KEGIATAN :
PEKERJAAN :
STRUKTUR
LOKASI :
SEPIT
TAHUN ANGGARAN
2021
RENCANA ANGGARAN BIAYA
(RAB)
KEGIATAN : PEMBANGUNAN MASJID DJAMI'UL MUDJAHIDIN
PEKERJAAN : STRUKTUR
LOKASI : SEPIT
TAHUN ANGGARAN : 2021
LANTAI 2
7 Pek. Kolom
- Beton K250 M3 28,25 1.375.000,00 38.841.000,00
- Pembesian Kg 5.812,03 16.500,00 95.898.546,13
- Bekisting M2 244,80 125.401,40 30.698.262,72
8 Pek. Balok Atap
- Beton K250 M3 30,80 1.375.000,00 42.350.000,00
- Pembesian Kg 5.821,42 16.500,00 96.053.389,93
- Bekisting M2 224,00 130.651,40 29.265.913,60
9 Pekerjaan plat atap beton
- Beton K250 M3 38,50 1.375.000,00 52.937.500,00
- Pembesian Kg 10.599,81 16.500,00 174.896.940,60
- Bekisting M2 350,00 92.980,53 32.543.186,67
- Waterprofing Atap M2 350,00 45.000,00 15.750.000,00
REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PEMBANGUNAN MASJID DJAMI'UL MUDJAHIDIN
PEKERJAAN : STRUKTUR
LOKASI : SEPIT
TAHUN ANGGARAN : 2021
1 2 3
A PEKERJAAN PERSIAPAN -
B PEKERJAAN TANAH 86.841.153,49
C PEKERJAAN STRUKTUR 1.804.360.109,28
JUMLAH 1.891.201.262,76
PEMBULATAN 1.891.201.000,00
Catatan
- Harga terlampir merupakan harga estimasi dengan upah tenaga normal (borongan) dan harga material sesuai harga pasar
REKAP KEBUTUHAN BAHAN
KEGIATAN : PEMBANGUNAN MASJID DJAMI'UL MUDJAHIDIN
PEKERJAAN : STRUKTUR
LOKASI : SEPIT
TAHUN ANGGARAN : '2021
1 Besi
D.16 1128,00 Btg
D.13 70,00 Btg
P12 1294,00 Btg
P10 3239,00 Btg
P8 853,00 Btg
Bendrat (@25kg) 50,00 Roll
Wiremesh (2,4 x 54 m) 3 Roll