WAKTU PELAKSANAAN
BULAN KE 1 BULAN KE 2
HARGA SATUAN JUMLAH HARGA BOBOT
NO URAIAN/ ITEM PEKERJAAAN VOLUME SATUAN KETERANGAN
(Rp) (Rp) (%) 10 AGUST 16 AGUST 23 AGUST 30 AGUST 06 SEPT 13 SEPT
s/d 15 s/d 22 s/d 29 s/D 05 s/d 12 s/d 19
AGUST AGUST AGUST SEPT SEPT SEPT
2 Penutup Atap Spandek 0,3mm x 6m 70,00 M2 150.000,00 10.500.000,00 40,19 4,02 8,04 8,04 9,65 10,45
WAKTU PELAKSANAAN
BULAN 3 BULAN 4
JUMLAH
NO URAIAN/ ITEM PEKERJAAAN VOLUME SATUAN 10 AGUST 16 AGUST 23 AGUST 30 AGUST 06 SEPT 13 SEPT KETERANGAN
UNIT
s/d 15 s/d 22 s/d 29 s/D 05 s/d 12 s/d 19
AGUST AGUST AGUST SEPT SEPT SEPT
Estimasi Tenaga Kerja (Org) 20,00 20,00 40,00 40,00 40,00 40,00
2 Penutup Atap Spandek 0,3mm x 6m 350,00 M2 350,00 35,00 70,00 70,00 85,00 90,00 Asumsi Tenaga
yang dibutuhkan
= 4Org/ Unit
Estimasi Tenaga Kerja (Org) 20,00 40,00 40,00 49,00 52,00