Rab Pasar Rev. 1a2
Rab Pasar Rev. 1a2
PASAR SAYUR
DEMOLENG KETANGGUNGAN BREBES
12.036.750,00 12.036.750,00
VI PEKERJAAN LANTAI
1 Pek. Screeding+Aci Floor Hardener m2 700,00 78.958,13 55.270.691,84
2 Pek. Paving Area Parkir m2 70,00 130.000,00 9.100.000,00
Sub Total III (Rp.) 64.370.691,84 64.370.691,84
VII PEKERJAAN PENGECATAN
1 Pek. Cat Luar dan Dalam Partisi Luar Ex. Avian Stara m2 150 23.689,10 3.553.365,00
Pek. Cat Lisplang m2 130 48.467,70 6.300.801,00
Sub Total IX (Rp.) 9.854.166,00 9.854.166,00
VIII PEKERJAAN ATAP
1 Pas. Rangka Atap Canal C 100 m2 1.479,00 23.000,00 34.017.000,00
2 Pek. Pas. Penutup Atap Spandek m2 1.170,00 100.552,50 117.646.425,00
3 Pek. Pas. Nok Atap Spandek m1 94,00 65.018,75 6.111.762,50
4 Pek. Pas. Lisplang m1 225,00 85.000,00 19.125.000,00
5 Pek. Signage bh 24,00 70.000,00 1.680.000,00
Sub Total XI (Rp.) 178.580.187,50 178.580.187,50
SATU VOLU JUMLAH HARGA
NO URAIAN PEKERJAAN AN ME HARGA SATUAN TOTAL TOTAL
(Rp) (Rp) (Rp)
1 2 3 4 5 6 7
IX PEKERJAAN SANITAIR & PLUMBING
A INSTALASI PLUMBING
1 Instalasi Air Hujan PVC. 3" D ex. Union Setara m' 98 50.937,00 4.991.826,00
2 Acesories Pipa m' 98 8.252,40 808.735,20
3 Talang PVC 1/2 l 4' m 188 48.500,00 9.118.000,00
4 Grevel m 195.000,00 -
Sub Total IX (Rp.) 14.918.561,20 14.918.561,20
JUMLAH TOTAL I S.D IX Rp. 759.522.146,03 759.522.146,03
NOTE :
1. Item Pekerjaaan yang belum masuk dalam list diatas, akan dimasukan dalam pekerjaaan Addendum setelah pekerjaan berjalan
............................... NASUTION
Owner