TIME SCHEDULE

KEGIATAN : PENGADAAN BARANG MILIK DAERAH PENUNJANG URUSAN PEMERINTAH DAERAH


PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR BPBD KOTA SURAKARTA TAHUN 2021
TAHUN : 2021
LOKASI : KOTA SURAKARTA
JUMLAH HARGA
NO URAIAN PEKERJAAN BOBOT BULAN 1 BULAN 2 BULAN 3 BULAN 4
Rp.
1 2 6 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

A PEKERJAAN PERSIAPAN 29,301,000.00 0.366 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023 100%

B PEKERJAAN LANTAI I
I PEKERJAAN TANGGA DEPAN 71,845,997.52 0.898 0.224 0.224 0.224 0.224

II PEKERJAAN PENAMBAHAN BV 1,333,409.80 0.017 0.017

III PEKERJAAN PINTU KOBOI 3,500,000.00 0.044 0.044

IV PEKERJAAN PARTISI 26,978,966.16 0.337 0.169 0.169

C PEKERJAAN BANGUNAN LANTAI II


I PEKERJAAN PASANGAN DAN PLESTERAN 495,545,029.64 6.193 1.032 1.032 1.032 1.032 1.032 1.032

II PEKERJAAN BETON 374,640,279.50 4.682 1.171 1.171 1.171 1.171

III PEKERJAAN LANTAI 445,976,782.52 5.574 1.115 1.115 1.115 1.115 1.115

IV PEKERJAAN ATAP DAN RANGKA 1,987,548,359.61 24.841 3.105 3.105 3.105 3.105 3.105 3.105 3.105 3.105

V PEKERJAAN PINTU JENDELA 282,687,557.54 3.533 0.883 0.883 0.883 0.883

VI PEKERJAAN PARTISI 284,798,722.75 3.559 0.890 0.890 0.890 0.890

VII PEKERJAAN PLAFOND 155,739,337.60 1.946 0.649 0.649 0.649

VIII PEKERJAAN SANITASI 147,663,844.73 1.846 0.461 0.461 0.461 0.461

IX PEKERJAAN PENGECATAN 187,801,907.74 2.347 0.587 0.587 0.587 0.587

D PEKERJAAN ELEKTRIKAL
I GROUP LANTAI ATAS 83,780,000.00 1.047 0.262 0.262 0.262 0.262

II RUANG GENSET 554,875,000.00 6.935 0.867 0.867 0.867 0.867 0.867 0.867 0.867 0.867

III POS JAGA 47,255,000.00 0.591 0.197 0.197 0.197

IV PEKERJAAN HYDRANT 778,065,000.00 9.724 1.621 1.621 1.621 1.621 1.621 1.621

V INSTALASI PIPA HYDRANT 542,940,000.00 6.786 1.131 1.131 1.131 1.131 1.131 1.131

VI PEKERJAAN PENANGKAL PETIR 26,300,000.00 0.329 0.164 0.164


50%
E PEKERJAAN AC
I PERALATAN UTAMA 283,808,750.00 3.547 1.182 1.182 1.182

II INSTALASI PIPA 150,964,000.00 1.887 0.943 0.943

F GROUND WATER TANK DAN RUMAH POMPA (J)


I GROUND WATER TANK DAN RUMAH POMPA (J) 216,962,752.02 2.712 0.678 0.678 0.678 0.678

G RUMAH POS JAGA ( F )


I PEKERJAAN TANAH 1,053,190.91 0.013 0.013

II PEKERJAAN PASANGAN & PLESTERAN 17,407,738.50 0.218 0.109 0.109

III PEKERJAAN BETON 21,359,591.23 0.267 0.133 0.133

IV PEKERJAAN PINTU JENDELA 14,888,704.58 0.186 0.186

V PEKERJAAN ATAP DAN PLAFOND 60,096,249.77 0.751 0.376 0.376

VI PEKERJAAN PENGECATAN 4,668,309.61 0.058 0.058

H PEKERJAAN SARANA DAN PRASARANA


I PEKERJAAN TALUD ( PENUTUPAN PINTU MASUK ) ( A ) 11,293,925.78 0.141 0.047 0.047 0.047

II PEKERJAAN PENINGGIAN PEIL HALAMAN ( B ) 43,969,803.84 0.550 0.137 0.137 0.137 0.137

III PEKERJAAN TIANG BENDERA ( C ) 10,056,264.84 0.126 0.126

IV PEKERJAAN PAGAR DAN PINTU BESI ( D ) ( E ) 162,983,217.35 2.037 0.509 0.509 0.509 0.509

V PEKERJAAN RAMP ( G ) 223,021,011.96 2.787 1.394 1.394

VI PEKERJAAN PAVING ( I ) 75,499,618.20 0.944 0.472 0.472

VII PEKERJAAN PENGERUKAN DAN BONGKAR TALUD ( O ) 67,884,570.00 0.848 0.283 0.283 0.283

VIII PEKERJAAN TANAMAN 980,000.00 0.012 0.012

IX PEKERJAAN SALURAN DAN GRILL BESI 93,745,489.60 1.172 0.586 0.586

X PENGADAAN ALAT PEMADAM KEBAKARAN 12,000,000.00 0.150 0.150


0%
JUMLAH TOTAL 8,001,219,383.30 100.00 2.976 4.758 4.775 4.609 5.973 5.871 6.508 7.731 7.386 8.216 8.979 8.932 8.278 5.750 5.181 4.075
2.976 7.73 12.51 17.12 23.09 28.96 35.47 43.20 50.59 58.80 67.78 76.72 84.99 90.74 95.92 100.00