,000.00 Rp 79,200.00
JUMLAH HARGA BAHAN Rp 79,200.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 107,950.00
E Overhead & Profit ( 10 % ) 10% x D Rp 10,795.00
F Harga Satuan Pekerjaan (D+E) Rp 118,745.00
A TENAGA
Pekerja L.01 OH 0.250 Rp 100,000.00 Rp 25,000.00
Mandor L.04 OH 0.025 Rp 150,000.00 Rp 3,750.00
JUMLAH TENAGA KERJA Rp 28,750.00
B BAHAN
Tanah Hitam M3 1.200 175,000.00 Rp 210,000.00
JUMLAH HARGA BAHAN Rp 210,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 238,750.00
E Overhead & Profit ( 10 % ) 10% x D Rp 23,875.00
F Harga Satuan Pekerjaan (D+E) Rp 262,625.00
III. PEKERJAAN PONDASI
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.300 Rp 100,000.00 Rp 30,000.000
Tukang Kayu L.02 OH 0.150 Rp 120,000.00 Rp 18,000.000
Kepala Tukang L.03 OH 0.015 Rp 150,000.00 Rp 2,250.000
Mandor L.04 OH 0.030 Rp 150,000.00 Rp 4,500.000
JUMLAH TENAGA KERJA Rp 54,750.00
B BAHAN
Papan Kayu Kelas II M3 0.014 Rp 2,695,000.00 Rp 37,730.00
Kaso Uk.5/7 Cm Kayu Kelas II M3 0.003 Rp 2,695,000.00 Rp 8,085.00
Paku 5 dan 7 cm Kg 0.300 Rp 28,550.00 Rp 8,565.00
Minyak Bekisting Liter 0.200 Rp 7,000.00 Rp 1,400.00
JUMLAH HARGA BAHAN Rp 55,780.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 110,530.00
E Overhead & Profit ( 10 % ) 10% x D Rp 11,053.00
F Harga Satuan Pekerjaan (D+E) Rp 121,583.00
3 Pemasangan 1 M2 bekisting untuk pondasi
Permen PUPERA No. 28 /PRT/M/2016 Hal. 600
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.520 Rp 100,000.00 Rp 52,000.00
Tukang Kayu L.02 OH 0.260 Rp 120,000.00 Rp 31,200.00
Kepala Tukang L.03 OH 0.026 Rp 150,000.00 Rp 3,900.00
Mandor L.04 OH 0.026 Rp 150,000.00 Rp 3,900.00
JUMLAH TENAGA KERJA Rp 91,000.00
B BAHAN
Kayu Kelas III M3 0.040 Rp 2,050,000.00 Rp 82,000.00
Paku 5 - 10 CM Kg 0.300 Rp 28,550.00 Rp 8,565.00
Minyak bekisting Liter 0.100 Rp 7,000.00 Rp 700.00
JUMLAH HARGA BAHAN Rp 91,265.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 182,265.00
E Overhead & Profit ( 10 % ) 10% x D Rp 18,226.50
F Harga Satuan Pekerjaan (D+E) Rp 200,491.50
A TENAGA
Pekerja L.01 OH 0.297 Rp 100,000.00 Rp 29,700.00
Tukang Batu L.02 OH 0.033 Rp 120,000.00 Rp 3,960.00
Tukang Kayu L.02 OH 0.033 Rp 120,000.00 Rp 3,960.00
Tukang Besi L.02 OH 0.033 Rp 120,000.00 Rp 3,960.00
Kepala Tukang L.03 OH 0.010 Rp 150,000.00 Rp 1,500.00
Mandor L.04 OH 0.015 Rp 150,000.00 Rp 2,250.00
JUMLAH TENAGA KERJA Rp 45,330.00
B BAHAN
Kayu Kelas III ( papan ) M3 0.003 Rp 2,050,000.00 Rp 6,150.00
Paku 5 cm - 12 cm Kg 0.020 Rp 28,550.00 Rp 571.00
Minyak Bekisting Liter Rp -
Besi Beton Polos Kg 3.600 Rp 15,540.00 Rp 55,944.00
Kawat Beton Kg 0.050 Rp 18,800.00 Rp 940.00
Semen Portland Kg 5.500 Rp 1,550.00 Rp 8,525.00
Pasir Beton M3 0.009 Rp 173,000.00 Rp 1,557.00
Kerikil M3 0.015 Rp 191,300.00 Rp 2,869.50
JUMLAH HARGA BAHAN Rp 76,556.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 121,886.50
E Overhead & Profit ( 10 % ) 10% x D Rp 12,188.65
F Harga Satuan Pekerjaan (D+E) Rp 134,075.15
A TENAGA
Pekerja L.01 OH 1.000 100,000.00 100,000.00
Tukang Batu L.02 OH 0.250 120,000.00 30,000.00
Kepala Tukang L.03 OH 0.025 150,000.00 3,750.00
Mandor L.04 OH 0.100 150,000.00 15,000.00
JUMLAH TENAGA KERJA 148,750.00
B BAHAN
Beton Ready Mixed K-250 ( Batu M.09. x M3 1.02 1,080,000.00 1,101,600.00
Split / Batu Pecah)
JUMLAH HARGA BAHAN 1,101,600.00
C PERALATAN
Pompa dan Conveyor Beton E.35 Sewa- 0.12 -
Hari
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 1,250,350.00
E Overhead & Profit ( 10 % ) 10% x D 125,035.00
F Harga Satuan Pekerjaan (D+E) 1,375,385.00
14 Membuat Beton Camp. 1 PC : 3 Psr : 5 Krk
Permenpupera No. 28/PRT/M/2016 Hal. 242
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.320 Rp 100,000.00 Rp 132,000.00
Tukang Batu L.02 OH 0.220 Rp 120,000.00 Rp 26,400.00
Kepala Tukang L.02 OH 0.022 Rp 150,000.00 Rp 3,300.00
Mandor L.02 OH 0.132 Rp 150,000.00 Rp 19,800.00
JUMLAH TENAGA KERJA Rp 181,500.00
B BAHAN
Semen Portland Kg 200.000 Rp 1,550.00 Rp 310,000.00
Pasir Beton M3 0.522 Rp 173,000.00 Rp 90,306.00
Kerikil M3 0.862 Rp 191,300.00 Rp 164,900.60
JUMLAH HARGA BAHAN Rp 565,206.60
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 746,706.60
E Overhead & Profit ( 10 % ) 10% x D Rp 74,670.66
F Harga Satuan Pekerjaan (D+E) Rp 821,377.26
A TENAGA
Pekerja L.01 OH 1.320 Rp 100,000.00 Rp 132,000.00
Tukang Batu L.02 OH 0.220 Rp 120,000.00 Rp 26,400.00
Kepala Tukang L.02 OH 0.022 Rp 150,000.00 Rp 3,300.00
Mandor L.02 OH 0.132 Rp 150,000.00 Rp 19,800.00
JUMLAH TENAGA KERJA Rp 181,500.00
B BAHAN
Semen Portland Kg 220.000 Rp 1,550.00 Rp 341,000.00
Pasir Beton M3 0.588 Rp 173,000.00 Rp 101,724.00
Kerikil M3 0.755 Rp 191,300.00 Rp 144,431.50
JUMLAH HARGA BAHAN Rp 587,155.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 768,655.50
E Overhead & Profit ( 10 % ) 10% x D Rp 76,865.55
F Harga Satuan Pekerjaan (D+E) Rp 845,521.05
16 Membuat 1 M3 Beton Mutu F'c = 14,5 Mpa Atau Setara K 175, Slump ( 120±20 ) MM
Permenpupera No. 28/PRT/M/2016 Hal. 592
A TENAGA
Pekerja L.01 OH 1.650 Rp 100,000.00 Rp 165,000.00
Tukang Batu L.02 OH 0.275 Rp 120,000.00 Rp 33,000.00
Kepala Tukang L.02 OH 0.028 Rp 150,000.00 Rp 4,200.00
Mandor L.02 OH 0.083 Rp 150,000.00 Rp 12,450.00
JUMLAH TENAGA KERJA Rp 214,650.00
B BAHAN
Semen Portland Kg 326.00 1,550.00 505,300.00
Pasir Beton Kg 760.00 108.13 82,175.00
Kerikil Kg 1,029.00 103.41 106,404.16
Air Kerja Liter 215.00 200.00 43,000.00
JUMLAH HARGA BAHAN 736,879.16
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 951,529.16
E Overhead & Profit ( 10 % ) 10% x D Rp 95,152.92
F Harga Satuan Pekerjaan (D+E) Rp 1,046,682.08
A TENAGA
Pekerja L.01 OH 1.650 Rp 100,000.00 Rp 165,000.00
Tukang Batu L.02 OH 0.275 Rp 120,000.00 Rp 33,000.00
Kepala Tukang L.02 OH 0.028 Rp 150,000.00 Rp 4,200.00
Mandor L.02 OH 0.083 Rp 150,000.00 Rp 12,450.00
JUMLAH TENAGA KERJA Rp 214,650.00
B BAHAN
Semen Portland Kg 384.00 1,550.00 595,200.00
Pasir Beton Kg 692.00 108.13 74,822.50
Kerikil Kg 1,039.00 103.41 107,438.22
Air Kerja Liter 215.00 200.00 43,000.00
JUMLAH HARGA BAHAN 820,460.72
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,035,110.72
E Overhead & Profit ( 10 % ) 10% x D Rp 103,511.07
F Harga Satuan Pekerjaan (D+E) Rp 1,138,621.79
A TENAGA
Pekerja L.01 OH 1.650 Rp 100,000.00 Rp 165,000.00
Tukang Batu L.02 OH 0.275 Rp 120,000.00 Rp 33,000.00
Kepala Tukang L.02 OH 0.028 Rp 150,000.00 Rp 4,200.00
Mandor L.02 OH 0.083 Rp 150,000.00 Rp 12,450.00
JUMLAH TENAGA KERJA Rp 214,650.00
B BAHAN
Semen Portland Kg 413.00 1,550.00 640,150.00
Pasir Beton Kg 681.00 108.13 73,633.13
Kerikil Kg 1,021.00 103.41 105,576.92
Air Kerja Liter 215.00 200.00 43,000.00
JUMLAH HARGA BAHAN 862,360.04
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,077,010.04
E Overhead & Profit ( 10 % ) 10% x D Rp 107,701.00
F Harga Satuan Pekerjaan (D+E) Rp 1,184,711.05
V. PEKERJAAN BESI DAN ALUMINIUM
A TENAGA
Pekerja L.01 OH 1.200 Rp 100,000.00 Rp 120,000.00
Tukang Las Biasa L.03 OH 1.200 Rp 120,000.00 Rp 144,000.00
Kepala Tukang L.03 OH 0.120 Rp 150,000.00 Rp 18,000.00
Mandor L.04 OH 0.006 Rp 150,000.00 Rp 900.00
JUMLAH TENAGA KERJA Rp 282,900.00
B BAHAN
Folding Gate M2 1.000 Rp 755,000.00 Rp 755,000.00
JUMLAH HARGA BAHAN Rp 755,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,037,900.00
E Overhead & Profit ( 10 % ) 10% x D Rp 103,790.00
F Harga Satuan Pekerjaan (D+E) Rp 1,141,690.00
A TENAGA
Pekerja L.01 OH 0.250 Rp 100,000.00 Rp 25,000.00
Tukang Besi L.03 OH 0.250 Rp 120,000.00 Rp 30,000.00
Kepala Tukang L.03 OH 0.025 Rp 150,000.00 Rp 3,750.00
Mandor L.04 OH 0.013 Rp 150,000.00 Rp 1,950.00
JUMLAH TENAGA KERJA Rp 60,700.00
B BAHAN
Rangka Besi Hollow (20x40x1,1) MM M' 3.500 Rp 18,700.00 Rp 65,450.00
Assesoris (Perkuatan, Las DLL) LS 25% x Rp 16,362.50
Rangka
JUMLAH HARGA BAHAN Rp 81,812.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 142,512.50
E Overhead & Profit ( 10 % ) 10% x D Rp 14,251.25
F Harga Satuan Pekerjaan (D+E) Rp 156,763.75
A TENAGA
Pekerja L.01 OH 0.350 Rp 100,000.00 Rp 35,000.00
Tukang Besi L.03 OH 0.350 Rp 120,000.00 Rp 42,000.00
Kepala Tukang L.03 OH 0.035 Rp 150,000.00 Rp 5,250.00
Mandor L.04 OH 0.018 Rp 150,000.00 Rp 2,700.00
JUMLAH TENAGA KERJA Rp 84,950.00
B BAHAN
Rangka Besi Hollow (20x40x1,1) MM M' 4.000 Rp 18,700.00 Rp 74,800.00
Assesoris (Perkuatan, Las DLL) LS 25% x Rp 18,700.00
Rangka
JUMLAH HARGA BAHAN Rp 93,500.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 178,450.00
E Overhead & Profit ( 10 % ) 10% x D Rp 17,845.00
F Harga Satuan Pekerjaan (D+E) Rp 196,295.00
VI. PEKERJAAN PASANGAN DINDING
A TENAGA
Pekerja L.01 OH 0.600 Rp 100,000.00 Rp 60,000.00
Tukang Batu L.02 OH 0.200 Rp 120,000.00 Rp 24,000.00
Kepala Tukang L.03 OH 0.020 Rp 150,000.00 Rp 3,000.00
Mandor L.04 OH 0.030 Rp 150,000.00 Rp 4,500.00
JUMLAH TENAGA KERJA Rp 91,500.00
B BAHAN
Bata Merah Buah 140.000 Rp 600.00 Rp 84,000.00
Semen Protland Kg 26.550 Rp 1,550.00 Rp 41,152.50
Pasir Pasang M3 0.093 Rp 145,000.00 Rp 13,485.00
JUMLAH HARGA BAHAN Rp 138,637.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 230,137.50
E Overhead & Profit ( 10 % ) 10% x D Rp 23,013.75
F Harga Satuan Pekerjaan (D+E) Rp 253,151.25
3 Pemasangan 1 M2 dinding bata merah tebal 1/2 batu camp. 1PC:2PP
Permen PUPERA No. 28 /PRT/M/2016 Hal. 632
A TENAGA
Pekerja L.01 OH 0.300 Rp 100,000.00 Rp 30,000.00
Tukang Batu L.02 OH 0.100 Rp 120,000.00 Rp 12,000.00
Kepala Tukang L.03 OH 0.010 Rp 150,000.00 Rp 1,500.00
Mandor L.04 OH 0.015 Rp 150,000.00 Rp 2,250.00
JUMLAH TENAGA KERJA Rp 45,750.00
B BAHAN
Bata Merah Buah 70.000 Rp 600.00 Rp 42,000.00
Semen Protland Kg 18.950 Rp 1,550.00 Rp 29,372.50
3
Pasir Pasang M 0.038 Rp 145,000.00 Rp 5,510.00
JUMLAH HARGA BAHAN Rp 76,882.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 122,632.50
E Overhead & Profit ( 10 % ) 10% x D Rp 12,263.25
F Harga Satuan Pekerjaan (D+E) Rp 134,895.75
A TENAGA
Pekerja L.01 OH 0.300 Rp 100,000.00 Rp 30,000.00
Tukang Batu L.02 OH 0.100 Rp 120,000.00 Rp 12,000.00
Kepala Tukang L.03 OH 0.010 Rp 150,000.00 Rp 1,500.00
Mandor L.04 OH 0.015 Rp 150,000.00 Rp 2,250.00
JUMLAH TENAGA KERJA Rp 45,750.00
B BAHAN
Bata Merah Buah 70.000 Rp 600.00 Rp 42,000.00
Semen Protland Kg 11.500 Rp 1,550.00 Rp 17,825.00
3
Pasir Pasang M 0.043 Rp 145,000.00 Rp 6,235.00
JUMLAH HARGA BAHAN Rp 66,060.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 111,810.00
E Overhead & Profit ( 10 % ) 10% x D Rp 11,181.00
F Harga Satuan Pekerjaan (D+E) Rp 122,991.00
VII. PEKERJAAN PLESTERAN
6 Pemasangan 1 M2 Acian
Permen PUPERA No. 28 /PRT/M/2016 Hal. 655
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.200 Rp 100,000.00 Rp 20,000.00
Tukang Batu L.03 OH 0.100 Rp 120,000.00 Rp 12,000.00
Kepala Tukang L.03 OH 0.010 Rp 150,000.00 Rp 1,500.00
Mandor L.04 OH 0.010 Rp 150,000.00 Rp 1,500.00
JUMLAH TENAGA KERJA Rp 35,000.00
B BAHAN
Portland Cement Kg 3.250 1,550.00 Rp 5,037.50
JUMLAH HARGA BAHAN Rp 5,037.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 40,037.50
E Overhead & Profit ( 10 % ) 10% x D Rp 4,003.75
F Harga Satuan Pekerjaan (D+E) Rp 44,041.25
A TENAGA
Pekerja L.01 OH 0.150 Rp 100,000.00 Rp 15,000.00
Tukang Batu L.03 OH 0.075 Rp 120,000.00 Rp 9,000.00
Kepala Tukang L.03 OH 0.008 Rp 150,000.00 Rp 1,200.00
Mandor L.04 OH 0.008 Rp 150,000.00 Rp 1,200.00
JUMLAH TENAGA KERJA Rp 26,400.00
B BAHAN
Portland Cement Kg 3.108 1,550.00 Rp 4,817.40
JUMLAH HARGA BAHAN Rp 4,817.40
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 31,217.40
E Overhead & Profit ( 10 % ) 10% x D Rp 3,121.74
F Harga Satuan Pekerjaan (D+E) Rp 34,339.14
VIII. PEKERJAAN PENUTUP LANTAI & PENUTUP DINDING
A TENAGA
Pekerja L.01 OH 0.270 Rp 100,000.00 Rp 27,000.00
Tukang Batu L.02 OH 0.135 Rp 120,000.00 Rp 16,200.00
Kepala Tukang L.03 OH 0.014 Rp 150,000.00 Rp 2,100.00
Mandor L.04 OH 0.014 Rp 150,000.00 Rp 2,100.00
JUMLAH TENAGA KERJA Rp 47,400.00
B BAHAN
Keramik Uk. 20x20 CM Bh 26.500 Rp 3,400.00 Rp 90,100.00
Semen portland Kg 10.400 Rp 1,550.00 Rp 16,120.00
Semen Warna Kg 1.000 Rp 3,100.00 Rp 3,100.00
Pasir Pasang M3 0.045 Rp 145,000.00 Rp 6,525.00
JUMLAH HARGA BAHAN Rp 115,845.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 163,245.00
E Overhead & Profit ( 10 % ) 10% x D Rp 16,324.50
F Harga Satuan Pekerjaan (D+E) Rp 179,569.50
3 Pemasangan 1 M2 Lantai Granit Uk. 60/60 CM
Permen PUPERA No. 28 /PRT/M/2016 Hal. 663
A TENAGA
Pekerja L.01 OH 0.240 Rp 100,000.00 Rp 24,000.00
Tukang Batu L.02 OH 0.120 Rp 120,000.00 Rp 14,400.00
Kepala Tukang L.03 OH 0.012 Rp 150,000.00 Rp 1,800.00
Mandor L.04 OH 0.012 Rp 150,000.00 Rp 1,800.00
JUMLAH TENAGA KERJA Rp 42,000.00
B BAHAN
Granit Uk. 60 x 60 cm Bh 3.100 Rp 61,000.00 Rp 189,100.00
Semen portland Kg 9.600 Rp 1,550.00 Rp 14,880.00
Semen warna Kg 1.500 Rp 3,100.00 Rp 4,650.00
Pasir Pasang M3 0.045 Rp 145,000.00 Rp 6,525.00
JUMLAH HARGA BAHAN Rp 215,155.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 257,155.00
E Overhead & Profit ( 10 % ) 10% x D Rp 25,715.50
F Harga Satuan Pekerjaan (D+E) Rp 282,870.50
A TENAGA
Pekerja L.01 OH 0.090 Rp 100,000.00 Rp 9,000.00
Tukang Batu L.02 OH 0.090 Rp 120,000.00 Rp 10,800.00
Kepala Tukang L.03 OH 0.009 Rp 150,000.00 Rp 1,350.00
Mandor L.04 OH 0.005 Rp 150,000.00 Rp 750.00
JUMLAH TENAGA KERJA Rp 21,900.00
B BAHAN
Keramik Uk. 20 x 20 cm Buah 2.500 Rp 3,400.00 Rp 8,500.00
Semen portland Kg 1.140 Rp 1,550.00 Rp 1,767.00
Semen warna Kg 0.150 Rp 3,100.00 Rp 465.00
3
Pasir Pasang M 0.003 Rp 145,000.00 Rp 435.00
JUMLAH HARGA BAHAN Rp 11,167.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 33,067.00
E Overhead & Profit ( 10 % ) 10% x D Rp 3,306.70
F Harga Satuan Pekerjaan (D+E) Rp 36,373.70
A TENAGA
Pekerja L.01 OH 0.090 Rp 100,000.00 Rp 9,000.00
Tukang Batu L.02 OH 0.090 Rp 120,000.00 Rp 10,800.00
Kepala Tukang L.03 OH 0.009 Rp 150,000.00 Rp 1,350.00
Mandor L.04 OH 0.005 Rp 150,000.00 Rp 750.00
JUMLAH TENAGA KERJA Rp 21,900.00
B BAHAN
Keramik Uk. 40 x 40 cm Buah 0.750 Rp 13,300.00 Rp 9,975.00
Semen portland Kg 1.140 Rp 1,550.00 Rp 1,767.00
Semen warna Kg 0.100 Rp 3,100.00 Rp 310.00
Pasir Pasang M3 0.003 Rp 145,000.00 Rp 435.00
JUMLAH HARGA BAHAN Rp 12,487.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 34,387.00
E Overhead & Profit ( 10 % ) 10% x D Rp 3,438.70
F Harga Satuan Pekerjaan (D+E) Rp 37,825.70
A TENAGA
Pekerja L.01 OH 0.090 Rp 100,000.00 Rp 9,000.00
Tukang Batu L.02 OH 0.090 Rp 120,000.00 Rp 10,800.00
Kepala Tukang L.03 OH 0.009 Rp 150,000.00 Rp 1,350.00
Mandor L.04 OH 0.005 Rp 150,000.00 Rp 750.00
JUMLAH TENAGA KERJA Rp 21,900.00
B BAHAN
Granit Uk. 60 x 60 cm Buah 0.333 Rp 61,000.00 Rp 20,333.33
Semen portland Kg 1.140 Rp 1,550.00 Rp 1,767.00
Semen warna Kg 0.100 Rp 3,100.00 Rp 310.00
Pasir Pasang M3 0.003 Rp 145,000.00 Rp 435.00
JUMLAH HARGA BAHAN Rp 22,845.33
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 44,745.33
E Overhead & Profit ( 10 % ) 10% x D Rp 4,474.53
F Harga Satuan Pekerjaan (D+E) Rp 49,219.87
A TENAGA
Pekerja L.01 OH 0.900 Rp 100,000.00 Rp 90,000.00
Tukang Batu L.02 OH 0.450 Rp 120,000.00 Rp 54,000.00
Kepala Tukang L.03 OH 0.045 Rp 150,000.00 Rp 6,750.00
Mandor L.04 OH 0.045 Rp 150,000.00 Rp 6,750.00
JUMLAH TENAGA KERJA Rp 157,500.00
B BAHAN
Keramik Uk. 20 x 20 cm Buah 26.500 Rp 3,400.00 Rp 90,100.00
Semen portland Kg 9.300 Rp 1,550.00 Rp 14,415.00
Pasir pasang M3 0.018 Rp 145,000.00 Rp 2,610.00
Semen warna Kg 1.940 Rp 3,100.00 Rp 6,014.00
JUMLAH HARGA BAHAN Rp 113,139.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 270,639.00
E Overhead & Profit ( 10 % ) 10% x D Rp 27,063.90
F Harga Satuan Pekerjaan (D+E) Rp 297,702.90
A TENAGA
Pekerja L.01 OH 0.170 Rp 100,000.00 Rp 17,000.00
Tukang Kayu L.02 OH 0.170 Rp 120,000.00 Rp 20,400.00
Kepala Tukang L.03 OH 0.017 Rp 150,000.00 Rp 2,550.00
Mandor L.04 OH 0.009 Rp 150,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 41,300.00
B BAHAN
Karpet M2 1.050 Rp 38,750.00 Rp 40,687.50
Lem Kg 0.350 Rp 35,400.00 Rp 12,390.00
JUMLAH HARGA BAHAN Rp 53,077.50
C PERALATAN
JUMLAH HARGA ALAT Rp 94,377.50
D Jumlah (A+B+C) Rp 9,437.75
E Overhead & Profit ( 10 % ) 10% x D Rp 103,815.25
F Harga Satuan Pekerjaan (D+E) Rp 103,815.25
A TENAGA
Pekerja L.01 OH 0.700 Rp 100,000.00 Rp 70,000.00
Tukang Kayu L.02 OH 0.350 Rp 120,000.00 Rp 42,000.00
Kepala Tukang L.03 OH 0.035 Rp 150,000.00 Rp 5,250.00
Mandor L.04 OH 0.035 Rp 150,000.00 Rp 5,250.00
JUMLAH TENAGA KERJA Rp 122,500.00
B BAHAN
Parquet M2 1.050 Rp 200,200.00 Rp 210,210.00
Lem Kg 0.600 Rp 35,400.00 Rp 21,240.00
JUMLAH HARGA BAHAN Rp 231,450.00
C PERALATAN
JUMLAH HARGA ALAT Rp 353,950.00
D Jumlah (A+B+C) Rp 35,395.00
E Overhead & Profit ( 10 % ) 10% x D Rp 389,345.00
F Harga Satuan Pekerjaan (D+E) Rp 389,345.00
A TENAGA
Pekerja L.01 OH 0.700 Rp 100,000.00 Rp 70,000.00
Tukang Batu L.02 OH 0.350 Rp 120,000.00 Rp 42,000.00
Kepala Tukang L.03 OH 0.035 Rp 150,000.00 Rp 5,250.00
Mandor L.04 OH 0.035 Rp 150,000.00 Rp 5,250.00
JUMLAH TENAGA KERJA Rp 122,500.00
B BAHAN
Batu Tempel Uk. 20 x 20 CM Bh 26.500 Rp 5,100.00 Rp 135,150.00
Semen Portland Kg 11.750 Rp 1,550.00 Rp 18,212.50
Pasir Pasang M3 0.035 Rp 145,000.00 Rp 5,075.00
JUMLAH HARGA BAHAN Rp 158,437.50
C PERALATAN
JUMLAH HARGA ALAT Rp 280,937.50
D Jumlah (A+B+C) Rp 28,093.75
E Overhead & Profit ( 10 % ) 10% x D Rp 309,031.25
F Harga Satuan Pekerjaan (D+E) Rp 309,031.25
IX. PEKERJAAN PLAFOND
A TENAGA
Pekerja L.01 OH 0.500 Rp 100,000.00 Rp 50,000.00
Tukang Kayu L.02 OH 0.500 Rp 120,000.00 Rp 60,000.00
Kepala Tukang L.03 OH 0.050 Rp 150,000.00 Rp 7,500.00
Mandor L.04 OH 0.030 Rp 150,000.00 Rp 4,500.00
JUMLAH TENAGA KERJA Rp 122,000.00
B BAHAN
Kayu papan Kelas II M3 0.012 Rp 2,695,000.00 Rp 32,340.00
Paku tripleks Kg 0.008 Rp 28,550.00 Rp 228.40
JUMLAH HARGA BAHAN Rp 32,568.40
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 154,568.40
E Overhead & Profit ( 10 % ) 10% x D Rp 15,456.84
F Harga Satuan Pekerjaan (D+E) Rp 170,025.24
3 Pemasangan 1 M2 langit-langit gypsum board ukuran (120x240x9)mm, tebal 9 mm
Permen PUPERA No. 28 /PRT/M/2016 Hal. 693
A TENAGA
Pekerja L.01 OH 0.100 Rp 100,000.00 Rp 10,000.00
Tukang Kayu L.02 OH 0.050 Rp 120,000.00 Rp 6,000.00
Kepala Tukang L.03 OH 0.005 Rp 150,000.00 Rp 750.00
Mandor L.04 OH 0.005 Rp 150,000.00 Rp 750.00
JUMLAH TENAGA KERJA Rp 17,500.00
B BAHAN
Gypsum board Tebal 9 MM Lembar 0.364 Rp 96,400.00 Rp 35,089.60
Paku skrup Kg 0.110 Rp 40,200.00 Rp 4,422.00
JUMLAH HARGA BAHAN Rp 39,511.60
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 57,011.60
E Overhead & Profit ( 10 % ) 10% x D Rp 5,701.16
F Harga Satuan Pekerjaan (D+E) Rp 62,712.76
A TENAGA
Pekerja L.01 OH 0.050 Rp 100,000.00 Rp 5,000.00
Tukang Kayu L.02 OH 0.050 Rp 120,000.00 Rp 6,000.00
Kepala Tukang L.03 OH 0.005 Rp 150,000.00 Rp 750.00
Mandor L.04 OH 0.003 Rp 150,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 12,200.00
B BAHAN
List kayu profil M 1.050 Rp 2,700.00 Rp 2,835.00
Paku Kg 0.010 Rp 28,550.00 Rp 285.50
JUMLAH HARGA BAHAN Rp 3,120.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 15,320.50
E Overhead & Profit ( 10 % ) 10% x D Rp 1,532.05
F Harga Satuan Pekerjaan (D+E) Rp 16,852.55
X. PEKERJAAN ATAP
A TENAGA
Pekerja L.01 OH 0.120 Rp 100,000.00 Rp 12,000.00
Tukang Kayu L.03 OH 0.060 Rp 120,000.00 Rp 7,200.00
Kepala Tukang L.11 OH 0.006 Rp 150,000.00 Rp 900.00
Mandor L.15 OH 0.006 Rp 150,000.00 Rp 900.00
JUMLAH TENAGA KERJA Rp 21,000.00
B BAHAN
Seng gelombang Lembar 0.700 Rp 50,500.00 Rp 35,350.00
paku biasa 1/2"-1" Kg 0.020 Rp 28,550.00 Rp 571.00
JUMLAH HARGA BAHAN Rp 35,921.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 56,921.00
E Overhead & Profit ( 10 % ) 10% x D Rp 5,692.10
F Harga Satuan Pekerjaan (D+E) Rp 62,613.10
A TENAGA
Pekerja L.01 OH 0.150 Rp 100,000.00 Rp 15,000.00
Tukang Kayu L.03 OH 0.070 Rp 120,000.00 Rp 8,400.00
Kepala Tukang L.11 OH 0.007 Rp 150,000.00 Rp 1,050.00
Mandor L.15 OH 0.006 Rp 150,000.00 Rp 900.00
JUMLAH TENAGA KERJA Rp 25,350.00
B BAHAN
Seng plat Lembar 0.300 Rp 50,500.00 Rp 15,150.00
paku biasa 1/2"-1" Kg 0.040 Rp 28,550.00 Rp 1,142.00
JUMLAH HARGA BAHAN Rp 16,292.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 41,642.00
E Overhead & Profit ( 10 % ) 10% x D Rp 4,164.20
F Harga Satuan Pekerjaan (D+E) Rp 45,806.20
A TENAGA
Pekerja L.01 OH 0.150 Rp 100,000.00 Rp 15,000.00
Tukang Kayu L.03 OH 0.050 Rp 120,000.00 Rp 6,000.00
Kepala Tukang L.11 OH 0.005 Rp 150,000.00 Rp 750.00
Mandor L.15 OH 0.008 Rp 150,000.00 Rp 1,200.00
JUMLAH TENAGA KERJA Rp 22,950.00
B BAHAN
Aluminium foil M2 1.050 15,300.00 Rp 16,065.00
JUMLAH HARGA BAHAN Rp 16,065.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 39,015.00
E Overhead & Profit ( 10 % ) 10% x D Rp 3,901.50
F Harga Satuan Pekerjaan (D+E) Rp 42,916.50
A TENAGA
Pekerja L.01 OH 0.120 Rp 100,000.00 Rp 12,000.00
Tukang Kayu L.03 OH 0.060 Rp 120,000.00 Rp 7,200.00
Kepala Tukang L.11 OH 0.006 Rp 150,000.00 Rp 900.00
Mandor L.15 OH 0.006 Rp 150,000.00 Rp 900.00
JUMLAH TENAGA KERJA Rp 21,000.00
B BAHAN
Atap Spandek Tebal 0,30 MM M2 1.000 Rp 46,000.00 Rp 46,000.00
paku biasa 1/2"-1" Kg 0.020 Rp 28,550.00 Rp 571.00
JUMLAH HARGA BAHAN Rp 46,571.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 67,571.00
E Overhead & Profit ( 10 % ) 10% x D Rp 6,757.10
F Harga Satuan Pekerjaan (D+E) Rp 74,328.10
XI. HARGA SATUAN PEKERJAAN KAYU
1 Pembuatan & Pemasangan 1 m3 Kusen Pintu dan Kusen Jendela, Kayu Kelas I
Permen PUPERA No. 28 /PRT/M/2016 Hal. 716
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 7.000 Rp 100,000.00 Rp 700,000.00
Tukang Kayu L.02 OH 21.000 Rp 120,000.00 Rp 2,520,000.00
Kepala Tukang L.03 OH 2.100 Rp 150,000.00 Rp 315,000.00
Mandor L.04 OH 0.350 Rp 150,000.00 Rp 52,500.00
JUMLAH TENAGA KERJA Rp 3,587,500.00
B BAHAN
Balok Kayu Kelas I M3 1.100 Rp 5,585,000.00 Rp 6,143,500.00
Paku 10 cm Kg 1.250 Rp 28,550.00 Rp 35,687.50
Lem Kayu Kg 1.000 Rp 26,400.00 Rp 26,400.00
JUMLAH HARGA BAHAN Rp 6,205,587.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 9,793,087.50
E Overhead & Profit ( 10 % ) 10% x D Rp 979,308.75
F Harga Satuan Pekerjaan (D+E) Rp 10,772,396.25
2 Pembuatan & Pemasangan 1 M3 Kusen Pintu dan Kusen Jendela Kayu Kelas II
Permen PUPERA No. 28 /PRT/M/2016 Hal. 717
A TENAGA
Pekerja L.01 OH 6.000 Rp 100,000.00 Rp 600,000.00
Tukang Kayu L.02 OH 18.000 Rp 120,000.00 Rp 2,160,000.00
Kepala Tukang L.03 OH 1.800 Rp 150,000.00 Rp 270,000.00
Mandor L.04 OH 0.300 Rp 150,000.00 Rp 45,000.00
JUMLAH TENAGA KERJA Rp 3,075,000.00
B BAHAN
Balok Kayu Kelas II M3 1.200 Rp 2,695,000.00 Rp 3,234,000.00
Paku 10 cm Kg 1.250 Rp 28,550.00 Rp 35,687.50
Lem Kayu Kg 1.000 26,400.00 Rp 26,400.00
JUMLAH HARGA BAHAN Rp 3,296,087.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 6,371,087.50
E Overhead & Profit ( 10 % ) 10% x D Rp 637,108.75
F Harga Satuan Pekerjaan (D+E) Rp 7,008,196.25
3 Pembuatan & Pemasangan 1 M2 Daun Pintu Panel, Kayu Kelas II
Permen PUPERA No. 28 /PRT/M/2016 Hal. 718
A TENAGA
Pekerja L.01 OH 1.000 Rp 100,000.00 Rp 100,000.00
Tukang Kayu L.02 OH 3.000 Rp 120,000.00 Rp 360,000.00
Kepala Tukang L.03 OH 0.300 Rp 150,000.00 Rp 45,000.00
Mandor L.04 OH 0.050 Rp 150,000.00 Rp 7,500.00
JUMLAH TENAGA KERJA Rp 512,500.00
B BAHAN
Papan Kayu Kelas II M3 0.040 Rp 2,695,000.00 Rp 107,800.00
Lem Kayu Kg 0.500 Rp 26,400.00 Rp 13,200.00
JUMLAH HARGA BAHAN Rp 121,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 633,500.00
E Overhead & Profit ( 10 % ) 10% x D Rp 63,350.00
F Harga Satuan Pekerjaan (D+E) Rp 696,850.00
A TENAGA
Pekerja L.01 OH 0.800 Rp 100,000.00 Rp 80,000.000
Tukang Kayu L.02 OH 2.400 Rp 120,000.00 Rp 288,000.000
Kepala Tukang L.03 OH 0.240 Rp 150,000.00 Rp 36,000.000
Mandor L.04 OH 0.040 Rp 150,000.00 Rp 6,000.000
JUMLAH TENAGA KERJA Rp 410,000.00
B BAHAN
Papan Kayu Kelas II M3 0.024 Rp 2,695,000.00 Rp 64,680.00
Kaca Tebal 3 MM M2 1.000 Rp 90,800.00 Rp 90,800.00
Lem Kayu Kg 0.300 Rp 26,400.00 Rp 7,920.00
JUMLAH HARGA BAHAN Rp 163,400.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 573,400.00
E Overhead & Profit ( 10 % ) 10% x D Rp 57,340.00
F Harga Satuan Pekerjaan (D+E) Rp 630,740.00
A TENAGA
Pekerja L.01 OH 1.000 Rp 100,000.00 Rp 100,000.00
Tukang Kayu L.02 OH 3.000 Rp 120,000.00 Rp 360,000.00
Kepala Tukang L.03 OH 0.300 Rp 150,000.00 Rp 45,000.00
Mandor L.04 OH 0.050 Rp 150,000.00 Rp 7,500.00
JUMLAH TENAGA KERJA Rp 512,500.00
B BAHAN
Papan Kayu Kelas II M3 0.064 Rp 2,695,000.00 Rp 172,480.00
Lem Kayu Kg 0.500 Rp 26,400.00 Rp 13,200.00
JUMLAH HARGA BAHAN Rp 185,680.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 698,180.00
E Overhead & Profit ( 10 % ) 10% x D Rp 69,818.00
F Harga Satuan Pekerjaan (D+E) Rp 767,998.00
A TENAGA
Pekerja L.01 OH 6.700 Rp 100,000.00 Rp 670,000.000
Tukang Kayu L.02 OH 20.100 Rp 120,000.00 Rp 2,412,000.000
Kepala Tukang L.03 OH 2.010 Rp 150,000.00 Rp 301,500.000
Mandor L.04 OH 0.335 Rp 150,000.00 Rp 50,250.000
JUMLAH TENAGA KERJA Rp 3,433,750.000
B BAHAN
Balok Kayu Kelas II M3 1.100 Rp 2,695,000.00 Rp 2,964,500.00
Besi strip tebal 5mm Kg 15.000 Rp 12,200.00 Rp 183,000.00
Paku 12 cm Kg 3.000 Rp 28,550.00 Rp 85,650.00
JUMLAH HARGA BAHAN Rp 3,233,150.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 6,666,900.00
E Overhead & Profit ( 10 % ) 10% x D Rp 666,690.00
F Harga Satuan Pekerjaan (D+E) Rp 7,333,590.00
A TENAGA
Pekerja L.01 OH 0.200 Rp 100,000.00 Rp 20,000.000
Tukang Kayu L.02 OH 0.300 Rp 120,000.00 Rp 36,000.000
Kepala Tukang L.03 OH 0.030 Rp 150,000.00 Rp 4,500.000
Mandor L.04 OH 0.010 Rp 150,000.00 Rp 1,500.000
JUMLAH TENAGA KERJA Rp 62,000.00
B BAHAN
Balok Kayu Kelas II M3 0.0163 Rp 2,695,000.00 Rp 43,928.50
Paku 7 – 10 cm Kg 0.250 Rp 28,550.00 Rp 7,137.50
JUMLAH HARGA BAHAN Rp 51,066.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 113,066.00
E Overhead & Profit ( 10 % ) 10% x D Rp 11,306.60
F Harga Satuan Pekerjaan (D+E) Rp 124,372.60
A TENAGA
Pekerja L.01 OH 0.150 Rp 100,000.00 Rp 15,000.000
Tukang Kayu L.02 OH 0.450 Rp 120,000.00 Rp 54,000.000
Kepala Tukang L.03 OH 0.045 Rp 150,000.00 Rp 6,750.000
Mandor L.04 OH 0.008 Rp 150,000.00 Rp 1,200.000
JUMLAH TENAGA KERJA Rp 76,950.00
B BAHAN
Balok Kayu Kelas II M3 0.028 Rp 2,695,000.00 Rp 75,460.00
Paku 7 – 10 cm Kg 0.150 Rp 28,550.00 Rp 4,282.50
JUMLAH HARGA BAHAN Rp 79,742.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 156,692.50
E Overhead & Profit ( 10 % ) 10% x D Rp 15,669.25
F Harga Satuan Pekerjaan (D+E) Rp 172,361.75
A TENAGA
Pekerja L.01 OH 0.200 Rp 100,000.00 Rp 20,000.000
Tukang Kayu L.03 OH 0.600 Rp 120,000.00 Rp 72,000.000
Kepala Tukang L.03 OH 0.060 Rp 150,000.00 Rp 9,000.000
Mandor L.04 OH 0.010 Rp 150,000.00 Rp 1,500.000
JUMLAH TENAGA KERJA Rp 102,500.00
B BAHAN
Balok Kayu Kelas II M3 0.028 Rp 2,695,000.00 Rp 75,460.00
Paku 7 – 10 cm Kg 0.150 Rp 28,550.00 Rp 4,282.50
Plywood 4 MM Uk.120 x 240 CM Lembar 0.860 Rp 86,100.00 Rp 74,046.00
Lem Kayu Kg 0.560 Rp 26,400.00 Rp 14,784.00
JUMLAH HARGA BAHAN Rp 168,572.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 271,072.50
E Overhead & Profit ( 10 % ) 10% x D Rp 27,107.25
F Harga Satuan Pekerjaan (D+E) Rp 298,179.75
11 Pemasangan 1 M' Listplank Ukuran ( 3x20 ) cm , Kayu Kelas II
Permen PUPERA No. 28 /PRT/M/2016 Hal. 726
A TENAGA
Pekerja L.01 OH 0.100 Rp 100,000.00 Rp 10,000.000
Tukang Kayu L.03 OH 0.200 Rp 120,000.00 Rp 24,000.000
Kepala Tukang L.03 OH 0.020 Rp 150,000.00 Rp 3,000.000
Mandor L.04 OH 0.005 Rp 150,000.00 Rp 750.000
JUMLAH TENAGA KERJA Rp 37,750.00
B BAHAN
Papan Kayu Kelas II M3 0.0108 Rp 2,695,000.00 Rp 29,106.00
Paku 5 dan 7 cm Kg 0.100 Rp 28,550.00 Rp 2,855.00
JUMLAH HARGA BAHAN Rp 31,961.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 69,711.00
E Overhead & Profit ( 10 % ) 10% x D Rp 6,971.10
F Harga Satuan Pekerjaan (D+E) Rp 76,682.10
XII. PEKERJAAN KUNCI DAN KACA
A TENAGA
Pekerja L.01 OH 0.010 Rp 100,000.00 Rp 1,000.00
Tukang Kayu L.02 OH 0.500 Rp 120,000.00 Rp 60,000.00
Kepala Tukang L.03 OH 0.050 Rp 150,000.00 Rp 7,500.00
Mandor L.04 OH 0.005 Rp 150,000.00 Rp 750.00
JUMLAH TENAGA KERJA Rp 69,250.00
B BAHAN
Kunci Tanam Biasa Bh 1.000 130,150.00 Rp 130,150.00
JUMLAH HARGA BAHAN Rp 130,150.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 199,400.00
E Overhead & Profit ( 10 % ) 10% x D Rp 19,940.00
F Harga Satuan Pekerjaan (D+E) Rp 219,340.00
A TENAGA
Pekerja L.01 OH 0.015 Rp 100,000.00 Rp 1,500.00
Tukang Kayu L.02 OH 0.150 Rp 120,000.00 Rp 18,000.00
Kepala Tukang L.03 OH 0.015 Rp 150,000.00 Rp 2,250.00
Mandor L.04 OH 0.0008 Rp 150,000.00 Rp 120.00
JUMLAH TENAGA KERJA Rp 21,870.00
B BAHAN
Engsel pintu Buah 1.000 Rp 14,150.00 Rp 14,150.00
JUMLAH HARGA BAHAN Rp 14,150.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 36,020.00
E Overhead & Profit ( 10 % ) 10% x D Rp 3,602.00
F Harga Satuan Pekerjaan (D+E) Rp 39,622.00
3 Pemasangan 1 Buah Engsel jendela Kupu-kupu
Permen PUPERA No. 28 /PRT/M/2016 Hal. 732
A TENAGA
Pekerja L.01 OH 0.010 Rp 100,000.00 Rp 1,000.00
Tukang Kayu L.02 OH 0.100 Rp 120,000.00 Rp 12,000.00
Kepala Tukang L.03 OH 0.010 Rp 150,000.00 Rp 1,500.00
Mandor L.04 OH 0.0005 Rp 150,000.00 Rp 75.00
JUMLAH TENAGA KERJA Rp 14,575.00
B BAHAN
Engsel kupu-kupu Buah 1.000 Rp 14,150.00 Rp 14,150.00
JUMLAH HARGA BAHAN Rp 14,150.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 28,725.00
E Overhead & Profit ( 10 % ) 10% x D Rp 2,872.50
F Harga Satuan Pekerjaan (D+E) Rp 31,597.50
A TENAGA
Pekerja L.01 OH 0.015 Rp 100,000.00 Rp 1,500.00
Tukang Kayu L.02 OH 0.150 Rp 120,000.00 Rp 18,000.00
Kepala Tukang L.03 OH 0.015 Rp 150,000.00 Rp 2,250.00
Mandor L.04 OH 0.008 Rp 150,000.00 Rp 1,200.00
JUMLAH TENAGA KERJA Rp 22,950.00
B BAHAN
Kait angin Buah 1.000 Rp 8,150.00 Rp 8,150.00
JUMLAH HARGA BAHAN Rp 8,150.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 31,100.00
E Overhead & Profit ( 10 % ) 10% x D Rp 3,110.00
F Harga Satuan Pekerjaan (D+E) Rp 34,210.00
A TENAGA
Pekerja L.01 OH 0.015 Rp 100,000.00 Rp 1,500.00
Tukang Kayu L.02 OH 0.150 Rp 120,000.00 Rp 18,000.00
Kepala Tukang L.03 OH 0.015 Rp 150,000.00 Rp 2,250.00
Mandor L.04 OH 0.008 Rp 150,000.00 Rp 1,200.00
JUMLAH TENAGA KERJA Rp 22,950.00
B BAHAN
Handle Jendela Buah 1.000 Rp 8,150.00 Rp 8,150.00
JUMLAH HARGA BAHAN Rp 8,150.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 31,100.00
E Overhead & Profit ( 10 % ) 10% x D Rp 3,110.00
F Harga Satuan Pekerjaan (D+E) Rp 34,210.00
A TENAGA
Pekerja L.01 OH 0.015 Rp 100,000.00 Rp 1,500.00
Tukang Kayu L.02 OH 0.150 Rp 120,000.00 Rp 18,000.00
Kepala Tukang L.03 OH 0.015 Rp 150,000.00 Rp 2,250.00
Mandor L.04 OH 0.008 Rp 150,000.00 Rp 1,200.00
JUMLAH TENAGA KERJA Rp 22,950.00
B BAHAN
Grendel Jendela Buah 1.000 Rp 10,150.00 Rp 10,150.00
JUMLAH HARGA BAHAN Rp 10,150.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 33,100.00
E Overhead & Profit ( 10 % ) 10% x D Rp 3,310.00
F Harga Satuan Pekerjaan (D+E) Rp 36,410.00
A TENAGA
Pekerja L.01 OH 0.050 Rp 100,000.00 Rp 5,000.00
Tukang Kayu L.02 OH 0.500 Rp 120,000.00 Rp 60,000.00
Kepala Tukang L.03 OH 0.050 Rp 150,000.00 Rp 7,500.00
Mandor L.04 OH 0.003 Rp 150,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 72,950.00
B BAHAN
Door Closer Buah 1.000 Rp 430,250.00 Rp 430,250.00
JUMLAH HARGA BAHAN Rp 430,250.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 503,200.00
E Overhead & Profit ( 10 % ) 10% x D Rp 50,320.00
F Harga Satuan Pekerjaan (D+E) Rp 553,520.00
A TENAGA
Pekerja L.01 OH 0.010 Rp 100,000.00 Rp 1,000.00
Tukang Kayu L.02 OH 0.100 Rp 120,000.00 Rp 12,000.00
Kepala Tukang L.03 OH 0.010 Rp 150,000.00 Rp 1,500.00
Mandor L.04 OH 0.005 Rp 150,000.00 Rp 750.00
JUMLAH TENAGA KERJA Rp 15,250.00
B BAHAN
Door Stop Buah 1.000 Rp 22,200.00 Rp 22,200.00
JUMLAH HARGA BAHAN Rp 22,200.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 37,450.00
E Overhead & Profit ( 10 % ) 10% x D Rp 3,745.00
F Harga Satuan Pekerjaan (D+E) Rp 41,195.00
A TENAGA
Pekerja L.01 OH 0.015 Rp 100,000.00 Rp 1,500.00
Tukang Kayu L.02 OH 0.150 Rp 120,000.00 Rp 18,000.00
Kepala Tukang L.03 OH 0.015 Rp 150,000.00 Rp 2,250.00
Mandor L.04 OH 0.0008 Rp 150,000.00 Rp 120.00
JUMLAH TENAGA KERJA Rp 21,870.00
B BAHAN
Kaca tebal 3mm m2 1.100 Rp 90,800.00 Rp 99,880.00
Sealant Kg 0.050 Rp 75,400.00 Rp 3,770.00
JUMLAH HARGA BAHAN Rp 103,650.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 125,520.00
E Overhead & Profit ( 10 % ) 10% x D Rp 12,552.00
F Harga Satuan Pekerjaan (D+E) Rp 138,072.00
A TENAGA
Pekerja L.01 OH 0.015 Rp 100,000.00 Rp 1,500.00
Tukang Kayu L.02 OH 0.150 Rp 120,000.00 Rp 18,000.00
Kepala Tukang L.03 OH 0.015 Rp 150,000.00 Rp 2,250.00
Mandor L.04 OH 0.0008 Rp 150,000.00 Rp 120.00
JUMLAH TENAGA KERJA Rp 21,870.00
B BAHAN
Kaca tebal 5 mm m2 1.100 Rp 103,000.00 Rp 113,300.00
Sealant Kg 0.050 Rp 75,400.00 Rp 3,770.00
JUMLAH HARGA BAHAN Rp 117,070.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 138,940.00
E Overhead & Profit ( 10 % ) 10% x D Rp 13,894.00
F Harga Satuan Pekerjaan (D+E) Rp 152,834.00
A TENAGA
Pekerja L.01 OH 0.265 Rp 100,000.00 Rp 26,500.00
Tukang L.03 OH 0.400 Rp 120,000.00 Rp 48,000.00
Kepala Tukang L.03 OH 0.040 Rp 150,000.00 Rp 6,000.00
Mandor L.04 OH 0.014 Rp 150,000.00 Rp 2,070.00
JUMLAH TENAGA KERJA Rp 82,570.00
B BAHAN
Rangka Aluminium 3 Inch M1 3.900 Rp 54,000.00 Rp 210,600.00
Kaca Tebal 5 MM M2 0.903 Rp 103,000.00 Rp 92,957.50
Perlengkapan dan Aksesoris LS 100% X Rp 210,600.00
Rangka
JUMLAH HARGA BAHAN Rp 514,157.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 596,727.50
E Overhead & Profit ( 10 % ) 10% x D Rp 59,672.75
F Harga Satuan Pekerjaan (D+E) Rp 656,400.25
XIII. PEKERJAAN PENGECATAN
A TENAGA
Pekerja L.01 OH 0.150 Rp 100,000.00 Rp 15,000.00
Mandor L.04 OH 0.003 Rp 150,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 15,450.00
B BAHAN
Soda api Kg 0.050 Rp 13,300.00 Rp 665.00
JUMLAH HARGA BAHAN Rp 665.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 16,115.00
E Overhead & Profit ( 10 % ) 10% x D Rp 1,611.50
F Harga Satuan Pekerjaan (D+E) Rp 17,726.50
A TENAGA
Pekerja L.01 OH 0.150 Rp 100,000.00 Rp 15,000.00
Mandor L.04 OH 0.003 Rp 150,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 15,450.00
B BAHAN
Sabun Kg 0.050 Rp 34,000.00 Rp 1,700.00
JUMLAH HARGA BAHAN Rp 1,700.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 17,150.00
E Overhead & Profit ( 10 % ) 10% x D Rp 1,715.00
F Harga Satuan Pekerjaan (D+E) Rp 18,865.00
3 Pengecatan 1 M2 Bidang Kayu Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup )
Permen PUPERA No. 28 /PRT/M/2016 Hal. 743
A TENAGA
Pekerja L.01 OH 0.070 Rp 100,000.00 Rp 7,000.00
Tukang Cat L. 02 OH 0.009 Rp 120,000.00 Rp 1,080.00
Kepala Tukang L.03 OH 0.006 Rp 150,000.00 Rp 900.00
Mandor L.04 OH 0.003 Rp 150,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 9,430.00
B BAHAN
Cat menie Kg 0.200 Rp 30,300.00 Rp 6,060.00
Plamir Kg 0.150 Rp 30,300.00 Rp 4,545.00
Cat dasar Kg 0.170 Rp 30,300.00 Rp 5,151.00
Cat penutup / Cat Minyak Kg 0.260 Rp 60,300.00 Rp 15,678.00
Kuas Buah 0.010 Rp 17,400.00 Rp 174.00
Pengencer Kg 0.030 Rp 41,300.00 Rp 1,239.00
Ampelas Lbr 0.200 Rp 8,100.00 Rp 1,620.00
JUMLAH HARGA BAHAN Rp 34,467.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 43,897.00
E Overhead & Profit ( 10 % ) 10% x D Rp 4,389.70
F Harga Satuan Pekerjaan (D+E) Rp 48,286.70
A TENAGA
Pekerja L.01 OH 0.070 Rp 100,000.00 Rp 7,000.00
Tukang Cat L. 02 OH 0.009 Rp 120,000.00 Rp 1,080.00
Kepala Tukang L.03 OH 0.006 Rp 150,000.00 Rp 900.00
Mandor L.04 OH 0.003 Rp 150,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 9,430.00
B BAHAN
Cat penutup / Cat Minyak Kg 0.260 Rp 60,300.00 Rp 15,678.00
Kuas Buah 0.010 Rp 17,400.00 Rp 174.00
Pengencer / Thiner Kg 0.030 Rp 41,300.00 Rp 1,239.00
Ampelas Lbr 0.200 Rp 8,100.00 Rp 1,620.00
JUMLAH HARGA BAHAN Rp 18,711.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 28,141.00
E Overhead & Profit ( 10 % ) 10% x D Rp 2,814.10
F Harga Satuan Pekerjaan (D+E) Rp 30,955.10
A TENAGA
Pekerja L.01 OH 0.160 Rp 100,000.00 Rp 16,000.00
Tukang Cat L. 02 OH 0.160 Rp 120,000.00 Rp 19,200.00
Kepala Tukang L.03 OH 0.016 Rp 150,000.00 Rp 2,400.00
Mandor L.04 OH 0.003 Rp 150,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 38,050.00
B BAHAN
Vernis L 0.150 Rp 30,300.00 Rp 4,545.00
Dempul Kg 0.050 Rp 43,300.00 Rp 2,165.00
Kertas Ampelas Lbr 0.100 Rp 8,100.00 Rp 810.00
JUMLAH HARGA BAHAN Rp 7,520.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 45,570.00
E Overhead & Profit ( 10 % ) 10% x D Rp 4,557.00
F Harga Satuan Pekerjaan (D+E) Rp 50,127.00
6 Pengecatan 1 M2 Tembok Baru Standar Catylac (1 Lapis Plamuur, 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup)
Permen PUPERA No. 28 /PRT/M/2016 Hal. 746
A TENAGA
Pekerja L.01 OH 0.020 Rp 100,000.00 Rp 2,000.00
Tukang Cat L.02 OH 0.063 Rp 120,000.00 Rp 7,560.00
Kepala Tukang L.03 OH 0.0063 Rp 150,000.00 Rp 945.00
Mandor L.04 OH 0.003 Rp 150,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 10,955.00
B BAHAN
Plamuur Kg 0.100 Rp 30,300.00 Rp 3,030.00
Cat dasar Catylac Kg 0.100 Rp 22,800.00 Rp 2,280.00
Cat Penutup Catylac Kg 0.260 Rp 22,800.00 Rp 5,928.00
JUMLAH HARGA BAHAN Rp 11,238.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 22,193.00
E Overhead & Profit ( 10 % ) 10% x D Rp 2,219.30
F Harga Satuan Pekerjaan (D+E) Rp 24,412.30
7 Pengecatan 1 M2 Tembok Lama Standar Catylac ( 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup )
Permen PUPERA No. 28 /PRT/M/2016 Hal. 746
A TENAGA
Pekerja L.01 OH 0.028 Rp 100,000.00 Rp 2,800.00
Tukang Cat L.02 OH 0.042 Rp 120,000.00 Rp 5,040.00
Kepala Tukang L.03 OH 0.0042 Rp 150,000.00 Rp 630.00
Mandor L.04 OH 0.003 Rp 150,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 8,920.00
B BAHAN
Cat dasar catylac Kg 0.120 Rp 22,800.00 Rp 2,736.00
Cat Penutup Catylac Kg 0.180 Rp 22,800.00 Rp 4,104.00
JUMLAH HARGA BAHAN Rp 6,840.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 15,760.00
E Overhead & Profit ( 10 % ) 10% x D Rp 1,576.00
F Harga Satuan Pekerjaan (D+E) Rp 17,336.00
8 Pemasangan 1 M2 Wallpaper
Permen PUPERA No. 28 /PRT/M/2016 Hal. 748
A TENAGA
Pekerja L.01 OH 0.020 Rp 100,000.00 Rp 2,000.00
Tukang L. 02 OH 0.200 Rp 120,000.00 Rp 24,000.00
Kepala Tukang L.03 OH 0.020 Rp 150,000.00 Rp 3,000.00
Mandor L.04 OH 0.0025 Rp 150,000.00 Rp 375.00
JUMLAH TENAGA KERJA Rp 29,375.00
B BAHAN
Wallpaper M2 1.200 Rp 46,000.00 Rp 55,200.00
Lem Kg 0.200 Rp 35,400.00 Rp 7,080.00
JUMLAH HARGA BAHAN Rp 62,280.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 91,655.00
E Overhead & Profit ( 10 % ) 10% x D Rp 9,165.50
F Harga Satuan Pekerjaan (D+E) Rp 100,820.50
A TENAGA
Pekerja L.01 OH 0.020 Rp 100,000.00 Rp 2,000.00
Tukang Cat L. 02 OH 0.200 Rp 120,000.00 Rp 24,000.00
Kepala Tukang L.03 OH 0.020 Rp 150,000.00 Rp 3,000.00
Mandor L.04 OH 0.0025 Rp 150,000.00 Rp 375.00
JUMLAH TENAGA KERJA Rp 29,375.00
B BAHAN
Menie besi Kg 0.100 Rp 16,800.00 Rp 1,680.00
Kuas Buah 0.010 Rp 17,400.00 Rp 174.00
JUMLAH HARGA BAHAN Rp 1,854.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 31,229.00
E Overhead & Profit ( 10 % ) 10% x D Rp 3,122.90
F Harga Satuan Pekerjaan (D+E) Rp 34,351.90
XIV. PEKERJAAN SANITASI DALAM GEDUNG
A TENAGA
Pekerja L.01 OH 3.30 Rp 100,000.00 Rp 330,000.00
Tukang Batu L.02 OH 1.10 Rp 120,000.00 Rp 132,000.00
Kepala Tukang L.03 OH 0.01 Rp 150,000.00 Rp 1,500.00
Mandor L.04 OH 0.16 Rp 150,000.00 Rp 24,000.00
JUMLAH TENAGA KERJA Rp 487,500.00
B BAHAN
Closet duduk Unit 1.00 Rp 1,525,000.00 Rp 1,525,000.00
A TENAGA
Pekerja L.01 OH 1.00 Rp 100,000.00 Rp 100,000.00
Tukang Batu L.02 OH 1.50 Rp 120,000.00 Rp 180,000.00
Kepala Tukang L.03 OH 0.15 Rp 150,000.00 Rp 22,500.00
Mandor L.04 OH 0.16 Rp 150,000.00 Rp 24,000.00
JUMLAH TENAGA KERJA Rp 326,500.00
B BAHAN
Closet jongkok Unit 1.00 Rp 269,000.00 Rp 269,000.00
Semen Portland Kg 6.00 Rp 1,550.00 Rp 9,300.00
Pasir Pasang M3 0.01 Rp 145,000.00 Rp 1,450.00
JUMLAH HARGA BAHAN Rp 279,750.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 606,250.00
E Overhead & Profit ( 10 % ) 10% x D Rp 60,625.00
F Harga Satuan Pekerjaan (D+E) Rp 666,875.00
3 Pemasangan 1 Buah urinoir
Permen PUPERA No. 28 /PRT/M/2016 Hal. 754
A TENAGA
Pekerja L.01 OH 1.000 Rp 100,000.00 Rp 100,000.00
Tukang Batu L.02 OH 1.000 Rp 120,000.00 Rp 120,000.00
Kepala Tukang L.03 OH 0.100 Rp 150,000.00 Rp 15,000.00
Mandor L.04 OH 0.050 Rp 150,000.00 Rp 7,500.00
JUMLAH TENAGA KERJA Rp 242,500.00
B BAHAN
Urinoir Unit 1.000 Rp 1,475,000.00 Rp 1,475,000.00
Semen Portland Kg 6.000 Rp 1,550.00 Rp 9,300.00
Pasir pasang M3 0.010 Rp 145,000.00 Rp 1,450.00
Perlengkapan % 30.000 Rp 445,725.00 Rp 445,725.00
JUMLAH HARGA BAHAN Rp 1,931,475.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 2,173,975.00
E Overhead & Profit ( 10 % ) 10% x D Rp 217,397.50
F Harga Satuan Pekerjaan (D+E) Rp 2,391,372.50
A TENAGA
Pekerja L.01 OH 1.200 Rp 100,000.00 Rp 120,000.00
Tukang Batu L.02 OH 1.450 Rp 120,000.00 Rp 174,000.00
Kepala Tukang L.03 OH 0.150 Rp 150,000.00 Rp 22,500.00
Mandor L.04 OH 0.060 Rp 150,000.00 Rp 9,000.00
JUMLAH TENAGA KERJA Rp 325,500.00
B BAHAN
Wastafel Unit 1.200 Rp 525,000.00 Rp 630,000.00
Semen Portland Kg 6.000 Rp 1,550.00 Rp 9,300.00
Pasir pasang M3 0.010 Rp 145,000.00 Rp 1,450.00
Perlengkapan % 12.000 Rp 76,890.00 Rp 76,890.00
JUMLAH HARGA BAHAN Rp 717,640.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,043,140.00
E Overhead & Profit ( 10 % ) 10% x D Rp 104,314.00
F Harga Satuan Pekerjaan (D+E) Rp 1,147,454.00
A TENAGA
Pekerja L.01 OH 0.010 Rp 100,000.00 Rp 1,000.00
Tukang Batu L.02 OH 0.100 Rp 120,000.00 Rp 12,000.00
Kepala Tukang L.03 OH 0.010 Rp 150,000.00 Rp 1,500.00
Mandor L.04 OH 0.005 Rp 150,000.00 Rp 750.00
JUMLAH TENAGA KERJA Rp 15,250.00
B BAHAN
Floor Drain Plastik Unit 1.000 Rp 16,750.00 Rp 16,750.00
JUMLAH HARGA BAHAN Rp 16,750.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 32,000.00
E Overhead & Profit ( 10 % ) 10% x D Rp 3,200.00
F Harga Satuan Pekerjaan (D+E) Rp 35,200.00
A TENAGA
Pekerja L.01 OH 0.081 Rp 100,000.00 Rp 8,100.00
Tukang Batu L.02 OH 0.135 Rp 120,000.00 Rp 16,200.00
Kepala Tukang L.03 OH 0.0135 Rp 150,000.00 Rp 2,025.00
Mandor L.04 OH 0.004 Rp 150,000.00 Rp 600.00
JUMLAH TENAGA KERJA Rp 26,925.00
B BAHAN
Pipa PVC Diameter 3 Inchi M1 1.200 Rp 45,300.00 Rp 54,360.00
Perlengkapan % 35.000 Rp 19,026.00 Rp 19,026.00
JUMLAH HARGA BAHAN Rp 73,386.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 100,311.00
E Overhead & Profit ( 10 % ) 10% x D Rp 10,031.10
F Harga Satuan Pekerjaan (D+E) Rp 110,342.10
A TENAGA
Pekerja L.01 OH 0.081 Rp 100,000.00 Rp 8,100.00
Tukang Batu L.02 OH 0.135 Rp 120,000.00 Rp 16,200.00
Kepala Tukang L.03 OH 0.0135 Rp 150,000.00 Rp 2,025.00
Mandor L.04 OH 0.004 Rp 150,000.00 Rp 600.00
JUMLAH TENAGA KERJA Rp 26,925.00
B BAHAN
Pipa PVC Diameter 4,0 Inchi M1 1.200 Rp 70,400.00 Rp 84,480.00
Perlengkapan % 35.000 Rp 29,568.00 Rp 29,568.00
JUMLAH HARGA BAHAN Rp 114,048.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 140,973.00
E Overhead & Profit ( 10 % ) 10% x D Rp 14,097.30
F Harga Satuan Pekerjaan (D+E) Rp 155,070.30
XV. PEKERJAAN RANGKA ATAP BAJA RINGAN
1 1 M2 Pasang Kuda - Kuda Baja Ringan + Reng untuk Atap Genteng Metal biasa
A TENAGA
Pekerja L.01 OH 0.200 Rp 100,000.00 Rp 20,000.00
Tukang Besi L.02 OH 0.450 Rp 120,000.00 Rp 54,000.00
Kepala Tukang L.03 OH 0.010 Rp 150,000.00 Rp 1,500.00
Mandor L.04 OH 0.050 Rp 150,000.00 Rp 7,500.00
JUMLAH TENAGA KERJA Rp 83,000.00
B BAHAN
Baja Ringan C. 75.75 M' 3.720 15,300.00 Rp 56,916.00
Baut (Screw Driver) Bh 28.000 300.00 Rp 8,400.00
Dyna Bolt Bh 1.600 1,100.00 Rp 1,760.00
Reng Baja Ringan M' 3.000 7,800.00 Rp 23,400.00
JUMLAH HARGA BAHAN Rp 90,476.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 173,476.00
E Overhead & Profit ( 10 % ) 10% x D Rp 8,300.00
F Harga Satuan Pekerjaan (D+E) Rp 181,776.00
2 1 M2 Pasang Kuda - Kuda Baja Ringan + Reng untuk Atap Asbes / Spandek
A TENAGA
Pekerja L.01 OH 0.200 Rp 100,000.00 Rp 20,000.00
Tukang Besi L.02 OH 0.450 Rp 120,000.00 Rp 54,000.00
Kepala Tukang L.03 OH 0.010 Rp 150,000.00 Rp 1,500.00
Mandor L.04 OH 0.050 Rp 150,000.00 Rp 7,500.00
JUMLAH TENAGA KERJA Rp 83,000.00
B BAHAN
Baja Ringan C. 75.75 M' 3.720 15,300.00 Rp 56,916.00
Baut (Screw Driver) Bh 28.000 300.00 Rp 8,400.00
Dyna Bolt Bh 1.600 1,100.00 Rp 1,760.00
Reng Baja Ringan M' 2.400 7,800.00 Rp 18,720.00
JUMLAH HARGA BAHAN Rp 85,796.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 168,796.00
E Overhead & Profit ( 10 % ) 10% x D Rp 8,300.00
F Harga Satuan Pekerjaan (D+E) Rp 177,096.00
A TENAGA
Pekerja L.01 OH 0.200 Rp 100,000.00 Rp 20,000.00
Tukang Besi L.02 OH 0.450 Rp 120,000.00 Rp 54,000.00
Kepala Tukang L.03 OH 0.010 Rp 150,000.00 Rp 1,500.00
Mandor L.04 OH 0.050 Rp 150,000.00 Rp 7,500.00
JUMLAH TENAGA KERJA Rp 83,000.00
B BAHAN
Baja Ringan C. 75.100 M' 3.720 17,800.00 Rp 66,216.00
Baut (Screw Driver) Bh 28.000 300.00 Rp 8,400.00
Dyna Bolt Bh 1.600 1,100.00 Rp 1,760.00
Reng Baja Ringan M' 2.400 7,800.00 Rp 18,720.00
JUMLAH HARGA BAHAN Rp 95,096.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 178,096.00
E Overhead & Profit ( 10 % ) 10% x D Rp 8,300.00
F Harga Satuan Pekerjaan (D+E) Rp 186,396.00
XVI. PEKERJAAN PONDASI TIANG PANCANG
A TENAGA
Pekerja L.01 OH 0.1070 100,000.00 10,700.00
Operator OH 0.0070 94,500.00 661.50
Mandor L.04 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 11,811.50
B BAHAN
Kawat Las Kg 0.3500 29,500.00 10,325.00
JUMLAH HARGA BAHAN 10,325.00
C PERALATAN
Mesin Las Jam 0.150 101,000.00 15,150.00
Alat Bantu LS 1.000 500.00 500.00
JUMLAH HARGA ALAT 15,650.00
D Jumlah (A+B+C) 37,786.50
E Overhead & Profit ( 10 % ) 10% x D 3,778.65
F Harga Satuan Pekerjaan (D+E) 41,565.15
A TENAGA
Pekerja L.01 OH 0.7500 100,000.00 75,000.00
Mandor L.04 OH 0.0375 150,000.00 5,625.00
JUMLAH TENAGA KERJA 80,625.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 80,625.00
E Overhead & Profit ( 10 % ) 10% x D 8,062.50
F Harga Satuan Pekerjaan (D+E) 88,687.50
XVII. PEKERJAAN LAIN - LAIN
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.017 Rp 100,000.00 Rp 1,680.00
Mandor L.04 OH 0.003 Rp 150,000.00 Rp 480.00
JUMLAH TENAGA KERJA Rp 2,160.00
B BAHAN
Aspal Kg 0.679 Rp 14,800.00 Rp 10,049.20
Kerosene / Minyak Tanah Liter 0.371 Rp 11,550.00 Rp 4,285.05
JUMLAH HARGA BAHAN Rp 14,334.25
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 16,494.25
E Overhead & Profit ( 10 % ) 10% x D Rp 1,649.43
F Harga Satuan Pekerjaan (D+E) Rp 18,143.68
A TENAGA
Pekerja L.01 OH 0.040 Rp 100,000.00 Rp 4,000.00
Mandor L.04 OH 0.004 Rp 150,000.00 Rp 600.00
JUMLAH TENAGA KERJA Rp 4,600.00
B BAHAN
Pupuk Kandang Krg 0.040 2,850.00 Rp 114.00
Rumput Gajah Mini M2 1.050 42,000.00 Rp 44,100.00
JUMLAH HARGA BAHAN Rp 44,214.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 48,814.00
E Overhead & Profit ( 10 % ) 10% x D Rp 4,881.40
F Harga Satuan Pekerjaan (D+E) Rp 53,695.40