OWNER ESTIMATE (OE)

SATUAN KERJA : DINAS PEKERJAAN UMUM DAN PENATAAN RUANG


PEKERJAAN : PEMBANGUNAN SISTEM DRAINASE PERKOTAAN PAKET 3
LOKASI : KOTA AMBON
T.A : 2021

NO URAIAN PEKERJAAN HARGA

1 Dokumen Pra Rencana (Laporan Pendahuluan) 21,703,574.70


2 Dokumen DED (Laporan Akhir) 47,024,411.85
3 Draft Dokumen Pelelangan 3,617,262.45

JUMLAH 72,345,249.00
PPN (10%) 7,234,524.90
JUMLAH TOTAL 79,579,773.90
DIBULATKAN 79,570,000.00

Terbilang : Tujuh Puluh Sembilan Juta Lima Ratus Tujuh Puluh Ribu Rupiah

Ambon, September 2021


Pejabat Pembuat Komitmen

R. PAYAPO, ST
NIP. 19760207200012 1003
REKAPITULASI
RENCANA ANGGARAN BIAYA

PROGRAM : PEMBANGUNAN SISTEM DRAINASE PERKOTAAN PAKET 3


KEGIATAN : PEMBANGUNAN SISTEM DRAINASE PERKOTAAN PAKET 3
LOKASI : KOTA AMBON
T. A : 2021

JUMLAH
NO URAIAN
( Rp )

I BIAYA LANGSUNG PERSONIL 49,345,249.00

II BIAYA LANGSUNG NON PERSONIL 23,000,000.00

Jumlah Harga 72,345,249.00


PPN 10 % 7,234,524.90
Total 79,579,773.90
PEMBULATAN 79,570,000.00
Terbilang : Tujuh Puluh Sembilan Juta Lima Ratus Tujuh Puluh Ribu Rupiah

Ambon, September 2021

Dibuat oleh,
Pejabat Pembuat Komitmen

R. PAYAPO, ST
NIP. 19760207200012 1003
RENCANA ANGGARAN BIAYA

PROGRAM : PEMBANGUNAN SISTEM DRAINASE PERKOTAAN PAKET 3


KEGIATAN : PEMBANGUNAN SISTEM DRAINASE PERKOTAAN PAKET 3
LOKASI : KOTA AMBON
T. A : 2021

JUMLAH HARGA
NO URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA
(Rp.) (Rp.)
a b c d e f
I BIAYA LANGSUNG PERSONIL
1 Team Leader / Koordinator Tim org/bln 1.00 15,800,000.00 15,800,000.00
2 Surveyor 1 org/bln 1.00 6,761,312.25 6,761,312.25
3 Surveyor 2 org/bln 1.00 6,761,312.25 6,761,312.25
5 Draftman 1 org/bln 1.00 6,761,312.25 6,761,312.25
6 Draftman 2 org/bln 1.00 6,761,312.25 6,761,312.25
7 Staf Administrasi org/bln 1.00 6,500,000.00 6,500,000.00

Jumlah I 49,345,249.00
II BIAYA LANGSUNG NON PERSONIL
1 ATK Ls 1.00 2,550,000.00 2,550,000.00
2 Sewa Kendaraan Bermotor Roda 2 unit 2.00 3,000,000.00 6,000,000.00
3 Sewa kendaraan Bermotor Roda 4 Unit 1.00 7,500,000.00 7,500,000.00
4 Biaya Komunikasi Ls 1.00 1,500,000.00 1,500,000.00
5 Sewa Printer A3 Unit 1.00 1,500,000.00 1,500,000.00
6 Sewa Kamera Digital Unit 1.00 300,000.00 300,000.00
7 Perlengkapan K3 Ls 1.00 1,500,000.00 1,500,000.00
8 Pelaporan
- Lap. Pendahuluan ( 1 x 3 buku ) Buku 3.00 300,000.00 900,000.00
- Lap. Akhir ( 1 x 3 buku ) Buku 3.00 300,000.00 900,000.00
- Flashdisk 16 GB Bh 1.00 350,000.00 350,000.00

Jumlah II 23,000,000.00