NO Kegiatan
A.1 Konstruksi Penambahan Lantai
A.1.1 Kolom
A.1.1.1 Pengecoran
A.1.1.2 Bekisting
A.1.1.3 Pembesian
A.1.2 Balok
A.1.1.1 Pengecoran
A.1.1.2 Bekisting
A.1.1.3 Pembesian
A.1.3 Pelat
A.1.1.1 Pengecoran
A.1.1.2 Bekisting
A.1.1.3 Pembesian
B.1 Perkuatan Struktur
B.1.1 FRP
B.1.1.1 Pekerjaan Persiapan
B.1.1.2 Pekerjaan Pelaksanaan
B.1.1.3 Pekerjaan akhir
B.1.2 Concrete Jacketing
B.1.2.1 pembobokan
B.1.2.2 pengeboran
B.1.2.3 dibersihkan pk kompresor
B.1.2.4 menyuntikan epoksy
B.1.2.5 pasang tulangan
B.1.2.6 pengecoran pk compresor
B.1.2.7 pelepasan bekisting
Keterangan
Lantai 5-8
lt 1-4
Pemasangan
DAFTAR HARGA SATUAN DASAR (BASIC PRICE)
621.60 Kg
33.60 m2
3.15 m2
2756.40 Kg
97.20 m2
13.20 m2
621.60 Kg
33.60 m2
3.15 m2
2756.40 Kg
97.20 m2
13.20 m2
621.60 Kg
33.60 m2
3.15 m2
2756.40 Kg
97.20 m2
13.20 m2
621.60 Kg
33.60 m2
3.15 m2
3785.40 kg
75.60 m2
7.80 m3
4109.00 kg
72.00 m2
7.00 m3
88.10 kg
6.30 m2
0.50 m3
3038.00 kg
35.00 m2
2.10 m3
327.30 kg
18.00 m2
0.80 m3
3785.40 kg
75.60 m2
7.80 m3
4109.00 kg
72.00 m2
7.00 m3
88.10 kg
6.30 m2
0.50 m3
3038.00 kg
35.00 m2
2.10 m3
327.30 kg
18.00 m2
0.80 m3
3785.40 kg
75.60 m2
7.80 m3
4109.00 kg
72.00 m2
7.00 m3
88.10 kg
6.30 m2
0.50 m3
3038.00 kg
35.00 m2
2.10 m3
327.30 kg
18.00 m2
0.80 m3
3785.40 kg
75.60 m2
7.80 m3
4109.00 kg
72.00 m2
7.00 m3
1502.70 kg
112.00 m2
1363.20 m3
3038.00 kg
35.00 m2
2.10 m3
327.30 kg
18.00 m2
0.80 m3
3785.40 kg
75.60 m2
7.80 m3
4109.00 kg
72.00 m2
7.00 m3
1502.70 kg
112.00 m2
1363.20 m3
3038.00 kg
35.00 m2
2.10 m3
327.30 kg
18.00 m2
0.80 m3
44782.50 kg
253.10 m2
35.40 m3
44782.50 kg
253.10 m2
35.40 m3
44782.50 kg
253.10 m2
35.40 m3
44782.50 kg
253.10 m2
35.40 m3
4918.03 kg
99.96 m2
24.99 m3
4918.03 kg
99.96 m2
24.99 m3
4918.03 kg
99.96 m2
24.99 m3
4918.03 kg
99.96 m2
24.99 m3
228.31 kg
30.24 m2
0.81 m3
228.31 kg
30.24 m2
0.81 m3
228.31 kg
30.24 m2
0.81 m3
228.31 kg
30.24 m2
0.81 m3
383.04 m3
382.98 m3
870.00 m2
1740.40 m2
RENCANA ANGGARAN BIAYA
ID
NAMA PROJECT
LOKASI
TAHUN
A
1 A1
2 A2
3 A3
B
1 B1
2 B2
3 B3
C
1 C1
2 C2
3 C3
D
1 D1
2 D2
3 D3
E
1 E1
2 E2
3 E3
F
1 F1
2 F2
3 F3
G
1 G1
2 G2
3 G3
H
1 H1
2 H2
3 H3
I
1 I1
2 I2
3 I3
K
1 K1
2 K2
3 K3
L
1 L1
2 L2
3 L3
M
1 M1
2 M2
3 M3
N
1 N1
2 N2
3 N3
O
1 O1
2 O2
3 O3
P
1 P1
2 P2
3 P3
Q
1 Q1
2 Q2
3 Q3
R
1 R1
2 R2
3 R3
S
1 S1
2 S2
3 S3
T
1 T1
2 T2
3 T3
U
1 U1
2 U2
3 U3
V
1 V1
2 V2
3 V3
W
1 W1
2 W2
3 W3
X
1 X1
2 X2
3 X3
Y
1 Y1
2 Y2
3 Y3
U
1 U1
2 U2
3 U3
W
1 W1
2 W2
3 W3
X
1 X1
2 X2
3 X3
Y
1 Y1
2 Y2
3 Y3
Z
1 Z1
2 Z2
3 Z3
AA
1 AA1
2 AA2
3 AA3
AB
1 AB1
2 AB2
3 AB3
AC
1 AC1
2 AC2
3 AC3
AD
1 AD1
2 AD2
3 AD3
AE
1 AE1
2 AE2
3 AE3
AF
1 AF1
2 AF2
3 AF3
AG
1 AG1
2 AG2
3 AG3
AH
1 AH1
2 AH2
3 AH3
AI
1 AI1
2 AI2
3 AI3
AI
1 AI1
2 AI2
3 AI3
AJ
1 AJ1
AK
1 AK1
AL
1 AL1
2 AL2
RENCANA ANGGARAN BIAYA
TOTAL RAB :
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
PEKERJAAN CONCRETE JACKETTING LANTAI 1 (K1) VOLUME UNIT
VOLUME PEKERJAAN PEMBESIAN 4918.03 kg
VOLUME PEKERJAAN BEKISTING 99.96 m2
VOLUME PEKERJAAN PENGECORAN 24.99 m3
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
SUBTOTAL
PEKERJAAN INJEKSI
VOLUME PEKERJAAN INJEKSI 382.98 m3
SUBTOTAL
PEKERJAAN DINDING
VOLUME PEMASANGAN BATA 870.00 m2
VOLUME PLESTERAN 1740.40 m2
SUBTOTAL
Rp 4,030,367,381
TOTAL
Rp 30,285,945
Rp 7,822,462
Rp 11,751,811
Rp 49,860,218
TOTAL
Rp 6,829,830
Rp 2,704,061
Rp 2,804,409
Rp 12,338,300
TOTAL
Rp 30,285,945
Rp 7,822,462
Rp 11,751,811
Rp 49,860,218
TOTAL
Rp 6,829,830
Rp 2,704,061
Rp 2,804,409
Rp 12,338,300
TOTAL
Rp 30,285,945
Rp 7,822,462
Rp 11,751,811
Rp 49,860,218
TOTAL
Rp 6,829,830
Rp 2,704,061
Rp 2,804,409
Rp 12,338,300
TOTAL
Rp 30,285,945
Rp 7,822,462
Rp 11,751,811
Rp 49,860,218
TOTAL
Rp 6,829,830
Rp 2,704,061
Rp 2,804,409
Rp 12,338,300
TOTAL
Rp 41,592,083
Rp 6,084,137
Rp 6,944,252
Rp 54,620,471
TOTAL
Rp 45,147,638
Rp 5,794,416
Rp 6,232,021
Rp 57,174,075
TOTAL
Rp 967,999
Rp 507,011
Rp 445,144
Rp 1,920,155
TOTAL
Rp 33,380,025
Rp 2,816,730
Rp 1,869,606
Rp 38,066,361
TOTAL
Rp 3,596,209
Rp 1,448,604
Rp 712,231
Rp 5,757,044
TOTAL
Rp 41,592,083
Rp 6,084,137
Rp 6,944,252
Rp 54,620,471
TOTAL
Rp 45,147,638
Rp 5,794,416
Rp 6,232,021
Rp 57,174,075
TOTAL
Rp 967,999
Rp 507,011
Rp 445,144
Rp 1,920,155
TOTAL
Rp 33,380,025
Rp 2,816,730
Rp 1,869,606
Rp 38,066,361
TOTAL
Rp 3,596,209
Rp 1,448,604
Rp 712,231
Rp 5,757,044
TOTAL
Rp 41,592,083
Rp 6,084,137
Rp 6,944,252
Rp 54,620,471
TOTAL
Rp 45,147,638
Rp 5,794,416
Rp 6,232,021
Rp 57,174,075
TOTAL
Rp 967,999
Rp 507,011
Rp 445,144
Rp 1,920,155
TOTAL
Rp 33,380,025
Rp 2,816,730
Rp 1,869,606
Rp 38,066,361
TOTAL
Rp 3,596,209
Rp 1,448,604
Rp 712,231
Rp 5,757,044
TOTAL
Rp 41,592,083
Rp 6,084,137
Rp 6,944,252
Rp 54,620,471
TOTAL
Rp 45,147,638
Rp 5,794,416
Rp 6,232,021
Rp 57,174,075
TOTAL
Rp 33,380,025
Rp 2,816,730
Rp 1,869,606
Rp 38,066,361
TOTAL
Rp 3,596,209
Rp 1,448,604
Rp 712,231
Rp 5,757,044
TOTAL
Rp 492,047,719
Rp 20,368,982
Rp 31,516,221
Rp 543,932,921
TOTAL
Rp 492,047,719
Rp 20,368,982
Rp 31,516,221
Rp 543,932,921
TOTAL
Rp 492,047,719
Rp 20,368,982
Rp 31,516,221
Rp 543,932,921
TOTAL
Rp 492,047,719
Rp 20,368,982
Rp 31,516,221
Rp 543,932,921
TOTAL
Rp 54,036,855
Rp 8,044,581
Rp 24,196,568
Rp 86,278,003
TOTAL
Rp 54,036,855
Rp 8,044,581
Rp 24,196,568
Rp 86,278,003
TOTAL
Rp 54,036,855
Rp 8,044,581
Rp 24,196,568
Rp 86,278,003
TOTAL
Rp 54,036,855
Rp 8,044,581
Rp 24,196,568
Rp 86,278,003
Rp 2,508,556
Rp 2,433,655
Rp 784,283
Rp 5,726,493
Rp 2,508,556
Rp 2,433,655
Rp 784,283
Rp 5,726,493
Rp 2,508,556
Rp 2,433,655
Rp 784,283
Rp 5,726,493
Rp 2,508,556
Rp 2,433,655
Rp 784,283
Rp 5,726,493
Rp 179,687,894
Rp 179,687,894
Rp 107,944,828
Rp 107,944,828
Rp 187,902,600
Rp 134,056,050
Rp 321,958,650
PEKERJAAN CONCRETE JACKETTING LANTAI
VOLUME PEKERJAAN PEMBES
VOLUME PEKERJAAN BEKISTI
VOLUME PEKERJAAN PENGEC
PEKERJAAN CONCRETE JACKETTING LANTAI
VOLUME PEKERJAAN PEMBES
VOLUME PEKERJAAN BEKISTI
AM VOLUME PEKERJAAN PENGEC
1 AM1 PEKERJAAN CONCRETE JACKETTING LANTAI
2 AM2VOLUME PEKERJAAN PEMBES
3 AM3VOLUME PEKERJAAN BEKISTI
AN VOLUME PEKERJAAN PENGEC
1 AN1 PEKERJAAN CONCRETE JACKETTING LANTAI
2 AN2 VOLUME PEKERJAAN PEMBES
3 AN3 VOLUME PEKERJAAN BEKISTI
AO VOLUME PEKERJAAN PENGEC
1 AO1 PEKERJAAN CONCRETE JACKETTING LANTAI 1
2 AO2 VOLUME PEKERJAAN PEMBES
3 AO3 VOLUME PEKERJAAN BEKISTI
AP VOLUME PEKERJAAN PENGEC
1 AP1 PEKERJAAN CONCRETE JACKETTING LANTAI 2
2 AP2 VOLUME PEKERJAAN PEMBES
3 AP3 VOLUME PEKERJAAN BEKISTI
AQ VOLUME PEKERJAAN PENGEC
1 AQ1 PEKERJAAN CONCRETE JACKETTING LANTAI 3
2 AQ2 VOLUME PEKERJAAN PEMBES
3 AQ3 VOLUME PEKERJAAN BEKISTI
AR VOLUME PEKERJAAN PENGEC
1 AR1 PEKERJAAN CONCRETE JACKETTING LANTAI 4
2 AR2 VOLUME PEKERJAAN PEMBES
3 AR3 VOLUME PEKERJAAN BEKISTI
AS VOLUME PEKERJAAN PENGEC
1 AS1 PEKERJAAN PEMBOBOKAN KOLOM
2 AS2 VOLUME PEKERJAAN PEMBO
3 AS3 PEKERJAAN INJEKSI
AT VOLUME PEKERJAAN INJEKSI
1 AT1 PEKERJAAN DINDING
2 AT2 VOLUME PEMASANGAN BATA
3 AT3 VOLUME PLESTERAN
AU
1 AU1
AV
1 AV1
AW
1 AW1
2 AW2
CRETE JACKETTING LANTAI 1 (K1)
4918.03 kg
99.96 m2
24.99 m3
CRETE JACKETTING LANTAI 2 (K1)
4918.03 kg
99.96 m2
24.99 m3
CRETE JACKETTING LANTAI 3 (K1)
4918.03 kg
99.96 m2
24.99 m3
CRETE JACKETTING LANTAI 4 (K1)
4918.03 kg
99.96 m2
24.99 m3
RETE JACKETTING LANTAI 1 (K2)
228.31 kg
30.24 m2
0.81 m3
RETE JACKETTING LANTAI 2 (K2)
228.31 kg
30.24 m2
0.81 m3
RETE JACKETTING LANTAI 3 (K2)
228.31 kg
30.24 m2
0.81 m3
RETE JACKETTING LANTAI 4 (K2)
228.31 kg
30.24 m2
0.81 m3
OBOKAN KOLOM
383.04 m3
382.98 m3
870.00 m2
1740.40 m2
Rp 86,278,003
Rp 54,036,855
Rp 8,044,581
Rp 24,196,568
Rp 86,278,003
Rp 54,036,855
Rp 8,044,581
Rp 24,196,568
Rp 86,278,003
Rp 54,036,855
Rp 8,044,581
Rp 24,196,568
Rp 86,278,003
Rp 54,036,855
Rp 8,044,581
Rp 24,196,568
Rp 5,726,493
Rp 2,508,556
Rp 2,433,655
Rp 784,283
Rp 5,726,493
Rp 2,508,556
Rp 2,433,655
Rp 784,283
Rp 5,726,493
Rp 2,508,556
Rp 2,433,655
Rp 784,283
Rp 5,726,493
Rp 2,508,556
Rp 2,433,655
Rp 784,283
Rp 179,687,894
Rp 179,687,894
Rp 107,944,828
Rp 107,944,828
Rp 51,450,055
Rp 187,902,600
Rp 134,056,050
REKAPITULASI RENCANA ANGGARAN BIAYA
NAMA PROJECT : PEMBANGUNAN PENINGKATAN JUMLAH LANTAI GEDUNG DARUT
LOKASI : BANDUNG, JL. GEGERKALONG GIRANG NO 56
TAHUN :
NO NAMA PEKERJAAN
A PEKERJAAN KOLOM K1
B PEKERJAAN KOLOM K2
C PEKERJAAN BALOK B1
D PEKERJAAN BALOK B2
E PEKERJAAN BALOK B3
F PEKERJAAN BALOK B4
G PEKERJAAN BALOK B5
H PEKERJAAN PELAT
I PEKERJAAN CONCRETE JACKETING K1
J PEKERJAAN CONCRETE JACKETING K2
K PEKERJAAN PEMBOBOKAN KOLOM
L PEKERJAAN INJEKSI
M PEKERJAAN DINDING
NILAI RAB :
PPN 10% :
TOTAL :
DIBULATKAN :
Terbilang :
Empat Miliyar Empat Ratus Tiga Puluh Tiga Juta Empat Ratus Empat Lima Ribu Rupiah
ANGGARAN BIAYA
KATAN JUMLAH LANTAI GEDUNG DARUT
ONG GIRANG NO 56
BIAYA
Rp 199,440,871
Rp 49,353,201
Rp 218,481,885
Rp 228,696,298
Rp 5,760,464
Rp 152,265,445
Rp 23,028,175
Rp 2,175,731,685
Rp 345,112,012
Rp 22,905,973
Rp 179,687,894
Rp 107,944,828
Rp 321,958,650
Rp 4,030,367,381
Rp 403,036,738
Rp 4,433,404,119
Rp 4,433,405,000